XML 104 R87.htm IDEA: XBRL DOCUMENT v3.21.1
Environment (Tables)
12 Months Ended
Dec. 31, 2020
ENVIRONMENT  
Summary of Environmental Expenses

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12-31-2020

12-31-2019

Disbursing Company

Project Name

Environmental Description

Project status [Finished, in progress]

Disbursement amount

Capitalized amount

Expense amount

Future disbursement amount

Estimated date of future disbursement

Total disbursements

Amount of prior period disbursement

Pehuenche

PEHUENCHE CENTRAL

Waste Management

In progress

13,128

 —

13,128

19,298

12-31-2021

32,426

3,165

 

 

Environmental Sanitation

In progress

3,528

 —

3,528

5,334

12-31-2021

8,862

1,988

 

 

Materials Environment

In progress

4,993

 —

4,993

24,720

12-31-2021

29,713

9,061

 

 

Campaigns and Studies

In progress

4,235

 —

4,235

6,180

12-31-2021

10,415

 —

Enel Distribución Chile S.A.

VEGETATION CONTROL IN AT NETWORKS

It consists of cutting branches until reaching the safety conditions that the foliage must be left with respect to the drivers.

Completed

305,701

 —

305,701

 —

12-31-2020

305,701

2,600

 

 

This activity contemplates the maintenance of the band of easement of high voltage lines between 34,5 y 500kv.

Completed

303,873

 —

303,873

 —

12-31-2020

303,873

67,291

 

VEGETATION CONTROL IN MT/BT

Pruning of trees near the media network and low voltage.

Completed

3,296,066

 —

3,296,066

 —

12-31-2020

3,296,066

3,507,502

 

IMPROVEMENTS IN THE MT NETWORK

Replacement underground transformers by Technical Standard (PCB)

Completed

91,353

91,353

 —

 —

12-31-2020

91,353

170,077

 

REPLACE TRAFOS TRIFAS  MEJ QUALITY BT

This project corresponds to:
- replacement of traditional network by Calpe BT
- replacement of concentrical network by Calpe BT
- replacement of transformers with loadability problems

Completed

3,649,294

3,649,294

 —

 —

12-31-2020

3,649,294

1,168,343

 

ENVIRONMENTAL MANAGEMENT IN SSEE

The service consists of the maintenance of green areas with replacement of species and grass in Enel substation enclosures.
Maintenance tree planting of SSEE and removal of weeds, debris and garbage, exterior perimeter.
The withdrawal and transfer was carried out.

Completed

340,704

 —

340,704

 —

12-31-2020

340,704

64,737

 

RESPEL MANAGEMENT

Hazardous waste removal and treatment management

Completed

19,122

 —

19,122

 —

12-31-2020

19,122

103,847

 

SEC STANDARDIZATION PROJECT (CAPEX)

Maintenance of trees, SSEE and removal of weeds, debris and garbage, exterior perimeter.

Completed

1,774,155

1,774,155

 —

 —

12-31-2020

1,774,155

 

 

ENVIRONMENTAL MANAGEMENT

Environmental Management of Reforestation in the Metropolitan Park.

Completed

1,374

 —

1,374

 —

12-31-2020

1,374

2,337

 

OIL ANALYSIS AT POWER TD (OPEX)

The waste material was removed and transferred to a dump from a Substation.

Completed

32,096

 —

32,096

 —

12-31-2020

32,096

 —

Enel Generación Chile S.A.

ENVIRONMENTAL EXPENSES CC.CC.

The main expenses incurred are: Operation and maintenance, monitoring air quality and meteorological stations, Environmental audit monitoring network once a year, Annual CEMS Validation, Biomass Protocol Service, Environmental Materials (magazine, books), Isokinetic Measurements, SGI Works (NC objective, inspections, audits and supervision) ISO 14001, OHSAS certification, CEMS operation and maintenance service.

In progress

595,987

95,976

500,011

599,144

12-31-2021

1,195,131

2,307,825

 

ENVIRONMENTAL EXPENSES CC.TT.

Studies, monitoring, laboratory analysis, removal and final disposal of solid waste in thermoelectric plants (C.T.)

In progress

2,048,635

158,028

1,890,607

1,520,333

12-31-2021

3,568,968

7,151,486

 

ENVIRONMENTAL EXPENSES CC.HH.

Studies, monitoring, laboratory analysis, removal and final disposal of solid waste in hydroelectric plants (C.H.)

In progress

263,737

 —

263,737

 —

12-31-2020

263,737

759,980

Enel Green Power Chile S.A.

Waste management

Contracts for the removal of hazardous and non-hazardous waste, and removal of household waste.

In progress

84,113

 —

84,113

148,447

12-31-2021

232,560

33,841

 

Environmental Sanitation

Contracts for vector control, deratization, disinsection.

In progress

46,957

 —

46,957

104,448

12-31-2021

151,405

36,175

 

Water Analysis

Monitoring and analysis of drinking water and sewage

In progress

 —

 —

35,266

44,588

12-31-2021

 —

 —

 

Rent/Vehicle Expenses

Vehicle rental for environmental trips (field visits / Plants)

In progress

51,716

 —

51,716

66,741

12-31-2021

118,457

 —

 

Campaigns and Studies

Contracts for Environmental Monitoring (Collision of Birds- Flora and Fauna- Archeology, others)

In progress

189,321

 —

189,321

355,550

12-31-2021

544,871

147,392

 

Technical Counterpart Environmental Studies

Technical Counterpart Environmental Studies

In progress

 —

 —

 —

5,287

12-31-2021

5,287

 —

 

Environmental Materials

Buy environmental materials (containers, spill kit, others)

In progress

32,032

 —

32,032

40,578

12-31-2021

72,610

4,822

 

Sewage Treatment Plant

Contract for removal and cleaning of pits and sewage

In progress

8,066

 —

8,066

31,591

12-31-2021

39,657

17,629

 

Outsourced Services

Other services (contracts with third parties)

In progress

222,291

 —

222,291

297,167

12-31-2021

519,458

53,970

 

Travel Environment

Tickets - accommodation and viatics for site visit in facilities

In progress

56,820

 —

56,820

85,150

12-31-2021

140,368

 —

Geotérmica del Norte S.A.

Waste management

Contracts for the removal of hazardous and non-hazardous waste, and removal of household waste.

In progress

21,992

 —

21,992

32,918

12-31-2021

54,910

 —

 

Environmental Sanitation

Contracts for vector control, deratization, disinsection.

In progress

6,500

 —

6,500

14,319

12-31-2021

20,819

 —

 

Campaigns and Studies

Contracts for Environmental Monitoring (Collision of Birds- Flora and Fauna- Archeology, others)

In progress

313,280

 —

313,280

339,170

12-31-2021

652,450

 —

 

Environmental Materials

Buy environmental materials (containers, spill kit, others)

In progress

91

 —

91

3,559

12-31-2021

3,650

 —

 

Sewage Treatment Plant

Contract for removal and cleaning of pits and sewage

In progress

4,816

 —

4,816

1,324

12-31-2021

6,140

 —

Parque Eólico Talinay Oriente S.A.

Waste management

Contracts for the removal of hazardous and non-hazardous waste, and removal of household waste.

In progress

13,064

 —

13,064

18,580

12-31-2021

31,644

11,865

 

Environmental Sanitation

Contracts for vector control, deratization, disinsection.

In progress

6,939

 —

6,939

4,109

12-31-2021

11,048

 —

 

Campaigns and Studies

Contracts for Environmental Monitoring (Collision of Birds- Flora and Fauna- Archeology, others)

In progress

76,595

 —

76,595

 —

12-31-2021

76,595

63,666

 

Sewage Treatment Plant

Contract for removal and cleaning of pits and sewage

In progress

2,087

 —

2,087

 —

12-31-2021

2,087

1,738

Almeyda Solar SpA

Waste management

Contracts for the removal of hazardous and non-hazardous waste, and removal of household waste.

In progress

39,521

 —

39,521

31,508

12-31-2021

71,029

37,904

 

Environmental Sanitation

Contracts for vector control, deratization, disinsection.

In progress

33,992

 —

33,992

36,542

12-31-2021

70,534

33,467

 

Water Analysis

Monitoring and analysis of drinking water and sewage

In progress

 —

 —

 —

24,435

12-31-2020

24,435

 —

 

Campaigns and Studies

Contracts for Environmental Monitoring (Collision of Birds- Flora and Fauna- Archeology, others)

In progress

63,736

 —

63,736

64,160

12-31-2021

127,896

121,506

 

Environmental Materials

Buy environmental materials (containers, spill kit, others)

In progress

16,663

 —

16,663

28,702

12-31-2021

45,365

394

 

Sewage Treatment Plant

Contract for removal and cleaning of pits and sewage

In progress

8,149

 —

8,149

12,795

12-31-2021

20,944

17,419

 

 

Total

 

14,046,722

5,768,806

8,313,182

3,966,677

 

17,967,209

15,902,027

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12-31-2019

Disbursing Company

Project Name

Environmental Description

Project status [Finished, in progress]

Disbursement amount

Capitalized amount

Expense amount

Future disbursement amount

Estimated date of future disbursement

Total disbursements

Pehuenche

PEHUENCHE CENTRAL

Waste Management

In progress

3,165

 -

3,165

 -

 -

3,165

 

 

Environmental Sanitation

In progress

1,988

 -

1,988

 -

 -

1,988

 

CURILLINQUE CENTRAL

Campaigns and Studies

In progress

9,061

 -

9,061

 -

 -

9,061

 

 

Environmental Sanitation

In progress

882

 -

882

 -

 -

882

 

LOMA ALTA CENTRAL

Environmental Sanitation

In progress

882

 -

882

 -

 -

882

Enel Distribución Chile S.A.

CHANGE OF TRAD X CALPE NETWORK

Concentrical network replacement by Calpe (Pre-assembled aluminum cable) BT

In progress

1,476,780

1,476,780

 -

 -

12-31-2019

1,476,780

 

VEGETATION CONTROL IN AT NETWORKS

It consists of cutting branches until reaching the safety conditions that the foliage must be left with respect to the drivers.

Completed

2,600

 -

2,600

 -

12-31-2019

2,600

 

 

This activity contemplates the maintenance of the band of easement of high voltage lines between 34,5 y 500kv.

Completed

67,291

 -

67,291

 -

12-31-2019

67,291

 

VEGETATION CONTROL IN MT/BT

Pruning of trees near the media network and low voltage.

Completed

3,507,502

 -

3,507,502

 -

12-31-2019

3,507,502

 

 

The service consists of the maintenance of green areas with replacement of species and grass in Enel substation enclosures.
Maintenance tree planting of SSEE and removal of weeds, debris and garbage, exterior perimeter.

Completed

64,737

 -

64,737

 -

12-31-2019

64,737

 

ENVIRONMENTAL MANAGEMENT IN SSEE

The service consists of weeding and weed control in electrical power substation enclosures in order to keep the enclosures free of weeds, ensuring a good operation of these facilities.

Completed

19,706

 -

19,706

 -

12-31-2019

19,706

 

 

The removal and transfer to waste dump from a Substation was carried out.

Completed

21,719

 -

21,719

 -

12-31-2019

21,719

 

MANEJO AMBIENTAL

Environmental Management of Reforestation in Metropolitan Park.

Completed

2,337

 -

2,337

 -

12-31-2019

2,337

 

MEJORAS EN LA RED MT

Replacement of MT network with protected cable

In progress

170,077

170,077

 -

 -

12-31-2019

170,077

 

GESTIÓN DE RESPEL

Hazardous waste removal and treatment management

Completed

103,847

 

103,847

 -

12-31-2019

103,847

 

REPLACE TRIFAS TRIFAS MEJ QUALITY BT

Replacement of transformers with chargeability problems

In progress

1,168,343

1,168,343

 -

 -

12-31-2019

1,168,343

 

REPLACEMENT TD DAE CONCENTRICA X TD. TRIF. RED CALPE

Concentrical network replacement by Calpe (Pre-assembled aluminum cable) BT

In progress

492,260

492,260

 -

 -

12-31-2019

492,260

Enel Generación Chile S.A.

ENVIRONMENTAL MONITORING

Environmental Monitoring Contract with SK Ecology, operation and maintenance CEMS.

In progress

576,519

 -

576,519

 -

 -

576,519

 

CEMS STANDARDIZATION

Warehouse standardization, environmental management, regularization of environmental impact assessment (EIA)

In progress

207,966

207,966

 -

 -

 -

207,966

 

HYDRAULIC CENTRALS

Waste management and sanitation

In progress

2,315

 -

2,315

 -

 -

2,315

 

ENVIRONMENTAL EXPENSES CC.CC.

The main expenses incurred are: Bocamina U1-2: Operation and maintenance, monitoring air quality and meteorological stations, Environmental audit monitoring network once a year, CEMS Annual Validation, Biomass Protocol Service, Environmental Materials (magazine, books), Measurements Isokineticas, Trabajos SGI (NC objective, inspections, audits and supervision) ISO 14001, OHSAS certification, CEMS operation and maintenance service.

In progress

1,452,158

855,667

596,491

855,667

12-31-2020

2,307,825

 

ENVIRONMENTAL EXPENSES CC.TT.

Studies, monitoring, laboratory analysis, removal and final disposal of solid waste in thermoelectric plants (C.T.)

In progress

5,387,657

1,763,829

3,623,828

1,763,829

12-31-2020

7,151,486

 

ENVIRONMENTAL EXPENSES CC.HH.

Studies, monitoring, laboratory analysis, removal and final disposal of solid waste in hydroelectric plants (C.H.)

In progress

339,103

 -

339,103

420,877

12-31-2020

759,980

 

CENTRAL QUINTERO

CEMS Central Quinteros

In progress

458,001

110,923

347,078

37,983

12-31-2020

495,984

Enel Green Power del Sur Spa.

Carrera Pinto

Waste Management

Completed

4,432

 -

4,432

 -

 -

4,432

 

 

Environmental Sanitation

Completed

6,466

 -

6,466

 -

 -

6,466

 

 

Wastewater Treatment Plant

Completed

4,436

 -

4,436

 -

 -

4,436

 

Finis Terrae

Waste Management

Completed

10,954

 -

10,954

 -

 -

10,954

 

 

Environmental Sanitation

Completed

7,674

 -

7,674

 -

 -

7,674

 

 

Wastewater Treatment Plant

Completed

2,154

 -

2,154

 -

 -

2,154

 

La Silla

Environmental Sanitation

Completed

2,902

 -

2,902

 -

 -

2,902

 

Los Buenos Aires

Waste Management

Completed

1,509

 -

1,509

 -

 -

1,509

 

 

Campaigns and Studies

Completed

20,613

 -

20,613

 -

 -

20,613

 

 

Environmental Sanitation

Completed

3,989

 -

3,989

 -

 -

3,989

 

 

Wastewater Treatment Plant

Completed

882

 -

882

 -

 -

882

 

 

Materials Environment

Completed

5,589

 -

5,589

 -

 -

5,589

 

Pampa Norte

Waste Management

Completed

5,098

 -

5,098

 -

 -

5,098

 

 

Environmental Sanitation

Completed

6,618

 -

6,618

 -

 -

6,618

 

 

Wastewater Treatment Plant

Completed

3,459

 -

3,459

 -

 -

3,459

 

Renaico

Waste Management

Completed

2,281

 -

2,281

 -

 -

2,281

 

 

Campaigns and Studies

Completed

83,820

 -

83,820

 -

 -

83,820

 

 

Environmental Sanitation

Completed

5,226

 -

5,226

 -

 -

5,226

 

 

Wastewater Treatment Plant

Completed

982

 -

982

 -

 -

982

 

 

Materials Environment

Completed

4,822

 -

4,822

 -

 -

4,822

 

 

Outsourced Services

Completed

53,970

 -

53,970

 -

 -

53,970

 

Sierra Gorda

Waste Management

Completed

13,999

 -

13,999

 -

 -

13,999

 

 

Campaigns and Studies

Completed

42,959

 -

42,959

 -

 -

42,959

 

 

Environmental Sanitation

Completed

3,300

 -

3,300

 -

 -

3,300

 

 

Wastewater Treatment Plant

Completed

127

 -

127

 -

 -

127

Empresa Electrica Panguipulli S.A.

Chañares

Waste Management

Completed

1,613

 -

1,613

 -

 -

1,613

 

 

Campaigns and Studies

Completed

7,981

 -

7,981

 -

 -

7,981

 

 

Environmental Sanitation

Completed

5,262

 -

5,262

 -

 -

5,262

 

 

Wastewater Treatment Plant

Completed

5,591

 -

5,591

 -

 -

5,591

 

Lalackama

Waste Management

Completed

1,678

 -

1,678

 -

 -

1,678

 

 

Environmental Sanitation

Completed

7,091

 -

7,091

 -

 -

7,091

 

 

Wastewater Treatment Plant

Completed

3,273

 -

3,273

 -

 -

3,273

 

Pilmaiquen

Waste Management

Completed

1,450

 -

1,450

 -

 -

1,450

 

 

Environmental Sanitation

Completed

6,822

 -

6,822

 -

 -

6,822

 

Pullinque

Waste Management

Completed

785

 -

785

 -

 -

785

 

 

Campaigns and Studies

Completed

2,627

 -

2,627

 -

 -

2,627

 

 

Environmental Sanitation

Completed

4,129

 -

4,129

 -

 -

4,129

 

 

Materials Environment

Completed

394

 -

394

 -

 -

394

 

Talinay Poniente

Campaigns and Studies

Completed

46,026

 -

46,026

 -

 -

46,026

Parque Eolico Tal Tal S.A.

Taltal

Waste Management

Completed

10,745

 -

10,745

 -

 -

10,745

 

 

Campaigns and Studies

Completed

44,656

 -

44,656

 -

 -

44,656

 

 

Environmental Sanitation

Completed

2,476

 -

2,476

 -

 -

2,476

 

 

Wastewater Treatment Plant

Completed

2,515

 -

2,515

 -

 -

2,515

Parque Eolico Valle De Los Vientos S.A.

Valle de los Vientos

Waste Management

Completed

11,546

 -

11,546

 -

 -

11,546

 

 

Campaigns and Studies

Completed

20,216

 -

20,216

 -

 -

20,216

 

 

Environmental Sanitation

Completed

2,471

 -

2,471

 -

 -

2,471

Parque Eolico Talinay Oriente S.A.

Talinay Oriente

Waste Management

Completed

11,865

 -

11,865

 -

 -

11,865

 

 

Campaigns and Studies

Completed

63,666

 -

63,666

 -

 -

63,666

 

 

Environmental Sanitation

Completed

9,419

 -

9,419

 -

 -

9,419

 

 

Wastewater Treatment Plant

Completed

1,738

 -

1,738

 -

 -

1,738

Almeyda Solar Spa

Diego de Almagro

Waste Management

Completed

10,087

 -

10,087

 -

 -

10,087

 

 

Environmental Sanitation

Completed

5,216

 -

5,216

 -

 -

5,216

 

 

Wastewater Treatment Plant

Completed

6,040

 -

6,040

 -

 -

6,040

Total

16,132,535
6,245,845
9,886,690
3,078,356

 

19,210,891

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12-31-2018

Disbursing Company

Project Name

Environmental Description

Project status [Finished, in progress]

Disbursement amount

Capitalized amount

Expense amount

Future disbursement amount

Estimated date of future disbursement

Total disbursements

Pehuenche

ENVIRONMENTAL EXPENSES HYDROELECTRIC POWER PLANTS

C.H. Pehuenche E E Pehuenche S.A. Supply of flow measurement equipment.
.

In progress

48,574

48,574

 -

 -

 

48,574

 

 

Studies, monitoring, laboratory analysis, removal and final disposal of solid waste in thermoelectric plants (C.T.)

In progress

62,560

 -

62,560

 -

 -

62,560

Enel Distribución Chile S.A.

VEGETATION CONTROL IN AT NETWORKS

It consists of cutting branches until reaching the safety conditions that the foliage must be left with respect to the drivers.

In progress

134,394

 -

134,394

19,654

12-31-2018

154,048

 

 

Tree pruning near the medium voltage network.

In progress

5,790,042

2,472,768

3,317,274

502,599

03-31-2019

6,292,641

 

RESPEL MANAGEMENT

Hazardous waste management.

Completed

1,780

 -

1,780

 -

06-30-2018

1,780

 

ENVIRONMENTAL MANAGEMENT IN SSEE

The service consists of the maintenance of green areas with replacement of species and grass in Enel substation enclosures.

Completed

15,383

 -

15,383

36,633

12-31-2018

52,016

 

 

The service consists of weeding and weed control in electrical power substation enclosures in order to keep the enclosures free of weeds, ensuring a good operation of these facilities.

En proceso

46,339

 -

46,339

568

03-31-2018

46,907

 

ENVIRONMENTAL PERMITS

Environmental Impact Statement: 1) New Lampa Sectioning Substation and 2) Ochagavia - Florida Line, Sanjon La Aguada section.

In progress

1,767

1,767

 -

5,203

03-31-2019

6,970

 

VEGETATION CONTROL IN MT / BT NETWORKS

Improvement in the traditional network by calpe (pre-assembled aluminum cable)

In progress

19,416

19,416

 -

373,059

03-31-2019

392,475

 

IMPROVEMENTS IN THE MT NETWORK

Replacement of MT bare network by shielded cable

In progress

158,086

158,086

 -

18,056

03-31-2019

176,142

 

CHANGE OF NETWORK TRAD X CALPE

Replacement of traditional network by Calpe (Pre-assembled aluminum cable) BT

In progress

851,792

851,792

 -

530,712

03-31-2019

1,382,504

 

REPLACEMENT TD DAE CONCENTRICA X TD. TRIF. RED CALPE

Concentrical network replacement by Calpe (Pre-assembled aluminum cable) BT

In progress

712,455

712,455

 -

295,961

03-31-2019

1,008,416

 

REPLACEMENT OF TRAFOS TRIFAS QUALITY BT

Replacement of transformers with chargeability problems

In progress

1,288,155

1,288,155

 -

1,353,909

03-31-2019

2,642,064

 

ENVIRONMENTAL MANAGEMENT

Environmental Management of Reforestation in Cerro Chena and Metropolitan Park.

In progress

5,831

 -

5,831

803

03-31-2019

6,634

 

Asbestos removal from underground cables

Removal of asbestos flame retardant tape from the MT underground network.

In progress

265,577
146,300

119,277

118,337

03-31-2019

383,914

Enel Generación Chile S.A.

ENVIRONMENTAL MONITORING

Environmental Monitoring Contract with SK Ecology, operation and maintenance CEMS

In progress

797,543

 -

797,543

 -

 -

797,543

 

CEMS STANDARDIZATION

Winery standardization, environmental management, environmental impact assessment regularization (EIA)

In progress

645,302

645,302

 -

 -

 -

645,302

 

HYDRAULIC CENTRALS

Waste Management e higienización

In progress

11,567

 -

11,567

 -

 -

11,567

 

ENVIRONMENTAL EXPENSES CC.TT.

The main expenses incurred are: Bocamina U1-2: Operation and maintenance, monitoring air quality and meteorological stations, Environmental audit monitoring network once a year, CEMS Annual Validation, Biomass Protocol Service, Environmental Materials (magazine, books), Measurements Isokineticas, Trabajos SGI (NC objective, inspections, audits and supervision) ISO 14001, OHSAS certification, CEMS operation and maintenance service.

In progress

2,102,056

 -

2,102,056

 -

 -

2,102,056

 

 

Studies, monitoring, laboratory analysis, removal and final disposal of solid waste in thermoelectric plants (C.T.)

In progress

2,867,523

 -

2,867,523

 -

 -

2,867,523

 

ENVIRONMENTAL EXPENSES CC.HH.

Studies, monitoring, laboratory analysis, removal and final disposal of solid waste in hydroelectric plants (C.H.)

In progress

183,156

 -

183,156

 -

 -

183,156

 

C.H. RALCO

Ralco Plan: Reforestation according to an agreement with the Universidad Católica and electrification of homes in Ayin Maipú.

In progress

4,542,216

4,542,216

 -

 -

 -

4,542,216

 

CENTRAL QUINTERO

CEMS Central Quinteros

In progress

417,194

417,194

 -

 -

 -

417,194

Total

20,968,708
11,304,025
9,664,683
3,255,494

 