As of March 31, 2020, the Company had outstanding letters of credit of $10.6 million as security for obligations under the terms of its lessee agreements.

The Company has entered into non-cancellable contracted commitments for construction of data center facilities and acquisition of equipment. As of March 31, 2020, these commitments were approximately $196.7 million and are expected to be incurred over the next one to two years. In addition, the Company has entered into equipment and electricity power contracts, which require minimum purchase commitments for power. These agreements range from one to two years and provide for payments for early
termination or require minimum payments for the remaining term. As of March 31, 2020, the minimum commitments for these arrangements were approximately $85.2 million.

The Company has entered into an Agreement to Lease contract that requires the Company to enter into a lease upon shell completion of a building in London, UK totaling 70,000 square feet with annual rent totaling £1.4 million for initial lease terms of 20 years. We expect construction of the shell building to be completed in 2020.

During the normal course of business, the Company and its subsidiaries have made certain indemnities and commitments to customers, vendors and associated parties related to the use, protection and security of intellectual property and claims for negligence or willful misconduct. Further, customer contracts generally require specified levels of performance related to uninterrupted service and cooling temperatures. Also, in the normal course of our business, the Company is involved in legal, tax and regulatory proceedings arising from the conduct of its business activities. Management assesses the probability that these performance standards, credits, claims or indemnities have been incurred and liabilities or asset reserves are established for loss contingencies when the losses associated are deemed to be probable and the loss can be reasonably estimated. Based on information currently available, the Company believes that the outcome of such matters will not, individually or in the aggregate, have a material effect on its condensed consolidated financial statements.