The Company’s lease portfolio primarily comprises operating leases for office, laboratory, non-good manufacturing practices pilot plant manufacturing, and industrial space. These leases contain various rent abatement periods, after which they require monthly lease payments that may be subject to annual increases throughout the lease term. Certain leases include options to extend the term. The renewal option is considered in the remaining lease term for the lease only when the Company is reasonably certain it will renew the lease. Certain leases provide the Company with the right to make tenant improvements, including the addition of laboratory space or build-out of manufacturing capabilities, and include a lease incentive allowance.

In June 2022, the Company entered into a lease agreement for 79,565 square feet of office, laboratory, and industrial space located in Bothell, Washington. The initial term of the lease is 16 years from the date the premises are delivered to the Company for construction of certain tenant improvements and includes the option to extend the lease for up to three additional five-year terms. The lease agreement also provides for up to $19.9 million for reimbursement of tenant improvements, as well as an additional $8.0 million for tenant improvements, available at the Company’s election, which the Company would be obligated to repay to the landlord monthly over the initial term of the lease with interest at a rate of 6.5% per annum. The Company is obligated to pay base rent of approximately $68.8 million over the initial term of the lease. In accordance with the lease agreement, the Company has obtained a letter of credit in the amount of $1.6 million. The Company will recognize the right-of-use asset and lease liability when the lease commences in January 2023.

In July 2021, the Company entered into a lease for industrial space located in Fremont, California (the Fremont facility), with the intent to establish and develop its manufacturing operations at the Fremont facility. However, the Company determined in June 2022 to establish and develop its manufacturing operations at the Bothell facility rather than the Fremont facility. The original right-of-use asset and lease liability for the Fremont facility was calculated assuming the Company would exercise its option to renew the lease for two additional five-year terms. The Company remeasured the lease for the Fremont facility due to the shorter expected lease term, which resulted in a $12.8 million reduction in the related right-of-use asset and lease liability. Additionally, for the twelve months ended December 30, 2022, the Company wrote-off $4.5 million of construction in progress costs incurred in connection with the Fremont facility in general and administrative expense.

The following table contains additional information related to the Company’s operating leases:

 

Location

 

Use

 

Approximate

Square Footage

 

Commencement Dates

 

Expiration Dates

Seattle, WA

 

Office/Laboratory

 

48,000

 

March 2019 to September 2020

 

December 2026 to April 2028

Cambridge, MA

 

Office/Laboratory

 

60,000

 

March 2019 to January 2022

 

December 2025 to February 2028

South San Francisco, CA

 

Office/Laboratory

 

100,000

 

December 2019 to April 2022

 

April 2024 to April 2030

Fremont, CA

 

Industrial

 

163,000

 

July 2021

 

November 2031

Rochester, NY

 

Office/Laboratory

 

3,000

 

January 2022

 

January 2025

Bothell, WA

 

Office/Laboratory/Industrial

 

80,000

 

January 2023

 

January 2039

 

Throughout the term of the lease agreements, the Company is responsible for paying certain operating costs in addition to rent, such as common area maintenance, taxes, utilities, and insurance. These additional charges are considered variable lease costs and are recognized in the period in which the costs are incurred.

The following table summarizes the Company’s lease costs:

 

 

 

Year Ended December 31,

 

 

 

2022

 

 

2021

 

 

2020

 

 

 

(in thousands)

 

Operating lease cost

 

$

23,881

 

 

$

16,425

 

 

$

10,757

 

Short-term lease cost

 

 

-

 

 

 

512

 

 

 

1,886

 

Variable lease cost

 

 

7,193

 

 

 

5,230

 

 

 

3,081

 

Total lease cost

 

$

31,074

 

 

$

22,167

 

 

$

15,724

 

 

As of December 31, 2022, the weighted-average remaining lease term was 6.2 years and the weighted-average IBR was 9.68%.

The following table reconciles the Company’s undiscounted operating lease cash flows by fiscal year to the present value of the operating lease liabilities as of December 31, 2022 (in thousands):

 

2023

 

$

23,523

 

2024

 

 

24,321

 

2025

 

 

24,298

 

2026

 

 

21,343

 

2027

 

 

18,736

 

2028 and thereafter

 

 

36,367

 

Total undiscounted lease payments

 

 

148,588

 

Less: imputed interest

 

 

(39,018

)

Less: tenant improvement allowances

 

 

(1,317

)

Present value of operating lease liabilities

 

 

108,253

 

Less: current portion of operating lease liabilities

 

 

(12,393

)

Operating lease liabilities, net of current portion

 

$

95,860