XML 24 R13.htm IDEA: XBRL DOCUMENT v3.10.0.1
Construction Contracts
6 Months Ended
Jun. 30, 2018
Contractors [Abstract]  
Construction Contracts
Construction Contracts

Construction contract costs and estimated earnings in excess of billings represent reimbursable costs and amounts earned under contracts in progress as of the balance sheet date. Such amounts become billable according to contract terms, which usually consider the passage of time, achievement of certain milestones or completion of the project. The Company expects to bill and collect substantially all construction contract costs and estimated earnings in excess of billings as of June 30, 2018 during the next twelve months.  
 
Billings in excess of construction contract costs and estimated earnings represent billings or collections on contracts made in advance of revenue recognized.

The following table summarizes the changes to the balances in the Company’s construction contract costs and estimated earnings in excess of billings account and the billings in excess of construction contract costs and estimated earnings account for the six months ended June 30, 2018 (in thousands):

 
 
Construction contract costs and estimated earnings in excess of billings
 
Billings in excess of construction contract costs and estimated earnings
Balance as of January 1, 2018
 
$
245

 
$
3,591

Revenue recognized that was included in the balance at the beginning of the period
 

 
(3,591
)
Increases due to new billings, excluding amounts recognized as revenue during the period
 

 
1,898

Transferred to receivables
 
(245
)
 

Construction contract costs and estimated earnings not billed during the period
 
1,287

 

Changes due to cumulative catch-up adjustment arising from changes in the estimate of the stage of completion
 

 
(187
)
Balance as of June 30, 2018
 
$
1,287

 
$
1,711



The Company defers pre-contract costs when such costs are directly associated with specific anticipated contracts and their recovery is probable. Pre-contract costs of $0.5 million and $0.6 million were deferred as of June 30, 2018 and December 31, 2017, respectively.
 
Construction receivables and payables include retentions, amounts that are generally withheld until the completion of the contract or the satisfaction of certain restrictive conditions such as fulfillment guarantees. As of June 30, 2018 and December 31, 2017, construction receivables included retentions of $8.9 million and $9.9 million, respectively. The Company expects to collect substantially all construction receivables as of June 30, 2018 during the next twelve months. As of June 30, 2018 and December 31, 2017, construction payables included retentions of $17.4 million and $17.4 million, respectively. The Company expects to pay substantially all construction payables as of June 30, 2018 during the next twelve months.

The Company’s net position on uncompleted construction contracts comprised the following as of June 30, 2018 and December 31, 2017 (in thousands):

 
June 30,
2018
 
December 31,
2017
Costs incurred on uncompleted construction contracts
$
562,879

 
$
520,368

Estimated earnings
19,222

 
18,070

Billings
(582,525
)
 
(541,784
)
Net position
$
(424
)
 
$
(3,346
)

 
June 30,
2018
 
December 31,
2017
Construction contract costs and estimated earnings in excess of billings
$
1,287

 
$
245

Billings in excess of construction contract costs and estimated earnings
(1,711
)
 
(3,591
)
Net position
$
(424
)
 
$
(3,346
)


The Company’s balances and changes in construction contract price allocated to unsatisfied performance obligations (backlog) as of June 30, 2018 and December 31, 2017 were as follows (in thousands):

 
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
 
2018
 
2017
 
2018
 
2017
Beginning backlog
 
$
30,733

 
$
157,722

 
$
49,167

 
$
217,718

New contracts/change orders
 
27,807

 
15,519

 
32,376

 
18,960

Work performed
 
(20,619
)
 
(56,584
)
 
(43,622
)
 
(120,021
)
Ending backlog
 
$
37,921

 
$
116,657

 
$
37,921

 
$
116,657



The Company expects to complete a majority of the uncompleted contracts as of June 30, 2018 during the next 12 to 18 months.