Commitments and Contingencies Commitments and Contingencies
 
Legal Proceedings
 
The Company is from time to time involved in various disputes, lawsuits, warranty claims, environmental and other matters arising in the ordinary course of its business. Management makes assumptions and estimates concerning the likelihood and amount of any potential loss relating to these matters.
 
The Company currently is a party to various legal proceedings, none of which management expects will have a material adverse effect on the Company’s financial position, results of operations, or liquidity. Management accrues a liability for litigation if an unfavorable outcome is determined to be probable and the amount of loss can be reasonably estimated. If an unfavorable outcome is determined by management to be probable and a range of loss can be reasonably estimated, management accrues the best estimate within the range; however, if no amount within the range is a better estimate than any other, the minimum amount within the range is accrued. Legal fees related to litigation are expensed as incurred. Management does not believe that the ultimate outcome of these matters, either individually or in the aggregate, could have a material adverse effect on the Company’s financial position or results of operations; however, litigation is subject to inherent uncertainties.

Under the Company’s leases, tenants are typically obligated to indemnify the Company from and against all liabilities, costs, and expenses imposed upon or asserted against it as owner of the properties due to certain matters relating to the operation of the properties by the tenant.
 
Guarantees

In connection with the Company's mezzanine lending activities and equity method investments, the Company has made guarantees to pay portions of certain senior loans of third parties associated with the development projects. The following table summarizes the outstanding guarantees made by the Company as of December 31, 2022 (in thousands):
Development projectPayment guarantee amountGuarantee liability
Interlock Commercial$37,450 $701 
Harbor Point Parcel 4 (a)
32,910 198 
Total$70,360 $899 
_______________________________________
(a) As of December 31, 2022, no amounts have been funded on this senior loan.


Commitments
 
The Company has a bonding line of credit for its general contracting construction business and is contingently liable under performance and payment bonds, bonds for cancellation of mechanics liens, and defect bonds. Such bonds collectively totaled $8.5 million and $2.1 million as of December 31, 2022 and 2021, respectively. In addition, during the year ended December 31, 2019, the Company issued a letter of credit for $9.5 million to secure certain performances of the Company's subsidiary construction company under a related party project, which was still in effect at December 31, 2022.

On January 7, 2021, the Operating Partnership entered into a $15.0 million standby letter of credit using the available capacity under the credit facility to guarantee the funding of its investment in the Harbor Point Parcel 3 joint venture, which is the developer of T. Rowe Price's new global headquarters. This letter of credit was available for draw down
on the revolving credit facility in the event the Company did not meet its equity requirement. The letter of credit expired on January 4, 2022 and was not required to be renewed.
 
Unfunded Loan Commitments

The Company has certain commitments related to its notes receivable investments that it may be required to fund in the future. The Company is generally obligated to fund these commitments at the request of the borrower or upon the occurrence of events outside of the Company's direct control. As of December 31, 2022, the Company had three notes receivable with a total of $18.2 million of unfunded commitments. If commitments are funded in the future, interest will be charged at rates consistent with the existing investments. As of December 31, 2022, the Company has recorded a $0.3 million CECL allowance that relates to the unfunded commitments, which was recorded as a liability in Other liabilities in the consolidated balance sheet. See Note 6 for more information.

The Operating Partnership has entered into standby letters of credit related to the guarantee of future performance on certain of the Company’s construction contracts. Letters of credit generally are available for draw down in the event the Company does not perform. As of both December 31, 2022 and 2021, the Operating Partnership had outstanding letters of credit totaling $9.5 million, as noted above.  

Concentrations of Credit Risk
 
The majority of the Company’s properties are located in Hampton Roads, Virginia. For the years ended December 31, 2022, 2021, and 2020, rental revenues from Hampton Roads properties represented 38%, 40% and 44%, respectively, of the Company’s rental revenues. Many of the Company’s Hampton Roads properties are located in the Town Center of Virginia Beach. For the years ended December 31, 2022, 2021, and 2020, rental revenues from Town Center properties represented 25%, 26% and 27%, respectively, of the Company’s rental revenues.

The Company also has a concentration of properties at Harbor Point in Baltimore, Maryland. For the years ended December 31, 2022, 2021, and 2020, rental revenues from Harbor Point properties represented 26%, 14% and 14%, respectively, of the Company's rental revenues.
 
A group of three construction customers comprised 89%, 58%, and 65% of the Company’s general contracting and real estate services revenues for the years ended December 31, 2022, 2021, and 2020, respectively.