Construction Contracts (Tables)
12 Months Ended
Dec. 31, 2024
Contractors [Abstract]  
Schedule of Balances and Changes of Construction Contracts
The following table summarizes the changes to the balances in the Company’s construction contract costs and estimated earnings in excess of billings account and the billings in excess of construction contract costs and estimated earnings account for the years ended December 31, 2024 and 2023 (in thousands):
Year ended December 31, 2024Year ended December 31, 2023
Construction contract costs and estimated earnings in excess of billingsBillings in excess of construction contract costs and estimated earningsConstruction contract costs and estimated earnings in excess of billingsBillings in excess of construction contract costs and estimated earnings
Beginning balance$104 $21,414 $342 $17,515 
Revenue recognized that was included in the balance at the beginning of the period— (21,414)— (17,515)
Increases due to new billings, excluding amounts recognized as revenue during the period— 8,722 — 23,309 
Transferred to receivables(105)— (394)— 
Construction contract costs and estimated earnings not billed during the period— 104 — 
Changes due to cumulative catch-up adjustment arising from changes in the estimate of the stage of completion(2,851)52 (1,895)
Ending balance$$5,871 $104 $21,414 
The Company's balances and changes in construction contract price allocated to unsatisfied performance obligations (backlog) for each of the three years ended December 31, 2024, 2023 and 2022 were as follows (in thousands):
 Years Ended December 31, 
 202420232022
Beginning backlog$472,170 $665,564 $215,518 
New contracts/change orders85,883 221,474 685,754 
Work performed(434,269)(414,868)(235,708)
Ending backlog$123,784 $472,170 $665,564 
Schedule of Net Position of Uncompleted Construction Contracts
The Company’s net position on uncompleted construction contracts comprised the following as of December 31, 2024 and 2023 (in thousands):
 
 December 31, 
 20242023
Costs incurred on uncompleted construction contracts$1,006,508 $718,571 
Estimated earnings37,250 26,089 
Billings(1,049,623)(765,970)
Net position$(5,865)$(21,310)
Construction contract costs and estimated earnings in excess of billings$$104 
Billings in excess of construction contract costs and estimated earnings(5,871)(21,414)
Net position$(5,865)$(21,310)