Vessels Under Construction (Details) (USD $)
6 Months Ended
Sep. 30, 2014
Mar. 31, 2014
Sep. 30, 2014
Vessels under commitment
Sep. 30, 2014
Vessels under commitment
Manager
Sep. 30, 2014
Vessels under commitment
Third party vendors
Vessels under construction          
Balance $ 352,708,919 $ 323,206,206 $ 323,206,206    
Installment payments to shipyards     178,511,791    
Other capitalized expenditures     5,627,131 900,000 3,500,000
Capitalized interest     1,568,543    
Vessels delivered (transferred to Vessels)     (156,204,752)    
Balance 352,708,919 323,206,206 352,708,919    
LPG coolant cost included in Other capitalized expenditures     $ 1,100,000