Commitments and Contingencies Disclosure [Text Block] Commitments and Contingencies

MPLX is the subject of, or a party to, a number of pending or threatened legal actions, contingencies and commitments involving a variety of matters, including laws and regulations relating to the environment. Some of these matters are discussed below. For matters for which MPLX has not recorded an accrued liability, MPLX is unable to estimate a range of possible losses because the issues involved have not been fully developed through pleadings, discovery or court proceedings. However, the ultimate resolution of some of these contingencies could, individually or in the aggregate, be material.

Environmental Matters – MPLX is subject to federal, state and local laws and regulations relating to the environment. These laws generally provide for control of pollutants released into the environment and require responsible parties to undertake remediation of hazardous waste disposal sites. Penalties may be imposed for non-compliance.

At March 31, 2020 and December 31, 2019, accrued liabilities for remediation totaled $17 million and $19 million, respectively. However, it is not presently possible to estimate the ultimate amount of all remediation costs that might be incurred or the penalties, if any, which may be imposed. At March 31, 2020 and December 31, 2019, there were no balances with MPC for indemnification of environmental costs.

MPLX is involved in environmental enforcement matters arising in the ordinary course of business. While the outcome and impact to MPLX cannot be predicted with certainty, management believes the resolution of these environmental matters will not, individually or collectively, have a material adverse effect on its consolidated results of operations, financial position or cash flows.

MPLX is also a party to a number of other lawsuits and other proceedings arising in the ordinary course of business. While the ultimate outcome and impact to MPLX cannot be predicted with certainty, management believes the resolution of these lawsuits and proceedings will not, individually or collectively, have a material adverse effect on its consolidated results of operations, financial position or cash flows.

Guarantees – Over the years, MPLX has sold various assets in the normal course of its business. Certain of the related agreements contain performance and general guarantees, including guarantees regarding inaccuracies in representations, warranties, covenants and agreements, and environmental and general indemnifications that require MPLX to perform upon the occurrence of a triggering event or condition. These guarantees and indemnifications are part of the normal course of selling assets. MPLX is typically not able to calculate the maximum potential amount of future payments that could be made under such contractual provisions because of the variability inherent in the guarantees and indemnities. Most often, the nature of the guarantees and indemnities is such that there is no appropriate method for quantifying the exposure because the underlying triggering event has little or no past experience upon which a reasonable prediction of the outcome can be based.

In connection with our 9.19 percent indirect interest in a joint venture that owns and operates the Dakota Access Pipeline and Energy Transfer Crude Oil Pipeline projects, collectively referred to as the Bakken Pipeline system, we have entered into a Contingent Equity Contribution Agreement whereby MPLX LP, along with the other joint venture owners in the Bakken Pipeline system, have agreed to make equity contributions to the joint venture upon certain events occurring to allow the entities that own and operate the Bakken Pipeline system to satisfy their senior note payment obligations. The senior notes were issued to repay amounts owed by the pipeline companies to fund the cost of construction of the Bakken Pipeline system.

In March 2020, the U.S. District Court for the District of Columbia ordered the U.S. Army Corps of Engineers, which granted permits for the Bakken Pipeline system, to conduct a full environmental impact statement (“EIS”), and further requested briefing on whether an easement permit necessary for the operation of the Bakken Pipeline system should be vacated while the EIS is being prepared. If the permit is vacated pending completion of the EIS and the vacatur is deemed temporary, MPLX would have to contribute its 9.19 percent pro rata share of funds required to pay interest accruing on the notes while the pipeline is shutdown and its 9.19 percent pro rata share of any costs to remediate any deficiencies to reinstate the permit and/or return the pipeline into operation. If the court vacates the permit and such action results in a permanent shutdown of the pipeline, MPLX would have to contribute its 9.19 percent pro rata share of the cost to redeem the bonds (including the 1% redemption premium required pursuant to the indenture governing the notes) and any accrued and unpaid interest, if any. As of March 31, 2020, our maximum potential undiscounted payments under the Contingent Equity Contribution Agreement were approximately $230 million.

Contractual Commitments and Contingencies – At March 31, 2020, MPLX’s contractual commitments to acquire property, plant and equipment totaled $318 million. These commitments were primarily related to G&P plant expansion, terminal and pipeline projects. In addition, from time to time and in the ordinary course of business, MPLX and its affiliates provide guarantees of MPLX’s subsidiaries payment and performance obligations in the G&P segment. Certain natural gas processing and gathering arrangements require MPLX to construct new natural gas processing plants, natural gas gathering pipelines and NGL pipelines and contain certain fees and charges if specified construction milestones are not achieved for reasons other than force majeure. In certain cases, certain producers may have the right to cancel the processing arrangements if there are significant delays that are not due to force majeure. As of March 31, 2020, management does not believe there are any indications that MPLX will not be able to meet the construction milestones, that force majeure does not apply or that such fees and charges will otherwise be triggered.