2022 Lease

In March 2021, as amended in November 2021, the Company entered into a non-cancelable operating lease for a facility in San Diego, California (the 2022 Lease). The 2022 Lease had an initial term that ended in May 2024, although this was subsequently amended such that this lease now ends on that date occurring 14 days after the lease commencement date for the 2024 Lease (see below). The 2022 Lease provides for the rental of lab and office space, contains rent escalation provisions, and requires the Company to pay a portion of the operating costs related to the underlying multitenant facility. Rental payments under the 2022 Lease commenced in mid-January 2022. Based on information obtained from its landlord, the Company has recorded a right-of-use (ROU) asset and an associated lease obligation for the lab and office space leased under the 2022 Lease. The net ROU asset of $0.8 million and associated lease obligation of $0.8 million are reflected in the Company’s balance sheet as of June 30, 2024 and are estimates that will change should there be a change in the anticipated occupancy date of the property and associated campus underlying the 2024 Lease. The Company’s estimated incremental borrowing rate of approximately 8.0% was used in its present value calculation as the 2022 Lease does not have a stated rate and the implicit rate was not readily determinable.

As of June 30, 2024, future minimum lease payments under the 2022 Lease are expected to total $0.8 million, including imputed interest of approximately $7,000. All future payments under the 2022 Lease are expected to occur in 2024.

2024 Lease

In December 2021, the Company entered into a non-cancelable facility lease for approximately 80,000 square feet of lab and office space in La Jolla, California (the 2024 Lease). The facility to be occupied by the Company under the 2024 Lease will be built to the Company’s specifications; the 2024 Lease agreement includes tenant improvement allowances totaling $22.0 million, repayment of which is included in the future minimum lease payments called for under the agreement.

As of June 30, 2024, although construction of the property underlying the 2024 Lease is underway, the commencement date of the 2024 Lease has not yet been determined. At completion of construction, the Company will occupy the facility for a 120-month term, with payments under the lease commencing after a six-month rent abatement period and continuing through the conclusion of the term. As of June 30, 2024, the landlord has advised the Company that this property will be available for occupancy in October 2024. This date is an estimate, which is subject to change based on the delivery of the property and its associated campus. The 2024 Lease includes base lease payments aggregating $71.9 million, as well as additional charges for common area maintenance and property taxes. The Company has the right to extend the term of the 2024 Lease for an additional 60 months.

Additionally, as a security deposit under this agreement, the Company is required to maintain a standby letter-of-credit in the amount of $0.5 million, which must remain in place until November 2034.

Operating Leases

The Company has made upfront payments under its lease agreements totaling $0.8 million, $0.5 million of which is included in other long-term assets on the balance sheet as of June 30, 2024 and December 31, 2023.

 