COMMITMENTS AND CONTINGENCIES
9 Months Ended
Sep. 30, 2024
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES COMMITMENTS AND CONTINGENCIES
Legal Matters

From time to time, the Company may be involved in various lawsuits and legal proceedings that arise in the ordinary course of business. However, litigation is subject to inherent uncertainties, and an adverse result in such matters may arise and harm the Company’s business. Except as otherwise disclosed in this Note 10, "Commitments and Contingencies—Legal Matters", the Company is currently not aware of any such legal proceedings or claims that it believes will have a material adverse effect on its business, financial condition, or operating results.
Title V Air Permit Renewal Litigation

In late June 2022, the New York State Department of Environmental Conservation ("NYSDEC") announced its denial of the Title V Air Permit renewal for our New York Facility. We filed a notice with NYSDEC in July 2022 requesting a hearing on NYSDEC’s decision. In September 2023, the administrative law judge presiding over the hearing issued a ruling with respect to the status of the parties and certain issues to be adjudicated in the hearing. We submitted an interim appeal with NYSDEC thereafter challenging such ruling with a motion to stay the broader appeals process while the interim appeal was being resolved. On May 8, 2024, our interim appeal to NYSDEC and request for an adjudicatory hearing were ultimately denied, and the June 2022 non-renewal of our Title V Air Permit was affirmed by NYSDEC’s Regional Director for Region 7, which rendered NYSDEC’s decision final for purposes of seeking judicial review. On August 15, 2024, we filed a verified petition and complaint pursuant to Article 78 of the New York Civil Practice Law and Rules against NYSDEC in New York Supreme Court, Yates County (the "Court"), seeking declaratory and injunctive relief relating to NYSDEC's denial of our renewal application for our New York Facility, including, among other things, to (i) annul NYSDEC's June 2022 denial of our renewal application and the May 8, 2024 affirmation of such denial by NYSDEC's Regional Director for Region 7; (ii) issue certain declaratory judgments with respect to NYSDEC's interpretation of the New York Climate Leadership and Community Protection Act on which the denial of our renewal application was predicated; and (iii) enjoin NYSDEC from taking any action to request that the New York Facility cease operations. On August 20, 2024, we submitted a motion to the Court by Order to Show Cause seeking a temporary restraining and preliminary injunction (the “TRO Request”) permitting the Facility to continue operations during the pendency of the Article 78 proceeding. Subsequent to submission of the TRO Request, Greenidge and NYSDEC agreed to a briefing schedule with the respect to the TRO Request, with a hearing before the Court which occurred in late October 2024. In connection with the agreed-upon briefing schedule, NYSDEC agreed that Greenidge need not (i) cease operations of any air contamination sources located at the Facility, (ii) render such air contamination sources inoperable, or (iii) relinquish the Title V Air Permit until November 1, 2024 (the "November 1 Stay"). On October 29, 2024, a hearing was held before the Court and a stipulation on the record was entered into between the Company and NYSDEC, agreeing to extend the November 1 Stay through
November 14, 2024 (the “November 14 Stay”). The Company expects that the Court will render a decision on the TRO Request or, alternatively, the Company's Article 78 challenge of the denial of the permit renewal application in total, prior to the expiration of the November 14 Stay. This challenge has, and will continue, to cause us to incur additional costs and result in the diversion of management attention, which could adversely affect our business, financial condition and results of operations. We expect that the judicial proceedings related to the challenge of NYSDEC’s denial of our Title V Air Permit renewal application may take a number of years to fully resolve, and there can be no assurance that our efforts will be successful. Our inability to secure a temporary restraining order or preliminary injunction to allow the New York Facility to continue operating during the pendency of the litigation or to otherwise succeed in securing a renewal of our Title V Air Permit for the New York Facility could have a material adverse effect on our business, financial condition, and operating results, and our ability to continue operating as a going concern. See Note 2, “Summary of Significant Accounting Policies,” in the Notes to Condensed Consolidated Financial Statements.

Environmental Liabilities

The Company has a CCR liability associated with the closure of a coal ash pond located on the Company’s property in the Town of Torrey, New York. In accordance with ASC 410-30, the Company has a liability of $17.3 million as of September 30, 2024 and December 31, 2023, respectively. CCRs are subject to federal and state requirements. In October 2023, the Company completed the necessary steps to officially cease use of the coal ash pond. Following this occurring, the Company is required to complete the remediation of the coal ash pond CCR by November 2028 and will perform the work in stages over the next five years. Current estimates are based on various assumptions including, but not limited to, closure and post-closure cost estimates, timing of expenditures, escalation factors, and requirements of granted permits. Additional adjustments to the environment liability may occur periodically due to changes in remediation requirements regarding CCRs, which may lead to material changes in estimates and assumptions.

The Company owns and operates a fully permitted landfill that also acts as a leachate treatment facility. In accordance with ASC 410-30, Environmental Obligations ("ASC 410-30"), the Company has recorded an environmental liability of $12.9 million as of September 30, 2024 and December 31, 2023. As required by NYSDEC, companies with landfills are required to fund a trust to cover closure costs and expenses after the landfill has stopped operating or, in lieu of a trust, may negotiate to maintain a letter of credit guaranteeing the payment of the liability. Estimates are based on various assumptions including, but not limited to, closure and post-closure cost estimates, timing of expenditures, escalation factors, and requirements of granted permits. Additional adjustments to the environment liability may occur periodically due to potential changes in estimates and assumptions. The liability has been determined based on estimated costs to remediate as well as post-closure costs which are assumed over an approximate 30-year period and assumes an annual inflation rate of 2.4%.

Commitments

The Company entered into a contract with Empire Pipeline Incorporated in September 2020 which provides for the transportation to its pipeline of 15,000 dekatherms of natural gas per day, approximately $0.2 million per month. The contract ends in September 2030 and may be terminated by either party with 12 months’ notice after the initial 10-year period.