HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS

For the three and nine months ended September 30, 2018 and 2017

The following Management’s Discussion and Analysis (MD&A) of the financial condition and results of operations should be read together with the condensed interim unaudited consolidated financial statements and accompanying notes thereto (Consolidated Financial Statements) of Hydro One Limited (Hydro One or the Company) for the three and nine months ended September 30, 2018, as well as the Company’s audited consolidated financial statements and MD&A for the year ended December 31, 2017. The Consolidated Financial Statements are presented in Canadian dollars and have been prepared in accordance with United States (US) Generally Accepted Accounting Principles (GAAP). All financial information in this MD&A is presented in Canadian dollars, unless otherwise indicated.

The Company has prepared this MD&A in accordance with National Instrument 51-102 – Continuous Disclosure Obligations of the Canadian Securities Administrators. This MD&A provides information for the three and nine months ended September 30, 2018, based on information available to management as of November 7, 2018.

CONSOLIDATED FINANCIAL HIGHLIGHTS AND STATISTICS

 

    

Three months ended September 30

 

   

Nine months ended September 30

 

 
  (millions of dollars, except as otherwise noted)    2018      2017      Change     2018      2017     Change  

Revenues

     1,606        1,522        5.5     4,659        4,551       2.4

Purchased power

     733        675        8.6     2,158        2,213       (2.5 %) 

Revenues, net of purchased power1

     873        847        3.1     2,501        2,338       7.0

Operation, maintenance and administration costs (OM&A)

     271        277        (2.2 %)      797        822       (3.0 %) 

Depreciation and amortization

     213        209        1.9     620        603       2.8

Financing charges

     149        114        30.7     336        320       5.0

Income tax expense

     41        23        78.3     115        73       57.5

Net income attributable to common shareholders of Hydro One

     194        219        (11.4 %)      616        503       22.5

Basic earnings per common share (EPS)

     $0.33        $0.37        (10.8 %)      $1.03        $0.85       21.2

Diluted EPS

     $0.32        $0.37        (13.5 %)      $1.03        $0.84       22.6

Basic adjusted non-GAAP EPS (Adjusted EPS)1

     $0.38        $0.40        (5.0 %)      $1.06        $0.88       20.5

Diluted Adjusted EPS1

     $0.38        $0.40        (5.0 %)      $1.06        $0.88       20.5

Net cash from operating activities

     508        442        14.9     1,176        1,193       (1.4 %) 

Funds from operations (FFO)1

     418        385        8.6     1,211        1,177       2.9

Capital investments

     402        380        5.8     1,108        1,136       (2.5 %) 

Assets placed in-service

     239        294        (18.7 %)      861        859       0.2

Transmission: Average monthly Ontario 60-minute peak demand (MW)

     22,759        20,857        9.1     20,841        19,801       5.3

Distribution:     Electricity distributed to Hydro One customers (GWh)

     6,817        6,226        9.5     20,334        19,046       6.8
                                     2018     2017  

Debt to capitalization ratio2

                                        53.1     52.9

 

1 

See section “Non-GAAP Measures” for description and reconciliation of basic and diluted Adjusted EPS, FFO and Revenues, net of purchased power.

 

2 

Debt to capitalization ratio has been presented at September 30, 2018 and December 31, 2017, and has been calculated as total debt (includes total long-term debt, convertible debentures and short-term borrowings, net of cash and cash equivalents) divided by total debt plus total shareholders’ equity, including preferred shares but excluding any amounts related to noncontrolling interest.

OVERVIEW

For the nine months ended September 30, 2018, Hydro One’s business segments accounted for the Company’s total revenues, net of purchased power, as follows:

 

      Transmission      Distribution      Other  

Percentage of Company’s total revenues, net of purchased power

     54%        45%        1%  

At September 30, 2018, Hydro One’s business segments accounted for the Company’s total assets as follows:    

 

      Transmission      Distribution      Other  

Percentage of Company’s total assets

     52%        35%        13%  

 

   1   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

 

RESULTS OF OPERATIONS

Net Income

Net income attributable to common shareholders for the quarter ended September 30, 2018 of $194 million is a decrease of $25 million or 11.4% from the prior year. Significant influences on net income included:

 

   

increase in transmission and distribution revenues due to higher energy consumption resulting from favourable weather;

 

   

lower transmission revenues driven by the timing of Ontario Energy Board (OEB)‘s decision on the 2017-2018 transmission rate filing, which resulted in recognition of year-to-date revenues in the third quarter of 2017, partially offset by increased OEB-approved transmission rates;

 

   

lower OM&A costs primarily resulting from lower costs related to the acquisition of Avista Corporation (Merger), savings related to the renewed information technology (IT) outsourced contract, lower customer programs costs; partially offset by higher corporate support costs;

 

   

higher financing charges primarily due to revaluation losses on the deal-contingent foreign exchange forward contract, and an increase in interest expense on long-term debt and on the convertible debentures issued in August 2017; and

 

   

higher income tax expense primarily attributable to a combination of an increase in the estimated annual effective tax rate (ETR) for 2018 arising from higher forecast earnings coupled with a corresponding decrease in the estimated annual ETR for 2017 arising from lower forecast earnings.

Net income attributable to common shareholders for the nine months ended September 30, 2018 of $616 million is an increase of $113 million or 22.5% from the prior year. Significant influences on net income included:

 

   

increase in transmission and distribution revenues due to higher energy consumption resulting from favourable weather;

 

   

higher transmission revenues driven by increased OEB-approved transmission rates;

 

   

lower OM&A costs primarily resulting from lower costs related to the acquisition of Avista Corporation, savings related to the renewed IT outsourced contract, lower customer programs costs, lower storm restoration costs and timing of work programs; partially offset by higher project write-offs due to revision of asset replacement strategies and alternatives not pursued;

 

   

higher financing charges primarily due to an increase in interest expense incurred on the convertible debentures issued in August 2017 and on short-term notes payable, partially offset by revaluation gains on the deal-contingent foreign exchange forward contract and a decrease in interest expense on long-term debt; and

 

   

higher income tax expense primarily attributable to a combination of an increase in the estimated annual ETR for 2018 arising from higher forecast earnings coupled with a corresponding decrease in the estimated annual ETR for 2017 arising from lower forecast earnings.

EPS and Adjusted EPS

EPS was $0.33 and $1.03 in the three and nine months ended September 30, 2018, respectively, compared to EPS of $0.37 and $0.85 in the comparable periods last year. The changes in EPS were driven by changes in net income for the three and nine months ended September 30, 2018, as discussed above. Adjusted EPS, which adjusts for income and costs related to Avista Corporation acquisition, including the gains and losses on the deal-contingent foreign exchange forward contract, was $0.38 and $1.06 in the three and nine months ended September 30, 2018, compared to $0.40 and $0.88 in the comparable periods last year. The changes in Adjusted EPS were driven by changes in net income for the three and nine months ended September 30, 2018, as discussed above, but exclude the impact of items related to Avista Corporation acquisition. See section “Non-GAAP Measures” for description of Adjusted EPS.

 

   2   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

 

Revenues

 

    

Three months ended September 30

 

   

Nine months ended September 30

 

 
  (millions of dollars, except as otherwise noted)    2018      2017      Change     2018      2017      Change  

Transmission

     493        471        4.7     1,344        1,199        12.1

Distribution

     1,103        1,040        6.1     3,284        3,317        (1.0 %) 

Other

     10        11        (9.1 %)      31        35        (11.4 %) 

Total revenues

     1,606        1,522        5.5     4,659        4,551        2.4

Transmission

     493        471        4.7     1,344        1,199        12.1

Distribution, net of purchased power

     370        365        1.4     1,126        1,104        2.0

Other

     10        11        (9.1 %)      31        35        (11.4 %) 

Total revenues, net of purchased power

     873        847        3.1     2,501        2,338        7.0

Transmission: Average monthly Ontario 60-minute peak demand (MW)

     22,759        20,857        9.1     20,841        19,801        5.3

Distribution:     Electricity distributed to Hydro One customers (GWh)

     6,817        6,226        9.5     20,334        19,046        6.8

Transmission Revenues

Transmission revenues increased by 4.7% for the quarter ended September 30, 2018 primarily due to the following:

 

   

higher average monthly Ontario 60-minute peak demand primarily driven by favourable weather in the summer of 2018; and

 

   

increased 2018 allowed return on equity (ROE) for the transmission business; partially offset by

 

   

lower revenues driven by the timing of the OEB’s decision on the 2017-2018 transmission rate filing, which resulted in recognition of year-to-date revenues in the third quarter of 2017; partially offset by increased OEB-approved transmission rates for 2018; and

 

   

lower deferred regulatory adjustments.

The increase of 12.1% in transmission revenues for the nine months ended September 30, 2018 was primarily due to the following:

 

   

higher average monthly Ontario 60-minute peak demand primarily driven by favourable weather in May, June and the summer of 2018;

 

   

higher revenues driven by increased OEB-approved transmission rates for 2018; and

 

   

increased 2018 allowed ROE for the transmission business; partially offset by

 

   

lower deferred regulatory adjustments.

Distribution Revenues, Net of Purchased Power

Distribution revenues, net of purchased power, increased by 1.4% for the quarter ended September 30, 2018 primarily due to the following:

 

   

higher energy consumption resulting from favourable weather in the summer of 2018; partially offset by

 

   

lower external revenues in 2018 primarily due to revenues received in 2017 for Hurricane Irma restoration assistance efforts in Florida. These restoration efforts had no impact on the Company’s net income, as related costs were recorded in distribution OM&A during the third quarter of 2017; and

 

   

lower deferred regulatory adjustments.

The increase of 2.0% in distribution revenues, net of purchased power, for the nine months ended September 30, 2018 was the result of similar factors as noted above.

OM&A Costs

 

    

Three months ended September 30

 

   

Nine months ended September 30

 

 
  (millions of dollars)    2018      2017      Change     2018      2017      Change  

Transmission

     95        95            295        296        (0.3 %) 

Distribution

     150        149        0.7     435        447        (2.7 %) 

Other

     26        33        (21.2 %)      67        79        (15.2 %) 
       271        277        (2.2 %)      797        822        (3.0 %) 

Transmission OM&A Costs

Transmission OM&A costs for the quarter ended September 30, 2018 were comparable to prior year, and were primarily impacted by the following:

 

   

insurance proceeds received for the National Research Council (NRC) transformer station;

 

   

lower costs related to the renewed IT outsourced contract;

 

   3   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

 

   

higher volume of work on vegetation management;

 

   

higher project write-offs due to revision of asset replacement strategies and alternatives not pursued; and

 

   

higher corporate support costs.

Transmission OM&A costs for the nine months ended September 30, 2018 were comparable to prior year, and were primarily impacted by factor noted above, as well as lower volume of work on environmental management.

Distribution OM&A Costs

Distribution OM&A costs for the quarter ended September 30, 2018 were comparable to prior year, and were primarily impacted by:

 

   

lower storm restoration costs in 2018 as a result of Hurricane Irma restoration assistance efforts in Florida in 2017. These restoration efforts had no impact on the Company’s net income, as related revenues were recorded in distribution revenues during the third quarter of 2017;

 

   

lower costs associated with customer programs, primarily related to the Call Center and a lower volume of field collections and investigations as a result of extended winter moratorium;

 

   

lower costs related to the renewed IT outsourced contract;

 

   

higher spend on vegetation management;

 

   

higher volume of emergency calls; and

 

   

higher corporate support costs.

The decrease of 2.7% in distribution OM&A costs for the nine months ended September 30, 2018 was primarily due to the following:

 

   

lower storm restoration costs;

 

   

lower costs associated with customer programs, primarily related to Call Center, less demand for low income assistance program and a lower volume of field collections and investigations as a result of extended winter moratorium;

 

   

lower costs related to the renewed IT outsourced contract;

 

   

lower bad debt expense; partially offset by

 

   

project and inventory write-offs due to revision of asset replacement strategies, alternatives not pursued, and obsolete inventory and technology; and

 

   

higher volume of emergency calls.

Other OM&A Costs

The decrease in other OM&A costs for the quarter and nine months ended September 30, 2018 was primarily due to lower consulting and contract costs related to the acquisition of Avista Corporation, partially offset by higher labour costs.

Financing Charges

The increase of $35 million or 30.7% in financing charges for the quarter ended September 30, 2018 was primarily due to the following:

 

   

an unrealized loss recorded in the third quarter of 2018 due to revaluation of the deal-contingent foreign exchange forward contract related to the Avista Corporation merger;

 

   

an increase in interest expense related to the convertible debentures issued in August 2017; and

 

   

an increase in interest expense on long-term debt driven by higher long-term debt balance outstanding during the third quarter of 2018.

The increase of $16 million or 5.0% in financing charges for the nine months ended September 30, 2018 was primarily due to the following:

 

   

an increase in interest expense related to the convertible debentures issued in August 2017; and

 

   

an increase in interest expense on short-term notes payable driven by higher weighted average interest rates and balance of short-term notes outstanding in 2018; partially offset by

 

   

an unrealized gain recorded in 2018 due to revaluation of the deal-contingent foreign exchange forward contract related to the Avista Corporation merger; and

 

   

a decrease in interest expense on long-term debt driven by lower long-term debt balance outstanding in 2018.

Income Tax Expense

Income tax expense was $41 million and $115 million for the three and nine months ended September 30, 2018, respectively, compared to $23 million and $73 million in the same periods of 2017. The Company realized an ETR for the three and nine months ended September 30, 2018 of approximately 17.1% and 15.4%, respectively, compared to approximately 9.3% and 12.3% in the same periods last year.

 

   4   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

As prescribed by the regulators, the Company recovers income taxes and is required to accrue its tax expense based on the tax liability determined without accounting for temporary differences recoverable in the future from customers. The annual ETR is re-forecast at each interim reporting period and can fluctuate based on the change in forecast annual earnings at the conclusion of each reporting period.

The increase in income tax expense for the three and nine months ended September 30, 2018 was primarily attributable to a combination of an increase in the estimated annual ETR for 2018 arising from higher forecast earnings coupled with a corresponding decrease in the estimated annual ETR for 2017 arising from lower forecast earnings.

Common Share Dividends

In 2018, the Company declared and paid cash dividends to common shareholders as follows:

 

  Date Declared    Record Date    Payment Date    Amount per Share     

Total Amount  

(millions of dollars)  

 

February 12, 2018

   March 13, 2018    March 29, 2018      $0.22        131    

May 14, 2018

   June 12, 2018    June 29, 2018      $0.23        137    

August 13, 2018

   September 11, 2018    September 28, 2018      $0.23        137    
                          405    

Following the conclusion of the third quarter of 2018, the Company declared a cash dividend to common shareholders as follows:

 

  Date Declared    Record Date    Payment Date    Amount per Share     

Total Amount  

(millions of dollars)  

 

  November 7, 2018

   December 11, 2018    December 31, 2018      $0.23        137    

QUARTERLY RESULTS OF OPERATIONS

 

Quarter ended (millions of dollars, except EPS)     Sep 30, 2018      Jun 30, 2018      Mar 31, 2018      Dec 31, 2017      Sep 30, 2017      Jun 30, 2017      Mar 31, 2017      Dec 31, 2016    

Revenues

     1,606        1,477        1,576        1,439        1,522        1,371        1,658        1,614    

Purchased power

     733        674        751        662        675        649        889        858    

Revenues, net of purchased power

     873        803        825        777        847        722        769        756    

Net income to common shareholders

     194        200        222        155        219        117        167        128    

Basic EPS

     $0.33        $0.34        $0.37        $0.26        $0.37        $0.20        $0.28        $0.22    

Diluted EPS

     $0.32        $0.33        $0.37        $0.26        $0.37        $0.20        $0.28        $0.21    

Basic Adjusted EPS1

     $0.38        $0.33        $0.35        $0.29        $0.40        $0.20        $0.28        $0.22    

Diluted Adjusted EPS1

     $0.38        $0.32        $0.35        $0.28        $0.40        $0.20        $0.28        $0.21    

 

1 

See section “Non-GAAP Measures” for description of Adjusted EPS.

Variations in revenues and net income over the quarters are primarily due to the impact of seasonal weather conditions on customer demand and market pricing, as well as timing of regulatory decisions.

CAPITAL INVESTMENTS

The Company makes capital investments to maintain the safety, reliability and integrity of its transmission and distribution system assets and to provide for the ongoing growth and modernization required to meet the expanding and evolving needs of its customers and the electricity market. This is achieved through a combination of sustaining capital investments, which are required to support the continued operation of Hydro One’s existing assets, and development capital investments, which involve both additions to existing assets and large scale projects such as new transmission lines and transmission stations.

Assets Placed In-Service

The following table presents Hydro One’s assets placed in-service during the three and nine months ended September 30, 2018 and 2017:

 

    

Three months ended September 30

 

    

Nine months ended September 30 

 

 
(millions of dollars)    2018      2017      Change      2018      2017      Change   

Transmission

     112        120        (6.7%)        466        367        27.0%    

Distribution

     126        172        (26.7%)        389        482        (19.3%)   

Other

     1        2        (50.0%)        6        10        (40.0%)   

Total assets placed in-service

     239        294        (18.7%)        861        859        0.2%    

 

   5   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Transmission Assets Placed In-Service

Transmission assets placed in-service decreased by $8 million or 6.7% during the third quarter of 2018 primarily due to the following:

 

   

timing of assets placed in-service for station sustainment investments, including Richview transmission station, Lakehead transmission station, and Kirkland Lake transmission station, partially offset by Beach transmission station;

 

   

lower volume of overhead lines and component replacement work placed in-service;

 

   

lower volume of fleet and work equipment purchases;

 

   

lower volume of wood pole replacements; partially offset by

 

   

higher volume of spare transformer purchases; and

 

   

higher volume of replacement work on transmission facilities as a result of the wind storm.

Transmission assets placed in-service increased by $99 million or 27.0% during the nine months ended September 30, 2018 primarily due to the factors listed above, as well as the following:

 

   

substantial completion of major development work at the Clarington transmission station; partially offset by

 

   

timing of assets placed in-service for station sustainment investments, including Aylmer transmission station, Goderich transmission station, DeCew Falls switching station, Nepean transmission station, and Hinchinbrooke switching station; partially offset by NRC transmission station, and Bruce A transmission station;

 

   

the completion of the Field Workforce Optimization (Move-to-Mobile) project in June 2017; and

 

   

cumulative investments for major local area supply projects at the Manby and Hawthorne transmission stations placed in-service in 2017.

Distribution Assets Placed In-Service

Distribution assets placed in-service decreased by $46 million or 26.7% during the third quarter of 2018 primarily due to the following:

 

   

the completion of the Outage Response Management System (ORMS) project in the third quarter of 2017;

 

   

lower volume of fleet and work equipment purchases;

 

   

timing of assets that were placed in-service for system capability reinforcement projects;

 

   

lower volume of distribution station refurbishments;

 

   

lower volume of wood pole replacements; and

 

   

higher volume of lines large sustainment carryover work in the third quarter of 2017; partially offset by

 

   

higher volume of emergency power and storm restorations work.

Distribution assets placed in-service decreased by $93 million or 19.3% during the nine months ended September 30, 2018 primarily due to the factors listed above, as well as the following:

 

   

the completion of the Move-to-Mobile project in June 2017; and

 

   

completion of an operation center in Bolton in February 2017; partially offset by

 

   

increased investments for meter sustainment work were placed in-service;

 

   

cumulative investments that were placed in-service for the Source-to-Order Transformation project, which aims to modernize the Company’s sourcing and procurement capabilities; and

 

   

the completion of the Bill Redesign project, which included investments in application enhancements and software upgrades.

Capital Investments

The following table presents Hydro One’s capital investments during the three and nine months ended September 30, 2018 and

2017:

 

    

Three months ended September 30

 

    

Nine months ended September 30

 

 
  (millions of dollars)    2018      2017      Change      2018      2017      Change  

Transmission

                 

Sustaining

     221        189        16.9%         587        548        7.1%   

Development

     30        32        (6.3%)        77        108        (28.7%)  

Other

     10        19        (47.4%)        29        45        (35.6%)  
       261        240        8.8%         693        701        (1.1%)  

Distribution

                 

Sustaining

     72        63        14.3%         232        215        7.9%   

Development

     59        53        11.3%         153        162        (5.6%)  

Other

     7        22        (68.2%)        24        50        (52.0%)  
       138        138        —%         409        427        (4.2%)  

Other

     3        2        50.0%         6        8        (25.0%)  

Total capital investments

     402        380        5.8%         1,108        1,136        (2.5%)  

 

   6   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

 

Transmission Capital Investments

Transmission capital investments increased by $21 million or 8.8% during the third quarter of 2018. Principal impacts on the levels of capital investments included:

 

   

higher volume of demand work associated with equipment failures;

 

   

higher volume of overhead lines refurbishments and replacements;

 

   

timing of project activities on major development projects, including the Niagara Reinforcement and Lake Superior Link projects, as well as work at Brant, Holland, and Clarington transmission stations;

 

   

higher volume of work required to adhere to the North American Electric Reliability Corporation (NERC) Critical Infrastructure Protection (Cyber Security) standards; and

 

   

higher volume of IT upgrades and enhancements primarily related to the Private Cloud Data Center project in support of the modernization of Hydro One’s IT infrastructure; partially offset by

 

   

lower volume of transmission station refurbishments and replacements work;

 

   

lower spend on load customer connections due to the completion of work at Leamington transmission station in 2017; partially offset by timing of work at Enfield transmission station; and

 

   

decreased investment in fleet and work equipment purchases as a result of fleet standardization and asset specification review.

Transmission capital investments decreased by $8 million or 1.1% during the nine months ended September 30, 2018, primarily due to the factors listed above, as well as the following:

 

   

lower spend on load customer connections attributable to higher capital contribution received from customers;

 

   

timing of work on the Hawthorne transmission station;

 

   

lower volume of wood pole replacements; and

 

   

the completion of the Move-to-Mobile project in second quarter of 2017; partially offset by

 

   

higher volume of spare transformer purchases.

Distribution Capital Investments

Distribution capital investments for the quarter ended September 30, 2018 were comparable to prior year, and were primarily impacted by:

 

   

decreased investments in fleet and work equipment purchases as a result of fleet standardization and asset specification review;

 

   

lower volume of wood pole replacements;

 

   

lower volume of distribution lines and station refurbishments and replacements work;

 

   

increased volume of emergency power and storm restorations work due to higher storm activity in 2018; and

 

   

higher volume of IT upgrades and enhancements primarily related to the Private Cloud Data Center project in support of the modernization of Hydro One’s IT infrastructure.

Distribution capital investments decreased by $18 million or 4.2% during the nine months ended September 30, 2018, primarily due to the factors listed above, as well as the following:

 

   

lower spend on Advanced Distribution System infrastructures;

 

   

the completion of the Move-to-Mobile project in second quarter of 2017; and

 

   

lower spend on new connections and upgrades.

 

   7   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Major Transmission Capital Investment Projects

The following table summarizes the status of significant transmission projects as at September 30, 2018:

 

  Project Name      Location      Type    Anticipated
In-Service Date
     Estimated
Cost
    Capital Cost
To Date
 
               (year)      (millions of dollars)  

Development Projects:

           

Supply to Essex County Transmission Reinforcement

  

Windsor-Essex area Southwestern Ontario

  

New transmission line and station

     2018        55 1        54  

Clarington Transmission Station

  

Oshawa area Southwestern Ontario

  

New transmission station

     2018        240 1       235  

Niagara Reinforcement Project

  

Niagara area Southwestern Ontario

  

New transmission line

     2019        130       114  

East-West Tie Station Expansion

  

Northern Ontario

  

New transmission connection and station expansion

     2021        157       12  

Northwest Bulk Transmission Line

 

  

Thunder Bay-Atikokan Northwestern Ontario

 

  

New transmission line

     2024        350       1  

Sustainment Projects:

             

Richview Transmission Station Circuit Breaker Replacement

  

Toronto Southwestern Ontario

  

Station sustainment

     2019        104       96  

Bruce A Transmission Station

  

Tiverton Southwestern Ontario

  

Station sustainment

     2020        138       119  

Beck #2 Transmission Station Circuit Breaker Replacement

  

Niagara area Southwestern Ontario

  

Station sustainment

     2022        114       61  

Lennox Transmission Station Circuit Breaker Replacement

 

  

Napanee Southeastern Ontario

  

Station sustainment

     2023        98       56  

 

1

Major portions of the Supply to Essex County Transmission Reinforcement and Clarington Transmission Station projects were completed and placed in-service. Work on certain minor portions of the project continues in the second half of 2018.

Future Capital Investments

Following is a summary of estimated capital investments by Hydro One over the years 2018 to 2022. The Company’s estimates are based on management’s expectations of the amount of capital expenditures that will be required to provide transmission and distribution services that are efficient, reliable, and provide value for customers, consistent with the OEB’s Renewed Regulatory Framework. The 2019 transmission capital investments estimates differ from the prior year disclosures, representing a decrease of $158 million to reflect Hydro One’s recent one-year inflation-based application for 2019 transmission rates. The projections and the timing of 2020-2022 expenditures are subject to approval by the OEB.

The following table summarizes Hydro One’s annual projected capital investments for 2018 to 2022, by business segment:

 

  (millions of dollars)    2018      2019      2020      2021      2022  

Transmission

     1,010        1,059        1,278        1,486        1,404  

Distribution

     641        751        715        719        805  

Other

     9        8        6        9        8  

Total capital investments

     1,660        1,818        1,999        2,214        2,217  

The following table summarizes Hydro One’s annual projected capital investments for 2018 to 2022, by category:    

 

  (millions of dollars)    2018      2019      2020      2021      2022  

Sustainment

     1,103        1,040        1,328        1,547        1,608  

Development

     340        523        487        490        430  

Other1

     217        255        184        177        179  

Total capital investments

     1,660        1,818        1,999        2,214        2,217  

 

1

“Other” capital expenditures consist of special projects, such as those relating to IT.    

 

   8   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

 

SUMMARY OF SOURCES AND USES OF CASH

Hydro One’s primary sources of cash flows are funds generated from operations, capital market debt issuances and bank credit facilities that are used to satisfy Hydro One’s capital resource requirements, including the Company’s capital expenditures, servicing and repayment of debt, and dividend payments.

 

     Three months ended
September 30
    Nine months ended
September 30
 
  (millions of dollars)    2018     2017     2018     2017  

Cash provided by operating activities

     508       442       1,176       1,193  

Cash provided by (used in) financing activities

     (746     529       487       506  

Cash used in investing activities

     (394     (382     (1,075     (1,127

Increase (decrease) in cash and cash equivalents

     (632     589       588       572  

Cash provided by operating activities

Cash from operating activities for the third quarter of 2018 increased by $66 million compared to the third quarter of 2017, were impacted by various factors, including higher cash earnings, and favourable changes in non-cash balances related to operations. Cash from operating activities for the nine months ended September 30, 2018 decreased by $17 million compared to the same period in 2017, were impacted by various factors, including improved collection of accounts receivables in 2017 that reached a stabilized level in 2018, and disposition of certain regulatory variance and deferral accounts in 2018, partially offset by higher cash earnings in 2018.

Cash provided by financing activities

Sources of cash

 

   

During the nine months ended September 30, 2018, the Company issued $1,400 million of long-term debt, all in the second quarter, compared to no long-term debt issued in the prior year.

 

   

The Company received proceeds of $445 million and $2,987 million from the issuance of short-term notes in the three and nine months ended September 30, 2018, respectively, compared to $1,232 million and $2,810 million received in the same periods last year.

 

   

During the three and nine months ended September 30, 2017, the Company issued $513 million of convertible debentures, gross of $27 million financing costs, compared to no convertible debenture issuances in 2018.

Uses of cash

 

   

Dividends paid in the three and nine months ended September 30, 2018 were $141 million and $418 million, respectively, compared to dividends of $135 million and $400 million paid in the same periods last year.

 

   

The Company repaid $1,049 million and $3,469 million of short-term notes in the three and nine months ended September 30, 2018, respectively, compared to $1,053 million and $2,385 million repaid in the same periods last year.

Cash used in investing activities

Uses of cash

 

   

Capital expenditures were $13 million higher in the third quarter of 2018 and $45 million lower year-to-date 2018, primarily due to volume and timing of capital investment work.

LIQUIDITY AND FINANCING STRATEGY

Short-term liquidity is provided through funds from operations, Hydro One Inc.’s commercial paper program, and the Company’s consolidated bank credit facilities. Under the commercial paper program, Hydro One Inc. is authorized to issue up to $1.5 billion in short-term notes with a term to maturity of up to 365 days. At September 30, 2018, Hydro One Inc. had $444 million in commercial paper borrowings outstanding, compared to $926 million outstanding at December 31, 2017. In addition, the Company has revolving bank credit facilities (Operating Credit Facilities) with total availability of $2,550 million maturing in 2021 and 2022, with no amounts used at September 30, 2018 or December 31, 2017. The Company may use these credit facilities for working capital and general corporate purposes. The short-term liquidity under the commercial paper program, the Operating Credit Facilities and anticipated levels of funds from operations are expected to be sufficient to fund the Company’s normal operating requirements.

At September 30, 2018, the Company had long-term debt outstanding in the principal amount of $11,468 million which included $11,323 million of long-term debt issued by Hydro One Inc. and long-term debt in the principal amount of $145 million held by Hydro One Sault Ste. Marie LP (HOSSM). The majority of long-term debt issued by Hydro One Inc. has been issued under its Medium Term Note (MTN) Program. The maximum authorized principal amount of notes issuable under the current MTN Program prospectus filed in March 2018 is $4.0 billion. At September 30, 2018, $2.6 billion remained available for issuance until April 2020. The long-term debt consists of notes and debentures that mature between 2018 and 2064, and at September 30, 2018, had a weighted-average term to maturity of approximately 15.5 years and a weighted-average coupon rate of 4.1%.

 

   9   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

On June 18, 2018, Hydro One filed a short form base shelf prospectus (Universal Base Shelf Prospectus) with securities regulatory authorities in Canada to replace the universal base shelf prospectus that expired on April 30, 2018. The Universal Base Shelf Prospectus allows Hydro One to offer, from time to time in one or more public offerings, up to $4.0 billion of debt, equity or other securities, or any combination thereof, during the 25-month period ending on July 18, 2020. Hydro One filed the Universal Base Shelf Prospectus to provide the Company with financing flexibility going forward. Hydro One Holdings Limited, an indirect wholly-owned subsidiary of Hydro One, expects to file in the future a short form base shelf prospectus with securities regulatory authorities in Canada and the US for the purposes of funding a portion of the cash purchase price of the Merger.

Acquisition Credit Facilities

For the purpose of bridge financing for the pending acquisition of Avista Corporation, the Company secured a $1.0 billion non-revolving equity bridge credit facility, and a US$2.6 billion non-revolving debt bridge credit facility (Acquisition Credit Facilities) in June 2018. The equity bridge credit facility matures 90 days after the drawdown date and in any event not later than June 30, 2019. The debt bridge credit facility is available until March 31, 2019, and matures one year after the drawdown date. At September 30, 2018, no amounts have been drawn on the Acquisition Credit Facilities.

Hydro One is required to make prepayments of the Acquisition Credit Facilities in an amount equal to the net cash proceeds from any common equity, preferred equity, bond or other debt offerings, including the net proceeds from the final instalment of convertible debentures issued in August 2017, and any non-ordinary course asset sales by Hydro One and its subsidiaries, subject to certain exceptions. Any prepayment under the Acquisition Credit Facilities may not be re-borrowed. The Acquisition Credit Facilities agreements contain customary representations and warranties and affirmative and negative covenants of Hydro One that are consistent with those of Hydro One’s Operating Credit Facilities. If the Merger does not close, then these agreements will be cancelled.

To mitigate the foreign currency risk related to the portion of the Avista Corporation acquisition purchase price financed by the issuance of convertible debentures, in October 2017, the Company entered into a deal-contingent foreign exchange forward contract to convert $1.4 billion Canadian to US dollars. For the nine months ended September 30, 2018, an unrealized fair value gain of $25 million was recorded related to this contract, compared to an unrealized fair value loss of $3 million recorded for the year ended December 31, 2017. At September 30, 2018, the corresponding derivative asset was $22 million, compared to a derivative liability of $3 million at December 31, 2017.

The cash purchase price of the Merger and the Merger-related costs are expected to be financed at the closing of the Merger with a combination of some or all of the following sources: (i) net proceeds of the first instalment from the sale in August 2017 of $1.54 billion aggregate principal amount of 4.00% convertible debentures of the Company represented by instalment receipts; (ii) net proceeds of any subsequent bond or other offering; (iii) amounts drawn under the existing $250 million operating credit facility of the Company; (iv) amounts drawn under the $1 billion non-revolving equity bridge credit facility; (v) amounts drawn under the US $2.6 billion non-revolving debt bridge credit facility; (vi) net proceeds of any offering of securities from the Company’s Universal Base Shelf Prospectus; and (vii) existing cash on hand and other sources available to the Company.

Compliance

At September 30, 2018, the Company was in compliance with all financial covenants and limitations associated with the outstanding borrowings and credit facilities.

Credit Ratings

Following the announcement of the Avista Corporation transaction on July 19, 2017, various ratings organizations undertook a review of the Company’s and Hydro One Inc.’s debt ratings. These ratings organizations may take various actions, positive or negative. The Company cannot predict what actions rating agencies may take in the future. The failure to maintain the Company’s current credit ratings could adversely affect the Company’s financial condition and results of operations, and a downgrade in the Company’s credit ratings could restrict the Company’s ability to access debt capital markets and increase the Company’s cost of debt.

On June 20, 2018, Moody’s Investors Service (Moody’s) downgraded the long-term debt rating for Hydro One Inc. to “Baa1” from “A3”, and revised its outlook on Hydro One Inc. to stable from negative. In addition, Moody’s affirmed the existing “Prime-2” short-term debt rating for Hydro One Inc. Moody’s no longer assigns any probability of extraordinary support from the Province of Ontario (Province) in Hydro One Inc.’s credit analysis which has led to the downgrade.

On June 15, 2018, S&P Global Ratings (S&P) placed its ratings on the Company and Hydro One Inc. on CreditWatch negative reflecting the likelihood of a one-notch downgrade to both companies due to the Avista Corporation transaction. On July 18, 2018, S&P released an update maintaining the CreditWatch negative placement, which continued to reflect the likelihood of a one-notch downgrade in the Company and Hydro One Inc.‘s issuer credit rating of “A” due to the Avista Corporation transaction, and also incorporated the possibility that the Company’s governance structure could result in an additional one-notch downgrade if S&P concludes that recent developments related to the retirement of the Company’s Chief Executive Officer (CEO) and the replacement of the Company’s Board of Directors (Board) adversely impact management decision making and fails to promote the interests of all stakeholders. See section “Hydro One Board of Directors and Executive Officers” for more information.

 

   10   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

On September 13, 2018, S&P lowered its issuer credit ratings on the Company to “A-” from “A”. At the same time, S&P lowered the issue-level rating on Hydro One Inc.‘s senior unsecured debt by one notch to “A-” from “A” and lowered the rating on Hydro One Inc.‘s commercial paper program by one notch to “A-1(low)” from “A-1(mid)” on the Canadian National Scale. All ratings remain on CreditWatch where S&P placed them with negative implications on June 15, 2018. The one-notch downgrade reflects S&P’s reassessment of Hydro One’s management and governance structure, which has weakened following the Province’s decision to exert its influence on the Company’s compensation structure through legislation, potentially promoting the interests and priorities of one owner above those of other stakeholders.

The following tables present the Company’s and Hydro One Inc.‘s credit ratings at September 30, 2018:

Hydro One

 

  Rating Agency    Corporate Credit
Rating
     

S&P

   A-   

 

Hydro One Inc.

 

 Rating Agency    Short-term Debt
Rating
  Long-term Debt
Rating
    
 DBRS Limited    R-1 (low)   A (high)  
 Moody’s    Prime-2   Baa1  
 S&P    A-1 (low)   A-  

 

OTHER OBLIGATIONS

Off-Balance Sheet Arrangements

There are no off-balance sheet arrangements that have, or are reasonably likely to have, a material current or future effect on the Company’s financial condition, changes in financial condition, revenues or expenses, results of operations, liquidity, capital expenditures or capital resources.

 

   11   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Summary of Contractual Obligations and Other Commercial Commitments

The following table presents a summary of Hydro One’s debt and other major contractual obligations and commercial commitments:

 

  September 30, 2018 (millions of dollars)    Total      Less than
1 year
     1-3 years      3-5 years      More than
5 years
 

Contractual obligations (due by year)

              

Long-term debt – principal repayments

     11,468        981        1,956        736        7,795  

Long-term debt – interest payments

     8,329        459        858        776        6,236  

Convertible debentures - principal repayments1

     513                             513  

Convertible debentures - interest payments

     554        62        123        123        246  

Short-term notes payable

     444        444                       

Pension contributions2

     159        66        93                

Environmental and asset retirement obligations

     197        30        64        61        42  

Outsourcing agreements

     271        124        138        5        4  

Operating lease commitments

     31        9        16        3        3  

Long-term software/meter agreement

     41        14        23        3        1  

Total contractual obligations

     22,007        2,189        3,271        1,707        14,840  

 

 

Other commercial commitments (by year of expiry)

              

Operating Credit Facilities3

     2,550                      2,550         

Letters of credit4

     167        162        5                

Guarantees5

     325        325                       

 

 

Total other commercial commitments

     3,042        487        5        2,550         

 

 

 

1 

The Company expects that the convertible debentures will be converted to common shares upon closing of the Avista Corporation acquisition.

 

2 

Contributions to the Hydro One Pension Fund are generally made one month in arrears. The 2018, 2019 and 2020 minimum pension contributions are based on an actuarial valuation as at December 31, 2017 and projected levels of pensionable earnings.

 

3 

For repayment and expiry details of the Acquisition Credit Facilities, please see section Liquidity and Financing Strategy.

 

4 

Letters of credit consist of a $154 million letter of credit related to retirement compensation arrangements, a $7 million letter of credit provided to the Independent Electricity System Operator (IESO) for prudential support, $5 million in letters of credit to satisfy debt service reserve requirements, and $1 million in letters of credit for various operating purposes.

 

5 

Guarantees consist of prudential support provided to the IESO by Hydro One Inc. on behalf of its subsidiaries.

SHARE CAPITAL

The common shares of Hydro One are publicly traded on the Toronto Stock Exchange (TSX) under the trading symbol “H”. Hydro One is authorized to issue an unlimited number of common shares. The amount and timing of any dividends payable by Hydro One is at the discretion of the Hydro One Board and is established on the basis of Hydro One’s results of operations, maintenance of its deemed regulatory capital structure, financial condition, cash requirements, the satisfaction of solvency tests imposed by corporate laws for the declaration and payment of dividends and other factors that the Board may consider relevant. At November 7, 2018, Hydro One had 595,882,438 issued and outstanding common shares.

The Company is authorized to issue an unlimited number of preferred shares, issuable in series. At November 7, 2018, two series of preferred shares are authorized for issuance: the Series 1 preferred shares and the Series 2 preferred shares. At November 7, 2018, the Company had 16,720,000 Series 1 preferred shares and no Series 2 preferred shares issued and outstanding.

The number of common shares of Hydro One that would be issued if all outstanding stock options and convertible debentures were converted as at November 7, 2018 is 949,910 and 71,962,660, respectively.

REGULATION

The OEB approves both the revenue requirements of and the rates charged by Hydro One’s regulated transmission and distribution businesses. The rates are designed to permit the Company’s transmission and distribution businesses to recover the allowed costs and to earn a formula-based annual rate of return on its deemed 40% equity level invested in the regulated businesses. This is done by applying a specified equity risk premium to forecast interest rates on long-term bonds. In addition, the OEB approves rate riders to allow for the recovery or disposition of specific regulatory deferral and variance accounts over specified time frames.

 

   12   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

The following table summarizes the status of Hydro One’s major regulatory proceedings:

 

  Application    Years    Type    Status

Electricity Rates

        

Hydro One Networks

   2017-2018    Transmission – Cost-of-service    OEB decision received1

Hydro One Networks

   2019    Transmission – Revenue Cap    OEB decision pending

Hydro One Networks

   2018-2022    Distribution – Custom    OEB decision pending

B2M LP

   2015-2019    Transmission – Cost-of-service    OEB decision received

HOSSM

   2017-2026    Transmission – Revenue Cap    OEB decision received2

NRLP

   2019    Transmission – Interim Revenue    OEB decision pending

 

Mergers Acquisitions Amalgamations and Divestitures (MAAD)

  

Orillia Power

   n/a    Acquisition    OEB decision pending3

Peterborough Distribution

   n/a    Acquisition    OEB decision pending

 

Leave to Construct

        

East-West Tie Station Expansion

   n/a    Section 92    OEB decision pending

Lake Superior Link Project

   n/a    Section 92    OEB decision pending

 

 

1 

In August 2018, the OEB returned the portion of the Decision relating to the deferred tax asset to an OEB panel for reconsideration.

 

2 

In October 2016, the OEB approved the 2017-2026 revenue requirements. In July 2018, HOSSM filed an application for an inflationary increase (Price Cap Escalator factor) to its 2019 revenue requirement.

 

3 

In September 2018, Hydro One filed a new MAAD application with the OEB to acquire Orillia Power.

The following table summarizes the key elements and status of Hydro One’s electricity rate applications:

 

  Application   Year     ROE
Allowed (A)
or Forecast (F)
 

Rate Base

Allowed (A)

or Forecast (F)

  Rate Application Status   Rate Order Status

Transmission

         

Hydro One Networks

    2018     9.00% (A)   $11,148 million (A)   Approved in September 2017   Approved in December 2017
    2019       n/a1   n/a1   Filed in October 2018   To be filed

 

B2M LP

    2018     9.00% (A)   $502 million (A)   Approved in December 2015   OEB decision received
    2019     9.00% (F)   $496 million (A)   Approved in December 2015   To be filed in 2018 Q4

 

HOSSM

    2017-2026     9.19% (A)   $218 million (A)   Approved in October 2016   OEB decision received2

 

NRLP

    2019     9.00% (F)   $123 million (F)   Filed in October 2018   To be filed

 

Distribution

         

Hydro One Networks

    2018     9.00% (A)   $7,650 million (F)   Filed in March 20173   To be filed in 2018 Q4
    2019     9.00% (F)   $8,009 million (F)   Filed in March 20173   To be filed in 2018 Q4
    2020     9.00% (F)   $8,412 million (F)   Filed in March 20173   To be filed in 2019 Q4
    2021     9.00% (F)   $8,941 million (F)   Filed in March 20173   To be filed in 2020 Q4
    2022     9.00% (F)   $9,306 million (F)   Filed in March 20173   To be filed in 2021 Q4

 

 

1 

The Revenue Cap application is a formulaic adjustment to the approved revenue requirement and does not consider ROE or rate base.

 

2 

In October 2016, the OEB approved the 2017-2026 revenue requirements. In July 2018, HOSSM filed an application for an inflationary increase (Price Cap Escalator factor) to its 2019 revenue requirement.

 

3 

In June 2018, Hydro One Networks filed an undertaking with the OEB which included updated rate base amounts.

Electricity Rates Applications

Hydro One Networks - Transmission

On September 28, 2017, the OEB issued its Decision and Order on Hydro One Networks’ 2017 and 2018 transmission rates revenue requirements (Decision), with 2017 rates effective January 1, 2017. Key changes to the application as filed included reductions in planned capital expenditures of $126 million and $122 million for 2017 and 2018, respectively, in OM&A expenses related to compensation by $15 million for each year, and in estimated tax savings from the Initial Public Offering (IPO) by $24 million and $26 million for 2017 and 2018, respectively. On October 10, 2017, Hydro One Networks filed a Draft Rate Order reflecting the changes outlined in the Decision.

In its Decision, the OEB concluded that the net deferred tax asset resulting from transition from the payments in lieu of tax regime under the Electricity Act (Ontario) to tax payments under the federal and provincial tax regime should not accrue entirely to Hydro One’s shareholders and that a portion should be shared with ratepayers. On November 9, 2017, the OEB issued a Decision and Order that calculated the portion of the tax savings that should be shared with ratepayers. The OEB’s calculation would result in an

 

   13   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

impairment of Hydro One Networks’ transmission deferred income tax regulatory asset of up to approximately $515 million. If the OEB were to apply the same calculation for sharing in Hydro One Networks’ 2018-2022 distribution rates, for which a decision is currently outstanding, it would result in an additional impairment of up to approximately $370 million related to Hydro One Networks’ distribution deferred income tax regulatory asset. The exposure from the potential impairments would be a one-time decrease in net income of up to approximately $885 million, resulting in an annual decrease to FFO in the range of $50 million to $60 million.

In October 2017, the Company filed a Motion to Review and Vary (Motion) the Decision and filed an appeal with the Divisional Court of Ontario (Appeal). In both cases, the Company’s position is that the OEB made errors of fact and law in its determination of allocation of the tax savings between the shareholders and ratepayers. An OEB hearing of the merits of the Motion was held on February 12, 2018. On August 31, 2018, the OEB granted the Motion and returned the portion of the Decision relating to the deferred tax asset to an OEB panel for reconsideration. Based on the assumptions that the OEB applies established rate making principles in a manner consistent with its past practice and does not exercise its discretion to take other policy considerations into account, management is of the view that it is likely that the aforementioned tax savings will be allocated to the benefit of Hydro One shareholders.

In October 2017, the intervenor Anwaatin Inc. also filed a Motion to Review and Vary the OEB Decision (Anwaatin Motion) alleging that the OEB breached its duty of procedural fairness, failed to respond to certain evidence, and failed to provide reasons on the capital budget as it related to reliability issues impacting Anwaatin Inc.’s constituents. The Anwaatin Motion was heard by the OEB on February 13, 2018. Hydro One reached a settlement agreement with Anwaatin Inc. regarding the Anwaatin Motion. On June 15, 2018, the settlement agreement was filed with the OEB for approval.

On November 23, 2017, the OEB approved the 2017 rates revenue requirement of $1,438 million. On December 20, 2017, the OEB approved the 2018 rates revenue requirement of $1,511 million, which included a $25 million increase from the approved amount, as a result of the OEB-updated cost of capital parameters. Uniform Transmission Rates (UTRs), reflecting these approved amounts, were approved by the OEB on February 1, 2018 to be effective as of January 1, 2018.

In March 2017, the Financial Accounting Standards Board (FASB) issued an Accounting Standards Update (ASU) 2017-07, which limits capitalization of post-employment benefit related costs to the service cost component. Hydro One filed an application requesting the OEB to approve a regulatory asset, to record the amounts no longer permitted for capitalization under the new standard, effective January 1, 2018. In May 2018, the OEB approved the regulatory asset.

On March 16, 2018, the OEB issued a letter requesting Hydro One to file the transmission revenue requirement application for a four-year test period from 2019 to 2022, rather than the minimum 5-year period allowed under existing OEB policy. The OEB indicated that it is more appropriate to consider rates for Hydro One’s distribution and transmission businesses in a single application, and stated that it expected Hydro One to file a single application for distribution rates (including Hydro One Remote Communities Inc.) and transmission revenue requirement for the period from 2023 to 2027.

A one-year inflation-based application for 2019 transmission rates was filed with the OEB on October 26, 2018.

Hydro One Networks - Distribution

The OEB oral hearing related to Hydro One Networks’ application for 2018-2022 distribution rates was held on June 11-28, 2018. On July 20, 2018, Hydro One submitted its Argument-in-Chief. Intervenors had until August 10, 2018 to respond. On August 31, 2018, Hydro One filed its reply argument with the OEB. This concludes the evidentiary process with the exception of pole attachment charges, and matters relating to recovery of certain amounts paid for executive compensation, as per the Hydro One Accountability Act (Act). See section “Hydro One Board of Directors and Executive Officers” for more information. For both of these matters, the OEB issued a procedural order on October 12, 2018 outlining the next steps in the process throughout the fourth quarter of 2018. As part of these steps, on October 26, 2018, Hydro One filed a submission with the OEB on how the Act impacts its distribution rate application. On November 2, 2018, Hydro One filed a submission with the OEB on the pole attachment charges.

On June 27, 2018, the OEB issued a letter deferring Hydro One’s request for the OEB to approve an alternative method to calculate amounts related to the post-employment benefit costs for Hydro One Networks’ distribution business until the next re-basing application is filed, as the OEB noted that the issue is relevant to both the distribution and transmission businesses of Hydro One Networks. In the 2019 transmission rates application filed with the OEB on October 26, 2018, Hydro One requested this decision be made as part of its next transmission re-basing application.

B2M LP

On May 10, 2018, the OEB issued its Decision and Rate Order on B2M LP’s 2018 transmission application reflecting revenue requirement of $36 million, effective January 1, 2018.

Hydro One Remote Communities Inc.

On March 19, 2018, the OEB approved the settlement agreement related to the 2018 rates application reached by Hydro One Remote Communities Inc. and the intervenors in the rate proceeding. On March 26, 2018, a draft rate order was filed with the OEB for 2018 rates. The OEB approved the draft rate order on April 12, 2018, and the new rates were implemented effective May 1, 2018.

 

   14   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

HOSSM

HOSSM is under a 10-year deferred rebasing period for years 2017-2026, as approved in the OEB MAAD decision dated October 13, 2016. On July 26, 2018, HOSSM filed a 2019 application to allow for inflationary increase (Price Cap Escalator factor) to its previously approved revenue requirement. The Price Cap Escalator factor is designed to add inflationary increases to the revenue requirement on an annual basis.

Niagara Reinforcement Limited Partnership (NRLP)

On September 19, 2018, NRLP was formed to own and operate a new 230 kV transmission line, the Niagara Reinforcement Project, built to connect generators in the Niagara area and the load centres of the Greater Toronto and Hamilton areas.

On September 27, 2018, Hydro One filed a transmission licence application with the OEB for NRLP. On October 25, 2018, Hydro One filed two other applications with the OEB relating to NRLP requesting approval for Hydro One Networks to sell the applicable assets to NRLP and approval of interim rates to include in the 2019 UTRs.

MAAD Applications

Orillia Power MAAD Application

In 2016, Hydro One filed a MAAD application (2016 Application) with the OEB to acquire Orillia Power Distribution Corporation (Orillia Power) from the City of Orillia, Ontario. On April 12, 2018, the OEB issued a decision denying Hydro One’s proposed acquisition of Orillia Power. The decision indicated that with the exception to pricing, the transaction met the no harm test. Additionally, the OEB indicated that it required additional evidence on the overall cost structure following the deferral period and the impact on Orillia Power’s customers. On May 2, 2018, Hydro One and Orillia Power both filed a Motion to Review and Vary the OEB’s decision, and on August 23, 2018, the OEB issued a decision upholding its April 12, 2018 decision to deny Hydro One’s proposed acquisition of Orillia Power.

On September 26, 2018, Hydro One filed a new MAAD application (2018 Application) with the OEB to acquire Orillia Power. The evidence in the 2018 Application is similar to that provided in the 2016 Application, with the exception of updates to reflect current variables to costs and other metrics, as well as future cost structures.

Peterborough Distribution MAAD Application

On October 12, 2018, the Company filed an application with the OEB for approval of the acquisition of business and distribution assets of Peterborough Distribution Inc. (Peterborough Distribution). On October 25, 2018, an advance ruling certification application was filed with the Competition Bureau. See section “Other Developments - Peterborough Distribution Purchase Agreement” for more information on the acquisition.

Other Applications

Lake Superior Link Project

On February 15, 2018, Hydro One filed a Leave to Construct application with the OEB to construct the east-west tie line (EWT Line) in northwestern Ontario (Lake Superior Link Project), which will compete with an application filed by NextBridge Infrastructure (NextBridge) to construct the EWT Line. Pursuant to the OEB’s direction, on July 26, 2018, the IESO issued its analysis of the impacts of a delay to the in-service date for the construction of the EWT Line. In its analysis, the IESO recommends an in-service date of 2020 for the completion of the EWT Line and does not support a delay beyond 2022, due to increased risks to system reliability and the associated cost uncertainties.

A combined OEB oral hearing for the Hydro One EWT Line application, the Hydro One East-West Tie Station Expansion application, and the NextBridge EWT Line application was held on October 2-12, 2018. The OEB’s decision is expected by the end of 2018.

OTHER DEVELOPMENTS

Collective Agreements

On March 1, 2018, Hydro One insourced its customer service operations, which had been previously outsourced to Inergi LP and Vertex Customer Management (Canada) Limited since 2002. The insourcing was facilitated through labour agreements reached with the Power Workers’ Union (PWU) and The Society of United Professionals (formerly The Society of Energy Professionals) in 2017.

The current collective agreement with the PWU expired on March 31, 2018. On March 26, 2018, Hydro One and the PWU reached a tentative agreement, and on June 27, 2018, the agreement has been ratified by the PWU. The term of the agreement is for two years ending on March 31, 2020.

US GAAP - Exemptive Relief

On March 27, 2018, Hydro One was granted exemptive relief by securities regulators in each province and territory of Canada which allows Hydro One to continue to report its financial results in accordance with US GAAP (Exemptive Relief). The Exemptive Relief

 

   15   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

will remain in effect until the earlier of: (i) January 1, 2024; (ii) the first day of Hydro One’s financial year that commences after Hydro One ceases to have activities subject to rate regulation; and (iii) the effective date prescribed by the International Accounting Standards Board for the mandatory application of a standard within International Financial Reporting Standards specific to entities with activities subject to rate regulation.

Avista Corporation Merger

In July 2017, Hydro One reached an agreement to acquire Avista Corporation. The following table summarizes the status of the Merger approval process:

 

Approval Required    Status

Alaska1

  

Approval received on June 4, 201810

Washington1

  

Settlement agreement filed on March 27, 20184

Idaho1

  

Settlement agreement filed on April 13, 20186

Oregon1

  

Settlement agreement filed on May 25, 20189

Montana1

  

Approval received on July 10, 201811

Federal Communications Commission

  

Consent received on May 4, 20187

Committee on Foreign Investment in the United States

  

Clearance received on May 18, 20188

Hart-Scott-Rodino Antitrust

  

Clearance received on April 5, 20185

Federal Energy Regulatory Commission

  

Approval received on January 16, 20183

Avista Corporation shareholders

  

Approval received on November 21, 20172

 

1 

On September 14, 2017, Hydro One and Avista Corporation filed applications with the state utility commissions in Alaska, Washington, Idaho, Oregon, and Montana, requesting regulatory approval of the Merger on or before August 14, 2018.

 

2 

On November 21, 2017, the Merger was approved by the shareholders of Avista Corporation.

 

3 

On January 16, 2018, the Federal Energy Regulatory Commission approved the Merger application.

 

4 

On March 27, 2018, an all-parties, all-issues settlement agreement was filed with the Washington Utilities and Transportation Commission. On July 12, 2018, the Washington Utilities and Transportation Commission gave notice of its intent to conduct additional process, and on July 20, 2018, it gave notice that it is extending the deadline for a decision to December 14, 2018. On October 4, 2018, all parties to the settlement filed testimony in support of the settlement and additional and modified commitments offered by Avista Corporation and Hydro One. A hearing on this matter was held on October 23, 2018.

 

5 

On April 5, 2018, the 30-day waiting period under the Hart-Scott-Rodino Antitrust Improvements Act of 1976, as amended, for the Merger expired. This expiration of the waiting period means that the parties have received antitrust clearance for the Merger and satisfies one of the closing conditions of the transaction.

 

6 

On April 13, 2018, a multi-party settlement agreement was filed with the Idaho Public Utilities Commission. On July 20, 2018, the Idaho Public Utilities Commission ordered that a hearing initially scheduled for July 23, 2018 was vacated in response to the leadership changes at Hydro One announced in July 2018. A new hearing date has been set for November 26-27, 2018.

 

7 

On May 4, 2018, consent for the transfer of control of the wireless licences held by Avista Corporation and one of its subsidiaries to Hydro One as a result of the Merger was received from the Federal Communications Commission. On October 3, 2018, the Federal Communications Commission granted an extension to consummate the transfer of control of the wireless licenses to April 13, 2019.

 

8 

On May 18, 2018, the Committee on Foreign Investment in the United States has completed its review of the proposed merger, and has concluded that there are no unresolved national security concerns with respect to the Merger.

 

9 

On May 25, 2018, an all-parties, all-issues settlement agreement was filed with the Oregon Public Utility Commission. In response to the leadership changes at Hydro One announced in July 2018, one party no longer supports Hydro One’s acquisition of Avista Corporation. On July 25, 2018, a new procedural schedule was adopted for the proceedings, setting a hearing for November 15-16, 2018, and a target date of December 14, 2018 for a decision by the Oregon Public Utility Commission.

 

10 

On June 4, 2018, the Merger was approved by the Regulatory Commission of Alaska, subject to certain conditions.

 

11 

On July 10, 2018, the Merger was approved by the Montana Public Service Commission, subject to certain conditions.

Following the announcement on July 11, 2018 of the resignation of Hydro One’s Board and the immediate retirement of its President and CEO (see section “Hydro One Board of Directors and Executive Officers” for more information), regulatory authorities in Washington and Oregon extended the timetable for arriving at a decision in Hydro One’s acquisition of Avista Corporation to mid-December 2018. In addition, the Idaho Public Utilities Commission rescheduled its hearing from July 23, 2018 to November 26-27, 2018. Applications for regulatory approval of the Merger are pending with utility commissions in Washington, Idaho, and Oregon. The settlement agreements remain subject to approval by the respective commissions. Also required is the satisfaction of customary closing conditions.

The closing of the Merger is subject to the normal commercial risks that the Merger will not close on the terms negotiated or at all. The completion of the Merger is subject to receipt of certain regulatory and governmental approvals, including the expiration or termination of any applicable waiting period under the Hart-Scott-Rodino Antitrust Improvements Act of 1976, clearance of the Merger by the Committee on Foreign Investment in the United States, the approval by each of the Idaho Public Utilities Commission, the Public Service Commission of the State of Montana, the Public Utility Commission of Oregon, the Regulatory Commission of Alaska, the Washington Utilities and Transportation Commission, the United States Federal Energy Regulatory Commission and the United States Federal Communications Commission (the status of which are noted above), and the satisfaction or waiver of certain closing conditions contained in the Merger Agreement. The failure to obtain the required approvals or satisfy or waive the conditions contained in the Merger Agreement may result in the termination of the Merger Agreement. There is no assurance that such closing conditions will be satisfied or waived. Accordingly, there can be no assurance that Hydro One will complete the Merger in the timeframe or on the basis described herein, if at all. Failure to complete the Merger could expose Hydro One to litigation and resulting damages. The termination of the Merger Agreement may have an effect (which may be material and/or negative) on the price of the convertible debentures’ instalment receipts and the Hydro One common shares, and will result in the redemption of the

 

   16   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

convertible debentures. If the closing of the Merger does not take place as contemplated, the Company could suffer adverse consequences, including the loss of investor confidence, and may incur significant costs or losses, including an obligation to pay or cause to be paid to Avista Corporation a termination fee of US$103 million or other damages, which could be material. In addition, the redemption of the convertible debentures would result in the related deferred financing costs being expensed immediately ($24 million at September 30, 2018), and the deal-contingent foreign exchange forward contract would be revalued to $nil, which would result in a reversal of any previously recorded unrealized gains ($22 million at September 30, 2018).

Litigation

Class Action Lawsuit

Hydro One Inc., Hydro One Networks, Hydro One Remote Communities Inc., and Norfolk Power Distribution Inc. are defendants in a class action suit in which the representative plaintiff is seeking up to $125 million in damages related to allegations of improper billing practices. The plaintiff’s motion for certification was dismissed by the court on November 28, 2017, but the plaintiff has appealed the court’s decision. The appeal was heard on October 16, 2018, and it is likely that the court will render its decision before the end of 2018.

Litigation Relating to the Merger

To date, four putative class action lawsuits were filed by purported Avista Corporation shareholders in relation to the Merger. First, Fink v. Morris, et al., was filed in Washington state court and the amended complaint names as defendants Avista Corporation’s directors, Hydro One, Olympus Holding Corp., Olympus Corp., and Bank of America Merrill Lynch. The suit alleges that Avista Corporation’s directors breached their fiduciary duties in relation to the Merger, aided and abetted by Hydro One, Olympus Holding Corp., Olympus Corp. and Bank of America Merrill Lynch. The Washington state court issued an order staying the litigation until after the plaintiffs file an amended complaint, which must be no later than 30 days after Avista Corporation or Hydro One publicly announces that the Merger has closed. Second, Jenß v. Avista Corp., et al., Samuel v. Avista Corp., et al., and Sharpenter v. Avista Corp., et al., were each filed in the US District Court for the Eastern District of Washington and named as defendants Avista Corporation and its directors; Sharpenter also named Hydro One, Olympus Holding Corp., and Olympus Corp. The lawsuits alleged that the preliminary proxy statement omitted material facts necessary to make the statements therein not false or misleading. Jenß, Samuel, and Sharpenter were all voluntarily dismissed by the respective plaintiffs with no consideration paid by any of the defendants. The one remaining class action is consistent with expectations for US merger transactions and, while there is no certainty as to outcome, Hydro One believes that the lawsuit is not material to Hydro One.

Peterborough Distribution Purchase Agreement

On July 31, 2018, Hydro One reached an agreement to acquire the business and distribution assets of Peterborough Distribution, an electricity distribution company located in east central Ontario, from the City of Peterborough. Hydro One will pay the City of Peterborough $105 million for the transaction. The acquisition is conditional upon the satisfaction of customary closing conditions and approval by the OEB and the Competition Bureau. On October 12, 2018, the Company filed an application with the OEB for approval of the acquisition.

HYDRO ONE BOARD OF DIRECTORS AND EXECUTIVE OFFICERS

Directors and Executive Officers

On July 11, 2018, Hydro One, on behalf of itself and its wholly-owned subsidiary, Hydro One Inc., announced that it had entered into an agreement (Letter Agreement) with the Province for the purpose of the orderly replacement of the Board of Hydro One and Hydro One Inc. and the retirement of Mayo Schmidt as the CEO effective July 11, 2018. Hydro One also announced the appointment of Paul Dobson as Acting President and CEO of Hydro One and Hydro One Inc. effective July 11, 2018.

On August 14, 2018, Hydro One announced a new Board. Six directors were identified and nominated by Hydro One’s ad hoc nominating committee, comprised of three of the five largest shareholders of Hydro One excluding the Province, and four directors were identified and nominated by the Province, Hydro One’s largest shareholder. Each of the directors are independent of both Hydro One and the Province in accordance with the Governance Agreement dated as of November 5, 2015 between Hydro One and the Province (Governance Agreement).

The directors of Hydro One and Hydro One Inc. are the same in accordance with the provisions of the Governance Agreement.

On September 7, 2018, Hydro One announced the appointment of Chris Lopez as Acting Chief Financial Officer of Hydro One and Hydro One Inc., effective September 6, 2018. On September 7, 2018, Hydro One announced the appointment of Tom Woods as Chair of the Board of Hydro One and Hydro One Inc., effective September 6, 2018.

The following table sets forth information regarding the current directors and executive officers of Hydro One and Hydro One Inc. as at November 1, 2018. Each of the directors was first appointed effective August 13, 2018. Each director is elected annually to serve for one year or until his or her successor is elected or appointed.

 

   17   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

 

  Name, Province or State and
  Country of Residence
   Age    Position/Title   

Independent

Board Member

   Principal Occupation    Committees

Paul Dobson

   52    Acting President       Acting President   

Texas, USA

      and CEO       and CEO   

Jason Fitzsimmons

   48    Chief Corporate Affairs       Chief Corporate Affairs   

Ontario, Canada

      and Customer Care Officer       and Customer Care Officer   

Gregory Kiraly

   54    Chief Operating Officer       Chief Operating Officer   

Arizona, USA

              

Chris Lopez

   44    Acting Chief Financial       Acting Chief Financial   

Alberta, Canada

      Officer       Officer   

Judy McKellar

   62   

Executive Vice President,

Chief Human Resources

      Executive Vice President,   

Ontario, Canada

      Officer       Chief Human Resources   
            Officer   

Patrick Meneley

   54    Executive Vice President       Executive Vice President   

Ontario, Canada

      and Chief Corporate       and Chief Corporate   
      Development Officer       Development Officer   

James Scarlett

   65    Executive Vice President       Executive Vice President   

Ontario, Canada

      and Chief Legal Officer       and Chief Legal Officer   

Tom Woods1

   66    Director and Chair    Yes    Director   

Ontario, Canada

      of the Board         

Cherie Brant1

   43    Director    Yes    Partner,    Governance Committee;

Ontario, Canada

            Dickinson Wright LLP    Health, Safety, Environment and Indigenous
               Peoples Committee

Blair Cowper-Smith1

   70    Director    Yes    Director    Governance Committee (Chair);

Ontario, Canada

               Human Resources Committee

Anne Giardini

   59    Director    Yes    Director    Audit Committee; Health, Safety, Environment

British Columbia, Canada

               and Indigenous Peoples Committee (Chair)

David Hay

   63    Director    Yes    Managing Partner,    Audit Committee; Health, Safety, Environment

Ontario, Canada

            Delgatie Incorporated    and Indigenous Peoples Committee

Timothy Hodgson

   57    Director    Yes    Managing Partner and    Governance Committee;

Ontario, Canada

            Director, Alignvest    Human Resources Committee
            Management Corporation   

Jessica McDonald

   49    Director    Yes    Interim President and    Audit Committee;

British Columbia, Canada

            CEO, Canada Post    Human Resources Committee
            Corporation   

Russel Robertson1

   71    Director    Yes    Director    Audit Committee;

Ontario, Canada

               Human Resources Committee

William Sheffield

   70    Director    Yes    Director    Audit Committee (Chair);

Ontario, Canada

               Health, Safety, Environment and Indigenous
               Peoples Committee

Melissa Sonberg

   58    Director    Yes    Adjunct Professor,    Governance Committee;

Québec, Canada

                  McGill University    Human Resources Committee (Chair)

1 These directors have been designated as the Province’s nominees to the Board of Hydro One for the purpose of the Governance Agreement.

The following includes a brief profile of each of the executive officers and directors of Hydro One and Hydro One Inc., which includes a description of their present occupation and their principal occupations for the past five years:

Paul Dobson - Acting President and CEO

Effective July 11, 2018, Paul Dobson was appointed to the role of Acting President and CEO of Hydro One. Mr. Dobson joined the Company as Chief Financial Officer on March 1, 2018 responsible for finance, treasury, controller, internal audit, technology and regulation. Prior to joining Hydro One in 2018, Mr. Dobson served as Chief Financial Officer for Direct Energy Ltd. (Direct Energy), Houston, Texas, where he was responsible for overall financial leadership of a $15 billion revenue business with three million customers in Canada and the US. Since 2003, Mr. Dobson has held senior leadership positions in finance, operations, information technology and customer service across the Centrica Group, the parent company of Direct Energy. Prior to Direct Energy, Mr. Dobson worked at CIBC for 10 years in finance, strategy and business development roles in both Canada and the US. Mr. Dobson also brings considerable experience in mergers and acquisitions and integrating acquired companies across North America and in the United Kingdom. Mr. Dobson is a dual Canadian-US citizen who holds an honours bachelor’s degree from the University of Waterloo as well as a Masters of Business Administration (MBA) from the University of Western Ontario and is a CPA, CMA.

Jason Fitzsimmons - Chief Corporate Affairs and Customer Care Officer

Jason Fitzsimmons was promoted to Chief Corporate Affairs and Customer Care Officer in August 2018, with oversight of the customer service, corporate affairs, marketing and Indigenous relations functions. With more than 25 years of experience in the electricity sector, Mr. Fitzsimmons is a highly-regarded leader with a proven track record for successfully executing large-scale transformations and building strong relationships with key stakeholders. In his previous role as Vice President, Labour Relations at Hydro One, Mr. Fitzsimmons played an instrumental role in bringing the company’s 400-employee Customer Contact Centre in-house as the Company continuously strives to deliver best-in-class customer service. Prior to joining the Company in 2016, Mr. Fitzsimmons was the Chief Negotiations Officer at the Ontario Hospital Association and also held a number of executive roles at

 

   18   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Ontario Power Generation, including Vice President of Human Resources for the Nuclear division. He is a Certified Human Resource Executive known for his broad experience in labour management as well as his passion for health and safety in the workplace. He was a prior member of the Advisory Board for Ryerson University’s Centre for Labour Management Relations and has served on the Board for the Electrical Power Sector Construction Association.

Gregory Kiraly - Chief Operating Officer

Effective September 12, 2016, Gregory Kiraly was appointed to the role of Chief Operating Officer (COO) of Hydro One. As COO, Mr. Kiraly oversees the complete transmission and distribution value chain including planning, engineering, construction, operations, maintenance, and forestry; shared services functions including facilities, real estate, fleet, and procurement; and the Hydro One Telecom and Hydro One Remote Communities subsidiaries. Prior to joining Hydro One in 2016, Mr. Kiraly served as Senior Vice President of Electric Transmission and Distribution at Pacific Gas and Electric Company (PG&E) in San Francisco, which delivers safe and reliable energy to more than 16 million customers in northern and central California. Since joining PG&E in 2008, Mr. Kiraly led efforts that achieved the lowest employee injury rates ever, seven straight years of record electric reliability, and over $500 million in productivity improvements and efficiency savings. Before PG&E, Mr. Kiraly held executive-level positions in energy delivery at Commonwealth Edison (Exelon) in Chicago and leadership positions in both gas and electric distribution at Public Service Electric and Gas Company in Newark, New Jersey. Mr. Kiraly holds a bachelor’s degree in industrial engineering from New Jersey Institute of Technology and an MBA in finance from Seton Hall University. He is also a graduate of Harvard University’s Advanced Management Program.

Chris Lopez - Acting Chief Financial Officer

Effective September 6, 2018, Chris Lopez was appointed as Acting Chief Financial Officer of Hydro One. Prior to joining Hydro One, Mr. Lopez was the Vice President, Corporate Planning and Mergers & Acquisitions at TransAlta Corporation from 2011 to 2015. Prior to that, Mr. Lopez was Director of Operations Finance at TransAlta in Calgary from 2007 to 2011, and he held senior financial roles up to and including Country Financial Controller for TransAlta in Australia, from 1999 to 2007. Mr. Lopez worked as a Senior Financial Accountant with Rio Tinto Iron Ore, in Australia from 1997 to 1999. Mr. Lopez received a Bachelor of Business degree from Edith Cowan University in 1996, and a Chartered Accountant designation in Australia in 1999. He received a graduate diploma in corporate governance and directorships from the Australian Institute of Company Directors in 2007. Mr. Lopez was accountable for leading the management of financial governance and reporting, treasury management taxation and planning and analysis before stepping up into the acting role of Chief Financial Officer for the second half of 2017 following the departure of Michael Vels, until the appointment of Mr. Dobson as Chief Financial Officer on March 1, 2018.

Judy McKellar - Executive Vice President, Chief Human Resources Officer

Judy McKellar is the Executive Vice President, Chief Human Resources Officer of Hydro One. She was appointed to this position on November 11, 2016. Ms. McKellar has held various roles of increasing responsibility at Hydro One Networks, an indirect subsidiary of Hydro One, in the Human Resources department over her 30+ year career and was appointed Vice President of Human Resources in 2010. In 2014, she assumed the additional responsibility of Senior Vice President of People and Culture/Health, Safety and Environment and serves as the accountable executive for the Human Resources Committee of the Board. Ms. McKellar earned a Bachelor of Arts degree from Victoria College, University of Toronto, and was recently named as one of 2015’s 100 Most Powerful Women in Canada by PricewaterhouseCoopers in the “Public Sector” category.

Patrick Meneley - Executive Vice President and Chief Corporate Development Officer

Effective March 1, 2018, Patrick Meneley was appointed to the role of Executive Vice President and Chief Corporate Development Officer of Hydro One. In this capacity, Mr. Meneley is responsible for leading strategy, innovation and mergers and acquisitions. Prior to joining Hydro One in 2018, Mr. Meneley served as Executive Vice President, Wholesale Banking at TD Bank Group and Vice Chair and Head of Global Corporate and Investment Banking for TD Securities. Mr. Meneley spent 15 years leading and building one of the leading corporate and investment banking businesses in Canada, along with a profitable and growing franchise in the US. Mr. Meneley holds an MBA (with distinction) from the University of Western Ontario and a Bachelor of Commerce (with honours) from the University of British Columbia.

James Scarlett - Executive Vice President and Chief Legal Officer

Effective September 1, 2016, James Scarlett was appointed as Executive Vice President and Chief Legal Officer of Hydro One. Prior to joining Hydro One, Mr. Scarlett was a Senior Partner at Torys LLP. He joined Torys LLP in March 2000 and held a number of leadership roles at the firm, including head of Torys LLP’s Capital Markets Group, Mining Group and International Business Development Strategy. Mr. Scarlett was also a member of the firm’s Executive Committee from 2009-2015. Prior to joining Torys LLP, Mr. Scarlett was a Partner at another major Canadian law firm. While at that firm Mr. Scarlett held leadership roles as head of its Corporate Group, Securities Group and as a member of its Board. Mr. Scarlett was also seconded to the Ontario Securities Commission in 1987 and was appointed as the first Director of Capital Markets in 1988, a position he held until his return to private law practice in 1990. Mr. Scarlett earned his law degree (J.D.) from the University of Toronto in 1981 and his Bachelor of Commerce Degree from the University of McGill in 1975. In 2015, Mr. Scarlett earned his ICD.D (Institute of Corporate Directors) designation.

 

   19   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Tom Woods (provincial nominee) - Board Chair

Public Directorships (other than Hydro One and Hydro One Inc.): Bank of America Corporation

Public Board Interlocks: None

Mr. Woods is a corporate director. He previously had a 37-year career with CIBC, a major Canadian bank, and Wood Gundy, the predecessor firm of CIBC World Markets. He started in Investment Banking, advising companies raising financing in the equity and debt capital markets as well as mergers and acquisitions, and later was Head of Canadian Corporate Banking, Chief Financial Officer, Chief Risk Officer and Vice Chairman.

Mr. Woods also serves on the boards of Bank of America Corporation, Alberta Investment Management Corporation, Providence St. Joseph’s St. Michael’s Health Care (Board Chair), University of Toronto Mechanical & Industrial Engineering and CIBC Children’s Foundation. Previous directorships include TMX Group Inc., DBRS Limited, Jarislowsky Fraser Limited and Covenant House (Board Chair). Mr. Woods has a Bachelor of Applied Science in Industrial Engineering from University of Toronto, and an MBA from Harvard Business School.

Cherie Brant (provincial nominee)

Public Directorships (other than Hydro One and Hydro One Inc.): None

Public Board Interlocks: None

Ms. Brant is a Partner at Dickinson Wright’s Toronto law office where she has an Indigenous law practice with a focus on commercial real estate, energy and transmission and First Nations economic development. Ms. Brant provides strategic counsel to several First Nations and industry clients seeking to develop projects with First Nations and to understand and address Indigenous rights and interests. As lead counsel, Ms. Brant was instrumental in forming one of the largest First Nations-led limited partnerships in Canada resulting in the Ontario First Nations Sovereign Wealth LP’s share purchase of approximately 2.4% of Hydro One. Prior to being a Partner at Dickinson Wright LLP, she was a Partner at Willms & Shier LLP.

Ms. Brant is both Mohawk and Ojibway from the Mohawks of the Bay of Quinte and Wikwemikong Unceded Indian Territory. She also serves on the board of the Anishnawbe Health Foundation and is a member of the Canadian Council for Aboriginal Business, Research Advisory Board and the Aboriginal Energy Working Group of the IESO. Previous directorships include Women’s College Hospital and Trillium Gift of Life.

Ms. Brant has a Bachelor of Environmental Studies, Urban and Regional Planning Program from the University of Waterloo and a Juris Doctor from the University of Toronto. She is a member of the Ontario Bar Association and the Law Society of Ontario.

Blair Cowper-Smith (provincial nominee)

Public Directorships (other than Hydro One and Hydro One Inc.): None

Public Board Interlocks: None

Mr. Cowper-Smith is the principal and founder of Erin Park Business Solutions, a Canadian advisory and consulting firm. Previously, he was Chief Corporate Affairs Officer of Ontario Municipal Employees Retirement System (OMERS), one of Canada’s largest public pension plans, and a member of the Senior Executive Team where his responsibilities included regulatory affairs, law and governance. Prior to joining OMERS he was a Senior Partner at McCarthy Tetrault LLP where his practice focused on mergers and acquisitions, infrastructure, governance and private equity.

Board experience includes numerous advisory assignments, including governance advisory assignments, with boards of directors including OMERS, Stelco, Hammerson, and includes existing or prior director appointments and board committee leadership roles with companies like Porter Airlines, 407 ETR, the Financial Services Regulatory Authority and Face the Future Foundation. He served until recently on the Public Policy Committee of the Canadian Coalition for Good Governance and on the Securities Advisory Committee of the Ontario Securities Commission. He co-founded The Canadian Council for Public and Private Partnerships which led to a long-term interest in infrastructure policy and delivery of infrastructure based services to Canadians.

Mr. Cowper Smith has a Bachelor of Laws (LLB) and Master of Laws (LLM) from Osgoode Hall Law School at York University. He is a member of the Law Society of Ontario and holds the director designation through the Institute of Corporate Directors and is a regular faculty presenter for the Directors College.

Anne Giardini, O.C., O.B.C., Q.C.

Public Directorships (other than Hydro One and Hydro One Inc.): Nevsun Resources Ltd.

Public Board Interlocks: None

Ms. Giardini is a corporate director and Chancellor of Simon Fraser University, a public research university in British Columbia, Canada. She previously had a 20-year career with Weyerhaeuser Company Limited, a forestry and wood product manufacturing company, including as Canadian President. Before her tenure as President, she was Vice President and General Counsel at Weyerhaeuser where she worked on corporate, legal, policy and strategic matters. Ms. Giardini has been a newspaper columnist and is the author of two novels.

Ms. Giardini also serves on the boards of Nevsun Resources Ltd., Canada Mortgage & Housing Corporation, World Wildlife Fund (Canada), British Columbia Achievement Foundation, TransLink and the Greater Vancouver Board of Trade. Previous directorships include Thompson Creek Metals Company, Inc. and Weyerhaeuser Company Limited.

 

   20   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Ms. Giardini has a Bachelor of Arts (Economics) from Simon Fraser University, a Bachelor of Laws from the University of British Columbia and a Master of Law from the University of Cambridge (Trinity Hall). She is licensed to practice law in British Columbia (and formerly in Ontario and Washington State). In 2016, Ms. Giardini was appointed an Officer of the Order of Canada, and in 2018, she was appointed to the Order of British Columbia.

David Hay

Public Directorships (other than Hydro One and Hydro One Inc.): EPCOR Utilities Inc.

Public Board Interlocks: None

Mr. Hay is a corporate director and the Managing Director at Delgatie Incorporated, a strategic advisory firm. He is the former Vice-Chair and Managing Director of CIBC World Markets Inc., the investment banking subsidiary of CIBC, with power, utilities and infrastructure as a major focus. Formerly, he was President and CEO of New Brunswick Power Corporation, and held senior investment banking roles, including Senior Vice President and Director responsible for mergers and acquisitions with Merrill Lynch Canada and Managing Director of European mergers and acquisitions with Merrill Lynch International. He spent the early part of his career as a practicing lawyer and taught part-time at both the University of Toronto and University of New Brunswick.

Mr. Hay also serves on the boards of EPCOR Utilities Inc., SHAD (Chair), the Council of Clean and Reliable Energy and as Chair of the Acquisition Committee of the Beaverbrook Art Gallery. Prior directorships include Toronto Hydro-Electric System Limited (Vice Chair).

Mr. Hay has a Bachelor of Laws from Osgoode Hall Law School, York University and a Bachelor of Arts from the University of Toronto. He also holds a professional director designation from the Institute of Corporate Directors (ICD.D).

Timothy Hodgson

Public Directorships (other than Hydro One and Hydro One Inc.): Alignvest Acquisition II Corporation and MEG Energy Corp.

Public Board Interlocks: None

Mr. Hodgson is a Managing Partner and Director of Alignvest Capital Management, an investment management firm. Prior to that, Mr. Hodgson was Special Advisor to Governor Mark Carney at Bank of Canada. Mr. Hodgson also held various positions in New York, London, Silicon Valley and Toronto with Goldman Sachs and served as CEO of Goldman Sachs Canada. Mr. Hodgson has held roles with Salomon Brothers, Price Waterhouse & Co. and Merrill Lynch Canada.

Mr. Hodgson also serves on the boards of Alignvest Acquisition II Corporation (Chair), PSP Investments and MEG Energy Corp. Previous directorships included Alignvest Acquisition Corporation, KGS-Alpha Capital Markets L.P., The Global Risk Institute, The Ivey School of Business, The Next36, Bridgeport Health and CanWest Media Works Income Fund.

Mr. Hodgson has a Bachelor of Commerce from the University of Manitoba and a MBA from The Richard Ivey School of Business at Western University. He is a Chartered Accountant, a Chartered Professional Accountant and a member of the Institute of Corporate Directors.

Jessica McDonald

Public Directorships (other than Hydro One and Hydro One Inc.): Coeur Mining Inc. and Trevali Mining Corporation

Public Board Interlocks: None

Ms. McDonald is Interim President and CEO of Canada Post Corporation, a Crown corporation which functions as the primary postal operator in Canada. Previous roles include President and CEO of British Columbia Hydro & Power Authority, a Canadian electric utility in the province of British Columbia, and Executive Vice President of HB Global Advisors Corp., as well as a successful practice in mediation and negotiation on major commercial and industrial projects. In addition, Ms. McDonald has held many positions with the British Columbia government, including the most senior public service position in the provincial government as Deputy Minister to the Premier, Cabinet Secretary and Head of the BC Public Service, responsible for overseeing all aspects of government operations.

Ms. McDonald also serves on the boards of Canada Post Corporation, Coeur Mining Inc. and Trevali Mining Corporation, and is on the Member Council of Sustainable Development Technology Canada. Previous directorships include Powertech Labs (Chair) and Powerex Corp.

Ms. McDonald has a Bachelor of Arts (Political Science) from the University of British Columbia. She is also a member of the Institute of Corporate Directors of Canada.

Russel Robertson (provincial nominee)

Public Directorships (other than Hydro One and Hydro One Inc.): Bausch Health Companies Inc. and Turquoise Hill Resources Ltd.

Public Board Interlocks: None

Mr. Robertson is a corporate director and former Executive Vice President and Head, Anti-Money Laundering, BMO Financial Group, a major Canadian bank. Mr. Robertson has served as Chief Financial Officer, BMO Financial Group and Executive Vice President, Business Integration where he oversaw the integration of Harris Bank and M&I Bank forming BMO Harris Bank. Before joining BMO, he spent over 35 years as a Chartered Professional Accountant holding various senior positions including the positions of Vice-Chair, Deloitte & Touche LLP (Canada) and Canadian Managing Partner, Arthur Andersen LLP (Canada).

 

   21   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Mr. Robertson also serves on the boards of Bausch Health Companies Inc. and Turquoise Hill Resources Ltd. Previous directorships include Virtus Investment Partners, Inc.

Mr. Robertson has a Bachelor of Arts (Honours) in Business Administration from the Ivey School of Business at the University of Western Ontario. He is a Chartered Professional Accountant (FCPA, FCA) and a Fellow of the Institute of Chartered Accountants (Ontario). He is also a member of the Institute of Corporate Directors.

William Sheffield

Public Directorships (other than Hydro One and Hydro One Inc.): Houston Wire & Cable Company, Velan Inc.

Public Board Interlocks: None

Mr. Sheffield is a corporate director. He is the former CEO of Sappi Fine Papers, headquartered in South Africa. Previously, he held senior roles with Abitibi-Consolidated, Inc. and Abitibi-Price, Inc. He began his career in the steel industry and held General Manager, Industrial Engineering and Cold Mill Operating roles at Stelco Inc.

Mr. Sheffield also serves on the boards of Houston Wire & Cable Company, Velan, Inc., Burnbrae Farms Ltd., Longview Aviation Capital and Family Enterprise Xchange. Previous directorships include Canada Post Corporation, Ontario Power Generation, Corby Distilleries, Royal Group Technologies and SHAD.

Mr. Sheffield has a Bachelor of Science (Chemistry) from Carleton University and an MBA from McMaster University. He holds a professional director certification from the Institute of Corporate Directors (ICD.D) and a similar designation from the National Association of Corporate Directors in the US. He also completed the Family Enterprise Advisors Program (FEA) at the University of British Columbia.

Melissa Sonberg

Public Directorships (other than Hydro One and Hydro One Inc.): Exchange Income Corporation

Public Board Interlocks: None

Ms. Sonberg is a corporate director and Adjunct Professor and Executive-in-Residence at McGill University’s Desautel Faculty of Management, a public research university in Montreal, Quebec. She spent the early part of her career in the healthcare industry before joining Air Canada, where she held leadership positions in a range of customer facing, operational and corporate functions. Ms. Sonberg was part of the founding executive team of Aeroplan, now part of AIMIA, a marketing and loyalty analytics company. Ms. Sonberg held positions of Senior Vice President, Human Resources & Corporate Affairs and Senior Vice President, Global Brands, Communications and External Affairs at AIMIA.

Ms. Sonberg also serves on the boards of Exchange Income Corporation, MD Financial Holdings, Inc., Canadian Professional Sales Association, Groupe Touchette, Women in Capital Markets and Equitas - International Centre for Human Rights. Previous directorships include Rideau, Inc., Via Rail Canada, University of Ottawa, International Advisory Board and the McGill University Health Centre.

Ms. Sonberg has a Bachelor of Science (Psychology) from McGill University and a Masters of Health Administration from the University of Ottawa. She is a Certified Human Resource Executive and holds a professional director certification from the Institute of Corporate Directors (ICD.D).

Information Regarding Certain Directors and Executive Officers

As at November 1, 2018, the directors and executive officers of Hydro One and its subsidiaries beneficially owned, controlled or directed, directly or indirectly, as a group, 15,905 common shares, which represented approximately 0.003% of the outstanding common shares.

As at November 1, 2018, approximately 36.4% of the executives (those who hold a vice president role and above or equivalent) (12 out of 33) across Hydro One and its major subsidiaries, including 1 of 5 executive officers, are women.

Corporate Cease Trade Orders and Bankruptcies

Except as described below:

 

none of the directors or executive officers of Hydro One or Hydro One Inc. nor any shareholder holding shares sufficient to materially affect control of Hydro One or Hydro One Inc. is, or within the last 10 years has served as, a director or executive officer of any company that, during such service or within a year after the end of such service, became bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency or was subject to or instituted any proceedings, arrangement or compromise with creditors or had a receiver, receiver manager or trustee appointed to hold its assets;

 

none of the directors or executive officers of Hydro One or Hydro One Inc. is, or within the last 10 years has served as, a director, CEO, or chief financial officer of any company that, during such service or as a result of an event that occurred during such service, was subject to an order (including a cease trade order, or similar order or an order that denied access to any exemption under securities legislation), for a period of more than 30 consecutive days; or

 

none of the directors or executive officers of Hydro One or Hydro One Inc. nor any shareholder holding shares sufficient to materially affect control of Hydro One or Hydro One Inc., within the last 10 years has become bankrupt, made a proposal under any legislation relating to bankruptcy or insolvency, or become subject to or instituted any proceedings, arrangement or compromise with creditors, or had a receiver, receiver manager or trustee appointed to hold the assets of the director.

 

   22   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Blair Cowper-Smith was serving as the Corporate Secretary of Stelco Inc. (Stelco) in 2004. On January 29, 2004, Stelco filed for and was granted Court bankruptcy protection under the Companies’ Creditors Arrangement Act (CCAA). Stelco emerged from Court protection under the CCAA on March 31, 2006. Blair also served as a Director of Golfsmith International Holdings GP Inc. and Golf Town Canada Inc. (Golf Town) from 2016 to 2018. On September 14, 2016, Golf Town filed for and was granted Court bankruptcy protection under the CCAA. Golf Town emerged from Court protection after being sold to Fairfax Financial Holdings Limited and CI Investments Inc. in October 2016.

Penalties or Sanctions

None of the directors or executive officers of Hydro One or Hydro One Inc., nor any shareholder holding shares sufficient to materially affect control of Hydro One or Hydro One Inc., has been subject to any penalties or sanctions imposed by a court relating to securities legislation or by a securities regulatory authority or has entered into a settlement agreement with a securities regulatory authority or been subject to any other penalties or sanctions imposed by a court or regulatory body that would likely be considered important to a reasonable investor making an investment decision.

Conflicts of Interest

To the best of Hydro One’s and Hydro One Inc.’s knowledge, there are no existing material potential conflicts of interest among Hydro One or any of its subsidiaries and the directors or executive officers of Hydro One or any of its subsidiaries as a result of their outside business interests as at the date hereof. Certain of the directors and executive officers serve as directors and executive officers of other public companies. Accordingly, conflicts of interest may arise which could influence these persons in evaluating possible acquisitions or in generally acting on behalf of Hydro One or Hydro One Inc. Where conflicts arise, they are managed through a variety of measures, including declaration of the conflict, recusal from meetings and/or portions of meetings, and the creation of separate board materials for the affected directors.

Interest of Management and Others in Material Transactions

There are no material interests, direct or indirect, of any director or executive officer of Hydro One and its subsidiaries, or any associate or affiliate of any of the foregoing persons, in any transaction within the three years before the date hereof that has materially affected or is reasonably expected to materially affect Hydro One or Hydro One Inc.

Indebtedness of Directors and Executive Officers

No director, executive officer, employee, former director, former executive officer or former employee or associate of any director or executive officer of Hydro One or any of its subsidiaries had any outstanding indebtedness to Hydro One or any of its subsidiaries except routine indebtedness or had any indebtedness that was the subject of a guarantee, support agreement, letter of credit or other similar arrangement or understanding provided by Hydro One or any of its subsidiaries.

Independence Matters

The Board of Hydro One and Hydro One Inc. currently consists of 10 directors, all of whom are independent of Hydro One and Hydro One Inc. and independent of the Province within the meaning of the Governance Agreement.

For Hydro One’s purposes, an independent director is one who is independent of Hydro One and independent of the Province. Directors will be independent of Hydro One if they are independent within the meaning of all Canadian securities laws governing the disclosure of corporate governance practices and stock exchange requirements imposing a number or percentage of independent directors. Pursuant to Canadian securities laws, a director who is “independent” within the meaning of applicable securities laws is one who is free from any direct or indirect relationship which could, in the view of the board, be reasonably expected to interfere with a director’s independent judgement, with certain specified relationships deemed to be non-independent. A director will be “independent of the Province” if he or she is independent of Hydro One under Ontario securities laws governing the disclosure of corporate governance practices, where the Province and certain specified provincial entities are treated as Hydro One’s parent under that definition, but excluding current directors where the relationship ended before August 31, 2015. The Governance Agreement requires each of the directors, other than the CEO, to be both independent of Hydro One and independent of the Province. The Chair of Hydro One is independent of Hydro One and the Province.

 

   23   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

The following table summarizes the committee memberships and independence status of Board members:

 

            Committees                Independence
                    Health, Safety,          
               Human    Environment and    Independent    Independent
     Audit    Governance    Resources      Indigenous Peoples      of    of
  Director    Committee    Committee    Committee    Committee    Hydro One    the Province

Cherie Brant

      v       v    v    v

Blair Cowper-Smith

      v    v         v    v

Anne Giardini

   v          v    v    v

David Hay

   v          v    v    v

Timothy Hodgson

      v    v         v    v

Jessica McDonald

   v       v         v    v

Russel Robertson

   v       v         v    v

William Sheffield

   v          v    v    v

Melissa Sonberg

      v    v         v    v

Tom Woods

                       v    v

Diversity Policy

The Board has adopted a board diversity policy which formalizes the company’s commitment to diversity and its desire to maintain a board comprising talented and dedicated directors whose skills, experience, knowledge and backgrounds reflect the diverse nature of the business environment in which it operates, including an appropriate number of female directors. The Board aspires towards a board composition in which each gender comprises at least 40% of the directors on the Board. Currently, the Board includes four female directors (40%).

Director Attendance

Directors are expected to attend board meetings, meetings of the committees on which they serve and the annual meeting of shareholders.

Number of Board and Committee Meetings (August 13, 2018 to November 1, 2018)1:

 

      Regular    Non-Regular    In Camera Sessions

Board

   1    5    5

Audit Committee

   1    2    3

Health, Safety, Environment and Indigenous Peoples Committee

   1       1

Human Resources Committee

   1    2    3

Governance Committee

   1       1

 

1

All of the current directors were appointed directors of Hydro One effective August 13, 2018. The directors of Hydro One are also directors of Hydro One Inc. and the two boards and each committee thereof hold joint meetings.

Audit Committee

The Audit Committee must consist of at least three directors, all of whom are persons determined by Hydro One to be both “independent” (within the meaning of all Canadian securities laws and stock exchange requirements and the Governance Agreement) and “financially literate” (within the meaning of other applicable requirements or guidelines for audit committee service under securities laws or the rules of any applicable stock exchange, including National Instrument 52-110 - Audit Committees). At least one member of the Audit Committee will qualify as an “audit committee financial expert” as defined by the applicable rules of the US Securities and Exchange Commission. The Audit Committee comprises William Sheffield (Chair), Anne Giardini, David Hay, Jessica McDonald and Russel Robertson. Each of the Audit Committee members is independent and financially literate and each has an understanding of the accounting principles used to prepare Hydro One’s financial statements and varied experience as to the general application of such accounting principles, as well as an understanding of the internal controls and procedures necessary for financial reporting. Russel Robertson and David Hay each qualify as an audit committee financial expert.

Please refer to the biographies of our Audit Committee members described under “- Directors and Executive Officers” above for details of their additional invaluable skills and experience.

Human Resource Committee

Hydro One’s management team, the Human Resources Committee and the company’s compensation advisors all play a key role in determining executive compensation for the company’s directors and executives and in managing compensation risk on behalf of the Board of Hydro One. The Human Resources Committee is responsible for assisting the Board in fulfilling its oversight responsibilities relating to the attraction and retention of key senior management.

 

   24   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

All of the members of the Human Resources Committee are independent. The Human Resources Committee comprises Melissa Sonberg (Chair), Blair Cowper-Smith, Timothy Hodgson, Jessica McDonald and Russel Robertson. All of the members of the Human Resources Committee have gained the following relevant experience in human resources and compensation by serving as an executive officer (or equivalent) of a major organization and/or through prior service on the compensation committee of a stock exchange listed company or otherwise:

 

human resources experience (experience with benefit, pension and compensation programs (in particular, executive compensation));

 

risk management experience (knowledge and experience with internal risk controls, risk assessments and reporting as it pertains to executive compensation); and

 

executive leadership experience (experience as a senior executive/officer of a public company or major organization). Please refer to the biographies of our Human Resources Committee members described under “- Directors and Executive Officers” above for details of their additional invaluable skills and experience.

CEO Selection Committee

The Board has also formed an Ad-hoc CEO Selection Committee to identify and select a President and CEO.

Compensation Policies and Practices

Other than as set forth in Hydro One’s management information circular dated March 19, 2018 prepared in connection with the annual meeting of shareholders held on May 15, 2018 or as otherwise described below, there have been no material changes to the policies and practices adopted by the Board of Hydro One or Hydro One Inc. to determine compensation for Hydro One’s or Hydro One Inc.’s directors and executive officers since January 1, 2018.

Changes to Hydro One’s Board and CEO Compensation

As disclosed under “- Directors and Executive Officers” above, on July 11, 2018, Hydro One, on behalf of itself and Hydro One Inc., announced that it had entered into the Letter Agreement for the purpose of the orderly replacement of the Board of Hydro One and Hydro One Inc. and the retirement of Mayo Schmidt as the CEO effective July 11, 2018. In accordance with the Letter Agreement, Hydro One has agreed to consult with the Province in respect of future matters of executive compensation. In addition, the then-existing Hydro One and Hydro One Inc. Board volunteered and agreed to immediately reduce board compensation to the levels contemplated by the pre-January 1, 2018 director compensation policy. The then-existing Hydro One and Hydro One Inc. Board also volunteered and agreed to forego any compensation for their service after June 30, 2018.

In connection with Mr. Schmidt’s retirement, he received amounts consistent with Hydro One’s retirement policies applicable to his outstanding equity awards and his employment agreement as previously disclosed and was not entitled to severance. Mr. Schmidt received a $0.4 million lump sum payment in lieu of all post-retirement benefits and allowances.

Bill 2

On July 16, 2018, the Legislative Assembly of Ontario introduced Bill 2 (Bill 2) titled the Urgent Priorities Act, 2018. As an omnibus bill, among other matters, Bill 2, as proposed, would amend the Ontario Energy Board Act, 1998 (OEB Act) and enact the Hydro One Accountability Act (Act), and would require the Board of Hydro One to establish a new compensation framework for the Board and certain executives of Hydro One and its subsidiaries (excluding subsidiaries incorporated outside Canada) in consultation with the Province and the other five largest shareholders of Hydro One, which compensation framework is subject to approval by the Management Board of Cabinet. The Act provides the Management Board of Cabinet with the authority to issue directives governing the compensation of directors and certain executives of Hydro One and its subsidiaries (excluding subsidiaries incorporated outside Canada). The introduction of Bill 2 may adversely impact Hydro One and Hydro One Inc.’s ability to continue to attract and retain executives.

The Act also requires Hydro One to annually provide public disclosure concerning compensation paid to certain executives, and provides that the OEB Act will be amended so that the rates charged by Hydro One and its subsidiaries shall not reflect amounts paid for compensation of the CEO and certain executives of Hydro One and its subsidiaries. The impact of this amendment is expected to restrict Hydro One’s ability to recover certain amounts paid for executive compensation through separate rate mechanisms, which is estimated to result in a reduction in Hydro One’s net income for the year ending December 31, 2018 of up to $9 million, and is subject to a final determination by the OEB. The reduction may be materially lower, depending on the determination by the OEB of the executives whose compensation is to be excluded. Bill 2 expressly provides that certain causes of action and proceedings are not available or will be barred against the Province, Hydro One or any of its subsidiaries, or any of its current or former officers, directors, employees or agents in respect of the Act, the Province’s involvement in compensation matters or other aspects of the corporate governance of Hydro One or any of its subsidiaries or any alleged misrepresentation in any prospectus, document or other public statement related to the involvement of the Province in compensation matters at Hydro One or any of its subsidiaries. Bill 2 received Royal Assent on July 25, 2018.

 

   25   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Province of Ontario

Notwithstanding the Governance Agreement, and in light of actions taken by the Province following the provincial election in June 2018 including the passage of Bill 2, the Province may elect to make further decisions relevant to Hydro One that could be detrimental to the interests of shareholders.

NON-GAAP MEASURES

FFO

FFO is defined as net cash from operating activities, adjusted for (i) changes in non-cash balances related to operations, (ii) dividends paid on preferred shares, and (iii) distributions to noncontrolling interest. Management believes that FFO is helpful as a supplemental measure of the Company’s operating cash flows as it excludes timing-related fluctuations in non-cash operating working capital and cash flows not attributable to common shareholders. As such, FFO provides a consistent measure of the cash generating performance of the Company’s assets.

 

     Three months ended     Nine months ended  
     September 30     September 30  
  (millions of dollars)    2018     2017     2018     2017  

Net cash from operating activities

     508       442       1,176       1,193  

Changes in non-cash balances related to operations

     (85     (52     54       1  

Preferred share dividends

     (4     (4     (13     (13

Distributions to noncontrolling interest

     (1     (1     (6     (4

FFO

     418       385       1,211       1,177  

Adjusted Net Income and Adjusted EPS

The following basic and diluted Adjusted EPS has been calculated by management on a supplementary basis which excludes income related to the Avista Corporation acquisition from net income. Adjusted EPS is used internally by management to assess the Company’s performance and is considered useful because it excludes the impact of acquisition-related costs and loss or gain on the deal-contingent foreign exchange forward contract. It provides users with a comparative basis to evaluate the current ongoing operations of the Company compared to prior year.

 

     Three months ended September 30     Nine months ended September 30  
  (millions of dollars, except number of shares and EPS)    2018     2017     2018     2017  

Net income attributable to common shareholders

     194       219       616       503  

Impacts related to Avista Corporation acquisition:

        

Avista Corporation-related costs (before tax)

     40       24       24       27  

Tax impact

     (7     (6     (9     (6

Avista Corporation-related costs (after tax)

     33       18       15       21  

    

                                

Adjusted net income attributable to common shareholders

     227       237       631       524  

Weighted average number of shares

        

Basic

     595,882,438       595,386,308       595,714,016       595,254,201  

Effect of dilutive stock-based compensation plans

     1,968,856       2,130,453       2,128,211       2,172,635  

Diluted

     597,851,294       597,516,761       597,842,227       597,426,836  

Adjusted EPS

        

Basic

     $0.38       $0.40       $1.06       $0.88  

Diluted

     $0.38       $0.40       $1.06       $0.88  

 

   26   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

Revenues, Net of Purchased Power

Revenues, net of purchased power is defined as revenues less the cost of purchased power. Management believes that revenue, net of purchased power is helpful as a measure of net revenues for the Distribution segment, as purchased power is fully recovered through revenues.

 

    

Three months ended

September 30

    

Nine months ended

September 30

 
  (millions of dollars)    2018      2017      2018      2017  

Revenues

     1,606        1,522        4,659        4,551  

Less: Purchased power

     733        675        2,158        2,213  

Revenues, net of purchased power

     873        847        2,501        2,338  
     Three months ended
September 30
     Nine months ended
September 30
 
  (millions of dollars)    2018      2017      2018      2017  

Distribution revenues

     1,103        1,040        3,284        3,317  

Less: Purchased power

     733        675        2,158        2,213  

Distribution revenues, net of purchased power

     370        365        1,126        1,104  

FFO, basic and diluted Adjusted EPS, Adjusted Net Income, Revenues, Net of Purchased Power, and Distribution Revenues, Net of Purchased Power are not recognized measures under US GAAP and do not have a standardized meaning prescribed by US GAAP. They are therefore unlikely to be directly comparable to similar measures presented by other companies. They should not be considered in isolation nor as a substitute for analysis of the Company’s financial information reported under US GAAP.

RELATED PARTY TRANSACTIONS

The Province is a shareholder of Hydro One with approximately 47.4% ownership at September 30, 2018. The IESO, Ontario Power Generation Inc. (OPG), Ontario Electricity Financial Corporation (OEFC), and the OEB, are related parties to Hydro One because they are controlled or significantly influenced by the Province. The following is a summary of the Company’s related party transactions during the three and nine months ended September 30, 2018 and 2017:

 

(millions of dollars)

 

        Three months ended
September 30
     Nine months ended
September 30
 
  Related Party    Transaction    2018      2017      2018      2017  

Province

   Dividends paid      69        69        205        231  

IESO

   Power purchased      321        276        1,079        1,169  
   Revenues for transmission services      474        390        1,293        1,124  
   Amounts related to electricity rebates      113        181        353        321  
   Distribution revenues related to rural rate protection      59        61        177        185  
   Distribution revenues related to the supply of electricity to remote northern communities      8        8        24        24  
     Funding received related to Conservation and Demand Management programs      11        18        33        44  

OPG

   Power purchased      2        2        8        7  
   Revenues related to provision of construction and equipment maintenance services      2        2        6        6  
     Costs related to the purchase of services                           1  

OEFC

   Power purchased from power contracts administered by the OEFC      1               2        1  

OEB

   OEB fees      2        2        6        6  

DISCLOSURE CONTROLS AND PROCEDURES AND INTERNAL CONTROL OVER FINANCIAL REPORTING

Management is responsible for establishing and maintaining adequate disclosure controls and procedures and internal control over financial reporting as defined in National Instrument 52-109 Certification of Disclosure in Issuers’ Annual and Interim Filings. Internal control, no matter how well designed and operated, can provide only reasonable assurance of achieving the desired control objectives and due to its inherent limitations, may not prevent or detect all misrepresentations.

There were no changes in the Company’s internal control over financial reporting during the three months ended September 30, 2018 that materially affected, or are reasonably likely to materially affect, the Company’s disclosure controls and procedures and internal control over financial reporting.

 

   27   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

NEW ACCOUNTING PRONOUNCEMENTS

The following tables present Accounting Standards Codification (ASC) guidance issued by the FASB that are applicable to Hydro One:

Recently Adopted Accounting Guidance

 

Guidance    Date issued    Description    Effective date    Impact on Hydro One
ASC 606    May 2014 – November 2017    ASC 606 Revenue from Contracts with Customers replaced ASC 605 Revenue Recognition. ASC 606 provides guidance on revenue recognition relating to the transfer of promised goods or services to customers in an amount that reflects the consideration to which the entity expects to be entitled in exchange for those goods and services.    January 1, 2018    Hydro One adopted ASC 606 on January 1, 2018 using the retrospective method, without the election of any practical expedients and there was no material impact to the Company’s revenue recognition policy upon adoption. The Company has included the disclosure requirements of ASC 606 for interim periods in the year of adoption.
ASU 2017-07    March 2017    Service cost components of net benefit cost associated with defined benefit plans are required to be reported in the same line as other compensation costs arising from services rendered by the Company’s employees. All other components of net benefit cost are to be presented in the income statement separately from the service cost component. Only the service cost component is eligible for capitalization where applicable.    January 1, 2018    Hydro One applied for a regulatory asset to maintain the capitalization of post-employment benefit related costs and as such, there is no material impact upon adoption. See Note 2 - Significant Accounting Policies and Note 11 - Regulatory Assets and Liabilities in the Hydro One financial statements for the three and nine months ended September 30, 2018.
Recently Issued Accounting Guidance Not Yet Adopted      
Guidance    Date issued    Description    Effective date    Anticipated impact on Hydro One
2016-02 2018-01 2018-10 2018-11    February 2016 – July 2018    Lessees are required to recognize the rights and obligations resulting from operating leases as assets (right to use the underlying asset for the term of the lease) and liabilities (obligation to make future lease payments) on the balance sheet. ASU 2018-01 permits an entity to elect an optional practical expedient to not evaluate under ASC 842 land easements that exist or expired before the entity’s adoption of ASC 842 and that were not previously accounted for as leases under ASC 840. ASU 2018-10 amends narrow aspects of ASC 842. ASU 2018-11 provides entities with an additional and option transition method in adopting ASC 842. ASU 2018-11 also permits lessors to elect an optional practical expedient to not separate non-lease components from the associated lease component by underlying asset classes.    January 1, 2019    The Company has reviewed a substantial number of existing leases and relevant contracts and continues its assessment activities. No quantitative determination has been made at this time. The Company is on track for implementation of this standard by the effective date.
2018-07    June 2018    Expansion in the scope of ASC 718 to include share-based payment transactions for acquiring goods and services from non-employees. Previously, ASC 718 was only applicable to share-based payment transactions for acquiring goods and services from employees.    January 1, 2019    Under assessment
2018-13    August 2018    Disclosure requirements on fair value measurements in ASC 820 are modified to improve the effectiveness of disclosures in financial statement notes.    January 1, 2020    Under assessment
2018-14    August 2018    Disclosure requirements related to single-employer defined benefit pension or other post-retirement benefit plans are added, removed or clarified to improve the effectiveness of disclosures in financial statement notes.    January 1, 2021    Under assessment
2018-15    August 2018    The amendment aligns the requirements for capitalizing implementation costs incurred in a hosting arrangement that is a service contract with the requirements for capitalizing implementation costs incurred to develop or obtain internal-use software. The accounting for the service element of a hosting arrangement is not affected by the amendment.    January 1, 2020    Under assessment

 

   28   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

FORWARD-LOOKING STATEMENTS AND INFORMATION

The Company’s oral and written public communications, including this document, often contain forward-looking statements that are based on current expectations, estimates, forecasts and projections about the Company’s business and the industry, regulatory and economic environments in which it operates, and include beliefs and assumptions made by the management of the Company. Such statements include, but are not limited to, statements regarding: the Company’s transmission and distribution rate applications, including resulting decisions, rates and expected impacts and timing; the Company’s liquidity and capital resources and operational requirements; expectations regarding credit ratings; the Operating Credit Facilities; the Acquisition Credit Facilities; expectations regarding the Company’s financing activities; the Company’s maturing debt; ongoing and planned projects, including expected results, costs and completion dates; expected future capital investments, including expected timing and investment plans; contractual obligations and other commercial commitments; the OEB and applications before the OEB; the Company’s share capital and conversion of outstanding stock options and convertible debentures; NRLP and the Niagara Reinforcement Project, the Lake Superior Link Project, and related regulatory applications; collective agreements; the pension plan, future pension contributions, valuations and expected impacts; impacts of OEB treatment of post-employment benefit costs; dividends; estimated ETR; non-GAAP measures; internal control over financial reporting; recent accounting-related guidance; the Universal Base Shelf Prospectus; expectations relating to filing of a future base shelf prospectus by Hydro One Holdings Limited; the convertible debentures; the Exemptive Relief; the status of the Company’s acquisitions and mergers, including Orillia Power, Peterborough Distribution and Avista Corporation; the Company’s financing strategy and foreign currency hedging relating to the acquisition of Avista Corporation; class action litigation, including litigation relating to the Merger; the risk that the Company may fail to complete the Merger; the Agreement with the Province; changes to Hydro One’s Board and CEO, and Bill 2 and its anticipated impacts, including expectations relating to executive compensation; and the potential of government intervention in Hydro One’s business. Words such as “expect”, “anticipate”, “intend”, “attempt”, “may”, “plan”, “will”, “believe”, “seek”, “estimate”, “goal”, “aim”, “target”, and variations of such words and similar expressions are intended to identify such forward-looking statements. These statements are not guarantees of future performance and involve assumptions and risks and uncertainties that are difficult to predict. Therefore, actual outcomes and results may differ materially from what is expressed, implied or forecasted in such forward-looking statements. Hydro One does not intend, and it disclaims any obligation, to update any forward-looking statements, except as required by law.

These forward-looking statements are based on a variety of factors and assumptions including, but not limited to, the following: no unforeseen changes in the legislative and operating framework for Ontario’s electricity market or for Hydro One specifically; favourable decisions from the OEB and other regulatory bodies concerning outstanding and future rate and other applications; no unexpected delays in obtaining the required approvals; no unforeseen changes in rate orders or rate setting methodologies for the Company’s distribution and transmission businesses; continued use of US GAAP; a stable regulatory environment; no unfavourable changes in environmental regulation; no significant changes to the Company’s current credit ratings; no unforeseen impacts of new accounting pronouncements; and no significant event occurring outside the ordinary course of business. These assumptions are based on information currently available to the Company, including information obtained from third party sources. Actual results may differ materially from those predicted by such forward-looking statements. While Hydro One does not know what impact any of these differences may have, the Company’s business, results of operations, financial condition and credit stability may be materially adversely affected. Factors that could cause actual results or outcomes to differ materially from the results expressed or implied by forward-looking statements include, among other things:

Risks Related to the Avista Corporation Merger:

 

risks relating to the Merger, including (i) the risk that Hydro One may fail to complete the Merger, (ii) uncertainty regarding the length of time required to complete the Merger, (iii) the risk that the purchase price for Avista Corporation could increase, (iv) the risk that the anticipated benefits of the Merger may not materialize or may not occur within the time periods contemplated by Hydro One;

 

risks related to the financing of the Merger; and

 

risks associated with the Province’s share ownership of Hydro One and other relationships with the Province, including potential conflicts of interest that may arise between Hydro One, the Province and related parties.

 

Risks

Related to the Business:

 

risks associated with the Province’s share ownership of Hydro One and other relationships with the Province, including potential conflicts of interest that may arise between Hydro One, the Province and related parties;

 

risks associated with the Province exercising further legislative and regulatory powers in the implementation of Bill 2;

 

regulatory risks and risks relating to Hydro One’s revenues, including risks relating to rate orders, actual performance against forecasts and capital expenditures, or denials of applications;

 

the risk that the Company may be unable to comply with regulatory and legislative requirements or that the Company may incur additional costs for compliance that are not recoverable through rates;

 

the risk of exposure of the Company’s facilities to the effects of severe weather conditions, natural disasters or other unexpected occurrences for which the Company is uninsured or for which the Company could be subject to claims for damage;

 

public opposition to and delays or denials of the requisite approvals and accommodations for the Company’s planned projects;

 

   29   

LOGO


HYDRO ONE LIMITED

MANAGEMENT’S DISCUSSION AND ANALYSIS (continued)

For the three and nine months ended September 30, 2018 and 2017

 

 

the risk that Hydro One may incur significant costs associated with transferring assets located on reserves (as defined in the Indian Act (Canada));

 

the risks associated with information system security and maintaining a complex IT system infrastructure;

 

the risks related to the Company’s work force demographic and its potential inability to attract and retain qualified personnel;

 

the risk of labour disputes and inability to negotiate appropriate collective agreements on acceptable terms consistent with the Company’s rate decisions;

 

risk that the Company is not able to arrange sufficient cost-effective financing to repay maturing debt and to fund capital expenditures;

 

the risk of a credit rating downgrade and its impact on the Company’s funding and liquidity;

 

risks associated with fluctuations in interest rates and failure to manage exposure to credit risk;

 

the risk that the Company may not be able to execute plans for capital projects necessary to maintain the performance of the Company’s assets or to carry out projects in a timely manner;

 

the risk of non-compliance with environmental regulations or failure to mitigate significant health and safety risks and inability to recover environmental expenditures in rate applications;

 

the risk that assumptions that form the basis of the Company’s recorded environmental liabilities and related regulatory assets may change;

 

the risk of not being able to recover the Company’s pension expenditures in future rates and uncertainty regarding the future regulatory treatment of pension, other post-employment benefits and post-retirement benefits costs;

 

the potential that Hydro One may incur significant expenses to replace functions currently outsourced if agreements are terminated or expire before a new service provider is selected;

 

the risks associated with economic uncertainty and financial market volatility;

 

the inability to prepare financial statements using US GAAP;

 

the impact of the ownership by the Province of lands underlying the Company’s transmission system; and

 

the risk related to the impact of the new accounting pronouncements.

Hydro One cautions the reader that the above list of factors is not exhaustive. Some of these risks and other factors are discussed in additional detail under the section “Other Developments - Avista Corporation Merger” and under the section “Hydro One Board of Directors and Executive Officers - Province of Ontario” in this MD&A, and in the section “Risk Management and Risk Factors” in the 2017 MD&A.

In addition, Hydro One cautions the reader that information provided in this MD&A regarding the Company’s outlook on certain matters, including potential future investments, is provided in order to give context to the nature of some of the Company’s future plans and may not be appropriate for other purposes.

Additional information about Hydro One, including the Company’s Annual Information Form, is available on SEDAR at www.sedar.com

and the Company’s website at www.HydroOne.com/Investors.

 