The following table details the components of operating lease income from leases in which the Company is the lessor ($ in thousands):
 Three Months Ended June 30,Six Months Ended June 30,
 2023202220232022
Fixed lease payments$1,826,835 $1,358,425 $3,694,361 $2,570,963 
Variable lease payments117,806 90,668 238,345 181,850 
Rental revenue$1,944,641 $1,449,093 $3,932,706 $2,752,813 
The following table details the fixed and variable components of the Company’s financing leases ($ in thousands):
 Three Months Ended June 30,Six Months Ended June 30,
 2023202220232022
Interest on lease liabilities$1,024 $997 $2,048 $1,993 
Amortization of right-of-use assets320 330 639 654 
Total financing lease costs$1,344 $1,327 $2,687 $2,647 
Schedule of Undiscounted Future Minimum Rental Income
The following table presents the undiscounted future minimum rents the Company expects to receive for its industrial, net lease, data centers, retail, and office properties as of June 30, 2023 ($ in thousands). Leases at the Company’s rental housing and self storage properties are short term, generally 12 months or less, and are therefore not included.
YearFuture Minimum Rents
2023 (remaining)$909,480 
20241,779,384 
20251,651,722 
20261,500,612 
20271,288,147 
20281,075,149 
Thereafter15,783,417 
Total$23,987,911 
Schedule of Future Lease Payments Due Under Ground Leases
The following table details the future lease payments due under the Company’s ground leases as of June 30, 2023 ($ in thousands):
 Operating
Leases
Financing
Leases
2023 (remaining)$20,437 $2,102 
202437,073 4,266 
202537,690 4,385 
202637,855 4,507 
202738,253 4,633 
202838,605 4,763 
Thereafter2,574,603 559,374 
Total undiscounted future lease payments2,784,516 584,030 
Difference between undiscounted cash flows and discounted cash flows(2,141,188)(506,384)
Total lease liability$643,328 $77,646 
Summary of Fixed and Variable Components of Operating and Financing Leases
The following table details the fixed and variable components of the Company’s operating leases ($ in thousands):
 Three Months Ended June 30,Six Months Ended June 30,
 2023202220232022
Fixed ground rent expense$3,820 $2,264 $7,848 $4,533 
Variable ground rent expense6,831 12,825 10 
Total cash portion of ground rent expense10,651 2,269 20,673 4,543 
Straight-line ground rent expense5,520 3,217 10,923 6,070 
Total operating lease costs$16,171 $5,486 $31,596 $10,613