XML 55 R43.htm IDEA: XBRL DOCUMENT v3.25.2
Business, Significant Accounting Policies, Significant Events, and Recent Developments - Narrative (Details)
$ in Millions
3 Months Ended 6 Months Ended 12 Months Ended
Jun. 30, 2025
USD ($)
MW
Mar. 31, 2025
USD ($)
Jun. 30, 2024
USD ($)
Jun. 30, 2025
USD ($)
segment
MW
Jun. 30, 2024
USD ($)
Dec. 31, 2024
USD ($)
Jul. 31, 2025
USD ($)
Jul. 02, 2025
USD ($)
Jan. 16, 2025
facility
MW
Nov. 27, 2024
MW
Line of Credit Facility [Line Items]                    
Number of reportable segments | segment       5            
Property, plant and equipment — net $ 17,736     $ 17,736   $ 18,173        
Other current liabilities 694     694   645        
Other noncurrent liabilities 1,326     1,326   1,270        
Insurance settlements receivable 324 $ 439   324   0        
Insurance recoveries 80     80            
Interest costs incurred 6     20            
Other income, net 191   $ 59 186 $ 146          
Pulaski | Term Loan | Subsequent Event                    
Line of Credit Facility [Line Items]                    
Debt instrument, face amount             $ 168 $ 168    
Accounts Receivable Securitization Program | Maximum                    
Line of Credit Facility [Line Items]                    
Account receivable securitization program, total borrowing capacity 1,000     1,000            
Accounts Receivable Securitization Program | Maximum | Subsequent Event                    
Line of Credit Facility [Line Items]                    
Account receivable securitization program, total borrowing capacity             $ 1,100      
ASAOC                    
Line of Credit Facility [Line Items]                    
Total cost       110            
Interest costs incurred 25     102            
Moss Landing Power Plant (Battery Storage Project)                    
Line of Credit Facility [Line Items]                    
Other current liabilities   8                
Insurance settlements receivable 304 425   304   0        
Insurance recoveries 0     0            
Interest costs incurred 0     0            
Moss Landing Power Plant (Battery Storage Project) | Moss Landing Battery Energy Storage System Phase I                    
Line of Credit Facility [Line Items]                    
Battery energy storage system capacity | MW                 300  
Depreciation expense   400                
Insurance settlements, limit amount $ 500     $ 500            
Insurance settlements receivable   425                
Moss Landing Power Plant (Battery Storage Project) | Moss Landing Battery Energy Storage System Phases II and III                    
Line of Credit Facility [Line Items]                    
Number of battery facilities | facility                 2  
Moss Landing Power Plant (Battery Storage Project) | Moss Landing Battery Energy Storage System Phase III                    
Line of Credit Facility [Line Items]                    
Battery energy storage system capacity | MW 350     350            
Moss Landing Power Plant (Battery Storage Project) | Moss Landing Battery Energy Storage System Phase II                    
Line of Credit Facility [Line Items]                    
Battery energy storage system capacity | MW 100     100            
Property, plant and equipment — net $ 170     $ 170            
Moss Landing Power Plant (Battery Storage Project) | ASAOC                    
Line of Credit Facility [Line Items]                    
Total cost       110            
Estimated liability costs incurred 18     18            
Environmental remediation obligation 92     92            
Other current liabilities 74     74            
Other noncurrent liabilities 18     18            
Interest costs incurred 25     102            
Martin Lake Incident                    
Line of Credit Facility [Line Items]                    
Insurance settlements receivable 20 $ 14   20   0        
Insurance recoveries 80     80            
Interest costs incurred 6     20            
Martin Lake Incident | ASAOC                    
Line of Credit Facility [Line Items]                    
Interest costs incurred 0     0            
Martin Lake Incident | ERCOT                    
Line of Credit Facility [Line Items]                    
Battery energy storage system capacity | MW                   815
Depreciation expense           $ 1        
Total cash capital expenditures       280            
Capital expenditures incurred       100            
Insurance recoveries       100            
Interest costs incurred       $ 20            
Other income, net $ 80