XML 24 R9.htm IDEA: XBRL DOCUMENT v3.25.0.1
Property, Plant and Equipment
12 Months Ended
Dec. 31, 2024
Property, Plant and Equipment  
Property, Plant and Equipment

Note 3 – Property, Plant, and Equipment

Property, plant, and equipment are summarized as follows:

December 31, 

2024

    

2023

Production equipment

$

41,750

$

36,086

Laboratory equipment

12,611

9,910

Leasehold improvements

 

73,114

 

59,109

Furniture and computer equipment

 

4,298

 

3,915

Construction in progress

 

5,141

 

13,650

Total cost

 

136,914

 

122,670

Accumulated depreciation

 

(39,706)

 

(23,514)

Net property, plant and equipment

$

97,208

$

99,156

Depreciation expenses for dedicated laboratory equipment and production equipment are charged to research and development. The other depreciation expenses are included in the Company’s overhead and are allocated across Operating Expenses based on Company personnel costs incurred.

Depreciation expenses related to property, plant, and equipment are summarized as follows:

December 31, 

2024

    

2023

    

Depreciation expense

$

16,449

$

11,947

The Company expanded its pilot electrolyte production to produce larger quantities of electrolyte to feed cell-production lines and continue research and development efforts at its Thornton, Colorado facility (“SP2”). The Company began producing electrolyte at SP2 in 2023. The Company also built an electrolyte innovation center (the “EIC”) at SP2 to design, improve, and test electrolyte manufacturing processes. The Company placed nearly all of the EIC into service in 2024 and expects to place the remaining portion in service by the end of the first quarter 2025. Construction in progress related to property, plant, and equipment is summarized as follows:

    

December 31, 

Construction in progress

 

2024

    

2023

SP1 – Capital projects

$

1,896

$

2,298

SP2 – Increased scale electrolyte production

 

3,245

 

11,352