Chapter 11 Cases
On October 3, 2019, the Debtors filed the Chapter 11 Cases in the Bankruptcy Code seeking relief under the Bankruptcy Code. We expect to continue operations in the normal course during the pendency of the Chapter 11 Cases. In addition, commencement of the Chapter 11 Cases automatically stayed all of the proceedings and actions against the Company, including those noted below. For a further discussion of the Chapter 11 Cases, see Note 1A. Any claims filed, or to be filed in relation to the Chapter 11 Cases, will be investigated and addressed in connection with the claims resolution process. The Company will continue to evaluate these liabilities throughout the Chapter 11 process and adjust amounts as necessary.
Legal Matters
We and our subsidiaries and affiliates are parties to various legal actions and claims that arise in the ordinary course of our business. For each matter, we evaluate the merits of the case or claim, our exposure to the matter, possible legal or settlement strategies and the likelihood of an unfavorable outcome.  If we determine that an unfavorable outcome is probable and can be estimated, we establish the necessary accruals. While the outcome of our current matters cannot be predicted with certainty and there are still uncertainties related to the costs we may incur, based upon our evaluation and experience to date, we believe we have established appropriate reserves for these matters. It is possible, however, that new information or future developments could require us to reassess our potential exposure and adjust our accruals accordingly, and these adjustments could be material. As of December 31, 2019, we had approximately $26 million accrued for all outstanding legal matters, which also represents our best estimate of the allowed claims for these legal matters which have been reclassified as liabilities subject to compromise on our balance sheet at December 31, 2019.
FairfieldNodal v. EP Energy E&P Company, L.P. On March 3, 2014, Fairfield filed suit against one of our subsidiaries in the 157th District Court of Harris County, Texas, claiming we were contractually obligated to pay a transfer fee of approximately $21 million for seismic licensing, triggered by a change in control with the Sponsors' acquisition of our predecessor entity in 2012. Prior to the change in control, we had unilaterally terminated the seismic licensing agreements, and we returned the applicable seismic data. Fairfield also claimed EP Energy did not properly maintain the confidentiality of the seismic data and interpretations made from it. In April 2015, the district court granted summary judgment to EP Energy, and Fairfield then appealed. On July 6, 2017, an intermediate court of appeals in Texas reversed the judgment related to the transfer fee and denied rehearing on October 5, 2017. We filed a petition for review in the Texas Supreme Court, which denied review in June 2019. We filed a motion for rehearing in the Texas Supreme Court on July 31, 2019. If denied, the case will be remanded to the trial court for further proceedings. As of December 31, 2019, we had accrued approximately $21 million related to this matter.
Storey Minerals, Ltd., et al. v. EP Energy E&P Company, L.P. On May 29, 2018, Storey Minerals, Ltd., Maltsberger/ Storey Ranch, LLC, and Rene R. Barrientos, Ltd. (collectively, “MSB”) filed suit against EP Energy in the 81st Judicial District Court of La Salle County, Texas. MSB alleged that by acquiring certain oil and gas leases within the perimeter of the Storey Altito Ranch, EP Energy triggered the most favored nation clause (“MFN clause”) in the leases. After investigation, EP Energy agreed that the MFN clause had been triggered and tendered a lease amendment with a check for $4 million for increased lease bonus. EP Energy's calculation confirmed that no delay rentals were due. MSB, however, did not accept the tender and asserts that the MFN clause operates retroactively to the date of the lease and applies to all of the acreage leased at that time. EP Energy maintains that the unambiguous language in the MFN clause operates prospectively and supports its tendered amendment and calculation. The parties filed cross-motions for summary judgment. In June 2019, the court entered an order agreeing with EP Energy on delay rentals, but with MSB on lease bonus. The court entered a final judgment in July 2019 ordering EP Energy to pay MSB $43.8 million in increased lease bonus, attorney’s fees, expenses and interest to date. EP Energy filed an appeal to the Fourth Circuit Court of Appeals in San Antonio, Texas on July 17, 2019 and intends to pursue fully its appeal. As of December 31, 2019, EP Energy's accrual of approximately $4 million related to this matter reflects the amount tendered to MSB with the lease amendment noted above, which EP Energy believes is the appropriate amount of increased bonus due to MSB.
Environmental Matters
We are subject to existing federal, state and local laws and regulations governing environmental quality, pollution control and greenhouse gas emissions. Numerous governmental agencies, such as the EPA, issue regulations which often require difficult and costly compliance measures that carry substantial administrative, civil and criminal penalties and may result in injunctive obligations for non-compliance. Our management believes that we are in substantial compliance with applicable environmental laws and regulations, and we have not experienced any material adverse effect from compliance with these environmental requirements. For additional details on certain environmental matters, including matters related to climate change, air quality and other emissions, hydraulic fracturing regulations and waste handling, refer to Part I, Item 1A. "Risk Factors".
While our reserves for environmental matters are currently not material, there are still uncertainties related to the ultimate costs we may incur in the future in order to comply with increasingly strict environmental laws, regulations, and orders of regulatory agencies, as well as claims for damages to property and the environment or injuries to employees and other persons resulting from our current or past operations. Based upon our evaluation and experience to date, however, we believe our accruals for these matters are adequate. It is possible that new information or future developments could result in substantial additional costs and liabilities which could require us to reassess our potential exposure related to these matters and to adjust our accruals accordingly, and these adjustments could be material.
Other Matters

As of December 31, 2019, we had approximately $12 million accrued (in other accrued liabilities in our consolidated balance sheet) related to other contingent matters including, but not limited to, a number of examinations by taxing authorities on non-income matters and indemnifications that we periodically enter into as part of the divestiture of assets or businesses. These arrangements include, but are not limited to, indemnifications for income taxes, the resolution of existing disputes and other contingent matters. In addition, the decline in commodity prices has created an environment where there is an increased risk that owners and/or operators of assets previously purchased from us may no longer be able to satisfy plugging and abandonment obligations that attach to such assets. In that event, under various laws or regulations, we could be required to assume all, or a portion of the plugging or abandonment obligations on assets we no longer own or operate.

Lease Obligations

In the first quarter of 2019, we adopted ASU No. 2016-02, Leases on a modified retrospective basis, allowing us to account for leases entered into before adoption under prior ASC 840 guidance. The adoption did not have a material impact on our consolidated financial statements, nor did the adoption result in a cumulative-effect adjustment to retained earnings. In addition, we made certain permitted elections upon adoption, the most significant of which were (i) exempting short-term leases (i.e., leases with an initial term of less than 12 months) from balance sheet recognition, (ii) maintaining existing accounting treatment for existing or expired land easements not previously accounted for as leases under prior guidance and (iii) accounting for lease and non-lease components in a contract as a single lease component when not readily determinable.

Our noncancellable leases classified as finance leases for accounting purposes include certain compressors under long-term arrangements which were capitalized upon commencement of the lease term at the fair value of the leased asset, which was lower than the present value of the minimum lease payments. The discount rate used for our finance leases was the incremental borrowing rate adjusted so that the present value of the corresponding lease payments did not exceed the fair value of the leased asset. For the year ended December 31, 2019, interest and depreciation expense associated with our finance leases were approximately $4 million and $3 million, respectively, and related cash payments were approximately $4 million.

Our noncancellable leases classified as operating leases and capitalized upon commencement of the lease term for accounting purposes include those for office space, drilling rigs and field equipment. The discount rate used for our operating leases is either the discount rate implicit in the contract, or the applicable interest rate on a collateralized basis if not determinable. Operating lease costs for minimum lease payments are recognized as capital or expense on a straight-line basis over the lease term depending on the nature of the payment. For the year ended December 31, 2019, operating lease costs and related cash payments were approximately $11 million and $10 million, respectively. These were primarily capitalized as part of our oil and natural gas properties. Variable lease costs (amounts incurred beyond minimum lease payments such as utilities, usage, maintenance, mobilization fees, etc.) are recognized in the period incurred. For the year ended December 31, 2019, variable lease cost was approximately $3 million.
    
Short-term lease cost for the year ended December 31, 2019 was approximately $20 million, and was primarily capitalized as part of our oil and natural gas properties.

Supplemental balance sheet information related to leases was as follows:
 
 
December 31, 2019
 
 
(in millions)
Operating lease assets(1)(4)
 
$
18

Finance lease assets(2)
 
10

        Total lease assets
 
$
28

 
 
 
Operating leases(3)(4)
 
 
   Current liability
 
$
9

   Noncurrent liability
 
9

        Total operating lease liability
 
$
18

Finance leases(3)
 
 
   Current liability
 
$
2

   Noncurrent liability
 
9

        Total finance lease liability
 
$
11

 
 
 
Weighted average remaining lease term
 
 
   Operating leases
 
3 years

   Finance leases
 
4 years

Weighted average discount rate
 
 
   Operating leases
 
9.06
%
   Finance leases
 
26.53
%
 
(1)
Operating lease assets are reflected in Operating lease assets and other in our consolidated balance sheet as of December 31, 2019.
(2)
Finance lease assets are reflected in Other property, plant and equipment in our consolidated balance sheet as of December 31, 2019.
(3)
Current and noncurrent operating and finance lease liabilities are reflected in Other current liabilities and Lease obligations and other, respectively, in our consolidated balance sheet as of December 31, 2019.
(4)
Upon adoption of ASU 2016-02 effective January 1, 2019, we recognized operating leases of approximately $10 million. For the year ended December 31, 2019, we also recorded an additional $16 million of operating leases.

Future minimum annual rental commitments under non-cancelable future operating and finance lease commitments at December 31, 2019, were as follows:
Year Ending December 31,
 
Operating Leases
 
Finance Leases
 
 
(in millions)
2020
 
$
10

 
$
5

2021
 
3

 
5

2022
 
2

 
5

2023
 
2

 
2

Thereafter
 
4

 

Total
 
$
21

 
$
17

Less: imputed interest
 
(3
)
 
(6
)
   Present value of operating and finance lease obligations
 
$
18

 
$
11


Rental expense for the year ended December 31, 2018 was $7 million.
Other Commercial Commitments
At December 31, 2019, we have various commercial commitments totaling $134 million primarily related to commitments and contracts associated with volume and transportation, completion activities and seismic activities. Our annual obligations under these arrangements are $44 million in 2020, $35 million in 2021, $27 million in 2022, $9 million in 2023, and $19 million thereafter.