XML 25 R15.htm IDEA: XBRL DOCUMENT v3.23.1
Construction Contracts
3 Months Ended
Mar. 31, 2023
Contractors [Abstract]  
Construction Contracts Construction Contracts
Construction contract costs and estimated earnings in excess of billings represent reimbursable costs and amounts earned under contracts in progress as of the balance sheet date. Such amounts become billable according to contract terms, which usually consider the passage of time, achievement of certain milestones, or completion of the project. The Company expects to bill and collect substantially all construction contract costs and estimated earnings in excess of billings as of March 31, 2023 during the next 12 to 24 months.  
 
Billings in excess of construction contract costs and estimated earnings represent billings or collections on contracts made in advance of revenue recognized.

The following table summarizes the changes to the balances in the Company’s construction contract costs and estimated earnings in excess of billings account and the billings in excess of construction contract costs and estimated earnings account for the three months ended March 31, 2023 and 2022 (in thousands):
Three Months Ended 
March 31, 2023
Three Months Ended 
March 31, 2022
Construction contract costs and estimated earnings in excess of billingsBillings in excess of construction contract costs and estimated earningsConstruction contract costs and estimated earnings in excess of billingsBillings in excess of construction contract costs and estimated earnings
Beginning balance$342 $17,515 $243 $4,881 
Revenue recognized that was included in the balance at the beginning of the period— (17,515)— (4,881)
Increases due to new billings, excluding amounts recognized as revenue during the period— 17,150 — 15,055 
Transferred to receivables(347)— (266)— 
Construction contract costs and estimated earnings not billed during the period1,206 — 121 — 
Changes due to cumulative catch-up adjustment arising from changes in the estimate of the stage of completion(414)23 (1)
Ending balance$1,206 $16,736 $121 $15,054 

The Company defers pre-contract costs when such costs are directly associated with specific anticipated contracts and their recovery is probable. Pre-contract costs of $1.4 million and $1.3 million were deferred as of March 31, 2023 and December 31, 2022, respectively. Amortization of pre-contract costs for the three months ended March 31, 2023 and 2022 was $0.3 million and $0.1 million, respectively.
 
Construction receivables and payables include retentions, which are amounts that are generally withheld until the completion of the contract or the satisfaction of certain restrictive conditions such as fulfillment guarantees. As of March 31, 2023 and December 31, 2022, construction receivables included retentions of $17.5 million and $8.3 million, respectively. The Company expects to collect substantially all construction receivables outstanding as of March 31, 2023 during the next 12 to 24 months. As of March 31, 2023 and December 31, 2022, construction payables included retentions of $28.5 million and $24.7 million, respectively. The Company expects to pay substantially all construction payables outstanding as of March 31, 2023 during the next 12 to 24 months.
The Company’s net position on uncompleted construction contracts comprised the following as of March 31, 2023 and December 31, 2022 (in thousands):
 March 31, 2023December 31, 2022
Costs incurred on uncompleted construction contracts$400,028 $571,465 
Estimated earnings14,280 22,162 
Billings(429,838)(610,800)
Net position$(15,530)$(17,173)
Construction contract costs and estimated earnings in excess of billings$1,206 $342 
Billings in excess of construction contract costs and estimated earnings(16,736)(17,515)
Net position$(15,530)$(17,173)
The above table reflects the net effect of projects closed as of March 31, 2023 and December 31, 2022, respectively.

The Company’s balances and changes in construction contract price allocated to unsatisfied performance obligations (backlog) as of March 31, 2023 and 2022 were as follows (in thousands):
 Three Months Ended March 31,
 20232022
Beginning backlog$665,564 $215,518 
New contracts/change orders70,792 228,603 
Work performed(84,516)(24,682)
Ending backlog$651,840 $419,439 

The Company expects to complete a majority of the uncompleted contracts in place as of March 31, 2023 during the next 12 to 24 months.