XML 31 R16.htm IDEA: XBRL DOCUMENT v3.10.0.1
Commitments and Contingencies
12 Months Ended
Dec. 31, 2018
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Commitments and Contingencies
Included below is a discussion of various future commitments of the Partnership as of December 31, 2018. The commitments under these arrangements are not recorded in the accompanying Consolidated Balance Sheets. The amounts disclosed represent undiscounted cash flows on a gross basis and no inflation elements have been applied.
Operating lease. The Partnership has leases for certain machinery and equipment used in its operations, which it accounts for as operating leases in accordance with GAAP. For the years ended December 31, 2018 and 2017, the Partnership incurred rental expenses related to its operating lease agreements of $5.9 million and $1.8 million, respectively. No rental expenses were incurred related to operating lease agreements for the year ended December 31, 2016.
Future minimum rental payments at December 31, 2018 are as follows:
 
 
(In thousands)
2019
 
$
736

2020
 
—

2021
 
—

2022
 
—

2023
 
—

Thereafter
 
—

Total
 
$
736


Volume commitment agreements. As of December 31, 2018, the Partnership had certain agreements with an aggregate requirement to either deliver or purchase a minimum quantity of approximately 15.1 million barrels of water, prior to any applicable volume credits, within specified timeframes, all of which are ten years or less. For the years ended December 31, 2018, 2017 and 2016, purchase costs incurred related to these agreements were $4.7 million, $2.1 million and $6.7 million, respectively.
The estimable future commitments under these volume commitment agreements at December 31, 2018 are as follows:
 
 
(In thousands)
2019
 
$
2,948

2020
 
2,481

2021
 
2,663

2022
 
402

2023
 
—

Thereafter
 
1,654

Total
 
$
10,148


Subsequent to December 31, 2018, the Partnership entered into new agreements to deliver, transport, or purchase additional volumes of 9.0 million barrels of produced water within specified timeframes, all of which are ten years or less. The estimable future commitments under these volume commitment agreements were approximately $5.2 million.
Litigation. The Partnership is party to various legal and/or regulatory proceedings from time to time arising in the ordinary course of business. When the Partnership determines that a loss is probable of occurring and is reasonably estimable, the Partnership accrues an undiscounted liability for such contingencies based on its best estimate using information available at the time. The Partnership discloses contingencies where an adverse outcome may be material, or where in the judgment of management, the matter should otherwise be disclosed.
Mirada litigation. On March 23, 2017, Mirada filed a lawsuit against Oasis Petroleum, OPNA, and OMS, seeking monetary damages in excess of $100.0 million, declaratory relief, attorneys’ fees and costs (Mirada Energy, LLC, et al. v. Oasis Petroleum North America LLC, et al.; in the 334th Judicial District Court of Harris County, Texas; Case Number 2017-19911). In its original lawsuit, Mirada asserts that it is a working interest owner in certain acreage owned and operated by Oasis Petroleum in Wild Basin. Specifically, Mirada asserts that Oasis Petroleum has breached certain agreements by: (1) failing to allow Mirada to participate in Oasis Petroleum’s midstream operations in Wild Basin; (2) refusing to provide Mirada with information that Mirada contends is required under certain agreements and failing to provide information in a timely fashion; (3) failing to consult with Mirada and failing to obtain Mirada’s consent prior to drilling more than one well at a time in Wild Basin; and (4) overstating the estimated costs of proposed well operations in Wild Basin. Mirada seeks a declaratory judgment that OPNA be removed as operator in Wild Basin at Mirada’s election and that Mirada be allowed to elect a new operator; that certain agreements apply to Oasis Petroleum and Mirada and Wild Basin with respect to this dispute; that Oasis Petroleum be required to provide all information within its possession regarding proposed or ongoing operations in Wild Basin; and that OPNA not be permitted to drill, or propose to drill, more than one well at a time in Wild Basin without obtaining Mirada’s consent. Mirada also seeks a declaratory judgment with respect to Oasis Petroleum’s current midstream operations in Wild Basin. Specifically, Mirada seeks a declaratory judgment that Mirada has a right to participate in Oasis Petroleum’s Wild Basin midstream operations, consisting of produced and flowback water disposal, crude oil gathering and gas gathering and processing; that, upon Mirada’s election to participate, Mirada is obligated to pay its proportionate costs of Oasis Petroleum’s midstream operations in Wild Basin; and that Mirada would then be entitled to receive a share of revenues from the midstream operations and would not be charged any amount for its use of these facilities for production from the “Contract Area.”
On June 30, 2017, Mirada amended its original petition to add a claim that Oasis Petroleum has breached certain agreements by charging Mirada for midstream services provided by its affiliates and to seek a declaratory judgment that Mirada is entitled to be paid its share of total proceeds from the sale of hydrocarbons received by OPNA or any affiliate of OPNA without deductions for midstream services provided by OPNA or its affiliates.
On February 2, 2018 and February 16, 2018, Mirada filed a second and third amended petition, respectively. In these filings, Mirada alleged new legal theories for being entitled to enforce the underlying contracts, and added Bighorn DevCo LLC, Bobcat DevCo LLC and Beartooth DevCo LLC as defendants, asserting that these entities were created in bad faith in an effort to avoid contractual obligations owed to Mirada. Mirada may further amend its petition from time to time to assert additional claims as well as defendants.
On March 2, 2018, Mirada filed a fourth amended petition that described Mirada’s alleged ownership and assignment of interests in assets purportedly governed by agreements at issue in the lawsuit.  On August 31, 2018, Mirada filed a fifth amended petition that added the Partnership as a defendant, asserting that it was created in bad faith in an effort to avoid contractual obligations owed to Mirada.
Oasis Petroleum believes that Mirada’s claims are without merit, that Oasis Petroleum has complied with its obligations under the applicable agreements and that some of Mirada’s claims are grounded in agreements which do not apply to Oasis Petroleum. Oasis Petroleum filed answers denying all of Mirada’s claims and intends to continue to vigorously defend against Mirada’s claims. The Partnership has not yet filed an answer because it has not yet been served with process. Discovery is ongoing, and each of the parties has made a number of procedural filings and motions, and additional filings and motions can be expected over the course of the claim. Trial was previously scheduled for May 2019, but, in connection with a request by the parties to continue the trial until a later date, the trial is now scheduled for February 2020. Neither we nor Oasis Petroleum can predict or guarantee the ultimate outcome or resolution of such matter. If such matter were to be determined adversely to our or Oasis Petroleum’s interests, or if we or Oasis Petroleum were forced to settle such matter for a significant amount, such resolution or settlement could have a material adverse effect on our business, results of operations, financial condition and cash flows. Such an adverse determination could materially impact Oasis Petroleum’s ability to operate its properties in Wild Basin or develop its identified drilling locations in Wild Basin on its current development schedule. A determination that Mirada has a right to participate in Oasis Petroleum’s midstream operations could materially reduce the interests of Oasis Petroleum and us in our current assets and future midstream opportunities and related revenues in Wild Basin. Under the Omnibus Agreement the Partnership entered into with Oasis Petroleum in connection with the closing of the initial public offering, Oasis Petroleum agreed to indemnify the Partnership for any losses resulting from this litigation. However, the Partnership cannot guarantee that such indemnity will fully protect the Partnership from the adverse consequences of any adverse ruling.