XML 96 R84.htm IDEA: XBRL DOCUMENT v3.25.3
Commitments and Contingencies (Details)
$ in Millions
1 Months Ended 9 Months Ended
Aug. 31, 2024
state
May 31, 2024
petition
unit
category
Aug. 31, 2023
application
May 31, 2023
facility
Mar. 31, 2023
state
Oct. 31, 2022
Jul. 31, 2022
application
Jan. 31, 2022
application
Oct. 31, 2021
application
Sep. 30, 2025
USD ($)
application
lawsuit
Apr. 30, 2025
USD ($)
Mar. 31, 2025
USD ($)
Feb. 28, 2025
Jul. 31, 2019
plant
Loss Contingencies [Line Items]                            
Legal claim, duration           5 years                
Number of nuclear power plants | plant                           2
Greenhouse gas emissions, final rule, number of states filing petitions challenging final rule | petition   17                        
Environmental protection agency, number of categories of unit | category   2                        
Environmental protection agency, number of potential unit | unit   10                        
United States Environmental Protection Agency                            
Loss Contingencies [Line Items]                            
Cross-state air pollution rule, 2015 ozone national ambient air quality standards, federal implementation plan, beginning 2023 ozone season, number of states subject to rule | state         22                  
Clean air act, regional haze program, best available retrofit technology alternative, sulfur dioxide emissions, number of electricity generation units in texas subject to program | facility       6                    
Federal coal combustion residual rule, proposed groundwater monitoring and closure requirement, number of states challenging rule | state 17                          
Illinois Environmental Protection Agency                            
Loss Contingencies [Line Items]                            
Coal combustion residuals, rules for closure of coal ash ponds in Illinois, number of operating permit applications filed | application                 18 11        
Coal combustion residuals, rules for closure of coal ash ponds in Illinois, number of construction permit application filed | application     1       5 3            
ASAOC                            
Loss Contingencies [Line Items]                            
Total costs                   $ 110.0        
Moss Landing Power Plant (Battery Storage Project) | ASAOC                            
Loss Contingencies [Line Items]                            
Total costs                   110.0        
Martin Lake Steam Electric Station | Maximum                            
Loss Contingencies [Line Items]                            
Clean air act, regional haze program, best available retrofit technology alternative, sulfur dioxide emissions, number of years remaining before generation unit is subject to program period       3 years                    
Coleto Creek | Maximum                            
Loss Contingencies [Line Items]                            
Clean air act, regional haze program, best available retrofit technology alternative, sulfur dioxide emissions, number of years remaining before generation unit is subject to program period       5 years                    
Beaver Valley, Davis-Besse And Perry Facilities                            
Loss Contingencies [Line Items]                            
Nuclear decontamination and property insurance, maximum coverage                     $ 2,250.0      
Non-nuclear property damage insurance, maximum coverage                     1,000.0 $ 1,500.0    
Non-nuclear property damage insurance, deductible per accident, general                     10.0      
Non-nuclear property damage insurance, deductible per incident, natural hazard                     20.0      
Accidental outage insurance, coverage for obtaining replacement energy after 12 week waiting period, maximum weekly coverage first 52 weeks                   2.5 4.5      
Accidental outage insurance, coverage for obtaining replacement                   1.5 2.7      
Accidental outage insurance, coverage for obtaining replacement energy after 12 week waiting period, maximum weekly payments, remaining 26 weeks non-nuclear and 71 weeks nuclear property                   2.0 3.6      
Accidental outage insurance, coverage for obtaining replacement energy, coverage limit for non-nuclear accidents                   208.0 291.0      
Accidental outage insurance, coverage for obtaining replacement energy, coverage limit for nuclear accidents                   $ 350.0 $ 490.0      
Gas Index Pricing Litigation | Wisconsin                            
Loss Contingencies [Line Items]                            
Loss contingency, pending claims, number | lawsuit                   1        
Greenhouse Gas Emissions (GHG)                            
Loss Contingencies [Line Items]                            
Litigation, period   90 days                        
Legacy CCR Rulemaking                            
Loss Contingencies [Line Items]                            
Litigation, period                         120 days  
Letters of Credit | Vistra Operations Company LLC                            
Loss Contingencies [Line Items]                            
Letters of credit outstanding                   $ 2,782.0        
Letters of Credit | Vistra Operations Company LLC | Support Risk Management and Trading Margin Requirements Including Over the Counter Hedging Transactions and Collateral Postings with Electric Reliability Council of Texas                            
Loss Contingencies [Line Items]                            
Letters of credit outstanding                   2,400.0        
Letters of Credit | Vistra Operations Company LLC | Support Battery and Solar Development Projects                            
Loss Contingencies [Line Items]                            
Letters of credit outstanding                   257.0        
Letters of Credit | Vistra Operations Company LLC | Support Executory Contracts and Insurance Agreements                            
Loss Contingencies [Line Items]                            
Letters of credit outstanding                   25.0        
Letters of Credit | Vistra Operations Company LLC | Support Retail Electric Provider's financial requirements with the Public Utility Commission of Texas                            
Loss Contingencies [Line Items]                            
Letters of credit outstanding                   86.0        
Letters of Credit | Vistra Operations Company LLC | Miscellaneous Credit Support Requirements                            
Loss Contingencies [Line Items]                            
Letters of credit outstanding                   14.0        
Surety Bonds | Vistra Operations Company LLC                            
Loss Contingencies [Line Items]                            
Surety bonds outstanding                   $ 995.0