Asset Retirement Obligations
The Company has recognized asset retirement obligations, or AROs, for properties where it can make a reasonable estimate of the future expenditures necessary to satisfy the related obligations. The Company considers identified legally enforceable obligations, estimated settlement dates and appropriate discount and inflation rates in calculating the fair value of its AROs. As of September 30, 2015 and December 31, 2014, the Company's ARO reserves, included in other current and long term liabilities in the Condensed Consolidated Balance Sheets, totaled $17.8 million and $18.5 million, respectively, for sites in Europe, Latin America and North America.
Changes in the Company’s AROs were as follows:
 
Three Months Ended September 30,
 
Nine Months Ended September 30,
 (amounts in millions)
2015
 
2014
 
2015
 
2014
AROs, beginning of period
$
17.7

 
$
5.4

 
$
18.5

 
$
4.8

Acquisitions

 
0.1

 
0.4

 
0.4

Accretion expense
0.2

 
0.2

 
0.7

 
0.5

Remeasurements
0.5

 

 
(0.2
)
 

Payments
(0.4
)
 

 
(0.4
)
 

Foreign currency adjustments
(0.2
)
 
(0.2
)
 
(1.2
)
 
(0.2
)
AROs, end of period
$
17.8

 
$
5.5

 
$
17.8

 
$
5.5


Environmental
The Company formulates and distributes specialty chemical products, and is exposed to claims with respect to environmental cleanup or other matters, including those in connection with the disposal of hazardous materials. The Company is subject to extensive domestic and foreign laws and regulations relating to environmental protection and worker health and safety, including those governing discharges of pollutants into the air and water, the management and disposal of hazardous substances and wastes, and the cleanup of contaminated properties. The Company has incurred, and will continue to incur, costs and capital expenditures in complying with these laws and regulations. Additional costs could be incurred, including cleanup costs, fines, sanctions, and third-party claims, as a result of violations of or liabilities under environmental laws.
Remediation activities vary substantially in duration and cost from site to site. These activities, and their associated costs, depend on the mix of unique site characteristics, evolving remediation technologies, diverse regulatory agencies and enforcement policies, as well as the presence or absence of potentially responsible parties. The Company has received notices of violation with respect to instances of non-compliance with environmental laws. A number of facilities and former facilities of the Company have been environmentally impacted from historic operations and some facilities are in the process of being investigated and remediated. As of September 30, 2015 and December 31, 2014, approximately $1.7 million and $4.5 million, respectively, was reserved for various environmental matters. Ultimate costs may vary from current estimates. The discovery of additional contaminants at these facilities or other sites or the imposition of additional cleanup obligations or third-party claims relating thereto could result in additional costs. Management believes that any possible losses related to environmental remediation in addition to the amounts recorded as of September 30, 2015 and December 31, 2014 would not be material to the Company’s consolidated financial position, results of operations or cash flows.
Legal Proceedings
From time to time, the Company is involved in various legal proceedings in the normal course of its business. We believe that the resolution of these claims, to the extent not covered by insurance, will not individually or in the aggregate, have a material adverse effect on the Company’s consolidated financial position, results of operations or cash flows. As of September 30, 2015 and December 31, 2014, the Company has reserved approximately $6.6 million and $4.4 million, respectively, for its outstanding legal proceedings. The following is a description of certain litigation matters.
Product liability and/or personal injury claims for, or relating to, products we sell under our Agricultural Solutions segment are complex in nature and have outcomes that are difficult to predict. Since these products are used in the food chain on a global basis, any such product liability or personal injury claim could lead to litigation in multiple jurisdictions. During 2014, Agricola Colonet, SA de CV claimed that certain Arysta products purchased from a retail distributor in Mexico were contaminated, requiring treated crops to be destroyed. Agricola Colonet, SA de CV is seeking compensation of approximately MXN 181 million ($10.7 million, based on the MXN/ USD exchange rate of 0.0591 on September 30, 2015). The Company believes that it has adequate defenses and intends to vigorously defend against this claim, and therefore has not established a reserve related to this claim. Under its risk management policies, the Company maintains certain insurance policies under which such claims may be covered.
In March 2013, a claim was filed against Arysta LifeScience Corporation, a subsidiary of the Company, relating to a purchasing optimization agreement entered into in 2011 between Arysta LifeScience Corporation and a consulting firm. The agreement provided for an incentive fee to be paid to the plaintiff based upon savings to Arysta resulting from the plaintiff's work. In addition to fees already received, the plaintiff claims damages, which the Company considers to be non-material. The Company believes this claim is without merit and that the fees already paid under the agreement exceed or equal the fees owed to the plaintiff. An arbitration hearing was conducted in May 2014, and in May 2015 the tribunal published a partial award, ruling on various issues of principle, but declining to calculate an award amount, rather asking the parties to attempt to agree upon a calculation reflecting the decisions of the tribunal set out in the award. The plaintiff subsequently filed for an application for clarification of the partial award, to which we responded by filing our own calculation of the award. The tribunal issued its clarification of the partial award, and we are awaiting submission by the plaintiff of its calculation of the award, after which further decisions from the tribunal are expected.
The $600 million of Series B Convertible Preferred Stock issued in connection with the Arysta Acquisition may be converted into a maximum of 22,107,590 shares of Platform common stock.  To the extent that the aggregate value of such shares is less than $600 million (based on a 10-day volume weighted average price), then, such shortfall would be payable in cash by Platform. Such shortfall would however be reduced by a portion, or all, of the amount for which the arbitration matter described in the preceding paragraph may be resolved, either by order of the arbitrators or by settlement, pursuant to a formula negotiated by and between the Company and the Seller.
In June 2009, a lawsuit was filed by a private individual against Arysta LifeScience do Brasil Industria Química e Agropecuária Ltda, or Arysta Brazil, and 25 other defendants, and in November 2011, a claim was filed against Arysta Brazil and five other defendants by the city of Ulianopolis, in each case in connection with materials sent by Arysta Brazil and others to an incineration site owned and operated by an unaffiliated third party in the state of Pará, Brazil. Arysta Brazil was summoned and has filed its answer in connection with both cases. Proceedings have been suspended until October 15, 2015 in order to allow the Pará State Attorney to conduct civil inquiries to determine the extent of contamination and the appropriate remediation, and to identify potentially responsible parties. Damages sought in the private lawsuit include a penalty of BRL 50.0 million ($12.6 million, based on the BRL/USD exchange rate of 0.2527 on September 30, 2015), plus interest and the cost of remediation.  The cost of remediation in the case brought by the city of Ulianopolis was previously estimated by the city to be BRL 70.9 million ($17.9 million, based on the BRL/USD exchange rate of 0.2527 on September 30, 2015). In addition, 13 former employees of the incineration facility have brought actions naming 80 defendants, including Arysta Brazil, seeking compensation in an aggregate amount of BRL 173.3 million ($43.8 million, based on the BRL/USD exchange rate of 0.2527 on September 30, 2015) for health problems allegedly contracted as a result of their employment at the incineration site.

In April 2014, Arysta LifeScience North America, LLC, or ALSNA, was served by Natividad and Francisco Sanchez, as plaintiffs, with a complaint naming over 30 defendants, including several chemical companies and crop protection companies. The complaint alleges that one of the plaintiffs was exposed to various products during the course of employment with various employers between 1989 and 2012, and that those products caused the plaintiff to develop medical conditions, including acute myelogenous leukemia. The plaintiffs are seeking monetary damages in the amount of $13.2 million. ALSNA filed its answer in May 2014 and later negotiated a settlement with the plaintiffs for a total settlement amount, which we consider to be non-material, and for which a settlement agreement is expected to be executed shortly.

From time to time, in the ordinary course of our business, we contest tax assessments received by our subsidiaries in various jurisdictions. Our contested tax assessments have been most prevalent in Brazil, where the tax regime is complex, and the administrative and judicial procedures for resolving disputed tax assessments are expensive and time-consuming. In addition, short of simply paying the entire amount demanded, including penalties, interest, and attorney’s fees, it is not possible to settle disputed tax assessments other than by submission for inclusion in formal tax amnesty programs announced by the Brazilian federal or state governments from time to time at irregular intervals. The terms of such amnesty programs vary, but generally offer the possibility of reduced interest and penalties. In the past, Arysta has submitted selected contested tax matters for inclusion in such amnesty programs in Brazil, when it appeared prudent to management to do so, and we are currently contesting several tax assessments at various stages of the applicable administrative and judicial processes, with a combined amount at issue, including interest and penalties, of approximately BRL 41.8 million ($10.6 million, based on the BRL/USD exchange rate of 0.2527 on September 30, 2015). Because tax matters in Brazil historically take many years to resolve, it is very difficult to estimate when these matters will be finally resolved.  Based on management's judgments, the Company does not expect it will incur a material loss in excess of accrued liabilities.
In February 2015, MacDermid, as plaintiff, settled a litigation with Cookson Group plc, Enthone Inc., Cookson Electronics and David North, as defendants, for $25.0 million. The litigation related to certain corporate activities that occurred between MacDermid and the defendants in 2006 and 2007. On April 3, 2015, the Company received part of the settlement in the amount of $16.0 million, and placed the remainder, net of legal costs, into escrow for future distribution in accordance with the pending litigation provisions of our Business Combination Agreement and Plan of Merger dated as of October 10, 2013.