Note 9 – Commitments and Contingencies

Pilot Infrastructure Agreement

On July 5, 2022, EVgo entered into a charging infrastructure agreement (the “Pilot Infrastructure Agreement”) and an operations and maintenance agreement (the “Pilot O&M”) with Pilot Travel Centers LLC (“Pilot Company”) and General Motors LLC (“GM”) to build, operate, and maintain up to 2,000 stalls served by DC chargers that Pilot Company will own. The stalls will be located at approximately 500 Pilot Company sites across more than 40 states.

Pursuant to the Pilot Infrastructure Agreement, EVgo is required to meet certain construction milestones measured by the number of sites commissioned, and Pilot Company is required to make certain payments each month based on completion of pre-engineering and development work, the progress of construction at each site and for each charger procured by EVgo. Subject to extensions of time for specified excusable events, if EVgo is unable to meet its commissioning obligations, Pilot Company will be entitled to liquidated damages calculated per day, subject to a cap of $30,000 at each site. The Pilot Infrastructure Agreement contains various provisions that may permit or cause early termination, including Pilot’s right to terminate after 1,000 stalls have been completed, the inability of EVgo to secure certain chargers and a material increase in the price of chargers due to a change in law. If Pilot Company elects to terminate the Pilot Infrastructure Agreement after 1,000 stalls have been completed, Pilot Company must pay EVgo a termination fee per stall for those not built; such fee varies based on the number of stalls already built. If EVgo is wholly or partially unable to perform its obligations under the Pilot Infrastructure Agreement due to certain circumstances outside its control, including delays by permitting authorities and utilities or certain force majeure events, such inability will not be considered a breach or default under the Pilot Infrastructure Agreement.

Under the Pilot O&M, EVgo is required to perform operations, maintenance and networking services on stalls built and commissioned under the Pilot Infrastructure Agreement in exchange for payment of a monthly fee by Pilot to EVgo. EVgo is subject to certain performance criteria under the Pilot O&M.

Delta Charger Supply Agreement and Purchase Order

On July 12, 2022, EVgo entered into a General Terms and Conditions for Sale of EV Charger Products (the “Delta Charger Supply Agreement”) with Delta Electronics, Inc. (“Delta”), including an initial purchase order (the “Purchase Order”), pursuant to which EVgo will purchase and Delta will sell EV chargers manufactured by Delta in specified quantities at certain delivery dates. EVgo expects to use a portion of the chargers purchased under the Purchase Order to meet the requirements of the Pilot Infrastructure Agreement. EVgo is required to purchase a minimum of 1,000 chargers (which will enable the construction of 2,000 stalls) from Delta under the Purchase Order and may, at EVgo’s election, increase the number of chargers it purchases from Delta to 1,100.

Nissan Agreements

EVgo has executed two agreements with Nissan North America, Inc. (“Nissan”) under which EVgo has provided charger construction and installation and certain other services. Pursuant to the first agreement, entered into in March 2016 (the “Nissan 2016 Agreement”), the Company was required to support, maintain and make available at least 850 chargers through July 7, 2021, and purchasers or lessees of Nissan LEAF EVs in certain markets could receive charging services at EVgo stations or participating third-party charging stations. The Company fulfilled all build, support and maintenance obligations under the Nissan 2016 Agreement.

The second agreement between EVgo and Nissan, entered into in June 2019 (the “Nissan 2.0 Agreement”), provides for joint marketing activities, charging credit programs for purchasers or lessees of Nissan EVs, and a capital-build program. The Nissan 2.0 Agreement has been amended several times, including most recently in the fourth quarter of 2022 (the “Nissan Amendment”) to, among other things, adjust the allocation of the value of unused charging credits and to provide new offerings for purchasers or lessees of certain Nissan EV models. Under the joint-marketing activities provisions of the Nissan 2.0 Agreement, EVgo is obligated to spend a specified amount annually on joint-marketing activities that are mutually agreed-upon with Nissan. Under the charging credit program provisions in the Nissan 2.0 Agreement, credits for charging are allocated to purchasers or lessees of Nissan EVs, and such purchasers or lessees are permitted to charge their EV for 12 months at no charge to the participant, up to the amount of the charging credit allocated to such participant or on an unlimited basis, depending on the model of Nissan EV purchased or leased. In the event a participant does not use the entire amount of the allocated charging credit or if the annual charging credit pool is not exhausted within a specific period, a portion of the remaining dollar value of such credit rolls over to subsequent periods, and a portion is retained by the Company. The capital-build program provided for in the Nissan 2.0 Agreement requires the Company to install, operate and maintain public, high-power dual-standard chargers in specified markets pursuant to a schedule that outlines the build timelines for the chargers to be constructed (the “Build Schedule”). If the Company fails to meet its Build Schedule obligations, Nissan may invoke a penalty of up to $70,000 per delayed site beyond a designated cure period, up to 48 sites, which could result in an adjustment to the consideration received by the Company under the Nissan 2.0 Agreement. EVgo and Nissan previously agreed to amend the Nissan 2.0 Agreement to extend the installation deadlines under the Build Schedule by up to 12 months, and Nissan has waived penalties for installation delays relating to program year one. 

EVgo’s ability to meet its Build Schedule obligations may be impacted by delays in permitting, slower than expected third-party approvals of certain site acquisitions, delays in utility interconnection resulting from industry adaptation to the requirements of high-powered charger installation, as well as supply chain issues. Going forward, EVgo is uncertain if these, or other potential issues in the procurement, installation, or energization of DCFC, will be resolved in a timely fashion. At this time, EVgo’s ability to meet future Build Schedule obligations may continue to be impacted by circumstances similar to those experienced during the first half of 2021, or other potential issues including, but not limited to, equipment design and procurement, timing of third-party funding agreements, and the siting, permitting, construction, energizing of DCFC or delays in releasing public grant funding. 

The contract is accounted for under ASC 606, which includes performance obligations related to memberships, charging credits and joint marketing activities. The capital-build program is considered a set-up activity and not a performance obligation under ASC 606. Nissan has the right to terminate the Nissan 2.0 Agreement, without penalty or obligation of any kind, upon 30 days’ written notice if it is unable to secure funding to make payments required under the Nissan 2.0 Agreement. Nissan receives budget approvals annually from Nissan Motor Company Limited. As of September 30, 2022, Nissan has fulfilled its annual payment obligations under the Nissan 2.0 Agreement. If Nissan terminates the Nissan 2.0 Agreement due to a lack of funding, EVgo will still be required to perform the following: (i) pay any existing Build Schedule penalties due at the time of termination; (ii) meet a specified charger installation milestone of 80 chargers in certain designated markets within two years of such termination; (iii) provide an aggregate of $1.6 million in joint marketing activities; and (iv) provide $4.8 million worth of charging credits that shall continue to be administered. 

Pursuant to the Nissan 2.0 Agreement, as modified by the aforementioned extensions and other amendments, EVgo is required to install an aggregate of 210 chargers by February 29, 2024. Pursuant to the current Build Schedule, EVgo is required to install 48 chargers by February 28, 2023. 

General Motors Agreement

On July 20, 2020, EVgo entered into a five-year contract (the “GM Agreement”) with GM to build 2,750 fast chargers that EVgo will own and operate as part of the Company’s public network. On November 2, 2021, EVgo entered into an amendment agreement with GM in order to adjust stall installation targets and expand the overall number of chargers to be installed to 3,250 fast chargers. EVgo believes this agreement will serve to accelerate the Company’s development plans and enhance customer acquisition and brand equity among retail drivers. Pursuant to the GM Agreement, EVgo is required to meet certain quarterly milestones measured by the number of charger stalls installed, and GM is required to make certain payments based on chargers installed.

Under the GM Agreement, EVgo is required to install a total of 3,250 chargers by December 31, 2025, 72% of which are required to be installed by December 31, 2023. Meeting these milestones will require additional funds beyond the amounts committed by GM, and EVgo may face delays in construction, commission or aspects of installation of the chargers the Company is obligated to develop. EVgo is also required to maintain network availability (i.e., the percentage of time a charger is operational and available on the network) of at least 93%. In addition to the capital-build program, EVgo committed to providing a certain number of new GM EV cars with an EVgo charging credit and limited time access to other EVgo services at a discounted rate.

The GM Agreement is subject to early termination in certain circumstances, including in the event EVgo fails to meet the quarterly charger-installation milestones or maintain the specified level of network availability. If GM opts to terminate the agreement, EVgo may not be entitled to receive continued payments from GM and instead may be required to pay liquidated damages to GM. In the event EVgo fails to meet a charger-installation milestone or maintain the required network availability in a calendar quarter, GM has the right to provide EVgo with a notice of such deficiency within 30 days of the end of the quarter. If the same deficiency still exists at the end of the quarter immediately following the quarter for which a deficiency notification was delivered, GM may immediately terminate the agreement and seek pre-agreed liquidated damages of up to $15.0 million.

As of September 30, 2022, there were approximately 3,191 stalls already in the active engineering and construction development pipeline, of which 2,840 stalls had been approved by GM. As of September 30, 2022, EVgo had 457 stalls left to install in order to meet its charger-installation milestone. EVgo is required to open to the public 607 additional stalls by December 31, 2022 or GM will have the right, if it so chooses, to send EVgo a stall count breach notice, which would trigger a cure period through December 31, 2022. EVgo may not meet the charger-installation milestones under the GM Agreement in the future, particularly as a consequence of delays in permitting, commissioning and utility interconnection resulting from COVID-19 and supply chain disruptions in business operations across the utility, engineering and permitting chain, as well as industry and regulatory adaptation to the requirements of high-powered charger installation, including slower than expected third-party approvals between utilities and landowners of sites where charger stations will be located.

Legal Proceedings

In the ordinary course of the Company’s business, the Company may be subject to lawsuits, investigations, claims and proceedings, including, but not limited to, contractual disputes or employment, health and safety matters. Although the outcome of any potential future litigation is uncertain, the Company believes it has adequate insurance coverage in the event of any future litigation or disputes. Although the Company is not currently facing any material pending or threatened litigation, future events or circumstances, currently unknown to management, may potentially have a material effect on its financial position, liquidity or results of operations in any future reporting period.

Purchase Commitments

As of September 30, 2022, EVgo had $10.7 million in outstanding purchase order commitments to EVgo’s contract manufacturers and component suppliers for charging equipment. In certain instances, EVgo is permitted to cancel, reschedule or adjust these orders.