Office Lease.  The future contractual lease payments for our office lease and the reconciliation to the office lease liability reflected in our consolidated balance sheet as of December 31, 2019 is presented in the table below (in thousands):

 

 

 

 

 

Year

    

Amount

2020

 

$

152

2021

 

 

235

2022

 

 

242

2023

 

 

249

2024

 

 

256

Thereafter

 

 

88

Total future contractual lease payments

 

 

1,222

Effect of discounting

 

 

(20)

Office lease liability

 

$

1,202

 

Tenant Improvement Allowances. As of December 31, 2019, we had approximately $92.1 million of commitments related to tenant improvement allowances, which generally may be requested by the tenants at any time up until a date that is near the expiration of the initial term of the applicable lease. This amount does not include approximately $53.8 million which may be canceled by certain tenants at their option.

Construction Funding. As of December 31, 2019, we had approximately $1.7 million, $3.3 million and $22.8 million of commitments relating to construction funding for the development of certain properties in Massachusetts, Ohio and Pennsylvania, respectively, which the tenant has agreed to use commercially reasonable efforts to complete by March 31, 2020, June 13, 2020 and February 9, 2021, respectively. These amounts do not include $4.0 million which may be canceled by PharmaCann pursuant to our lease at one of our Pennsylvania properties. Subsequent to the end of the year, in February 2020, this optional $4.0 million in construction funding was canceled in its entirety.

Environmental Matters. We follow the policy of monitoring our properties, both targeted acquisition and existing properties, for the presence of hazardous or toxic substances. While there can be no assurance that a material environmental liability does not exist, we are not currently aware of any environmental liabilities that would have a material adverse effect on our financial condition, results of operations and cash flow, or that we believe would require disclosure or the recording of a loss contingency.

Litigation. We may, from time to time, be a party to legal proceedings, which arise in the ordinary course of our business. We are not aware of any pending or threatened litigation that, if resolved against us, would have a material adverse effect on our consolidated financial position, results of operations or cash flows.