Operating Leases
We lease various operating spaces in North America, Europe, Asia and Australia under non-cancelable operating lease arrangements that expire on various dates through 2025. We recognize rent expense under these arrangements on a straight-line basis over the term of the lease. Rent expense for all operating leases amounted to $2.4 million and $2.0 million, for the three months ended March 31, 2017 and 2016, respectively. There have been no material changes in our operating lease commitments under contractual obligation, as disclosed in our Annual Report on Form 10-K for the year ended December 31, 2016.
Financing Obligation—Build-to-Suit Lease
In August 2012, we executed a lease for a building then under construction in Santa Clara, California to serve as our headquarters. The lease term is 120 months and commenced in August 2013. The underlying building asset is depreciated over the building’s estimated useful life of 30 years. At the conclusion of the initial lease term, we will de-recognize both the net book values of the asset and the remaining financing obligation. There have been no material changes in our operating lease commitments under contractual obligation, as disclosed in our Annual Report on Form 10-K for the year ended December 31, 2016.
As of March 31, 2017 and December 31, 2016, we have recorded assets of $53.4 million, representing the total costs of the building and improvements incurred, including the costs paid by the lessor (the legal owner of the building) and additional improvement costs paid by us, and a corresponding financing obligation of $40.8 million and $41.2 million, respectively. As of March 31, 2017, $1.7 million and $39.1 million were recorded as short-term and long-term financing obligations, respectively.
Land lease expense related to our lease financing obligation is classified as rent expense in our unaudited condensed consolidated statements of income, and amounted to $0.3 million for both the three months ended March 31, 2017 and 2016.
Purchase Commitments
We outsource most of our manufacturing and supply chain management operations to third-party contract manufacturers, who procure components and assemble products on our behalf based on our forecasts in order to reduce manufacturing lead times and ensure adequate component supply. We issue purchase orders to our contract manufacturers for finished product and a significant portion of these orders consist of firm non-cancelable commitments. In addition, we purchase strategic component inventory from certain suppliers under purchase commitments that in some cases are non-cancelable, including integrated circuits, which are consigned to our contract manufacturers. As of March 31, 2017, we had non-cancelable purchase commitments of $362.6 million. In addition, we have provided deposits to secure our obligations to purchase inventory. We had $42.0 million and $63.1 million in deposits as of March 31, 2017 and December 31, 2016, respectively. These deposits are classified in other current and long term assets in our accompanying unaudited condensed consolidated balance sheets.
Guarantees
We have entered into agreements with some of our direct customers and channel partners that contain indemnification provisions relating to potential situations where claims could be alleged that our products infringe the intellectual property rights of a third party. We have at our option and expense the ability to repair any infringement, replace product with a non-infringing equivalent-in-function product or refund our customers all or a portion of the value of the product. Other guarantees or indemnification agreements include guarantees of product and service performance and standby letters of credit for lease facilities and corporate credit cards. We have not recorded a liability related to these indemnification and guarantee provisions and our guarantee and indemnification arrangements have not had any significant impact on our consolidated financial statements to date.
Legal Proceedings
OptumSoft, Inc. Matters
On April 4, 2014, OptumSoft filed a lawsuit against us in the Superior Court of California, Santa Clara County titled OptumSoft, Inc. v. Arista Networks, Inc., in which it asserts (i) ownership of certain components of our EOS network operating system pursuant to the terms of a 2004 agreement between the companies; and (ii) breaches of certain confidentiality and use restrictions in that agreement. Under the terms of the 2004 agreement, OptumSoft provided us with a non-exclusive, irrevocable, royalty-free license to software delivered by OptumSoft comprising a software tool used to develop certain components of EOS and a runtime library that is incorporated into EOS. The 2004 agreement places certain restrictions on our use and disclosure of the OptumSoft software and gives OptumSoft ownership of improvements, modifications and corrections to, and derivative works of, the OptumSoft software that we develop.
In its lawsuit, OptumSoft has asked the Court to order us to (i) give OptumSoft access to our software for evaluation by OptumSoft; (ii) cease all conduct constituting the alleged confidentiality and use restriction breaches; (iii) secure the return or deletion of OptumSoft’s alleged intellectual property provided to third parties, including our customers; (iv) assign ownership to OptumSoft of OptumSoft’s alleged intellectual property currently owned by us; and (v) pay OptumSoft’s alleged damages, attorney’s fees, and costs of the lawsuit. David Cheriton, one of our founders and a former member of our board of directors, who resigned from our board of directors on March 1, 2014 and has no continuing role with us, is a founder and, we believe, the largest stockholder and director of OptumSoft. The 2010 David R. Cheriton Irrevocable Trust dtd July 28, 2010, a trust for the benefit of the minor children of Mr. Cheriton, is one of our largest stockholders.
On April 14, 2014, we filed a cross-complaint against OptumSoft, in which we assert our ownership of the software components at issue and our interpretation of the 2004 agreement. Among other things, we assert that the language of the 2004 agreement and the parties’ long course of conduct support our ownership of the disputed software components. We ask the Court to declare our ownership of those software components, all similarly-situated software components developed in the future and all related intellectual property. We also assert that, even if we are found not to own certain components, such components are licensed to us under the terms of the 2004 agreement. However, there can be no assurance that our assertions will ultimately prevail in litigation. On the same day, we also filed an answer to OptumSoft’s claims, as well as affirmative defenses based in part on OptumSoft’s failure to maintain the confidentiality of its claimed trade secrets, its authorization of the disclosures it asserts and its delay in claiming ownership of the software components at issue. We have also taken additional steps to respond to OptumSoft’s allegations that we improperly used and/or disclosed OptumSoft confidential information. While we believe we have meritorious defenses to these allegations, we believe we have (i) revised our software to remove the elements we understand to be the subject of the claims relating to improper use and disclosure of OptumSoft confidential information and made the revised software available to our customers and (ii) removed information from our website that OptumSoft asserted disclosed OptumSoft confidential information.
The parties tried Phase I of the case, relating to contract interpretation and application of the contract to certain claimed source code, in September 2015. On December 16, 2015, the Court issued a Proposed Statement of Decision Following Phase 1 Trial, and on January 8, 2016, OptumSoft filed objections to that Proposed Statement of Decision. On March 23, 2016, the Court issued a Final Statement of Decision Following Phase I Trial, in which it agreed with and adopted our interpretation of the 2004 agreement and held that we, and not OptumSoft, own all the software at issue in Phase I. The remaining issues that were not addressed in the Phase I trial are set to be tried in Phase II including the application of the Court’s interpretation of the 2004 agreement as set forth in the Final Statement of Decision Following Phase I Trial to any other source code that OptumSoft claims to own following a review. Phase II was previously scheduled to be tried in April 2016; however, that trial date has been vacated and a new trial date has not yet been set.
We intend to vigorously defend against any claims brought against us by OptumSoft.  However, we cannot be certain that, if litigated, any claims by OptumSoft would be resolved in our favor.  For example, if it were determined that OptumSoft owned components of our EOS network operating system, we would be required to transfer ownership of those components and any related intellectual property to OptumSoft.  If OptumSoft were the owner of those components, it could make them available to our competitors, such as through a sale or license.  An adverse litigation ruling could result in a significant damages award against us and injunctive relief. In addition, OptumSoft could assert additional or different claims against us, including claims that our license from OptumSoft is invalid.
With respect to the legal proceedings described above, it is our belief that while a loss is not probable, it may be reasonably possible. Further, at this stage in the litigation, any possible loss or range of loss cannot be estimated.  However, the outcome of litigation is inherently uncertain. Therefore, if one or more of these legal matters were resolved against us in a reporting period for a material amount, our consolidated financial statements for that reporting period could be materially adversely affected.    
Cisco Systems, Inc. (“Cisco”) Matters    
We are currently involved in several litigation matters with Cisco Systems, Inc. These matters are summarized below.
Cisco Systems, Inc. v. Arista Networks, Inc. (Case No. 4:14-cv-05343) (“’43 Case”)
On December 5, 2014, Cisco filed a complaint against us in the District Court for the Northern District of California alleging that we infringe U.S. Patent Nos. 6,377,577; 6,741,592; 7,023,853; 7,061,875; 7,162,537; 7,200,145; 7,224,668; 7,290,164; 7,340,597; 7,460,492; 8,051,211; and 8,356,296 (respectively, “the ’577 patent,” “the ’592 patent,” “the ’853 patent,” “the 875 patent,” “the ’537 patent,” “the ’145 patent,” “the ’668 patent,” “the ’164 patent,” “the ’597 patent,” “the ’492 patent,” “the ’211 patent,” and “the ’296 patent”). Cisco seeks, as relief for our alleged infringement in the ’43 Case, lost profits and/or reasonable royalty damages in an unspecified amount, including treble damages, attorney’s fees, and associated costs. Cisco also seeks injunctive relief in the ’43 Case. On February 10, 2015, the Court granted our unopposed motion to stay the ’43 Case until the proceedings before the United States International Trade Commission (“USITC”) pertaining to the same patents (as discussed below) became final. Trial has not been scheduled in the ’43 Case.
Cisco Systems, Inc. v. Arista Networks, Inc. (Case No. 5:14-cv-05344) (“’44 Case”)    
On December 5, 2014, Cisco filed a complaint against us in the District Court for the Northern District of California alleging that we infringe numerous copyrights pertaining to Cisco’s “Command Line Interface” or “CLI” and U.S. Patent Nos. 7,047,526 and 7,953,886 (respectively, “the ’526 patent” and “the ’886 patent”). As relief for our alleged patent infringement in the ’44 Case, Cisco seeks lost profits and/or reasonable royalty damages in an unspecified amount including treble damages, attorney’s fees, and associated costs as well as injunctive relief. As relief for our alleged copyright infringement, Cisco seeks monetary damages for alleged lost profits, profits from our alleged infringement, statutory damages, attorney’s fees, and associated costs.
As described below, on May 25, 2016, our petition for Inter Partes Review (“IPR”) of the ’886 patent was instituted by the United States Patent Trial and Appeal Board (“PTAB”). Cisco subsequently agreed to dismiss its claims as to the ‘886 patent with prejudice.
Trial began on November 28, 2016, and the jury rendered its verdict on December 14, 2016. The jury found that Arista had proven its copyright defense of scenes a faire and that Cisco had failed to prove infringement of the ’526 patent, and on that basis judgment was entered in Arista’s favor on all claims on December 19, 2016.
On January 17, 2017, Cisco filed a motion for judgment as a matter of law, challenging the sufficiency of the evidence in support of Arista's scenes a faire defense. Cisco did not file any post-trial motion regarding the ’526 patent, nor did it file a motion for a new trial. We also filed a motion for judgment as a matter of law on several issues. The hearing on both parties’ motions was held on April 27, 2017.
Arista Networks, Inc. v. Cisco Systems, Inc. (Case No. 5:16-cv-00923) (“’23 Case”)
On February 24, 2016, we filed a complaint against Cisco in the District Court for the Northern District of California alleging antitrust violations and unfair competition. On August 23, 2016, the Court granted Cisco’s motion to stay the ’23 Case until judgment has been entered on Cisco’s copyright claims in the ’44 Case. On March 2, 2017, the Court lifted the stay and trial is set for August 3, 2018.
Certain Network Devices, Related Software, and Components Thereof (Inv. No. 337-TA-944) (“944 Investigation”)
On December 19, 2014, Cisco filed a complaint against us in the USITC alleging that we have violated 19 U.S.C. § 1337 (“Section 337”). The USITC instituted Cisco’s complaint as Investigation No. 337-TA-944. Cisco initially alleged that certain of our switching products infringe the ’592, ’537, ’145, ’164, ’597, and ’296 patents. Cisco subsequently dropped the ’296 patent from the 944 Investigation. Cisco sought, among other things, a limited exclusion order barring entry into the United States of accused switch products (including our 7000 Series of switches) and components and software therein and a cease and desist order against us restricting our activities with respect to our imported accused switch products and components and software therein.
On February 2, 2016, the Administrative Law Judge (“ALJ”) issued his initial determination finding a violation of Section 337. More specifically, the ALJ found that a violation has occurred in the importation into the United States, the sale for importation, or the sale within the United States after importation, of certain network devices, related software, and components thereof that the ALJ found infringe asserted claims 1, 2, 8-11, and 17-19 of the ’537 patent; asserted claims 6, 7, 20, and 21 of the ’592 patent; and asserted claims 5, 7, 45, and 46 of the ’145 patent. The ALJ did not find a violation of Section 337 with respect to any asserted claims of the ’597 and ’164 patents. On June 23, 2016, the Commission issued its Final Determination, which found a violation with respect to the ’537, ’592, and ’145 patents, and found no violation with respect to the ’597 and ’164 patents. The Commission also issued a limited exclusion order and a cease and desist order pertaining to network devices, related software and components thereof that infringe one or more of claims 1, 2, 8-11, and 17-19 of the ’537 patent; claims 6, 7, 20, and 21 of the ’592 patent; and claims 5, 7, 45, and 46 of the ’145 patent. On August 22, 2016, the Presidential review period for the 944 investigation expired. The USITC orders will be in effect until the expiration of the ’537, ’592, and ’145 patents.
Both we and Cisco filed petitions for review of the USITC’s Final Determination to the U.S. Court of Appeals for the Federal Circuit (“Federal Circuit”). The appeal is fully briefed and oral argument has not been scheduled.
On August 26, 2016, Cisco filed an enforcement complaint under Section 337 with the USITC. Cisco alleges that we are violating the cease and desist and limited exclusion orders issued in the 944 Investigation by engaging in the “marketing, distribution, offering for sale, selling, advertising, and/or aiding or abetting other entities in the sale and/or distribution of products that Cisco alleges continue to infringe claims 1-2, 8-11, and 17-19 of the ’537 patent,” despite the design changes we have made to those products. Cisco asks the USITC to (1) enforce the cease and desist order; (2) modify the Commission’s limited exclusion order and/or cease and desist order “in any manner that would assist in the prevention of the unfair practices that were originally the basis for issuing such Order or assist in the detection of violations of such Order”; (3) impose the maximum statutory civil penalties for violation of the cease and desist order “including monetary sanctions for each day’s violation of the cease and desist order of the greater of $100,000 or twice the domestic value of the articles entered or sold, whichever is higher”; (4) bring a civil action in U.S. district court “requesting collection of such civil penalties and the issuance of a mandatory injunction preventing further violation of Cease and Desist Order”; and (5) impose “such other remedies and sanctions as are appropriate and within the Commission’s authority.” On September 28, 2016, the Commission instituted the enforcement proceeding. The proceeding has been assigned to ALJ Judge Shaw, who presided over the underlying investigation. On October 14, 2016, we responded to the complaint by, among other things, denying the patent infringement allegations and raising affirmative defenses. On November 2, 2016, the ALJ issued an order setting the deadline for the initial determination for June 20, 2017 and the Target Date for September 20, 2017. On April 4 and 5, 2017, the ALJ held the evidentiary hearing in this proceeding.
Certain Network Devices, Related Software, and Components Thereof (Inv. No. 337-TA-945) (“945 Investigation”)
On December 19, 2014, Cisco filed a complaint against us in the USITC alleging that we violated Section 337. The USITC instituted Cisco’s complaint as Investigation No. 337-TA-945. Cisco alleges that certain of our switching products infringe the ’577, ’853, ’875, ’668, ’492, and ’211 patents. Cisco seeks, among other things, a limited exclusion order barring entry into the United States of accused switch products (including our 7000 Series of switches) related software, and components thereof and a cease and desist order against us restricting our activities with respect to our imported accused switch products, related software, and components thereof.
On December 9, 2016, the ALJ issued her initial determination finding a violation of Section 337. More specifically, the ALJ found that a violation has occurred in the importation into the United States, the sale for importation, or the sale within the United States after importation, of certain network devices, related software, and components thereof that the ALJ found infringe asserted claims 1, 7, 9, 10, and 15 of the ’577 patent; and asserted claims 1, 2, 4, 5, 7, 8, 10, 13, 19, 56, and 64 of the ’668 patent. The ALJ did not find a violation of Section 337 with respect to asserted claim 2 of the ’577 patent or any asserted claims of the ’853, ’492, ’875, and ’211 patents. On December 29, 2016, Arista, Cisco and the Office of Unfair Importation Investigation ("OUII") filed petitions for review of certain findings contained in the initial determination. On March 1, 2017, the Commission issued a notice that it was reviewing the final initial determination in part on certain issues.
On May 4, 2017, the Commission issued its Final Determination, which found a violation with respect to the ’577 and ’668 patents, and found no violation with respect to the ’211, ’853, ’875 and ’492 patents. The Commission also issued a limited exclusion order and a cease and desist order pertaining to network devices, related software and components thereof that infringe one or more of claims 1, 7, 9, 10, and 15 of the ’577 patent and 1, 2, 4, 5, 7, 8, 10, 13, 18, 56, and 64 of the ’668 patent. The Commission’s final determination is subject to a 60-day Presidential review period, during which the United States Trade Representative will decide whether to disapprove the decision. During the Presidential review period, we must pay a 5% bond on any imports of any products and components subject to the order, and on any sales of previously imported products and components subject to the order.
Inter Partes Reviews
We have filed petitions for Inter Partes Review of the ’597, ’211, ’668, ’853, ’537, ’577, ’886, and ’526 patents. IPRs relating to the ’597 (IPR No. 2015-00978) and ’211 (IPR No. 2015-00975) patents were instituted in October 2015 and hearings on these IPRs were completed in July 2016. On September 28, 2016, the PTAB issued a final written decision finding claims 1, 14, 39-42, 71, 72, 84, and 85 of the ’597 patent unpatentable. The PTAB also found that claims 29, 63, 64, 73, and 86 of the ’597 patent had not been shown to be unpatentable. On October 5, 2016, the PTAB issued a final written decision finding claims 1 and 12 of the ’211 patent unpatentable. The PTAB also found that claims 2, 6-9, 13, 17-20 of the ’211 patent had not been shown to be unpatentable. Both parties have appealed the final written decisions on the ’211 and ’537 patents IPRs.
The IPR relating to the ’886 patent was instituted on May 25, 2016. Following that decision, Cisco agreed to dismiss its claims as to the ʼ886 patent with prejudice, and we dismissed our counterclaims as to the ʼ886 patent without prejudice.
IPRs relating to the ’668 (IPR No. 2016-00309), ’577 (IPR No. 2016-00303), ’853 (IPR No. 2016-0306), and ’537 (IPR No. 2016-0308) patents were instituted in June 2016 and hearings were held on March 7, 2017. Final Written Decisions on these IPRs are expected to be issued by June 2017.
* * * * *
We intend to vigorously defend against each of the Cisco’s lawsuits, as summarized in the preceding paragraphs. However, we cannot be certain that any claims by Cisco would be resolved in our favor regardless of the merit of the claims. Any adverse litigation ruling could result in the above described injunctive relief, could require a significant damages award against us or a requirement that we make substantial royalty payments to Cisco, and/or could require that we modify our products.
For example, in the 944 Investigation, the USITC has issued a limited exclusion order barring entry into the United States of our network devices (including our 7000 Series of switches), related software, and components thereof that infringe one or more of the claims of the ʼ537, ʼ592, and ʼ145 patents specified above and a cease and desist order restricting our activities with respect to such imported products. In addition, in the 945 Investigation, the Commission has issued its Final Determination, finding a violation of section 337 of the Tariff Act with respect to the ʼ668 and ʼ577 patents.

To comply with these orders, we have sought to develop technical design-arounds that no longer infringe the patents that are the subject of the orders. In any efforts to develop technical design-arounds for our products, we may be unable to do so in a manner that does not continue to infringe the patents or that is acceptable to our customers. Our redesign efforts could be extremely costly and time consuming as well as disruptive to our other development activities and distracting to management. Moreover, in the 944 Investigation and 945 Investigation, such design-arounds would require us to obtain approval of either the USITC or U.S. Customs and Border Protection (“CBP”) to resume the importation of the redesigned products into the United States. We may not be successful in our efforts to obtain such approvals to import such modified products in a timely manner, or at all. While a favorable ruling from the CBP would allow us to resume importation of our redesigned products into the United States, the USITC could still determine in an enforcement action that our redesigned products continue to infringe the patents that are the subject of any USITC orders. Any failure to effectively redesign our products, to obtain timely clearance from USITC or CBP to import such redesigned products, or to address the USITC findings in a manner that complies with the USITC orders, may cause a disruption to our product shipments and materially and adversely affect our business, prospects, reputation, results of operations, and financial condition.
Specifically, in response to the USITC’s findings in the 944 Investigation, we have made design changes to our products for sale in the United States to address the features that were found to infringe the ’537, ’592, and ’145 patents. Following the issuance of the final determination in the 944 Investigation, we submitted a Section 177 ruling request to CBP seeking approval to import these redesigned products into the United States. On November 18, 2016, we received a 177 ruling from CBP finding that our redesigned products did not infringe the relevant claims of the ʼ537, ’592, and ʼ145 patents, and approving the importation of these redesigned products into the United States. However, on January 13, 2017, at the request of Cisco and without our input, CBP issued a letter to us revoking its prior November 18 ruling. CBP subsequently conducted an inter partes proceeding between Arista and Cisco to determine whether our redesigned products infringe and whether to approve them for importation into the United States. On April 7, 2017, following the inter partes proceeding, CBP again ruled that our design around products do not infringe the relevant claims of the ’537, ’592, and ’145 patents and again approved those design arounds for importation into the United States.

Similarly, on May 4, 2017, the USITC issued a limited exclusion order and cease and desist order in the 945 Investigation with respect to the ‘668 and ‘577 patents. If such orders are not disapproved by the United States Trade Representative, we would need to further modify our products to take our products outside the scope of the ‘668 and ‘577 patents and obtain the USITC and/or CBP approvals described above to resume importation of our redesigned products into the United States. For example, we submitted a technical design-around for the ‘668 patent into the 945 Investigation. However, in the Final Determination, the Commission found that this design around continues to infringe the patent. This will require us to implement an alternative redesign for our products to make them non-infringing. We may not be able to do so in a manner that does not continue to infringe the patent or that is acceptable to customers. We may not be able to complete, and our customers may not be able to qualify, such redesigned products in a timely fashion, if at all, following the end of the Presidential review period, leading to an inability to ship products to customers. Our redesign efforts could be extremely costly and time consuming as well as disruptive to our other development activities and distracting to management. In addition, during the Presidential review period, we must pay a 5% bond on imports of any products and components subject to the order, and on any sales of previously imported products and components subject to the order.
If the USITC determines that our redesigned products continue to infringe the patents subject to any USITC limited exclusion order or cease and desist order in an enforcement action for either the 944 Investigation or the 945 Investigation, the USITC may impose the maximum statutory civil penalties for violation of the cease and desist order “including monetary sanctions for each day’s violation of the cease and desist order of the greater of $100,000 or twice the domestic value of the articles entered or sold, whichever is higher,” bring a civil action in U.S. district court “requesting collection of such civil penalties and the issuance of a mandatory injunction preventing further violation of Cease and Desist Order,” or impose “such other remedies and sanctions as are appropriate and within the Commission’s authority.”
An adverse finding in an enforcement action would take effect immediately upon USITC’s issuance of the final determination, without any Presidential review period. To address such a finding, we would have to further redesign our products to make them non-infringing, and until we made such changes we would not be able to import or ship our products to customers. We may not be able to do so in a manner that does not continue to infringe the patents or that is acceptable to customers. We may not be able to complete, and our customers may not be able to qualify, such redesigned products in a timely fashion, if at all, following the issuance of an adverse final determination, leading to an inability to ship products to customers. Our redesign efforts could be extremely costly and time consuming as well as disruptive to our other development activities and distracting to management. We would also need to obtain USITC or CBP approval to resume importation of such redesigned products into the United States. In addition, the USITC would not provide a service and support exception for our previously redesigned products, and customers may be required to upgrade to new products to obtain service and support.
To comply with the USITC’s remedial orders, we have also made certain changes to our manufacturing, importation and shipping workflows. These changes have included shifting manufacturing and integration of our products to be sold in the United States to U.S. facilities. Such changes may be extremely costly, time consuming, and we may not be able to implement such changes successfully. Any failure to successfully change our manufacturing and importation processes or shipping workflows in a manner that is compliant with the limited exclusion order and cease and desist order may cause a disruption in our product shipments and materially and adversely affect our business, prospects, reputation, results of operations, and financial condition.
In connection with these changes, to the extent that we are required to make further modifications to our supply chain to obtain alternative U.S. sources for subcomponents, we may be unable to obtain a sufficient quantity of these components on commercially reasonable terms or in a timely manner, if at all, which could delay or halt entirely production of our products or require us to make further modifications to our products to incorporate new components that are available in the United States. Any of these events could result in lost sales, reduced gross margins or damage to our end-customer relationships, which would materially and adversely impact our business, financial condition, results of operations and prospects.
Additionally, the existence of Ciscoʼs lawsuits against us could cause concern among our customers and partners and could adversely affect our business and results of operations. Many of our customers and partners require us to indemnify and defend them against third party infringement claims and pay damages in the case of adverse rulings. These claims could harm our relationships with our customers or channel partners, cause them to delay or defer purchasing decisions or deter them from doing business with us. From time to time, we may also be required to provide additional assurances beyond our standard terms. Whether or not we prevail in the lawsuit, we expect that the litigation will be expensive, time-consuming and a distraction to management in operating our business.
With respect to the various legal proceedings described above, it is our belief that while a loss is not probable, it may be reasonably possible. Further, at this stage in the litigation, any possible loss or range of loss cannot be estimated.  However, the outcome of litigation is inherently uncertain. Therefore, if one or more of these legal matters were resolved against us in a reporting period for a material amount, our consolidated financial statements for that reporting period could be materially adversely affected.
In the Matter of Certain Semiconductor Devices, Semiconductor Device Packages, and Products Containing Same (337-TA-1010)
On May 23, 2016, Tessera Technologies, Inc., Tessera, Inc., and Invensas Corp. (“Tessera”) filed a complaint in the USITC alleging that Broadcom Limited, Broadcom Corporation, Avago Technologies Limited, and Avago Technologies U.S. Inc. (“Broadcom”) violated 19 U.S.C. § 1337 (“Section 337”). On June 10, 2016, the USITC instituted Tessera’s complaint as Investigation No. 337-TA-1010 on June 20, 2016.
Tessera alleges that certain Broadcom semiconductor devices infringe U.S. Patent No. 6,856,007; U.S. Patent No. 6,849,946; and U.S. Patent No. 6,133,136. Tessera further alleged that Broadcom's downstream customers, Arista Networks, Inc.; ARRIS International plc; ARRIS Group, Inc.; ARRIS Technology, Inc.; ARRIS Enterprises LLC; ARRIS Solutions, Inc.; Pace Ltd.; Pace Americas, LLC; Pace USA; LLC, ASUSteK Computer Inc.; ASUS Computer International; Comcast Cable Communications, LLC; Comcast Cable Communications Management, LLC; Comcast Business Communications, LLC; HTC Corporation; HTC America, Inc.; NETGEAR, Inc.; Technicolor S.A.; Technicolor USA, Inc.; and Technicolor Connected Home USA LLC (“Downstream Respondents”), were violating Section 337 by importing, selling after importation, or selling for importation products that incorporate the accused Broadcom semiconductor devices. The accused Company products include certain models of our switching products.
Tessera seeks the following relief: (1) a permanent limited exclusion order excluding from importation into the U.S. all of Tessera’s semiconductor devices and semiconductor device packages and Downstream Respondents’ products containing Broadcom’s semiconductor devices that infringe one or more of the three patents-in-suit and (2) a permanent cease and desist order prohibiting Broadcom and Downstream Respondents and related companies from importing, marketing, advertising, demonstrating, warehousing inventory for distribution, offering for sale, selling, qualifying for use in the products of others, distributing, or using the accused Broadcom semiconductor devices Downstream Respondents’ products containing Respondents’ semiconductor devices and semiconductor device packages that infringe one or more of the three patents subject to the ITC Investigation.
The evidentiary hearing was held on March 27 through March 31, 2017, and the target date for completion of the Investigation is October 24, 2017.

To the extent claims made by Tessera in the ITC Investigation against Arista are based solely on functionality residing in Broadcom’s products, Broadcom has agreed to defend Arista at no cost to Arista.
Plectrum, Inc. v. Arista Networks, Inc. (Case No. 4:17-cv-76)
On February 2, 2017, Plectrum LLC (“Plectrum”) filed a complaint against Arista Networks, Inc. in the U.S. District Court for the Eastern District of Texas alleging infringement of the U.S. Patent Nos. 6,205,149 (“the ‘149 Patent”), 5,978,951 (“the ‘951 Patent”), and 6,751,677 (“the ‘677 Patent”) based upon our manufacture, use, by sale and/or offer for sale of our 7150 series and 7500 series switches. Plectrum seeks a permanent injunction or ongoing royalty, unspecified damages and costs, pre-judgement and post-judgement interest on the damages, and attorneys’ fees. In addition to Arista, Plectrum has also sued some of our competitors, customers, and suppliers. Plectrum has filed lawsuits against sixteen (16) parties in total related to this effort. We believe that the claims are without merit and intend to defend ourselves vigorously against the claims.
Other Matters
In the ordinary course of business, we are a party to other claims and legal proceedings including matters relating to commercial, employee relations, business practices and intellectual property. We record a provision for contingent losses when it is both probable that a liability has been incurred and the amount of the loss can be reasonably estimated. As of March 31, 2017, provisions recorded for contingent losses related to other claims and matters have not been significant. Based on currently available information, management does not believe that any additional liabilities relating to other unresolved matters are probable or that the amount of any resulting loss is estimable, and believes these other matters are not likely, individually and in the aggregate, to have a material adverse effect on our financial position, results of operations or cash flows. However, litigation is subject to inherent uncertainties and our view of these matters may change in the future. Were an unfavorable outcome to occur, there exists the possibility of a material adverse impact on our financial position, results of operations or cash flows for the period in which the unfavorable outcome occurs, and potentially in future periods.