EX-96.1 54 tm224101d11_ex96-1.htm EX-96.1

 

Exhibit 96.1

 

 

TECHNICAL REPORT SUMMARY ON THE SANTA CRUZ PROJECT, ARIZONA, USA

 

S-K 1300 REPORT

 

IVANHOE ELECTRIC INC.

 

NORDMIN ENGINEERING LTD. PROJECT NO: 22032-01

 

SIGNATURE DATE: MAY 18, 2022

 

EFFECTIVE DATE: DECEMBER 8, 2021

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
1Nordmin Engineering Ltd.

 

 

TECHNICAL REPORT SUMMARY ON THE SANTA CRUZ PROJECT, ARIZONA, USA

 

NORDMIN ENGINEERING LTD. PROJECT NO: 22032-01

 

Prepared by:

 

Nordmin Engineering Ltd.

 

160 Logan Ave., Thunder Bay, ON P7A 6R1

 

for:

 

Ivanhoe Electric Inc.

606 – 999 Canada Place

Vancouver, BC V6C 3E1

Canada

 

Signature Date: May 18, 2022

 

Effective Date: December 8, 2021

 

REVISION HISTORY

 

REV. NO ISSUE DATE PREPARED BY REVIEWED BY APPROVED BY DESCRIPTION OF REVISION
4.3 December 13, 2021 Nordmin IVNE   Initial Draft
5.2 December 17, 2021 Nordmin IVNE   Draft
5.4 December 17, 2021 Nordmin QP QP/Nordmin Draft
6.1 March 8, 2022 Nordmin QP QP/Nordmin Draft
6.2 May 18, 2022 Nordmin QP QP/Nordmin Final Issued

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
2Nordmin Engineering Ltd.

 

 

CONTENTS

 

1 EXECUTIVE SUMMARY 14
  1.1 Summary 14
  1.2 Property Description, Ownership and Tenure 14
    1.2.1 Mineral Tenure, Surface Rights, Royalties, Agreements, and Permits 14
  1.3 Geology and Mineralization 15
  1.4 Status of Exploration 15
  1.5 Mineral Resource Estimate 16
  1.6 Conclusions and Recommendations 18
2 INTRODUCTION 19
  2.1 Registrant and Purpose 19
    2.1.1 Information Sources and References 19
    2.1.2 Site Visit 19
  2.2 Previous Reporting 20
    2.2.1 Previous Exploration Reports 20
  2.3 Units of Measure 20
  2.4 Symbols, Abbreviations and Acronyms 21
3 PROPERTY DESCRIPTION 23
  3.1 Legal Description of Real Property 23
  3.2 Property Location 23
  3.3 Land Tenure and Underlying Agreements 24
  3.4 Royalties 26
  3.5 Permits and Authorization 27
  3.6 Environmental Liabilities 28
4 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY 29
  4.1 Accessibility and Infrastructure 29
  4.2 Climate 30
  4.3 Local Resources 30
  4.4 Physiography 31
5 HISTORY 32
  5.1 Introduction 32

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
3Nordmin Engineering Ltd.

 

 

  5.2 Previous Exploration 34
    5.2.1 Sacaton Mine 34
    5.2.2 Santa Cruz and Texaco Deposits 35
  5.3 Previous Reporting 39
    5.3.1 Hanna 1982 39
    5.3.2 In Situ Joint Venture 1997 39
    5.3.3 IMC 2013 39
    5.3.4 Stantec-Mining 2013 40
    5.3.5 Physical Resource Engineering 2014 40
  5.4 Historical Production 40
  5.5 Nordmin QP Opinion 40
6 GEOLOGICAL SETTING, MINERALIZATION AND DEPOSIT 40
  6.1 Regional Geology 40
  6.2 Metallogenic Setting 41
  6.3 Santa Cruz Project Geology 45
    6.3.1 Geologic Units 48
  6.4 Property Mineralization 50
    6.4.1 Hypogene Mineralization at the Santa Cruz Deposit 52
    6.4.2 Supergene Mineralization at the Santa Cruz Deposit 53
    6.4.3 Hypogene Mineralization at the Texaco Deposit 53
    6.4.4 Supergene Mineralization at the Texaco Deposit 56
  6.5 Alteration 56
    6.5.1 Hypogene Alteration at the Santa Cruz Deposit 56
    6.5.2 Supergene Alteration at the Santa Cruz Deposit 57
    6.5.3 Hypogene Alteration at the Texaco Deposit 57
    6.5.4 Supergene Alteration at the Texaco Deposit 57
  6.6 Structural Geology 57
  6.7 Deposit Types 58
  6.8 Nordmin QP Opinion 61
7 EXPLORATION 62
  7.1 IVNE Geophysical Exploration 62
  7.2 Historic Geophysical Exploration 64
  7.3 Historical Data Compilation 67

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
4Nordmin Engineering Ltd.

 

 

  7.4 Drilling 69
    7.4.1 Historic Drilling – Santa Cruz Deposit 69
    7.4.2 Historic Drilling – Texaco Deposit 69
    7.4.3 2021 Drilling – IVNE 70
  7.5 Geotechnical Data 72
  7.6 Hydrogeological Data 72
  7.7 Nordmin QP Opinion 72
8 SAMPLE PREPARATION, ANALYSES AND SECURITY 74
  8.1 Assay Sample Preparation and Analysis 74
    8.1.1 IVNE Core Sample Preparation and Analysis – 2021 74
    8.1.2 Historic Core Assay Sample and Analysis 77
  8.2 Specific Gravity Sampling 77
  8.3 Quality Assurance/Quality Control Programs 78
    8.3.1 Standards 78
    8.3.2 Blanks 84
    8.3.3 Field and Laboratory Duplicates 85
  8.4 Security and Storage 89
  8.5 Nordmin QP’s Opinion on the Adequacy of Sample Preparation, Security, and Analytical Procedures. 89
9 DATA VERIFICATION 90
  9.1 Nordmin Site Visit 2022 90
    9.1.1 Field Collar Validation 91
    9.1.2 Core Logging, Sampling, and Storage Facilities 94
    9.1.3 Independent Sampling 97
    9.1.4 Audit of Analytical Laboratory 99
  9.2 Twin Hole Analysis 99
  9.3 Database Validation 103
  9.4 Review of Company’s QA/QC 103
  9.5 Nordmin QP’s Opinion 103
10 MINERAL PROCESSING AND METALLURGICAL TESTING 104
  10.1 CGCC Studies (1976-1982) 104
    10.1.1 Sample Selection 104
    10.1.2 Grinding Studies 105
    10.1.3 Flotation Studies 105

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
5Nordmin Engineering Ltd.

 

 

    10.1.4 Leaching Studies 106
    10.1.5 Copper Measurement 106
  10.2 ASARCO Study by Mountain States Engineering (1980) 107
  10.3 Santa Cruz In Situ Study 107
  10.4 Process Factors and Deleterious Elements 108
  10.5 QP Opinion 108
11 MINERAL RESOURCE ESTIMATES 109
  11.1 Drill Hole Database 109
  11.2 Domaining 110
    11.2.1 Geological Domaining 110
    11.2.2 Regression 112
    11.2.3 Mineralization Domaining 113
  11.3 Exploratory Data Analysis 114
  11.4 Data Preparation 118
    11.4.1 Non-assayed Assay Intervals 118
    11.4.2 Outlier Analysis and Capping 118
    11.4.3 Compositing 120
    11.4.4 Specific Gravity 120
    11.4.5 Block Model Strategy and Analysis 121
    11.4.6 Assessment of Spatial Grade Continuity 121
    11.4.7 Block Model Definition 125
    11.4.8 Interpolation Method 126
    11.4.9 Search Strategy 126
  11.5 Block Model Validation 127
    11.5.1 Visual Comparison 128
    11.5.2 Swath Plots 137
  11.6 Mineral Resource Classification 140
  11.7 Copper Pricing 142
    11.7.1 Global Refined Copper Consumption and Production 142
    11.7.2 Copper Prices 143
    11.7.3 Commodity Price Projections 146
  11.8 Reasonable Prospects of Eventual Economic Extraction 146
  11.9 Mineral Resource Estimate 147

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
6Nordmin Engineering Ltd.

 

 

  11.10 Mineral Resource Sensitivity to Reporting Cut-off 149
  11.11 Interpolation Comparison 149
  11.12 Factors That May Affect the Mineral Resources 151
  11.13 Nordmin’s QP Opinion 151
12 MINERAL RESERVE ESTIMATES 152
13 MINING METHODS 152
14 PROCESSING AND RECOVERY METHODS 152
15 INFRASTRUCTURE 152
16 MARKET STUDIES 152
17 ENVIRONMENTAL STUDIES, PERMITTING AND PLANS, NEGOTIATIONS, OR AGREEMENTS WITH LOCAL INDIVIDUALS OR GROUPS 152
18 CAPITAL AND OPERATING COSTS 152
19 ECONOMIC ANALYSIS 152
20 ADJACENT PROPERTIES 153
  20.1 Cactus Project 153
21 OTHER RELEVANT DATA AND INFORMATION 156
22 INTERPRETATION AND CONCLUSIONS 157
  22.1 Introduction 157
  22.2 Mineral Tenure, Surface Rights, Royalties, and Agreements 157
  22.3 Geology and Mineral Resource Modelling 158
  22.4 Exploration, Drilling, and Analytical Data Collection in Support of Mineral Resource Estimation 158
  22.5 Processing and Metallurgical Testing 159
  22.6 Mineral Resource Estimate 159
  22.7 Conclusions 162
23 RECOMMENDATIONS 163
24 REFERENCES 164
25 RELIANCE ON INFORMATION PROVIDED BY THE REGISTRANT 166
26 DATE AND SIGNATURE PAGE 167

 

APPENDIX A: Property and Rights

 

APPENDIX B: Standard, Blank and Duplicate Charts

 

APPENDIX C: Data Analysis Grade Domains

 

APPENDIX D: Block Model Classification Images

 

APPENDIX E: Block Model Validation Images

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
7Nordmin Engineering Ltd.

 

 

LIST OF FIGURES

 

Figure 3-1: Land ownership 24
Figure 3-2: Land ownership including Mainspring property location 26
Figure 4-1: Location map 29
Figure 4-2: Average temperatures and precipitation 30
Figure 5-1: Historic drill collars, IMC mineral inventory outlines and historic deposit and exploration target names (white) as well as current project names for IVNE and Arizona Sonoran Copper Company assets (in yellow). 33
Figure 6-1: Regional geology of Cu porphyry belt and map of location of Cu porphyry deposits hosted in the area 42
Figure 6-2: Map of structures related to extension during the mid-Cenozoic 43
Figure 6-3: Generalized cross-section through well-developed supergene enrichment profile showing geochemical stratigraphy Leached capping environment and metals mobility engendered through oxidative destruction of pyrite and Cu ore sulphides.Pyrite contributes four moles of H+(aq) per mole of pyrite, with Fe++(aq) and sulphate; ferrous iron oxidizes rapidly to H+(aq) and Fe+++(aq), the latter serving as a strong oxidizer for Cu sulphides. Cu sulphides produce nominal to no low pH solutions upon weathering. Lateral transport of iron and Cu produces ferricretes of hematite > goethite and exotic Cu as silicates, sulphates, halides, and Cu++ adsorbed onto goethite and manganese oxides. Oxidation along sheeted fractures and faults deepens the topographic base of all supergene stratigraphic intervals, as do supergene solutions migrating through phyllic and argillic-altered host rocks. Reactive host rocks shown on the margins of the figure attenuate Cu transport and produce erratic, fracture-controlled in situ development of Cu oxides; such in situ development of Cu oxides would be characteristic of K-silicate–altered (potassic) rock volumes. For scale, note that any of the three supergene-related geochemical zones may be variably developed such that thicknesses may range from nominal to several hundred metres as a function of the maturity of the weathering profile. Abbreviations: bn = bornite, cp = chalcopyrite, HW = hanging wall, mt = magnetite, py = pyrite (Chávez, 2021) 44
Figure 6-4: Santa Cruz property mineralization cross-section (ASARCO, 1978) 45
Figure 6-5: Cross-section of the Santa Cruz system (Vikre et al.2014) 46
Figure 6-6: Plan map of the diatreme pipes, maar and tephra deposits at the Santa Cruz Project (Vikre et al.2014) 47
Figure 6-7: Simplified stratigraphic section of the Santa Cruz Project (IVNE documents) 48
Figure 6-8: Plan map of simplified mineralization and alteration zonation at the Texaco deposit (Kreis, 1978) 54
Figure 6-9: Historic cross-section of mineralization and alteration zonation at the Texaco deposit (Kreis, 1978) 55
Figure 6-10: Simplified alteration and mineralization zonation model of a porphyry Cu deposit, after Lowell and Guilbert, 1970. 59

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
8Nordmin Engineering Ltd.

 

 

Figure 6-11: Schematic representation of an exotic Cu deposit and its relative position to an exposed porphyry Cu system (Fernandez-Mote et al., 2018; modified after Münchmeyer 1996; Sillitoe 2005). 60
Figure 6-12: Typical Cu porphyry cross-section displaying hypogene and supergene mineralization processes and associated minerals (modified from Asmus, B., [2013]) 61
Figure 7-1: Gravity data stations (left) and Arizona State aeromagnetic data (Earthfield report to IVNE, 2021) 62
Figure 7-2: Proposed passive seismic survey configuration and stations showing historic mineral inventories, IVNE surface access agreements, and historic drilling 63
Figure 7-3: ASARCO map illustrating interpreted ground and aeromagnetic data detailed in historic report “Recommended Drilling Santa Cruz Project,” M.A.970 Pinal County, Arizona, August 21, 1964, by W.E. Saegart 66
Figure 7-4 Plan map of CG drill hole collars as blue dots 67
Figure 7-5 Plan map of SC drill hole collars as red dots 68
Figure 7-6: Collar locations of the historic diamond drilling (orange) versus recent 2021 IVNE twin drill holes (blue) 71
Figure 8-1: NTT diamond bladed automatic core saw used for cutting diamond drill core for sampling 75
Figure 8-2: Core storage at IVNE offices/core shack 76
Figure 8-3: (Left) samples placed in burlap and inner plastic bags labelled with sample numbers; (Right) sample batches placed in large plastic bags and bins for shipping to lab 76
Figure 8-4: Santa Cruz deposit, Oreas 908 standard total Cu (g/t), assayed at Skyline Laboratories 81
Figure 8-5: Santa Cruz deposit, Oreas 908 standard cyanide soluble Cu (g/t), assayed at Skyline Laboratories 81
Figure 8-6: Santa Cruz deposit, Oreas 908 standard cyanide soluble Cu (g/t), assayed at Skyline Laboratories 82
Figure 8-7: Santa Cruz deposit, Oreas 908 standard total Cu (g/t), assayed at American Assay Laboratories 82
Figure 8-8: Santa Cruz deposit, Oreas 908 standard acid soluble Cu (g/t), assayed at American Assay Laboratories 83
Figure 8-9: Santa Cruz deposit, Oreas 908 standard cyanide soluble Cu (g/t), assayed at American Assay Laboratories 83
Figure 8-10: Blanks submitted by IVNE to Skyline Laboratories as a part of their QA/QC process 84
Figure 8-11: Blanks submitted by IVNE to American Assay Laboratories as a part of their QA/QC process 85
Figure 8-12: Original versus field duplicate sample results as total Cu (%) from samples submitted to Skyline Laboratories 86
Figure 8-13: Original versus field duplicate sample results as total Cu (%) from samples submitted to American Assay Laboratories 87
Figure 8-14: Duplicates completed by Skyline Laboratories as a part of their QA/QC process 88
Figure 8-15: Duplicates completed by American Assay Laboratories as a part of their QA/QC process 88
Figure 9-1: Map of check drill hole collars from the 2022 site visit, also displaying all diamond drill hole collars 92

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
9Nordmin Engineering Ltd.

 

 

Figure 9-2: Map of historic drill hole collars, also displaying all diamond drill hole collars 93
Figure 9-3: Collars for historic diamond drill holes CG-091 and CG-030 94
Figure 9-4: IVNE core logging facility located in Casa Grande, Arizona 95
Figure 9-5: Core photography station at the IVNE core logging facility 96
Figure 9-6: Nordmin independent sampling total Cu (%) assays from Skyline Laboratories 98
Figure 9-7: Nordmin independent sampling acid soluble Cu (%) assays from Skyline Laboratories 98
Figure 9-8: Nordmin independent sampling of cyanide soluble (%) assays from Skyline Laboratories 99
Figure 9-9: Collar locations of historic diamond drilling (orange) versus recent 2021 IVNE twin drill holes (blue) 100
Figure 9-10: Comparison of assays from SCC-001 versus CG-027. A) shows the direct comparison of total Cu assays as Cu (%). B) SCC-001 and CG-027 showing downhole charts of acid soluble Cu assays (%) on the left and total Cu (%) assays on the right. 101
Figure 11-1: Plan view of Santa Cruz Project diamond drilling 109
Figure 11-2: Domaining hierarchy of the Santa Cruz Project 110
Figure 11-3: Santa Cruz deposit domain idealized cross-section 112
Figure 11-4: Histogram and log probability plots for the Cu-oxide LG Sub-Domain 116
Figure 11-5: Histogram and log probability plots for the primary Cu LG Sub-Domain 116
Figure 11-6: Histogram and log probability plots for the chalcocite enrichment LG Sub-Domain 117
Figure 11-7: Histogram and log probability plots for the exotic Cu LG Sub-Domain 117
Figure 11-8: Primary Domain total Cu variogram 123
Figure 11-9: Oxide Domain total Cu variogram 123
Figure 11-10: Oxide Domain acid soluble Cu variogram 124
Figure 11-11: Chalcocite Enriched Domain Total Cu Variogram 124
Figure 11-12: Exotic Domain Total Cu Variogram 125
Figure 11-13: Cross-section outlining the analysis of cyanide soluble Cu estimation within the Chalcocite Enriched Domain 128
Figure 11-14: Block model validation, total Cu, cross-section 129
Figure 11-15: Block model validation, acid soluble Cu, cross-section 130
Figure 11-16: Block model validation, cyanide soluble Cu, cross-section 131
Figure 11-17: Block model validation, total Cu, cross-section 132
Figure 11-18: Block model validation, acid soluble Cu, cross-section 133
Figure 11-19: Block model validation, cyanide soluble Cu, cross-section 134
Figure 11-20: Block model validation, total Cu, cross-section 135

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
10Nordmin Engineering Ltd.

 

 

Figure 11-21: Block model validation, acid soluble Cu, cross-section 136
Figure 11-22: Block model validation, cyanide soluble Cu, cross-section 137
Figure 11-23: Swath plots, total cu 138
Figure 11-24: Swath plots, acid soluble cu 138
Figure 11-25: Swath plots, cyanide soluble cu 139
Figure 11-26: Plan section demonstrating resource classification, -260 m depth 140
Figure 11-27: Plan section demonstrating resource classification, -475 m depth 141
Figure 11-28: Vertical section displaying resource classification 142
Figure 11-29: Global copper demand 2000-2040 143
Figure 11-30: A century of Cu prices 144
Figure 11-31: Projected mine supply demand to 2040 146

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
11Nordmin Engineering Ltd.

 

 

 

LIST OF TABLES

 

Table 1-1: Santa Cruz Deposit Mineral Resource Estimate, 0.39% Total Cu CoG 17
   
Table 2-1: Symbols, Abbreviations and Acronyms Used in this Technical Report 21
   
Table 4-1: Description of Physiography of the Casa Grande Area, Santa Cruz Exploration Property 31
   
Table 5-1: Sacaton Historic Mine Production (Fiscal Years Ended December 31) 34
   
Table 5-2: History of Exploration Activities Across the Santa Cruz and Texaco Deposits 35
   
Table 7-1: Summary of Historic Exploration on the Santa Cruz Project and Surrounding Area 65
   
Table 7-2 Summary of Available Data by Region 68
   
Table 7-3: Drilling History Within the Santa Cruz Project Area 69
   
Table 7-4: Drilling History Within the Texaco Exploration Target Area of the Santa Cruz Project 70
   
Table 7-5 IVNE 2021 Drilling on the Santa Cruz Deposit 70
   
Table 7-6: Santa Cruz Project SG Measurements 72
   
Table 8-1: CRMs Inserted by IVNE into Sample Batches Sent to Skyline Laboratories 79
   
Table 8-2: CRMs Inserted by IVNE into Sample Batches Sent to American Assay Laboratories 80
   
Table 8-3: Skyline Laboratory Submitted CRMs 80
   
Table 8-4: American Assay Laboratory Submitted CRMs 80
   
Table 9-1: Check Coordinates for IVNE 2021 Drilling, March 3, 2022 91
   
Table 9-2: Check Coordinates for Historic Drilling Within the Santa Cruz Deposit, March 3, 2022 92
   
Table 9-3: Original Assay Values Versus Nordmin Check Sample Assay Values from the 2022 Site Visit 97
   
Table 9-4: Downhole Lithology Logging Comparison of CG-027 versus SCC-001 102
   
Table 11-1: Drill Hole Count Summary 110
   
Table 11-2: Mineral Resource Estimate Number of Assays by Assay Type 110
   
Table 11-3: Santa Cruz Geological Domains 111
   
Table 11-4: Regression Analysis for Acid Soluble Cu 113
   
Table 11-5: Regression Analysis for Cyanide Soluble Cu 113
   
Table 11-6: Santa Cruz Deposit Domain Wireframes 114
   
Table 11-7: Santa Cruz Deposit Domain, Assays by Cu Grade Sub-Domain 115
   
Table 11-8: Assays at Minimum Detection 118
   
Table 11-9: Santa Cruz Domain, Outlier Analysis, and Capping 119
   
Table 11-10: Santa Cruz Deposit Composite Analysis 120

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
12Nordmin Engineering Ltd.

 

 

Table 11-11: Santa Cruz Deposit Variography Parameters 122
   
Table 11-12: Santa Cruz Deposit Block Model Definition Parameters 125
   
Table 11-13: Santa Cruz Deposit Block Model Search Parameters 127
   
Table 11-14: Consensus Copper Pricing 2021-2024 145
   
Table 11-15: Input Parameter Assumptions 147
   
Table 11-16: Santa Cruz Deposit Mineral Resource Estimate, 0.39% Total Cu CoG 148
   
Table 11-17: Mineral Resource Sensitivity for Total Cu 149
   
Table 11-18: Interpolation Comparison 150
   
Table 20-1: Global Mineral Resource Estimate of the Cactus Project. Source – Arizona Sonoran Copper Company, Inc. Cactus Project, Arizona, USA, PEA, Effective August 31, 2021 155
   
Table 20-2: Resource Estimate Utilized for the PEA. Source – Arizona Sonoran Copper Company, Inc. Cactus Project, Arizona, USA, PEA, Effective August 31, 2021 155
   
Table 20-3: Financial Results of the Cactus Project PEA. Source – Arizona Sonoran Copper Company, Inc. Cactus Project, Arizona, USA, PEA, Effective August 31, 2021 155
   
Table 22-1: Santa Cruz Deposit Mineral Resource Estimate, 0.39% Total Cu CoG 161
   
Table 23-1: 2022 Budget 163

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
13Nordmin Engineering Ltd.

 

 

1EXECUTIVE SUMMARY

 

1.1Summary

 

Nordmin Engineering Ltd. (Nordmin) was retained by Ivanhoe Electric Inc. (IVNE or “the Company”) to prepare an independent Technical Report Summary (Technical Report) on the Santa Cruz Project, located approximately 11 km west of the town of Casa Grande in Arizona, USA. The purpose of this report is to support the Mineral Resource Estimate for the Santa Cruz Project (“the Project”) as of December 8th, 2021.

 

This Technical Report Summary conforms to United States Securities and Exchange Commission’s (SEC) Modernized Property Disclosure Requirements for Mining Registrants as described in Subpart 229.1300 of Regulation S-K, Disclosure by Registrants Engaged in Mining Operations (S-K 1300) and Item 601 (b)(96) Technical Report Summary. Nordmin completed a visit of the property from March 2nd to March 6th, 2022.

 

IVNE is a private company, with their corporate office located at 606 – 999 Canada Place, Vancouver, BC V6C 3E1, Canada.

 

1.2Property Description, Ownership and Tenure

 

The Santa Cruz Project is located 11 kilometres (km) west of the town of Casa Grande, Arizona, and is approximately one hour’s drive south of the capital Phoenix and covers a cluster of deposits/targets about 11 km long and 1.6 km wide. The Santa Cruz Project centroid is approximately -111.88212, 32.89319 (WGS84) in Township 6 S, Range 4E, Section 13, Quarter C.

 

The property and rights owned by IVNE are described in Appendix A. These rights and title have not been independently verified, and the Title Opinion and Reliance letter by Marian Lalonde dated October 29, 2021, of Fennemore Law, Tucson, Arizona, has been relied upon by Nordmin for this section of the Technical Report.

 

In 2021, IVNE executed an agreement with Central Arizona Resources (CAR) for the right to acquire 100% of CAR’s option over the DR Horton Energy (DRHE) mineral title and CAR’s Surface Use Agreement (SUA) with Legend Property Group (Legend).

 

1.2.1Mineral Tenure, Surface Rights, Royalties, Agreements, and Permits

 

The Santa Cruz Project lies primarily on private land, which is dominantly split estate surface and minerals. IVNE holds an option on the purchase of the mineral estate while holding an exclusive agreement on surface use. Additional lands and rights have been acquired by IVNE in the form of options on private parcels and staking of unpatented federal lode mining claims. The Santa Cruz exploration area covers 77.59 km2, including 27.75 km2 of private land, 30.52 km2 of Arizona State Mineral Exploration permits, and 238 unpatented claims, or 19.32 km2 of Bureau of Land Management (BLM) land.

 

Current exploration is conducted on private land under the SUA with Legend. Disturbance to date has been de minimis and permitting has consisted of filing Notices of Intent to Drill and to Abandon with the Arizona Department of Water Resources for each section of land on which drilling takes place.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
14Nordmin Engineering Ltd.

 

 

1.3Geology and Mineralization

 

The Santa Cruz Project lies along a northwest to southeast trending, approximately 600 km long porphyry Cu belt that includes many productive Cu deposits such as Mineral Park, Bagdad, Resolution, and the neighbouring Sacaton. These deposits lie within the Basin and Range province that covers most of the southwestern United States and Northwestern Mexico. The Cu porphyry deposits within this trend are the genetic product of igneous activity during an approximately 80 Ma to 50 Ma orogenic event that resulted in northeast-directed subduction and a northwest-southeast-striking magmatic arc (Leveille and Stegen, 2012). During tectonic extension porphyry Cu systems were variably dismembered, tilted, and buried beneath basin alluvium and conglomeratic deposits that fill the Casa Grande Valley. Prior to concealment porphyry systems of Arizona experienced supergene enrichment events that make them such economically significant deposits.

 

The Santa Cruz system (comprising Santa Cruz, Texaco, Parks-Salyer, and Sacaton areas) represents portions of one or more large, Laramide-aged porphyry Cu systems that have been subsequently enriched by supergene processes. Supergene enrichment is a mineral deposition process in which near-surface oxidation produces acidic solutions that leach metals, carry them downward, and reprecipitate them, thus enriching sulphide minerals already present. Sometime following the development of supergene mineralization, the Santa Cruz system was dismembered, displaced, and eventually buried as a result of tertiary Basin and Range extensional tectonism.

 

Mineralization at the Santa Cruz Project is generally divided into three main groups:

 

·Primary hypogene sulphide mineralization consists of chalcopyrite, pyrite, molybdenite, minor bornite, and covellite hosted within sulphide and quartz-sulphide stringers, veinlets, veins, vein breccias, and breccias as well as fine to coarse disseminations within vein envelopes (dominantly replacing mafic minerals biotite and hornblende) associated with hydrothermal porphyry-style mineralization and alteration related to Laramide-aged quartz-biotite-feldspar-phyric dykes (65-64 Ma from K-Ar; Balla, 1972).

 

·Secondary supergene sulphide mineralization is comprised of chalcocite (with accessory chalcopyrite-pyrite) that was incompletely replaced by chalcocite, as well as djurleite, and digenite identified in historic XRD analyses.

 

·Supergene enriched Cu mineralization, referred to as “oxide mineralization,” is dominated by chrysocolla (Cu-oxide) and atacamite (Cu-chloride) with subordinate brochantite, dioptase, tenorite, cuprite, Cu wad, and native Cu, and as Cu-bearing montmorillonite.

 

1.4Status of Exploration

 

The exploration programs completed by IVNE and previous operators are appropriate for the deposit style. The programs delineated the Santa Cruz and Texaco deposits, as well as other deposits along the Santa Cruz-Sacaton Cu trend. Diamond drilling indicates the potential to further define and potentially expand on known exploration targets. A research program on in-situ mining was completed in the 1990s (see Section 5), but all equipment from the program has been removed. As of writing, there is no development or mining on the property.

 

The quantity and the quality of lithological, collar, and downhole survey data collected in the various exploration programs by operators are sufficient to support the Mineral Resource Estimate. The collected sampling is representative of total Cu, acid soluble Cu, cyanide soluble Cu, and molybdenum data in the Santa Cruz deposit, reflecting areas of higher, and lower grades. The analytical laboratories used for legacy and current assaying are well known in the industry, produce reliable data, are properly accredited, and are widely used within the industry.

 

Nordmin is not aware of any drilling, sampling, or recovery factors that could materially impact the accuracy and reliability of the results. In Nordmin’s opinion, the drilling, core handling, logging, and sampling procedures meet or exceed industry standards and are adequate for the purpose of Mineral Resource Estimation.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
15Nordmin Engineering Ltd.

 

 

Nordmin considers the QA/QC protocols in place for the Project to be acceptable and in line with standard industry practice. Based on the data validation and the results of the standard, blank, and duplicate analyses, Nordmin is of the opinion that the assay and specific gravity (SG) databases are of sufficient quality for Mineral Resource Estimation for the Project.

 

1.5Mineral Resource Estimate

 

Mineral Resources have been classified in accordance with the definitions for Mineral Resources in S-K 1300. This estimate of Mineral Resources may be materially affected by environmental permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

 

The Mineral Resource Estimate was estimated from the main database of 104,184 m of diamond drilling in 121 drill holes spanning from 1964 to 2021. Nordmin, through an interactive process with IVNE, examined the historic interpretations of the mineralization. In 2021 IVNE completed four twin diamond drill holes (4,738 m) of historic drill holes. Nordmin utilized these drill holes and reviewed the assays, lithology, and mineralization to confirm the accuracy of the historic drilling as well as to determine the spatial controls on grade variations within the Project.

 

The Santa Cruz deposit model consists of four main Cu domains: the Exotic Domain, Oxide Domain, Chalcocite Enriched Domain, and Primary Domain. The Oxide Domain and Primary Domain are separated by a theoretical geochemical boundary defined by a 2:1 ratio of acid soluble Cu to total Cu. The Exotic Domain is separated by lithology and is only found above the Oracle Granite within Tertiary sediments. From a modelling perspective, each Cu-mineralized domain was further sub-domained into high, medium, and low grade (LG) domains to constrain grade distribution and geochemical differences. Overlap between domains exists between the Chalcocite Enriched Domain and Primary Domain, as well as the Chalcocite Enriched Domain and Oxide Domain, respectively.

 

Detailed wireframing of domains was completed in section and plan view to give better perspective of the depth and limits of the Cu-oxide mineralization. Special attention was given to consistent smoothing of wireframes to properly mimic the controls of mineralization including following the southwest dip of intrusives, and the steep topography of the Oracle Granite within the fault block. When not cut-off by drilling, the wireframes within each domain terminate at either the contact of the Cu-oxide boundary layer, the Tertiary sediments/Oracle Granite contact or D2 fault structure. There is an overlap of cyanide soluble Cu with either acid soluble Cu in the weathered supergene domain or with primary Cu in the primary hypogene mineralization domain. A block model has been fully validated with no material bias identified.

 

Mineral Resources were classified into Indicated and Inferred categories based on geological and grade continuity, in conjunction with data quality, spatial continuity based on variography, estimation pass, data density, and block model representativeness, specifically assay spacing and abundance, kriging variance, and search volume block estimation assignment.

 

The Mineral Resource Estimate has been defined based on an applied percentage (%) total copper (Cu) cut-off grade (CoG) to reflect processing methodology and assumed revenue stream from Cu.

 

The Mineral Resource Estimate is based on an underground mining methodology and surface leach float process to recover cathode Cu or a mixture of cathode Cu and Cu saleable concentrates.

 

The Santa Cruz deposit Mineral Resource Estimate is presented in Table 1-1 and has an effective date of December 8, 2022.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
16Nordmin Engineering Ltd.

 

 

Table 1-1: Santa Cruz Deposit Mineral Resource Estimate, 0.39% Total Cu CoG

 

Domain

Resource

Category

Kilotonnes
kt
Total
Cu %
Total
Soluble
Cu %
Acid
Soluble
Cu %
Cyanide
Soluble
Cu %
Total
Cu kt
Total
Soluble
Cu kt
Acid
Soluble
Cu kt
Cyanide
Soluble
Cu kt
Exotic Indicated 6,989 1.05 0.80 0.73 0.07 73 56 51 5
Inferred 11,680 1.28 1.00 0.98 0.02 149 118 115 3
Oxide Indicated 52,990 1.34 1.27 0.98 0.29 708 669 518 151
Inferred 126,138 1.06 1.00 0.71 0.29 1,336 1,253 892 361
Chalcocite Enriched Indicated 29,145 1.25 1.13 0.40 0.73 364 328 115 213
Inferred 14,838 1.36 1.28 0.52 0.76 202 191 78 113
Primary Indicated 184,877 0.75 n/a n/a n/a 1,394 n/a n/a n/a
Inferred 96,098 0.59 n/a n/a n/a 568 n/a n/a n/a
TOTAL
  Indicated 274,000 0.93 0.38 0.25 0.13 2,539 1,053 684 369
  Inferred 248,754 0.91 0.63 0.44 0.19 2,255 1,563 1,085 478

 

Notes on Mineral Resources

 

1.The Mineral Resources in this estimate were independently prepared by Nordmin Engineering Ltd and the Mineral Resources were prepared in accordance with Mineral Resources have been classified in accordance with the definitions for Mineral Resources in S-K 1300.

2.Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. No environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues are known that may affect this estimate of Mineral Resources.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
17Nordmin Engineering Ltd.

 

 

3.Verification included multiple site visits to inspect drilling, logging, density measurement procedures and sampling procedures, and a review of the control sample results used to assess laboratory assay quality. In addition, a random selection of the drill hole database results was compared with original records.

4.The Mineral Resources in this estimate for the Santa Cruz deposit used Datamine Studio RMTM software to create the block models.

5.The Mineral Resources have an effective date of December 8, 2021.

6.Underground Mineral Resources are reported at a CoG of 0.39% Total Cu, which is based upon a Cu price of US$$3.70/lb and a Cu recovery factor of 80%.

7.SG was applied using weighted averages by lithology.

8.All figures are rounded to reflect the relative accuracy of the estimates, and totals may not add correctly.

9.Excludes unclassified mineralization located along edges of the Santa Cruz deposit where drill density is poor.

10.Report from within a mineralization envelope accounting for mineral continuity.

11.Acid soluble Cu and cyanide soluble Cu are not reported for the Primary Domain.

 

There is a potential to increase the Mineral Resource by using infill drilling to expand and increase the Mineral Resource category.

 

Areas of uncertainty that may materially impact the Mineral Resource Estimate include:

 

·Changes to long term metal price assumptions.

·Changes to the input values for mining, processing, and G&A costs to constrain the estimate.

·Changes to local interpretations of mineralization geometry and continuity of mineralized zones.

·Changes to the density values applied to the mineralized zones.

·Changes to metallurgical recovery assumptions.

·Changes in assumption of marketability of the final product.

·Variations in geotechnical, hydrogeological, and mining assumptions.

·Changes to assumptions with an existing agreement or new agreements.

·Changes to environmental, permitting, and social licence assumptions.

·Logistics of securing and moving adequate services, labour, and supplies could be affected by epidemics, pandemics and other public health crises, including COVID-19, or similar such viruses.

 

1.6Conclusions and Recommendations

 

Under the assumptions presented in this Technical Report, and based on the available data, the Mineral Resources show reasonable prospects of economic extraction. Exploration activities have shown that the Santa Cruz deposit retains significant potential. Additional infill drilling in the categories of Inferred and Indicated Resource is warranted.

 

The recommended program is focused on drilling, analytical, metallurgical test work, geological modelling, Mineral Resource Estimation, economic studies (Preliminary Economic Assessment) and environmental baseline studies to support permitting efforts. The recommendations are estimated to require a 2022 budget of $73.7 million.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
18Nordmin Engineering Ltd.

 

 

2INTRODUCTION

 

2.1Registrant and Purpose

 

Nordmin was retained by IVNE to prepare an independent Technical Report Summary on the Santa Cruz Project located approximately 11 km west of the town of Casa Grande in Arizona, USA. This Technical Report is effective as of December 8, 2021 and supersedes all prior technical reports prepared for the Santa Cruz Project and was created for the purpose of defining and supporting a Mineral Resource Estimate for the Santa Cruz Project.

 

This Technical Report Summary conforms to United States SEC Modernized Property Disclosure Requirements for Mining Registrants as described in Subpart 229.1300 of Regulation S-K, Disclosure by Registrants Engaged in Mining Operations (S-K 1300) and Item 601 (b)(96) Technical Report Summary.

 

Nordmin visited the property from March 2nd to March 6th, 2022.

 

IVNE is a private company, with their corporate office located at 606 – 999 Canada Place, Vancouver, BC V6C 3E1, Canada.

 

2.1.1Information Sources and References

 

This Technical Report is based, in part, on internal Company technical reports and maps, published government reports, company letters and memoranda, and public information as listed in Section 24. Several sections from reports authored by other consultants have been directly quoted or summarized in this Technical Report and are so indicated where appropriate.

 

A draft copy of this Technical Report has been reviewed for factual errors by IVNE.

 

Any statements and opinions expressed in this document are given in good faith and in the belief that such statements and opinions are not false and misleading at the date of this Technical Report.

 

During the preparation of this Technical Report and the site visit, discussions were held with the following personnel:

 

·Eric Castleberry, PG – US Operations Manager, IVNE

·Shawn Vandekerhove – Senior Geologist, IVNE

·Lucas Forster – Geologist, IVNE

·Andrea Cade – Reporting Geologist, IVNE

·Charlie Forster – VP Exploration, IVNE

·Eric Finlayson – President, IVNE

·Mark Gibson – COO, IVNE

·Christopher Seligman, MAusIMM CP(Geo) – Senior Geologist, IVNE

·Graham Boyd – VP, US Projects, IVNE

·Christian Ballard, P.Geo. – Sr. Geologist, Nordmin

·Annika Van Kessel – Geologist in Training, Nordmin

·James J. Moore, P.E. - President, Met Engineering, LLC.

 

2.1.2Site Visit

 

Nordmin completed a visit to the Santa Cruz Project site from March 2nd to March 6th, 2022.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
19Nordmin Engineering Ltd.

 

 

Activities during the site visits included:

 

·Review of the geological and geographical setting of the Santa Cruz Project.

·Review and inspection of the site geology, mineralization, and structural controls on mineralization.

·Review of the drilling, logging, sampling, analytical and QA/QC procedures.

·Review of the chain of custody of samples from the field to the assay lab.

·Review of the drill logs, drill core, storage facilities, and independent assay verification on selected core samples.

·Confirmation of several drill hole collar locations.

·Review of the structural measurements recorded within the drill logs and how they are utilized within the 3D structural model.

·Validation of a portion of the drill hole database.

 

IVNE geologists completed the geological mapping, core logging, and sampling associated with each drill location. Therefore, Nordmin relied on IVNE’s database to review the core logging procedures, the collection of samples, and the chain of custody associated with the drilling programs. IVNE provided Nordmin with digital copies of the logging and assay reports. All drilling data, including collars, logs, and assay results, were provided to Nordmin prior to the site visit. No significant issues were identified during the site visit.

 

2.2Previous Reporting

 

Historical resources and estimates exist on the property and predate the Company’s acquisition. The following historical information is relevant to provide context but is not current and should not be relied upon. The Company has not verified the relevance and reliability of the estimate, key assumptions, parameters, and methods used to prepare the estimate and require further exploration work by the Company to appropriately determine the relevance and reliability of the non-compliant historical estimations. A qualified person has not done sufficient work to classify the historical estimate as current mineral resources or mineral reserves and the Company is not treating the historical estimate as current mineral resources or mineral reserves

 

2.2.1Previous Exploration Reports

 

·Watts Griffis McOuat Ltd. (WGM), 1982. Non-compliant ore and mining reserve for Hanna Mining in 1982.

·In-situ Joint Venture, 1999.

·Independent Mining Consultants, Inc. (IMC), 2013. Non-compliant block model for the Texaco deposit.

·IMC, 2013. Non-compliant block model for the Parks-Salyer deposit.

·IMC, 2013. Non-compliant Mineral Resource for the Santa Cruz South deposit.

·Stantec, 2013. Non-compliant conceptual study of geologic resource and reserve.

·Physical Resource Engineering, 2014. Non-compliant conceptual study of geologic resource and reserve.

 

2.3Units of Measure

 

Unless otherwise noted, the following measurement units, formats, and systems are used throughout this Technical Report.

 

·Measurement Units: all references to measurement units use the System International (SI, or metric) for measurement. The primary linear distance unit, unless otherwise noted, are metres (m).

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
20Nordmin Engineering Ltd.

 

 

·General Orientation: all references to orientation and coordinates in this Technical Report are presented as Universal Transverse Mercator (UTM) in metres unless otherwise noted.

·Currencies outlined in the Technical Report are stated in US$ unless otherwise noted.

 

2.4Symbols, Abbreviations and Acronyms

 

Table 2-1: Symbols, Abbreviations and Acronyms Used in this Technical Report

 

Abbreviation Unit or Term
% percent
° degree
less than
greater than
µm microns
AAS atomic-absorption spectroscopy
ADEQ Arizona Department of Environmental Quality
Ag silver
ASARCO Arizona Smelting and Refining Company Inc.
Au gold
BLM Bureau of Land Management
CAP covered area project
CAR Central Arizona Resources
CGCC Casa Grande Copper Corporation
CIM Canadian Institute of Mining, Metallurgy and Petroleum
CoG cut-off grade
CRM certified reference material
CSAMT controlled source audio-frequency magnetotelluric
Cu copper
DRHE DR Horton Energy
ESA environmental site audit
FS Feasibility Study
ft foot/feet
Ga giga annum
gpl grams per litre
g/t grams per tonne
HG high grade
ICP inductively coupled plasma
ICP-MS inductively coupled plasma mass spectrometry
ICP-OES inductively coupled plasma optical emission spectrometry
IMC Independent Mining Consultants, Inc.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
21Nordmin Engineering Ltd.

 

 

Abbreviation Unit or Term
IP induced polarization 
IRR internal rate of return
IVNE Ivanhoe Electric Inc.
Jacor Jacor, LLC
JORC Joint Ore Reserves Committee
km kilometre
kton/a thousand tons per annum
Legend Legend Property Group
LG low grade
m metre
MASW mega annum
MASW multichannel analysis of surface waves
Mlb million pounds
Mton Million tons
NEPA National Environmental Policy Act
NPV net present value
PEA Preliminary Economic Assessment
PFS Prefeasibility Study
PGS pale-green sericite
PLS pregnant leach solution
Presidio Presidio Capital
psi pounds per square inch
QA quality assurance
QA/QC quality assurance/quality control
QC quality control
QP Qualified Person
RC reverse circulation
ROFO right of first offer
ROFR right of first refusal
RTP reduced to pole
SCJV Santa Cruz Joint Venture
SEC Securities and Exchange Commission
SEQ sequential acid leaching
SG specific gravity
SUA surface use agreement
SX-EW solvent extraction-electrowinning
TMI total magnetic intensity
UIC underground injection control
USBR US Bureau of Reclamation
USGS US Geological Survey
WGM Watts Griffis McOuat Ltd.
XRF x-ray fluorescence

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
22Nordmin Engineering Ltd.

 

 

3PROPERTY DESCRIPTION

 

3.1Legal Description of Real Property

 

The property and rights owned by IVNE are described in Appendix A. These rights and title have not been independently verified, and the Title Opinion and Reliance letter by Marian Lalonde dated October 29, 2021, of Fennemore Law, Tucson, Arizona, has been relied upon by the Nordmin QP for this section of the Technical Report.

 

3.2Property Location

 

The Santa Cruz Project is located 11 km west of the town of Casa Grande, Arizona, and is approximately one hour’s drive south of the capital Phoenix (Figure 3-1). It is less than 10 km southwest of the Sacaton deposit, which was previously mined by ASARCO, and covers a cluster of deposits/targets about 11 km long and 1.6 km wide. The Santa Cruz Project centroid is approximately -111.88212, 32.89319 (WGS84) in Township 6 S, Range 4E, Section 13, Quarter C.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
23Nordmin Engineering Ltd.

 

 

 

 

Figure 3-1: Land ownership

 

3.3Land Tenure and Underlying Agreements

 

In 2021, IVNE executed an agreement with CAR for the right to acquire 100% of CAR’s option over the DRHE mineral title and CAR’s SUA with Legend. The Santa Cruz exploration area covers 77.59 km2, including 27.75 km2 of private land, 30.52 km2 of Arizona State Mineral Exploration permits, and 238 unpatented claims, or 19.32 km2 of BLM land (Figure 3-1).

 

Private Parcels

 

The Santa Cruz Project lies primarily on private land, which is dominantly split estate surface and minerals. IVNE holds an option on the purchase of the mineral estate, while holding an exclusive agreement on surface use. Additional lands and rights have been acquired by IVNE in the form of options on private parcels and staking of unpatented federal lode mining claims.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
24Nordmin Engineering Ltd.

 

 

DRHE Option

 

The agreement with DRHE provides that IVNE (by way of assignment from CAR) has the right, but not the obligation, to earn 100% of the mineral title in the fee simple mineral estate, 39 Federal Unpatented mining claims, and three small approximately 10 acre surface parcels (Figure 3-1), in cash or IVNE shares at DRHE election, over the course of three years as follows:

 

a.On the Effective Date, IVNE shall pay the “Initial Payment” [paid]; and
b.Within five (5) days following of the expiration of the Due Diligence Period, IVNE shall pay “Due Diligence Payment” [paid]; and
c.On or before the first anniversary of the Effective Date, IVNE shall pay “First Payment”; and
d.On or before the second anniversary of the Effective Date, IVNE shall pay collectively with the Initial Payment, the Due Diligence Payment, and the First Payment, the “Option Payments”.
e.Following the exercise of the Option and upon the Closing Date, IVNE shall pay the “Closing Payment”.

 

The agreement with DRHE also provides IVNE with a Right of First Refusal (ROFR) on certain surface parcels owned by Legend. This ROFR reserved by DRHE when the property was sold to Legend in 2007, and this right is now part of the rights being sold to IVNE and affords a great deal of control on the destiny of the surface estate overlying the Santa Cruz Project.

 

3.3.1.1Legend SUA

 

The SUA with Legend Property Group allows for the exclusive use of the property for the purposes of drilling and geophysical testing, as well as granting a Right of First Offer (ROFO) on the sale of the property. Legend has granted these rights to IVNE (by way of assignment from CAR) for up to four years under the following conditions:

 

Year 1 Payment –to be paid as follows:

 

Initial payment within five (5) days following the Effective Date [paid].
Trigger payment within five (5) days following the Trigger Date [paid].

 

Year 2 Payment – due on, or before the first anniversary of the Trigger Date.
Year 3 Payment –due on, or before the second anniversary of the Trigger Date.
Extension Period (“Fourth Year Payment”):

 

providing written notice to Legend of its intent to extend the term of this Agreement for an additional 12 months, for a total term of 48 months; and
paying to Legends the Fourth Year Payment

 

3.3.1.2Other Parcels

 

IVNE has entered into binding agreements to acquire an additional parcel of private land, called the “Mainspring” Parcel. This parcel is depicted in Figure 4-2. The lands were optioned to secure portions of, and exploration potential surrounding, the Parks-Salyer deposit.

 

This acquisition is structured as an option where failure to meet any payment would lose the right to acquire the property, and is budgeted as part of the “Land and Commercial” line item in Table 26-1.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
25Nordmin Engineering Ltd.

 

 

 

 

Figure 3-2: Land ownership including Mainspring property location

 

3.3.1.3Federal Unpatented Mineral Claims

 

IVNE (by way of assignment and deed from CAR) holds 238 unpatented Federal Mining claims (Appendix A).

 

DRHE also holds 39 Federal unpatented mining claims in T06S R04E in N/2 Section 12, W/2 Section 23 and W/2 Section 24, which are subject to the option described in Section 4.1.1.

 

3.4Royalties

 

Noted royalties on future mineral development of the Project are summarized here:

 

Royalty interests in favour of the royalty holders of a 5% net smelter return royalty interest for minerals derived from all portions of the property pursuant to terms contained therein recorded in the royalty document.

 

Royalty interests in favour of the royalty holder of a 10% net smelter return royalty interest in section 13, 18, 19, and 24, Township 6 South, Range 4 East, for minerals derived from the property pursuant to terms contained therein recorded in the royalty document.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
26Nordmin Engineering Ltd.

 

 

Rights conveyed to the royalty holder in Sections 13, 18, 19, 24, Township 6 South, Range 4 East, consisting of 10% of one eight-hundredth of Fair Market Value and interest in the Cu and other associated minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.

 

Rights granted to the royalty holders, as joint tenants with right of survivorship, a royalty in sections 13, 18, 19, and 24, Township 6 South, Range 4 East, consisting of 30% of five tenths of one percent of the net smelter return from all minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.

 

Royalty interest of a 2.25% in favour of the royalty holder in Section 1, Township 6 South, Range 4 East, and Sections 6, 7, 8, and 17, Township 6 South, Range 5 East, for net smelter return royalty interest in minerals derived from the property pursuant to terms contained therein recorded in the royalty document.

 

Rights conveyed to the royalty holder in Sections 13, 23, 24, 25, and 26, Township 6 South, Range 4 East and Sections 5, 6, 17, 18, 19, and 30, Township 6 South, Range 5 East, consisting of 60% of one eighth-hundredth of Fair Market Value and interest in the Cu and other minerals with additional terms, conditions, and matters contained therein, recorded in the royalty documents.

 

Reservation of a 1% royalty interest in favour of the royalty holder recorded in the royalty document, for E1/2 of Section 5, Township 6 South, Range 5 East, south and west of Southern Pacific RR, “that when mined or extracted therefrom shall be equal in value to 1% of the net smelter returns on all ores, concentrated, and precipitates mined, and shipped from said property.”

 

Reservation of a royalty interest in favour of the royalty holders in the SW1/4 of Section 17, Township 6 South, Range 5 East, for an amount equal to one half of 1% net smelter returns in the sale and disposal of all ores, minerals, and other products mined and removed from the above described parcel and sold to a commercial smelter or chemical hydrometallurgical plant or one half of 1% of 60% of the sales price if the mine product is disposed of other than to a commercial smelter, additional provisions contained therein, recorded in the royalty documents.

 

3.5Permits and Authorization

 

Current exploration is conducted on private land under the SUA with Legend. Disturbance to date has been de minimis and permitting has consisted of filing Notices of Intent to Drill and to Abandon with the Arizona Department of Water Resources for each section of land on which drilling takes place. IVNE will obtain additional permits as required. Specific permits to construct and operate mine facilities would be determined as the design of the Project advances.

 

Existing and past land uses in the Project area and immediately surrounding areas include agriculture, residential home development, light industrial facilities, and mineral exploration and development. Some dispersed recreation occurs in the area. The climate is dry, and most of the Project area is flat, sandy, and sparsely vegetated. Portions of the Project area are in the 100-year flood plain of the North Branch of Santa Cruz Wash. Within the Project area, approximately 85 acres of land located approximately ¾ mile north of the intersection of N. Spike Road and W. Clayton Road was used during an in situ leaching project in 1991. A Phase 1 Environmental Site Audit (ESA) was conducted on the Project area (Civil & Environmental Consultants 2021).

 

There is a large private land package covering the Project area and area of known mineralization. This private land position could result in reduced permitting time relative to projects that are required to undergo the National Environmental Policy Act (NEPA) process. The precise list of permits required to authorize the construction and operation of this Project will be determined as the mining and processing methods are designed. If NEPA and other federal permitting are avoided, required permits would be administered by Arizona State, Pinal County, and Casa Grande authorities.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
27Nordmin Engineering Ltd.

 

 

The permit approval process for some permits includes review and approval of the process design. Thus, the project design must be substantially advanced to support the application for those permits. These technical permits typically represent the “longest lead” permits. Technical permits with substantial technical design are needed as part of the applications. The anticipated issuing agencies include:

 

-Reclamation Plan approval (Arizona State Mine Inspector)
-Water permits
-Aquifer Protection Permit (ADEQ)
-Air Quality Operating Permit (Pinal County)

 

3.6Environmental Liabilities

 

The 2021 Phase 1 ESA study found no previously unmitigated environmental liabilities associated with the Santa Cruz Project.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
28Nordmin Engineering Ltd.

 

 

4ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY

 

4.1Accessibility and Infrastructure

 

The Santa Cruz Project is located 60 km south southwest of the Greater Phoenix metropolitan area and is accessed from the Gila Bend Highway, 9 km from the City of Casa Grande (population of 55,653 persons). The Santa Cruz Project, as shown in Figure 4-1, is surrounded by current and past-producing Cu mines and processing facilities. The Greater Phoenix area is a major population centre (approximately 4.6 million persons) with a major international airport (Phoenix Sky Harbour International Airport), and well-developed infrastructure, and services that support the mining industry. The cities of Casa Grande, Maricopa, and Phoenix can supply sufficient skilled water, electricity, labour, and supplies for the Santa Cruz Project.

 

 

 

Figure 4-1: Location map

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
29Nordmin Engineering Ltd.

 

 

4.2Climate

 

The climate at the Santa Cruz Project is typical of the Sonoran Desert, with temperatures ranging from -7 °C (19 °F) to 47 ⁰C (117 °F) and average annual precipitation ranging from 76 – 500 mm (3 – 30 in) per year. Precipitation occurs as frequent low-intensity winter (December/January) rains and violent summer (July/August) “monsoon” thunderstorms (Figure 4-2). The Santa Cruz Project site contains no surface water resources. Storm runoff waters from the site are drained toward the Santa Cruz River by minor tributaries to the Santa Rosa and North Santa Cruz washes. Operations at the Santa Cruz Project site can continue year-round as there are no limiting weather or accessibility factors.

 

 

 

Figure 4-2: Average temperatures and precipitation

 

The wind is usually calm. The windiest month is May, followed by April and July. May’s average wind speed of around 5.5 knots (6.4 mph or 10.3 km/h) is considered a light breeze. IVNE will institute measures to reduce dust that could be produced at the Santa Cruz Project site.

 

4.3Local Resources

 

Water rights to the property are held by Legend Property, LLC. Water for exploration drilling has been sourced from a local farm.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
30Nordmin Engineering Ltd.

 

 

Electrical power is available along Midway Road with a high voltage line along the Maricopa-Casa Grande Highway along the northern edges of the Santa Cruz Project area. Also, an east-west rail line parallels the Highway and passes through Casa Grande. A natural Gas line is available along Clayton Road on the southern side of the Project area.

 

IVNE is securing water rights and additional lands surrounding the Santa Cruz and Texaco Deposits (see Section 3) to allow for future mine development activities including potential tailings storage, potential waste disposal and heap leach pad, and processing plant areas as well as space for ramps for underground development.

 

4.4Physiography

 

The Santa Cruz Project is located in the Middle Gila Basin, entirely within the Sonoran Desert Ecoregion of Basin and Range Physiographic Province. The area is characterized by relatively low, jagged mountain ranges separated by broad alluvial-filled basins. This portion of the Sonoran Desert is sparsely vegetated with greater variability near washes and in areas that have lain fallow long. Near washes and longer abandoned areas, catclaw acacia, mesquite, creosote bush, bursage, and salt cedar are common. The Santa Cruz Project area is flat and featureless with an elevation of 403±5 masl and sloping gently to the northwest. The majority of the Santa Cruz Project area has been used for irrigated agriculture, with decaying remnants of an extensive system of wells and concrete lined ditches still present. The alignments of furrows are still visible despite decades of lying fallow. Efforts at real estate development in the 1990s and 2000s have also left visible remnants with preliminary roadworks and some planting (palm trees) overlying the previous agricultural remains. Soils proximal to washes tend to be more sand and gravel-rich, while soils in old agricultural areas are more silt and clay-rich. The physiography is further described in Table 4-1.

 

Table 4-1: Description of Physiography of the Casa Grande Area, Santa Cruz Exploration Property

 

General Physiographic Area Intermontane Plateaus
Physiographic Province Basin and Range
Physiographic Section Sonoran Desert
Alteration Potassic, Phyllic, and Argillic – more intense in mineralized areas
Associated Rocks

Breccia

Conglomerate

Schist

Porphyry

Granite

Diabase

Rock Unit Names

Pinal Schist

Oracle Granite

Gila Conglomerate

Laramide Porphyry

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
31Nordmin Engineering Ltd.

 

 

 

5HISTORY

 

5.1Introduction

 

Historically, there are three main deposit areas that make up the Santa Cruz project, including Texaco (to the northeast), Santa Cruz North directly southwest of Texaco, and Casa Grande West/Santa Cruz South which is the southernmost deposit (see Figure 5-1). ASARCO owned and drilled the Texaco and Santa Cruz North deposits and Hanna-Getty the Casa Grande/ Santa Cruz South deposit (Table 6 2). In 1990 ASARCO entered into a joint venture with Freeport McMoRan Copper & Gold Inc. on the Texaco land position (Table 5-2). Hanna-Getty continued to own and operate the Casa Grande West/Santa Cruz South deposit. The ownership and operations history is further described in Table 5-2.

 

The first discovery of Cu mineralization in the area occurred in February 1961 by geologists from ASARCO. They discovered a small outcrop of leached capping composed of granite cut by a thin monzonite porphyry dyke. The outcrop was altered to quartz-sericite-clay with weak but pervasive jarosite-goethite and a few specks of hematite after chalcocite, particularly in the dyke.

 

ASARCO proceeded with preliminary geophysical surveys that same year, including induced polarization (IP), resistivity, seismic reflection, and magnetics. Upon positive results from the geophysical surveys, a small drill program of six holes was funded, with the last hole being the first to intersect the significant mineralization that became known as the West Orebody and, in time, the Sacaton open pit mine (Figure 5-1).

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
32Nordmin Engineering Ltd.

 

 

 

 

Figure 5-1: Historic drill collars, IMC mineral inventory outlines and historic deposit and exploration target names (white) as well as current project names for IVNE and Arizona Sonoran Copper Company assets (in yellow).

 

Bolstered by the discovery at Sacaton, ASARCO expanded exploration efforts across the Casa Grande Valley and in 1964 the first hole was drilled on the Santa Cruz Project. By May 1965, seventeen drill holes were completed without similar success, and ASARCO reduced their land position. Subsequent reviews in 1970-1971 deemed the Santa Cruz Project worth renewed exploration activity. Following the initiation of the Santa Cruz Joint Venture (SCJV) between ASARCO Santa Cruz, Inc. and Freeport McMoRan Copper & Gold Inc. in 1974, additional ground was acquired around the Santa Cruz North deposit. By this time, various joint ventures, as below, had staked considerable ground over and around what would eventually be the Casa Grande West (now Santa Cruz South) deposit.

 

In 1973, David Lowell put together an exploration program called “the Covered Area Project” (CAP) that was funded first by Newmont Mining, then, in succession, by a joint venture between Newmont and Hanna Mining, then Hanna with Getty Oil Corp. and Quintana; though both Quintana and Newmont would pull out of the project before any discoveries were made. In 1974, after having systematically drilled over 120 holes at 20 projects across Southwestern Arizona, David Lowell and his team focused their attention on the Santa Cruz system (which Lowell and his team called “the Casa Grande Project”). ASARCO had just put the Sacaton operation into production and Lowell and associates were aware of the evidence for shallow angle faulting and potential for dissected porphyry mineralization that might have been displaced undercover in the Casa Grande Valley (Lowell, unpublished personal communication). Furthermore, the CAP program had compiled historic data of the area that indicated several water wells drilled had returned pebbles of Cu-oxide mineralization. Careful stream mapping and drainage analysis revealed that the Santa Cruz River had reversed flow directions at least twice in recent history, and it was this revelation that allowed Lowell to trace the exogenous oxide-Cu pebbles back to the Santa Cruz deposit area. They discovered evidence for porphyry mineralization in their first drill hole, which intersected leached capping, and by their seventh hole (CG-7), they had intersected ore grade supergene enriched Cu mineralization at what would be called the Casa Grande West deposit. Drilling under the CAP program continued through to 1977, at which point Hanna Mining took over as operator under a joint venture with operation funding from Getty Oil Corp. Between 1977 and 1982, Hanna-Getty advanced a tight spaced drill program that delineated an estimated 500 million tonnes of 1% Cu at Casa Grande West, and countless exploration holes in the surrounding Casa Grande Valley (Lowell unpublished personal communication). The decision to go underground and mine the Casa Grande West deposit was never made, and the combination of encroaching real estate, the growing environmental movement, and potential mismanagement by Hanna-Getty followed by the fall of Cu commodity prices all resulted in the Casa Grande West project becoming inactive in the early 80s.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
33Nordmin Engineering Ltd.

 

 

5.2Previous Exploration

 

5.2.1Sacaton Mine

 

ASARCO went on to mine the Sacaton deposit from 1974 to 1984. The Sacaton deposit was mined using open pit methods with the beginnings of underground workings initiated but depressed Cu prices resulted in the halt of all mining at Sacaton. Table 5-1 shows the historic mine production from Sacaton.

 

Table 5-1: Sacaton Historic Mine Production (Fiscal Years Ended December 31)

 

Year Ore Milled Short Tons Mill Grade Cu% Cu Short Tons Au Troy Oz. Ag Troy Oz.
1974 2,020,000 0.63 9,516 N/A N/A
1975 3,630,000 0.74 21,918 3,153 N/A
1976 3,782,000 0.71 22,021 3,151 N/A
1977 3,471,000 0.70 19,872 3,103 N/A
1978 4,153,000 0.67 23,042 3,691 N/A
1979 4,006,000 0.65 21,367 3,558 142,000
1980 3,819,000 - 16,097 2,504 124,000
1981 4,103,000 - 21,015 3,334 172,000
1982 4,165,000 - 20,892 2,499 154,000
1983 4,003,000 - 18,794 1,983 134,000
1984 1,000,000 - 4,496 479 33,000
Total 38,152,000 0.69 199,030 27,455 759,000

 

Source: Arizona Sonoran Copper Company, Inc. Preliminary Economic Assessment (NI 43-101), August 2021.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
34Nordmin Engineering Ltd.

 

 

5.2.2Santa Cruz and Texaco Deposits

 

Several other deposits, including Santa Cruz South (also known as Casa Grande West), Santa Cruz North (Santa Cruz North and South are collectively referred to as “Santa Cruz”), Texaco, and Parks-Salyer were identified during ASARCO drilling in the 1960s and subsequent drilling in the 1970s and 1980s by numerous exploration companies including Newmont Mining, Hanna, Hanna-Getty, and a joint venture between ASARCO Santa Cruz Inc. and Freeport McMoRan Copper & Gold Company (SCJV). In total, 362 drill holes totalling 229,577 m have been drilled by previous owners delineating the cluster of deposits. Table 5-2 presents a summarized history of exploration on the property. There are no records of work by Texaco, but the company held land over what is now called the Texaco deposit.

 

Table 5-2: History of Exploration Activities Across the Santa Cruz and Texaco Deposits

 

Dates Activities Company(s) Description Notes
1961 Prospecting and discovery ASARCO ASARCO geologists Kinnison and Blucher identify Sacaton Discovery Outcrop An outcrop of granite with a thin dyke of porphyry was discovered.
1961 Geophysical Surveying ASARCO ASARCO Geophysical Dept. report Geophysical surveys including IP, resistivity, magnetics.
1962 Drilling ASARCO Six exploration drill holes at Sacaton First five holes cut sulphides, but only a few short runs of ore grade rock. The sixth hole was the first hole within the West Orebody.
1964 Drilling ASARCO Five holes were drilled near the Santa Cruz deposit by ASARCO (SC-2 to SC-6) These were exploration drill holes, none of which intersected the main mineralization at Santa Cruz. SC-5 was drilled nearly 3 km SW of the main deposit.
1965 Drilling ASARCO 11 holes drilled near the Santa Cruz deposit by ASARCO (SC-7 to SC-17) These were exploration drill holes, SC-1 was drilled along the western margin of the subsequent Independent Mining Consultants, Inc. (IMC) block model. And SC-16 was just to the East of the future Santa Cruz North deposit. SC-17 was drilled approximately 4 km SW of the Casa Grande deposit (furthest step out exploration hole in the database).

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
35Nordmin Engineering Ltd.

 

 

Dates Activities Company(s) Description Notes
1974 Drilling and Discovery Hanna-Getty Five holes were drilled around Santa Cruz North and one at Casa Grande by Hanna-Getty (CG-1 to CG-6) Six holes drilled by Hanna-Getty under the CAP led by Lowell, one of which (CG-3) intersected near ore grade mineralization along the western boundary of what would become the Santa Cruz North and Casa Grande deposits.
1974 Drilling and Discovery ASARCO SC-18,19 and 20 are drilled at Santa Cruz North by ASARCO Following the initiation of exploration in the Santa Cruz area by the CAP initiative, led by Lowell, ASARCO re-initiated exploration drilling in the area. All three holes intersected porphyry-style mineralization at what would be called the Santa Cruz North deposit.
1975 Drilling Hanna-Getty Two holes were drilled at Casa Grande, two holes drilled at Santa Cruz North and one hole drilled at Texaco by Hanna-Getty (CG-7 to CG-11) Hole CG-7 was the first intersection of ore grade mineralization, as reported by Lowell.
1975 Drilling and Discovery ASARCO Four holes were drilled at Santa Cruz North and one at Texaco by ASARCO (SC-21 to SC-24) ASARCO drilled five holes, 3 nearby 1974 drilling that intersected mineralization at Santa Cruz North, and two exploration step out holes each 1.5 km to the NE of the Santa Cruz North area, SC-21, and SC-23 which intersected the Texaco deposit mineralization.
1976 Drilling and land position expansion Hanna-Getty Two holes were drilled at Santa Cruz North and 14 holes drilled at Casa Grande by Hanna-Getty (CG-12 to CG-33) Bolstered by success in CG-7, and led by Lowell, key ground over what would eventually be the Casa Grande deposit was picked up, and exploration drilling advanced through 1976.
1976 Drilling ASARCO One hole was drilled approximately 1 km NE of the Casa Grande deposit (SC-25), and six holes were drilled at Texaco (SC-27, -28, -29, -30, -31, and -34)  

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
36Nordmin Engineering Ltd.

 

 

Dates Activities Company(s) Description Notes
1977 Drilling and Operatorship change Hanna-Getty One hole was drilled at Texaco (CG-48), and 45 holes were drilled at Casa Grande (CG-34-CG-79) Hanna-Getty took over operatorship from Lowell and the CAP team and began a close-spaced drill program to delineate the ore body at Casa Grande.
1977 Drilling ASARCO Six holes were drilled at Texaco and 12 holes drilled at Santa Cruz North by ASARCO (SC-35 to SC-52)  
1978 Drilling Hanna-Getty One hole was drilled north of Santa Cruz North and 31 holes drilled at Casa Grande by Hanna-Getty (CG-80 to CG-122)  
1979 Drilling Hanna-Getty Six holes drilled by Hanna-Getty approximately 1 km west of the Casa Grande and Santa Cruz North deposits  
1979 Drilling ASARCO Four holes were drilled at Santa Cruz North by ASARCO (SC-55 to SC-58)  
1980 Drilling ASARCO Six holes were drilled at Santa Cruz North by ASARCO (SC-59 to SC-64)  
1981 Drilling Hanna-Getty Two holes were drilled north and west of Santa Cruz North  
1982 Drilling Hanna-Getty Two holes were drilled north and west of Santa Cruz North  
1990-1991 Land Consolidation SCJV (ASARCO, Santa Cruz Inc., and Freeport McMoRan Copper & Gold Inc.) – Texaco Texaco approached SCJV (ASARCO-Freeport) regarding the sale of the Texaco land position A series of internal memos from SCJV discussed the opportunity and holding costs and why they should acquire the lands from Texaco.
1994 In situ Cu Mining Research Project US Bureau of Reclamation (USBR) and SCJV   Permits received to begin injection of sulphuric acid.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
37Nordmin Engineering Ltd.

 

 

Dates Activities Company(s) Description Notes
1995 In situ Cu Mining Research Project USBR – SCJV  

Pilot plant completed.

 

1996 Drilling SCJV 11 holes drilled at and around Texaco by ASARCO (SC-65 to SC-74)  
1996 In situ Cu Mining Research Project USBR-SCJV  

Mining test started In February.

 

1997 Drilling SCJV Four holes were drilled by ASARCO at Texaco (SC-75 to SC-78)  
1997 In situ Cu Mining Research Project USBR-SCJV Lost funding – closure started

USBR lost Congressional funding in October. Injection continued until December.

 

1998 In situ CU Mining Research Project USBR-SCJV State required closure activities – final report to Bureau of Reclamation

Pumping continued until the end of February. Plant to care and maintenance. The final research report was never made public.

 

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
38Nordmin Engineering Ltd.

 

 

5.3Previous Reporting

 

5.3.1Hanna 1982

 

Watts Griffis McOuat Ltd. (WGM) calculated a historical ore and mining reserve for Hanna Mining in 1982. Ore was determined from sections by calculating areas from drill hole intercepts and distance between holes, and by assigning to each area the weighted average grade of the holes on either side. If a single hole was involved, the grade of that hole prevailed.

 

Mining reserves were calculated using mining blocks outlined for Hanna’s mining plan 5-E and took into consideration the additional work done on geologic interpretation.

 

WGM recommended additional consideration be given to a more flexible method of mining such as sublevel caving.

 

5.3.2In Situ Joint Venture 1997

 

In 1986, the Bureau of Mines obtained Congressional approval and funding to study in situ Cu mining. In 1988, the Santa Cruz deposit was selected for this research project sponsored by a joint venture program between landowners ASARCO Santa Cruz Inc. and Freeport McMoRan Copper & Gold Inc., and the main project funder the US Department of the Interior, Bureau of Reclamation.

 

Field testing began in 1988, and the test wells were constructed in 1989 in a 5-point pattern with one injection well centred between four extraction wells. Salt tracer tests were conducted in 1991, permits for the use of sulphuric acid were received in 1994, and the solvent extraction-electrowinning (SX-EW) pilot plant was completed in 1995.

 

The in situ testing began in February 1996, but research funding was halted in October 1997 due to a change from Congress. Utilizing the carryover funds from previous years of the program, injections continued until December 1997 and pumping until mid-February 1998. At this point, the remaining fluids in the leach zone were less acidic, and metals remaining in solution were redeposited into the ore body through precipitation. A final report was not made publicly available. However, a newsletter from the project was circulated in March 1998 and noted that 35,000 lbs. of Cu were extracted.

 

5.3.3IMC 2013

 

IMC constructed a block model for the Santa Cruz South deposit, the Texaco deposit, and the Parks-Salyer deposit for Russell Mining and Minerals in 2013.

 

The block model for the Santa Cruz South deposit was based on 116 drill holes with 18,034 assay intervals for a total of approximately 342,338 ft (104,344 m) of drilling, in which 90.7% of the intervals were assayed for Cu. Forty percent of the drill intervals were assayed for acid soluble Cu and 5% for cyanide soluble Cu.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
39Nordmin Engineering Ltd.

 

 

The block model for the Texaco deposit was based on all Cu drilling data available as of April 5, 2013. The block model was based on 29 drill holes with 2,281 assay intervals for a total of approximately 82,696 ft (25,205 m) of drilling, in which 92.5% of the intervals were assayed for Cu. Less than 9% of the drill intervals were assayed for acid soluble Cu or cyanide soluble Cu.

 

The block model for the Parks-Salyer was based on seven drill holes with 7,398 ft (2,254 m) of drilling. Topography, the bottom of the conglomerate, and the top of the bedrock were all added to the model using the drill hole collars, any downhole information that existed, plus additional data for drill holes from outside the model limits. These surfaces are a rough approximation based on the limited amount of information available.

 

5.3.4Stantec-Mining 2013

 

5.3.5Physical Resource Engineering 2014

 

In 2014 Physical Resource Engineering completed a conceptual study, “Mining Study Exploitation of the Santa Cruz South Deposit by Undercut Caving” for Casa Grande Resources LLC.

 

5.4Historical Production

 

No historical production has been carried out on the property.

 

5.5Nordmin QP Opinion

 

The historical mining and processing as described above are reasonable indicators of what IVNE could expect to encounter should IVNE develop any of the exploration potential areas into an Exploration Target in the future. The reader is cautioned that the historical mineral inventories listed above vary between different sources and therefore should be considered as an indicative only.

 

6GEOLOGICAL SETTING, MINERALIZATION AND DEPOSIT

 

6.1Regional Geology

 

Basement lithologies of Arizona consist of formations developed during the Paleoproterozoic collisional orogeny that were subsequently stitched together by anorogenic granitic plutonic suites in the Proterozoic. Basement lithologies are represented by units such as the Pinal Schist, a lithology common throughout southern Arizona, and the Oracle and Ruin anorogenic granites. Proterozoic anorogenic granitic complexes were emplaced between 1450-1350 Ma. Continental rifting in the Mesoproterozoic brought Paleo- and early Mesoproterozoic granitic complexes to the surface where they were subsequently buried beneath rocks of Apache Group, which represents a very shallow intracontinental basin. Around 1100 Ma, these rocks were intruded by Diabase dykes and sills related to the break-up of the Rodinia supercontinent.

 

Throughout the Paleozoic, Arizona was located within a craton with major disconformities in the stratigraphy interpreted to represent relative sea level changes. By the Triassic, a subduction zone was established along the continental margin of Pangea with a magmatic arc that lay largely to the west of Arizona. A sinistral convergence is generally assumed at the continental plate margin. This convergence geometry suggests the potential for arc parallel transtensional or transpressional deformation in the back arc. The magmatic arc led to the deposition of material into the Arizona continental interior. By the Middle Jurassic, the magmatic arc had been established through Arizona. The arc was low standing as an eolian dune field from the continental interior was blown into the basins and interbedded with the felsic volcanic rocks. At this time, the arc generally is considered to have been under transtension with a major sinistral strike-slip fault, the Mojave – Sonora Megashear, cutting across northern Mexico and linking with the opening of the Atlantic Ocean (Tosdal and Wooden, 2015; Anderson, 2015).

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
40Nordmin Engineering Ltd.

 

 

By the Late Jurassic Period and into the Early Cretaceous Period, the Santa Cruz Project area was located on the shoulder of a major rift, the Bisbee basin, which is a failed arm of the rift that created the Gulf of Mexico. By the end of the Early Cretaceous Period, the area lay in a back arc setting that was gradually being eroded. Material from this erosion was being shed to the northeast. By the Late Cretaceous Period (approximately 80 Ma), the magmatic arc had migrated into Arizona. Shortening is contemporaneous with diachronous magmatism within the same location (Tosdal and Wooden, 2015).

 

Cessation of magmatic activity in the Paleocene Period marked the onset of erosion of the uplifted arc, which lay southwest of the Colorado Plateau. Eocene sequences deposited from the Transition Zone, which separates the Colorado Plateau from the Basin and Range extended terrane, onto the Colorado Plateau represent the products of the exhumation of the arc.

 

6.2Metallogenic Setting

 

The Santa Cruz Project lies along a northwest to southeast trending, approximately 600 km long porphyry Cu belt that includes many productive Cu deposits such as Mineral Park, Bagdad, Resolution, Miami-Globe, San Manuel-Kalamazoo, Ray, Morenci, and the neighbouring Sacaton (Figure 6-1). These deposits lie within the Basin and Range province that covers most of the southwestern United States and Northwestern Mexico. This region is characterized by linear mountain chains separated by broad flat valleys that are the result of the tectonic extension during the mid-Cenozoic Period (Figure 6-2).

 

The Cu porphyry deposits within this trend are the genetic product of igneous activity during the Laramide orogeny (approximately 80 Ma to 50 Ma) when northeast-directed subduction of the Farallon Plate beneath the North American plate produced a northwest-southeast-striking magmatic arc (Leveille and Stegen, 2012) and associated porphyry Cu systems (Figure 6-1). Laramide porphyry systems in the immediate vicinity of the Santa Cruz Project define a southwest to northeast linear array orthogonal to the trend of the magmatic arc environment.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
41Nordmin Engineering Ltd.

 

 

 

 

Figure 6-1: Regional geology of Cu porphyry belt and map of location of Cu porphyry deposits hosted in the area

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
42Nordmin Engineering Ltd.

 

 

 

 

 

Figure 6-2: Map of structures related to extension during the mid-Cenozoic

 

During the tectonic extension of the mid-Cenozoic Period, the Laramide arc and related porphyry Cu systems were variably dismembered, tilted, and buried beneath basin alluvium and conglomeratic deposits that fill the Casa Grande Valley. Prior to concealment undercover, many of the Laramide porphyry systems of Arizona experienced supergene enrichment events that make them such economically significant deposits (Figure 6-3).

 

Supergene alunite from the Sacaton porphyry Cu deposit was K-Ar dated at 41 Ma (Cook, 1994). At the Santa Cruz Project, evidence for multiple cycles of supergene enrichment is represented by multiple chalcocite and oxide-Cu “blankets” that were developed oblique to each other (Figure 6-4) as a result of rotation and subsequent overprinting by new supergene blankets. Cook (1994) has shown that enrichment happened throughout the Tertiary and ceased with the deposition of overlying sedimentary packages, comprised predominantly of conglomerates, which changed the hydrology in the vicinity of the deposit(s). The earliest supergene enrichment is interpreted to have occurred in the Eocene epoch (Tosdal and Wooden, 2015).

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
43Nordmin Engineering Ltd.

 

 

 

 

Figure 6-3: Generalized cross-section through well-developed supergene enrichment profile showing geochemical stratigraphy Leached capping environment and metals mobility engendered through oxidative destruction of pyrite and Cu ore sulphides.Pyrite contributes four moles of H+(aq) per mole of pyrite, with Fe++(aq) and sulphate; ferrous iron oxidizes rapidly to H+(aq) and Fe+++(aq), the latter serving as a strong oxidizer for Cu sulphides. Cu sulphides produce nominal to no low pH solutions upon weathering. Lateral transport of iron and Cu produces ferricretes of hematite > goethite and exotic Cu as silicates, sulphates, halides, and Cu++ adsorbed onto goethite and manganese oxides. Oxidation along sheeted fractures and faults deepens the topographic base of all supergene stratigraphic intervals, as do supergene solutions migrating through phyllic and argillic-altered host rocks. Reactive host rocks shown on the margins of the figure attenuate Cu transport and produce erratic, fracture-controlled in situ development of Cu oxides; such in situ development of Cu oxides would be characteristic of K-silicate–altered (potassic) rock volumes. For scale, note that any of the three supergene-related geochemical zones may be variably developed such that thicknesses may range from nominal to several hundred metres as a function of the maturity of the weathering profile. Abbreviations: bn = bornite, cp = chalcopyrite, HW = hanging wall, mt = magnetite, py = pyrite (Chávez, 2021)

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
44Nordmin Engineering Ltd.

 

 

 

 

Figure 6-4: Santa Cruz property mineralization cross-section (ASARCO, 1978)

 

6.3Santa Cruz Project Geology

 

The Santa Cruz system (comprising Santa Cruz, Sacaton, Texaco and Parks-Salyer areas); (Figure 6-5) represent portions of one or more large porphyry Cu systems that have experienced supergene enrichment, dismemberment, and displacement during Tertiary extensional faulting.

 

The geology of the area is dominated by the 1450 Ma to 1350 Ma anorogenic Oracle Granite. Proterozoic aged (approximately 1100 Ma) diabase sills, and rare dykes, are also known from historic drilling and have a shallow dip to the west (25°/005°) that is interpreted to reflect rotation during Basin and Range extensional tectonics. The Diabase dykes are associated with discrete local increases in Cu grades attributable to rheological and geochemical contrasts with the more felsic Oracle host rocks.

 

At the Santa Cruz Project, porphyry-style mineralization is attributed to Laramide-aged (approximately 80 Ma to 50 Ma) magmatism characterized by biotite-quartz-feldspar-phyric granodiorite and quartz monzonite porphyry dykes that are interpreted to have shallow dips variably to the west. Sometime after emplacement, the Laramide dykes and the associated porphyry-style mineralized system experienced uplift, erosion, dismemberment, tilting, and supergene enrichment that continued until the system was buried under syn-extensional basin filling conglomerates that sealed off the system during Basin and Range formation.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
45Nordmin Engineering Ltd.

 

 

 

Figure 6-5: Cross-section of the Santa Cruz system (Vikre et al.2014)

 

Directly overlying the erosional surface of crystalline basement rocks is a series of sedimentary and volcanic units consisting predominantly of syn-extensional conglomerates (dipping as much as 50°), and andesitic, latitic, and alkali basalts associated with dykes, sills, flows, and three diatremes (Vikre et al., 2014). These units have all been intersected in drilling at the Santa Cruz Project (Figure 6-6). Some tephra deposits related to the diatremes are interbedded with a moderately sorted pebble conglomerate interpreted by Vikre et al. (2014) as being part of the basal Whitetail formation dated to approximately 40 Ma to 28 Ma (Banks et al., 1972; Cummings, 1982; Scarborough, 1989). The diatremes are similar in age and include maar and tephra variably deposited above the earliest syn-extensional conglomerates as well as directly onto the Oracle-Laramide erosional surface.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
46Nordmin Engineering Ltd.

 

 

 

 

Figure 6-6: Plan map of the diatreme pipes, maar and tephra deposits at the Santa Cruz Project (Vikre et al.2014)

 

These diatreme facies are buried beneath a 200 m to 900 m sequence of basin fill deposits that include well consolidated conglomerates (tentatively correlated with the Whitetail formation) and younger variably consolidated conglomerates interpreted to be equivalent to the Gila Group. These basin filling sediments predominantly composed of conglomeritic sequences cover the entire Santa Cruz Project area. Historic field mapping outside of the Santa Cruz Project subdivided outcropping conglomerate units into the Sacaton conglomerate, Burgess Peak conglomerate, and Gas line conglomerate.

 

Quaternary alluvium consisting of poorly sorted silt and sand is spread out across the Casa Grande valley, reaching up to 70 m thick near the Santa Cruz River and displays a conformable relationship with underlying Gila Group conglomerates. Dissected alluvial fans flank the Tabletop mountains to the southwest and are largely comprised of volcanic rubble. Figure 6-7 shows a simplified stratigraphic column of the geologic units and mineralization.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
47Nordmin Engineering Ltd.

 

 

 

Figure 6-7: Simplified stratigraphic section of the Santa Cruz Project (IVNE documents)

 

6.3.1Geologic Units

 

Detailed descriptions of the dominant lithologies present in the Santa Cruz Project area are as follows:

 

Proterozoic

 

·Pinal Schist: Quartz-sericite schist with banded injection gneiss, granitic gneiss, and aplite. The Pinal is a common basement rock of southeastern Arizona, possessing many of the characteristics of a subduction complex associated with the Paleoproterozoic (1.7 Gz to 1.64 Ga) Mazatzal volcanic arc. The Pinal Schist is well exposed throughout southern Arizona but is known in the area only from deep drilling near Sacaton and Parks-Salyer areas that intersected Pinal Schist beneath an interpreted sub-horizontal listric fault.

 

·Oracle Granite: There are two dominant phases identified from historic drilling. One is a coarse-grained granite with biotite and has noted similarities with the Mineral Butte Granite at Blackwater (report by A.G. Blucher) and a second coarse-grained megacrystic quartz monzonite with decrease biotite. In the surrounding mapped quadrangle, the Oracle Granite is prevailingly a coarse-grained hypidiomorphic biotite granite with large pink or salmon-coloured orthoclase feldspars 32 mm to 38 mm across that gives rock a pink or gray mottled appearance on fresh surfaces. Groundmass composed of uniformly sized, 5 mm, grains of clear white feldspar and glassy quartz with greenish-black masses of biotite and magnetite. Composition suggests that rock should be classed as quartz monzonite rather than granite. Surface exposures of light-buff colour. Age is interpreted to be 1450 Ma to 1350 Ma (Tosdal and Wooden, 2015). Alteration minerals are dominated by secondary orthoclase and sericite.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
48Nordmin Engineering Ltd.

 

 

·Proterozoic Diabase: Holocrystalline, medium- to coarse-grained ophitic to subophitic textures with plagioclase and clinopyroxene (augite) as the dominant primary phases. Magnetite, oligoclase, sulphide (pyrite and chacopyrite) mineralization are reported as minor phases within the diabase. The diabase is interpreted as belonging to the Mid-Proterozoic (1090 Ma) diabase province exposed throughout much of central Arizona, and is considered to be a ubiquitous feature of the Precambrian geology of central and western Arizona and southeastern California (Harlan, 1993). These diabase intrusions were dominantly emplaced as horizontal to sub-horizontal sills, though rare dykes are recognized. These dykes are associated with local discrete increases in observed hypogene sulphide mineralization – interpreted as being a more reactive and receptive host rock for hydrothermal fluid deposition of sulphide mineralization. Historic petrographic thin section analysis indicates diabase is dominantly associated with hydrothermal biotite and epidote.

 

Laramide Igneous Rocks

 

·Laramide Porphyry: Quartz-biotite-feldspar-phyric porphyritic dykes at the Santa Cruz Project are associated with primary hypogene mineralization and alteration. The porphyry has a quartz monzonite composition (35% quartz, 6% biotite, 29% feldspar, 30% K-feldspar, and plagioclase) with 40% phenocrysts averaging 1.5 mm and 60% aplitic to aphanitic groundmass. Quartz phenocrysts are less than 10 mm, sub-spherical, and comprise approximately 25% of the phenocrysts. Biotite makes up 15% of the phenocrysts and are less than 5 mm. Subhedral plagioclase phenocrysts, 60%, are generally less than 7 mm. There are at least two different mineralizing phases of Laramide-aged porphyritic intrusion at Santa Cruz. One porphyry contains quartz phenocrysts <5% by volume, and is generally associated with increased biotite phenocrysts as well as increased biotite content in the groundmass, typically giving this unit a darker colour. The other variant contains more quartz phenocrysts (>5%), and is often described as being more siliceous and lighter in colour. Historic petrographic reporting indicates the overall microscopic characteristics and model mineral abundances are broadly equivalent. Late biotite-quartz feldspar monzonite porphyry dykes intersected in SC-041 and SC-043 clearly cross-cut sulphide mineralization, but appear very similar to pre-mineral and mineralizing dykes and hosts strong biotite-orthoclase alteration interpreted as indicating a late emplacement but prior to cessation of hydrothermal activity. The late biotite-quartz feldspar monzonite porphyry is composed of 15% biotite, 25% K-feldspar, 40% plagioclase and 20% quartz with 15% phenocrysts consisting of 20% biotite, 70% plagioclase and 10% quartz in an aphanitic 15% biotite, 30% K-feldspar, 35% plagioclase, 20% and quartz groundmass with 0.06 mm average crystal size. Alteration minerals in mineralized Laramide dykes are dominated by hydrothermal biotite, sericite, and lesser orthoclase feldspar. K-Ar age dating reported in Balla (1972) returned 65 Ma to 64 Ma ranges for phyllic alteration of Oracle Granite and 70.53 Ma from Ar-Ar in biotite phenocrysts within a biotite-quartzfeldspar-phyric porphyry in central fault block at Sacaton.

 

Tertiary

 

·Syn-extensional Conglomerates: These conglomerates show wide variation in thickness, and characteristics across the property. They are mainly composed of locally derived material, dominant clasts have been identified as originating from the Oracle Granite, Pinal Schist, Laramide Porphyry, and diabase. They have been deposited directly atop the erosional surface of the previously described lithological units. The oldest basal conglomerates have been tentatively correlated with the Whitetail Conglomerate that has an age range of approximately 41 Ma to 28 Ma (Vikre et al., 2014)

 

·Diatremes and Associated Mafic Volcanics: Three diatremes are recognized on the property (Vikre et al., 2014) and consist of intrusive heterolithic breccias and eruptive deposits including tephras (tuff rungs) and tuffaceous sediments (maar-fil deposits) that border and fill diatreme vents respectively, and lie on the mid-Tertiary erosion surface of Middle Proterozoic granite and Laramide porphyry, which compose most xenoliths in pipes and are the host rocks of the system. Some igneous xenoliths in the pipes contain bornite-chalcopyrite-covellite assemblages with hypogene grades >1 wt % Cu, 0.34 g/t Au, 15.6 g/t Ag, and small amounts of Mo (<0.01 wt %), indicating the phreatomagmatic event has partially dissected and sampled mineralization at depth. The phreatomagmatic diatreme events are interpreted to be related to Tertiary igneous activity recognized outside of the project area to the south and west that consist of andesitic, latitic, and basaltic flows that are often tilted and faulted where exposed.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
49Nordmin Engineering Ltd.

 

 

·Conglomerates: The basin fill conglomerates are considered to be broadly corelative with the Gila Conglomerate, recognized throughout much of Southwestern Arizona. In the Santa Cruz Project area, the conglomerates are up to 900 m thick and are generally dominated by clasts of Oracle Granite, Pinal Schist and mafic volcanics sourced proximally, and are variably tilted at depth and structurally offset by numerous normal faults associated with Basin and Range extension. Historical mapping reports the Sacaton conglomerate is known near the Sacaton deposit to the northeast of the Santa Cruz deposit and consists of well consolidated, unsorted fanglomerate with indurrated Precambrian granite, schist, and gneissic boulders and grains. Burgess Peak conglomerate is exposed just northwest of Casa Grande and is composed of hard granite-boulder fanglomerate with hematite cement. The Gas Line conglomerate outcrops to the east of the Sacaton deposit, and consists of poorly consolidated fanglomerate and sandy stream and clay deposits that exited north and south into the valley and is considered an important component in the Casa Grande aquifer. Historic reporting by ASARCO describes three generalized units from historic drilling in the Santa Cruz Project area:

 

oUnit I is the lowermost conglomerate and is characterized by a massively bedded, well consolidated, poorly sorted, conglomerate with 30% to 70% clasts comprised of 70% to 100% altered leached capping and 0% to 30% granite, porphyry and gneiss in a heavily iron-stained sand and silt-sized matrix (Kreis, 1978). This unit closely resembles structureless fault gouge and breccia capping in general appearance.

 

oUnit II lies both above Unit 1 and directly upon bedrock and is characterized by well consolidated, poorly sorted, conglomerate with locally developed siltstone and sandstone beds dipping 30° to 50° (to core axis in vertical holes – no azimuth constrained historically), and massive conglomerate with approximately 60% clasts comprised of 90% to 100% gneiss and lesser volcanic agglomerate clasts with <10% granite, porphyry, and leached capping material supported by a brown to locally grey-coloured clay-sand matrix.

 

oUpper Unit conglomerates are reported from several historic holes (SC-45, SC-44, SC-41, SC-28, and SC-23) and are described as calcite-cement-supported indurated conglomerates with 45% clasts dominated by 60% fresh to propylitically altered granitic rocks, 25% propylitically altered porphyry and 15% unmineralized clasts in a sand to clay-sized matrix that ranges from brown to grey to locally brownish-red in colour. This lithology occurs in sedimentary contact between Unit I and Unit II in faulted contact with bedrock.

 

·Quaternary Alluvium: The alluvium is comprised of poorly consolidated silt and sand and minor volcaniclastic material from nearby weathering hills and is spread out across the Casa Grande valley, reaching a maximum thickness of around 80 m (approximately 262 ft) near the Santa Cruz River. It appears to have a gradational conformable contact with underlying conglomerates.

 

6.4Property Mineralization

 

Deep drilling through cover has delineated a 10 km by 2.5 km corridor trending from the Santa Cruz deposit in the southwest to the Sacaton deposit in the northeast, which contains basement rocks that host hypogene porphyry-style alteration and mineralization with secondary supergene enriched Cu mineralization relating to the oxidation of Laramide age porphyry mineralization of the Santa Cruz system. The Santa Cruz Project covers the southwest 5.5 km by 2.5 km of that corridor, encompassing the Santa Cruz deposit and Texaco target.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
50Nordmin Engineering Ltd.

 

 

Mineralization at the Santa Cruz Project is generally divided into three main groups:

 

1.Primary hypogene sulphide mineralization consists of chalcopyrite, pyrite, molybdenite, and minor bornite, and covellite hosted within sulphide and quartz-sulphide stringers, veinlets, veins, vein breccias, and breccias as well as fine to coarse disseminations within vein envelopes (dominantly replacing mafic minerals biotite and hornblende) associated with hydrothermal porphyry-style mineralization and alteration related to Laramide-aged quartz-biotite-feldspar-phyric dykes (65 Ma to 64 Ma from K-Ar; Balla, 1972). Hypogene mineralization appears concentrated around one or more intrusive centres that have been subsequently dismembered and buried during Basin and Range extension. Hypogene mineralization has been intersected in drilling to depths of over 1,200 m. Rock types hosting hypogene mineralization in and about the Santa Cruz deposit are comprised of 82% Precambrian granite (locally known as Oracle Granite), 15% Laramide biotite-quartz-feldspar porphyry dykes (quartz monzonite to granodiorite compositions), and 3% Precambrian Diabase dykes and other rock types.

 

2.Secondary supergene sulphide mineralization is comprised of chalcocite (with accessory chalcopyrite-pyrite that was incompletely replaced by chalcocite, as well as djurleite, and digenite identified in historic XRD analyses). Supergene mineralization was originally developed as sub-horizontal domains (i.e., “chalcocite blankets”) within the phreatic zone (below paleo water table) as a result of Cu being remobilized by acidic groundwater that leached Cu from the overlying oxidizing hypogene sulphide environment. The Cu was then subsequently transported through the vadose zone (above the paleo water table), where it was redeposited within the phreatic zone as chalcocite that dominantly replaces iron sulphide minerals (i.e., pyrite-chalcopyrite). As uplift and erosion occurred, this process was repeated several times, resulting in multiple chalcocite horizons being developed over geologic time. Basin and Range tectonic extension then exposed these horizons to subsequent leaching and oxidization (hematite replacing chalcocite) and structural modification by faulting that rotated, truncated, offset, and displaced domains of supergene sulphide mineralization.

 

3.Supergene enriched Cu mineralization, referred to as “oxide mineralization” is dominated by chrysocolla (Cu-oxide) and atacamite (Cu-chloride) with subordinate brochantite, dioptase, tenorite, cuprite, Cu wad, and native Cu, and as Cu-bearing montmorillonite. Cu oxide mineralization is generally developed at the interface between the leached capping and chalcocite zones, as well as being irregularly distributed within structures and in the overlying conglomerates, where they are present as exogenous, or “exotic” Cu occurrences (this includes Cu-oxide cemented paleo-gravels/conglomerates as well as remobilized clasts of weathered Cu-oxide mineralization). At the Santa Cruz deposit atacamite and chrysocolla mineralization exhibit a two-fold geometry, with a relatively steep northeast-dipping, and a shallow southwest-dipping horizon of mineralization with distinct zonation of chrysocolla overlying a zone of chrysocolla and atacamite, overlying a zone of atacamite that in turn overlies the secondary supergene chalcocite mineralization described above (Figure 6-4). Poorly crystalline chrysocolla was identified and studied by previous operators, Hanna-Getty, who noted an intimate association (and possibly intergrown relationship) with Cu-bearing montmorillonite. The poor crystallinity, exceptionally fine-grain size, intimate intergrowths, and silicate composition made the chrysocolla and Cu-bearing montmorillonite difficult to recover (Watts et al., 1982).

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
51Nordmin Engineering Ltd.

 

 

6.4.1Hypogene Mineralization at the Santa Cruz Deposit

 

Hypogene mineralization at the Santa Cruz deposit is distributed within an area approximately 2 km by 2 km and has been intersected in drilling from the bedrock interface at 300 m depth to over 1,200 m depth and exhibits potential to be open in all directions. Lithologies hosting hypogene mineralization in and about the Santa Cruz deposit are comprised of 82% Precambrian Oracle Granite, 15% Laramide porphyry dykes, and 3% Precambrian Diabase dykes and other rock types. Historic operators report a NE striking fault interpreted to cut-off mineralization to the SE. However, the evidence is equivocal, and the complicated paleotopographic and structural configuration are not altogether understood. Early sub-horizontal D1 faults that offset mineralization are recognized but do not appear to completely close it off, but rather place relatively weaker mineralization (i.e., higher pyrite to chalcopyrite ratio mineralization) in structural contact with more robust mineralization (chalcopyrite greater than pyrite).

 

Primary hypogene sulphide mineralization consists of chalcopyrite, pyrite, molybdenite, and minor bornite and covellite hosted within sulphide and quartz-sulphide stringers, veinlets, veins, vein breccias, and breccias as well as fine to coarse disseminations within vein envelopes (dominantly replacing mafic minerals biotite and hornblende) associated with hydrothermal porphyry-style mineralization and alteration related to Laramide-aged quartz-biotite-feldspar-phyric dykes (65 Ma to 64 Ma from K-Ar; Balla, 1972).

 

Minor gold (Au) and silver (Ag) were noted in historic flotation concentrates from the Casa Grande West deposit (Santa Cruz South; Watts et al., 1982). In general, Au, and Ag values range from 0.03 g/t to 0.3 g/t, with a single notable outlier from historic hole CG-031 that intersected 3.05 m of 307.9 g/t Au at 740.67 m depth in Oracle Granite. Where Au occurs as native flakes associated with quartz, orthoclase, analcime, clay, hematite, and mica. Trace amounts of Ag occur in solid solution within chalcocite and as an Ag selenide (estimated 60% Ag, 40% selenium) associated with chalcocite as evidenced by x-ray diffraction pattern analyses from historic reports.

 

Historic operators report several local centres of alteration-mineralization that exhibit distinct mineralogical and textural zonation. ASARCO outline two discrete centres of mineralization near historic drill holes SC-004 and SC-019 at their Santa Cruz North deposit. These centres of mineralization were present with inner chalcopyrite-molybdenite mineralization associated with orthoclase-biotite-sericite alteration assemblages that grade outward into pyrite-chalcopyrite mineralization associated with sericite-quartz alteration assemblages. Historic operators Hanna-Getty reported pyrite-chalcopyrite ratios that drop from 5:1, down to 3:1, with discrete domains of 1:1 near the centre of the historic Casa Grande West (Santa Cruz South) deposit. This coincides with the area with the most bornite noted in historic logs (centred on historic drill hole CG-027) and likely reflects an additional discrete locus for mineralization apart from the two centres identified and described by ASARCO nearly 2 km to the north.

 

Three diatremes are recognized on the property (Vikre et al., 2014; Figure 6-6), which consist of intrusive heterolithic breccias, eruptive deposits, including tephras (tuff rungs), and tuffaceous sediments (maar-fill deposits). All border and fill diatreme vents, respectively, and lie on the mid-Tertiary erosional surface of Middle Proterozoic granite and Laramide porphyry. Some igneous xenoliths in the pipes contain bornite-chalcopyrite-covellite assemblages with hypogene grades indicating the phreatomagmatic event has partially dissected and sampled mineralization at depth that has not been intersected in drilling to date. The phreatomagmatic diatreme events are interpreted to be related to Tertiary igneous activity recognized outside of the project area to the south and west that consist of andesitic, latitic, and basaltic flows that are often tilted and faulted where exposed.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
52Nordmin Engineering Ltd.

 

 

 

6.4.2Supergene Mineralization at the Santa Cruz Deposit

 

Prior to the burial of the Santa Cruz deposit by post-mineral cover, hypogene sulphide mineralization near the paleo ground surface was subjected to multiple cycles of oxidation and enrichment. This resulted in the locally abundant atacamite, chrysocolla, and chalcocite mineralization that form a supergene zone with complex geometries that is up to 600 m thick in vertical drill holes (Figure 6-4). Drilling to date has delineated a thick domain of supergene Cu mineralization (averaging approximately 200 m in thickness) contiguous over an area approximately 2,000 m (NNW-SSE) by 800 m (SW-NE) within the Santa Cruz deposit area. Supergene mineralization is generally subdivided into supergene sulphide (chalcocite) and Cu-oxide mineralization, with relatively minor quantities of exotic Cu mineralization. The exotic Cu mineralization is dominantly hosted in the overlying clastic and volcanic rocks at the Santa Cruz deposit. Supergene mineralization at the Santa Cruz Project reflects a mature, long lived supergene system (chalcocite replacing pyrite) with a well-developed supergene stratigraphy consisting of distinctly zoned mineralization with chrysocolla overlying chrysocolla-atacamite, overlying atacamite, overlying chalcocite. There is also abundant evidence for post rotational development of multiple supergene enrichment horizons as illustrated in historic Figure 6-4 that shows two or more distinct supergene sulphide (chalcocite) and oxide horizons exhibiting oblique configurations, with one set dipping shallowly to the southwest (interpreted as a younger overprint) and a second set dipping more steeply to the northeast. K-Ar age dating by Cook (1994) on supergene alunite returned an age of approximately 41 Ma. During the Tertiary (likely no later than 15 Ma), the rapid burial of the Santa Cruz deposit led to the cessation of supergene enrichment processes and subsequently interred the deposit(s) under 200 m to 900 m of post-mineral cover comprising the valley fill conglomerate units.

 

6.4.3Hypogene Mineralization at the Texaco Deposit

 

At Texaco deposit, hypogene mineralization has been intersected in drilling within a 2 km by 1 km zone prevalent between 400 m and 110 m depth; however, the hypogene system has not been systematically tested and remains open in all directions. Hypogene mineral assemblages consist of chalcopyrite, pyrite, and molybdenite hosted within sulphide and quartz-sulphide stringers, veinlets, veins, vein breccias, and breccias, as well as fine to coarse disseminations within vein envelopes (dominantly replacing mafic minerals biotite and hornblende). Hypogene mineralization is related to Laramide-aged quartz-biotite-feldspar-phyric dykes (65 Ma to 64 Ma from K-Ar; Balla, 1972). At the Texaco deposit, these sulphide minerals have been historically interpreted to exhibit a distinct zoning pattern, with a core zone of chalcopyrite-molybdenite, a chalcopyrite zone, and a pyrite zone (Figure 6-8 and Figure 6-9). The core and chalcopyrite zone host rocks are altered by biotite-orthoclase-sericite. Host rocks in the outer chalcopyrite zone and pyrite zone are altered by quartz-sericite (Kreis, 1978).

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
53Nordmin Engineering Ltd.

 

 

 

Figure 6-8: Plan map of simplified mineralization and alteration zonation at the Texaco deposit (Kreis, 1978)

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
54Nordmin Engineering Ltd.

 

 

 

Figure 6-9: Historic cross-section of mineralization and alteration zonation at the Texaco deposit (Kreis, 1978)

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
55Nordmin Engineering Ltd.

 

 

6.4.4Supergene Mineralization at the Texaco Deposit

 

Drilling by ASARCO at Texaco deposit delineated an approximately 100 m thick horizon of supergene Cu mineralization developed over 2000 m (NE-SW) by 1,000 m that remains open in all directions. The supergene mineralization at Texaco consists of a similar geochemical stratigraphy to that observed at the Santa Cruz deposit. The supergene mineralization contains a well-developed leached cap up to 300 m thick with abundant limonite consisting of hematite>goethite and minor jarosite. The limonite overlies a chalcocite enrichment blanket approximately 100 m thick, displaying evidence of minor oxidation at the contact in the form of chalcocite partially replaced by hematite-goethite. However, supergene mineralization at Texaco contains much less Cu-oxide and Cu-chloride mineralization compared to the Santa Cruz deposit. Brochantite was also noted as the dominant Cu-oxide phase in historic hole SC-23, where it is replacing chalcocite (Kreis, 1978). Chalcocite mineralization was historically interpreted by previous operators as having been developed in an originally thick sub-horizontal blanket and subsequently thinned due to faulting and extension (Figure 6-4). Observations of chalcocite mineralization with increased grades at the upper contact with the leached cap and a gradational decrease in mineralization with depth support an alternate hypothesis that the chalcocite blanket has not been rotated and offset to the degree that Figure 6-4 represents.

 

6.5Alteration

 

Alteration at the Santa Cruz deposit is dominated by 1) hypogene alteration assemblages related to Laramide age hydrothermal activity consisting predominantly of quartz, sericite, orthoclase (potassium feldspar), biotite, chlorite, and undivided clay group minerals with rare subordinate phases epidote, albite, tremolite, and kaolinite; and 2) supergene alteration relating to the weathering and oxidation of primary hypogene sulphides in the late cretaceous through to Tertiary time with clay and sericite alteration of primary and secondary biotite with minor sericitization, clay (kaolinite, montmorillonite and rare alunite) and rare analcime alteration of relict plagioclase, though hypogene replacement of plagioclase by sericite and orthoclase reduce the potential reactivity of relict feldspars.

 

6.5.1Hypogene Alteration at the Santa Cruz Deposit

 

The spatial distribution of alteration assemblages at the Santa Cruz deposit is complicated by post emplacement faulting and rotation. However, historic operators report several local centres of alteration-mineralization that exhibit distinct mineralogical and textural zonation. ASARCO identified two discrete centres of mineralization around SC-004 and SC-019, a chalcopyrite-molybdenite mineralization centre associated with orthoclase-biotite-sericite alteration assemblages that grade outward into pyrite-chalcopyrite mineralization associated with sericite-quartz alteration assemblages. Historic operator Hanna-Getty reports pyrite-chalcopyrite ratios that drop from 5:1, down to 3:1, with discrete domains of 1:1 near the centre of the historic Casa Grande West deposit. This coincides with the area of greatest bornite abundance noted in historic logs (centred on historic drill hole CG-027) and likely reflects an additional discrete locus for mineralization apart from the two centres identified by ASARCO nearly 2 km to the north. Observations from ongoing drill operations have identified the presence of pale-green sericite (PGS) in close association with hypogene sulphide-bearing vein selvedges and envelopes and are interpreted to be analogous to similar PGS-Sulphide vein relationships observed and reported at the Butte deposit, Montana.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
56Nordmin Engineering Ltd.

 

 

6.5.2Supergene Alteration at the Santa Cruz Deposit

 

Historic operators reported an absence of alunite-supergene silica, and dominant kaolinite that they interpreted as indicating a leached capping environment with modest oxidizing potential within a relatively low sulphide system. However, ongoing analyses utilizing a TerraSpec Halo handheld spectrometer have identified both supergene alunite as well as likely silica in the leached capping environment, potentially indicating a relatively robust oxidizing potential with low pH fluid generation. This is further supported by the presence of near complete chalcocite replacement of pyrite, which directly indicates cupric ion strength and reflects a longstanding supergene process (Chávez, 2021). Limonites, dominantly present as exogenous hematite>goethite>jarosite, are indigenous and proximally transported and occur with abundant hematite staining of feldspars and as thick accumulations on fractures. Hematite in the leached capping environment is also noted to occur as hematite after chalcocite pseudomorphing pyrite in cellular boxworks that exhibit a deep maroon colour referred to as “Live hematite,” in addition to botryoidal hematite observed in cavities. Locally, limonitic mixtures of hematite-goethite, and hematite-jarosite form as casts of subsequently leached mineral phases such as pyrite. Montmorillonite is present in the supergene environment replacing feldspars and has been noted to be Cu-bearing within the chrysocolla zone.

 

6.5.3Hypogene Alteration at the Texaco Deposit

 

Texaco deposit, as noted by ASARCO-Freeport in their 1978 internal report, illustrates distinct zonation in the drilling at their Santa Cruz North deposit that consisted of 1) a core zone with modest Cu contents, increased local molybdenite grades and strongly developed orthoclase alteration 2) Chalcopyrite zone with host rocks that are altered dominated by biotite-orthoclase-sericite assemblages; and 3) Outer chalcopyrite and pyrite zone that is dominated by quartz-sericite (Figure 7-9).

 

6.5.4Supergene Alteration at the Texaco Deposit

 

Supergene alteration within the Texaco deposit is similar to the Santa Cruz deposit. Limonites are dominantly present as hematite>goethite>jarosite and occur with abundant hematite staining of feldspars and their alteration products, as well as thick accumulations on fractures. Hematite in the leached capping environment is also noted to occur as hematite after chalcocite. This hematite is a pseudomorph of pyrite and forms in cellular boxworks that exhibit a deep maroon colour referred to as “Live hematite.” Botryoidal hematite is also observed in cavities. Locally, limonitic mixtures of hematite-goethite, and hematite-jarosite form as casts of subsequently leached mineral phases such as pyrite.

 

6.6Structural Geology

 

The Santa Cruz Project lies within the Basin and Range province, within a domain that has experienced some of the greatest degrees of extensional tectonism (Figure 6-2). The Santa Cruz system (including Santa Cruz, Sacaton, Texaco, and Parks-Salyer areas) represents portions of one or more large porphyry Cu systems that have been dismembered and displaced during Tertiary extensional faulting. As such, faulting at the Santa Cruz Project is intimately associated with mineralization and the current deposit configuration in several ways.

 

Firstly, major deep-seated NE-SW striking basement structures that run from Colorado to Mexico (i.e., The Jemez lineament) likely controlled or constrained Laramide age intrusive emplacement and metal endowment during transpressional arc magmatism. These structures have likely been reactivated multiple times, potentially serving as transfer faults for dextral offset during Basin and Range extension. Secondly, post-mineral faulting is recognized at Santa Cruz Project, and it is evident that at least three different generations of approximately NW-SE striking normal faulting have developed during Basin and Range extension, resulting in significant rotation and offset of fault blocks with the earliest (D1) generation of faults exhibiting a sub-horizontal configuration at present. This “deck of cards” rotation and offset of faults and fault blocks during Basin and Range extension is well documented in Arizona, for example, the Yerington, Ann Mason and MacArthur deposits of Nevada (Dilles et al., 2000). These structures exhibit a principal control on the present configuration of the Santa Cruz Project.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
57Nordmin Engineering Ltd.

 

 

Additionally, it is evident within the Santa Cruz deposit that post emplacement faulting has controlled and affected groundwater dynamics and the subsequent mobilization and deposition of Cu in supergene enrichment processes, as well as late intermediate argillic alteration and low temperature groundwater alteration and oxidative processes. These faults also played a key role in shaping the paleotopographic landscape prior to burial under the Valley conglomerate sequence, and the paleotopography will have had a controlling influence on the development and distribution of exotic Cu mineralization in paleodrainages that are recognized at the Santa Cruz deposit.

 

The Santa Cruz deposit is interpreted to be down-faulted to the west along the NW-trending, W-dipping Grande Fault, and may be offset by other faults. Post-mineralization faults have been found to displace overlying volcanic rocks and conglomerate. Heterolithic, igneous- and clastic-matrix breccias in the Middle Proterozoic and Late Cretaceous igneous bedrock and associated tuffaceous deposits are located along the contact of bedrock and basin fill deposits. The breccias and basin fill deposits, which consist of at least three diatremes, contain xenoliths, and xenocrysts from a variety of surrounding Precambrian and Late Cretaceous igneous, metamorphic, and sedimentary rocks (Vikre, 2014).

 

6.7Deposit Types

 

The Santa Cruz deposit is a portion of one or more large porphyry Cu systems that have been dismembered and displaced by tertiary extensional faulting. Porphyry Cu deposits form in areas of shallow magmatism within subduction-related tectonic environments (Sillitoe, 2010). The Santa Cruz system has typical characteristics of a porphyry Cu deposit defined by Berger et al. (2008) as follows (Figure 6-10):

 

·One wherein Cu-bearing sulphides are localized in a network of fracture-controlled stockwork veinlets and as disseminated grains in the adjacent altered rock matrix.

·Alteration and mineralization at 1 km to 4 km depth are genetically related to magma reservoirs emplaced into the shallow crust (6 km to over 8 km), predominantly intermediate to silicic in composition, in magmatic arcs above subduction zones.

·Intrusive rock complexes associated with porphyry Cu mineralization and alteration are predominantly in the form of upright-vertical cylindrical stocks and/or complexes of dykes.

·Zones of phyllic-argillic and marginal propylitic alteration overlap or surround a potassic alteration assemblage.

·Cu may also be introduced during overprinting phyllic-argillic alteration events.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
58Nordmin Engineering Ltd.

 

 

 

Figure 6-10: Simplified alteration and mineralization zonation model of a porphyry Cu deposit, after Lowell and Guilbert, 1970.

 

Hypogene (or primary) mineralization occurs as disseminations and in stockworks of veins, in hydrothermally altered, shallow intrusive complexes and their adjacent country rocks (Berger, Ayuso, Wynn, & Seal, 2008). Sulphides of the hypogene zone are dominantly chalcopyrite and pyrite, with minor bornite. The hydrothermal alteration zones and vein paragenesis of porphyry Cu deposits are well known and provide an excellent tool for advancing exploration. Schematic cross sections of the typical alteration zonation and associated minerals are presented in Figure 6-10, which were originally presented by Lowell and Guilbert (1970).

 

Supergene enrichment processes are a common feature of many porphyry Cu systems located in certain physiogeographical regions (semi-arid) that can result in upgrading of LG porphyry Cu primary sulphide mineralization into economically significant accumulations of supergene Cu species (Cu oxides, halides, carbonates, etc.), this is particularly important in the southwestern United States. Supergene enrichment occurs when uplift of a porphyry system to shallow depths exposes the system to surface oxidation processes leading to Cu being leached from the hypogene mineralization during weathering of sulphides (dominantly pyrite, which generates significant sulphuric acid in oxidizing conditions) and redeposits Cu below the water table as supergene Cu sulphides such as chalcocite and covellite. Above the water table, Cu-oxide minerals typically form (Figure 6-11). Figure 6-11 illustrates a schematic section through a secondary enriched porphyry Cu deposit, identifying the main mineral zones formed as an overprint from weathering of the hypogene system.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
59Nordmin Engineering Ltd.

 

 

 

Figure 6-11: Schematic representation of an exotic Cu deposit and its relative position to an exposed porphyry Cu system (Fernandez-Mote et al., 2018; modified after Münchmeyer 1996; Sillitoe 2005).

 

The Santa Cruz Project has a history of oxidation and leaching that resulted in the formation of enriched chalcocite horizons, and later stages of oxidation and leaching, which modified the supergene Cu mineralization by oxidizing portions of it in place and mobilizing some of the chalcocite to a greater depth (Figure 6-12). This process is associated with descending water tables and or erosion and uplift of the system, or changes in climate, or hydrogeological systematics.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
60Nordmin Engineering Ltd.

 

 

 

Figure 6-12: Typical Cu porphyry cross-section displaying hypogene and supergene mineralization processes and associated minerals (modified from Asmus, B., [2013])

 

These processes are also known to be associated with the generation of exotic Cu deposits. Exotic Cu mineralization is a complex hydrochemical process linking supergene enrichment, lateral Cu transport, and precipitation of Cu-oxide minerals in the drainage network of a porphyry Cu deposit (Mote et al., 2001). Supergene alteration primarily involves vertical solution movement, but percolation often involves a horizontal component whereby Cu-rich acidic solutions migrate laterally within the vadose zone. Depending on Eh and pH conditions, Cu may be transported through paleodrainage systems for distances of up to 8 km from the source to produce continuous Cu mineralization (Münchmeyer, 1998). These processes are incredibly complex and defining controls of mineralization can make targeting these deposits challenging.

 

6.8Nordmin QP Opinion

 

The Nordmin QP is of the opinion that the structure, geology, and mineralization of the Santa Cruz Project is well understood and document by several authors over multiple decades.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
61Nordmin Engineering Ltd.

 

 

7EXPLORATION

 

7.1IVNE Geophysical Exploration

 

Earthfield Technology (Earthfield) specializes in depth to basement and basin architecture analyses through application of proprietary geophysical data processing technologies. Earthfield was contracted by IVNE in 2021 to evaluate historic and publicly available topographic, magnetic and gravity datasets (Figure 7-1) to delineate depth to basement, structural lineaments and domains of potential Laramide intrusive bodies and associated alteration in the Casa Grande Basin and surrounding area. Products delivered to IVNE included the reduction to the magnetic pole (RTP), RTP first vertical derivative (RTP_1VD), RTP 5 km high pass filtered (RTP_HP5), RTP 2 km high pass filtered (RTP_HP2), total magnetic intensity (TMI), Bouguer Gravity, Bouguer Gravity 20 km high pass filtered, Bouguer Gravity 10 km high pass filtered, Bouguer Gravity 5 km high pass filtered, Lineaments, Basement depth, Basement Contours (50 m) and postulated Laramide intrusive and associated alteration zones. Results and products from Earthfield analyses have been compiled and integrated into ongoing 3D modelling efforts and will be used to constrain exploration targeting and refine the geological understanding of the Santa Cruz Project area, and inform subsequent geophysical investigations.

 

 

Figure 7-1: Gravity data stations (left) and Arizona State aeromagnetic data (Earthfield report to IVNE, 2021)

 

In November 2021, IVNE commenced a passive seismic survey, which is designed to provide 2D profiles of the basement surface in the area overlying and surrounding the Santa Cruz Project deposits (Figure 7-2). Delineating this surface will validate regional basement modelling by Earthfield and aid future exploration programs. The survey consists of five lines with stations spaced 100 m apart, three oriented in a NE/SW orientation and two in a SW/NW orientation. The survey covers an area of 27 square kilometres with 29 line kilometres and 295 individual stations. Depth profiles from the individual stations will be stitched together to create 2D line profiles across the survey area.

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
62Nordmin Engineering Ltd.

 

 

  

 

  

Figure 7-2: Proposed passive seismic survey configuration and stations showing historic mineral inventories, IVNE surface access agreements, and historic drilling

Technical Report Summary – December 8, 202263

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

The survey is being carried out using Tromino Passive seismic instruments, which use natural sources as the signals and measure vertical and horizontal movement in three corresponding axis (x,y,z).

 

TROMINO® is a small all-in-one instrument, equipped with:

 

  · Three velocimetric channels

 

  · Three accelerometric channels

 

  · One analog channel

 

  · GPS receiver

 

  · built-in radio transmitter/receiver (for synchronization among different units)

 

  · radio triggering system (for MASW surveys and similar)

 

  · TROMINO® works in the [0.1, 1024] Hz range

 

Additionally, IVNE mobilized their proprietary TyphoonTM IP-EM transmitter technology in December 2021 to conduct trial tests including 3DIP, Mise a la Masse, DHEM and DHIP methods to inform future geophysical survey designs.

 

7.2 Historic Geophysical Exploration

 

IVNE is also in possession of historic documents that detail historic geophysical exploration efforts and results over the Santa Cruz – Sacaton system (Table 7-1). To date, none of the original data has been located, but historic interpretations, and results remain valuable.

Technical Report Summary – December 8, 202264

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

Table 7-1: Summary of Historic Exploration on the Santa Cruz Project and Surrounding Area

 

Year Activities Company(s) Prospect/
Deposit
Description Notes
1961 Prospecting and discovery ASARCO Sacaton ASARCO geologists Kinnison and Blucher identify Sacaton Discovery Outcrop, consisting of weak Cu-oxide mineralization on what will eventually be the margin of the Sacaton pit. Based on Asarco's recognition that porphyry Cu deposits often have little or no associated Cu staining and on information from surrounding porphyry Cu deposits, Asarco's geologists were looking for other prospects in the area by driving and walking around. There was a faint trace of Cu-stain but not enough to have attracted previous exploration or prospecting. The outcrop was granite with a thin dyke of porphyry – both altered to quartz-sericite-clay with weak but pervasive jarosite-goethite and a few specks of hematite after chalcocite, particularly in the dyke. The outcrop was expected to have originally contained about 2% sulphides as pyrite/chalcocite/chalcopyrite.
1961 Geophysical Surveying ASARCO Sacaton ASARCO Geophysical Dept. report. Geophysical survey results were used to improve the interpretations of bedrock depth in the Sacaton area.
1967 Ground IP geophysics ASARCO   1967 Internal report indicates eight holes were drilled over a large 13.2 mv/v IP anomaly around 15 miles SW of Sacaton. None of the drill holes intersected primary sulphides, and the chargeability response was interpreted to have been caused by water-saturated clays in the overlying conglomerate.
1988-1991 Borehole Geophysics

SCJV

Santa Cruz Downhole geophysical data was collected during the in situ leach test program. During the SCJV In Situ leach tests (approximately 1988-1991), an undisclosed number of holes were subjected to downhole/borehole geophysical surveying that implemented the collection of caliper, density, resistivity, gamma-ray spectrometer, neutron activation spectrometry, dipmeter, sonic waveform, IP, and magnetic susceptibility data collection methods.
1988 In situ Cu Mining Research Project USBR, SCJV (ASARCO Santa Cruz Inc., and Freeport McMoRan Copper & Gold Inc.) Santa Cruz Santa Cruz selected over other deposits for research site; Field testing begins. The Santa Cruz deposit was 1,250 ft to 3,200 ft below the surface and contains 1.0 billion tons of potentially leachable grading 0.55% total Cu. The joint venture owns 7,000 surface acres, with the Cu mineralization under approximately 250 acres.

Technical Report Summary – December 8, 202265

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

Historic ASARCO documents detail multiple IP surveys over the Sacaton and Santa Cruz Deposits, as well as the historic Santa Rosa Prospect (located southwest of Santa Cruz deposit along the same trend as Sacaton). Historic IP survey reports indicate that extraneous responses in IP surveys at Sacaton and Santa Cruz resulted from groundwater present in the valley fill conglomerates (i.e., W.G. Farley “ASARCO, 1967, Induced Polarization Pinal County” report documents IP response correlating with the water table at Santa Cruz and Sacaton, within the overlying gravels, and well above the basement contact). In 1991, the ASARCO-Hanna-Getty-Bureau of Mines joint venture contracted Zonge Geophysical to implement Controlled Source Audio-frequency Magnetotelluric (CSAMT) tests evaluating the potential to use the application to non-invasively monitor in situ leachate plume activity during in situ leach tests. Results from phase one and two testing from May 1990 through June 1991 were considered promising for tracking leachate detectability with salt doping/tracing. Historic airborne and ground magnetic interpretations are also available, though arguably of lesser value than modern magnetic datasets available (Figure 7-3).

 

 

 

Figure 7-3: ASARCO map illustrating interpreted ground and aeromagnetic data detailed in historic report “Recommended Drilling Santa Cruz Project,” M.A.970 Pinal County, Arizona, August 21, 1964, by W.E. Saegart

Technical Report Summary – December 8, 202266

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

7.3 Historical Data Compilation

 

IVNE has obtained the geological information in the form of historical maps, sections, drill reports, drill logs and assay result reports. As a significant component of the exploration program the historical drill logs were interpreted and used to create a 3D (Leapfrog Geo™) geologic model of the Santa Cruz Project. Three-dimensional geological interpretations were derived from historical drill logs and 2D sections containing geologic interpretations. The drill core data was compiled by IVNE geologists.

  

The drilling within the Project area can be separated into CG and SC drilling, which were completed by different companies (Hanna Getty and ASARCO, respectively). The CG region was comprised of 122 holes from CG-001 to CG-122 with a total of 103,407 m drilled. A plan view map of collar locations can be viewed in Figure 7-4 and a summary is provided in Table 7-2. Twenty-nine original drill cross-sections from 1978 to 1980 covering 92 holes were digitized. Information collected included elevation, total and rotary depths, basic lithology, assays from the three most predominant Cu minerals (total Cu, acid soluble Cu and molybdenum), and survey depth. The archived data was originally logged using a series of numerical codes documented in the Casa Grande Copper Company Ore Reserves Study for the Hanna Mining Company (Watts Griffis McOuat, 1982).

 

 

 

Figure 7-4 Plan map of CG drill hole collars as blue dots

 

The SC series of drill holes was comprised of 80 drill holes from SC-001 to SC-078 with a total of 62,754 m drilled. A plan view map of collar locations can be viewed in Figure 7-5 and a summary is provided in Table 7-2. The archived data was originally logged using a series of numerical codes documented in the Casa Grande Copper Company Ore Reserves Study for the Hanna Mining Company (Watts Griffis McOuat, 1982).

Technical Report Summary – December 8, 202167

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

 

 

Figure 7-5 Plan map of SC drill hole collars as red dots

 

Table 7-2 Summary of Available Data by Region

 

  Dataset Region Total
CG SC
Total number of holes 122 80 202
Total metres drilled 103,407 62,754 166,161
% Collar Survey (holes) 100 100 100
% Downhole Survey (m drilled) 62.1 65.9 63.4
% Assay (m drilled) 96.5 34.4 73.0
% Mineralization 44.1 15.9 33.4

Technical Report Summary – December 8, 202168

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

7.4 Drilling

  

7.4.1 Historic Drilling – Santa Cruz Deposit

 

Santa Cruz deposit diamond drilling consists of 102,261 m of core from 117 NQ drill holes completed between 1965 to 1980. The historic diamond drill core is currently unavailable for review. Table 7-3 provides a summary of the drill campaigns by year and operator.

 

Table 7-3: Drilling History Within the Santa Cruz Project Area

 

Year Operator Total Metres
Unknown Casa Grande Copper Company, Hanna-Getty Mining 9,083
ASARCO/Freeport McMoRan Gold Co. JV 744
1965 ASARCO/Freeport McMoRan Gold Co. JV 2,698
1974 2,068
1975 Casa Grande Copper Company, Hanna-Getty Mining 2,348
ASARCO/Freeport McMoRan Gold Co. JV 682
1976 Casa Grande Copper Company, Hanna-Getty Mining 16,633
ASARCO/Freeport McMoRan Gold Co. JV 513
1977 Casa Grande Copper Company, Hanna-Getty Mining 28,147
ASARCO/Freeport McMoRan Gold Co. JV 9,184
1978 Casa Grande Copper Company, Hanna-Getty Mining 22,301
1979 ASARCO/Freeport McMoRan Gold Co. JV 2,468
1980 5,516
2021 IVNE 4,738

 

During the initial site assessment, it was determined that collar coordinates had variable errors. A program was conducted to check the collar locations of a selection from the drill hole database using a professionally licensed surveying company, D2 land surveying. Based on the transformation for these spot-checked drill holes, nearby hole collar locations were adjusted. All historic drilling is conducted at the vertical dip. For the Santa Cruz Project, the drilling has been completed along 100 m spaced section lines with drill holes spaced 90-100 m apart on each section line.

 

Holes are reverse circulation (RC) drilled through Tertiary sediments until the approximate depth of the Oracle Granite is reached by Major Drilling. Drilling is then switched to diamond drilling through the crystalline basement rocks, and again drilling is executed by Major Drilling.

 

7.4.2 Historic Drilling – Texaco Deposit

 

The historic Texaco deposit diamond drilling consists of 23,848 m of core from 27 diamond NQ drill holes completed between 1975 to 1997. The drill holes in this deposit area consist of the SC drill hole series. The historic diamond drill core is currently unavailable for review. Table 7-4 provides a summary of the drill campaigns by year and operator.

Technical Report Summary – December 8, 202169

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

Table 7-4: Drilling History Within the Texaco Exploration Target Area of the Santa Cruz Project

  

Year Operator Total Metres
1975 ASARCO and Freeport McMoRan Gold JV 1,719
1976 ASARCO and Freeport McMoRan Gold JV 5,207
1977 Casa Grande Copper Co., Hanna-Getty Mining 2,883
ASARCO and Freeport McMoRan Gold JV 5,906
1996 ASARCO and Freeport McMoRan Gold JV 5,086
1997 3,043

 

During the initial site assessment, it was determined that collar coordinates had variable errors. A program was conducted to check the collar locations of a selection from the drill hole database using a professionally licensed surveying company, D2 land surveying. Based on the transformation for these spot-checked drill holes nearby hole collar locations were adjusted. All historic drilling is conducted at the vertical dip. For the Texaco deposit, the historic drilling has been completed along 100 m to 200 m spaced section lines with drill holes spaced 200 m apart on each section line. The average drill section and spacing in the Texaco deposit is approximately 200 m and varies between approximately 90 m and 250 m.

 

7.4.3 2021 Drilling – IVNE

 

The company completed four diamond drill holes totalling 3,601 m within the Santa Cruz deposit at the time of this Technical Report (Table 7-5). The four diamond drill holes were twins of the historical drill holes. All drilling was a mix of rotary and diamond drilling where the first 300 m to 500 m of drilling was rotary to get past the barren tertiary sediments. All samples from within the interpreted mineralized zone were assayed for total Cu (%), acid soluble Cu (%), cyanide soluble Cu (%), and molybdenum (ppm). The collar locations, downhole surveys, logging (lithology, alteration, and mineralization), sampling and assaying between the two sets of drill holes were used to determine if the historical holes had valid information and would not be introducing a bias within the geological model or Mineral Resource Estimate. The comparison included a QA/QC analysis of the historical drill holes (Section 0). Plans for infill drilling and drilling of angled holes have been made to test the continuity of mineralization and gain more information.

 

Table 7-5 IVNE 2021 Drilling on the Santa Cruz Deposit

 

Year Operator Total Metres
2021 IVNE 3,601

 

A total of four historical holes were reviewed with the following outcomes (Figure 7-6):

 

  · All four historical hole assays aligned with the2021 diamond drilling assays.

 

  · The 2021 diamond drilling assays were of higher resolution due to smaller sample sizes.

 

  · The recent drilling validated the ASARCO cyanide soluble assays.

Technical Report Summary – December 8, 202170

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

 

 

Figure 7-6: Collar locations of the historic diamond drilling (orange) versus recent 2021 IVNE twin drill holes (blue)

 

7.4.3.1 Core Logging

 

Currently, oriented core data is not collected on vertical holes. A televiewer is sent down the completed hole to obtain structural information and to confirm the location of surveys/features. Initially, IVNE was hand-writing the logging data and transferring it into a word document table for daily drill report exports. IVNE now enters information into several tabs within MX Deposits™ while logging, including lithology, alteration, veining, structural zone, structure point, and mineralization. Optional characterizers, including colour and grain size, are available for further identification.

 

The current database has five major rock types, including 47 major lithologies in line with historically logged lithologies, 21 lithological textures, 17 alteration types, and 15 lithological structures. There are 28 unique economic minerals recorded in the current database, including chalcocite, chrysocolla, chalcopyrite, cuprite, molybdenum, and atacamite. X-ray fluorescence (XRF) measurements are taken by IVNE wherever mineralization of interest is present for internal use.

 

7.4.3.2 Surveying

 

During the 2021 drilling campaign, downhole surveying was conducted using a EZ Gyro single shot taken at the collar and every 30 m afterwards as the tool is being pulled from the hole.

 

After hole completion, all drill holes were surveyed using borehole geophysics and video through Southwest Exploration Service, LLC. Each borehole was surveyed for 4RX Sonic-Gamma (sampled every 0.06 m), Acoustic Televiewer (sampled every 0.003 m), E-Logs-Gamma (sampled every 0.06 m), and a Gamma Caliper test for fluid temperature conduction (sampled every 0.06 m). This downhole surveying allowed for the calibration of drill hole information post-drilling to ensure that surveying was correct and lithological and mineralogical contacts were logged properly. It also allowed for the collection of very accurate structural measurements.

Technical Report Summary – December 8, 202171

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

7.4.3.3 Specific Gravity

 

At both the Santa Cruz and Texaco deposits, no SG measurements were taken from historic diamond drill core. 2021 diamond drilling is aimed at twinning HG historic drilling to confirm the logging and assays. The Company collected 266 SG measurements over four diamond drill holes across the Santa Cruz Project (Table 7-6). SG measurements are taken every 3 m or at each new lithology to ensure a well-rounded database of measurements for each rock type. Measurements are taken using a water dispersion method. The samples are weighed in air, and then the uncoated sample is placed in a basket suspended in water and weighed again.

 

Table 7-6: Santa Cruz Project SG Measurements

 

Lithology (LITH_GEN) Average SG
Diabase 2.472
GDPorph 2.589
GranOracle 2.506
Lithology (LITH_SPEC) Average SG
Granite 2.500
Quartz Monzonite 2.529
FINAL AVERAGE SG
GDPorph/Diabase/Quartz Monzonite 2.552
GranOracle/Granite 2.500

 

Due to the overall low SG values, multiple different types of SG measurements were tested, all of which indicated that these values are correct. This result is likely due to the high porosity from leaching and excessive faulting/brecciation throughout the mineralized rock.

 

7.5 Geotechnical Data

 

No geotechnical work programs have been completed on the property to date.

 

7.6 Hydrogeological Data

 

No hydrogeological work programs have been completed on the property to date.

 

7.7 Nordmin QP Opinion

 

In the opinion of the Nordmin QP, the quantity and quality of the lithological, collar, downhole survey, and SG data collected in the historical data compilation and twin hole drilling programs are sufficient to support the Mineral Resource Estimate.

Technical Report Summary – December 8, 202172

Nordmin Engineering Ltd.

Santa Cruz Project, Arizona, USA  
Ivanhoe Electric Inc.  

 

   

 

 

 

Core logging completed by IVNE and previous operators meet industry standards for exploration on replacement and porphyry deposits:

 

·Collar surveys and downhole surveys were performed using industry-standard instrumentation,

 

·Drill hole orientations are appropriate for the mineralized style, and

 

·Drill hole intercepts demonstrate that sampling is representative.

 

No other factors were identified with the data collected from the drill programs that could significantly affect the Mineral Resource Estimate.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
73Nordmin Engineering Ltd.

 

 

8SAMPLE PREPARATION, ANALYSES AND SECURITY

 

8.1Assay Sample Preparation and Analysis

 

Historic drill core was analyzed at Skyline Laboratories in Tucson, Arizona. Assays were taken using acid dissolution of the sample followed by atomic-absorption spectroscopy (AAS).

 

From September to December 2021, IVNE samples were sent to either Skyline Laboratories facility located in Tucson, Arizona, or American Assay Laboratories located in Sparks, Nevada. At the time, both assay labs were well established and recognized assay and geochemical analytical services companies and were independent of IVNE.

 

Both laboratories are recognized by the International Standard demonstrating technical competence for a defined scope and the operation of a laboratory quality management system (ISO 17025). Additionally, Skyline Laboratories is recognized by ISO 9001, indicating that the quality management system conforms to the requirements of the international standard. American Assay Laboratories carries approval from the State of Nevada Department of Conservation and Natural Resources Division of Environmental Protection.

 

8.1.1IVNE Core Sample Preparation and Analysis – 2021

 

The diamond drill core from the Santa Cruz and Texaco properties was sampled by IVNE in 2021 under the direct supervision of Eric Castleberry, US Operations Manager and Santa Cruz Geology Manager Christopher Seligman, MAusIMM CP(Geo). Samples were cut lengthwise using an NTT brand diamond bladed saw; one half was placed in a plastic sample back which was then placed in a burlap sample bag labelled with the sample number, and the other half placed back in the box for catalogue and storage (Figure 8-1, Figure 8-2). Sample bags were then placed in large plastic bags in batches of 25, and were placed in large fold-out plastic bins for transport to the lab facility (Figure 11-3).

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
74Nordmin Engineering Ltd.

 

 

 

Figure 8-1: NTT diamond bladed automatic core saw used for cutting diamond drill core for sampling

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
75Nordmin Engineering Ltd.

 

 

 

 

Figure 8-2: Core storage at IVNE offices/core shack

 

 

 

Figure 8-3: (Left) samples placed in burlap and inner plastic bags labelled with sample numbers; (Right) sample batches placed in large plastic bags and bins for shipping to lab

 

8.1.1.1Skyline Laboratories

 

Half of the total drill core samples taken during the 2021 diamond drilling program were sampled and prepared at Skyline Laboratories, Tucson, Arizona. The samples were crushed from the split core to prepare a total sample of up to 5 kg at 75% passing ten microns (µm). Samples were then riffle split, and a 250 g sample was pulverized with a standard steel to plus 95% passing at 150 µm. After sample pulp preparation, the samples were analyzed in the following manner:

 

·All samples were analyzed for total Cu using multi-acid digestions with an AAS finish. The lower limit of detection is 0.01% for total Cu, with an upper detection limit of 10%.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
76Nordmin Engineering Ltd.

 

 

·Sequential Analysis for cyanide soluble and acid soluble were conducted via multi-acid leaching with an AAS finish. For sequential acid leaching (SEQ) Cu analyses, the lower limit of detection is 0.005%, with an upper detection limit of 10%.

 

·Molybdenum was prepared using multi-acid digestion and analyzed using inductively coupled plasma optical emission spectrometry (ICP-OES). This analysis has a lower detection limit of 0.001%.

 

·Samples greater than 10% Cu, with a 20% threshold, will be again analyzed using a Long Iodine method.

 

8.1.1.2American Assay Laboratories

 

Half of the total drill core samples from the 2021 drill campaign were prepared and analyzed at American Assay Laboratories in Sparks, Nevada. The samples were crushed from the split core to prepare a total sample of up to 5 kg at 75% passing 10 µm. Samples were then riffle split and pulverized with a standard steel to plus 95% passing at 150 µm. After sample pulp preparation, the samples were analyzed in the following manner:

 

·All samples were analyzed for total Cu using AAS, molybdenum with an ICP-MS and acid soluble and cyanide soluble Cu with sequential leaching (AAS). A measurement for residual Cu was also taken; this is essentially the Cu that is measured that cannot be attributed to cyanide soluble, acid soluble, or total Cu. The lower detection limit is 0.001%, with an upper limit of 10%. Samples greater than or equal to 10% will be alternatively measured using Long Iodine analysis, which has an upper detection limit of 20%.

 

·The detection limit at American Assay Laboratories is an order of magnitude less than at Skyline Laboratories; therefore, there is a lower resolution, but during a comparison between the two labs, it was found that the results were similar.

 

·Due to QA/QC failures at American Assay Laboratories, IVNE will not continue to use this lab after pre-paid analyses are completed.

 

8.1.2Historic Core Assay Sample and Analysis

 

Historically, samples for both the Texaco and Santa Cruz deposit drilling were sent to Skyline Laboratories to be assayed for standard total Cu and non-sulphide Cu methods. Samples were crushed and split; a 250-500 mg sample was then prepared in the following ways:

 

·Total Cu analysis samples were dissolved using a mixture of HCl, HNO3, and HClO4 over low heat. The mixture was then measured using AAS.

 

·Non-sulphide Cu was dissolved using a mixture of H2SO4 and H2SO3 over moderate to high heat. This mixture was then filtered, diluted, and measured using AAS.

 

8.2Specific Gravity Sampling

 

A total of 266 SG measurements for the Santa Cruz deposit were provided during 2021 on site drill core measurements. SG measurements were taken from representative core sample intervals (approximately 0.1 m to 0.2 m long). SG was measured using a water dispersion method. The samples were weighed in air, and then the uncoated sample was placed in a basket suspended in water and weighed again. SG is calculated by using the weight in air versus the weight in water method (Archimedes), by applying the following formula:

 

 

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
77Nordmin Engineering Ltd.

 

 

8.3Quality Assurance/Quality Control Programs

 

QC measures were set in place to ensure the reliability and trustworthiness of exploration data. These measures include written field procedures and independent verifications of aspects such as drilling, surveying, sampling, assaying, data management, and database integrity. Appropriate documentation of QC measures and regular analysis of QC data is essential as a safeguard for Project data and form the basis for the QA program implemented during exploration.

 

Analytical QC measures involve internal and external laboratory procedures implemented to monitor the precision and accuracy of the sample preparation and assay data. These measures are also important to identify potential sample sequencing errors and to monitor for contamination of samples.

 

The Company submitted a blank, standard, or duplicate sample on every seventh sample. Sampling and analytical QA/QC protocols typically involve taking duplicate samples and inserting QC samples (certified reference material [CRM] and blanks) to monitor the assay results' reliability throughout the drill program.

 

8.3.1Standards

 

During the 2021 drilling campaign, IVNE submitted six different CRMs as a part of their QA/QC protocol, with 16 submitted in total. The review of the CRM results identified no laboratory failures at Skyline Laboratories and seven failures at American Assay Laboratories. OREAS 908 falls within the range of +/- two standard deviations for Cu Total (%) and acid soluble Cu (%) (Table 8-1 and Table 8-2; Figure 8-4 to Figure 8-9). Skyline Laboratories submitted seven different CRMs, including two inhouse CRMs, as a part of their QA/QC process (Table 8-3), and American Assay Laboratories submitted three different CRMs as a part of their QA/QC process (Table 8-4).

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
78Nordmin Engineering Ltd.

 

 

Table 8-1: CRMs Inserted by IVNE into Sample Batches Sent to Skyline Laboratories

 

Standard Count Best
Value
Cu (%)
Mean
Value
Cu (%)
Bias
(%)
Best
Value
Cu-AS-
SEQ (%)
Mean
Value
Cu-AS-
SEQ (%)
Bias
(%)
Best
Value
CuCN-
SEQ (%)
Mean
Value
CuCN-
SEQ (%)
Bias
(%)
Oreas 908 9 1.26 1.256 0.004 1.078 1.067 0.011 0.022 0.024 0.002
Oreas 907 6 0.6 0.652 0.052 0.531 0.54 0.009 0.018 0.015 0.003
Oreas 906 4 0.31 0.31 0 0.269 1.126 -0.86 0.01 0.019- -0.009
Oreas 501 d 6 0.27 0.27 0 - - - - - -
Oreas 503 d 4 0.53 0.524 0.006 - - - - - -
Oreas 504c 1 1.13 1.09 0.04 - - - - - -

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
79Nordmin Engineering Ltd.

 

 

Table 8-2: CRMs Inserted by IVNE into Sample Batches Sent to American Assay Laboratories

 

Standard Count Best
Value
Cu
(%)
Mean
Value
Cu (%)
Bias
(%)
Best
Value CuAS-
SEQ
(%)
Mean
Value
CuAS-
SEQ
(%)
Bias
(%)
Best
Value
CuCN-
SEQ
(%)
Mean
Value
CuCN-
SEQ
(%)
Bias
(%)
Oreas 908 10 1.26 1.299 0.039 1.078 1.067 0.64 0.022 0.023 0.001
Oreas 907 5 0.6 0.643 0.043 0.531 0.54 1.31 0.018 0.009 0.009
Oreas 906 2 0.31 0.33 0.02 - - - - - -
Oreas 503c 1 0.27 0.545 0.275 - - - - - -
Oreas 504c 3 1.13 1.11 0.02 - - - - - -

 

Table 8-3: Skyline Laboratory Submitted CRMs

 

Standard Count Best
Value
CuT
(%)
Mean Value CuT
(%)
Bias
(%)
Best
Value
Cu-AS-
SEQ
(%)
Mean
Value
Bias
(%)
Best
Value Cu-CN-
SEQ
(%)
Mean
Value
Bias
(%)
SKY5 48 - - - 0.18 0.18 0.00 0.155 0.156 0.00
SKY6 48 - - - 0.42 0.41 0.01 0.076 0.077 0.00
CDN-CM-21 14 0.54 0.54 0.00 - - - - - -
CDN-CM-14 34 1.06 1.07 -0.01 - - - - - -
CDN-CM-29 12 0.74 0.74 0.00 - - - - - -
CDN-CM-33 12 0.35 0.36 -0.01 - - - - - -
CDN-W-4 20 0.14 0.14 0.00 - - - - - -

 

Table 8-4: American Assay Laboratory Submitted CRMs

 

Standard Count Best Value
Cu (%)
Mean
Value Cu
(%)
Bias (%) Best Value
Cu-AS-SEQ
(%)
Mean
Value Cu-
AS-SEQ
(%)
Bias (%)
OREAS 600b 3 0.05 0.051 0.00 - - -
OREAS 602b 3 0.494 0.495 0.00 - - -
OREAS 905 3 0.157 0.158 0.00 0.128 0.127 0.001

 

Technical Report Summary – December 8, 2022
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
80Nordmin Engineering Ltd.

 

 

 

 

Figure 8-4: Santa Cruz deposit, Oreas 908 standard total Cu (g/t), assayed at Skyline Laboratories

 

 

 

Figure 8-5: Santa Cruz deposit, Oreas 908 standard cyanide soluble Cu (g/t), assayed at Skyline Laboratories

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
81Nordmin Engineering Ltd.

 

 

 

 

Figure 8-6: Santa Cruz deposit, Oreas 908 standard cyanide soluble Cu (g/t), assayed at Skyline Laboratories

 

 

 

Figure 8-7: Santa Cruz deposit, Oreas 908 standard total Cu (g/t), assayed at American Assay Laboratories

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
82Nordmin Engineering Ltd.

 

 

 

 

Figure 8-8: Santa Cruz deposit, Oreas 908 standard acid soluble Cu (g/t), assayed at American Assay Laboratories

 

 

Figure 8-9: Santa Cruz deposit, Oreas 908 standard cyanide soluble Cu (g/t), assayed at American Assay Laboratories

 

Technical Report Summary – December 8, 202183Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

8.3.2Blanks

 

The Company submitted 50 coarse blanks during the 2021 drill campaign, at the time of this report, as part of its QA/QC process. The Company used local granite blanks during the 2021 drill campaign as part of its QA/QC process. One blank was used labelled as Blank. The blank has been tested by Skyline Laboratories to ensure that there is no trace of Cu present. The charts not presented in this section are available in Appendix B. No significant carryover of elevated metals is evident in blanks measured at Skyline Laboratories (Figure 8-10). There is a carryover of metals evident in blanks measured at American Assay Laboratories related to dust control issues at this lab (Figure 8-11). The samples from these batches were re-analyzed by the lab, as set out in the QA/QC protocol. Results from these samples were not received in time to be included in the Mineral Resource Estimate.

 

 

Figure 8-10: Blanks submitted by IVNE to Skyline Laboratories as a part of their QA/QC process

 

Technical Report Summary – December 8, 202184Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 8-11: Blanks submitted by IVNE to American Assay Laboratories as a part of their QA/QC process

 

8.3.3Field and Laboratory Duplicates

 

The Company submitted 64 field duplicates during the 2021 drill campaign, at the time of this report, as a part of its QA/QC process. Original versus duplicate sample results for total Cu (%) are present in Figure 8-12 and Figure 8-13. The results of the field duplicates are in good agreement for total Cu (%), acid soluble Cu (%) and cyanide soluble Cu (%). Skyline Laboratories submitted 175 lab duplicates (119 total Cu, 125 Acid Soluble, 125 Cyanide Soluble and 119 Mo) during the 2021 drill campaign as a part of their QA/QC process. The results of the laboratory duplicates versus the original sample measurements for total Cu (%) are presented in Figure 8-14. The results of the laboratory duplicates are in good agreement for total Cu (%), acid soluble Cu (%) and cyanide soluble Cu (%). American Assay Laboratories submitted 21 Lab duplicates (all measured for total Cu, acid soluble Cu, cyanide soluble Cu and molybdenum) during the 2021 drill campaign as a part of their QA/QC process. The results of the laboratory duplicates are in good agreement for total Cu (%), acid soluble Cu (%) and cyanide soluble Cu (%) and molybdenum (ppm). The results of the duplicates versus the original sample measurements for total Cu (%) can be viewed in Figure 8-15.

 

Technical Report Summary – December 8, 202185Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 8-12: Original versus field duplicate sample results as total Cu (%) from samples submitted to Skyline Laboratories

 

Technical Report Summary – December 8, 202186Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 8-13: Original versus field duplicate sample results as total Cu (%) from samples submitted to American Assay Laboratories

 

Technical Report Summary – December 8, 202187Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 8-14: Duplicates completed by Skyline Laboratories as a part of their QA/QC process

 

 

Figure 8-15: Duplicates completed by American Assay Laboratories as a part of their QA/QC process

 

Technical Report Summary – December 8, 202188Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

8.4Security and Storage

 

The Santa Cruz Project core is stored in wax impregnated core boxes and transported to the core logging shack. After being logged, the core boxes are stacked within metal shelving within the core shack/Company office. The building can be locked with bay doors for security purposes. All samples are transported by courier to the laboratory either in Tucson, Arizona, or Sparks, Nevada.

 

8.5Nordmin QP’s Opinion on the Adequacy of Sample Preparation, Security, and Analytical Procedures.

 

Nordmin has been supplied with all raw QA/QC data and has reviewed and completed an independent check of the results for all of the Santa Cruz Project sampling programs. Nordmin has completed a lab inspection of the Skyline Laboratories, and IVNE has completed a lab inspection of American Assay Laboratories. It is Nordmin’s opinion that the sample preparation, security, and analytical procedures used by all parties are consistent with standard industry practices and that the data is suitable for the Mineral Resource Estimate. Nordmin identified further recommendations to IVNE to ensure the continuation of a robust QA/QC program but has noted that there are no material concerns with the geological or analytical procedures used or the quality of the resulting data.

 

Technical Report Summary – December 8, 202189Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

9DATA VERIFICATION

 

Nordmin completed several data validation checks throughout the duration of the Mineral Resource Estimate. The verification process included a two-day site visit to the Santa Cruz Project by Nordmin to review surface geology, drill core geology, geological procedures, QA/QC procedures, chain of custody of drill core and the collection of independent samples for metal verification. The data verification included:

 

·a survey spot check of drill collars;

 

·a spot check comparison of assays from the drill hole database against original assay records (lab certificates);

 

·a spot check of drill core lithologies recorded in the database versus the core located in the core farm;

 

·a spot check of drill core lithologies in the database versus the lithological model;

 

·a review of the QA/QC performance of the drill programs.

 

Nordmin has also completed additional data analysis and validation, as outlined in Section 11.

 

9.1Nordmin Site Visit 2022

 

Nordmin completed a site visit to the Santa Cruz Project from March 2nd to March 6th, 2022. Nordmin was accompanied by IVNE management team members and project geologists. Additionally, Nordmin also visited the site on November 3rd and November 4th, 2021.

 

Activities during the site visits included the:

 

·Review of the geological and geographical setting of the Santa Cruz Project.

 

·Review and inspection of the site geology, mineralization, and structural controls on mineralization.

 

·Review of the drilling, logging, sampling, analytical and QA/QC procedures.

 

·Review of the chain of custody of samples from the field to the assay lab.

 

·Review of the drill logs, drill core, storage facilities, and independent assay verification on selected core samples.

 

·Confirmation of several drill hole collar locations.

 

·Review of the structural measurements recorded within the drill logs and how they are utilized within the 3D structural model.

 

·Validation of a portion of the drill hole database.

 

IVNE geologists completed the geological mapping, core logging, and sampling associated with each drill location. Therefore, Nordmin relied on IVNE’s database to review the core logging procedures, the collection of samples, and the chain of custody associated with the drilling programs. The Company provided Nordmin with digital copies of the logging and assay reports. All drilling data, including collars, logs, and assay results, were provided to Nordmin prior to the site visit.

 

No significant issues were identified during the site visit.

 

The Company employs a rigorous QA/QC protocol, including the routine insertion of field duplicates, blanks, and certified reference standards. Nordmin was provided with an excerpt from the database for review.

 

Technical Report Summary – December 8, 202190Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Currently, structural measurements are not taken during logging and are compiled after televiewer data collection. This allows for the accurate measurement of structures. The Company plans to employ oriented drilling in the future to allow for structural measurements to be taken during logging.

 

The geological data collection procedures and the chain of custody were found to be consistent with industry standards and following IVNE’s internal procedural documentation; and Nordmin was able to verify the quality of geological and sampling information and develop an interpretation of Cu (primary, acid soluble and cyanide soluble) grade distributions appropriate for the Mineral Resource Estimate.

 

9.1.1Field Collar Validation

 

The location of four drill holes within the Santa Cruz deposit were confirmed during the 2022 site visit (Table 9-1 and Figure 9-1. These holes are vertical twins of historic drilling. During the initial property assessment, it was determined that the historic collar locations were incorrect. This finding led to the re-surveying of multiple collars using a sub-metre scale GPS Professional Land surveyor; conducted by D2 surveying – licensed land surveyor for re-surveying of historic drill collars.

 

The QP and IVNE Senior Geologist collected several collar locations during the site visit using a Garmin GPSMAP 64sx handheld GPS unit. The collars taken by Nordmin are very similar, if not exact, to what IVNE had for collar locations. Table 9-1 and Figure 9-1 demonstrate the comparison between the collected 2021 collar locations to the IVNE collar locations used in the Mineral Resource Estimate (“MRE”). Table 9-2 and Figure 9-2 demonstrate the comparison between the collected collar locations for historic drill holes to the IVNE collar locations used in the MRE.

 

Photos of drill hole collars for historic holes CG-091 and CG-030 can be seen in Figure 9-3.

 

Table 9-1: Check Coordinates for IVNE 2021 Drilling, March 3, 2022

 

  Original Coordinates Check Coordinates
Hole ID Easting Northing Easting Northing
SCC-001 417,838 3,639,741 417,837 3,639,741
SCC-002 417,683 3,640,043 417,696 3,640,053
SCC-003 417,344 3,640,856 417,329 3,640,855
SCC-004 417,536 3,640,350 417,535 3,640,349

 

Technical Report Summary – December 8, 202191Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 9-1: Map of check drill hole collars from the 2022 site visit, also displaying all diamond drill hole collars

 

Table 9-2: Check Coordinates for Historic Drilling Within the Santa Cruz Deposit, March 3, 2022

 

  Original Coordinates Check Coordinates
Hole ID Easting Northing Easting Northing
CG-030 417,839 3,640,036 417,838 3,640,036
CG-055 417,833 3,639,421 417,833 3,639,425
CG-061 417,835 3,639,580 417,834 3,639,581
CG-068 417,893 3,639,504 417,894 3,639,506
CG-091 417,862 3,639,957 417,861 3,639,959
CG-092 417,769 3,640,118 417,768 3,640,117
CG-099 417,899 3,639,661 417,899 3,639,661
CG-100 417,758 3,639,654 417,759 3,639,655

 

Technical Report Summary – December 8, 202192Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 9-2: Map of historic drill hole collars, also displaying all diamond drill hole collars

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
93Nordmin Engineering Ltd.

 

 

 

Figure 9-3: Collars for historic diamond drill holes CG-091 and CG-030

 

9.1.2Core Logging, Sampling, and Storage Facilities

 

The Company drill holes are logged, photographed, and sampled on site at the core logging facility (Figure 9-4 and Figure 9-5). No historic core is available. Recently drilled core is currently being kept stacked on metal shelves within IVNE’s core logging facility (Figure 8-2). The core samples, pulps, and coarse rejects are kept at the core shack.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
94Nordmin Engineering Ltd.

 

 

 

Figure 9-4: IVNE core logging facility located in Casa Grande, Arizona

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
95Nordmin Engineering Ltd.

 

 

 

Figure 9-5: Core photography station at the IVNE core logging facility

 

Historic drill core has not been preserved; several core dumps can be found around the property, but it is not available for review.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
96Nordmin Engineering Ltd.

 

 

9.1.3Independent Sampling

 

Nordmin selected intervals from two Santa Cruz deposit holes. A total of 33 verification samples were collected (Table 9-3). Diamond drill core previously sampled (halved) was re-sampled by having the labs re-analyze the coarse reject material. Two assay laboratories were used during the 2021 drill campaign; therefore, the decision was made by Nordmin to send the independent samples to both laboratories to check for any lab bias.

 

Table 9-3: Original Assay Values Versus Nordmin Check Sample Assay Values from the 2022 Site Visit

 

  Original Sample Check Sample
Sample Number From To Cu T
(%)
CuAs-
SEQ
Cu-CN-SEQ Mo
(%)
Cu T
(%)
CuAs-
SEQ
Cu-
CN-
SEQ
Mo
(%)
SKY5022508 582.35 583.70 0.12 0.041 0.005 0.013 0.12 0.045 0.007 0.011
SKY5022513 587.70 588.70 6.05 4.535 0.014 0.012 6.03 5.544 0.012 0.012
SKY5022517 590.70 591.70 2.02 1.756 0.007 0.008 2.17 2.134 0.007 0.007
SKY5022525 591.70 600.70 1.2 1.069 0.011 0.009 1.23 1.207 0.012 0.006
SKY5022601 600.70 687.23 3.99 3.803 0.039 0.005 4.05 3.947 0.039 0.005
SKY5022604 600.70 690.23 6.89 1.472 3.742 0.011 6.95 1.527 5.31 0.01
SKY5022585 664.23 666.23 1.98 1.818 0.007 0.012 1.99 1.98 0.007 0.011
SKY5022565 666.23 642.10 2.63 2.348 0.012 0.007 2.62 2.621 0.014 0.005
SKY5022730 816.00 817.00 0.61 0.0025 0.068 0.005 0.62 0.005 0.075 0.003
SKY5022754 836.00 837.00 1.99 0.0025 0.204 0.012 2.05 0.0025 0.214 0.011
SKY5022823 939.00 941.00 0.62 0.007 0.064 0.002 0.64 0.009 0.066 0.002
SKY5022824 941.00 943.00 0.55 0.0025 0.031 0.006 0.55 0.005 0.031 0.006
SKY5022823 939.00 941.00 0.62 0.007 0.064 0.002 0.65 0.0025 0.06 0.002
SKY5022824 941.00 943.00 0.55 0.0025 0.031 0.006 0.55 0.0025 0.032 0.002

 

The Company uses unmineralized material (an alkaline granite from the area), where values of ore minerals are below detection limits or quartz gravel as sample blanks. The blank material was analyzed at Skyline Laboratories to ensure that there was no significant amount of Cu present. Coarse blanks are crushed as normal samples within the sample stream so that contamination during sample preparation can be detected. Blanks are used to assess proper instrument cleaning and instrument detection limits and contaminations within the lab.

 

The Nordmin assay results were compared to IVNE’s database and summarized in the scatter plots for total Cu (%) (Figure 9-6, Figure 9-7 and Figure 9-8). Despite some significant sample variances in a few samples, most assays compared within reasonable tolerances for the deposit type and no material bias was evident. No bias was evident among lab analyses.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
97Nordmin Engineering Ltd.

 

 

 

Figure 9-6: Nordmin independent sampling total Cu (%) assays from Skyline Laboratories

 

 

Figure 9-7: Nordmin independent sampling acid soluble Cu (%) assays from Skyline Laboratories

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
98Nordmin Engineering Ltd.

 

 

 

Figure 9-8: Nordmin independent sampling of cyanide soluble (%) assays from Skyline Laboratories

 

9.1.4Audit of Analytical Laboratory

 

On September 17, 2021, the Nordmin QP and representatives from IVNE audited the sample preparation and analysis facilities of Skyline Laboratories in Phoenix, Arizona. Recommendations from the audit were provided to Skyline Laboratories and follow up was completed by IVNE representatives to ensure that the recommendations were implemented.Santa Cruz Deposit

 

9.2Twin Hole Analysis

 

Nordmin completed a twin hole analysis between the historical Hanna-Getty and ASARCO diamond drilling versus the 2021 IVNE drilling to determine if the historical information could be used in the geologic model and Resource Estimate. The analysis compared the collar locations, downhole surveys, logging (lithology, alteration, and mineralization), sampling and assaying between the two groups to determine if the historical holes had valid information and would not be introducing a bias within the geological model or Resource Estimate. The comparison included a QA/QC analysis of the historical drill holes.

 

A total of four historical holes were reviewed with the following outcomes (Figure 9-9):

 

·All four historical hole assays aligned with 2021 diamond drilling assays

 

·2021 diamond drilling assays were of higher resolution due to smaller sample sizes

 

·Recent drilling validated the ASARCO cyanide soluble assays

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
99Nordmin Engineering Ltd.

 

 

 

Figure 9-9: Collar locations of historic diamond drilling (orange) versus recent 2021 IVNE twin drill holes (blue)

 

Figure 9-10 demonstrates that grade variability and location were insignificant between CG-027 and SCC-001 and demonstrated overall grade continuity between the intercepts. Resolution is higher in SCC-001 downhole due to smaller sample sizes compared to historic drilling. Table 9-4 demonstrates good agreement between historic logging and current logging using the same regional lithology types. This provides confidence in the accuracy of the geologic model and that associations made between mineralization and lithology are valid. Similar patterns are observed within the other three historical drill holes used within the Resource Estimate, which included reliable QA/QC data.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
100Nordmin Engineering Ltd.

 

 

 

Figure 9-10: Comparison of assays from SCC-001 versus CG-027. A) shows the direct comparison of total Cu assays as Cu (%). B) SCC-001 and CG-027 showing downhole charts of acid soluble Cu assays (%) on the left and total Cu (%) assays on the right.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
101Nordmin Engineering Ltd.

 

 

Table 9-4: Downhole Lithology Logging Comparison of CG-027 versus SCC-001

 

TgcU = Tertiary unconsolidated sediments, TgcL = Tertiary Lithified Sediments, Mixed = breccias, LI = Laramide Intrusives, pC = Precambrian Granites/Diabase Dykes and Aplites

 

Hole ID FROM (m) TO (m) Lithology Hole ID FROM (m) TO (m) Lithology
CG-027 0 24.38 Tert. Sediments SCC-001 0          514.78 Conglomerate
24.38 85.34 Tert. Sediments Conglomerate
85.34 195.07 Tert. Sediments Conglomerate
195.07 347.47 Tert. Sediments Conglomerate
347.47 542.54 Tert. Sediments 514.78 544.03 Conglomerate
542.54 563.88 Tert. Sediments 544.03 551.28 Conglomerate
563.88 566.92 No data 551.28 556.26 Fault
566.92 576.07 Tert. Sediments 556.26 578.76 Breccia
576.07 579.12 Tert. Sediments 578.76 600.93 Quartz Monzonite
579.12 585.52 No data 600.93 603.35 Quartz Monzonite
585.52 603.5 Mixed      
603.5 606.55 Tert. Sediments 603.35 615.03 Quartz Monzonite
606.55 612.64 Mixed      
612.64 615.69 Tert. Sediments      
615.69 621.79 Mixed 615.03 660.24 Granodiorite
621.79 640.08 Laramide Int.      
640.08 643.12 Tert. Sediments      
643.12 658.36 Laramide Int.      
658.36 694.94 Granite 660.24 705.39 Granite
694.94 697.99 Granite 705.39 707.83 Granodiorite
697.99 710.18 Granite      
710.18 713.23 Laramide Int. 707.83 724.47 Granite
713.23 719.32 Granite 724.47 732.03 Granodiorite
719.32 731.52 Laramide Int.      
731.52 734.56 Laramide Int. 732.03 751.71 Granite
734.56 807.72 Granite 751.71 769.62 Granite
      769.62 802.66 Granite
      802.66 807.511 Gabbro
807.72 816.86 Laramide Int. 807.511 818.39 Granite
816.86 923.54 Granite 818.39 820.23 Fault
      820.23 845.75 Granite
      845.75 849.17 Fault
      849.17 891.7 Granite
      891.7 897.94 Granite
      897.94 910 Granite
      910 921.22 Fault
923.54 926.59 Laramide Int. 921.22 928.75 Granodiorite
926.59 929.64 Granite 928.75 946.09 Fault

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
102Nordmin Engineering Ltd.

 

 

 

Several holes have been twinned over the course of the exploration work conducted on the Santa Cruz deposit. Nordmin was able to match most of the intervals for each of the pairs and plotted the grades for Cu, Cu-SEQ, and Mo. In Nordmin’s opinion, for most of the pairs, the assay results compared reasonably well; the HG and LG zones were similar, and the grades tended to cluster in the same ranges. In Nordmin’s opinion, the twinning has provided a reasonably consistent verification of the earlier Hanna-Getty and ASARCO drill results, particularly considering the differences in the assay, survey methods and QA/QC protocols.

 

9.3Database Validation

 

The Nordmin QP completed a spot check verification of the following drill holes:

 

Santa Cruz Project –89 (19%) of the lithologies, 388 (55%) of the geotechnical measurements, 328 (70%) of the assays.

 

The geology was validated for lithological units from handwritten logs transcribed into excel tables and historic logs compiled into a logging database. Lithological units being implemented in current logging are the same as the units used historically. The geological contacts and lithology aligned with the core contacts and lithology and are acceptable for use. Two assay depth errors from 2021 drilling were brought to the attention of the on site geologists. These errors were rectified, and the database was updated. The entire database was run through the QGIS validity check to look for errors. No significant errors were found in the database.

 

Within the database, a portion of historic drill holes is missing the downhole survey and assay data. Holes drilled by Casa Grande Copper Co. have 62.1% of the survey data and 96.5% of the assay data. Holes drilled by ASARCO have 65.9% of the downhole survey data and only 34.4% of the assay data available. Missing data has been well documented by IVNE, and vertical twins of historic drill holes have been and continue to be drilled to confirm lithology, assay, and geotechnical data (Section 9.1.4).

 

9.4Review of Company’s QA/QC

 

The Company has a robust QA/QC process in place, as previously described in Section 11. The Company geologists actively monitor the assay results throughout the drill programs and summarize the QA/QC results, reporting daily and monthly. In the event of a QA/QC failure, the entire sample batch would either be re-sampled at the same lab or sent to the secondary lab for re-sampling. The assay laboratories also employ a rigorous QA/QC protocol and will re-sample batches in the event of a QA/QC failure. The CRMs performed as expected within tolerances of two to three standard deviations of the mean grade. Blank failures at American Assay Laboratories lead to the re-sampling of several batches at American Assay Laboratories. Due to the continued dust issues found at this lab causing metal contamination amongst samples, this lab will no longer be employed by IVNE after pre-paid samples are run. Nordmin is satisfied that the QA/QC process performs as designed to ensure the assay data quality.

 

9.5Nordmin QP’s Opinion

 

Upon completion of the data verification process, it is the Nordmin QP’s opinion that the geological data collection and QA/QC procedures used by IVNE are consistent with standard industry practices and that the geological database is of suitable quality to support the Mineral Resource Estimate.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
103Nordmin Engineering Ltd.

 

 

10MINERAL PROCESSING AND METALLURGICAL TESTING

 

Mineralized material from the Santa Cruz deposit was evaluated by the Casa Grande Copper Corporation (CGCC) Hanna-Getty JV and by the SCJV in conjunction with the Department of the Interior Bureau of Mines (subsequently Bureau of Reclamation). Most of the mineral processing and metallurgical test program review relates to the studies conducted by CGCC. The QP has not been able to verify if the test samples are representative of the various types and styles of mineralization and the mineral deposit as a whole. Access to memos detailing the composition of the samples is being negotiated.

 

10.1CGCC Studies (1976-1982)

 

The CGCC studies were conducted by the Hanna Mining Company Research Centre in Minnesota. They evaluated three distinct processing routes listed below. Prefeasibility and/or feasibility level reports were prepared for each process. There is a fourth process, heap leach, that was investigated with conceptual studies, but no PFS, or FS level study was pursued for this process route. Approximately 90 mineral processing and metallurgical test programs were conducted. The number of tests conducted in each program ranged from 6 to 40. Three different processes were considered by CGCC:

 

All Agitated Tank Leach Approach (91% total Cu recovery to cathodes).

 

All-Float Approach (92% total Cu recovery to cathodes or a mixture of cathodes and saleable Cu concentrates).

 

Leach – Float Process (94% Cu recovery to cathodes or to a mixture of cathodes and saleable Cu concentrates).

 

CGCC selected the leach float process to move forward with.

 

10.1.1Sample Selection

 

Initial testing (1976 – 1977) was performed on drill core coarse rejects as they became available from the drilling program. Grinding tests, open cycle bench level flotation tests and bottle roll leach tests were performed. Composite samples from multiple holes and intervals were usually used in these tests. The composite sample was described in some test reports, or a reference was made to a separate memo regarding the composite make-up (drill holes and their intervals were listed); therefore, there was adequate information provided regarding the composite sample source material.

 

In 1977 and 1978, after more drilling, very large composites were produced for mineral processing tests. A memo was referenced in each test program that described the drill holes and intervals used to produce the composites. Two significant composites were referenced at this time: one composite represented the mineralized material in the HG part of the Santa Cruz deposit (1.5% total Cu). The other major composite represented the mineralized material in the entire deposit, including the primary Cu sulphides.

 

Additional selective composite samples, compared to the major ones described above, were generated in 1979, and used for test programs in 1979 and 1980. Memos provided describe what drill holes and intervals were used to generate each composite sample. These composites represented major ore types found in the Santa Cruz deposit. There was a composite generated for each of the ore types:

 

HG Supergene

 

Supergene Dilution

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
104Nordmin Engineering Ltd.

 

 

LG Supergene

 

Mixed Chalcocite/Chalcopyrite

 

Primary Chalcopyrite

 

Exotic Ore

 

Exotic Dilution Ore

 

Mineral processing and metallurgical tests were conducted on each ore type.

 

10.1.2Grinding Studies

 

Grinding studies were conducted using laboratory size rod mills on 1000-gram samples. The initial sample types from the early drilling programs were tested, as were the major composite samples of the Santa Cruz deposit that were available after the completion of several drill programs across the Santa Cruz deposit. Grinding for leaching was investigated separately from grinding for flotation purposes. The QP is of the opinion that industry accepted practices that conform to the 2019 CIM Best Practice Guidelines were applied. Ground samples for flotation were subjected to rougher flotation and standard Cu recovery (non-acid soluble Cu) and concentrate grade relationships developed to determine the best primary grind P80. Ground samples for leaching were subjected to bottle roll leaching with sulphuric acid or sulphuric acid and ferric sulphate as lixiviant.

 

The results of the grinding studies (leaching and flotation) on the major composite representing the whole deposit were used for testing later composites of the ore types listed above. The optimum primary grinding size for rougher Cu sulphide flotation was found to be P80 212 micron with a bond work index of 6.5 kWh/tonne. The optimum grind size for whole ore agitated tank leaching, with either type lixiviant mixture, was determined to P80 800 micron.

 

These grinding studies were applied to major composites of the Santa Cruz deposit and to the composites of ore types listed above under Sample Selection. There was no variability testing conducted. Therefore, the test results would be acceptable for a Preliminary Economic Assessment (PEA) level study program today. A PFS level study would require 30 to 40 variability tests of selected drill holes and drill intervals, and a FS level study would need 100 or more.

 

10.1.3Flotation Studies

 

The QP is of the opinion that the CGCC standard test procedures described for open cycle flotation and closed cycle flotation tests used industry accepted practices. The flotation equipment described is still in use today. All tests were documented just as they would be today, with such information as: P80’s, float times, reagent names, and consumptions, notes on froth appearance, etc. The regrind test program for the cleaner circuit flotation was somewhat vague. However, Cu sulphide concentrate grade and overall Cu recovery (non-acid soluble Cu) results were typical based on the rougher flotation recoveries reported (mid-nineties), so the regrind was performed correctly. Cu recovery after cleaning was in the low nineties and the concentrate grade varied from 25% to 50% Cu depending on Cu sulphide ore mineralogy.

 

Flotation of atacamite together with Cu sulphides was evaluated and found to be successful in producing a 12% concentrate at recoveries in the mid-nineties for the atacamite and Cu sulphide minerals. The chloride in this concentrate was leached out almost completely with a patented NaOH leach leaving behind Cu sulphides and Cu hydroxide. The Cu hydroxide was leached out with weak sulphuric acid solution producing a pregnant leach solution (PLS) for solvent extraction-electrowinning (SX-EW), and the left behind Cu sulphides were pH adjusted and reground, then upgraded in a cleaner flotation circuit. Cu recovery of the Cu oxides (excluding atacamite) was poor. Thus, total Cu recovery was in the mid-eighties. An all-float process was developed later where the Cu oxides were economically recovered, and total Cu recovery was raised to the low nineties for this flow sheet.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
105Nordmin Engineering Ltd.

 

 

Flotation test programs were applied to all the composite samples described above under Sample Selection. The test programs would be acceptable for a PEA level program today but not for a PFS or FS level study today because of the lack of any significant variability flotation testing of the Santa Cruz deposit.

 

10.1.4Leaching Studies

 

Leaching test programs were applied to the composite samples described above under Sample Selection. They were also applied to another ore deposit composite that represented mineralization containing principally acid soluble Cu minerals and secondary sulphide Cu minerals.

 

The QP is of the opinion that test procedures described would meet industry accepted practices and conform to 2019 CIM Best Practice Guidelines for determining the leachability of an ore with sulphuric acid or acidic ferric sulphate at the PEA level. Once again lack of any variability type test program prevents its use at the PFS and FS levels. Industry accepted practices for bottle roll tests were used where PLS samples were withdrawn at timed intervals, and Cu, acid, ferric, and pH levels were measured. Acid was added to maintain pH. Optimum leach time, ferric level, and pH were determined based on plots of Cu extraction rate, acid consumption rate, and ferric consumption rate.

 

Acid leach test results on the composites tested were generally consistent. Acid soluble Cu recovery was in the mid-nineties for a 4-hour leach time. Acid consumption ranged from 18.5 to 23 kg of acid per tonne of ore (without the SX-EW acid credit on Cu electrowon). The best pH was 1.5.

 

Acidic ferric sulphate leaching on a composite of acid soluble Cu minerals and secondary sulphide minerals was successful. The best agitated tank leach conditions were determined to be:

 

24-hour leach time

 

40oC leach temperature

 

10 grams per litre (gpl) ferric concentration

 

Acid soluble Cu recovery was 95%. Non-acid soluble Cu recovery was 90%. Total Cu recovery was 90-91%.

 

Sulphuric acid heap leaching was evaluated on one hole, 27 A, across most of its length using the column cell test method. Nine column cell tests were conducted from selected intervals of core. The calculated head grade was 1.4% total Cu and 1.2% acid soluble Cu. Total Cu extraction was 77% and acid soluble Cu 89%. Gangue acid consumption was 18.5 lb acid/ton ore. The QP is of the opinion that procedures applied during the tests were acceptable industry practices and conform to the 2019 CIM Best Practice Guidelines.

 

10.1.5Copper Measurement

 

An important aspect of the test programs described above are the analytical techniques used for measuring total Cu and acid soluble Cu in ores, and total Cu in concentrates. The sequential Cu assaying method had not been developed yet for the CGCC test programs from 1976 to 1982. Thus, secondary sulphide concentrations in the test composite samples were estimated from mineralogy studies on the composites and from drill core mineral logging records. The analytical methods used are referred to in several of the test memos on file. However, access to those memos was not available at the time when this report was written. Acceptable techniques for accurately measuring total Cu and acid soluble Cu in ore and total Cu in Cu concentrates were available at the time of the Hanna testing. Until those memos are available, the QP is of the opinion that it would be logical to assume Hanna applied well established analytical methods, with accurate Cu standards, for these determinations. The same assumptions would go for measuring Cu concentrations in PLS (by atomic-absorption) and Cu in electrolyte (by titration). Hanna had been an established mining company with a research centre for a few decades by this time.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
106Nordmin Engineering Ltd.

 

 

10.2ASARCO Study by Mountain States Engineering (1980)

 

This study evaluated leaching in place fragmented acid soluble Cu ore from block cave mining. There were no mineral processing and metallurgical tests associated with what was called, at the time, a preliminary feasibility study. As mentioned above, Cu recovery factor and column of ore caving factors are used from other nearby underground mines, using the block cave mining method, and/or that were leaching block cave rubbled ore with dilute sulphuric acid. This study could not be used today for a PEA level study due to no test work. This work can be considered conceptual and referenced as such.

 

10.3Santa Cruz In Situ Study

 

As discussed in Section 6, the Santa Cruz In Situ project was a research project between the Department of the Interior Bureau of Mines (subsequently Bureau of Reclamation) and the landowners, the SCJV between ASARCO Santa Cruz Inc. and Freemont McMoRan Copper & Gold Inc.

 

Metallurgical studies of core (2-inch diameter by 2.5-inch-long), from the proposed in situ leach zone in the pilot program reported Cu recoveries ranging from 57 % to 90%. Total Cu ranged from 2.3% to 9%. Tests were run for 3,000 hours to 3,800 hours (125 days to 158 days), and no extraction rate versus time data was reported, which is unusual because it is critical to know for the process design and for the well development schedule. Flow volumes varied from two millilitres per day to several litres per day, and pressures ranged from 0 psi to 1000 psi. The studies reported the acid consumption would be 1.2 lbs per 1.0 pound of Cu recovered on atacamite samples and ranged between 3-8 pounds per pound of Cu for the chrysocolla samples (with some very high consumption rates initially, 10+ pounds per pound). The initial acid concentration in the feed solution varied from 5 to 40 gpl H2SO4.

 

Leach tests on the core showed that initial permeability rates were very low when the solution initially contacted the core in the test apparatus. But, later, as Cu-oxide minerals dissolved from the filled fractures, acceptable permeability rates were achieved.

 

The QP is of the opinion that the in situ leach test program used industry accepted practices and conforms to the 2019 CIM Best Practise Guidelines. Total Cu and acid soluble analytical methods were satisfactory for the measurement of the core samples. Identification of the core sample by drill hole and interval was performed. Cross sections of the sample location in the proposed ore area for the five-spot injection and well design were provided. Samples were representative of the proposed test region.

 

The pilot program started in February 1996. Funding was cancelled in October 1997 after the US Bureau of Mines folded, but injection continued until December 1997 and pumping until the end of February 1998. No metallurgical or economic results were made public afterwards. Pilot program Cu cathode production was much less than anticipated according to reported production of 18 tons of cathode Cu and the SX-EW (solvent extraction, electrowinning) design capacity of 1,000 tons per year. The pilot program was never restarted, and the JV partners of ASARCO and Freeport McMoRan did not show interest in pursuing the project further, and neither has pursued in situ Cu mining anywhere else since 1998.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
107Nordmin Engineering Ltd.

 

 

10.4Process Factors and Deleterious Elements

 

There are no processing factors or deleterious elements that could have a significant effect on economic extraction. The processes proposed in the CGCC, ASARCO, and Santa Cruz In Situ studies for extraction of Cu from the ore are all conventional in design and have been used economically for many decades. There have been significant advances in most of these technologies since 1980, when most of the studies were conducted, which have improved the economics of these processes. Some examples are:

 

Materials of construction of SX plants are cheaper and more resistant to chlorides in solution from leaching atacamite. SX wash circuits or organic coalescers eliminate the concern of chloride carryover to the EW.

 

SX reagents are much more selective for Cu extraction, react faster, separate faster from the aqueous media they are mixed with and are more robust today.

 

SAG and ball mill grinding circuits are designed much more efficiently today and the liner and grinding media used last much longer than in 1980.

 

Flotation cell designs are more efficient now and have raised recovery and concentrate grades.

 

Environmental controls for dust, volatile organic compounds (VOC), and aerosol mists are much more efficient compared to then.

 

10.5QP Opinion

 

After completion of the review of mineral processing and metallurgical testing by The Hanna Mining Company and the United States Bureau of Mines, it is the opinion of the QP that the testing procedures, results interpretations and reporting met standard industry practices. The only issue noted was the samples selected by The Hanna Mining Company for their testing programs were not described in adequate enough detail to confirm the representativeness of the mineralized material tested. The referenced reports describing the drill holes and selected drill core intervals of the samples were not available at the time of publishing this technical report. However, these reports are expected to be available in the future.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
108Nordmin Engineering Ltd.

 

 

11MINERAL RESOURCE ESTIMATES

 

11.1Drill Hole Database

 

The work on the Mineral Resource Estimate included a detailed geological and structural re-examination of the Santa Cruz deposit.

 

The Santa Cruz deposit Mineral Resource Estimate benefits from approximately 104,184 m of diamond drilling in 121 drill holes spanning from 1964 to 2021 (Figure 11-1).

 

 

 

Figure 11-1: Plan view of Santa Cruz Project diamond drilling

 

Diamond drill hole samples were analyzed for total Cu and acid soluble Cu using AAS. A decade after initial drilling, ASARCO re-analyzed select samples for cyanide soluble Cu (AAS) and molybdenum (ICP). The Company currently analyzes all samples for total Cu, acid soluble Cu, cyanide soluble Cu, and molybdenum. Due to the re-analyses to determine cyanide soluble Cu within historic samples, there are instances where cyanide soluble Cu is greater than total Cu. It has been determined that the historic cyanide soluble assays are valid as they align with recent assays in 2021 drill holes. Therefore, a cap has been applied to historic cyanide soluble assays such that they must be equal to or less than the associated total Cu value for each sample. Drill hole counts are summarized in Table 11-1, and the number of assays used within each Mineral Resource Estimate is provided in Table 11-2.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
109Nordmin Engineering Ltd.

 

 

Table 11-1: Drill Hole Count Summary

 

Deposit DDH Count Total Meterage (m)
Santa Cruz 125 104,184

 

Table 11-2: Mineral Resource Estimate Number of Assays by Assay Type

 

Assay Type Santa Cruz Deposit Assays
Total Cu 17,692
Acid Soluble Cu 2,583
Cyanide Soluble Cu 826
Molybdenum 5,114

 

11.2Domaining

 

11.2.1Geological Domaining

 

Geological domains were developed within the Santa Cruz deposit based upon geographical, lithological, and mineralogical characteristics, along with incorporating both regional and local structural information. Local D2 fault structures separate the mineralization at the adjacent Santa Cruz and Texaco deposits. Local fault zones were created and/or extrapolated by Rogue using Seequent’s LeapfrogTM geological modelling software. The Santa Cruz deposit was divided into two main geological domains consisting of the weathered supergene enrichment and the primary hypogene mineralization domain. Each of these geological domains was further subdivided based upon their type of Cu speciation, specifically acid soluble (Oxide Domain), cyanide soluble (Chalcocite Enrichment Domain), primary Cu sulphide (Primary Domain), and exotic Cu (Cu oxides in overlying Tertiary sediments). Collectively each of these domains was further subdivided based upon their individual grade profiles. A schematic for the Santa Cruz deposit hierarchy is outlined in Figure 11-2 and Table 11-3.

 

 

 

Figure 11-2: Domaining hierarchy of the Santa Cruz Project

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
110Nordmin Engineering Ltd.

 

 

Table 11-3: Santa Cruz Geological Domains

 

Santa Cruz deposit
Weathered Supergene Enrichment Oxide Domain (Primarily Acid Soluble Cu)
Chalcocite Enriched Domain (Primarily Cyanide Soluble Cu)
Exotic Domain (Tertiary-Hosted Exotic Cu)
 Hypogene Mineralization Primary Domain (Primarily Primary Sulphide Cu)

 

Exotic Cu is primarily present within the CG2 and CG3 D2 Fault structures. All other Cu styles of mineralization hosted within the Oracle Granite lithology terminate at the contact of the Tertiary sediments. The current drilling indicates that the Cu mineralization is truncated at depth by the basal faults within the region.

 

The Oracle Granite hosts both the Laramide Porphyry and Diabase dykes, both of which are associated with brecciation and Cu mineralization. Secondary supergene Cu mineralization is separated from the primary hypogene mineralization by a Cu-oxide boundary layer titled the Chalcocite Enriched Domain. This domain is defined by a 2:1 relationship of acid soluble to total Cu and follows the dip of the contact of the Oracle Granite-Tertiary sediments contact. The Chalcocite Enriched Domain was formed by two different enrichment events. HG Cu oxides follow the trend of the Laramide porphyries closely and likely contain significant amounts of primary mineralization. Cyanide soluble Cu can be found within both the supergene Cu and hypogene Cu domains as a form of secondary enrichment of chalcocite. Cyanide soluble assays were measured a decade after initial diamond drilling by ASARCO, and as such, the data is not available for all of the sample intervals within the drill holes. As such, the cyanide soluble Cu wireframes were built based upon available data, and a regression analysis was used to infill the missing values for acid and cyanide soluble Cu. Figure 11-3 is a conceptual example of the Santa Cruz deposit domaining.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
111Nordmin Engineering Ltd.

 

 

 

 

Figure 11-3: Santa Cruz deposit domain idealized cross-section

 

11.2.2Regression

 

A regression analysis was conducted to infill the downhole intervals that are missing relevant acid soluble and cyanide soluble data. The analysis used the relationships between all applicable data available to determine the most appropriate regression calculations using Orange Datamining Software (version 3.30.2). The software created regression formulas that were applied to the total Cu assays to calculate accurate acid soluble and/or cyanide soluble values. Table 11-4 and Table 11-5 define the regression formulas that were used. All further references to acid soluble and cyanide soluble Cu grades will apply to the full regression-applied values.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
112Nordmin Engineering Ltd.

 

 

 

Table 11-4: Regression Analysis for Acid Soluble Cu

 

Domain Criteria/Field Criteria 2 Regression Formula R2
Exotic No conditions - ASCu % = (0.9333 * Total Cu %) - 0.0338 0.99
Oxide No conditions - ASCu % = (0.6758 * Total Cu %) + 0.123 0.64
Chalcocite Enrichment In LG Wireframe - ASCu % = (0.8007 * Total Cu %) - 0.4162 0.68
In MG Wireframe - ASCu % = (0.1741 * Total Cu %) + 0.0899 0.20
Primary

Assay Field:

LITH_SPEC_GROUP

DacPorph ASCu % = (0.1192 * Total Cu %) + 0.0314 0.38
GranOracle ASCu % = (0.0862 * Total Cu %) + 0.0095 0.22
Absent, AndPorph, SGHc ASCu % = (0.072 * Total Cu %) + 0.0297 0.68
Background

Assay Field:

LITH_GEN_GROUP

TVP ASCu % = (0.677 * Total Cu %) + 0.0514 0.80
Tgc ASCu % = (0.9606 * Total Cu %) - 0.0651 0.97
TgcS ASCu % = (0.9081 * Total Cu %) - 0.0267 0.97
pC Grouped ASCu % = (0.5225 * Total Cu %) - 0.0899 0.37
Absent ASCu % = (0.6349 * Total Cu %) - 0.1107 0.47

 

Table 11-5: Regression Analysis for Cyanide Soluble Cu

 

Domain Criteria/Field Criteria 2 Regression Formula R2
Exotic n/a - CNCu % = 0 n/a
Oxide In LG Wireframe - CNCu % = (1.0237 * Total Cu %) - 0.0847 0.87
In MG Wireframe - CNCu % = (1.0115 * Total Cu %) - 0.3625 0.63
In HG Wireframe - CNCu % = (0.6778 * Total Cu %) - 0.1683 0.52
Chalcocite Enrichment No conditions - CNCu % = (0.7612 * Total Cu %) + 0.0258 0.73
Primary No criteria - CNCu % = (0.9459 * Total Cu %) - 0.2093 0.85
Background No conditions - CNCu % = (0.8288 * Total Cu %) - 0.1101 0.81

 

11.2.3Mineralization Domaining

 

Mineralization within the Santa Cruz deposit is hosted within crystalline basement rocks, including the Oracle Granite, Laramide porphyry, and Diabase dykes.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
113Nordmin Engineering Ltd.

 

 

Nordmin initially examined and modelled the grade distributions for the hypogene and supergene Cu domains and their corresponding sub-domains. Each sub-domain was further domained based upon their Cu grade distribution. The grade distributions were created for exotic Cu, Cu oxides, chalcocite enrichment, and primary hypogene Cu. The analysis confirmed that the changes in mineralization and corresponding grade are associated with the type of Cu mineralization. The higher-grade mineralization is a result of secondary supergene enrichment and is near the contact between the Oracle Granite and Tertiary sediments. While the Primary Domain consists of moderate grade hypogene Cu that is predominately hosted within the Laramide porphyry, Diabase dykes, and associated breccias at greater depth. As such, Nordmin created grade shells for each of the Cu types at multiple grades to reflect the lithological and geochemical differences.

 

Mineralization wireframes were initially created on 50 m sections and plans and adjusted between various views to edit and smooth each wireframe where required. The wireframes were permitted to follow lithological boundaries and trends where applicable. When not cut-off by drilling, the wireframes terminate at either the contact of the Cu-oxide boundary layer, the Tertiary sediments/Oracle Granite contact or D2 fault structure. There is an overlap of cyanide soluble Cu with either acid soluble Cu in the weathered supergene domain or with primary Cu in the primary hypogene mineralization domain. Otherwise, no wireframe overlapping exists within a given grade domain. The use of explicit modelling allows for mineralization in context with the Santa Cruz deposit geology and associated geochemistry to be considered. It is Nordmin’s opinion that the explicit modelling approach minimizes risks within the resource estimation process when compared to using implicit modelling.

 

Grade domain wireframes were modelled for four domains: acid soluble Cu, primary sulphide Cu (chalcocite, chalcopyrite), cyanide soluble Cu, and exotic Cu. Each domain consists of sub-domains, that are based on the following grade distributions outlined in Table 14-6.

 

Table 11-6: Santa Cruz Deposit Domain Wireframes

 

Domain Sub-Domain Grade Bin
Exotic Low Grade Total Cu 0.5-2.0%
High Grade Total Cu >= 2.0%
Oxide Low Grade Acid Soluble Cu 0.5-2.0%
High Grade Acid Soluble Cu >= 2.0%
Chalcocite Enrichment Low Grade Cyanide Soluble Cu 0.5-1.0%
Medium Grade Cyanide Soluble Cu >= 1.0%
Primary Low Grade Total Cu 0.5-1.0%
Medium Grade Total Cu 1.0-1.5%
High Grade Total Cu >= 1.5%

 

11.3Exploratory Data Analysis

 

The exploratory data analysis was conducted on raw drill hole data to determine the nature of the element distribution, correlation of grades within individual rock units, and the identification of HG outlier samples. Nordmin used a combination of descriptive statistics, histograms, probability plots, and XY scatter plots to analyze the grade population data using X10- Geo (V1.4.18). The findings of the exploratory data analysis were used to help define modelling procedures and parameters used in the Mineral Resource Estimate.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
114Nordmin Engineering Ltd.

 

 

Descriptive statistics were used to analyze the grade distribution of each sample population, determine the presence of outliers, and identify correlations between grade and rock types for each mineral sub-domain.

 

One drill hole, SC-013, contained assay interval errors. The interval from 0 m to 696.77 m was removed from the flagging process.

 

CG-018 had collar and survey errors. This drill hole has been re-drilled and named CG-018A. Relevant data that would be present in CG-018 can be found in CG-018A. Since the location of the drill hole is incorrect, there can be no way to confirm what depths the assays are from with confidence. Therefore, due to the surveying issues, this drill hole was removed from the database.

 

Individual drill hole tables (collar, survey, assay, etc.) were merged to create one single master de-surveyed drill hole file. The processing to create this file splits assay intervals to allow for all records in all drilling tables to be included in one single file. Values in Table 11-7 are based on analysis of this master file; counts will differ when compared with the original data.

 

Table 11-7: Santa Cruz Deposit Domain, Assays by Cu Grade Sub-Domain

 

Domain Sub-Domain Sample Count Total Cu Acid Soluble Cu Cyanide Soluble Cu Mo
Exotic LG (0.5%) 110 110 110 110 110
HG (2.0%) 29 29 29 29 29
Oxide LG (0.5%) 2,140 2,140 2,140 2,140 2,140
HG (2.0%) 836 836 836 836 836
Chalcocite Enrichment Low 588 588 588 588 588
Med 434 434 434 434 434
Primary LG (0.5%) 2,917 2,917 2,917 2,917 2,917
Medium Grade (1.0%) 954 954 954 954 954
HG (1.5%) 222 222 222 222 222
Background 4,717 4,696 4,717 4,717 4,716
Total 13,704 13,725 13,725 13,724 13,704

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
115Nordmin Engineering Ltd.

 

 

Figure 11-5 to Figure 11-7 provide the data analysis for the total Cu LG, MG, and HG sub-domains for the Cu-Oxide Domain within the Santa Cruz deposit. The data analysis for all grade domains is available in Appendix C.

 

 

 

Figure 11-4: Histogram and log probability plots for the Cu-oxide LG Sub-Domain

 

 

 

Figure 11-5: Histogram and log probability plots for the primary Cu LG Sub-Domain

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
116Nordmin Engineering Ltd.

 

 

 

 

Figure 11-6: Histogram and log probability plots for the chalcocite enrichment LG Sub-Domain

 

 

 

Figure 11-7: Histogram and log probability plots for the exotic Cu LG Sub-Domain

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
117Nordmin Engineering Ltd.

 

 

11.4Data Preparation

 

 

Prior to grade estimation, the data was prepared in the following matter:

 

All drill hole assays that intersected a wireframe within each domain were assigned a set of codes representative of the domain, wireframe number, and mineralization type.

 

The raw assay data was manually “flagged” to intersecting Cu mineralization sub-domains outlined by the wireframe coding process.

 

HG outlier assays in each domain were reviewed, and if needed, a top cut was applied (capped).

 

11.4.1Non-assayed Assay Intervals

 

Table 11-8 summarizes the drill holes used in the resource model. The assay database provided to Nordmin by IVNE contained appropriately substituted minimum detection assay values.

 

Table 11-8: Assays at Minimum Detection

 

Field Count Minimum Detection Limit Count at Minimum Detection Limit % at Minimum Detection Limit
Cu Total (%) 33,247 0.01 71 0.21
Acid Soluble Cu (%) 10,941 0.005 171 1.56
Cyanide Soluble Cu (%) 2,297 0.005 111 4.83
Mo (%) 7,307 0.001 3,066 41.9

 

11.4.2Outlier Analysis and Capping

 

Grade outliers that are much higher than the general population of assays have the potential to bias (inflate) the quantity of metal estimated in a block model. Geostatistical analysis using XY scatter plots, cumulative probability plots, and decile analysis was used by Nordmin to analyze the raw drill hole assay data for each domain to determine appropriate grade capping. Statistical analysis was performed independently on all domains. After capping, the resulting change to the overall mean grades is insignificant at the Santa Cruz deposit. Cap values and theoretical metal loss are described in Table 11-9.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
118Nordmin Engineering Ltd.

 

 

Table 11-9: Santa Cruz Domain, Outlier Analysis, and Capping

 

  Sub-domain Field Number of Samples Number of Capped Samples Min Max Uncapped Average Capped Average Capped Value Theoretical Metal Loss (%)
Cu Oxide Enrichment LG T_Cu 1,083 - 0.000 2.230 0.392 - - -
AS_Cu 610 - 0.003 1.850 0.413 - - -
CN_Cu 138 - 0.007 2.290 0.544 - - -
Mo (%) 321 - 0.000 0.057 0.009 - - -
HG T_Cu 802 - 0.005 10.100 2.250 -   -
AS_Cu 764 - 0.003 8.400 1.810 - - -
CN_Cu 299 - 0.003 9.950 1.030 - - -
Mo (%) 394 1 0.000 0.233 0.014 0.014 0.150 0.800
Primary Cu LG T_Cu 2,241 1 0.005 1.930 0.547 0.547 1.500 0.040
AS_Cu 2,122 - 0.001 0.960 0.050 - - -
CN_Cu 280 - 0.007 1.860 0.445 - - -
Mo (%) 639 - 0.000 0.115 0.012 - - -
MG T_Cu 1,042 3 0.01 5.200 0.934 0.929 3.000 0.500
AS_Cu 1,016 - 0.001 1.190 0.099 - - -
CN_Cu 372 - 0.008 2.180 0.712 - - -
Mo (%) 452 - 0.000 0.100 0.016 - - -
HG T_Cu 244 - 0.29 11.650 2.094 - - -
AS_Cu 243 - 0.003 1.230 0.189 - - -
CN_Cu 115 1 0.111 11.030 2.085 2.076 9.000 0.400
Mo (%) 60 2 0.000 0.347 0.037 0.035 0.250 5.400
Chalcocite Enrichment LG T_Cu 440 - 0.000 6.930 0.899 - - -
AS_Cu 415 - 0.001 5.387 0.338 - - -
CN_Cu 405 - 0.006 2.050 0.574 - - -
Mo (%) 241 1 0.000 0.233 0.016 0.016 0.150 1.100
MG T_Cu 437 - 0.02 11.650 1.620 - - -
AS_Cu 430 - 0.02 3.640 0.396 - - -
CN_Cu 431 - 0.01 11.030 1.450 - - -
Mo (%) 168 - 0.000 0.347 0.022 0.021 0.20 3.800
Exotic Cu LG T_Cu 94 - 0.01 2.400 0.737 - - -
AS_Cu 79 - 0.14 2.220 0.773 - - -
CN_Cu   - - - - - - -
Mo (%) 30 - 0.000 0.028 0.005 - - -
HG T_Cu 35 - 1.91 12.600 4.640 - - -
AS_Cu 34 - 0.85 11.700 4.320 - - -
CN_Cu - - - - - - - -
Mo (%) 21 - 0.000 0.014 0.005 - - -

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
119Nordmin Engineering Ltd.

 

 

11.4.3Compositing

 

Compositing of assays is a technique used to give each assay a relatively equal length and therefore reduce the potential for bias due to uneven assay lengths; it prevents the potential loss of assay data and reduces the potential for grade bias due to the possible creation of short and potentially HG composites that tend to be situated along the edge of a wireframe contact when using a fixed length.

 

The raw assay data was found to have a relatively narrow range of assay lengths. Assays captured within all wireframes were composited to 3.0 m regular intervals based on the observed modal distribution of assay lengths, which supports a 5.0 m x 5.0 m x 5.0 m block model (with sub-blocking). An option to use a slightly variable composite length was chosen to allow for backstitching shorter composites that are located along the edges of the composited interval. All composite assays were generated within each mineral lens with no overlaps along boundaries. The composite assays were validated statistically to ensure there was no loss of data or change to the mean grade of each assay population (Table 11-10).

 

Table 11-10: Santa Cruz Deposit Composite Analysis

 

Domain Sub-domain Number of Composites
Primary LG 3,454
MG 1,007
HG 194
Oxide LG 3,170
HG 635
Chalcocite Enriched LG 855
MG 382
Exotic LG 129
HG 29
Background n/a 5,375

 

11.4.4Specific Gravity

 

A total of 266 SG measurements from four diamond drill holes exist from the Santa Cruz deposit. Measurements were calculated using the weight in air versus the weight in water method (Archimedes), by applying the following formula:

 

 

 

Nordmin determined that the required amount and distribution of SG measurements did not allow for direct estimation of SG within the block model. SG values were assigned to blocks based on lithology as seen in Table 7-6.

 

To summarize, SG values were assigned as follows:

 

Granodiorite and quartz monzonite were attributed an SG value of 2.552.

 

Oracle Granite was attributed an SG value of 2.500.

 

Technical Report Summary – December 17, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
120Nordmin Engineering Ltd.

 

 

11.4.5Block Model Strategy and Analysis

 

A series of upfront test modelling was completed to define an estimation methodology to meet the following criteria:

 

Representative of the Santa Cruz deposit geological and structural controls.
Accounts for the variability of grade, orientation, and continuity of mineralization.
Controls the smoothing (grade spreading) or grades and the influence of outliers.
Accounts for most of the mineralization within the Santa Cruz deposit.
Is robust and repeatable within the mineral domains.
Supports multiple domains.

 

Multiple test scenarios were evaluated to determine the optimum processes and parameters to use to achieve the stated criteria. Each scenario was based on Nearest Neighbour (NN), inverse distance squared (ID2), inverse distance cubed (ID3), and ordinary kriging (OK) interpolation methods.

 

All test scenarios were evaluated based on global statistical comparisons, visual comparisons of composite assays versus block grades, and the assessment of overall smoothing. Based on the results of the testing, it was determined that the final resource estimation methodology would constrain the mineralization by using hard wireframe boundaries to control the spread of mineralization. OK was selected as the interpolation method best representative of the Santa Cruz deposit.

 

11.4.6Assessment of Spatial Grade Continuity

 

Datamine and Sage 2001 was used to determine the geostatistical relationships of the Santa Cruz deposit. Independent variography was performed on composite data for each domain. Experimental grade variograms were calculated from the capped/composited assay data for each element to determine the approximate search ellipse dimensions and orientations.

 

The analyses considered the following for each analysis:

 

Downhole variograms were created and modelled to define the nugget effect.
Experimental pairwise to relative correlogram variograms were calculated to determine directional variograms for the strike and down dip orientations.
Variograms were modelled using an exponential with practical range.
Directional variograms were modelled using the nugget defined in the downhole variography, and the ranges for the along strike, perpendicular to strike, and down dip directions.
Variograms outputs were re-oriented to reflect the orientation of the mineralization.

 

Search parameters were applied using dynamic anisotropy for exotic Cu. Dynamic anisotropy interpolation is an estimation method used in conjunction with “normal” estimation interpolation methods (NN, ID, OK, etc.), which takes into consideration the local variation of the domain orientation in the block estimation. Practically, this involves in a per block inclusion and modification of the search parameters. This generally results in a lower number of search ellipsoids.

 

Six search ellipsoids were applied to estimation, one for each type of Cu mineralization, including two for Cu-oxide mineralization (HG, LG), and background (primary supergene, secondary Cu-oxide (HG, LG), exotic Cu, chalcocite, and background). The search parameters used for the estimation are provided in Section 14.4.9. Some domains share variography parameters due to similar behaviour. The variography used for Santa Cruz is provided in Table 11-11. Figure 11-8 is the Primary Domain total Cu variogram, Figure 11-9 is the Oxide Domain total Cu variogram, Figure 11-10 is the Oxide Domain acid soluble Cu variogram, Figure 11-11 is the Chalcocite Enriched Domain total Cu variogram and Figure 11-12 is the Exotic Domain total Cu variogram.

 

Technical Report Summary – December 17, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
121Nordmin Engineering Ltd.

 

 

Table 11-11: Santa Cruz Deposit Variography Parameters

 

Domain Element Rotation Angles Structure 1 Structure 2  
1 2 3 Axes Range 1 Range 2 Range 3 C1 Range 1 Range 2 Range 3 C1 Nugget
Primary TCu -12 -11 38 Z-Y-Z 27.9 249 28.4 0.26 300 1,430 170 0.09 0.64
ASCu 1 32 -39 Z-Y-Z 26.9 38.1 48.6 0.26 98 2,844 50 0.45 0.27
CNCu -78 -9 34 Z-Y-Z 6.4 33 24.2 0.72 370 91 61 0.18 0.72
Oxide TCu -75 33 -15 Z-Y-Z 24.3 46.9 27.2 0.56 920 79 87 0.08 0.35
ASCu -20 -41 9 Z-Y-Z 28 23.9 23.7 0.59 898 86 81 0.14 0.27
CNCu 22 62 32 Z-Y-Z 6.1 8.3 15.1 0.05 40 272 34 0.50 0.44

Chalcocite

Enriched

TCu -3 20 -31 Z-Y-Z 8.5 39.9 24.5 0.51 1,876 111 115 0.42 0.06
ASCu -55 -70 92 Z-Y-Z 30.4 10.3 54.7 0.72 382 90 154 0.72 0.16
CNCu -55 19 14 Z-Y-Z 7.8 24.7 25.2 0.56 2,521 87 76 0.43 0.006
Exotic TCu 4 45 -53 Z-Y-Z 35.5 34.6 38.4 0.63 34.7 69.6 65 0.34 0.2
ASCu -43 48 -34 Z-Y-Z 33.3 34.8 34.7 0.56 33.6 99.2 63.3 0.41 0.029
CNCu -78 -9 34 Z-Y-Z 6.4 33 24.2 0.72 370 91 61 0.18 0.09
Background TCu -33 6 -7 Z-Y-Z 35.5 17.3 62.4 0.24 1,067 544 336 0.48 0.28
ASCu 10 1 21 Z-Y-Z 32.5 20.8 502 0.44 1,689 392 232 0.31 0.24
CNCu -130 2 -29 Z-Y-Z 23.9 31.2 86.1 0.35 428 804 337 0.34 0.30

 

Technical Report Summary – December 17, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
122Nordmin Engineering Ltd.

 

 

 

 

 

Figure 11-8: Primary Domain total Cu variogram

 

 

 

Figure 11-9: Oxide Domain total Cu variogram

 

Technical Report Summary – December 17, 2021123Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-10: Oxide Domain acid soluble Cu variogram

 

 

 

Figure 11-11: Chalcocite Enriched Domain Total Cu Variogram

 

Technical Report Summary – December 17, 2021124Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-12: Exotic Domain Total Cu Variogram

 

11.4.7Block Model Definition

 

The block model shape and size are typically a function of the geometry of the deposit, the density of assay data, drill hole spacing, and the selected mining unit. Taking this into consideration, the block model was defined with parent blocks at 5.0 m x 5.0 m x 5.0 m (N-S x E-W x Elevation). The block model prototype parameters are listed in Table 11-12.

 

Table 11-12: Santa Cruz Deposit Block Model Definition Parameters

 

Item Block Origin
(m)
Block Max
(m)
Block Dimension
(m)
Number of
Parent Blocks
Minimum Sub-
Block (m)
Easting 414,200 421,500 5 1,460 1.25
Northing 3,637,800 3,644,800 5 1,400 1.25
Elevation -1,200 500 5 340 1.25

 

All mineral Sub-domain wireframe volumes were filled with blocks using the parameters described in Table 11-12. Block volumes were compared to the mineral Sub-domain wireframe volumes to confirm there were no significant differences. Block volumes for all sub-domains were found to be within reasonable tolerance limits for all mineral Sub-domain volumes. Sub-blocking was allowed to maintain the geological interpretation and accommodate the HG, MG, and LG sub-domains (wireframes), the lithological SG, and the category application. Sub-blocking has been allowed to the following minimums:

 

·5.0 m x 5.0 m x 5.0 m blocks are sub-blocked two-fold to 1.25 m x 1.25 m in the N to S and E to W directions with a variable elevation calculated based on the other sizes.

 

Technical Report Summary – December 17, 2021125Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

The block models were not rotated, and it was not necessary to clip them to topography due to their depth. The resource estimation was conducted using Datamine Studio RMTM version 1.7.100.0 within the NAD 83 UTM Zone 12 N projection grid.

 

11.4.8Interpolation Method

 

The Santa Cruz deposit block model was estimated using NN, ID2 (inverse distance to the power of 2), ID3 (inverse distance to the power of 3), and OK (Ordinary Kriging) interpolation methods for global comparisons and validation purposes. The OK method was used for the Mineral Resource Estimate; it was selected over ID2, ID3, and NN as the OK method was the most representative approach to controlling the smoothing of grades.

 

11.4.9Search Strategy

 

Zonal controls were used to constrain the grade estimates to within each LG, MG, and HG wireframe. These controls prevented the assays from individual domain wireframes from influencing the block grades of one another, acting as a “hard boundary” between the sub-domains. For instance, the composites identified within the BG total Cu wireframe were used to estimate the BG total Cu, and all other composites were ignored during the estimation. A “soft boundary” was used in all other Sub-domain wireframes. For example, a LG wireframe was allowed to use composites from the MG wireframe to help populate the block model; the low grade primary total Cu composites included composites from both the low and medium grade flagging. These soft boundaries are as follows (in the case where no MG Sub-domain exists, the HG composites were substituted):

 

·BG: No soft boundary

·LG: Soft boundary with MG composites

·MG: Soft boundary with HG composites

·HG: No soft boundary

 

Search orientations were used for estimation of the block model and were based on the shape of the modelled mineral domains (Table 11-15). A total of three nested searches were performed on all sub-domains. The search distances were based upon the variography ranges outlined in Table 11-11. The search radius of the first search was based upon the first structure of the variogram, the second search is approximately two times the first search pass, and the third search pass is 1.5 times the initial search. Search strategies for each domain used an elliptical search with a minimum, and a maximum number of composites defined in estimated blocks were left as absent and not reported in the Mineral Resource Estimate.

 

Technical Report Summary – December 17, 2021126Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Table 11-13: Santa Cruz Deposit Block Model Search Parameters

 

  Search Distances Search Rotation      
Domain Dist 1 Dist 2 Dist 3 Angle 1 Angle 2 Angle 3 Axis 1 Axis 2 Axis 3
Primary (LG/MG/ HG) 27.9 100 28.4 -12 -11 38 3 2 3
Oxide LG 24.3 46.9 27.2 -80 33 -60 3 2 3
Oxide HG 24.3 46.9 27.2 -75 33 -15 3 2 3
Chalcocite (LG/MG) 8.5 39.9 24.5 -3 20 -31 3 2 3
Exotic (LG/HG) 60 80 10 60 25 10 3 1 3
Background 35.5 17.3 62.4 -33 6 -7 3 2 3

 

11.5Block Model Validation

 

The block model validation process included visual comparisons between block estimates and composite grades in plan and section views, local versus global estimates for NN, ID2, ID3, and OK, and swath plots. Block estimates were visually compared to the drill hole composite data in all domains and corresponding sub-domains to ensure agreement. A non-material bias was noted in the lower grade cyanide soluble Cu cut-off within the Chalcocite Enriched Domain Estimated OK values for cyanide soluble Cu are notably higher than NN, ID2, and ID3 values. An analysis led to the following conclusion:

 

·A lack of sufficient cyanide soluble Cu lab assays.

·The variography of the cyanide soluble Cu within the Chalcocite Enriched Domain is oriented notably different than the search used for estimating NN, ID2, and ID3). Figure 11-13 demonstrates the estimation orientation differences, as well as the OK variography ellipsoid.

 

While this bias is notable, it has been determined that the OK estimation is accurately estimating grade within the Chalcocite Enriched Domain, while the NN, ID2, and ID3 estimations are under-representing the cyanide soluble Cu grade.

 

Technical Report Summary – December 17, 2021127Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-13: Cross-section outlining the analysis of cyanide soluble Cu estimation within the Chalcocite Enriched Domain

 

11.5.1Visual Comparison

 

The validation of the interpolated block model was assessed by using visual assessments and validation plots of block grades versus capped assay grades and composites. The review demonstrated a good comparison between local block estimates and nearby samples without excessive smoothing in the block model.

 

Figure 11-14 through Figure 11-22 are the block model validation images, displaying total Cu, acid soluble Cu, or cyanide soluble Cu grades in the block model and drill holes. Visual block model validation images, including Au, Cu, and Ag, are available in Appendix D.

 

Technical Report Summary – December 17, 2021128Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-14: Block model validation, total Cu, cross-section

 

Technical Report Summary – December 17, 2021129Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-15: Block model validation, acid soluble Cu, cross-section

 

Technical Report Summary – December 17, 2021130Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-16: Block model validation, cyanide soluble Cu, cross-section

 

Technical Report Summary – December 17, 2021131Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-17: Block model validation, total Cu, cross-section

 

Technical Report Summary – December 17, 2021132Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

 

Figure 11-18: Block model validation, acid soluble Cu, cross-section

 

Technical Report Summary – December 17, 2021133Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-19: Block model validation, cyanide soluble Cu, cross-section

 

Technical Report Summary – December 17, 2021134Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-20: Block model validation, total Cu, cross-section

 

Technical Report Summary – December 17, 2021135Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-21: Block model validation, acid soluble Cu, cross-section

 

Technical Report Summary – December 17, 2021136Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-22: Block model validation, cyanide soluble Cu, cross-section

 

11.5.2Swath Plots

 

A series of swath plots were generated for total Cu, acid soluble Cu, and cyanide soluble Cu from slices throughout each domain. They compare the block model grades for NN, ID2, ID3, and OK to the drill hole composite grades to evaluate any potential local grade bias. A review of the swath plots did not identify bias in the model that is material to the Mineral Resource Estimate, as there was a strong overall correlation between the block model grade and the capped composites used in the Mineral Resource Estimate. Figure 11-23, Figure 11-24, and Figure 11-25 are the swath plots for total Cu, acid soluble Cu, and cyanide soluble Cu.

 

Technical Report Summary – December 17, 2021137Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 11-23: Swath plots, total cu

 

 

Figure 11-24: Swath plots, acid soluble cu

 

Technical Report Summary – December 17, 2021138Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 11-25: Swath plots, cyanide soluble cu

 

Technical Report Summary – December 17, 2021139Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

11.6Mineral Resource Classification

 

The Mineral Resource Estimate was classified in accordance with S-K 1300. Mineral Resource classifications were assigned to broad regions of the block model based on the Nordmin QP’s confidence and judgment related to geological understanding, continuity of mineralization in conjunction with data quality, spatial continuity based on variography, estimation pass, data density, and block model representativeness.

 

Classification (Indicated and Inferred) was applied to the Santa Cruz deposit based on a full review that included the examination of drill spacing, visual comparison, kriging variance, and search volume estimation (the estimation pass in which each block was populated) along with the search ellipsoid ranges. Collectively this information was used to manually construct wireframes to further limit the mineral resource classification.

 

Figure 11-26, Figure 11-27, and Figure 11-28 demonstrate the resource classification in section throughout the Santa Cruz deposit. Additional figures can be found in Appendix E.

 

The areas of greatest uncertainty are attributed to Inferred Resources. These are areas with limited drilling or very large drill spacing (>100 m). Due to lack of drilling it is difficult to be confident in the continuity of mineralization and is therefore classified as Inferred and may be upgraded via infill drilling to support mineralization continuity. Indicated Resources are resources that have consistent drill spacing, low to moderate kriging variance and a visual comparison. In the Santa Cruz deposit the drill spacing that supports the Indicated Resource classification constitutes approximately 80 m to 100 m. There is the possibility for Indicated Resources to be upgraded to Measured Resources via additional infill drilling that would reduce the drill spacing to <25 m. Currently the Santa Cruz deposit does not have a Measured Resource. Additional uncertainty lies in the historical drill measurements including logging, assaying and surveying. The 2021 twin drilling program conducted by IVNE outlined in Section 7.4.3 and Section 9.1.4 has demonstrated overall grade continuity, location and continuity between intercepts. There is the potential for unknown errors within the database which could affect the size and quantity of Measured, Indicated and Inferred Mineral Resources.

 

 

 

Figure 11-26: Plan section demonstrating resource classification, -260 m depth

 

Technical Report Summary – December 17, 2021140Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-27: Plan section demonstrating resource classification, -475 m depth

 

Technical Report Summary – December 17, 2021141Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

 

Figure 11-28: Vertical section displaying resource classification

 

11.7Copper Pricing

 

11.7.1Global Refined Copper Consumption and Production

 

World usage of refined Cu has more than tripled in the last 50 years thanks to expanding sectors such as electrical and electronic products, building construction, industrial machinery and equipment, transportation equipment, and consumer, and general products. Because of its properties, Cu has become a major industrial metal, ranking third after Fe, and aluminum in terms of quantities consumed.

 

As noted in the International Copper Study Group (“ICSG”) 2020 Copper Factbook, since 1900 when world production was less than 500 thousand tonnes Cu world mine production has grown by 3.2% per annum to 20.5 million tonnes in 2019. In fact, more than 97% of all Cu ever mined and smelted has been extracted since 1900.

 

Technical Report Summary – December 17, 2021142Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Global demand for Cu is expected to grow at 1.3% compound annual growth rate (“CAGR”) over the next five years. In the short term, the Cu market balance is expected to turn into a surplus, though in order to reach the future demand, more investments are needed in expansions and new projects.

 

Although Cu demand scenarios differ among analysts, there is a general agreement that the major driver for increased Cu demand will come from infrastructure investments associated with energy transitions.

 

The International Energy Agency (“IEA”) recently published a comprehensive report titled “The Role of Critical Materials in Clean Energy Transitions”. The IEA notes that the shift to clean energy naturally involves burning less fuel but building more equipment. Since 2010 the average amount of minerals needed for a new unit of power generation capacity has increased by 50%, with an onshore wind facility requiring nine times more Mineral Resources than a gas-fired plant of the same capacity. Clean energy rollout requires significant electrical network expansion. The IEA estimates an annual average grid expansion and replacement of approximately 3,600 thousand km by 2040. This translates to 7,613 kt of Cu demand in 2040. The IEA also predicts Cu demand from renewables will increase 108% to 1,289 kt Cu by 2040, 94% of which will come from solar photovoltaic and wind. The report details a tripling of solar photovoltaic deployment by 2040, driven by growth in emerging economies, which equates to the addition of just under 645 kilotonnes per annum (“ktpa”) of Cu demand from this energy type by the end of 2040 (Figure 11-29).

 

 

Figure 11-29: Global copper demand 2000-2040

 

11.7.2Copper Prices

 

Cu prices, in theory, correlate to the supply and demand of refined Cu. However economic policy, geopolitical events, wars, black swan events like the COVID-19 pandemic and the development of financial derivatives and associated market speculation has contributed to the volatility in prices. While the recent price has reached a historic high in nominal terms, this is not the case in real terms.

 

Cu price is dynamic. The graph in Figure 11-30 provides some explanation of the variability of the price over the last century, and while history does not necessarily provide the answer to the future Cu price, it can provide prognosticators with various factors which are monitored to fine tune their forecasts of the forward Cu price.

 

Technical Report Summary – December 17, 2021143Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

Figure 11-30: A century of Cu prices

 

There will always be differing views of what the future holds in terms of price based on analysis and assumptions. With a number of significant mining operations due to come on-line in the next one to two years, many analysts are forecasting a decline in prices from the current highs (Table 11-14).

 

Technical Report Summary – December 17, 2021144Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Table 11-14: Consensus Copper Pricing 2021-2024 

 

Copper (US$/lb)       November 30, 2021
Date Firm 2021 2022 2023 2024 Long Term
19-Nov-21 CIBC $4.46 $4.75 $3.75 $3.55 $3.30
19-Nov-21 Deutsche Bank $4.22 $4.28 $3.74 $3.77 $3.63
15-Nov-21 BAML $4.24 $4.48 $4.31 $4.04 $3.09
15-Nov-21 BMO $4.09 $3.48 $3.01 $3.35 $3.25
15-Nov-21 Canaccord $4.19 $4.25 $4.00 $4.25 $3.30
15-Nov-21 Credit Suisse $4.25 $3.40 $3.20 $3.30 $3.50
15-Nov-21 Desjardins $4.32 $4.73 $4.10 $4.10 $4.10
15-Nov-21 Morgan Stanley $4.16 - - - $2.82
15-Nov-21 Raymond James $4.16 $3.75 $3.50 $3.50 $3.50
15-Nov-21 Scotia $4.15 $4.25 $4.25 $4.50 $3.25
14-Nov-21 National Bank $4.21 $4.30 $3.75 $3.75 $3.30
13-Nov-21 Jefferies $4.13 $4.50 $5.50 $6.00 $3.25
12-Nov-21 Societe Generale $4.20 $3.63 $4.31 $4.99 -
10-Nov-21 Eight Capital $4.37 $3.75 $3.50 $3.50 $3.50
09-Nov-21 RBC $4.12 $3.75 $3.50 $3.50 $3.50
08-Nov-21 Paradigm $4.21 $4.00 $4.00 $3.50 $3.50
05-Nov-21 HSBC $4.16 $3.95 $3.60 $3.50 $3.00
05-Nov-21 JP Morgan $4.14 $3.83 $3.27 - $3.30
04-Nov-21 Haywood $4.19 $4.15 $4.15 $4.15 $4.15
03-Nov-21 Stifel $4.20 $3.75 $3.75 $3.75 $3.75
22-Oct-21 Cormark $4.05 $3.75 $3.50 $3.50 $3.50
20-Oct-21 TD $4.22 $4.00 $3.50 $3.35 $3.50
08-Oct-21 Barclays $4.15 $3.55 $2.85 - $3.00
07-Oct-21 Berenberg $4.14 $3.94 $3.86 $3.86 $3.22
06-Oct-21 BNP Paribas $4.17 $4.08 $4.04 - $3.63
05-Oct-21 UBS $4.12 $3.50 $3.30 $3.30 $3.00
             
Average $4.19 $3.99 $3.77 $3.86 $3.39

 

Source: CIBC Mining Markets

 

Technical Report Summary – December 17, 2021145Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Beyond 2024, the supply demand gap is expected to widen leading to higher Cu prices (Figure 11-31).

 

 

Figure 11-31: Projected mine supply demand to 2040

 

11.7.3Commodity Price Projections

 

Project economics were estimated based on a long term copper price of US$ 3.70/lb.

 

11.8Reasonable Prospects of Eventual Economic Extraction

 

The Mineral Resource was created using Datamine Studio RMTM version 1.7.100.0 software to create the block models for the Santa Cruz deposit, and Deswik.CADTM 2022.1 and Deswik.SOTM 4.1 for stope optimization.

 

To demonstrate reasonable prospects for eventual economic extraction for the Santa Cruz Mineral Resource Estimate, representational minimum mining unit shapes were created using Deswik’s minimum mining unit shape optimizer (MSO) tool. This MSO tool constrains and evaluates the block model based on economic and geometric parameters, shown in Table 11-15, generating potentially mineable shapes. The deposit was assumed to be developed as a long-life operation consisting of an underground bulk mining plan, with an initial mining rate of 40,000 tonnes/day to produce a Cu concentrate. The Mineral Resource Estimate comprises of all material found within the MSO wireframes generated at a cut-off of 0.39% Cu, including material below cut-off.

 

Technical Report Summary – December 17, 2021146Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Table 11-15: Input Parameter Assumptions

 

Parameter Value Unit
Cu Price 3.701 US$/lb
Payable Cu 97 %
Payable Cu Price 3.59 US$/Tonne Proc.
Mining Cost 7.50 US$/Tonne Proc.
Processing Cost 6.00 US$/Tonne Proc.
Water Treatment and Disposal 1.00 US$/Tonne Proc.
G&A Cost 3.33 US$/Tonne Proc.
Cathode Shipping 24.76 US$/Tonne Cathode
Royalties 6.5 %
Mining Recovery 100 %
Mining Dilution 0 %
Process Recoveries Cu 80 %
Cu In Situ Mineral Resource CoG 0.35 %

 

1 See Section 11.7 for Copper Pricing Assumptions and Justification

 

11.9Mineral Resource Estimate

 

Due to a lack of sample data as well as a bias in sampling for acid soluble Cu and cyanide soluble Cu within the Primary Domain, it was determined that the acid soluble Cu and cyanide soluble Cu estimation within the Primary Domain was not representative of the actual cyanide soluble Cu within the domain and has been removed from all reports and totals. Acid soluble Cu and cyanide soluble Cu was determined to be accurate within the Exotic Domain, Oxide Domain, and Chalcocite Enriched Domain.

 

Technical Report Summary – December 17, 2021147Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

The Santa Cruz deposit Mineral Resource Estimate is presented in Table 11-16.

 

Table 11-16: Santa Cruz Deposit Mineral Resource Estimate, 0.39% Total Cu CoG

 

Domain

Resource

 

Category

 

Kilotonnes kt Total Cu % Total Soluble Cu % Acid  Soluble Cu % Cyanide Soluble Cu % Total Cu kt Total Soluble Cu kt Acid Soluble Cu kt Cyanide Soluble Cu kt
Exotic Indicated 6,989 1.05 0.80 0.73 0.07 73 56 51 5
Inferred 11,680 1.28 1.00 0.98 0.02 149 118 115 3
Oxide Indicated 52,990 1.34 1.27 0.98 0.29 708 669 518 151
Inferred 126,138 1.06 1.00 0.71 0.29 1,336 1,253 892 361
Chalcocite Enriched Indicated 29,145 1.25 1.13 0.40 0.73 364 328 115 213
Inferred 14,838 1.36 1.28 0.52 0.76 202 191 78 113
Primary Indicated 184,877 0.75 n/a n/a n/a 1,394 n/a n/a n/a
Inferred 96,098 0.59 n/a n/a n/a 568 n/a n/a n/a
TOTAL
  Indicated 274,000 0.93 0.38 0.25 0.13 2,539 1,053 684 369
  Inferred 248,754 0.91 0.63 0.44 0.19 2,255 1,563 1,085 478

 

Notes on Mineral Resources

 

1.The Mineral Resources in this estimate were independently prepared by Nordmin Engineering Ltd and the Mineral Resources were prepared in accordance S-K 1300. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. No environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues are known that may affect this estimate of Mineral Resources.

2.Verification included multiple site visits to inspect drilling, logging, density measurement procedures and sampling procedures, and a review of the control sample results used to assess laboratory assay quality. In addition, a random selection of the drill hole database results was compared with original records.

3.The Mineral Resources in this estimate for the Santa Cruz deposit used Datamine Studio RMTM software to create the block models.

 

Technical Report Summary – December 17, 2021148Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

4.The sensitivity of the Mineral Resources have an effective date of December 8, 2021.

5.Underground Mineral Resources are reported at a CoG of 0.39% Total Cu, which is based upon a Cu price of US$$3.70/lb and a Cu recovery factor of 80%. See Section 11.7 for Cu pricing assumptions and justification.

6.SG was applied using weighted averages by lithology.

7.All figures are rounded to reflect the relative accuracy of the estimates, and totals may not add correctly

8.Excludes unclassified mineralization located along edges of the Santa Cruz deposit where drill density is poor

9.Report from within a mineralization envelope accounting for mineral continuity

10.Acid soluble Cu and cyanide soluble Cu are not reported for the Primary Domain.

 

11.10Mineral Resource Sensitivity to Reporting Cut-off

 

he updated Santa Cruz deposit Mineral Resource Estimate to a Cu (%) cut-off is summarized in Table 11-17 across all interpolation methods.

 

Table 11-17: Mineral Resource Sensitivity for Total Cu

 

Resource Category

Cut-Off

Total Cu %

Tonnes

Total Cu

%

Acid Soluble Cu % Cyanide Soluble Cu % Total Cu Tonnes Acid Soluble Cu Tonnes Cyanide Soluble Cu Tonnes
Indicated 0.15 314,273,007 0.85 0.23 0.12 2,686,651 712,0990 383,669
Inferred 0.15 533,663,405 0.58 0.23 0.10 3,106,552 1,215,144 533,071
Indicated 0.30 283,328,659 0.92 0.25 0.13 2,616,190 695,802 376,862
Inferred 0.30 322,817,980 0.82 0.36 0.16 2,640,301 1,148,266 511,241
Indicated 0.35 271,312,798 0.95 0.25 0.14 2,577,188 689,348 374,520
Inferred 0.35 265,823,077 0.92 0.42 0.19 2,455,978 1,122,809 502,656
Indicated 0.50 219,131,684 1.07 0.30 0.17 2,353,684 668,114 364,050
Inferred 0.50 174,941,611 1.19 0.60 0.27 2,080,315 1,050,293 472,372
Indicated 0.80 117,239,321 1.46 0.52 0.28 1,709,776 610,282 322,538
Inferred 0.80 98,139,965 1.63 0.90 0.40 1,598,724 879,141 393,015
Indicated 1.00 83,359,021 1.69 0.68 0.33 1,407,930 568,069 272,262
Inferred 1.00 74,106,551 1.87 1.08 0.46 1,383,711 801,363 344,161
Indicated 2.00 22,872,137 2.58 1.37 0.57 590,080 312,528 130,458
Inferred 2.00 28,098,868 2.66 1.72 0.63 748,727 483,315 178,079

 

11.11Interpolation Comparison

 

Global statistical comparisons between the composite samples, NN estimates, ID2 estimates, ID3 estimates, and OK for various cut-off grades were compared to assess global bias, where the NN model estimates represent de-clustered composite data. Clustering of the drill hole data can result in differences between the global means of the composites and NN estimates.

 

The OK method was used as the reporting estimation interpolation method, while NN, ID2, and ID3 were also calculated for validation purposes, as described in Section 14.5.

 

Technical Report Summary – December 17, 2021149Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Table 11-18 demonstrates the total Cu interpolation comparison across OK, ID2, ID3, and NN interpolation methods.

 

Table 11-18: Interpolation Comparison

 

Cut-Off

Total Cu %

Total Cu

OK

Total Cu

ID2

Total Cu

ID3

Total Cu

NN

Acid Soluble Cu

OK

Acid Soluble Cu

ID2

Acid Soluble Cu

ID3

Acid Soluble Cu

NN

Cyanide Soluble Cu

OK

Cyanide Soluble Cu

ID2

Cyanide Soluble Cu

ID3

Cyanide Soluble Cu

NN

0.15 0.85 0.68 0.68 0.69 0.23 0.23 0.23 0.22 0.11 0.11 0.11 0.10
0.30 0.87 0.86 0.86 0.88 0.30 0.31 0.31 0.30 0.15 0.17 0.16 0.15
0.35 0.93 0.92 0.92 0.95 0.33 0.33 0.33 0.33 0.16 0.16 0.16 0.15
0.50 1.17 1.16 1.16 1.18 0.50 0.50 0.51 0.49 0.25 0.25 0.24 0.22
0.80 1.57 1.55 1.55 1.58 0.75 0.76 0.76 0.75 0.36 0.37 0.35 0.32
1.00 1.80 1.78 1.78 1.81 0.93 0.93 0.94 0.93 0.42 0.42 0.41 0.36
2.00 2.64 2.61 2.60 2.66 1.60 1.62 1.62 1.62 0.62 0.62 0.60 0.55

 

Technical Report Summary – December 17, 2021150Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

11.12Factors That May Affect the Mineral Resources

 

Areas of uncertainty that may materially impact the Mineral Resource Estimates include:

 

changes to long term metal price assumptions;

changes to the input values for mining, processing, and G&A costs to constrain the estimate;

changes to local interpretations of mineralization geometry and continuity of mineralized sub-domains;

changes to the density values applied to the mineralized zones;

changes to metallurgical recovery assumptions;

changes in assumptions of marketability of the final product;

variations in geotechnical, hydrogeological and mining assumptions;

changes to assumptions with an existing agreement or new agreements;

changes to environmental, permitting, and social license assumptions; and

Logistics of securing and moving adequate services, labour, and supplies could be affected by epidemics, pandemics and other public health crises, including COVID-19, or similar such viruses.

 

11.13Nordmin’s QP Opinion

 

Nordmin is not aware of any environmental, legal, title, taxation, socio to economic, marketing, political or other relevant factors that would materially affect the estimation of Mineral Resources that are not discussed in this Technical Report.

 

Nordmin is of the opinion that the Mineral Resources were estimated using industry accepted practices and conforms to the 2014 CIM Definition Standards and 2019 CIM Best Practice Guidelines. Technical and economic parameters and assumptions applied to the Mineral Resource Estimate are based on parameters received from IVNE and reviewed within the Nordmin technical team to determine if they were appropriate.

 

Technical Report Summary – December 17, 2021151Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

12MINERAL RESERVE ESTIMATES

 

This section is not relevant to this Technical Report.

 

13MINING METHODS

 

This section is not relevant to this Technical Report.

 

14PROCESSING AND RECOVERY METHODS

 

This section is not relevant to this Technical Report.

 

15INFRASTRUCTURE

 

This section is not relevant to this Technical Report.

 

16MARKET STUDIES

 

This section is not relevant to this Technical Report.

 

17ENVIRONMENTAL STUDIES, PERMITTING AND PLANS, NEGOTIATIONS, OR AGREEMENTS WITH LOCAL INDIVIDUALS OR GROUPS

 

This section is not relevant to this Technical Report.

 

18CAPITAL AND OPERATING COSTS

 

This section is not relevant to this Technical Report.

 

19ECONOMIC ANALYSIS

 

This section is not relevant to this Technical Report.

 

Technical Report Summary – December 17, 2021152Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

 

20ADJACENT PROPERTIES

 

20.1Cactus Project

 

The Cactus Project in Pinal County, Arizona, is the primary asset of the Arizona Sonoran Copper Company (ASCU), a pre-production Cu-focused company. The Project includes the past-producing Sacaton open pit mine and stockpile, the Cactus East deposit, and parts of the Parks-Salyer deposit. The 4,300-acre Cactus Project is located on 100% private land, approximately five kilometres (km) northwest of Casa Grande, 9.4 km northeast of IVNE’s Santa Cruz Project, and 65 km south of the city of Phoenix.

 

The Sacaton mineral deposit was discovered by ASARCO geologists in the early 1960s and brought into production in 1972. Open pit mining operated continuously until permanent closure in 1984 and primarily exploited higher-grade enriched sulphide material processed through a typical concentrator processing flowsheet. By the end of its mine life, Sacaton produced an estimated 180,557 tonnes of Cu, 27,455 oz of Au, and 759,000 oz of Ag from a milled resource of 34,610,912 tonnes with head grades of 0.69% Cu, 0.025 g/t Au, and 1.87 g/t Ag. After the ASARCO bankruptcy in 2005, the asset was placed into a Custodial Trust in 2009, tasked with clean up associated with the mining activity. In 2018 Cactus110 LLC, a subsidiary to ASCU, executed both the purchase and the prospective purchase agreements with the trust. The acquisition closed in July 2020 and included the Sacaton land parcels, mineral titles, and remaining infrastructure with no environmental legacy issues.

 

Technical Report Summary – December 17, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
153Nordmin Engineering Ltd.

 

 

ASCU, since the acquisition of the Sacaton project, has completed their initial public offering on the Toronto Stock Exchange and published NI 43-101 compliant resources on the oxide, enriched, and primary sulphide mineralization remaining in the historic stockpile, the historic open pit, and the Cactus East deposit (Table 20-1). Following the updated Resource Estimate, ASCU completed a PEA exploiting the oxide material present in the stockpile resource, the oxide, and enriched material in the Open Pit and Underground resources, excluding primary sulphide material (Table 20-2). The Cactus Project PEA shows a favourable mining operation utilizing conventional Cu heap leach, modular design solvent extraction and electrowinning processing to produce an average of 25,597 tonnes per annum of London Metal Exchange Grade A quality cathode (Table 20-3). ASCU publicly states they are targeting completion of a prefeasibility study in the second half of 2022 and completion of feasibility by the end of 2022, which will lead them into project financing discussions early in 2023.

 

The QP has been unable to verify the geology and mineralization on the adjacent Cactus Project, and mineralization at the Cactus Project is not indicative of the mineralization within the Santa Cruz Project.

 

Technical Report Summary – December 17, 2021154Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Table 20-1: Global Mineral Resource Estimate of the Cactus Project. Source – Arizona Sonoran Copper Company, Inc. Cactus Project, Arizona, USA, PEA, Effective August 31, 2021

 

Mineral Resource Category and Type Tonnes (Kt) CuT (%) Tsol (%) Tsol_lbs (klbs)
Indicated Resources
Oxide 28,487 - 0.559 349,700
Enriched 38,555 - 0.844 715,500
Total Leachable 67,041 - 0.723 1,065,200
Primary 70,670 0.350 - 545,500
Cactus – Total Indicated Resource 137,711 0.531 - 1,610,700
Inferred Resources
Oxide 56,699 - 0.346 430,500
Enriched 49,986 - 0.498 548,800
Total Leachable 106,685 - 0.417 979,300
Primary 100,970 0.349 - 776,000
Cactus – Total Inferred Resource 207,655 0.384 - 1,755,300
Stockpile – Total Inferred Resource 70,216 0.169 0.144 233,500

 

Table 20-2: Resource Estimate Utilized for the PEA. Source – Arizona Sonoran Copper Company, Inc. Cactus Project, Arizona, USA, PEA, Effective August 31, 2021

 

Mining Source Material Type Leach Material (t) Tsol (%) Leachable Cu (t)
Stockpile Project Oxide 74,689,427 0.141 105,487
Open Pit Oxide 42,465,318 0.190 80,684
  Enriched 20,984,090 0.420 88,133
Underground Oxide 5,730,686 1.180 67,378
  Enriched 19,239,574 1.126 249,110
Total Oxide 122,885,431 0.203 249,208
  Enriched 40,223,664 0.822 330,552
  Total 163,109,095 0.355 579,760

 

Table 20-3: Financial Results of the Cactus Project PEA. Source – Arizona Sonoran Copper Company, Inc. Cactus Project, Arizona, USA, PEA, Effective August 31, 2021

 

Financial Results Units Value
Cumulative Cashflow (LOM) US$ million 960
NPV (4%) US$ million 540
NPV (8%) US$ million 312
NPV (10%) US$ million 238
IRR (after-tax) % 33
Payback Years 3.5
Initial Capital Construction Costs US$ million 124

 

Technical Report Summary – December 17, 2021155Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

21OTHER RELEVANT DATA AND INFORMATION

 

This section is not relevant to this Technical Report.

 

Technical Report Summary – December 17, 2021156Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

22INTERPRETATION AND CONCLUSIONS

 

22.1Introduction

 

Nordmin notes the following interpretations and conclusions in their respective areas of expertise, based on the review of data available for this Technical Report.

 

22.2Mineral Tenure, Surface Rights, Royalties, and Agreements

 

The Santa Cruz Project is located 11 km west of the town of Casa Grande, Arizona, and is approximately one hour’s drive south of the capital Phoenix. The centroid is approximately -111.88212, 32.89319 (WGS84) in Township 6 S, Range 4E, Section 13, Quarter C.

 

The Santa Cruz exploration area covers 77.59 km2 including 27.75 km2 of private land, 30.52 km2 of Arizona State Mineral Exploration permits, and 238 unpatented claims, or 19.32 km2 of BLM land.

 

Current exploration is conducted on private land under the SUA with Legend. Disturbance to date has been de minimis and permitting has consisted of filing Notices of Intent to Drill and to Abandon with the Arizona Department of Water Resources for each section of land on which drilling takes place. IVNE will obtain additional permits as required. Specific permits to construct and operate mine facilities would be determined as the design of the Project advances.

 

Existing and past land uses in the Project area and immediately surrounding areas include agriculture, residential home development, light industrial facilities, and mineral exploration, and development. Some dispersed recreation occurs in the area. The climate is dry and most of the Project area is flat, sandy, and sparsely vegetated. Portions of the Project area are in the 100-year flood plain of the North Branch of Santa Cruz Wash. Within the Project area, approximately 85 acres of land located approximately ¾ mile north of the intersection of N. Spike Road and W. Clayton Road was used during an in situ leaching project in 1991. A Phase 1 ESA was conducted on the Project area (Civil & Environmental Consultants 2021).

 

There is a large private land package covering the Project area and area of known mineralization. This private land position could result in reduced permitting time relative to projects that are required to undergo the NEPA process. The precise list of permits required to authorize construction and operation of this Project will be determined as the mining and processing methods are designed. If NEPA and other federal permitting is avoided, required permits would be administered by Arizona State, Pinal County, and Casa Grande authorities.

 

The permit approval process for some permits includes review and approval of the process design. Thus, the project design must be substantially advanced to support application for those permits. These technical permits typically represent the “longest lead” permits. Technical permits with substantial technical design needed as part of their applications, and the issuing agencies are anticipated to include:

 

-Reclamation Plan approval (Arizona State Mine Inspector)

-Water permits

-Aquifer Protection Permit (ADEQ)

-Air Quality Operating Permit (Pinal County)

 

At the effective date of this Technical Report, IVNE held access agreements for diamond drilling. Further permitting will be acquired as necessary.

 

Technical Report Summary – December 17, 2021157Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

22.3Geology and Mineral Resource Modelling

 

The Santa Cruz deposit is a portion of a large porphyry Cu system that has been dismembered and displaced by extensional faulting and exhibits typical characteristics of a porphyry Cu deposit.

 

The geology is dominated by the anorogenic Oracle Granite, diabase sills, and rare dykes. Laramide porphyritic intrusives, and breccias are intruded into the Oracle Granite and diabase sills. These intrusive complexes are associated with discrete high grade hypogene mineralization. The entire Santa Cruz deposit is underlain by the Pinal Schist, which marks the end of mineralization at depth within the Santa Cruz deposit area. There are two key types of Cu mineralization found within the Santa Cruz Project. Supergene mineralization, which represents the highest grades within the Santa Cruz deposit and is dominated by Cu-oxide minerals, and hypogene mineralization which contains primary Cu sulphide minerals. Modelling of the Santa Cruz deposit was split into four main Cu domains which represent different subcategories of Cu mineralization: the Exotic Domain, Oxide Domain, Chalcocite Enriched Domain, and Primary Domain.

 

The Mineral Resource Estimate was created from the main drill hole database containing 104,184 m of diamond drilling in 121 drill holes spanning from 1964 to 2021. Nordmin, through an interactive process with IVNE, examined the historic interpretations of the mineralization to produce the Cu domains. To ensure the accuracy of the interpreted location of mineralized domains IVNE completed five twin diamond drill holes (4,738 m) of historic drill holes in 2021. Nordmin reviewed the assays, lithology, and mineralization to confirm the historic drilling and add to the interpreted mineralization. Once a geologic interpretation was established, wireframes could be created. Detailed wireframing of the domains was completed in section and plan view to give better perspective of the depth and limits of the Cu mineralization. Attention was given to consistent smoothing of the wireframes and ensuring that wireframes followed interpreted geological, and structural trends. Wireframes were constrained by D2 fault structures to the north and south, and mineralization of the Oxide Domain was terminated at the acid soluble Cu boundary; a theoretical layer used to ensure no overlap of primary Cu and oxide Cu wireframes. A block model has been fully validated with no material bias identified. Lithological, structural, and mineralization trends were used in the interpretation and selection of the block modelling parameters. Nordmin feels that the interpreted geological and mineralization domains produced accurately represents the deposit style of the Santa Cruz deposit.

 

22.4Exploration, Drilling, and Analytical Data Collection in Support of Mineral Resource Estimation

 

The exploration programs completed by IVNE, and previous operators are appropriate for the deposit style. The programs delineated the Santa Cruz and Texaco deposits, as well as other mines and deposits along the Santa Cruz-Sacaton Cu trend. Diamond drilling indicates the potential to further define, and potentially expand, on known exploration targets.

 

The quantity and the quality of lithological, collar, and downhole survey data collected in the various exploration programs by various operators are sufficient to support the Mineral Resource Estimate. The collected sampling is representative of total Cu, acid soluble Cu, cyanide soluble Cu, and molybdenum data in the Santa Cruz deposit, reflecting areas of higher, and lower grades. This has been confirmed by 2021 diamond drill hole twinning of historic, high-grade drill holes. It is seen that assays in 2021 drill holes align with historic assays even though samples were taken with higher resolution in 2021, confirming mineralization interpretations. The analytical laboratories used for legacy and current assaying are well known in the industry, produce reliable data, are properly accredited, and are widely used within the industry. Nordmin considers the QA/QC protocols in place for the Project to be acceptable and in line with standard industry practice. Based on the data validation and the results of the standard, blank, and duplicate analyses, Nordmin is of the opinion that the assay and SG databases are of sufficient quality for Mineral Resource Estimation for the Project.

 

Technical Report Summary – December 17, 2021158Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Nordmin is not aware of any drilling, sampling, or recovery factors that could materially impact the accuracy and reliability of the results. In Nordmin’s opinion the drilling, core handling, logging, and sampling procedures meet or exceed industry standards, and are adequate for the purpose of Mineral Resource Estimation.

 

22.5Processing and Metallurgical Testing

 

Mineralized material from the Santa Cruz deposit was evaluated by the CGCC Hanna-Getty JV and by the SCJV in conjunction with the Department of the Interior Bureau of Mines (subsequently Bureau of Reclamation). Currently, IVNE is in the process of developing its own mineral processing and metallurgical test program for the evaluation of the Santa Cruz deposit

 

The Hanna Mining Company, a large miner of iron ore and coking coal, began feasibility studies on the Santa Cruz deposit in 1976. Their studies continued until 1982 and consisted of flotation, grinding, and leaching studies. Tests consisted of all agitated tank leach approach (91% total Cu recovery to cathodes), all-float approach (92% total Cu recovery to cathodes or a mixture of cathodes and saleable Cu concentrates), and a leach float process (94% Cu recovery to cathodes or to a mixture of cathodes and saleable Cu concentrates. Hanna Mining selected the latter of these methods to move forward with. Composite samples were generated for HG supergene, supergene dilution, LG supergene, mixed chalcocite/chalcopyrite, primary chalcopyrite, exotic ore, and exotic dilution ore types. In 1980, ASARCO contracted Mountain States Engineering to evaluate fragmented acid soluble Cu ore versus block caving. Flotation test programs were applied to all the composite samples. The test programs would be acceptable for a PEA level program today, but not for a PFS or FS level study because of the lack of any significant variability flotation testing of the Santa Cruz deposit.

 

BLM, ASARCO, and Freeport McMoRan conducted an in situ sulphuric acid leach study with 2-inch diameter by 2.5-inch-long pieces of diamond drill core from the proposed in situ leach zone in the pilot program. Reported Cu recoveries ranged from 57% to 90%. Total Cu ranged from 2.3% to 9%. The conclusion from this program that was completed in 1996-1997, demonstrated that in situ leaching was not economically practical using the Cu price in 1996 for this type of mineralization. With the increased geological and geochemical understanding of the mineralization, further in situ leaching studies are warranted.

 

There are no processing factors or deleterious elements that could significantly affect economic extraction. Historically proposed processes for the extraction of Cu ore are all conventional in design and have been used economically for many decades. Advances in most technology since the 1980s when these studies were conducted has improved the economics of the proposed methods and could warrant re-visiting them as viable methodology for processing by IVNE in the future.

 

22.6Mineral Resource Estimate

 

The Mineral Resource Estimate for the Project conforms to industry best practices and is reported using the S-K 1300. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. This estimate of Mineral Resources may be materially affected by environmental permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

 

Technical Report Summary – December 17, 2021159Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Mineral Resources were classified into Indicated and Inferred categories based on geological and grade continuity, in conjunction with data quality, spatial continuity based on variography, estimation pass, data density, and block model representativeness, specifically assay spacing and abundance, kriging variance, and search volume block estimation assignment.

 

The Mineral Resource Estimate has been defined based on an applied total Cu (%) CoG to reflect processing methodology and assumed revenue stream from Cu.

 

Resource Estimate is based on an underground mining methodology and surface leach float process to recover cathode Cu or a mixture of cathode Cu and Cu saleable concentrates.

 

The Santa Cruz deposit Mineral Resource Estimate is presented in Table 22-1.

 

Technical Report Summary – December 17, 2021160Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Table 22-1: Santa Cruz Deposit Mineral Resource Estimate, 0.39% Total Cu CoG

 

Domain

Resource

Category

Kilotonnes
kt
Total
Cu %
Total
Soluble
Cu %
Acid
Soluble
Cu %
Cyanide
Soluble
Cu %
Total
Cu kt
Total
Soluble
Cu kt
Acid
Soluble
Cu kt
Cyanide
Soluble
Cu kt
Exotic Indicated 6,989 1.05 0.80 0.73 0.07 73 56 51 5
Inferred 11,680 1.28 1.00 0.98 0.02 149 118 115 3
Oxide Indicated 52,990 1.34 1.27 0.98 0.29 708 669 518 151
Inferred 126,138 1.06 1.00 0.71 0.29 1,336 1,253 892 361
Chalcocite Enriched Indicated 29,145 1.25 1.13 0.40 0.73 364 328 115 213
Inferred 14,838 1.36 1.28 0.52 0.76 202 191 78 113
Primary Indicated 184,877 0.75 n/a n/a n/a 1,394 n/a n/a n/a
Inferred 96,098 0.59 n/a n/a n/a 568 n/a n/a n/a
TOTAL
  Indicated 274,000 0.93 0.38 0.25 0.13 2,539 1,053 684 369
  Inferred 248,754 0.91 0.63 0.44 0.19 2,255 1,563 1,085 478

 

Technical Report Summary – December 17, 2021161Nordmin Engineering Ltd.
Santa Cruz Project, Arizona, USA 
Ivanhoe Electric Inc.  

 

 

Notes on Mineral Resources

 

1.The Mineral Resources in this estimate were independently prepared by Nordmin Engineering Ltd and the Mineral Resources were prepared in accordance with S-K 1300. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. No environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues are known that may affect this estimate of Mineral Resources.

2.Verification included multiple site visits to inspect drilling, logging, density measurement procedures and sampling procedures, and a review of the control sample results used to assess laboratory assay quality. In addition, a random selection of the drill hole database results was compared with original records.

3.The Mineral Resources in this estimate for the Santa Cruz deposit used Datamine Studio RMTM software to create the block models.

4.The Mineral Resources have an effective date of December 8, 2021.

5.Underground Mineral Resources are reported at a CoG of 0.39% Total Cu, that is based upon a Cu price of US$$3.70/lb and a Cu recovery factor of 80%

6.SG was applied using weighted averages by lithology.

7.All figures are rounded to reflect the relative accuracy of the estimates and totals may not add correctly

8.Excludes unclassified mineralization located along edges of the Santa Cruz deposit where drill density is poor

9.Report from within a mineralization envelope accounting for mineral continuity

10.Acid soluble Cu and cyanide soluble Cu are not reported for the Primary Domain.

 

There is a potential to increase the Mineral Resource by using infill drilling to expand and increase the Mineral Resource category.

 

Areas of uncertainty that may materially impact the Mineral Resource Estimate include:

 

·Changes to long term metal price assumptions.

·Changes to the input values for mining, processing, and G&A costs to constrain the estimate.

·Changes to local interpretations of mineralization geometry and continuity of mineralized zones.

·Changes to the density values applied to the mineralized zones.

·Changes to metallurgical recovery assumptions.

·Changes in assumption of marketability of the final product.

·Variations in geotechnical, hydrogeological, and mining assumptions.

·Changes to assumptions with an existing agreement or new agreements.

·Changes to environmental, permitting, and social licence assumptions.

·Logistics of securing and moving adequate services, labour, and supplies could be affected by epidemics, pandemics and other public health crises, including COVID-19, or similar such viruses.

 

These risks and uncertainties may cause delays in economic resource extraction and/or cause the resource to become economically non-viable.

 

22.7Conclusions

 

Under the assumptions presented in this Technical Report, and based on the available data, the Mineral Resource shows reasonable prospects of economic extraction. Exploration activities have shown that the Santa Cruz deposit retains significant potential. Additional infill drilling in the categories of Inferred and Indicated Resource is warranted.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
162Nordmin Engineering Ltd.

 

 

23RECOMMENDATIONS

 

The recommended program is focused on drilling, analytical, metallurgical test work, geological modelling, resource estimation, and environmental baseline studies to support permitting efforts. The recommendations are estimated to require a 2022 budget of $73.7 million.

 

In 2022, IVNE is planning is as follows:

 

·Complete an Initial Assessement

·Infill drill according to guidance from Resource Model and Economic Parameters

·Complete modern metallurgical testing on select holes

·Create a baseline groundwater model based on data obtained from piezometers installed in SCC-001, SCC-004, and SCC-005

·Do baseline environmental work to support future permitting efforts

·Exploration drilling at key targets

 

The budget for 2022 is presented in Table 23-1.

 

Table 23-1: 2022 Budget

 

Item Budget
(US$Millions)
Drilling and Assays $17.0
Land and Commercial $50.0
Geophysics $1.2
Initial Assessment $1.5
Operational Support – staff, facilities, vehicles, transport, new core shed, community office, community relations $4.0
Total $73.7

 

Advancing to subsequent phases of exploration is contingent on positive results in the Initial Assessment.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
163Nordmin Engineering Ltd.

 

 

24REFERENCES

 

Anderson, T. H., (2015). Jurassic (170–150 Ma) basins: The tracks of a continental-scale fault, the Mexico-Alaska megashear, from the Gulf of Mexico to Alaska.

 

Asmus, B., (2013). Gossan or the iron cap. Retrieved from https://en.archaeometallurgie.de/gossan-iron-cap/

 

Balla, J. C., (1972). The relationship of Laramide stocks to regional structure in central Arizona.

 

Banks, N. G., Cornwall, H. R., Silberman, M. L., Creasey, S. C., & Marvin, R. F.,(1972). Chronology of Intrusion and Ore Deposition at Ray, Arizona; Part I, K-Ar Ages. Economic Geology, 67(7), 864-878.

 

Berger, B., Ayuso, R., Wynn, J., & Seal, R., (2008). Preliminary Model of Porphyry Copper Deposits. USGS Open-File Report 2008-1321. Retrieved from http://pubs.er.usgs.gov/usgspubs/ofr/ofr20081321

 

Chávez, W. X., (2021). Weathering of Copper Deposits and Copper Mobility: Mineralogy, Geochemical Stratigraphy, and Exploration Implications. SEG Discovery, (126), 16-27.

 

Dilles, John H., et al., (2000). Overview of the Yerington porphyry copper district: Magmatic to nonmagmatic sources of hydrothermal fluids, their flow paths, alteration affects on rocks, and Cu-Mo-Fe-Au ores.

 

Cook III, S. S. (1994)., The geologic history of supergene enrichment in the porphyry copper deposits of southwestern North America (Doctoral dissertation, The University of Arizona).

 

Cummings, R. B., & Titley, S. R., (1982). Geology of the Sacaton porphyry copper deposit. Advances in Geology of the Porphyry Copper Deposits, Southwest North America, 507-521.

 

Fernández-Mort, A., & Riquelme, R. A.-Z., (2018). genetic model based on evapoconcentration for sediment-hosted exotic-copper mineralization in arid environments: the case of the El Tesoro Central copper deposit, Atacama Desert, Chile. Miner Deposita, 53, 775-795. Retrieved from https://doi.org/10.1007/s00126-017-0780-2

 

Harlan, S. S., (1993). Paleomagnetism of Middle Proterozoic diabase sheets from central Arizona. Canadian Journal of Earth Sciences, 30(7), 1415-1426.

 

Kreis, (1978). A Structural and Related Mineral Reinterpretation of the Santa Cruz Horst Block. Internal report.

 

Leveille, R. A., & Stegen, R. J., (2012). The southwestern North America porphyry copper province.

 

Lipske, J. L., & Dilles, J. H., (2000). Advanced argillic and sericitic alteration in the subvolcanic environment of the Yerington porphyry copper system, Buckskin Range, Nevada.

 

Lowell, J., & Guilbert, J., (1970). Lateral and vertical alteration-mineralization zoning in porphyry ore deposits. Economic Geology, 65, 373-408.

 

Mote, T., Becker, T., Renne, P., & Brimhall, G., (2001). Chronology of Exotic Mineralization at El Salvador, Chile, by 40Ar/39Ar Dating of Copper Wad and Supergene Alunite. Economic Geology, 351-366. doi:10.2113/96.2.351

 

Münchmeyer, C., (1998). Exotic Deposits - Products of Lateral Migration of Supergene Solutions from Porphyry Copper Deposits. Andean Copper Deposits: New Discoveries, Mineralization, Styles and Metallogeny. Francisco Camus, Richard M. Sillitoe, Richard Petersen.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
164Nordmin Engineering Ltd.

 

 

Tosdal, R. M., & Wooden, J. L., (2015). Construction of the Jurassic magmatic arc, southeast California and southwest Arizona. Geological Society of America Special Papers, 513, 189-221.

 

Scarborough, R., & Meader, N., (1989). Geologic Map of the Northern Plomosa Mountains, Yuma [La Paz] County, Arizona.

 

Sell, J.D., (1976). A Structural and Related Mineral Reinterpretation of the Santa Cruz Horst Block - Santa Cruz Project Studies, Pinal County, Arizona, internal report from Sell to F.T. Greybeal.

 

Sillitoe, R. H., (2010). Porphyry Copper Systems. Economic Geology. Retrieved from https://doi.org/10.2113/gsecongeo.105.1.3

 

Vikre, P., Graybeal, F., & Koutz, F., (2014). Concealed Basalt-Matrix Diatremes with Cu-Au-Ag-(Mo)-Mineralized Xenoliths, Santa Cruz Porphyry Cu-(Mo) System, Pinal County, Arizona. Economic Geology. doi:10.2113/econgeo.109.5.1271

 

Watts, A. B., Karner, G., & Steckler, M. S., (1982). Lithospheric flexure and the evolution of sedimentary basins. Philosophical Transactions of the Royal Society of London. Series A, Mathematical and Physical Sciences, 305(1489), 249-281.

 

Watts Griffis McQuat, Evoy, E.F., (1982). Casa Grande Copper Company Ore Reserve Study for the Hanna Mining Company.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
165Nordmin Engineering Ltd.

 

 

25RELIANCE ON INFORMATION PROVIDED BY THE REGISTRANT

 

This Technical Report Summary has been prepared by Nordmin for IVNE. The information, conclusions, opinions, and estimates contained herein are based on:

 

·Information available to Nordmin at the time of preparation of this report,

·Assumptions, conditions, and qualifications as set forth in this report, and

·Data, reports, and other information supplied by IVNE.

 

For the purpose of the Summary and Section 3 of this report, Nordmin has relied on ownership information provided in an internal Title Opinion and Reliance letter by Marian Lalonde dated October 29, 2021, of Fennemore Law, Tucson, Arizona.

 

Nordmin has not researched property title or mineral rights for the Santa Cruz Project as we consider it reasonable to rely on IVNEs legal counsel who is responsible for maintaining this information.

 

Nordmin has taken all appropriate steps, in their professional opinion, to ensure that the above information from IVNE is sound.

 

Except for the purposes legislated under US federal securities laws and the Canadian provincial securities laws, any use of this Technical Report Summary by any third party is at that party’s sole risk.

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
166Nordmin Engineering Ltd.

 

 

26DATE AND SIGNATURE PAGE

 

This report titled “Technical Report Summary on the Santa Cruz Project, Arizona, USA” with an effective date of December 8, 2021 was prepared and signed by:

 

Nordmin Engineering Ltd. (Signed) Nordmin Engineering Ltd.
Dated at Thunder Bay, ON  
May 18, 2022  

 

Technical Report Summary – December 8, 2021
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
167Nordmin Engineering Ltd.

 

 

 

Appendix A: Property and Rights

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Nordmin Engineering Ltd.
Appendix A

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix A | Page 1 of 7

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix A | Page 2 of 7

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix A | Page 3 of 7

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix A | Page 4 of 7

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix A | Page 5 of 7

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix A | Page 6 of 7

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix A | Page 7 of 7

 

 

 

Appendix B: Standard, Blank and duplicate Charts

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Nordmin Engineering Ltd.
Appendix B

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 1 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 2 of 26

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 3 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 4 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 5 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 6 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 7 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 8 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 9 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 10 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 11 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 12 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 13 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 14 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 15 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 16 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 17 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 18 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 19 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 20 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 21 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 22 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 23 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 24 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 25 of 26

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix B | Page 26 of 26

 

 

Appendix C: Data Analysis Grade Domains

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Nordmin Engineering Ltd.
Appendix C

 

 

0.001 0.01 0.1 1 CU_PCT 0 1 2 3 4 5 6 7 8 9 10 11 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 2 7 4 6 ) WF-AS_BIN-2 = 1 Log CU_PCT Histogram 0.001 0.01 0.1 1 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-AS_BIN-2 = 1 Log Probability Plot CU_PCT mgm25 50 75 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 CU_PCT 0.0 0.5 1.0 1.5 2.0 0 100 200 300 400 500 600 700 800 900 1000 1100 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 1 0 8 3 ) C U _ P C T WF-AS_BIN-2 = 1 CU_PCT Mean Above CU_PCT Count Above CU_PCT Copper Oxide 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 1 of 20

 

0.001 0.01 0.1 1 CU_PCT 0 2 4 6 8 10 12 14 16 18 20 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 1 9 2 2 ) WF-AS_BIN-2 = 2 Log CU_PCT Histogram 0.001 0.01 0.1 1 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-AS_BIN-2 = 2 Log Probability Plot CU_PCT mgm25 50 75 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 CU_PCT 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 0 100 200 300 400 500 600 700 800 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 8 2 3 ) C U _ P C T WF-AS_BIN-2 = 2 CU_PCT Mean Above CU_PCT Count Above CU_PCT Copper Oxide 1.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 2 of 20

 

0.01 0.1 1 10 CU_PCT 0 5 10 15 20 25 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 1 7 5 6 ) WF-AS_BIN-2 = 3 Log CU_PCT Histogram 0.01 0.1 1 10 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-AS_BIN-2 = 3 Log Probability Plot CU_PCT mgm25 50 75 0 1 2 3 4 5 6 7 8 9 10 CU_PCT 0 1 2 3 4 5 6 7 8 9 10 0 100 200 300 400 500 600 700 800 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 8 0 2 ) C U _ P C T WF-AS_BIN-2 = 3 CU_PCT Mean Above CU_PCT Count Above CU_PCT Copper Oxide 2.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 3 of 20

 

0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 CU_PCT 0 5 10 15 20 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 5 8 4 9 ) WF-PR_BIN = 1 CU_PCT Histogram mgm25 50 75 0.005 0.01 0.05 0.1 0.5 1 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-PR_BIN = 1 Log Probability Plot CU_PCT mgm25 50 75 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 CU_PCT 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 0 500 1000 1500 2000 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 2 2 4 1 ) C U _ P C T WF-PR_BIN = 1 CU_PCT Mean Above CU_PCT Count Above CU_PCT Primary Cu 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 4 of 20

 

0 1 2 3 4 5 CU_PCT 0 2 4 6 8 10 12 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 2 5 2 7 ) WF-PR_BIN = 2 CU_PCT Histogram mgm25 50 75 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-PR_BIN = 2 Log Probability Plot CU_PCT mgm25 50 75 0 1 2 3 4 5 CU_PCT 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 0 100 200 300 400 500 600 700 800 900 1000 1100 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 1 0 3 9 ) C U _ P C T WF-PR_BIN = 2 CU_PCT Mean Above CU_PCT Count Above CU_PCT Primary Cu 1.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 5 of 20

 

2 4 6 8 10 CU_PCT 0 1 2 3 4 5 6 7 8 9 10 11 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 5 4 3 . 9 ) WF-PR_BIN = 3 CU_PCT Histogram mgm2550 75 0.5 1 2 5 10 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-PR_BIN = 3 Log Probability Plot CU_PCT mgm25 50 75 0 2 4 6 8 10 CU_PCT 0 2 4 6 8 10 12 0 50 100 150 200 250 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 2 4 4 ) C U _ P C T WF-PR_BIN = 3 CU_PCT Mean Above CU_PCT Count Above CU_PCT Primary Cu 1.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 6 of 20

 

0.001 0.01 0.1 1 10 CU_PCT 0 5 10 15 20 25 30 35 40 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 1 0 0 6 ) WF-CN BIN IN 1 Log CU_PCT Histogram 0.001 0.01 0.1 1 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-CN BIN IN 1 Log Probability Plot CU_PCT mgm25 5075 0 1 2 3 4 5 6 CU_PCT 0 1 2 3 4 5 6 7 0 50 100 150 200 250 300 350 400 450 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 4 4 0 ) C U _ P C T WF-CN BIN IN 1 CU_PCT Mean Above CU_PCT Count Above CU_PCT Chalcocite Enrichment 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 7 of 20

 

0.05 0.1 0.5 1 5 10 CU_PCT 0 5 10 15 20 25 30 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 1 0 3 9 ) WF-CN BIN IN 2 Log CU_PCT Histogram 0.05 0.1 0.5 1 5 10 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-CN BIN IN 2 Log Probability Plot CU_PCT mgm25 50 75 0 2 4 6 8 10 CU_PCT 0 2 4 6 8 10 12 0 50 100 150 200 250 300 350 400 450 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 4 3 7 ) C U _ P C T WF-CN BIN IN 2 CU_PCT Mean Above CU_PCT Count Above CU_PCT Chalcocite Enrichment – 1.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 8 of 20

 

0.01 0.02 0.05 0.1 0.2 0.5 1 2 CU_PCT 0 5 10 15 20 25 30 35 40 45 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 2 1 1 . 8 ) WF-EX BIN IN 1 Log CU_PCT Histogram 0.01 0.02 0.05 0.1 0.2 0.5 1 2 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-EX BIN IN 1 Log Probability Plot CU_PCT mgm25 50 75 0.0 0.5 1.0 1.5 2.0 CU_PCT 0.0 0.5 1.0 1.5 2.0 2.5 0 10 20 30 40 50 60 70 80 90 100 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 9 4 ) C U _ P C T WF-EX BIN IN 1 CU_PCT Mean Above CU_PCT Count Above CU_PCT Exotic Copper – 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 9 of 20

 

2 5 10 CU_PCT 0 10 20 30 40 50 60 70 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 9 3 . 5 7 ) WF-EX BIN IN 3 Log CU_PCT Histogram 2 5 10 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-EX BIN IN 3 Log Probability Plot CU_PCT mgm25 50 75 2 4 6 8 10 12 CU_PCT 5 6 7 8 9 10 11 12 13 0 5 10 15 20 25 30 35 L E N G T H W e i g h t e d M e a n A b o v e C U _ P C T C o u n t A b o v e ( o f 3 5 ) C U _ P C T WF-EX BIN IN 3 CU_PCT Mean Above CU_PCT Count Above CU_PCT Exotic Copper – 2.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 10 of 20

 

Capping Charts

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 11 of 20

 

0.8 0.9 1 2 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-AS_BIN-2 = 1 Cap=2.23 Capped=0 CV=0.88 Total Lost=0% Log Probability Plot CU_PCT 0.85 90% 0.87 91% 0.89 92% 0.91 93% 0.94 94% 0.96 95% 0.983 96% 1.1 97% 1.24 98% 2.23 100% Max 0.001 0.01 0.1 1 CU_PCT 0 1 2 3 4 5 6 7 8 9 10 11 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 2 7 4 6 ) WF-AS_BIN-2 = 1 Log CU_PCT Histogram Copper Oxide 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 12 of 20

 

5 10 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-AS_BIN-2 = 3 Cap=10.1 Capped=0 CV=0.62 Total Lost=0% Log Probability Plot CU_PCT 3.9 90% 4.095 91% 4.202 92% 4.3 93% 4.46 94% 4.64 95% 4.995 96% 5.536 97% 6.247 98% 10.1 100% Max 0.001 0.01 0.1 1 10 CU_PCT 0 5 10 15 20 25 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 1 7 5 6 ) WF-AS_BIN-2 = 3 Log CU_PCT Histogram Copper Oxide 2.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 13 of 20

 

0.8 0.9 1 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-PR_BIN = 1 Cap=1.5 Capped=1 CV=0.4 Total Lost=0.04% Log Probability Plot CU_PCT 0.84 90% 0.85 91% 0.87 92% 0.88 93% 0.9 94% 0.92 95% 0.94 96% 0.97 97% 0.99 98% 1.5 99.9% Max 0.005 0.01 0.05 0.1 0.5 1 CU_PCT 0 1 2 3 4 5 6 7 8 9 10 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 5 8 4 9 ) WF-PR_BIN = 1 Log CU_PCT Histogram Primary Cu 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 14 of 20

 

2 3 4 5 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-PR_BIN = 2 Cap=3 Capped=5 CV=0.46 Total Lost=0.5% Log Probability Plot CU_PCT 1.429 90% 1.46 91% 1.47 92% 1.5 93% 1.569 94% 1.652 95% 1.736 96% 1.888 97% 1.985 98% 3 99.7% Max 0.01 0.02 0.05 0.1 0.2 0.5 1 2 CU_PCT 0 1 2 3 4 5 6 7 8 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 2 5 2 7 ) WF-PR_BIN = 2 Log CU_PCT Histogram Primary Cu 1.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 15 of 20

 

5 10 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-PR_BIN = 3 Cap=11.648 Capped=0 CV=0.6 Total Lost=0% Log Probability Plot CU_PCT 3.267 90% 3.343 91% 3.416 92% 3.491 93% 3.751 94% 4.031 95% 4.227 96% 4.818 97% 5.781 98% 11.65 100% Max 0.5 1 2 5 10 CU_PCT 0 2 4 6 8 10 12 14 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 5 4 3 . 9 ) WF-PR_BIN = 3 Log CU_PCT Histogram Primary Cu 1.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 16 of 20

 

2 5 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-CN BIN IN 1 Cap=6.93 Capped=0 CV=0.74 Total Lost=0% Log Probability Plot CU_PCT 1.76 90% 1.839 91% 1.89 92% 2 93% 2.046 94% 2.13 95% 2.394 96% 2.45 97% 2.816 98% 6.93 100% Max 0.001 0.01 0.1 1 10 CU_PCT 0 5 10 15 20 25 30 35 40 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 1 0 0 6 ) WF-CN BIN IN 1 Log CU_PCT Histogram Chalcocite Enrichment 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 17 of 20

 

5 10 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-CN BIN IN 2 Cap=11.648 Capped=0 CV=0.73 Total Lost=0% Log Probability Plot CU_PCT 2.847 90% 3.012 91% 3.153 92% 3.24 93% 3.38 94% 3.464 95% 3.79 96% 4.097 97% 4.819 98% 11.65 100% Max 0.05 0.1 0.5 1 5 10 CU_PCT 0 5 10 15 20 25 30 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 1 0 3 9 ) WF-CN BIN IN 2 Log CU_PCT Histogram Chalcocite Enrichment 1.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 18 of 20

 

1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 CU_PCT 0.01 0.02 0.05 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.95 99.98 99.99 C u m u l a ti v e % WF-EX BIN IN 1 Cap=2.04 Capped=1 CV=0.72 Total Lost=0.3% Log Probability Plot CU_PCT 1.561 90% 1.61 91% 1.619 92% 1.634 93% 1.676 94% 1.693 95% 1.771 96% 1.847 97% 1.951 98% 2.04 99% Max 0.01 0.05 0.1 0.5 1 5 10 50 CU_PCT 0 2 4 6 8 10 12 14 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 2 1 1 . 8 ) WF-EX BIN IN 1 Log CU_PCT Histogram Exotic Copper – 0.5%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 19 of 20

 

6 7 8 9 10 CU_PCT 0.01 0.1 0.2 0.5 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 99.5 99.8 99.9 99.99 C u m u l a ti v e % WF-EX BIN IN 3 Cap=12.6 Capped=0 CV=0.49 Total Lost=0% Log Probability Plot CU_PCT 6.697 90% 7.126 91% 7.68 92% 8.234 93% 8.572 94% 8.71 95% 8.848 96% 9.241 97% 10.36 98% 12.6 100% Max 0.01 0.050.1 0.5 1 5 10 50 CU_PCT 0 5 10 15 20 25 30 L E N G T H W e i g h t e d F r e q u e n c y ( % o f 9 3 . 5 7 ) WF-EX BIN IN 3 Log CU_PCT Histogram Exotic Copper – 2.0%

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix C | Page 20 of 20

 

 

 

Appendix D: Block Model CLASSIFICATION IMAGES

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Nordmin Engineering Ltd.
Appendix D

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 1 of 8

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 2 of 8

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 3 of 8

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 4 of 8

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 5 of 8

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 6 of 8

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 7 of 8

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix D | Page 8 of 8

 

 

Appendix E: Block Model VALIDATION IMAGES

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Nordmin Engineering Ltd.
Appendix E

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 1 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 2 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 3 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 4 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 5 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 6 of 15

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 7 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 8 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 9 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 10 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 11 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 12 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 13 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 14 of 15

 

 

 

 

Technical Report Summary
Santa Cruz Project, Arizona, USA
Ivanhoe Electric Inc.
Appendix E | Page 15 of 15