COMMITMENTS AND CONTINGENCIES (Details)
$ in Thousands
9 Months Ended
Oct. 17, 2025
USD ($)
Oct. 09, 2025
USD ($)
Feb. 19, 2025
USD ($)
Nov. 14, 2024
USD ($)
Jul. 15, 2024
USD ($)
Jul. 01, 2024
USD ($)
Jun. 20, 2024
USD ($)
Sep. 30, 2025
USD ($)
action
Dec. 31, 2024
USD ($)
May 28, 2024
USD ($)
Commitments and Contingencies (Details) [Line Items]                    
Loss contingency, new claims filed | action               3    
Liens amount               $ 23,590    
Property, plant and equipment, net               524,016 $ 478,189  
Bank Acceptance Note                    
Commitments and Contingencies (Details) [Line Items]                    
Property, plant and equipment, net               21,559    
Inventories                    
Commitments and Contingencies (Details) [Line Items]                    
Purchase obligation               44,140    
Capital Commitments                    
Commitments and Contingencies (Details) [Line Items]                    
Capital commitments               $ 10,111    
DPR Construction GP                    
Commitments and Contingencies (Details) [Line Items]                    
Loss contingency, damages sought, value             $ 19,950      
Loss contingency, damages sought, retainage             $ 1,566      
Faith Technologies, Inc.                    
Commitments and Contingencies (Details) [Line Items]                    
Loss contingency, damages sought, value         $ 1,699          
Bernhard MCC, LLC. vs. U.S. Engineering Innovations, LLC, DPR Construction, Microvast, Inc. and the Industrial Development Board of the County of Montgomery                    
Commitments and Contingencies (Details) [Line Items]                    
Liens amount                   $ 5,681
Virginia Transformer Corp. v. Microvast, Inc.and the Industrial Development Board of the County of Montgomery, Tennessee                    
Commitments and Contingencies (Details) [Line Items]                    
Liens amount           $ 1,769        
Settlement payment           212        
Payment sought by hacker           $ 425        
Grupo Basan Barba Santana, S.A. De C.V.                    
Commitments and Contingencies (Details) [Line Items]                    
Loss contingency, receivable     $ 3,500              
Litigation settlement, termination costs     2,400              
Litigation settlement, fees and interest     $ 2,600              
Clenera Battery Holdco LLC v. Microvast, Inc.                    
Commitments and Contingencies (Details) [Line Items]                    
Litigation settlement, refund sought       $ 36,000            
Clenera Battery Holdco LLC v. Microvast, Inc. | Subsequent Event                    
Commitments and Contingencies (Details) [Line Items]                    
Loss contingency, damages sought, value $ 6,800                  
Litigation settlement, amount awarded to other party   $ 36,000