XML 132 R20.htm IDEA: XBRL DOCUMENT v2.4.0.8
LEASES
12 Months Ended
Dec. 31, 2013
LEASES  
LEASES

NOTE 12—LEASES

        The following table sets forth the future minimum rental payments, by calendar year, required under existing operating leases and digital projector equipment leases payable to DCIP that have initial or remaining non-cancelable terms in excess of one year as of December 31, 2013:

(In thousands)
  Minimum operating
lease payments
 

2014

  $ 428,108  

2015

    435,906  

2016

    420,230  

2017

    403,552  

2018

    360,704  

Thereafter

    1,606,326  
       

Total minimum payments required

  $ 3,654,826  
       
       

        As of December 31, 2013, the Company has lease agreements for four theatres with 41 screens which are under construction or development and are expected to open in 2014.

        Included in other long-term liabilities as of December 31, 2013 and December 31, 2012 is $55,272,000 and $10,318,000, respectively, of deferred rent representing future minimum rental payments for leases with scheduled rent increases, and $194,233,000 and $211,329,000, respectively, for unfavorable lease liabilities.

        Rent expense is summarized as follows:

(In thousands)
  12 Months
Ended
December 31,
2013
  From Inception
August 31,
2012 through
December 31,
2012
   
  March 30,
2012 through
August 30,
2012
  52 Weeks
Ended
March 29,
2012
 
 
  (Successor)
  (Successor)
   
  (Predecessor)
  (Predecessor)
 
 
   
   
   
   
   
 

Minimum rentals

  $ 394,937   $ 126,529       $ 166,220   $ 394,742  

Common area expenses

    44,198     12,968         17,591     40,918  

Percentage rentals based on revenues

    12,693     3,877         5,275     9,666  
                       

Rent

    451,828     143,374         189,086     445,326  

General and administrative and other

    13,393     3,940         4,207     8,747  
                       

Total

  $ 465,221   $ 147,314       $ 193,293   $ 454,073