Note 10 - Commitments and Contingencies
From time to time, the Company may be subject to various claims, title matters, and legal proceedings arising in the ordinary course of business, including environmental contamination claims, personal injury and property damage claims, claims related to joint interest billings and other matters under natural gas operating agreements, and other contractual disputes. The Company maintains general liability and other insurance to cover some of these potential liabilities. All known liabilities are fully accrued based on the Company's best estimate of the potential loss. While the outcome and impact on the Company cannot be predicted with certainty, results may change in future periods. For the periods presented in the condensed consolidated financial statements, the Company believes that its ultimate liability, with respect to any such matters, will not have a significant impact or material adverse effect on its financial positions, results of operations, or cash flows. Results of operations and cash flows, however, could be significantly impacted in the reporting periods in which such matters are resolved.
As a part of the consideration paid for the Devon Barnett Acquisition, additional cash consideration would be required to be paid by the Company if certain thresholds were met for average Henry Hub natural gas and WTI crude oil prices for each of the calendar years during the period beginning January 2021 through December 31, 2024 (the “Devon Barnett Earnout). Average Henry Hub payouts and threshold were as follows: $2.75/MMBtu $20.0 million, $3.00/MMBtu $25.0 million, $3.25/MMBtu $35.0 million, and $3.50/MMBtu $45.0 million; average WTI payouts and thresholds are as follows for these periods: $50.00/Bbl $10.0 million, $55.00/Bbl $12.5 million, $60.00/Bbl $15.0 million, and $65.00/Bbl $20.0 million. Payments were due in the month following the end of the respective measurement period for which the hurdle rates were set. As of December 31, 2024, the final portion of the arrangement was considered to be settled resulting in a settlement of $20.0 million, which is reflected as contingent consideration payable within current liabilities on the condensed consolidated balance sheets, and was paid on January 8, 2025. As described in Note 4 - Fair Value Measurements and Note 5 - Derivative Instruments, the contingent consideration was accounted for as a derivative instrument. Management uses NYMEX forward pricing estimates for both Henry Hub and WTI hurdle rates and Monte Carlo simulations to determine the fair value of the contingent consideration. For the three months ended March 31, 2024, the change in the fair value of the contingent consideration was a gain of $4.6 million. This change in the fair value during this period impacted the associated liability on the condensed consolidated balance sheets and recognition of the gain was recognized in the gains on contingent consideration liabilities on the condensed consolidated statements of operations.
In conjunction with the Exxon Barnett Acquisition, additional cash consideration would have been required to be paid by the Company if certain thresholds for future Henry Hub natural gas prices were met for the year ended December 31, 2024. Based on the thresholds for this period, no payout was required. As of December 31, 2024, the fair value of the contingent consideration was zero. The change in the fair value of the contingent consideration for the three months ended March 31, 2024 was a gain of $2.0 million. This change in the fair value during this period reduced the associated liability on the condensed consolidated balance sheets and recognition of the gain was recognized in the gains on contingent consideration liabilities on the condensed consolidated statements of operations. Refer to Note 4 - Fair Value Measurements for the valuation methodology and associated inputs.
The Company has volume commitments in the form of gathering, processing, and transportation agreements with various third parties that require delivery of 1,068,885,447 dekatherms of natural gas. The significant majority of the agreements terminate by 2029, with one agreement extending through 2036. As of March 31, 2025, the aggregate undiscounted future payments required under these contracts total $304.7 million.
A summary of the Company's commitments, excluding contingent consideration, as of March 31, 2025, is provided in the following table:
(in thousands)20252026202720282029ThereafterTotal
RBL Credit Agreement$— $— $— $200,000 $— $— $200,000 
Interest payable612 — — — — — 612 
Operating lease payments941 1,047 908 924 947 3,662 8,429 
Volume commitments51,775 67,615 58,959 53,144 34,257 38,929 304,679 
Total$53,328 $68,662 $59,867 $254,068 $35,204 $42,591 $513,720