Construction Contracts (Summary of Backlog) (Details) - USD ($)
$ in Thousands
12 Months Ended
Dec. 31, 2018
Dec. 31, 2017
Dec. 31, 2016
Revenue, Remaining Performance Obligation [Roll Forward]      
Beginning backlog $ 49,167 $ 217,718 $ 83,433
New contracts/change orders 192,852 25,224 293,115
Work performed (76,156) (193,775) (158,830)
Ending backlog $ 165,863 $ 49,167 $ 217,718
Minimum | Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction, Start Date [Axis]: 2019-01-01      
Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction [Line Items]      
Expected completion of contracts 12 months    
Maximum | Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction, Start Date [Axis]: 2019-01-01      
Revenue, Remaining Performance Obligation, Expected Timing of Satisfaction [Line Items]      
Expected completion of contracts 18 months