Construction Contracts
12 Months Ended
Dec. 31, 2021
Contractors [Abstract]  
Construction Contracts Construction Contracts
 
Construction contract costs and estimated earnings in excess of billings represent reimbursable costs and amounts earned under contracts in progress as of the balance sheet date. Such amounts become billable according to contract terms, which usually consider the passage of time, achievement of certain milestones, or completion of the project. The Company expects to bill and collect substantially all construction contract costs and estimated earnings in excess of billings as of December 31, 2021 during the year ending December 31, 2022.  

Billings in excess of construction contract costs and estimated earnings represent billings or collections on contracts made in advance of revenue recognized.
The following table summarizes the changes to the balances in the Company’s construction contract costs and estimated earnings in excess of billings account and the billings in excess of construction contract costs and estimated earnings account for the year ended December 31, 2021 and 2020 (in thousands):
Year ended December 31, 2021Year ended December 31, 2020
Construction contract costs and estimated earnings in excess of billingsBillings in excess of construction contract costs and estimated earningsConstruction contract costs and estimated earnings in excess of billingsBillings in excess of construction contract costs and estimated earnings
Beginning balance$138 $6,088 $249 $5,306 
Revenue recognized that was included in the balance at the beginning of the period— (6,088)— (5,306)
Increases due to new billings, excluding amounts recognized as revenue during the period— 6,237 — 6,244 
Transferred to receivables(714)— (545)— 
Construction contract costs and estimated earnings not billed during the period243 — 138 — 
Changes due to cumulative catch-up adjustment arising from changes in the estimate of the stage of completion576 (1,356)296 (156)
Ending balance$243 $4,881 $138 $6,088 

The Company defers pre-contract costs when such costs are directly associated with specific anticipated contracts and their recovery is probable. Pre-contract costs of $2.2 million and $1.7 million were deferred as of December 31, 2021 and 2020, respectively. Amortization of pre-contract costs for the years ended December 31, 2021 and 2020 was $0.3 million and $0.8 million, respectively.
 
Construction receivables and payables include retentions, which are amounts that are generally withheld until the completion of the contract or the satisfaction of certain restrictive conditions such as fulfillment guarantees. As of December 31, 2021 and 2020, construction receivables included retentions of $3.1 million and $17.1 million, respectively. The Company expects to collect substantially all construction receivables as of December 31, 2021 during the year ending December 31, 2022. As of December 31, 2021 and 2020, construction payables included retentions of $4.2 million and $17.7 million, respectively. The Company expects to pay substantially all construction payables as of December 31, 2021 during the year ending December 31, 2022.

The Company’s net position on uncompleted construction contracts comprised the following as of December 31, 2021 and 2020 (in thousands):
 
 December 31, 
 20212020
Costs incurred on uncompleted construction contracts$379,993 $461,725 
Estimated earnings15,115 13,205 
Billings(399,746)(480,880)
Net position$(4,638)$(5,950)
Construction contract costs and estimated earnings in excess of billings$243 $138 
Billings in excess of construction contract costs and estimated earnings(4,881)(6,088)
Net position$(4,638)$(5,950)
 
The Company's balances and changes in construction contract price allocated to unsatisfied performance obligations (backlog) for each of the three years ended December 31, 2021, 2020 and 2019 were as follows (in thousands):
 Years Ended December 31, 
 202120202019
Beginning backlog$71,258 $242,622 $165,863 
New contracts/change orders236,077 45,882 182,495 
Work performed(91,816)(217,246)(105,736)
Ending backlog$215,519 $71,258 $242,622 
The Company expects to complete a majority of the uncompleted contracts as of December 31, 2021 during the next 12 to 18 months.