Litigation

In the normal course of its operations, the Company becomes involved in various legal actions, including claims relating to injuries and damage to property. The Company maintains provisions it considers to be adequate for such actions. While the final outcome with respect to actions outstanding or pending at September 30, 2024 cannot be predicted with certainty, it is the opinion of management that their resolution will not have a material adverse effect on the Company’s business, financial position, results of operations, or liquidity. However, an unexpected adverse resolution of one or more of these legal actions could have a material adverse effect on the Company's business, financial position, results of operations, or liquidity in a particular quarter or fiscal year.

Legal proceedings related to Lac-Mégantic rail accident

On July 6, 2013, a train carrying petroleum crude oil operated by Montréal Maine and Atlantic Railway (“MMAR”) or a subsidiary, Montréal Maine & Atlantic Canada Co. (“MMAC” and collectively the “MMA Group”), derailed in Lac-Mégantic, Québec. The derailment occurred on a section of railway owned and operated by the MMA Group and while the MMA Group exclusively controlled the train.

Following the derailment, MMAC sought court protection in Canada under the Companies’ Creditors Arrangement Act and MMAR filed for bankruptcy in the U.S. Plans of arrangement were approved in both Canada and the U.S. (the “Plans”), providing for the distribution of approximately $440 million amongst those claiming derailment damages.

A number of legal proceedings, set out below, were commenced in Canada and the U.S. against the Company and others:

(1)Québec's Minister of Sustainable Development, Environment, Wildlife and Parks ordered various parties, including the Company, to remediate the derailment site (the "Cleanup Order") and served the Company with a Notice of Claim for $95 million for those costs. The Company appealed the Cleanup Order and contested the Notice of Claim with the Administrative Tribunal of Québec. These proceedings are stayed pending determination of the Attorney General of Québec (“AGQ”) action (paragraph 2 below).

(2)The AGQ sued the Company in the Québec Superior Court claiming $409 million in damages, which was amended and reduced to $315 million (the “AGQ Action”). The AGQ Action alleges that: (i) the Company was responsible for the petroleum crude oil from its point of origin until its delivery to Irving Oil Ltd.; and (ii) the Company is vicariously liable for the acts and omissions of the MMA Group.

(3)A class action in the Québec Superior Court on behalf of persons and entities residing in, owning or leasing property in, operating a business in, or physically present in Lac-Mégantic at the time of the derailment was certified against the Company on May 8, 2015 (the "Class Action"). Other defendants including MMAC and Mr. Thomas Harding ("Harding") were added to the Class Action on January 25, 2017. On November 28, 2019, the plaintiffs' motion to discontinue their action against Harding was granted. The Class Action seeks unquantified damages, including for wrongful death, personal injury, property damage, and economic loss.

(4)Eight subrogated insurers sued the Company in the Québec Superior Court claiming approximately $16 million in damages, which was amended and reduced to approximately $15 million (the “Promutuel Action”), and two additional subrogated insurers sued the Company claiming approximately $3 million in damages (the “Royal Action”). Both actions contain similar allegations as the AGQ Action. The actions do not identify the subrogated parties. As such, the extent of any overlap between the damages claimed in these actions and under the Plans is unclear. The Royal Action is stayed pending determination of the consolidated proceedings described below.

On December 11, 2017, the AGQ Action, the Class Action and the Promutuel Action were consolidated. The joint liability trial of these consolidated claims commenced on September 21, 2021 with oral arguments ending on June 15, 2022. The Québec Superior Court issued a decision on December 14, 2022 dismissing all claims against the Company, finding that the Company’s actions were not the direct and immediate cause of the accident and the damages suffered by the plaintiffs. All three plaintiffs
filed a declaration of appeal on January 13, 2023. The appeal was heard October 7 to 10, 2024 and the Québec Court of Appeal reserved its decision. A damages trial will follow after the disposition of all appeals, if necessary.

(5)Forty-eight plaintiffs (all individual claims joined in one action) sued the Company, MMAC, and Harding in the Québec Superior Court claiming approximately $5 million in damages for economic loss and pain and suffering, and asserting similar allegations as in the Class Action and the AGQ Action. The majority of the plaintiffs opted-out of the Class Action and all but two are also plaintiffs in litigation against the Company, described in paragraph 7 below. This action is stayed pending determination of the consolidated claims described above.

(6)The MMAR U.S. bankruptcy estate representative commenced an action against the Company in November 2014 in the Maine Bankruptcy Court claiming that the Company failed to abide by certain regulations and seeking approximately U.S. $30 million in damages for MMAR’s loss in business value according to an expert report filed by the bankruptcy estate. This action asserts that the Company knew or ought to have known that the shipper misclassified the petroleum crude oil and therefore should have refused to transport it. Summary judgment motion was argued and taken under advisement on June 9, 2022, and decision is pending. On May 23, 2023, the case management judge stayed the proceedings pending the outcome of the appeal in the Canadian consolidated claims.

(7)The class and mass tort action commenced against the Company in June 2015 in Texas (on behalf of Lac-Mégantic residents and wrongful death representatives) and the wrongful death and personal injury actions commenced against the Company in June 2015 in Illinois and Maine, were all transferred and consolidated in Federal District Court in Maine (the “Maine Actions”). The Maine Actions allege that the Company negligently misclassified and improperly packaged the petroleum crude oil. On the Company’s motion, the Maine Actions were dismissed. The plaintiffs appealed the dismissal decision to the U.S. First Circuit Court of Appeals, which dismissed the plaintiffs' appeal on June 2, 2021. The plaintiffs further petitioned the U.S. First Circuit Court of Appeals for a rehearing, which was denied on September 8, 2021. On January 24, 2022, the plaintiffs further appealed to the U.S. Supreme Court on two bankruptcy procedural grounds. On May 31, 2022, the U.S. Supreme Court denied the petition, thereby rejecting the plaintiffs' appeal.

(8)The trustee for the wrongful death trust commenced Carmack Amendment claims against the Company in North Dakota Federal Court, seeking to recover approximately U.S. $6 million for damaged rail cars and lost crude oil and reimbursement for the settlement paid by the consignor and the consignee under the Plans (alleged to be U.S. $110 million and U.S. $60 million, respectively). The Court issued an Order on August 6, 2020 granting and denying in parts the parties' summary judgment motions which has been reviewed and confirmed following motions by the parties for clarification and reconsideration. Final briefs of dispositive motions for summary judgment and for reconsideration on tariff applicability were submitted on September 30, 2022. On January 20, 2023, the Court granted in part the Company's summary judgment motion by dismissing all claims for recovery of settlement payments but leaving for trial the determination of the value of the lost crude oil. It also dismissed the Company's motion for reconsideration on tariff applicability. The remaining issues of the value of the lost crude oil and applicability of judgment reduction provisions do not require trial, and were fully briefed in 2024. On January 5, 2024, the Court issued its decision finding that the Company is liable for approximately U.S. $3.9 million plus pre-judgment interest, but declined to determine whether judgment reduction provisions were applicable, referring the parties to a court in Maine on that issue. On January 18, 2024, the Company filed a motion for reconsideration for the Court to apply the judgment reduction provisions. On January 19, 2024, the trustee for the wrongful death trust filed a Notice of Appeal for the January 5, 2024 decision, as well as prior decisions. On February 23, 2024, the Court denied the Company’s motion for reconsideration, again referring the parties to a court in Maine to apply the judgment reduction provision. On March 6, 2024, the Company filed its notice of appeal of this latest ruling, as well as prior decisions.

At this stage of the proceedings, any potential responsibility and the quantum of potential losses cannot be determined. Nevertheless, the Company denies liability and is vigorously defending these proceedings.

Court decision related to Remington Development Corporation legal claim

On October 20, 2022, the Court of King’s Bench of Alberta issued a decision in a claim brought by Remington Development Corporation (“Remington”) against the Company and the Province of Alberta (“Alberta”) with respect to an alleged breach of contract by the Company in relation to the sale of certain properties in Calgary. In its decision, the Court found the Company had breached its contract with Remington and Alberta had induced the contract breach. The Court found the Company and Alberta liable for damages of approximately $164 million plus interest and costs, and subject to an adjustment to the acquisition value of the property. In a further decision on August 30, 2023, the Court determined that adjustment and set the total damages at $165 million plus interest and costs. On October 20, 2023, the Court determined the costs payable to Remington, however, the Court has not provided any indication of how the damages, which are currently estimated to total approximately $225 million, should be apportioned between the Company and Alberta. On November 17, 2022, the Company filed an appeal of the Court’s decision. On April 11, 2024, the Court of Appeal of Alberta stayed the judgment pending the outcome of the appeal. On September 10, 2024, the Court of Appeal of Alberta heard the Company's appeal and reserved its decision. At this time, the Company cannot reasonably estimate the amount of damages for which it is liable under the ruling of the Court.
2014 Tax Assessment

On April 13, 2022, the SAT delivered an audit assessment of CPKCM’s 2014 tax returns (the "2014 Assessment"). As at September 30, 2024, the 2014 Assessment was Ps.6,247 million ($430 million), which included inflation, interest, and penalties. On July 7, 2022, CPKCM filed an administrative appeal (the “Administrative Appeal”) before the SAT, seeking to revoke the 2014 Assessment and claiming that the notification of the 2014 Assessment was not legal for being made through the tax mailbox in violation of a tax mailbox injunction previously granted on March 19, 2015, to CPKCM. On September 26, 2022, the SAT issued a resolution dismissing the Administrative Appeal filed by CPKCM arguing that it was not submitted timely (the “Administrative Appeal Resolution”).

On October 10, 2022, CPKCM submitted a petition of annulment lawsuit before the Federal Administrative Court, challenging the 2014 Assessment, its notification, and the dismissal of the Administrative Appeal Resolution. On January 5, 2023, the Administrative Court granted a definitive injunction against the enforcement and collection of the 2014 Tax Assessment.

On April 24, 2024, the Administrative Court resolved the annulment lawsuit confirming the Administrative Appeal Resolution and the 2014 Assessment (the "Administrative Court Resolution"). On June 21, 2024, CPKCM challenged the Administrative Court Resolution by submitting an Amparo petition (Demanda de Amparo) before the Collegiate Circuit Court (Tribunal Colegiado de Circuito). CPKCM expects to prevail based on the technical merits of its case.

On August 15, 2024, the Administrative Court informed CPKCM that the SAT submitted two motions (recurso de reclamación and recurso de queja) claiming that the Administrative Court did not cite the applicable legal provisions when granting the injunction against any tax collection action of the 2014 Tax Assessment. Because all the applicable requirements to grant the injunction have been satisfied by CPKCM and the surety bond has been approved and accepted by the SAT, it is not expected that the outcome of these motions will result in the enforcement and collection of the 2014 Assessment until the Amparo petition is resolved by the Collegiate Circuit Court.

Environmental liabilities

Environmental remediation accruals, recorded on an undiscounted basis unless a reliable, determinable estimate as to an amount and timing of costs can be established, cover site-specific remediation programs.

The accruals for environmental remediation represent the Company’s best estimate of its probable future obligation and include both asserted and unasserted claims, without reduction for anticipated recoveries from third parties. Although the recorded accruals include the Company’s best estimate of all probable costs, the Company’s total environmental remediation costs cannot be predicted with certainty. Accruals for environmental remediation may change from time to time as new information about previously untested sites becomes known, and as environmental laws and regulations evolve and advances are made in environmental remediation technology. The accruals may also vary as the courts decide legal proceedings against outside parties responsible for contamination. These potential charges, which cannot be quantified at this time, may materially affect income in the particular period in which a charge is recognized. Costs related to existing, but as yet unknown, or future contamination will be accrued in the period in which they become probable and reasonably estimable.

The expense included in “Purchased services and other” in the Company's Interim Consolidated Statements of Income for the three and nine months ended September 30, 2024 was $2 million and $6 million, respectively (three and nine months ended September 30, 2023 - $2 million and $6 million, respectively). Provisions for environmental remediation costs are recorded in the Company's Interim Consolidated Balance Sheets in “Other long-term liabilities”, except for the current portion, which is recorded in “Accounts payable and accrued liabilities”. The total amount provided as at September 30, 2024 was $249 million (December 31, 2023 - $220 million). Payments are expected to be made over 10 years through 2033.