Plant, Equipment, and Mine Development, Net
9 Months Ended
Sep. 30, 2021
Property, Plant and Equipment [Abstract]  
Plant, Equipment, and Mine Development, Net Plant, Equipment, and Mine Development, Net
The following table provides the components of Plant, equipment, and mine development, net (dollars in thousands):
Depreciation Life
or Method
September 30,
2021
December 31,
2020
Leach padsUnits-of-production$17,708 $17,432 
Process equipment
5 - 15 years
17,597 16,065 
Buildings and leasehold improvements
10 years
10,507 10,507 
Mine equipment
5 - 7 years
8,242 5,961 
Vehicles
3 - 5 years
1,454 991 
Furniture and office equipment
7 years
352 322 
Mine developmentUnits-of-production6,673 756 
Mineral propertiesUnits-of-production37 37 
Construction in progress and other36,529 33,185 
$99,099 $85,256 
Less, accumulated depreciation and amortization(29,322)(25,033)
Total$69,777 $60,223 
Mine development
During the nine months ended September 30, 2021, the Company incurred costs of $5.9 million related to metallurgical testing and drill work.
Construction in progress and other
The primary project included in construction in progress as of September 30, 2021 was construction of a new larger leach pad, which continued through February 2021 at which time construction was suspended ($3.2 million, including $0.7 million of capitalized interest), resulting in construction costs for the new larger leach pad of $34.1 million since commencing construction in 2020.