Construction Contracts - Summary of Backlog (Details) - USD ($)
$ in Thousands
3 Months Ended
Mar. 31, 2020
Mar. 31, 2019
Revenue, Remaining Performance Obligation [Roll Forward]    
Beginning backlog $ 242,622 $ 165,863
New contracts/change orders 40,440 12,019
Work performed (47,420) (17,011)
Ending backlog $ 235,642 $ 160,871
Minimum | Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction, Start Date [Axis]: 2020-04-01    
Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction [Line Items]    
Expected completion of contracts 12 months  
Maximum | Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction, Start Date [Axis]: 2020-04-01    
Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction [Line Items]    
Expected completion of contracts 18 months