XML 32 R10.htm IDEA: XBRL DOCUMENT v3.19.3
Mineral properties and development costs
9 Months Ended
Aug. 31, 2019
Mineral properties and development costs  
Mineral properties and development costs

4Mineral properties and development costs

 

 

 

 

 

 

 

 

 

 

in thousands of dollars

 

    

November 30, 2018

 

Acquisition costs

 

August 31, 2019

 

    

$

    

$

    

$

Alaska, USA

 

 

 

  

 

 

Ambler (a)

 

26,587

 

 —

 

26,587

Bornite (b)

 

4,000

 

 —

 

4,000

 

 

30,587

 

 —

 

30,587

 

 

 

 

 

 

 

 

 

 

in thousands of dollars

 

    

November 30, 2017

 

Acquisition costs

 

November 30, 2018

 

    

$

    

$

    

$

Alaska, USA

 

 

 

  

 

 

Ambler (a)

 

26,587

 

 —

 

26,587

Bornite (b)

 

4,000

 

 —

 

4,000

 

 

30,587

 

 —

 

30,587

 

(a)Ambler

On January 11, 2010, NovaGold Resources Inc. (“NovaGold”), through Alaska Gold Company (“AGC”), at the time a wholly-owned NovaGold subsidiary, purchased 100% of the Ambler lands in Northwest Alaska, which contains the copper-zinc-lead-gold-silver Arctic Project and other mineralized targets within the volcanogenic massive sulfide belt, through a series of cash and share payments. Total fair value of the consideration was $26.6 million. The vendor retained a 1% net smelter return royalty that the Company can purchase at any time for a one-time payment of $10.0 million.

The Ambler lands were acquired on October 17, 2011 by Trilogy Metals US through a purchase and sale agreement with AGC. On October 24, 2011, NovaGold transferred its ownership of Trilogy Metals US to the Company, then itself a wholly owned subsidiary of NovaGold, which was subsequently spun-out to NovaGold shareholders and publicly listed on April 30, 2012 (“NovaGold Arrangement”).

(b)Bornite

On October 19, 2011, Trilogy Metals US acquired the exclusive right to explore and the non-exclusive right to access and enter on the Bornite lands, and lands deeded to NANA Regional Corporation, Inc. (“NANA”) through the Alaska Native Claims Settlement Act, located adjacent to the Ambler lands in Northwest Alaska. As consideration, Trilogy Metals US paid $4 million to acquire the right to explore and develop the combined Upper Kobuk Mineral Projects through an Exploration Agreement and Option to Lease with NANA. Upon a decision to proceed with construction of a mine on the lands, NANA maintains the right to purchase between a 16%‑25% ownership interest in the mine or retain a 15% net proceeds royalty which is payable after Trilogy Metals US has recovered certain historical costs, including capital and cost of capital. Should NANA elect to purchase an ownership interest, consideration will be payable equal to all historical costs incurred on the properties at the elected percentage purchased less $40 million, not to be less than zero. The parties would form a joint venture and be responsible for all future costs, including capital costs of the mine based on their pro-rata share.

NANA would also be granted a net smelter return royalty of between 1% and 2.5% upon the execution of a mining lease or a surface use agreement, the amount of which is determined by the classification of land from which production originates.

(c)Option Agreement

On April 10, 2017, Trilogy and Trilogy Metals US entered into an Option Agreement to form a Joint Venture with South32 Group Operations Pty Ltd., a wholly-owned subsidiary of South32 Limited, which agreement was later assigned by South32 Operations to its affiliate, South32 USA Exploration Inc. (“South32”) on the UKMP (“Option Agreement”). Under the terms of the Option Agreement, as amended, Trilogy Metals US granted South32 the right to form a 50/50 joint venture to hold all of Trilogy Metals US’ Alaskan assets. Upon exercise of the option, Trilogy Metals US will transfer its Alaskan assets, including the UKMP, and South32 will contribute a minimum of $150 million, to a newly formed and jointly held, limited liability company (“LLC”).

To maintain the option in good standing, South32 is required to fund a minimum of $10 million per year for up to a three-year period, which funds will be used to execute a mutually agreed upon program at the UKMP. The funds provided by South32 may only be expended in accordance with an approved program by a technical committee with equal representation from Trilogy and South32. South32 may exercise its option at any time over the three-year period to enter into the 50/50 joint venture. To subscribe for 50% of the JV, South32 must contribute a minimum of $150 million, plus (i) any amounts Trilogy spends on matched parallel funding to a maximum of $16 million over the three year period and (ii) $5 million if the option had been exercised between April 1, 2018 and March 31, 2019 or $10 million if the option is exercised between April 1, 2019 and the expiration date of the option, less the amount of the initial funding contributed by South32 (the “Subscription Price”). South32 has now funded the full three-year option period. South32 has until the end of January 2020 to exercise the option to form the JV LLC and make the subscription payment. Should South32 not make its annual minimum payment or elect to withdraw, the option will lapse and South32 will have no claim to property ownership or to the funds already spent.

During the year ended November 30, 2017, the Company received the first payment of $10.0 million and these funds were expended on the year 1 program at the Bornite Project. In October 2017, the Company received $0.4 million as a first instalment towards the year 2 program and budget to begin preparatory work. During the year ended November 30, 2018, the Company received payments totaling $10.4 million following the approval of the year 2 program and budget in January 2018, including a $0.80 million advance on South32’s year three funding obligation per the Option Agreement. During the quarter ended February 28, 2019, the Company received payments totaling $10.2 million following the approval of the year 3 program and budget, including an additional $1 million of funding for the approved regional exploration program. The receipt of the year 3 funding represents receipt of the final tranche of funding from South32. The Company is responsible for the disbursement of these funds in accordance with the approved program and budget and accordingly has not classified the funds as restricted cash.

As the initial option payments are credited against the future subscription price upon exercise, the Company has accounted for the payments received from South32 as deferred consideration for the purchase of the UKMP interest. At such time as the option is exercised, the $31.0 million of payments received will be recognized as part of the consideration received for the Company’s contribution of the UKMP into JV LLC. If South32 withdraws from the Option Agreement, the consideration will be recognized as income in the statement of loss at that time.

The option to form the JV LLC is recognized as a financial instrument at inception of the arrangement with an initial fair value of $nil. This option is required to be re-measured at fair value at each reporting date with any changes in fair value recorded in loss for the period. The Company determined that the fair value of the option remains $nil as at August 31, 2019.

(d)Mineral properties expense

The following table summarizes mineral properties expense for the noted periods.

 

 

 

 

 

 

 

 

 

 

 

 

In thousands of dollars

 

    

Three months ended

    

Three months ended

    

Nine months ended

    

Nine months ended

 

 

August 31, 2019

 

August 31, 2018

 

August 31, 2019

 

August 31, 2018

 

    

$

    

$

    

$

    

$

Alaska, USA

 

 

 

 

 

 

 

 

Community

 

164

 

81

 

428

 

324

Drilling

 

4,760

 

3,624

 

4,933

 

3,804

Engineering

 

663

 

245

 

1,287

 

750

Environmental

 

153

 

313

 

424

 

482

Geochemistry and geophysics

 

252

 

420

 

1,010

 

1,066

Land and permitting

 

163

 

145

 

523

 

504

Project support

 

3,062

 

2,703

 

4,066

 

3,381

Other income

 

 —

 

 —

 

(1)

 

(20)

Wages and benefits

 

1,734

 

1,520

 

2,722

 

2,366

Mineral property expense

 

10,951

 

9,051

 

15,392

 

12,657

 

Mineral property expenses consist of direct drilling, personnel, community, resource reporting and other exploration expenses as outlined above, as well as indirect project support expenses such as fixed wing charters, helicopter support, fuel, and other camp operation costs. Cumulative mineral properties expense in Alaska from the initial earn-in agreement on the property in 2004 to August 31, 2019 is $110.0 million and cumulative acquisition costs are $30.6 million totaling $140.6 million spent to date.