Purchase Commitments
We outsource most of our manufacturing and supply chain management operations to third-party contract manufacturers, who procure components and assemble products on our behalf. A significant portion of our purchase orders for finished goods and strategic components, including integrated circuits consigned to contract manufacturers, consists of non-cancellable commitments. Our purchase obligations also encompass software and technology licenses, property and equipment, and other corporate goods and services. As of December 31, 2025, we had non-cancellable purchase commitments not recorded on our balance sheet of $6.8 billion, of which $6.3 billion have confirmed receipt dates within 12 months, and $0.5 billion have confirmed receipt dates greater than 12 months. These open purchase orders are considered enforceable and legally binding, and while we may have some limited ability to reschedule, and adjust our requirements based on our business needs prior to the delivery of goods or performance of services, this can only occur with the agreement of the related supplier.
We also had deposits to our contract manufacturers to secure our purchase commitments in the amount of $53.0 million and $95.8 million as of December 31, 2025 and 2024, respectively, which were recorded within prepaid expenses and other current assets, as well as other assets in the consolidated balance sheets.
Leases
We have operating lease arrangements for office space, data center, equipment and other corporate assets. As of December 31, 2025, we had lease payment obligations, net of immaterial sublease income, of $90.5 million, with $22.1 million payable within 12 months.
Property project
During the year ended December 31, 2021, we purchased land and the improvements thereon in Santa Clara, California to construct a building for office, lab and data center space. The estimated capital expenditures related to this project is expected to be approximately $170.0 million to $195.0 million through December 31, 2026 at which time construction is expected to be completed.
Guarantees
We have entered into agreements with some of our direct customers and channel partners that contain indemnification provisions relating to potential situations where claims could be alleged that our products infringe the intellectual property rights of a third-party. We have, at our option and expense, the ability to repair any infringement, replace product with a non-infringing equivalent-in-function product or refund our customers all or a portion of the value of the product. Other guarantees or indemnification agreements include guarantees of product and service performance and standby letters of credit for leased facilities and corporate credit cards. We have not recorded a liability related to these indemnification and guarantee provisions, and our guarantee and indemnification arrangements have not had any material impact on our consolidated financial statements to date.
Legal Proceedings
    In the ordinary course of business, we are a party to other claims and legal proceedings including matters relating to commercial, employee relations, business practices and intellectual property.
    We record a provision for contingent losses when it is both probable that a liability has been incurred and the amount of the loss can be reasonably estimated. As of December 31, 2025, provisions recorded for contingent losses related to other claims and matters have not been significant. Based on currently-available information, management does not believe that any additional liabilities relating to other unresolved matters are probable or that the amount of any resulting loss is estimable, and believes these other matters are not likely, individually and in the aggregate, to have a material adverse effect on our financial position, results of operations or cash flows; however, litigation is subject to inherent uncertainties and our view of these matters may change in the future. Were an unfavorable outcome to occur, there exists the possibility of a material adverse impact on our financial position, results of operations or cash flows for the period in which the unfavorable outcome occurs, and potentially in future periods.