Schedule of Lease Cost
The components of lease costs and other information related to leases were as follows (in thousands):

Fiscal Year Ended January 31,
202420232022
Operating lease costs$52,892 $46,240 $35,745 
Variable lease costs11,667 7,906 6,029 
Sublease income(11,943)(12,782)(12,722)
Total lease costs$52,616 $41,364 $29,052 

Supplemental cash flow information and non-cash activity related to the Company’s operating leases were as follows (in thousands):

Fiscal Year Ended January 31,
202420232022
Cash payments (receipts) included in the measurement of operating lease liabilities—operating cash flows
$40,498 $42,342 $38,249 
Operating lease liabilities arising from obtaining right-of-use assets$56,037 $72,158 $28,314 

Weighted-average remaining lease term and discount rate for the Company’s operating leases were as follows:

January 31, 2024January 31, 2023
Weighted-average remaining lease term (years)
7.58.2
Weighted-average discount rate
6.1 %6.5 %
Schedule of Operating Leases and Subleases
The total remaining lease payments under non-cancelable operating leases and lease receipts for subleases as of January 31, 2024 were as follows (in thousands):

Operating Leases
Subleases
Total
Fiscal Year Ending January 31,
2025$46,530 $(7,709)$38,821 
202647,944 (5,774)42,170 
202746,651 (5,960)40,691 
202845,132 (6,153)38,979 
202943,001 (6,351)36,650 
Thereafter136,207 (3,235)132,972 
Total lease payments (receipts)
$365,465 $(35,182)$330,283 
Less: imputed interest(77,484)
Present value of operating lease liabilities$287,981 
Schedule of Other Contractual Commitments
Future minimum payments under the Company’s non-cancelable purchase commitments with a remaining term in excess of one year as of January 31, 2024 are presented in the table below (in thousands):

Amount
Fiscal Year Ending January 31,
2025$498,704 
2026528,063 
2027563,994 
2028656,162 
20291,176,725 (1)(2)
Thereafter
Total$3,423,648 
________________
(1)Includes $929.5 million of remaining non-cancelable contractual commitments as of January 31, 2024 related to one of the Company’s third-party cloud infrastructure agreements, under which the Company committed to spend an aggregate of at least $1.0 billion between June 2023 and May 2028 with no minimum purchase commitment during any year. The Company is required to pay the difference if it fails to meet the minimum purchase commitment by May 2028 and such payment can be applied to qualifying expenditures for cloud infrastructure services for up to twelve months after May 2028.
(2)Also includes $247.2 million of remaining non-cancelable contractual commitments as of January 31, 2024 related to another one of the Company’s third-party cloud infrastructure agreements, under which the Company committed to spend an aggregate of at least $250.0 million between January 2024 and December 2028 with no minimum purchase commitment during any year. The Company is required to pay the difference if it fails to meet the minimum purchase commitment by December 2028.