XML 101 R83.htm IDEA: XBRL DOCUMENT v3.26.1
Jointly Owned Generation Units (Details)
$ in Thousands
Dec. 31, 2025
USD ($)
MW
Acadia Power Station common facilities  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 19,142
ACCUMULATED DEPRECIATION 4,532
CONSTRUCTION WORK IN PROGRESS $ 395
OWNERSHIP INTEREST PERCENTAGE 50.00%
Acadia Unit 1  
Jointly Owned Utility Plant Interests [Line Items]  
OWNERSHIP INTEREST PERCENTAGE 100.00%
Rodemacher Unit 2  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 89,412
ACCUMULATED DEPRECIATION 61,900
CONSTRUCTION WORK IN PROGRESS $ 671
OWNERSHIP INTEREST PERCENTAGE 30.00%
RATED CAPACITY (MW) | MW 523
OWNERSHIP INTEREST (MW) | MW 157
Common facilities - Nesbitt Unit 1 and Rodemacher Unit 2  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 3,369
ACCUMULATED DEPRECIATION 862
CONSTRUCTION WORK IN PROGRESS $ 15
OWNERSHIP INTEREST PERCENTAGE 62.00%
Common facilities - Rodemacher Unit 2 and Madison Unit 3  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 3,245
ACCUMULATED DEPRECIATION 554
CONSTRUCTION WORK IN PROGRESS $ 11
OWNERSHIP INTEREST PERCENTAGE 69.00%
Common facilities - Nesbitt Unit 1, Rodemacher Unit 2, and Madison Unit 3  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 11,801
ACCUMULATED DEPRECIATION 2,769
CONSTRUCTION WORK IN PROGRESS $ 112
OWNERSHIP INTEREST PERCENTAGE 77.00%
CLECO POWER | Acadia Power Station common facilities  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 19,916
ACCUMULATED DEPRECIATION 5,306
CONSTRUCTION WORK IN PROGRESS $ 395
OWNERSHIP INTEREST PERCENTAGE 50.00%
CLECO POWER | Acadia Unit 1  
Jointly Owned Utility Plant Interests [Line Items]  
OWNERSHIP INTEREST PERCENTAGE 100.00%
CLECO POWER | Rodemacher Unit 2  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 162,992
ACCUMULATED DEPRECIATION 135,480
CONSTRUCTION WORK IN PROGRESS $ 671
OWNERSHIP INTEREST PERCENTAGE 30.00%
RATED CAPACITY (MW) | MW 523
OWNERSHIP INTEREST (MW) | MW 157
CLECO POWER | Common facilities - Nesbitt Unit 1 and Rodemacher Unit 2  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 4,776
ACCUMULATED DEPRECIATION 2,269
CONSTRUCTION WORK IN PROGRESS $ 15
OWNERSHIP INTEREST PERCENTAGE 62.00%
CLECO POWER | Common facilities - Rodemacher Unit 2 and Madison Unit 3  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 3,335
ACCUMULATED DEPRECIATION 644
CONSTRUCTION WORK IN PROGRESS $ 11
OWNERSHIP INTEREST PERCENTAGE 69.00%
CLECO POWER | Common facilities - Nesbitt Unit 1, Rodemacher Unit 2, and Madison Unit 3  
Jointly Owned Utility Plant Interests [Line Items]  
UTILITY PLANT IN SERVICE $ 21,844
ACCUMULATED DEPRECIATION 12,812
CONSTRUCTION WORK IN PROGRESS $ 112
OWNERSHIP INTEREST PERCENTAGE 77.00%