XML 27 R12.htm IDEA: XBRL DOCUMENT v3.6.0.2
Percentage of Completion Contracts
12 Months Ended
Dec. 31, 2016
Contractors [Abstract]  
Percentage of Completion Contracts
Percentage-of-Completion Contracts

During 2016, we were break-even for our Zubair contract and cumulative estimated loss from the Iraq contracts was $532 million as of December 31, 2016. On May 26, 2016, we entered into an agreement with our customer containing the terms and conditions of the settlement on the Zubair contract. The settlement to be paid to us is a gross amount of $150 million, of which $62 million and $72 million was received in the second and third quarters of 2016, respectively. The settlement includes variation order requests, claims for extension of time, payments of remaining contract milestones and new project completion timelines that resulted in relief from the liquidated damages provisions. Of the remaining gross settlement, we collected $16 million during January 2017.

As of December 31, 2016, we have no claims revenue, and our percentage-of-completion project estimate includes a cumulative $25 million in approved change orders and $16 million of back charges. Our net billings in excess of costs as of December 31, 2016 were $45 million and are shown in the “Other Current Liabilities” on the Consolidated Balance Sheet. The amounts associated with contract change orders or claims are included in revenue only when they can be reliably estimated and their realization is reasonably assured.

During 2015, we recognized estimated project losses of $153 million related to our long-term early production facility construction contracts in Iraq accounted for under the percentage-of-completion method. Total estimated losses on these loss projects were $532 million at December 31, 2015. As of December 31, 2015, our percentage-of-completion project estimates include $116 million of claims revenue and $28 million of back charges. During 2015, an additional $32 million of claims revenue was included in our project estimates. Our costs in excess of billings as of December 31, 2015 were $6 million and are shown in the “Other Current Assets” on our Consolidated Balance Sheets. We also had a variety of unapproved contract change orders or claims that are not included in our revenues as of December 31, 2015. The amounts associated with these contract change orders or claims are included in revenue only when they can be reliably estimated and their realization is reasonably assured.

During 2014, we recognized estimated project losses of $72 million related to our long-term early production facility construction contracts in Iraq accounted for under the percentage-of-completion method. Total estimated losses on these projects were $379 million at December 31, 2014. As of December 31, 2014, our percentage-of-completion project estimates include $90 million of claims revenue and $24 million of back charges. Our costs in excess of billings as of December 31, 2014 were $128 million and are shown in the “Other Current Assets” on the balance sheet. We had a variety of unapproved contract change orders or claims that were not included in our revenues as of December 31, 2014. During 2014, an additional $80 million of claims revenue was included in our project estimates and $26 million of our prior claims were approved.