EX-96.1 2 tm231507d1_ex96-1.htm EXHIBIT 96.1

 

 

 

 

 

Arctic Project

 

S-K 1300 Technical Report Summary

 

Ambler Mining District, Alaska

 

Report Date: November 30, 2022

 

Prepared for: Trilogy Metals Inc.

1150 – Granville Street

Vancouver, British COlumbia

Canada V7Y 1G5

 

Prepared by: Ausenco Engineering Canada Inc.

 

1050 W Pender St, Suite 1200
Vancouver, British Columbia
Canada V6E 4T3

 

 

 

 

 

 

 

 

   
   

  

Table of Contents

  

1 Executive Summary 1
  1.1 Introduction 1
  1.2 Property Description 1
    1.2.1 Mineral Tenure, Surface Rights, Water Rights, Royalties and Agreements 1
  1.3 Accessibility, Climate, Local Resources, and Infrastructure 2
  1.4 History 3
  1.5 Geological Setting, Mineralization, and Deposit 3
  1.6 Exploration 4
  1.7 Sample Preparation, Analysis and Security 4
  1.8 Data Verification 4
  1.9 Mineral Processing and Metallurgical Testing 5
  1.10 Mineral Resource Estimates 8
  1.11 Mineral Reserve Estimates 11
  1.12 Mining Methods 14
  1.13 Processing and Recovery Methods 14
  1.14 Infrastructure 15
    1.14.1 Infrastructure Requirements 15
    1.14.2 Access 16
    1.14.3 Power 16
    1.14.4 Accommodation 16
    1.14.5 Waste Rock Facility 16
    1.14.6 Overburden Stockpiles 17
    1.14.7 Tailings Management Facility 17
    1.14.8 Water Management 17
    1.14.9 Water Treatment Plant 17
  1.15 Market Studies 18
  1.16 Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups 18
    1.16.1 Permitting Considerations 18
    1.16.2 Social and Community 19
    1.16.3 Closure Planning 20
  1.17 Capital and Operating Cost Estimates 20
    1.17.1 Capital Costs 20
    1.17.2 Operating Costs 21
  1.18 Economic Analysis 21

  

  
Arctic ProjectPage i
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

  1.19 Interpretations and Conclusions 22
  1.20 Recommendations 22
    1.20.1 Mining 23
    1.20.2 Geology and Resource Models 23
    1.20.3 Open Pit Geotechnical work 24
    1.20.4 Hydrogeology 24
    1.20.5 Tailings Management Facility 24
    1.20.6 Closure 25
    1.20.7 Water Treatment 25
    1.20.8 Metallurgical testing 25
    1.20.9 Recovery methods 25
    1.20.10 Operational Readiness Plan 25
2 Introduction 27
  2.1 Introduction 27
  2.2 Terms of Reference 27
  2.3 Qualified Persons 27
  2.4 Site Visits 28
  2.5 Currency of Report 28
  2.6 Information Sources and References 28
  2.7 Previous Reports 29
  2.8 Abbreviations and Acronyms 29
3 Property Description and Location 36
  3.1 Introduction 36
  3.2 Property Ownership 37
  3.3 Mineral Tenure 37
  3.4 Royalties, Agreements and Encumbrances 42
    3.4.1 Kennecott Agreements 42
    3.4.2 NANA Agreement 42
  3.5 State Royalty 43
  3.6 Surface Rights 43
  3.7 Environmental Considerations 44
  3.8 Permits 44
  3.9 Social Considerations 44
  3.10 Comment on Property Description and Location 44
4 ACESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE and PHYSIOGRAPHY 45
  4.1 Accessibility 45
    4.1.1 Air 45
    4.1.2 Road 45
    4.1.3 Water 45
  4.2 Climate 45

 

  
Arctic ProjectPage ii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

  4.3 Local Resources and Infrastructure 46
  4.4 Physiography 46
  4.5 Comments on Accessibility, Climate, Local Resources, Infrastructure and Physiography 47
5 HISTORY 48
  5.1 Regional History 48
  5.2 Prior Ownership and Ownership Changes – Arctic Deposit and the Ambler Lands 49
  5.3 Previous Exploration and Development Results – Arctic Deposit 49
    5.3.1 Introduction 49
    5.3.2 Geochemistry 56
    5.3.3 Geophysics 56
    5.3.4 Drilling 56
    5.3.5 Specific Gravity 57
    5.3.6 Petrology, Mineralogy, and Research Studies 57
    5.3.7 Geotechnical, Hydrogeological and Acid-Base Accounting Studies 57
      5.3.7.1 Geotechnical and Hydrogeological Studies 57
      5.3.7.2 Acid-Base Accounting Studies 60
    5.3.8 Metallurgical Studies 60
    5.3.9 Historical Mineral Resource and Mineral Reserve Estimates 60
    5.3.10 Development Studies 60
6 Geological Setting, Mineralization, and Deposit 62
  6.1 Deposit Types 62
    6.1.1 Deposit Model 62
  6.2 Regional Geology – Southern Brooks Range 62
    6.2.1 Terrane Descriptions 63
    6.2.2 Regional Tectonic Setting 65
  6.3 Local Geology 65
    6.3.1 General Stratigraphy of the Ambler Sequence 67
    6.3.2 Structural Framework of the Ambler Mining District 69
      6.3.2.1 F1 Deformation 69
      6.3.2.2 F2 Deformation 70
  6.4 Arctic Property Geology 71
    6.4.1 Lithologies and Lithologic Domain Descriptions 72
      6.4.1.1 Greenstone (GNST) 73
      6.4.1.2 Chlorite Schist (ChS) 73
      6.4.1.3 Talc Schist (TS) 73
      6.4.1.4 Black to Grey Schist (GS) 73
      6.4.1.5 Button Schist (MRP) 74
      6.4.1.6 Quartz-Mica-(Feldspar) Schist (QMS/QFMS) 74
      6.4.1.7 Debris Flow (DM) 74
      6.4.1.8 Greywacke (GW) 74
      6.4.1.9 Lithogeochemistry of Immobile Trace Elements 74
      6.4.1.10 Lithologic Domains 75

 

  
Arctic ProjectPage iii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

    6.4.2 Structure 75
    6.4.3 Arctic Deposit Alteration 75
    6.4.4 Arctic Deposit Mineralization 76
  6.5 Prospects 77
7 EXPLORATION 79
  7.1 Exploration 79
    7.1.1 Grids and Surveys 81
    7.1.2 Geological Mapping 81
    7.1.3 Geochemistry 83
    7.1.4 Geophysics 83
    7.1.5 Petrology, Minerology and Research Studies 86
  7.2 Drilling 87
    7.2.1 Overview 87
    7.2.2 Drill Companies 98
    7.2.3 Drill Core Procedures 100
      7.2.3.1 BCMC/Kennecott 100
      7.2.3.2 NovaGold/Trilogy (formerly, NovaCopper)/Ambler Metals 100
    7.2.4 Geotechnical and Hydrogeological Drilling 101
    7.2.5 Collar Surveys 104
      7.2.5.1 Kennecott 104
      7.2.5.2 NovaGold/Trilogy (formerly, NovaCopper)/Ambler Metals 104
    7.2.6 Downhole Surveys 105
    7.2.7 Recovery 105
      7.2.7.1 Kennecott 105
      7.2.7.2 NovaGold/Trilogy (formerly, NovaCopper)/Ambler Metals 105
    7.2.8 Drill Intercepts 106
8 Sample Preparation, Ananlyses and Security 111
  8.1 Sample Preparation 111
    8.1.1 Core 111
      8.1.1.1 Kennecott and BCMC 111
      8.1.1.2 NovaGold/Trilogy (formerly, NovaCopper) 111
    8.1.2 Acid-Base Accounting Sampling 112
    8.1.3 Density Determinations 113

    8.1.4 Sample Security 114
    8.1.5 Assay Laboratories 114
    8.1.6 Sample Preparation and Analytical Methods 115
  8.2 Quality Assurance/Quality Control 116
    8.2.1 Database Verification 116
    8.2.2 NovaGold QA/QC Review of Historical Analytical Results 116
    8.2.3 NovaGold/Trilogy (2004 to 2019) QA/QC Results Review 120

 

  
Arctic ProjectPage iv
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

      8.2.3.1 2004 121
      8.2.3.2 2005 121
      8.2.3.3 2006 121
      8.2.3.4 2007 121
      8.2.3.5 2008 121
      8.2.3.6 2011 (analysed in 2013) 122
      8.2.3.7 2015 122
      8.2.3.8 2016 122
      8.2.3.9 2017 122
      8.2.3.10 2019 122
    8.2.4 Density Determination QA/QC 123
      8.2.4.1 Laboratory vs. Fields Determinations 123
      8.2.4.2 Stoichiometric Method 124
      8.2.4.3 Multiple Regressions Method 125
      8.2.4.4 Random Forest Machine Learning Method 126
      8.2.4.5 Comments on Density Determinations 127
    8.2.5 Acid-Base Accounting Sampling QA/QC 127
  8.3 Comments on Sample Preparation, Analyses and Security 128
9 Data Verification 129
  9.1 Comments on Data Verification 129
10 Mineral Processing and Metallurgical Testing 130
  10.1 Introduction 130
  10.2 Historical Testwork Review 132
    10.2.1 Metallurgical Testing – Kennecott Research Centre (1968 to 1976) 132
    10.2.2 Metallurgical Testwork – Lakefield (1998 to 1999) 133
  10.3 Mineralogical and Metallurgical Testwork – 2012 to 2019 134
    10.3.1 Introduction 134
    10.3.2 Test Samples 135
    10.3.3 Mineralogical Investigations 139
    10.3.4 Comminution Testwork 140
    10.3.5 Flotation Testwork 142
    10.3.6 Copper/Lead Separation Testwork 145
  10.4 Mineralogical and Metallurgical Testwork – 2021 to 2022 150
    10.4.1 Introduction 150
    10.4.2 Test Samples 151
    10.4.3 Mineralogical Investigations 157
      10.4.3.1 Talc Optimization Samples 157
      10.4.3.2 Flow Sheet Development Samples 158
      10.4.3.3 Variability Samples 160
    10.4.4 Comminution Testwork 162
    10.4.5 Flotation Testwork 164

 

  
Arctic ProjectPage v
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

   

      10.4.5.1 Talc Optimization Testwork 164
      10.4.5.2 Flowsheet Development Testwork 165
      10.4.5.3 Variability Testwork 166
      10.4.5.4 Copper/Lead Separation Testwork 169
  10.5 Comment on Mineral Processing and Metallurgical Testwork 172
11 Mineral Resource Estimates 173
  11.1 Introduction 173
  11.2 Drill Hole Database 174
  11.3 Interpretations and Geological Modelling Procedures 177
    11.3.1 Lithology Modelling 177
    11.3.2 Talc Modelling 178
    11.3.3 Mineralization Domains 179
  11.4 Exploratory Data Analysis 180
    11.4.1 Specific Gravity 180
    11.4.2 Compositing 183
    11.4.3 Grade Capping 185
    11.4.4 Spatial Analysis 185
    11.4.5 Block Model Setup 193
  11.5 Mineral Resource Estimation 193
    11.5.1 Validation 197
      11.5.1.1 Visual Inspection 197
      11.5.1.2 Statistical Validation 200
      11.5.1.3 Swath Plots 200
      11.5.1.4 Validation of Block Model with the New Drill Holes 207
    11.5.2 Mineral Resource Classification 208
    11.5.3 Uncertainties Affecting Mineral Resource Confidence Classification 210
    11.5.4 Reasonable Prospects for Economic Extraction 210
      11.5.4.1 Basis of Commodity Prices and Cost Assumptions 210
    11.5.5 Mineral Resource Statement 211
12 Mineral Reserve Estimates 213
  12.1 Introduction 213
  12.2 Basis of Commodity Prices and Cost Assumptions Used in Pit Optimization and Cut-Off Determination 213
  12.3 Pit Optimization 213
  12.4 Dilution and Ore Losses 217
  12.5 Cut-Off Definition 219
  12.6 Mineral Reserves Statement 220
  12.7 Risk Factors that Could Materially Affect the Mineral Reserve Estimates 220
13 Mining Methods 222
  13.1 Overview 222
  13.2 Mine Design 222

  

  
Arctic ProjectPage vi
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

  13.3 Interim Phase Design 227
  13.4 Waste Rock Facilities and Stockpile Designs 229
  13.5 Production Schedule 230
  13.6 Waste Material Handling 233
  13.7 Operating Schedule 233
  13.8 Mining Equipment 234
    13.8.1 Blasting 234
    13.8.2 Drilling 237
    13.8.3 Loading 240
    13.8.4 Hauling 243
    13.8.5 Support 244
    13.8.6 Auxiliary 246
    13.8.7 Labour 247
  13.9 Geotechnical and Hydrogeological Assessments 248
    13.9.1 Data Sources 249
    13.9.2 Geology and Structure 249
    13.9.3 Geotechnical Laboratory Testing 251
    13.9.4 Rock Mass Assessment 254
    13.9.5 Kinematic Stability Assessment 255
    13.9.6 Hydrogeology 255
    13.9.7 Pit Inflow 257
    13.9.8 Pore Pressure 258
    13.9.9 Stability Modelling 260
    13.9.10 Slope Design 261
  13.10 Geotechnical Review of Open Pit Design 263
    13.10.1 Slope Stability Risks 263
  13.11 Geochemistry Assessment 265
    13.11.1 Acid Base Accounting Studies 265
    13.11.2 Geochemical Kinetic Studies 265
      13.11.2.1 Waste Rock Program 265
      13.11.2.2 Tailings Program 266
      13.11.2.3 Ore Program 266
14 Processing and Recovery Methods 267
  14.1 Overview 267
  14.2 Process Flowsheet and Area Plan 267
  14.3 Process Design Criteria 271
  14.4 Plant Description 274
    14.4.1 Crushing Plant 274
    14.4.2 Coarse Ore Storage 274
    14.4.3 Grinding and Classification 274
      14.4.3.1 Primary Grinding and Classification 274

 

  
Arctic ProjectPage vii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

    14.4.4 Flotation 275
      14.4.4.1 Talc Pre-Flotation 275
      14.4.4.2 Copper – Lead Bulk Flotation and Regrinding 275
      14.4.4.3 Copper and Lead Separation Flotation Circuit 276
      14.4.4.4 Zinc Flotation and Regrind 276
    14.4.5 Product Dewatering 277
      14.4.5.1 Copper Concentrate Dewatering 277
      14.4.5.2 Lead Concentrate Dewatering 278
      14.4.5.3 Zinc Concentrate Dewatering 278
    14.4.6 Tailings Disposal 279
    14.4.7 Reagent Handling and Storage 279
      14.4.7.1 Collectors 279
      14.4.7.2 Frother 280
      14.4.7.3 Lime 280
      14.4.7.4 Flocculant 280
      14.4.7.5 Other Reagents 280
    14.4.8 Power Supply 280
    14.4.9 Water Supply 280
      14.4.9.1 Fresh Water Supply System 281
      14.4.9.2 WRCP Water Supply System 281
      14.4.9.3 Process Water Supply System 281
    14.4.10 Air Supply 281
    14.4.11 Assay/Metallurgical Laboratory and Quality Control 281
  14.5 Personnel 282
15 Infrastructure 283
  15.1 Introduction 283
  15.2 Access Roads 286
    15.2.1 Ambler Mining District Industrial Access Road 286
    15.2.2 Arctic Access Road 288
  15.3 Airstrip 290
  15.4 Camps 290
    15.4.1 Bornite Exploration Camp 290
    15.4.2 Construction Camp 290
    15.4.3 Permanent Accommodations Facility 291
  15.5 Fuel Supply, Storage and Distribution 291
  15.6 Power Generation 291
  15.7 Electrical System 292
  15.8 Surface Water Management 292
    15.8.1 Process Water Supply 295
    15.8.2 Water Management Infrastructure 295
      15.8.2.1 Diversions and Collection Channels 295

 

  
Arctic ProjectPage viii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

      15.8.2.2 Culverts 296
      15.8.2.3 Collections Ponds 297
    15.8.3 Waste Rock Collection Pond 297
    15.8.4 Process Pond 300
    15.8.5 Groundwater Management System 300
    15.8.6 Site Water and Load Balance 301
  15.9 Water Treatment Plant 301
  15.10 Tailings Management Facility 303
    15.10.1 General Description 303
    15.10.2 Design Criteria 303
    15.10.3 Overburden Geotechnical Investigation 304
    15.10.4 Site Selection 305
    15.10.5 Starter Dam 305
    15.10.6 Dam Raises and Final Dam 308
    15.10.7 TMF Water Pool and Water Return 308
    15.10.8 Tailings Delivery and Return Systems 308
  15.11 Waste Rock Facility and Overburden Stockpiles 308
    15.11.1 Waste Rock Facility 309
    15.11.2 Overburden and Topsoil Stockpiles 309
  15.12 Compressed Air Supply 309
  15.13 Site Communications 310
  15.14 Fire Protection 310
  15.15 Plant Buildings 310
    15.15.1 Truck Shop and Mine Offices 310
    15.15.2 Laboratory 311
    15.15.3 Administration Building 311
    15.15.4 Mill Dry Facility 311
    15.15.5 Plant Workshop and Warehouse 311
    15.15.6 Primary Crushing 311
    15.15.7 Crushed Ore Stockpile 311
    15.15.8 Process Plant 311
    15.15.9 Concentrate Loadout 312
    15.15.10 Reagent Storage and Handling 312
    15.15.11 Water Supply 312
  15.16 Concentrate Transportation 312
16 Market Studies 314
  16.1 Introduction 314
  16.2 Metal Prices 314
  16.3 Markets and Contracts 317
    16.3.1 Chinese Import Restrictions 318
    16.3.2 Copper Concentrate 318

 

  
Arctic ProjectPage ix
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

    16.3.3 Zinc Concentrate 318
    16.3.4 Lead Concentrate 319
  16.4 Smelter Term Assumptions 320
    16.4.1 Copper 321
    16.4.2 Zinc 321
    16.4.3 Lead 321
  16.5 Transportation and Logistics 322
  16.6 Insurance 322
  16.7 Representation and Marketing 322
  16.8 Comments on Market Studies and Contracts 322
17 Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups 323
  17.1 Environmental Studies 323
    17.1.1 Hydrology 323
      17.1.1.1 Recommendations 325
    17.1.2 Water Management 325
    17.1.3 Wetlands Data 326
    17.1.4 Aquatic Life Data 326
    17.1.5 Hydrogeology Data 328
    17.1.6 Cultural Resources Data 329
    17.1.7 Subsistence Data 330
    17.1.8 Endangered Species, Migratory Birds, and Bald and Golden Eagle protection 331
    17.1.9 Metal Leaching / Acid Base Accounting Data 331
  17.2 Operational Site Monitoring 332
  17.3 Mine Reclamation and Closure 332
    17.3.1 Reclamation and Closure Plan 332
    17.3.2 Closure Objectives and Closure Criteria 333
    17.3.3 Closure Activities 333
      17.3.3.1 Open Pit Workings 336
      17.3.3.2 Waste Rock Facility and Tailings Management Facility 336
      17.3.3.3 Buildings and Equipment 337
      17.3.3.4 Mine Infrastructure 337
      17.3.3.5 Landfill 338
      17.3.3.6 Water Management System 338
    17.3.4 Closure Water Treatment 338
    17.3.5 Post-Closure 339
    17.3.6 Closure Cost Estimate 339
      17.3.6.1 General 339
      17.3.6.2 Closure Water Treatment Costs 341
    17.3.7 Reclamation and Closure Financial Assurance 341
  17.4 Permitting Considerations 342

 

  
Arctic ProjectPage x
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

    17.4.1 Exploration Permits 342
    17.4.2 Major Mine Permits 342
  17.5 Social or Community Considerations 344
  17.6 Comment on Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups 345
18 Capital and Operating Costs 346
  18.1 Capital Costs 346
    18.1.1 Introduction 346
    18.1.2 Arctic Project Execution 346
    18.1.3 Work Breakdown Structure 347
    18.1.4 Estimate Summary 347
    18.1.5 Definition 349
      18.1.5.1 Definition of Costs 349
      18.1.5.2 General Methodology 349
      18.1.5.3 Basic Information 350
      18.1.5.4 Exchange Rates 350
      18.1.5.5 Market Availability 350
    18.1.6 Mining (WBS 1000) 351
      18.1.6.1 Mining Capital Cost Basis of Estimate 353
      18.1.6.2 Mining Equipment 353
      18.1.6.3 Ancillary Equipment 355
      18.1.6.4 Capital Spares 356
      18.1.6.5 Other Capital Costs 357
    18.1.7 Crushing and Process Plant (WBS 2000 & 3000) 357
    18.1.8 Tailings Management Facility (WBS 4000) 358
    18.1.9 Onsite Infrastructure (WBS 5000) 359
      18.1.9.1 Water Treatment Plant 359
      18.1.9.2 Other Onsite Infrastructure Costs 359
    18.1.10 Offsite Infrastructure (WBS 6000) 360
      18.1.10.1 Main Access Road 360
      18.1.10.2 Other Offsite Infrastructure Costs 360
    18.1.11 Indirects (WBS 7000) 360
    18.1.12 Provisions / Contingency (WBS 8000) 361
    18.1.13 Owner’s Costs (WBS 9000) 362
    18.1.14 Sustaining Capital and Closure Costs 363
  18.2 Operating Cost Estimate 364
    18.2.1 Operating Cost Summary 364
    18.2.2 Mining Operating Cost Estimate 365
      18.2.2.1 Mining Operating Cost Basis of Estimate 369
      18.2.2.2 Personnel Costs 369
      18.2.2.3 Maintenance and Repair Cost 370
      18.2.2.4 Diesel and Fuel Consumption 371

  

  
Arctic ProjectPage xi
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

      18.2.2.5 Explosives Cost 372
      18.2.2.6 Tires Cost 373
      18.2.2.7 Other Operating Costs 374
    18.2.3 Processing Operating Cost Estimate 374
      18.2.3.1 Power 375
      18.2.3.2 Consumables 375
      18.2.3.3 Maintenance Consumables 376
      18.2.3.4 Labour 376
    18.2.4 General and Administrative and Surface Services Cost Estimates 376
    18.2.5 Road Toll Cost Estimate 378
    18.2.6 Water Treatment Costs 378
19 Economic Analysis 379
  19.1 Forward-Looking Information Cautionary Statements 379
  19.2 Methodology 380
  19.3 Financial Model Parameters 380
  19.4 Economic Analysis 381
    19.4.1 Pre-Tax Financial Analysis 381
      19.4.1.1 Basis of Pre-Tax Financial Evaluation 381
      19.4.1.2 Pre-Tax Financial Results 382
    19.4.2 Post-Tax Financial Analysis 383
      19.4.2.1 US Federal Tax 383
      19.4.2.2 Alaska State Tax 384
      19.4.2.3 Alaska Mining License Tax 384
      19.4.2.4 Post-Tax Financial Results 384
  19.5 Cash Flow 384
  19.6 Sensitivity Analysis 388
20 Adjacent Properties 393
21 Other Relevant Data and Information 394
  21.1 Project Execution Plan 394
    21.1.1 Constraints and Interfaces 394
    21.1.2 Key Project Milestones 394
    21.1.3 Proven Technology 396
    21.1.4 Engineering, Procurement and Construction Management Approach 396
      21.1.4.1 Early Engineering Only with 2-Stage Procurement 396
      21.1.4.2 Early EPCM Leading to Plant Care and Maintenance 397
22 Interpretations and Conclusions 398
  22.1 Introduction 398
  22.2 Mineral Tenure, Surface Rights, Royalties and Agreements 398
  22.3 Geology and Mineralization 398

 

  
Arctic ProjectPage xii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

  22.4 Exploration, Drilling and Analytical Data Collection in Support of Mineral Resource Estimation 398
  22.5 Metallurgical Testwork 399
  22.6 Mineral Resource Estimates 399
  22.7 Mineral Reserve Estimates 400
  22.8 Mining Recovery 401
  22.9 Recovery Methods 401
  22.10 Infrastructure 401
  22.11 Environmental, Permitting and Social 402
  22.12 Market Studies and Contracts 402
  22.13 Capital Costs 403
  22.14 Operating Costs 403
  22.15 Economic Analysis 404
  22.16 Conclusions 404
  22.17 Risks and Opportunities 404
    22.17.1 Permitting 404
    22.17.2 Mining 404
    22.17.3 Geotechnical 404
    22.17.4 Hydrogeology 405
    22.17.5 Tailings Management, Waste Rock and Water Management Facilities 406
    22.17.6 Hydrology 407
    22.17.7 Water and Load Balance 408
    22.17.8 Metallurgical Testwork 409
23 Recommendations 410
  23.1 Introduction 410
  23.2 Mining 410
  23.3 Geology and Resource Models 411
  23.4 Open Pit Geotechnical work 412
  23.5 Hydrogeology 412
  23.6 Tailings Management Facility 413
  23.7 Closure 413
  23.8 Water Treatment 414
  23.9 Metallurgical testing 414
  23.10 Recovery Methods 414
  23.11 Operational Readiness Plan 414
24 References 416
25 RELIANCE ON INFORMATION PROVIDED BY THE REGISTRANT 424
  25.1 Introduction 424
  25.2 Legal Matters 424
  25.3 Taxation 424
  25.4 Environmental Matters and Community Accommodations 425
  25.5 Marketing Information 425

 

Appendix A – Mineral Claims

 

  
Arctic ProjectPage xiii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

List of Tables

 

Table 1-1: Comparison of Bulk versus Sequential Locked-Cycle Test Results – ALS 2021 7
Table 1-2: Summary of Overall Metal Recovery – Arctic Project 8
Table 1-3: Mineral Resource Summary Table, Inclusive of Mineral Reserves 10
Table 1-4: Mineral Resource Summary Table, Exclusive of Mineral Reserves 10
Table 1-5: Optimization Inputs 11
Table 1-6: Mineral Reserve Statement 13
Table 1-7: LOM Average Recovery and Grade 15
Table 1-8: Capital Cost Summary 20
Table 1-9: Overall Operating Cost Estimate 21
Table 1-10: Summary of Recommended Work Packages 23
Table 2-1: Report Contributors 27
Table 2-2: Unit Abbreviations 29
Table 2-3: Acronyms and Abbreviations 31
Table 5-1: Known Mapping, Geochemical, and Geophysical Programs Targeting VMS Prospects in the Ambler Mining District 51
Table 5-2: Summary of Previous Geotechnical and Hydrogeological Work Completed After 1998 58
Table 5-3: Mining and Technical Services 61
Table 7-1: Summary of NovaGold/Trilogy/Ambler Metals Exploration Activities Targeting VMS-style Mineralization in the Ambler Sequence Stratigraphy and the Arctic Deposit 79
Table 7-2: TDEM Loops and Locations 84
Table 7-3: Companies, Campaigns, Drill Holes and Meters Drilled at the Arctic Deposit 87
Table 7-4: Summary of NovaGold/Trilogy/Ambler Metals Arctic Deposit Drilling 88
Table 7-5: Drill, Meterage and Average Drill Depth for Ambler Sequence VMS Targets 90
Table 7-6: Ambler Metals Exploration Drilling – Ambler Schist Belt 91
Table 7-7: 2019-2021 Regional Prospect Drilling Significant Intercepts 92
Table 7-8: Drill Contractors, Drill Holes, Meterage and Core Sizes by Drill Campaign at the Arctic Deposit 99
Table 7-9: Summary of Geotechnical Drilling 101
Table 7-10: Summary of Geotechnical Drilling by Year and Purposes 102
Table 7-11: Recovery and RQD 2004 to 2008 Arctic Drill Campaigns 106
Table 8-1: Analytical Laboratories used for Acid Base Accounting and Kinetic Studies for the Arctic Project 113

 

  
Arctic ProjectPage xiv
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

  

   
   

 

Table 8-2: Analytical Laboratories Used by Operators of the Arctic Project 115
Table 10-1: Summary of Overall Forecast Metal Recovery – Arctic Deposit 131
Table 10-2: Summary of Testwork Chronology and Reporting 131
Table 10-3: Head Analysis, Lakefield Research 1999 133
Table 10-4: Flotation Test on Ambler Low Talc Composite 134
Table 10-5: SGS Burnaby Head Grades – Composite Samples – 2012 135
Table 10-6: ALS Metallurgy Head Grades – Composite Samples – 2017 136
Table 10-7: Mineral Modal Abundance for Composite Samples – SGS Burnaby 2012 139
Table 10-8: Bond Ball Mill Work Index and Abrasion Index Test Results 140
Table 10-9: Summary of SMC Test Results and Additional BMI Data 141
Table 10-10: Summary of Locked Cycle Recovery Data for Composite Sample Testing 143
Table 10-11: Locked Cycle Metallurgical Test Results – SGS Burnaby 2012 144
Table 10-12: Locked Cycle Metallurgical Test Results – ALS Metallurgy 2017 144
Table 10-13: SGS Burnaby Open Circuit Copper and Lead Separation Test Results 146
Table 10-14: ALS Metallurgy Locked Cycle Testing of Copper-Lead Separation Process 146
Table 10-15: Summary of Lead Concentrate Grades for Various Talc Grades in Feed 147
Table 10-16: Summary of Flotation Reagent and Grind Size Objectives 148
Table 10-17: Summary of Lead Concentrate Quality 148
Table 10-18: Summary of Copper Concentrate Quality 149
Table 10-19: Summary of Zinc Concentrate Quality 149
Table 10-20: ALS Head Grades – Pre-Flotation Samples – 2021 151
Table 10-21: ALS Flowsheet Development Head Composites – 2021 151
Table 10-22: ALS Flowsheet Development Composites Head Assays – 2021 152
Table 10-23: ALS Variability Sample Details – 2022 153
Table 10-24: ALS Variability Samples Head Assays – 2022 154
Table 10-25: Bond Ball Mill Work Index and Abrasion Index Test Results 162
Table 10-26: Summary of SPI Test Results 163

  
Arctic ProjectPage xv
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

  

   
   

 

Table 10-27: Summary of Baseline Pre-Flotation Tests 164
Table 10-28: Comparison of Bulk vs. Sequential Locked-Cycle Test Results – ALS 2021 165
Table 10-29: Summary of Variability Open Circuit Flotation Test Results – ALS 2022 167
Table 10-30: ALS Lead Separation Test Results 171
Table 11-1: List of Drill Holes used in 2022 Ambler Metals Resource Model that were Not Included in the 2020 SRK Model 173
Table 11-2: Summary Statistics of Assay Database, Length Weighted 175
Table 11-3: Arctic Lithological Units 178
Table 11-4: Summary of Mineralized Zone Domains 180
Table 11-5: Summary Statistics for SG by Mineralized Zone 181
Table 11-6: Summary Statistics for SG Measured and SG Predicted 182
Table 11-7: Mean SG Values for Measured and Predicted by Bins 182
Table 11-8: Summary Statistics of the Composite Database 184
Table 11-9: Capping Values 186
Table 11-10: Summary Statistics of Uncapped and Capped Values for Payable Metal 187
Table 11-11: Summary Statistics of Uncapped and Capped Values for Deleterious Elements 188
Table 11-12: Estimation Domains 189
Table 11-13: Variogram Models for the Bottom Group 190
Table 11-14: Variogram Models for the Middle Group 191
Table 11-15: Variogram Models for the Top Group 192
Table 11-16: Variogram Model for Talc 193
Table 11-17: Arctic Block Model Parameters 193
Table 11-18: Search Ellipsoid Parameters Used for Payable Metals (Cu, Zn, Ag, and Au) 194
Table 11-19: Search Ellipsoid Parameters Used for Deleterious Elements 195
Table 11-20: Search Ellipsoid Parameters Used for Talc 195
Table 11-21: Search Ellipsoid Parameters Used for SG 196
Table 11-22: Statistics of OK and NN for Payable Metals for the Main Mineralized Zones 202

 

  
Arctic ProjectPage xvi
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

 

   
   

 

Table 11-23: Mineral Resource Classification and Criteria 208
Table 11-24: Parameters Used to Generate a Resource Constraining Pit Shell 210
Table 11-25: Mineral Resource Summary Table, Inclusive of Mineral Reserves 211
Table 11-26: Mineral Resource Summary Table, Exclusive of Mineral Reserves 211
Table 12-1: Optimization Inputs 213
Table 12-2: Variable Process Recoveries Used in the NSR Calculation 219
Table 12-3: Mineral Reserve Statement 220
Table 13-1: Geotechnical Design Parameters 223
Table 13-2: Production Schedule 231
Table 13-3: Gross Operating Hours per Year 233
Table 13-4: Equipment Utilization and Efficiency 234
Table 13-5: Blasting Design Input 235
Table 13-6: Material Blasted Quantities 236
Table 13-7: Explosives Quantities 236
Table 13-8: Rock Type Weight and UCS 238
Table 13-9: Workman, Szumanski (1996,1997) Inputs 238
Table 13-10: Drill Penetration Rates 239
Table 13-11: Drill Requirements and Performance 239
Table 13-12: Loading Requirements and Performance 240
Table 13-13: Hydraulic Shovel Productivity 241
Table 13-14: Front End Loader Productivity 242
Table 13-15: Truck Speed Limits 243
Table 13-16: Truck Speed Limits 243
Table 13-17: Truck Requirements and Performance 244
Table 13-18: Support Equipment 245
Table 13-19: Auxiliary Equipment 246
Table 13-20: Ratio Maintenance Hours to Equipment Operated Hours 248
Table 13-21: Summary of Unconfined Compressive Strength by Lithological Units 252

 

  
Arctic ProjectPage xvii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Table 13-22: Shear Strength Laboratory Test Results Excluding Talc Samples 253
Table 13-23: Summary of Derived Rock Mass Parameter Values per Rock Mass Domain 255
Table 13-24: Estimate Pit Inflow 258
Table 13-25: Selected Slope Stability Acceptance Criteria 260
Table 14-1: Process Design Criteria – Overview 271
Table 14-2: Comminution Design Criteria 271
Table 14-3: Flotation Plant Design Criteria 272
Table 14-4: Annual Reagent Consumption 279
Table 15-1: Personnel Onsite during Operations 291
Table 15-2: Process Water Supply Summary 295
Table 15-3: TMF Design Parameters and Design Criteria 304
Table 15-4: Mode of Transport and Distances for Concentrate Shipping 313
Table 16-1: Average Metal Prices (Data from S&P Market Intelligence and CIBC, 2022) 314
Table 16-2: Chinese Import Restrictions for Copper, Zinc, and Lead Concentrates 318
Table 16-3: Concentrate Transport Costs 322
Table 17-1: Summary of Closure and Reclamation Costs 340
Table 17-2: Major Mine Permits Required for the Arctic Project 343
Table 18-1: Estimate Summary Level 1 Major Facility 347
Table 18-2: Initial Estimate by Major Discipline 348
Table 18-3: Estimate Exchange Rates 350
Table 18-4: Mining Initial and Sustaining Capital Cost 351
Table 18-5: Sustaining Capital Cost Distribution 352
Table 18-6: 141t Truck Capital Pricing 354
Table 18-7: Mine Equipment Capital Cost Inputs 354
Table 18-8: Ancillary Equipment Capital Cost Inputs 355
Table 18-9: Capital Spares 356
Table 18-10: Other Capital Costs 357
Table 18-11: Crushing and Process Plant Capital Costs 357
Table 18-12: TMF Capital Costs 359
Table 18-13: Onsite Infrastructure Costs 359
Table 18-14: Offsite Infrastructure Costs 360
Table 18-15: Indirect Capital Costs 360
Table 18-16: Estimate Contingency 361
Table 18-17: Owner’s Costs 362
Table 18-18: Sustaining Capital and Closure Costs 363

 

  
Arctic ProjectPage xviii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Table 18-19: Overall Operating Cost Estimate 365
Table 18-20: Mining Operating Cost Summary by Cost Centre 367
Table 18-21: Operating Cost Summary by Cost Centre 367
Table 18-22: Annual Mine Expenditure 368
Table 18-23: Maintenance and Repair Cost 370
Table 18-24: Equipment Fuel Burn Rates 371
Table 18-25: Annual Diesel Consumption 372
Table 18-26: Blasting Explosives and Accessories Cost and Service Fee 373
Table 18-27: Tire Sizes, Pricing, and Life 373
Table 18-28: Other Operating Costs 374
Table 18-29: Summary of Processing Operating Cost Estimates 375
Table 18-30: G&A Cost Estimates 377
Table 19-1: Mine and Payable Metal Production for the Arctic Mine 380
Table 19-2: Summary of Pre-Tax Financial Results 382
Table 19-3: Summary of Post-Tax Financial Results 384
Table 19-4: Pre and Post-Tax Arctic Project Production and Cashflow Forecast 385
Table 19-5: Pre-Tax Sensitivity Summary 389
Table 19-6: Post-Tax Sensitivity Summary 392
Table 23-1: Summary of Recommended Work Packages 410

  

  
Arctic ProjectPage xix
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

  List of Figures  
     
Figure 3-1: Arctic Project Location Map 36
Figure 3-2: Upper Kobuk Mineral Projects Lands 38
Figure 3-3: Arctic Project Mineral Tenure Plan 39
Figure 3-4: Mineral Tenure Layout Plan 40
Figure 3-5: Arctic Deposit Location 41
Figure 6-1: Regional Geologic Terranes of the Southern Brooks Range 64
Figure 6-2: Local Geology of the Ambler Mining District 66
Figure 6-3: Ambler Sequence Stratigraphy in the Arctic Deposit Area 68
Figure 6-4: Generalized Geology of the Central Ambler Mining 69
Figure 6-5: Typical F1 Isoclinal Folds Developed in Calcareous Gnurgle Gneiss 70
Figure 6-6: Generalized Geologic Map of the Arctic Deposit 72
Figure 6-7: Major Prospects of the Ambler Mining District 78
Figure 7-1: Mapping Campaigns in and around the Arctic Deposit 82
Figure 7-2: VTEM Flight Lines Over the Ambler Belt and Cosmos Hill Prospective Areas 85
Figure 7-3: ZTEM Flight Lines Over the Ambler VMS Belt and the Bornite Deposit 86
Figure 7-4: Plan Map of Drill Holes coloured by Year in the Vicinity of the Arctic Deposit. Dark Grey is Limits of 2021 Conceptual Pit 89
Figure 7-5: Collar Locations and Principal Target Areas – Ambler Mining District 90
Figure 7-6: Sunshine Prospect and Drill Hole Locations 93
Figure 7-7: Snow Project and Drill Hole Locations 94
Figure 7-8: Northeast and Southeast Arctic and Drill Hole Locations 95
Figure 7-9: 98-9(NEN) Prospect and Drill Hole Locations 96
Figure 7-10: East Dead Creek Prospect and Drill Hole Locations 97
Figure 7-11: Plan Map of Drill Holes in the Vicinity of the Arctic Deposit 98
Figure 7-12: Locations of Geotechnical Drilling 103
Figure 7-13: Locations of Hydrogeological Drilling 104
Figure 7-14: Drill Plan of Arctic Copper Results 107
Figure 7-15: Cross-Section 1 of Arctic Copper Results Looking South 108
Figure 7-16: Cross-Section 2 of Arctic Copper Results Looking South 108
Figure 7-17: Drill Plan of Arctic Zinc Results 109
Figure 7-18: Cross-Section 1 of Arctic Zinc Results Looking South 110
Figure 7-19: Cross-Section 2 of Arctic Zinc Results Looking South 110
Figure 8-1: Historical Cu Re-Assay RMA Chart 117
Figure 8-2: Historical Pb Re-Assay RMA Chart 118
Figure 8-3: Distribution of Historical Samples with Original Laboratory Results (Original Historic Assay Intervals are Indicated in Magenta, Recent Assays are Indicated in Green) 119
Figure 8-4: Spatial Availability of QA/QC Data 120
     

  
Arctic ProjectPage xx
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Figure 8-5: Graph showing Good Agreement between Wet-Dry Measured Specific Gravity and Pycnometer  Measured Specific Gravity 124
Figure 8-6: Measured vs. Stoichiometric Specific Gravities 125
Figure 8-7: Scatter Plot Showing the Measured Specific Gravity vs. Multiple (Copper, Iron, Zinc, Barium) Regression 126
Figure 8-8: Reduced to Major Axis (RMA) Scatter Plot Showing the Predicted and Measured SG Values 127
Figure 10-1: Cu and Zn Test Sample Grades for ALS Metallurgy/SGS Burnaby Programs 137
Figure 10-2: Cu and Pb Test Sample Grades for ALS Metallurgy/SGS Burnaby Programs 137
Figure 10-3: Distribution of Talc Content within the 2012 and 2017 Test Samples 138
Figure 10-4: Cu and Pb Test Sample Grades for ALS Metallurgy Test Program 156
Figure 10-5: Cu and Zn Test Sample Grades for ALS Metallurgy Test Program 156
Figure 10-6: Talc Optimization Composites Mineral Content 158
Figure 10-7: Parent Composite Mineral Content 159
Figure 10-8: Mineral Modal Abundance for Variability Samples 161
Figure 10-9: Variability Composite Copper Recovery vs. Concentrate Grade 169
Figure 10-10: Variability Composite Lead Recovery vs. Concentrate Grade 170
Figure 11-1: East-West Cross Section for Copper Drill Hole Data, Looking North (Resource pit depicted in red) 176
Figure 11-2: East-West Cross-Section of the Arctic Geological Model, Looking North 177
Figure 11-3: East-West Cross-Section of Talc Model Wireframes, Looking North 178
Figure 11-4: East-West Cross-Section of the Arctic Deposit Showing Mineralized Zones 179
Figure 11-5: Cumulative Probability Plot for SG in the Resource Block Model 183
Figure 11-6: Histogram of Composite Lengths 184
Figure 11-7: Cross-Section of Estimation Domains and Talc 189
Figure 11-8: LVA Search Ellipsoids Used in Minzone 5 (Red, Top Group) for Cu Estimation 197
Figure 11-9: East-West Cross-Section for Cu Block Model and Composite Data, Looking North (Resource pit depicted in red) 198
Figure 11-10: East-West Cross-Section for Zn Block Model and Composite Data, Looking North (Resource pit depicted in red) 198
Figure 11-11: East-West Cross-Section for Pb Block Model and Composite Data, Looking North (Resource pit depicted in red) 199
Figure 11-12: East-West Cross-Section for Ag Block Model and Composite Data, Looking North (Resource pit depicted in red) 199
Figure 11-13: East-West Cross-Section for Au Block Model and Composite Data, Looking North (Resource pit depicted in red) 200
Figure 11-14: Cu Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction 203
Figure 11-15: Pb Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction 204
Figure 11-16: Zn Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction 205
Figure 11-17: Ag Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction 206
Figure 11-18: Au Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction 207
Figure 11-19: Oblique View of Mineral Resource Classification Model 209
Figure 11-20: Cross-Section of Mineral Resource Classification Model, Looking North 209
Figure 11-21: Isometric View of Arctic Mineral Resource 212
Figure 12-1: Pit-by-Pit Analysis 216
Figure 12-2: Selected Pit Shell 217
Figure 12-3: Contact Dilution Concept 218
Figure 12-4: Contact Dilution Estimation Procedure 219
Figure 13-1: Geotechnical Slope Design Domains 223
     

  
Arctic ProjectPage xxi
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 13-2: Ultimate Pit Design 225
Figure 13-3: Section 1 Showing Mine Design and Selected Pit Shells (looking NW) 226
Figure 13-4: Section 2 Showing Mine Design and Selected Pit Shells (looking W) 226
Figure 13-5: Phase 1 Design 227
Figure 13-6: Phase 2 Design 228
Figure 13-7: Phase 3 Design 228
Figure 13-8: Waste Rock Facility 229
Figure 13-9: Ore Stockpile 230
Figure 13-10: Annual Production Schedule 232
Figure 13-11: Total Tonnage Mined, Scheduled by Phase 232
Figure 13-12: Isometric View (looking southeast) of Talc Zone Domain Modelled by SRK (2022) Using Leapfrog on the EoY12 design pit 249
Figure 13-13: SRK Structural Model (SRK, 2019) used in the Slope Stability Analysis on the EoY12 Design Pit 250
Figure 13-14: Location Plan, Structural and Geomechanical Domains 251
Figure 13-15: Talc Geotechnical Laboratory Testing Results 254
Figure 13-16: Summarized Hydrogeological Conceptual Model for Pit Area 257
Figure 13-17: Pore Pressure Management Assumptions for East and Northeast Pit Walls 259
Figure 13-18: Recommended Inter-Ramp Angles by Slope Design Domains Projected on EOY12 Design Pit 262
Figure 13-19: Potential Areas of Slope Instability Risks in the 2022 Open Pit Designs 264
Figure 14-1: Process Plant Flowsheet 268
Figure 14-2: Overall Plant Area Plan 269
Figure 14-3: Process Plant Plan 270
Figure 15-1: Proposed Site Layout 284
Figure 15-2: Proposed Location of the Processing Plant and Other Buildings 285
Figure 15-3: Proposed Route of AAP Road 287
Figure 15-4: Arctic Access Road 289
Figure 15-5: Surface Water Management Plan During Operations (Year 2) 293
Figure 15-6: Surface Water Management Plan at the End of LOM (Year 13) 294
Figure 15-7: WRCP and Process Pond Plan 298
Figure 15-8: WRCP and Process Pond 299
Figure 15-9: WRCP and Process Pond 299
Figure 15-10: Cross Section of the TMF & WRF showing Starter Dam to Elevation 805 m 307
Figure 15-11: Cross Section of the TMF and Raises to Final Design Evaluation 307
Figure 16-1: 5-year Average Daily Closing Price for Copper 315
Figure 16-2: 5-year Average Daily Closing Price for Zinc 315
Figure 16-3: 5-year Average Daily Closing Price for Lead 316
Figure 16-4: 5-year Average Daily Closing Price for Gold 316
Figure 16-5: 5-year Average Daily Closing Price for Silver 317
Figure 17-1: Current Water Quality and Hydrology Stations’ Location Map 324
Figure 17-2: 2021 Aquatics Sampling Sites 327
Figure 17-3: Phase One Closure 334
Figure 17-4: Phase Two Closure 335
Figure 18-1: Initial Mining Capital Cost Distribution by Cost Centre 353
Figure 18-2: Costs by Cost Centre 365
     

  
Arctic ProjectPage xxii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 18-3: Costs by Cost Item 366
Figure 18-4: Total Material Mined and Mine Operating Cost 368
Figure 19-1: Pre-Tax NPV Sensitivity Analysis 390
Figure 19-2: Pre-Tax IRR Sensitivity Analysis 391
Figure 21-1: Project Execution Schedule 395

 

  
Arctic ProjectPage xxiii
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

 

1EXECUTIVE SUMMARY

 

1.1Introduction

 

Trilogy Metals Inc. (Trilogy or Trilogy Metals) is listed on the Toronto Stock Exchange (TSX) and the New York Stock Exchange (NYSE). As a result, Trilogy is a reporting issuer in Canada and must comply with National Instrument 43-101 Standards of Disclosure for Mineral Projects (NI 43-101) and is a registrant with the United States Securities and Exchange Commission (SEC) and must also comply with subpart 229.1300 – Disclosure by Registrants Engaged in Mining Operations of Regulation S-K (S-K 1300).

 

Trilogy commissioned Ausenco Engineering Canada Inc. (Ausenco) to manage the update of the 2020 Arctic Feasibility Study Technical Report (2020 FS) prepared in accordance with NI 43-101 into a prefeasibility-level study (the Arctic Project) and summarize into a S-K 1300 Technical Report Summary (the Report) on the Arctic deposit in the Ambler Mining District of northwest Alaska.

 

This Report was prepared by Ausenco, Brown & Caldwell (B&C), SRK Consulting (Canada) Inc. (SRK or SRK Canada), and Wood Canada Limited (Wood) for Trilogy to support disclosures in its Annual Report on Form 10-K for the fiscal year ended November 30, 2022.

 

The Report supports Mineral Resources and Mineral Reserves using the standards and definitions in S-K 1300.

 

The Report presents Mineral Resource and Mineral Reserve estimates for the Project, and an economic assessment based on open pit mining operations and a conventional processing circuit that would produce copper, zinc, and lead concentrates.

 

All units of measurement in this Report are metric, unless otherwise stated. Monetary units are in US dollars, unless otherwise stated.

 

1.2Property Description

 

The Arctic property is located in the Ambler mining district (Ambler Mining District) of the southern Brooks Range, in the Northwest Arctic Borough (NWAB) of Alaska. The property is geographically isolated with no current road access or nearby power infrastructure. The property is located 270 km east of the town of Kotzebue, 37 km northeast of the village of Kobuk, and 260 km west of the Dalton Highway, an all-weather state-maintained highway and centred around geographic coordinates N67.17° latitude and W156.39° longitude.

 

1.2.1Mineral Tenure, Surface Rights, Water Rights, Royalties and Agreements

 

NovaGold Resources Inc. (NovaGold) acquired the Arctic Project from Kennecott Exploration Company and Kennecott Arctic Company (collectively, Kennecott) in 2004. In 2011, NovaGold transferred all copper projects to NovaCopper Inc. and spun-out NovaCopper to its then existing shareholders in 2012. NovaCopper Inc. subsequently underwent a name change to Trilogy Metals Inc. in 2016. Under the Kennecott Purchase and Termination Agreement, Kennecott retained a 1% net smelter return (NSR) royalty that has been subsequently sold by Kennecott. The 1% NSR runs with the lands and is purchasable at any time from the royalty holder for a one-time payment of $10 million.

 

The Project is directly held by Ambler Metals LLC (Ambler Metals), in a 50/50 joint venture formed between South32 Limited (South32) and Trilogy Metals in February 2020. Upon the formation of the joint venture, Trilogy Metals contributed all of its Alaskan assets, including the Project and the agreement with NANA (see below), to Ambler Metals in exchange for a 50% membership interest and at the same time, South32 contributed $145 million in cash for a 50% membership interest.

  
Arctic ProjectPage 1
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The UKMP consists of an approximately 448,217-acre land package containing state, patented and native lands within an area of interest. There are two discrete mineralized belts within the UKMP – the Devonian Ambler Schist Belt and the Devonian Bornite Carbonate Sequence. The Project is located within the Ambler Schist Belt which comprises approximately 231,008 acres (93,446 ha) of State of Alaska mining claims and US Federal patented mining claims in the Kotzebue Recording District. Exclusive of native lands, the UKMP land tenure consists of 2,136 contiguous State claims totalling 230,736 acres (93,336 ha), including 905 40-acre claims, 1,231 160-acre claims, and 18 Federal patented claims comprising 271.9 acres (110 ha) held in the name of Ambler Metals LLC. Surface use of the private land held as Federal patented claims is limited only by reservations in the patents and by generally applicable environmental laws. Surface use of State claims allows the owner of the mining claim to make such use of the surface as is “necessary for prospecting for, extraction of, or basic processing of minerals.”

 

The UKMP also consists of lands owned by NANA Regional Corporation, Inc. (NANA), who controls lands granted under the Alaska Native Claims Settlement Act (ANCSA) to the south of the Project boundary. Ambler Metals and NANA are parties to an agreement dated October 19, 2011 (the NANA Agreement) that consolidates the parties’ land holdings into an approximately 190,929 ha land package and provides a framework for the exploration and development of the area. The NANA Agreement has a term of 20 years, with an option in favour of Ambler Metals to extend the term for an additional 10 years. If, following receipt of a feasibility study and the release for public comment of a related draft environmental impact statement, a decision is made to proceed with construction of a mine on the lands subject to the NANA Agreement, NANA will have 120 days to elect to either (a) exercise a non-transferrable back-in-right to acquire between 16% and 25% (as specified by NANA) of that specific project; or (b) not exercise its back-in-right, and instead receive a net proceeds royalty equal to 15% of the net proceeds realized from such project. In the event that NANA elects to exercise its back-in-right, the parties will, as soon as reasonably practicable, form a joint venture with NANA electing to participate between 16% to 25%, and Ambler Metals owning the balance of the interest in the joint venture. If Ambler Metals decides to proceed with construction of a mine on its own lands subject to the NANA Agreement, NANA will enter into a surface use agreement which will afford Ambler Metals access to the project along routes approved by NANA. In consideration for the grant of such surface use rights, NANA will receive a 1% net smelter royalty on production and provide an annual payment on a per acre basis.

 

1.3Accessibility, Climate, Local Resources, and Infrastructure

 

Primary access to the Project is by air, using both fixed wing aircraft and helicopters.

 

There are four well-maintained, approximately 1,500 m-long gravel airstrips located near the Project, capable of accommodating charter fixed wing aircraft. These airstrips are located 64 km west at Ambler, 46 km southwest at Shungnak, 37 km southwest at Kobuk, and 34 km southwest at Dahl Creek. There is daily commercial air service from Kotzebue to the village of Kobuk, the closest community to the Project. During the summer months, the Dahl Creek Camp airstrip is suitable for larger aircraft, such as a C-130 and DC-6.

 

In addition to the four 1,500 m airstrips, there is a 700 m airstrip located at the Bornite Camp. The airstrip at Bornite is suited to smaller aircraft, which support the Bornite Camp with personnel and supplies. There is also a 450 m airstrip (Arctic airstrip) located at the base of Arctic Ridge that can support smaller aircraft.

 

A winter trail and a one-lane dirt track suitable for high-clearance vehicles or construction equipment links the Arctic Project’s main camp located at Bornite to the Dahl Creek airstrip southwest of the Arctic deposit. An unimproved gravel track connects the Arctic airstrip with the Arctic deposit.

  
Arctic ProjectPage 2
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The climate in the region is typical of a sub-arctic environment. Weather conditions on the Project can vary significantly from year to year and can change suddenly. During the summer exploration season, average maximum temperatures range from 10 °C to 20 °C, while average lows range from -2°C to 7°C (Western Regional Climate Center: WRCC - Alaska Climate Summaries: Kobuk 1971 to 2000). By early October, unpredictable weather limits safe helicopter travel to the Project. During winter months, the Project can be accessed by snow machine, track vehicle, or fixed wing aircraft. Winter temperatures are routinely below -25°C and can exceed -50°C. Annual precipitation in the region varies with elevation.

 

It is expected that any future mining activity will be conducted on a year-round basis. Exploration activities are generally confined to the period from late May to late September.

 

Kotzebue is a potential source of limited mining-related supplies and labourers, and is the nearest centre serviced by regularly scheduled, large commercial aircraft (via Nome or Anchorage). In addition, there are seven other villages in the region that will be a potential source of some of the workforce for the Project. Fairbanks (population 32,515; 2020 US Census) has a long mining history along with currently operating mines and can provide most mining-related supplies and support that cannot be sourced closer to the Project area.

 

Drilling and mapping programs are seasonal and have been supported out of the Bornite Camp and Dahl Creek Camp. The Bornite Camp facilities are located on Ruby Creek on the northern edge of the Cosmos Hills. The camp provides office space and accommodations for the geologists, drillers, pilots, and support staff. Power is supplied by two diesel generators – one 300 kW and one 225 kW. Water was supplied by the permitted artesian well located 250 m from camp; however, a water well was drilled in camp during the 2017 field season that was permitted by 2019 to provide all potable water for the Bornite Camp.

 

1.4History

 

Prior to Trilogy’s Project interest, work programs were conducted by Bear Creek Mining Company (BCMC), an exploration subsidiary of Kennecott Exploration (Kennecott) and Anaconda. Exploration activities included geological and reconnaissance mapping, geochemical sampling, airborne and ground geophysical surveys, drilling, metallurgical testwork, petrological and mineralogical studies, and resource estimates.

 

Trilogy obtained its project interest from NovaGold in 2011. NovaGold obtained its project interest in 2004, when the Alaska Gold Company, a wholly-owned subsidiary of NovaGold completed an Exploration and Option Agreement with Kennecott to earn an interest in the Ambler land holdings. In 2010, NovaGold acquired a 100% controlling interest by buying out Kennecott’s interest, although Kennecott retained an NSR royalty. Work conducted by NovaGold and Trilogy Metals (formerly, NovaCopper) included geological mapping, soil and silt geochemical sampling, time-domain electromagnetic (TDEM) ground geophysical surveys, airborne DIGHEM geophysical surveys, down-hole geophysics, drilling programs, metallurgical testwork, Mineral Resource and Mineral Reserve estimates, mining studies, and baseline environmental studies.

 

1.5Geological Setting, Mineralization, and Deposit

 

The Arctic deposit is hosted in the Ambler Sequence, in the upper part of the regional Anirak Schist, in the Ambler Mining District on the southern margin of the Brooks Range in Alaska. Ambler Sequence is a group of Middle Devonian to Early Mississippian, metamorphosed, bimodal volcanic rocks with interbedded tuffaceous, graphitic, and calcareous volcaniclastic metasediments. The Arctic deposit has characteristics that are representative of a volcanogenic massive sulphide (VMS) deposit based on its geologic setting, associated host rocks, ore morphology, and ore mineralogy. VMS-style mineralization is found along the entire 110 km strike length of the Ambler Sequence.

  
Arctic ProjectPage 3
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Mineralization occurs as stratiform semi-massive sulphide (SMS) to massive sulphide (MS) beds within primarily graphitic chlorite schists and fine-grained quartz schists. The sulphide beds average 4 m in thickness but vary from less than 1 m up to as much as 18 m in thickness.

 

The bulk of the mineralization occurs within eight modelled SMS and MS zones lying along the upper and lower limbs of the interpreted Arctic isoclinal anticline. All the zones are within an area of roughly 1 km2 with mineralization extending to a depth of approximately 250 m below the surface. Mineralization is predominately coarse-grained sulphides consisting mainly of chalcopyrite, sphalerite, galena, tetrahedrite-tennantite, pyrite, arsenopyrite, and pyrrhotite. Trace amounts of electrum are also present.

 

1.6Exploration

 

Drilling at the Arctic deposit and within the Ambler Mining District has been ongoing since its discovery in 1966. Approximately 67,639 m of drilling was completed within the Ambler Mining District, including 55,038 m of drilling in 285 drill holes at the Arctic deposit or on potential extensions in 32 campaigns spanning 56 years. Drill programs were completed by Kennecott and its subsidiaries, Anaconda, NovaGold, Trilogy and Ambler Metals.

 

Drill collar and downhole survey measurement collected since 2004 have used industry-recognized instrumentation and methods. Many historical collar locations have been resurveyed using these current methods. Between 1998 and 2011, Specific Gravity (SG) measurements were collected from short whole core samples using water displacement or water immersion methods. Since 2011 SG measurements are collected from assay sample intervals of half or whole core using water immersion methods. Core recovery is good.

 

1.7Sample Preparation, Analysis and Security

 

Analytical methods and laboratory accreditations used for historical samples are not known. Samples from the NovaGold/NovaCopper/Trilogy/Ambler Metals programs were submitted to ALS Minerals of Vancouver, British Columbia, Canada for multielement analysis by Inductively Coupled Plasma Mass Spectrometry (ICP MS) following a 4-acid digestion, and for gold analysis of a 30-gram sample by Fire Assay (FA) with an Atomic Absorption (AA) finish. Over limit ICP-MS samples were resubmitted for analysis by ICP-Atomic Emission Spectroscopy (AES) or AA following a 4-acid digestion. Over limit gold results were resubmitted for analysis of a 30-gram sample by FA with a Gravimetric finish.

 

Standard reference materials, blanks, duplicates, and check samples have been regularly submitted for all NovaGold/NovaCopper/Trilogy and Ambler Metals era sampling campaigns. No significant quality control issues are evident in samples analysed since 2004. Samples analyzed since 2004 are in the QP’s opinion appropriate for the mineralization style observed at Arctic and provide adequate confidence in the reported assay values. Historical copper and lead values (pre-2004) that remain in the primary assay database appear to be biased high and low, respectively. The broad spatial distribution of these original historical samples and density of samples with more recent assay values surrounding these samples in the QP’s opinion reduces the risk associated with these observed biases.

 

1.8Data Verification

 

Kennecott entered the historical drill hole information into tables in 1995. In 2006, NovaGold geologists verified the geologic data from the original paper logs against the Kennecott electronic format, and then merged the data into a Microsoft SQL database. In 2013, NovaCopper retained GeoSpark Consulting to complete a 100% verification of the collar survey, downhole survey, and sample interval data. Geospark was also retained to generate QA/QC reports for the NovaGold-era 2004 to 2008 and NovaCopper/Trilogy-era 2011, 2015, 2016, 2017, and 2019 drill campaigns. All data for the Arctic resource area is stored in the GeoSpark Core Database System created and managed by GeoSpark Consulting.

  
Arctic ProjectPage 4
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Between 2004 and 2005 NovaGold completed a resampling program of historic drill holes. As a result, 85 % of the entire assay interval database now has well supported recent assay results. The resampling program included reassay of 289 previously assayed historic sample intervals. Analysis of the paired historic and reassay results indicates there is a 10 % high bias in the legacy Cu values and a 13 % low bias in the legacy Pb values. Legacy sample represent only 15% of the entire assay database and are generally evenly distributed spatially between samples with more recent assay reducing the risk associated with these observed biases.

 

It is the QP’s opinion the drill database and topographic information for the Arctic deposit are reliable and sufficient to support the current estimate of Mineral Resources.

 

1.9Mineral Processing and Metallurgical Testing

 

Since 1970, metallurgical testwork has been conducted to evaluate the ability of the Arctic deposit to produce copper, lead and zinc concentrates. In-general, the samples tested produced similar metallurgical performances and the project has seen the development of a robust metal recovery process to support the current operational plans. Work conducted included mineralogy and flotation testing, locked cycle tests, comminution tests, copper/lead separation testwork, talc optimization testwork, and thickening and filtration testing.

 

Testwork can be broken into four key time periods:

 

1.Historical testwork completed prior to 2012, primarily by Kennecott Research Centre (KRC) in Utah, and Lakefield Research Ltd., Lakefield, Ontario;

 

2.Preliminary Trilogy Metals testwork conducted at SGS Mineral Services, Vancouver (SGS Vancouver), in 2012 to 2015;

 

3.Detailed Trilogy Metals testwork conducted at ALS Metallurgy in Kamloops, BC (ALS Metallurgy) in 2015 to 2019; and

 

4.Ambler Metals testwork conducted at ALS Metallurgy and SGS Mineral Services in 2021 to 2022.

 

In 2012, SGS Vancouver conducted a metallurgical test program to further study metallurgical responses of the samples produced from Zones 1, 2, 3, and 5 of the Arctic deposit. The flotation test procedures used talc pre-flotation, conventional copper-lead bulk flotation and zinc flotation, followed by copper and lead separation. In general, the 2012-2015 test results indicated that the samples responded well to the flowsheet tested. The average results of the locked cycle tests (without copper and lead separation) were as follows:

 

The copper recoveries to the bulk copper-lead concentrates ranged from 89% to 93% excluding the Zone 1 & 2 composite which produced a copper recovery of approximately 84%; the copper grades of the bulk concentrates were 24% to 28%.

 

Approximately 92% to 94% of the lead was recovered to the bulk copper–lead concentrates containing 9% to 13% lead.

  
Arctic ProjectPage 5
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The zinc recovery was 84.2% from Composite Zone 1 & 2, 93.0% from Composite Zone 3 and 90.5% from Composite Zone 5. On average, the zinc grades of the concentrates produced were higher than 55%, excluding the concentrate generated from Composite Zone 1 & 2, which contained only 44.5% zinc.

 

Gold and silver were predominantly recovered into the bulk copper–lead concentrates. Gold recoveries to this concentrate ranged from 65% to 80%, and silver recoveries ranged from 80% to 86%.

 

Using an open circuit procedure, the copper and lead separation tests on the bulk copper–lead concentrate produced from the locked cycle tests generated reasonable copper and lead separation. The copper concentrates produced contained approximately 28% to 31% copper, while the grades of the lead concentrates were in the range of 41% to 67% lead. In this testwork program, it appeared that most of the gold reported to the copper concentrate and on average the silver was equally recovered into the copper and lead concentrates. Subsequent testwork to better define the copper and lead separation process was conducted in 2017, including a more detailed evaluation of the precious metal deportment in the copper and lead separation process.

 

Grindability testing was completed during both the SGS Vancouver and ALS Metallurgy testwork programs to support the design and economics of efficient grinding of the Arctic materials. Semi-autogenous grind (SAG) mill test results included a single JKTech drop-weight test and 19 SAG media competency (SMC) tests using variability samples. Test results show the material is amenable to SAG milling and is relatively soft, with a reported breakage (axb) average value of 189.7. Bond ball mill work index (BWi) tests were completed on 44 samples and values ranged from 5.4 to 13.1 kWh/t with an average BWi of 8.82 kWh/t. Abrasion index (Ai) tests were completed on five samples and values fluctuated from 0.017 to 0.072 g for the measured samples. The data indicate that the samples are neither resistant nor abrasive to ball mill grinding. The materials are considered to be soft or very soft in terms of grinding requirements. The grinding testwork was used to support detailed grinding circuit design.

 

In 2017, ALS Metallurgy conducted detailed copper and lead separation flotation testwork using a bulk sample of copper–lead concentrate produced from the operation of a pilot plant. This testwork confirmed high lead recoveries in locked cycle testing of the copper–lead separation process and confirmed precious metal recoveries into the representative copper and lead concentrates. This testwork indicated a clear tendency of the gold values to follow the lead concentrate, giving it a significant gold grade and value. Detailed mineralogical analysis showed that a majority of gold values were occurring as liberated fine-grained gold particles.

 

The conclusions of testwork conducted both in 2012 and 2017 indicate that the Arctic materials are well-suited to the production of high-quality copper and zinc concentrates using flotation techniques which are industry standard. Copper and zinc recovery data were reported in the range of 88% to 92%, which reflected the high-grade nature of the deposit as well as the coarse-grained nature of these minerals. Grade variations within the deposit will be observed as indicated by the grade variations observed in variability samples, however, mill feed variability is expected to be limited and readily manageable with good plant operational practices. Lead concentrates have the potential to be of good quality and can also be impacted by zones of very high talc. Considerable care will be required to ensure maximum talc recovery to remove talc, which has the potential to dilute lead concentrate grades. The lead concentrate is also shown to be rich in precious metals, which has some advantages in terms of marketability of this material.

 

Ancillary testwork was completed by third party consultants on representative concentrate samples, to provide thickening and filtration data for the various concentrates. Settling and filtration rates were observed to be typical for sulphide concentrates and moisture contents in final filter cakes were observed to be lower than expected.

 

Metallurgical testwork was completed to provide representative tailings samples for use in detailed solids settling and compaction testwork to provide data for tailings design studies.

  
Arctic ProjectPage 6
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

A detailed study of water treatment chemistry was undertaken to evaluate and confirm the option of destroying cyanide contained in solutions from the proposed copper–lead separation process. The use of an SO2/air process in a small-scale pilot plant demonstrated removal of 99% of the contained cyanide and supported the concept of maintaining low cyanide concentrations within the proposed tailings pond solutions.

 

In 2021, various metallurgical testwork programs were conducted at ALS Metallurgy, SGS, and MO Group. ALS Metallurgy completed several testwork programs, including flotation testing with the Preflotation circuit only to establish talc performance; further flowsheet development testwork to investigate the benefits of sequential flotation versus the original bulk flow sheet; and a variability testwork to support the development of improved metallurgical recovery models.

 

The objective of the ALS Metallurgy program was to investigate bulk and sequential flotation flowsheets with composites formed from two parent composites, and then select a flowsheet for a geo-metallurgical evaluation through testing with variability samples.

 

The mineralization was amenable to either a bulk flowsheet followed by copper-lead separation, or a sequential flowsheet, both following a pre-flotation stage to remove talc.

 

Table 1-1 shows average performance obtained for the Avg Talc Composite in the Flowsheet Development phase of the testing.

 

Table 1-1:Comparison of Bulk versus Sequential Locked-Cycle Test Results – ALS 2021

 

   Assays   Distribution (%) 
Composite  Cu
(%)
   Pb
(%)
   Zn
(%)
   Ag
(g/t)
   Au
(g/t)
   Mg
(%)
   Cu   Pb   Zn   Ag   Au 
Avg Talc Bulk                                                       
Copper concentrate   28.0    0.86    4.27    181    4.17    0.46    87.3    8.3    9.1    36.0    60.9 
Lead concentrate   7.90    39.0    6.30    1124    4.75    1.23    5.1    78.1    2.8    46.0    14.3 
Zinc concentrate   0.87    0.38    55.9    41    0.35    0.04    1.9    2.6    83.3    5.7    3.5 
Avg Talc – Sequential                                                       
Copper concentrate   27.6    0.87    2.05    168    3.23    1.96    90.2    8.9    4.7    34.9    48.7 
Lead concentrate   2.72    49.3    9.71    1360    5.31    1.40    1.2    69.9    3.1    39.4    11.2 
Zinc concentrate   0.98    1.09    54.5    47    0.77    0.17    2.1    7.3    83.5    6.5    7.7 

 

Copper recovery to the copper concentrate was slightly higher for the sequential flowsheet; however, gold recovery to the copper concentrate was substantially lower. The lead concentrate grade for the Avg Talc composite could likely be improved over that shown above with optimization of copper-lead separation conditions given the higher lead concentrate grade measured with other composites.

 

Zinc circuit performance was similar for the two flowsheets, although higher zinc recovery to the copper concentrate was recorded for the bulk circuit. Magnesium content in the copper concentrate was higher for the sequential circuit, but similar in the lead concentrate for both circuits.

  
Arctic ProjectPage 7
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Based on economic analysis comparing the bulk and sequential circuit, the bulk circuit flowsheet was selected for the Variability testing.

 

An overall metallurgical balance for the project is summarized in Table 1-2. The projected metallurgical recoveries are based on an expected average recovery over the life-of-mine (LOM), and results of metallurgical variability testwork conducted in 2021 and 2022.

 

Table 1-2:Summary of Overall Metal Recovery – Arctic Project

 

      Concentrate Grade   Metal Recoveries 
Process stream  Mass
(%)
   Cu
(%)
   Pb
(%)
   Zn
(%)
   Au
(g/t)
   Ag
(g/t)
   Cu
(%)
   Pb
(%)
   Zn
(%)
   Au
(%)
   Ag
(%)
 
Process Feed   100    2.1    0.5    2.8    0.4    31.1    -    -    -    -    - 
Copper Conc.   6.3    30.3    1.7    0.7    3.4    160.5    92.1    19.4    1.6    52.2    32.4 
Lead Conc.   0.6    2.0    53.9    5.9    14.1    2425.8    0.6    61.3    1.3    21.4    48.8 
Zinc Conc.   4.7    1.0    0.5    53.6    0.3    38.3    2.2    4.4    88.4    3.2    5.7 
Tailings   88.4    0.1    0.1    0.3    0.1    4.6    5.1    14.8    8.7    23.2    13.1 

 

SGS conducted SAG Power Index (SPI®) tests to investigate the effect of friable ores on the plant throughput.

 

MO Group conducted talc circuit modelling using the data obtained from the ALS Metallurgy Preflotation testwork program to investigate the benefits of talc circuit open and closed-circuit cleaning. The MO Group also conducted dewatering and filtration testwork on the talc concentrate and final tailings generated from the Preflotation testwork program.

 

Thickening and filtration testwork were completed by the MO Group on representative preflotation concentrate and tailings samples, to investigate opportunities to improve water recovery and reduce operating costs. The results were used to incorporate a tailings thickener in the process plant flow sheet.

 

1.10Mineral Resource Estimates

 

Mineral resource estimates are performed from a 3D block model based on geostatistical applications using Leapfrog software. The resource estimate was generated using drill hole sample assay results and the interpretation of a geological model which relates to the spatial distribution of copper, lead, zinc, gold, and silver. The grade models have been validated using a combination of visual and statistical methods. The resources were classified according to their proximity to the sample data locations and are reported using the standards and definitions of S-K 1300. Model blocks estimated by three or more drill holes spaced at a maximum distance of 100 m are included in the Indicated category. Inferred blocks are within a maximum distance of 150 m from a drill hole.

  
Arctic ProjectPage 8
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The deposit is amenable to open pit extraction methods. The reasonable prospects for economic extraction was established by the constraining mineralization within a pit shell derived based on a series of technical and economic assumptions. Mineral Resources were established within the constraining pit shell using the copper equivalent (CuEq) grade of 0.5%.

 

Mineral Resources are reported in accordance with the standards and definitions of S-K 1300. The Mineral Resource estimate inclusive of Mineral Reserves is stated in Table 1-3. The Mineral Resource estimate exclusive of Mineral Reserves is stated in Table 1-4. All Indicated Mineral Resources have been converted to Mineral Reserves. Mineral Resources are reported in place (point of reference) and on a 100% basis; however, Trilogy’s attributable interest is 50% of the tonnes and metal content.

  
Arctic ProjectPage 9
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 1-3:Mineral Resource Summary Table, Inclusive of Mineral Reserves

 

      Average Grade   Contained Metal Content 
Confidence  Tonnage   Cu   Pb   Zn   Au   Ag   Cu   Pb   Zn   Au   Ag 
Category  (Mt)   (%)   (%)   (%)   (g/t)   (g/t)   (Mlb)   (Mlb)   (Mlb)   (koz)   (Moz) 
Indicated   35.7    2.98    0.79    4.09    0.59    45.2    2,347    621    3,216    675    52 
Inferred   4.5    1.92    0.70    2.93    0.43    35.6    189    69    288    62    5 

 

Notes:

 

1.Mineral Resources are current as of November 30, 2022 and were verified by a Wood QP.

2.Mineral Resources were prepared in accordance with the standards and definitions of S-K 1300.

3.Mineral Resources stated are contained within a conceptual pit shell developed using metal prices of $3.00/lb Cu, $0.90/lb Pb, $1.00/lb Zn, $1300/oz Au and $18/oz Ag and metallurgical recoveries of 92% Cu, 77% Pb, 88% Zn, 63% Au and 56% Ag and operating costs of $3/t mining and $35/t process and G&A. The assumed average pit slope angle is 43°.

4.The cut-off grade is 0.5% copper equivalent. CuEq = (Cu%x0.92) + (Zn%x0.290) + (Pb%x0.231) + (Au g/tx0.398) + (Ag g/tx0.005).

5.As a result of flattening the north end of the reserve pit to stabilize the pit wall due to the presence of talc, a portion of the reserve pit extended beyond the resource constraining pit shell. Approximately 568kt of 1.72% Cu, 0.77% Pb, 0.23 g/t Au and 21.3 g/t Ag in the Indicated category, and approximately 319 kt of 2.01% Cu, 0.87% Pb, 2.53% Zn, 0.50 g/t Au and 37.5 g/t Ag in the Inferred category were added to the Mineral Resource tabulation.

6.The Mineral Resource estimate is reported inclusive of those Mineral Resource that were converted to Mineral Reserves.

7. Trilogy’s attributable interest is 50% of the tonnage and contained metal stated in the table.

8.Figures may not sum due to rounding.

 

Table 1-4:Mineral Resource Summary Table, Exclusive of Mineral Reserves

 

      Average Grade   Contained Metal Content 
Confidence  Tonnage   Cu   Pb   Zn   Au   Ag   Cu   Pb   Zn   Au   Ag 
Category  (Mt)   (%)   (%)   (%)   (g/t)   (g/t)   (Mlb)   (Mlb)   (Mlb)   (koz)   (Moz) 
Inferred   4.5    1.92    0.70    2.93    0.43    35.6    189    69    288    62    5 

 

Notes:

 

1.Mineral Resources are current as of November 30, 2022 and were verified by a Wood QP.

2.Mineral Resources were prepared in accordance with the standards and definitions of S-K 1300.

3.Mineral Resources stated are contained within a conceptual pit shell developed using metal prices of $3.00/lb Cu, $0.90/lb Pb, $1.00/lb Zn, $1,300/oz Au and $18/oz Ag and metallurgical recoveries of 92% Cu, 77% Pb, 88% Zn, 63% Au and 56% Ag and operating costs of $3/t mining and $35/t process and general and administrative costs. The assumed average pit slope angle is 43º.

4.As a result of flattening the north end of the reserve pit to stabilize the pit wall due to the presence of talc, a portion of the reserve pit extended beyond the resource constraining pit shell and approximately 319 kt of 2.01% Cu, 0.87% Pb, 2.53% Zn, 0.50 g/t Au and 37.5 g/t Ag in the Inferred category were added to the Mineral Resource tabulation.

5.The cut-off grade is 0.5% copper equivalent: CuEq = (Cu% x 0.92) + (Zn% x 0.290) + (Pb% x 0.231) + (Au g/t x 0.398) + (Ag g/t x 0.005).

6.The Mineral Resource estimate is reported exclusive of those Mineral Resources that were converted to Mineral Reserves.

7. Trilogy’s attributable interest is 50% of the tonnage and contained metal stated in the table.

8.Figures may not sum due to rounding.

  
Arctic ProjectPage 10
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1.11Mineral Reserve Estimates

 

Mineral Reserves were classified in accordance with the standards and definitions of S-K 1300. Modifying factors were applied to the Indicated Mineral Resources to convert them to Probable Mineral Reserves. Mineral Reserves for the Arctic deposit incorporate appropriate mining dilution and mining recovery estimations for the open pit mining method.

 

The pit shell that defines the ultimate pit limit was derived in Whittle using the Pseudoflow pit optimization algorithm. The optimization procedure uses the block value and pit slopes to determine a group of blocks representing pits of valid slopes that yield the maximum profit. The block value is calculated using information stored in the geological block model, commodity prices, mining and processing costs, process recovery, and the sales cost for the metals produced. The pit slopes are used as constraints for removal precedence of the blocks (Xiaoyu Bai, et al., 2017). Table 1-5 provides a summary of the primary optimization inputs.

 

Table 1-5:Optimization Inputs

 

Parameter  Unit  Value   Cu Conc.   Pb Conc.   Zn Conc. 
                    
Metal Prices 
Copper  $/lb   3.46          
Lead  $/lb   0.91          
Zinc  $/lb   1.12                
Gold  $/oz   1,615                
Silver  $/oz   21.17                
Discount Rate  %   8                
Dilution and Mine Losses  %   Estimated in a block-by-block basis, adding up 30% to 40%. 
Mining Cost 
Reference Bench Elevation  m   790                
Base Cost  $/t   2.52                
Incremental Mining Cost                       
Uphill (below 790m)  $/t/5m   0.02                
Downhill (above 790m)  $/t/5m   0.012                
Process Costs 
Operating Cost  $/t milled   18.31                
G&A  $/t milled   5.83                
Sustaining Capital  $/t milled   2.37                
Road Toll Cost  $/t milled   8.04                
Closure  $/t milled   4.27                
Processing Rate  kt/d   10                

  
Arctic ProjectPage 11
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Parameter  Unit   Value   Cu Conc.   Pb Conc.   Zn Conc. 
                     
Process Recovery
Copper   %         89.9    2.4    2.7 
Lead   %         8.1    79    2.2 
Zinc   %         3.4    0.4    90.6 
Gold   %         10.9    62.1    5.4 
Silver   %         26.4    63.1    3.4 
Payable – Main Element   %         96.5    95    85 
Treatment Cost   $/dmt         80    160    215 
Refining Cost
Copper   $/lb         0.08    -    - 
Gold   $/oz         5    10    - 
Silver   $/oz         0.5    1.25    - 
Transport Cost   $/dmt    271                
Concentrate Losses   % weight    0.42                
Insurance Cost   %    0.15                
Representation/Marketing   $/wmt    2.5                
Slope Angles
Geotechnical Sector 1 (2L-E)   degrees   Variable based on slope dip direction. IRA ranging from 26 to 56. 
Geotechnical Sector 2 (2L-W)   degrees   Variable based on slope dip direction IRA ranging from 38 to 56. 
Geotechnical Sector 3 (2U)   degrees   Variable based on slope dip direction IRA ranging from 29 to 56. 
Geotechnical Sector 4 (3)   degrees   Variable based on slope dip direction IRA ranging from 30 to 56. 
Geotechnical Sector 5 (4L)   degrees   Variable based on slope dip direction IRA ranging from 34 to 56. 
Geotechnical Sector 6 (4U)   degrees   Variable based on slope dip direction IRA ranging from 37 to 56. 
Royalties
NANA Surface Use   %NSR    1                

 

Note: IRA = inter ramp angle

  
Arctic ProjectPage 12
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The Mineral Reserve estimates are shown in Table 1-6. Only Probable Mineral Reserves have been classified. The point of reference for the Mineral Reserves is defined at the point where the ore is delivered to the processing plant. Trilogy’s attributable interest is 50% of the tonnes of the Mineral Reserves.

 

Table 1-6:Mineral Reserve Statement

 

   Tonnage   Average Grade 
Confidence Category  Mt   Cu (%)   Pb (%)   Zn (%)   Au (g/t)   Ag (g/t) 
Probable Mineral Reserves   46.7    2.11    0.56    2.90    0.42    31.8 

 

Notes:

 

1.Mineral Reserves estimates are current as of November 30, 2022 and were prepared by a Wood QP.

2.Mineral Reserves were estimated assuming open pit mining methods and include a combination of internal and contact dilution. Total dilution is expected to be between 30% and 40%. Pit slopes vary by sector and range from 26° to 56°. A marginal NSR cut-off of $38.8 /t is used.

3.Mineral Reserves are based on prices of $3.46/lb Cu, $0.91/lb Pb, $1.12/lb Zn, $1,615/oz Au, and $21.17/oz Ag.

4.Variable process recoveries averaging 92.2% Cu in Cu concentrate, 62.2% Pb in Pb concentrate, 8887.6% Zn in Zn concentrate, 16.0% Pb in Cu concentrate, 1.9% Zn in Cu concentrate, 47.2% Au in Cu concentrate, 32.7% Ag in Cu concentrate, 0.8% Cu in Pb concentrate, 1.3% Zn in Pb concentrate, 26.1% Au in Pb concentrate, 48.7% Ag in Pb concentrate, 2.1% Cu in Zn concentrate, 4.5% Pb in Zn concentrate, 3.3% Au in Zn concentrate, 5.8% Ag in Zn concentrate.

5.Mineral Reserves are based on mining cost of $2.52/t incremented at $0.02/t/5m and $0.012/t/5m below and above 790 m elevation, respectively.

6.Costs applied to processed material following process operating cost of $18.31/t, G&A of $5.83/t, sustaining capital cost of $2.37/t, closure cost of $4.27/t, road toll cost of $8.04/t.

7.Strip ratio (waste: ore) is 7.3:1.

8.Selling terms following payables of 96.5% of Cu, 95% of Pb and 85% of Zn, treatment costs of $80/t Cu concentrate, $160/t Pb concentrate and $215/t Zn concentrate; refining costs of $0.08/lb Cu in Cu concentrate, $10/oz Au, $1.25/oz Ag in Pb concentrate; and transport cost $270.98/t concentrate.

9.Fixed royalty percentage of 1% NSR.

10. Trilogy’s attributable interest is 50% of the tonnage stated in the table.

 

Specific risks to the Arctic Mineral Reserve estimate include:

 

The uncertainty in the construction and timing of the Ambler Mining District Industrial Access Project (AMDIAP) road, also called the Ambler Access Project (AAP), and whether a favourable road toll agreement can be negotiated.

 

The presence of talc layers in the rock that have not been included in the current geological model could affect metallurgical recoveries and slope stability.

 

Other risk factors that may affect the Mineral Reserve estimates include: metal price assumptions; changes to the assumptions used to generate the NSR cut-offs that constrains the estimate; changes in local interpretations of mineralization geometry and continuity of mineralized zones; changes to geological and mineralization shapes, and geological and grade continuity assumptions; density and domain assignments; changes to geotechnical and hydrological assumptions, changes to mining and metallurgical recovery assumptions; changes to the input and design parameter assumptions that pertain to the conceptual pit constraining the estimates; assumptions as to concentrate marketability, payability and penalty terms; assumptions as to the continued ability to access the site, retain mineral tenure and obtain surface rights titles, obtain environment and other regulatory permits, and maintain the social license to operate.

  
Arctic ProjectPage 13
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1.12Mining Methods

 

The Arctic Project is designed as a conventional truck-shovel operation with 144 t trucks and 15 m3 shovels. The pit design includes four nested phases to balance stripping requirements while satisfying the concentrator requirements.

 

The design parameters include a ramp width of 30 m, road grades of 10%, bench height of 5 m, targeted mining width between 70 m and 100 m, berm interval of 20 m, variable slope angles by sector and a minimum mining width of 30 m.

 

The smoothed final pit design contains approximately 46.7 Mt of ore and 340.2 Mt of waste for a resulting stripping ratio of 7.3:1. Within the 46.7 Mt of ore, the average grades are estimated to be 2.11% Cu, 2.90% Zn, 0.56% Pb, 0.42 g/t Au and 31.8 g/t Ag.

 

The scheduling constraints set the maximum mining capacity at 35 Mt/a, and the maximum process capacity at 10 kt/d. The production schedule based on the Probable Mineral Reserves shows a total LOM of 15 years, including 2 years of pre-production and 13 years of production.

 

1.13Processing and Recovery Methods

 

The 10,000 t/d process plant design is conventional for the industry and will operate two 12- hour shifts per day, 365 d/a with an overall plant availability of 92%. The process plant will produce three concentrates: 1) copper concentrate, 2) zinc concentrate, and 3) lead concentrate. Gold and silver are expected to be payable at a smelter; both silver and gold are expected to be payable in the copper and lead concentrates.

 

While there are several deleterious elements reporting to the concentrates at levels that could incur penalties, special processing provisions have been included in the flowsheet to make a readily saleable concentrate. The presence of naturally hydrophobic talc minerals was consistently observed in the various testwork programs. There is little reason to expect concentrates will be impaired by talc contamination as talc can be effectively removed from the flotation process prior to base metal flotation. Talc and fluorine levels will be managed by optimization of the talc pre-float circuit, effectively removing talc and fluorine to ensure the quality of the lead concentrate.

 

The mill feed will be hauled from the open pit to a primary crushing facility where the material will be crushed by a jaw crusher to a particle size of 80% passing 80 mm.

 

The crushed material will be ground by two stages of grinding, consisting of one SAG mill and one ball mill in closed circuit with hydrocyclones (SAB circuit). The hydrocyclone overflow with a grind size of approximately 80% passing 70 μm will first undergo talc pre-flotation, and then be processed by conventional bulk flotation (to recover copper, lead, and associated gold and silver), followed by zinc flotation. The bulk rougher concentrate will be cleaned and followed by copper and lead separation to produce a lead concentrate and a copper concentrate. The final tailings from the zinc flotation circuit will be pumped to a tailings management facility (TMF). Copper, lead, and zinc concentrates will be thickened and pressure-filtered before being transported by truck to a port and shipped to smelters.

 

Based on the mine plan developed for the Report and metallurgical testwork results, the LOM average metal recoveries and concentrate grades are as presented in Table 1-7.

  
Arctic ProjectPage 14
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 1-7:LOM Average Recovery and Grade

 

Description  Unit   Cu con  Pb con  Zn con 
LOM Production  t/a   234,132  23,300   174,202 
Grade  %   30.3% Cu  53.9% Pb   53.7% Zn 
Recovery  %   92.1% Cu
52.2% Au
32.5% Ag
  61.3% Pb
21.6% Au
48.6% Ag
   88.5% Zn 

 

The recovery plan includes provision for reagents, and water and power requirements.

  

1.14Infrastructure

 

1.14.1Infrastructure Requirements

 

The Project site is a remote, greenfield site that is remote from existing infrastructure. Infrastructure that will be required for the mining and processing operations will include:

 

Open pit mine

 

Stockpiles and Waste Rock Facility (WRF)

 

Truck workshop, truck wash, mine offices, mine dry facility and warehouse

 

Administration building

 

Mill dry facility

 

Plant workshop and warehouse

 

Primary crushing building

 

Fine ore stockpile building

 

Process plant and laboratory

 

Concentrate loadout building

 

Reagent storage and handling building

 

Raw water supply building

 

Explosives storage silos and magazines

 

Avalanche mitigation structures

 

TMF

 

Surface water diversion and collection channels, culverts, and containment structures

 

Waste rock collection pond (WRCP)

 

Water treatment plant (WTP)

  
Arctic ProjectPage 15
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Process pond

 

1.14.2Access

 

The Project site will be accessed through a combination of State of Alaska-owned highways (existing), an Alaska Industrial Development and Export Authority (AIDEA)-owned private road (proposed) and Ambler Metals-owned access roads (proposed). The AAP road is proposed by AIDEA to connect the Ambler Mining District to the Dalton Highway. The AAP road will be permitted as a private road with restricted access for industrial use. To connect the Arctic Project site and the existing exploration camp to the proposed AAP road, a 30.7 km access road (the Arctic access road) will need to be built.

 

The State of Alaska-owned, public Dahl Creek airport will require upgrades to support the planned regular transportation of crews to and from Fairbanks. The cost of these upgrades has been included in the capital cost estimate.

 

1.14.3Power

 

Power generation will be by five diesel generators, producing a supply voltage of 13.8 kV. The total connected load will be 25.9 MW with a normal running load of 21.0 MW. Diesel will be supplied via existing fuel supply networks in the region and shipped along the AAP road.

 

1.14.4Accommodation

 

The Project will require three self-contained camps, in two different locations, equipped with their own power and heat generation capabilities, potable WTP (PWTP), sewage treatment plant (STP), and garbage incinerator. The existing 90-person Bornite Camp currently used for exploration will be expanded and used to start the construction of the Arctic access road and the logistics yard and construction camp. This Bornite Camp will be expanded and available prior to surface access from the Dalton Highway via the AAP road is available. A 250-person construction camp (CC) will be constructed at location near the intersection of the AAP road and Arctic Mine Access road (AMA), across the road from the Logistics Yard. CC will be constructed when limited access via the AAP is available for the transport of camp modules. A 400-person Permanent Accommodations Facility (PAF) will be constructed in the same location as CC. The PAF will be constructed when the AAP is available to transportation of the modules by truck and will be operational by the peak accommodation requirements for the construction phase. CC will be adjacent to the PAF, and the accommodation sections will be integrated and operated with the kitchen, dining, and support facilities of the PAF. The PWTP, STP, and garbage incinerator will be transported to site and constructed with the CC and will be sized to support the future PAF and the capacities of both the CC and PAF (650-persons).

 

1.14.5Waste Rock Facility

 

The WRF will be developed north of the Arctic pit in the upper part of the Subarctic Creek valley. The WRF is designed as part of the tailings dam structure to provide a buttress for tailings containment in the adjacent footprint. The total volume of waste rock is expected to be 162.6 Mm3 (340 Mt); however, there is potential for expanded volume in the waste if placement density is <2.0 t/m3. The WRF will have a final height of 340 m to an elevation of 990 masl and is planned to be constructed in lifts of either 5, 10 or 20 m height with catch benches every 20 m to achieve an overall slope angle of 2.5H:1V.

 

Most of the waste rock is anticipated to be potentially acid-generating (PAG) and there will be no separation of waste based on acid generation potential. Rather, seepage from the WRF will be collected and treated.

  
Arctic ProjectPage 16
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1.14.6Overburden Stockpiles

 

There will also be three overburden stockpiles to store the stripped topsoil and overburden from the TMF and WRF footprint. The topsoil stockpile will be placed between the haul roads to store up to 325,000 m3 while the overburden stockpile will be located south of the WRF to store up to 2,200,000 m3.

 

1.14.7Tailings Management Facility

 

The TMF will be located at the headwaters of Subarctic Creek, in the upper-most portion of the creek valley. The 59 ha footprint of the TMF will be fully lined with a geomembrane liner. Tailings containment will be provided by an engineered dam, buttressed by the WRF that will be constructed immediately downstream of the TMF, and the natural topography on the valley sides. A starter dam will be constructed to elevation 830 m. Three subsequent raises will bring the final dam crest elevation to 892 m, which is 98 m lower than the final elevation of the WRF. The TMF is designed to store approximately 37.4Mm3 (41.2 Mt) of tailings produced over the 13-year mine life, 3.3 Mm3 of additional pond water, as well as 1.5 times the probable maximum flood, with 2.5 m of freeboard.

 

1.14.8Water Management

 

The proposed mine development is located in the valley of Subarctic Creek, a tributary to the Shungnak River. A surface water management system will be constructed to segregate contact and non-contact water. Non-contact water will be diverted around mine infrastructure to Subarctic Creek. A groundwater seepage monitoring and collection system will be located down gradient of the WRF and seepage collection pond. Contact water will be conveyed to treatment facilities prior to discharge to the receiving environment.

 

A WRCP will be located directly below the toe of the WRF and will be used to collect seepage from the WRF, runoff from the WRF and haul road corridor area, and water pumped from the open pit.

 

The Project water and load balance model was updated to include the current water management plan. The model indicates that during operations, excess water from the WRCP will need to be treated prior to discharge to the receiving environment. During closure, water from the dewatering of the TMF will also need to be treated prior to discharge to the receiving environment.

 

1.14.9Water Treatment Plant

 

It was assumed the site will be assigned water quality-based effluent limits (WQBEL) matching the state’s Water Quality Standards (WQS) for the nearby Subarctic Creek. Therefore, Water Treatment Plant (WTP) is designed to treat all parameters in the predicted site wastewater to the WQS of Subarctic Creek. This will eliminate the need for a mixing zone and allow treated water to be discharged year-round if needed.

 

A single WTP, built in stages, will be used. During Operations phase the WTP will treat effluent from the Waste Rock Collection Pond (WRCP), and during Closure phase effluent from the pit. The WTP will initially consist of chemical/physical treatment with reverse osmosis (RO) filtration. During operations, the RO reject will be sent to the TMF, and only RO permeate will be discharged to Subarctic Creek. When the TMF is closed at the end of the operations, a biological/chemical/physical plant will be added to treat the RO reject. The biologic plant discharge will be mixed with the RO prior to discharge. 

  
Arctic ProjectPage 17
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1.15Market Studies

 

Metal pricing was guided by 3-year trailing average prices and long-term price forecasts from analysts as published by CIBC in 2022.

 

The long-term consensus metal price assumptions selected for the economic analysis in the Report were:

 

Copper: $3.65/lb

Zinc: $1.15/lb

Lead: $1.00/lb

Gold: $1,650/oz

Silver: $21.00/oz

 

Smelter terms were prepared in January 2023 by StoneHouse Consulting Inc. Smelter terms were applied for the delivery of copper, zinc and lead concentrate. It was assumed that delivery of all concentrates would be to a smelter in the Asia Pacific region at currently available freight rates. Total transport costs for the concentrate are estimated at $324.37/dmt.

 

1.16Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups

 

The Arctic Project area includes the Ambler lowlands and Subarctic Creek within the Shungnak River drainage. A significant amount of baseline environmental data collection has occurred in the area including surface and groundwater quality sampling, surface hydrology monitoring, wetlands mapping, aquatic life surveys, avian and mammal habitat surveys, cultural resource surveys, hydrogeology studies, meteorological monitoring, and metal leaching and acid rock drainage (ML/ARD) studies.

 

1.16.1Permitting Considerations

 

Current mineral exploration activities are conducted at the Arctic deposit under State of Alaska and Northwest Arctic Borough (NWAB) permits. The State of Alaska Miscellaneous Land Use Permit (MLUP) and the NWAB Permit both expires at the end of 2022 and will be renewed.

 

Mine development permitting will be largely driven by the underlying land ownership with regulatory requirements varying depending on land ownership. The Arctic Project area includes patented mining claims owned by Ambler Metals (private land), NANA land (private land), and State of Alaska land.

 

The Arctic deposit is mainly on private lands owned by Ambler Metals and infrastructure for the Arctic Project is situated to a large extent on State land. It will be necessary to obtain a Plan of Operation Approval (which includes the Reclamation Plan and Closure Cost Estimate) from the Alaska Department of Natural Resources (ADNR). The Project will also require certificates to construct and operate dams (tailings and water storage) from the ADNR (Dam Safety Unit) as well as water use and discharge authorizations, an upland mining lease and a mill site lease, as well as several minor permits including those that authorize access to construction material sites from ADNR.

 

The Alaska Department of Environmental Conservation (ADEC) would authorize waste management under an Integrated Waste Management permit, air emissions during construction and operations under an air permit, and an Alaska Pollutant Discharge Elimination System (APDES) permit for any wastewater discharges, and a Multi-Sector General Permit for stormwater discharges. The ADEC would also be required to review the US Army Corps of Engineers (USACE) Section 404 permit to certify that it complies with Section 401 of the Clean Water Act (CWA).

  
Arctic ProjectPage 18
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The Alaska Department of Fish and Game (ADF&G) would have to authorize any culverts or bridges that are required to cross fish-bearing streams or other impacts to fish-bearing streams that result in the altering or affecting fish habitat.

 

US Army Corps of Engineers (USACE) would require a CWA Section 404 permit for dredging and filling activities in Waters of the United States including jurisdictional wetlands. The USACE Section 404 permitting action would require the USACE to comply with the Natural Environmental Policy Act (NEPA) and, for a project of this magnitude, the development of an Environmental Impact Statement (EIS) is anticipated. The USACE would likely be the lead federal agency for the NEPA process. As part of the Section 404 permitting process, the Arctic Project will have to meet USACE wetlands guidelines to avoid, minimize and mitigate impacts to waters of the US including wetlands.

 

The Arctic Project will also have to obtain approval for a Master Plan from the NWAB. In addition, actions will have to be taken to change the borough zoning for the Arctic Project area from Subsistence Conservation and General Conservation to Resource Development and Transportation.

 

The overall timeline required for permitting would be largely driven by the time required for the NEPA process, which is triggered by the submission of the Section 404 permit application to the USACE. The timeline includes the development and publication of a draft and final EIS and ends with a Record of Decision and Section 404-permit issuance. In Alaska, the EIS and other State and Federal permitting processes are generally coordinated so that permitting and environmental review occurs in parallel. The NEPA process could require about three years to complete and could potentially take longer.

 

1.16.2Social and Community

 

The Arctic Project is located approximately 40 km northeast of the villages of Shungnak and Kobuk, and 65 km east-northeast of the community of Ambler. The population in these villages are 151 in Kobuk (2020 Census), 210 in Shungnak (2020 Census), and 275 in Ambler (2020 Census). Residents largely live a subsistence lifestyle with incomes supplemented by guiding, local development projects, employment through tribal and city councils, government aid, and employment both in and outside of their home villages.

 

The Arctic Project has the potential to significantly improve work opportunities for residents during the exploration phase, construction, and during full operation. Trilogy’s joint venture, Ambler Metals works directly with the Upper Kobuk villages and communities throughout the region to employ residents as mechanics, geotechnicians, core cutters, administrative staff, camp services, heavy equipment operators, drill helpers, and environmental technicians.

 

Stakeholder outreach and community meetings in the region by the Project’s owners over many years have provided the opportunity to engage with residents, provide updated information on the project and future plans for the UKMP, hear concerns, answer questions, and build relationships.

 

This engagement has also identified various hurdles residents have faced when applying for employment. Opportunities have been created for NANA shareholders to apply and receive educational scholarships, participate in job shadowing at Bornite, driver’s license courses, and heavy equipment operator training sponsored by the Project’s owners.

 

It is the company’s goal to continue and grow these efforts throughout the permitting process and the life of the project – encouraging and supporting education, job training, employment, and economic growth.

  
Arctic ProjectPage 19
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1.16.3Closure Planning

 

Mine reclamation and closure are largely driven by State of Alaska regulations that specify that a mine must be reclaimed concurrent with mining operations to the greatest extent possible and then closed in a way that leaves the site stable in terms of erosion and avoids degradation of water quality from acid rock drainage or metal leaching on the site. A detailed Reclamation Plan will be submitted to the State of Alaska agencies for review and approval in the future, during the formal mine permitting process.

 

Owing to the fact that the Arctic Project is likely to have facilities on a combination of private (patented mining claims and native land) and State land, the Reclamation Plan will be submitted and approved as part of the Plan of Operations, which is approved by the ADNR. However, since the Reclamation and Closure Plan must meet regulations of both ADNR and the ADEC, both agencies will review and approve the Reclamation Plan. In addition, private landowners must formally concur with the portion of the Reclamation Plan for their lands so that it is compatible with their intended post-mining land use.

 

1.17Capital and Operating Cost Estimates

 

1.17.1Capital Costs

 

The capital cost estimate has an estimated accuracy of ±15% and uses Q3/Q4-2022 US dollars as the base currency. The total estimated initial capital cost for the design, construction, installation, and commissioning of the Arctic Project is estimated to be $1,177 million including ≤15% contingency. A summary of the estimated initial capital cost, sustaining capital cost and closure costs is shown in Table 1-8.

 

Table 1-8:Capital Cost Summary

 

WBS
Level 1
   WBS Level 1 Description  Initial Capex
($ M)
   Sustaining Capex
($ M)
   Total Capex
($ M)
 
1000   Mining   277.4    17.5    294.9 
2000   Crushing   42.5    0    42.5 
3000   Process Plant   158.0    1.3    159.3 
4000   Tailings   88.3    32.4    120.7 
5000   On-site Infrastructure   172.8    35.1    207.9 
6000   Off-site Infrastructure   75.8    0    75.8 
Sub-total Direct Costs   834.1    86.3    920.4 
7000   Indirects   177.4    15.1    192.5 
8000   Contingency (~12% of total project cost)   138.5    13.0    151.5 
9000   Owner’s Costs   26.8    0    26.8 
Sub-total Indirect Costs    342.7    28.1    370.8 
Project Total   1,176.8    114.4    1,291.2 
Project Total – Closure Costs             170.8 

  
Arctic ProjectPage 20
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1.17.2Operating Costs

 

The operating cost estimates use US dollars as the base currency and have an accuracy of ±15% and include contingency. An average operating cost was estimated for the Arctic Project based on the proposed mining schedule. These costs included mining, processing, G&A, surface services, and road toll & maintenance costs. The average LOM unit operating cost for the Arctic Project is estimated to be $59.83/t milled. The breakdown of costs in Table 1-9 is estimated based on the LOM average mill feed rate of 3,650,000 t/a.

 

All pre-production costs have been included in the capital cost estimate in Section 1.1 above.

 

Table 1-9:Overall Operating Cost Estimate

 

Description  LOM Average Unit Operating Cost
($/ t milled)
   LOM Average Annual Cost
($ M/a)
   Percentage of Total Annual
Operating Costs
 
Mining*   22.49    82.1    37.6%
Processing   22.60    82.5    37.8%
G&A   5.85    21.3    9.8%
Road Toll and Maintenance   7.72    28.2    12.9%
Water Treatment   1.17    4.3    2.0%
Total Operating Cost   59.83    218.4    100%

 

* Excludes pre-production costs. Includes contingency which is less than 15%.

 

1.18Economic Analysis

 

The results of this economic analysis represent forward looking information. The results depend on the inputs that are subject to several known and unknown risks, uncertainties, and other factors that may cause actual results to differ materially from those presented in this section. Information that is forward looking includes mineral reserve estimates, commodity prices, the proposed mine production plan, construction schedule, projected recovery rates, proposed capital and operating cost estimates, closure cost estimates, toll road cost estimates, and assumptions on geotechnical, environmental, permitting, royalties, and hydrogeological information.

 

An economic analysis was undertaken on a 100% project ownership basis to determine the internal rate of return (IRR), net present value (NPV) and payback on initial investment of the Arctic Project. Trilogy holds 50% interest in the Arctic Project through its ownership in Ambler Metals. The Project consists of a three-year construction period, followed by 13 years of production.

 

Ausenco developed a pre-tax cash flow model for the Arctic Project and the NPV and IRR were calculated at the beginning of the construction period in Year -3.

 

The pre-tax financial model incorporated the production schedule and smelter term assumptions to produce annual recovered payable metal, or gross revenue, in each concentrate stream by year. Off-site costs, including the applicable refining and treatment costs, penalties, concentrate transportation charges, marketing and representation fees, and royalties were then deducted from gross revenue to determine the NSR. The operating cash flow was then produced by deducting annual mining, processing, G&A, surface services, and road toll & maintenance charges from the NSR. Initial and sustaining capital was deducted from the operating cash flow in the years they occur, to determine the net cash flow before taxes. Initial capital cost includes all estimated expenditures in the construction period, from Year -3 to Year -1 inclusive. First production occurs at the beginning of Year 1. Sustaining capital expenditure includes all capital expenditures purchased after first production, including mine closure and rehabilitation. The model includes an allocation of a 1% NSR attributable to NANA.

  
Arctic ProjectPage 21
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

With total capital costs of $1,719 million over LOM ($1,177 million initial capital cost, $114 million sustaining capital cost and $428 million closure costs), the project demonstrates a pre-tax NPV of $1,500 million at an 8% discount rate, IRR of 25.8% and payback period of 2.9 years. Post-tax financials have an NPV of $1,108 million at an 8% discount rate, IRR of 22.8% and payback period of 3.1 years.

 

1.19Interpretations and Conclusions

 

The Arctic deposit will be mined at an annual rate of 35 Mt of ore per year with an overall stripping ratio of 7.3. Ore will be processed by conventional methods to annually produce 234 kt of copper, 23 kt of lead, and 174 kt of zinc, all in concentrates for provision to third party refiners. Waste and tailings materials will be stored in surface facilities, which will be closed and reclaimed at the end of the mine; contact water will be treated and discharged to the environment throughout the LOM. Precious metals attendant with the concentrates will be largely payable. While there are deleterious elements reporting to the concentrates at levels that could incur penalties, special processing provisions have been included in the flowsheet to make a readily saleable concentrate.

 

In terms of project execution, the mine requires nominally two years of pre-strip operations, tailings pond starter dam development and water accumulation before actual production mining operations can commence.

 

For that pre-strip work to start, the Arctic access road from the AMDIAP intersection to the mine site will have to be constructed to at least a pioneer road condition that will allow the mine fleet and the support facilities to be delivered, built, and made operational.

 

Positive financial results support the declaration of Mineral Reserves.

 

1.20Recommendations

 

It is the QPs’ opinion that the identified technical and economic risks and uncertainly related to the property can be reduced and improved with the additional recommended work programs as outlined below, helping to continue developing the Project through engineering and de-risking, and into construction at a total cost of $14.4 million.

 

Table 1-10 and the following subsections summarize the key recommendations arising from a review of each major area of investigation completed as part of this study to improve the base case design.

  
Arctic ProjectPage 22
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 1-10:Summary of Recommended Work Packages

 

Description  Cost ($) 
Mining   1,073,000 
Geology and Resource Models   10,190,000 
Open Pit Geotechnical Work   150,000 
Hydrogeology   490,000 
Tailings Management Facility   1,420,000 
Closure   250,000 
Water Treatment   170,000 
Metallurgical Testing   175,000 
Recovery Methods   350,000 
Operational Readiness Plan   120,000 
Total   14,388,000 

 

1.20.1Mining

 

Perform a SMU study to define an optimal block size that can support the envisioned production rate while minimizing dilution

 

Requote explosives as Ammonium nitrate prices are currently in record highs due to the Ukraine-Russia conflict

 

Assess the use of alternate fuel sources for the mine mobile equipment

 

Confirm the location, thickness, and continuity of the talc layers near to the northeast wall of the final pit.

 

1.20.2Geology and Resource Models

 

Bias in historical copper and lead assays: compare the current Mineral Resource estimate with an estimate prepared using a correction factor applied to the historic Cu and Pb assay values that remain in the assay database or an estimate that does not use these historical intervals

 

Bias in predicted SG values: review methodology and dataset used to generate the predicted SG values to minimize or mitigate apparent bias

 

Mineral Resource Classification confidence related to geological complexity: consider putting additional in-fill holes in drill grids to mitigate the risk of complex geology within the first 5 years of production. This is recommended to classify Measured Resources which can then be converted to Proven Mineral Reserves and provide high confidence in the production plan at project start and payback period.

  
Arctic ProjectPage 23
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Update the geological and resource model using all available data, including that from the 2022 drilling program

 

Review and update variogram models for all metals and SG using all available data

 

Review and update the resource model estimation parameters for all metals and SG

 

Review the current compositing length of 1m that is more in agreement with the average sample length

 

Update the geological model wireframes with all available data.

 

Address minor database issues: transcription error checks, removing survey measurements causing excessive deviation, reviewing detection limits, and including additional fields to indicate if chosen values are supported by QC

 

1.20.3Open Pit Geotechnical work

 

Update the 3D talc model to include all available drilling and laboratory testing data and complete a geotechnical review to update the slope designs

 

Consider potential slope instability risks identified in the interim and final mining phases of the open pit design

 

Re-evaluate seismic impact on the slope design

 

Review the pore pressure monitoring system and mitigation plan as additional data becomes available, adopting mitigation efforts as appropriate.

 

1.20.4Hydrogeology

 

Update the hydrogeological conceptual model for the pit and valley areas as more data becomes available

 

For the pit, continue water level monitoring, assess potential effects of seasonal or rapid and high amplitude recharge events (i.e., freshet), assess pit sump locations, assess drainage ditches around and set back from the pit perimeter, consider snow removal or clearing off high elevation portions of the pit, update pit Groundwater Management Plan as mine design advances, and install general pit perimeter groundwater monitoring on the north, south and west sides of the pit.

 

For the valley bottom, conduct hydrogeological drilling at location of the groundwater seepage interception system (SIS), update conceptual model, update estimates of potential groundwater bypass of the WRCP and the groundwater SIS design, and initiate baseline monitoring of groundwater quality around groundwater SIS.

 

1.20.5Tailings Management Facility

 

Complete geotechnical and hydrogeological investigations in the foundations of the TMF, WRF, WRCP, and Process Pond including borehole drilling and laboratory testing

 

Conduct Dam Breach Assessment, based on site specific hazard assessment for the TMF, the WRCP and Process pond

 

Finite element consolidation and seepage modelling of the TMF

 

Tailings deposition planning and water balance update

 

Evaluate tailings consolidation and requirement for an underdrain system

 

Update WRF, TMF, WRCP, and Process Pond stability analyses (including liquefaction assessment) based on additional field investigation results and lab testing

  
Arctic ProjectPage 24
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Evaluate whether heat or gas generation during oxidation of waste rock may adversely affect the closure cover.

 

1.20.6Closure

 

Conduct revegetation and cover study, and conduct trials during operations to develop a revegetation program, including climatic variables

 

Consult with the Alaska Plant Materials Center to develop a revegetation program utilizing native species to determine the optimal growth media depth, amendments, and soil cover to optimize plant survival.

 

1.20.7Water Treatment

 

Review and adjust the WTP design as the discharge permitting advances and the actual permitted discharge criteria become more defined

 

Continue to track and address identified project risks and opportunities

 

Implement bench-scale and pilot-scale treatment tests to confirm high treatment rates required to meet the WQS and to right-size treatment equipment

 

Evaluate RO reject treatment train once real mine-impacted water is generated during the operation phase

 

Refine the acids and bases used in the WTP to reduce the risk of TDS WQS compliance issues

 

Continue to refine WTP influent water quality predictions.

 

1.20.8Metallurgical testing

 

Additional testwork to further refine metallurgical performance and recovery estimates for the flowsheet, including:

 

Variability testing on samples with characteristics that match the LOM feed material

 

Circuit flowsheet modifications to improve concentrate quality and reduce deleterious elements, where applicable

 

Comminution testing on new samples to optimize comminution power.

 

1.20.9Recovery methods

 

Capital cost optimization and a thorough review of equipment sizing/selection based on the geometallurgy outcomes.

 

1.20.10Operational Readiness Plan

 

Develop a robust Operational Readiness (OR) plan to address risks and challenges associated with operating at a remote site:

 

Review project and operating assumptions to take into consideration the impacts of labour availability and logistical challenges with availability of equipment

 

Create a start-up/operational risk register to highlight issues for decisions taken during design

 

Incorporate development and implementation considerations for the remote cold-weather project site with limited access.

  
Arctic ProjectPage 25
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Develop alternatives for supply, transportation and logistics for reagents, concentrate, and any other goods

 

Track environment and operations-related permits to avoid costly alternatives

 

Explore opportunities to develop synergies with existing businesses and build an “industrial base” required to sustain mining and processing operations

 

Identify vendors to support contracts, parts, warehousing, training and first fills

 

Consider strategic Human Resources (HR) staffing decisions such as innovative labour scheduling and local sourcing

 

Identify Health, Safety, Environment and Community (HSEC) policies and procedures for a remote site to leverage local resources and other tie-ins where possible

 

Early mobilization of key technical functions to support mining and operations.

  
Arctic ProjectPage 26
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

2INTRODUCTION

 

2.1Introduction

 

Trilogy Metals Inc. (Trilogy or Trilogy Metals) is listed on the Toronto Stock Exchange (TSX) and the New York Stock Exchange (NYSE). As a result, Trilogy is a reporting issuer in Canada and must comply with National Instrument 43-101 Standards of Disclosure for Mineral Projects (NI 43-101) and is a registrant with the United States Securities and Exchange Commission (SEC) and must also comply with subpart 229.1300 - Disclosure by Registrants Engaged in Mining Operations of Regulation S-K (S-K 1300).

 

Trilogy commissioned Ausenco Engineering Canada Inc. (Ausenco) to manage the update of the 2020 Arctic Feasibility Study Technical Report (2020 FS) prepared in accordance with NI 43-101 into a prefeasibility-level study (the Arctic Project) and summarize into a S-K 1300 Technical Report Summary (the Report) on the Arctic deposit in the Ambler Mining District of northwest Alaska.

 

The Arctic Project is directly held by Ambler Metals, a 50/50 joint venture formed between South32 and Trilogy in February 2020. Upon the formation of the joint venture, Trilogy contributed all of its Alaskan assets, including the Arctic Project and Trilogy's agreement with NANA (see Section 3.4.2), to Ambler Metals in exchange for a 50% ownership interest and at the same time, South32 contributed $145 million in cash for their 50% ownership interest.

 

2.2Terms of Reference

 

The firms and consultants who have provided updates and are co-authors of this Report are Ausenco, B&C, SRK and Wood.

 

The Report excludes the Bornite group of claims, which is a separate project and subject to a separate technical report summary.

 

All units of measurement in this Report are metric, unless otherwise stated.

 

The monetary units are in US dollars, unless otherwise stated.

 

Mineral Resources and Mineral Reserves are prepared in accordance with the standards and definitions of S-K 1300.

 

2.3Qualified Persons

 

Table 2-1 provides a list of the firms and individuals that acted as third party Qualified Persons (QPs) in the preparation of this Report.

 

Table 2-1:Report Contributors

 

Qualified Person Report Responsibilities Report Sections
Ausenco Plant and infrastructure design, metallurgy, recovery methods, consolidation of the capital costs and operating costs and the overall financial model 1.1, 1.3, 1.4, 1.9, 1.13, 1.14.1, 1.14.2, 1.14.3, 1.14.4, 1.15, 1.17, 1.18, 1.19, 1.20.8, 1.20.9, 1.20.10, 2, 3.1, 3.2, 3,10, 4, 5.3.8, 10, 14, 15.1, 15.2, 15.3, 15.4, 15.5, 15.6, 15.7, 15.10.8, 15.12, 15.13, 15.14, 15.15, 15.16, 16, 18.1.1, 18.1.2, 18.1.3, 18.1.4, 18.1.5, 18.1.7, 18.1.9, 18.1.10, 18.1.11, 18.1.12, 18.1.13, 18.1.14, 18.2.1, 18.2.3, 18.2.4, 18.2.5, 18.2.6, 19, 21, 22.1, 22.5, 22.9, 22.10, 22.12, 22.13, 22.14, 22.15, 22.16, 22.17.8, 22.17.9, 23.1, 23.9, 23.10, 23.11, 24, 25.1, 25.3, 25.5
B&C Water treatment 1.14.9, 1.20.7, 2.3, 15.9, 17.3.4, 17.3.6.2, 18.1.9.1, 18.2.6, 23.8, 25.2
SRK Tailings waste design, pit slope design, hydrology, water management, hydrogeology 1.14.6, 1.14.7, 1.14.8, 1.16.3, 1.20.3, 1.20.4, 1.20.5, 1.20.6, 2.3, 2.4, 3.7, 3.8, 3.9, 3.10, 5.3.7, 7.2.4, 8.1.2, 8.2.5, 13.9, 13.10.1, 13.11, 15.8, 15.10.1, 15.10.2, 15.10.3, 15.10.4, 15.10.5, 15.10.6, 15.10.7, 15.11, 17.3.1, 17.3.2, 17.3.3, 17.3.5, 17.6, 22.17.3, 22.17.4, 22.17.5, 22.17.6, 22.17.7, 23.4, 23.5, 23.6, 23.7, 25.2, 25.4
Wood Geology, mine design, mineral resource estimate, mineral reserve estimates 1.2.1, 1.5, 1.6, 1.7, 1.8, 1.10, 1.11, 1.12, 1.14.5, 1.20.1, 1.20.2, 2.3, 2.4, 2.5, 2.6, 3.3, 3.4, 3.5, 3.6, 3.10, 6, 7.1, 7.2.1, 7.2.2, 7.2.3, 7.2.5, 7.2.6, 7.2.7, 7.2.8, 8.1.1, 8.1.3, 8.1.4, 8.1.5, 8.1.6, 8.2.1, 8.2.2, 8.2.3, 8.2.4, 8.3, 9, 11, 12, 13.1, 13.2, 13.3, 13.4, 13.5, 13.6, 13.7, 13.8, 13.10, 17.1, 17.2, 18.1.6, 18.2.2, 22.2, 22.3, 22.4, 22.6, 22.7, 22.8, 22.17.1, 22.17.2, 23.2, 23.3, 25.2, 25.4, 25.5

  
Arctic ProjectPage 27
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

2.4Site Visits

 

Ausenco's process QP relied on information from another Ausenco QP's visit to the Arctic Project site on July 25, 2017, during which that QP inspected the property access, viewed the surface topography in the area proposed for the process plant and supporting infrastructure.

  

SRK's tailings QP visited the Arctic Project site from July 24-25, 2017, and July 10-12, 2018. He inspected property access and surface topography where the waste rock facility and tailings management facilities are to be located, as well as available space for other mine facilities.

 

SRK's geotechnical QP visited the Arctic Project site August 27-29, 2019. During the visit he reviewed selected drill core, and inspected the Arctic deposit discovery outcrop, 2019 drill pads at Arctic, and a talc outcrop.

  

Wood's geology and resource QP visited the Arctic Project site during August 29 to September 8, 2022. During the site visit, he observed the diamond drill core logging processes that include geology, structure and geotechnical logging, sampling, and specific gravity (SG) measurement process. He also visited Arctic site area, measured historical collar locations with a handheld global positioning system (GPS), reviewed representative drill cores, observed active drilling process. He visited drill core and pulp storage sites at camp and in Fairbanks office/warehouse.

 

Wood's mining QP visited the site on August 30, 2022. During the visit, Wood inspected the property access and viewed the surface topography in the areas proposed for the locations of the open pit, mine infrastructure and waste rock facility are to be located; inspected lithologies in selected drill cores that would support the pit walls; and observed talc outcrop and main foliation that could affect pit slope stability.

 

2.5Currency of Report

 

This Report is current as of November 30, 2022.

 

2.6Information Sources and References

 

Reports and documents listed in Section 2.7 and Section 24 were used to support the preparation of the Report. Additional information was sought from Trilogy where required.

 

Trilogy contributed to Sections 1.16, 2.3, 5, 17.1, 17.2, 17.3, 17.4, 18.1, 22.11 and 25 of this Report.

 

This is the first S-K 1300 Technical Report Summary filed by Trilogy on the Arctic Project.

 

  
Arctic ProjectPage 28
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

2.7Previous Reports

 

Previous reports filed by NovaGold and NovaCopper/Trilogy and available on SEDAR (www.sedar.com) include:

  

Staples, P., Davis, B., MacDonald AJ., Austin, J., Sim, R., Boese, C., Murphy, B., and Sharp, T., Peralta Romero, A., 2020: Arctic Project, Northwest Alaska, USA, NI 43-101 Technical Report on Feasibility Study, report prepared by Ausenco Engineering Canada Inc. for Trilogy Metals Inc., effective date August 20, 2020.

 

Staples, P., Hannon, J., Peralta Romero, A., Davis, B., DiMarchi, J., Austin, J., Sim, R., Boese, C., Murphy, B., and Sharp, T., 2018: Arctic Project, Northwest Alaska, USA, NI 43-101 Technical Report on Pre-Feasibility Study, report prepared by Ausenco Engineering Canada Inc. for Trilogy Metals Inc., effective date February 20, 2018.

 

Davis, B., Sim, R., and Austin, J., 2017: NI 43-101 Technical Report on the Arctic Project, Northwest Alaska, USA: report prepared by BD Resource Consulting, Inc., SIM Geological Inc., and International Metallurgical & Environmental Inc. for Trilogy Metals Inc., effective date April 25, 2017.

 

Wilkins, G., Stoyko, H.W., Ghaffari, H., DiMarchi, J., Huang, J., Silva, M., O’Brien, M.F., Chin, M., and Hafez, S.A., 2013: Preliminary Economic Assessment Report on the Arctic Project, Ambler Mining District, Northwest Alaska: report prepared by Tetra Tech for NovaCopper inc., effective date September 12, 2013.

 

Rigby, N., White, R., Volk, J., Braun, T., and Olin, E.J., 2012: NI 43-101 Preliminary Economic Assessment Ambler Project Kobuk, AK: report prepared by SRK Consulting (US) Inc. for NovaCopper inc., effective date February 1, 2012.

 

Rigby, N., and White, R., 2011: NI 43-101 Preliminary Economic Assessment Ambler Project Kobuk, AK: report prepared by SRK Consulting (US) Inc. for NovaGold Resources Inc., effective date May 9, 2011.

 

Rigby, N., and White, R., 2008: NI 43-101 Technical Report on Resources Ambler Project Arctic Deposit, Alaska: report prepared by SRK Consulting (US) Inc. for NovaGold Resources Inc., effective date January 31, 2008.

 

2.8Abbreviations and Acronyms

 

A list of unit abbreviations is provided in Table 2-2 and an acronyms and abbreviations in Table 2-3.

 

Table 2-2:Unit Abbreviations

 

Abbreviation Definition Abbreviation Definition
% Percent km/h Kilometres per hour
Minute (plane angle) km2 Square kilometer
Second (plane angle) kPa Kilopascal
< Less than kt Thousand tonnes
> Greater than kV Kilovolt
° Degree kW Kilowatt
°C Degrees Celsius kWh Kilowatt hour
°F Degrees Fahrenheit kWh/a Kilowatt hours per year (annum)
µm Microns kWh/t Kilowatt hours per tonne (metric ton)
A Ampere L Litres

  
Arctic ProjectPage 29
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Abbreviation Definition Abbreviation Definition
a Annum (year) L/m Litres per minute
ac Acre lb Pounds
B Billion lb/ton Pounds per ton
cfm Cubic feet per minute m Metres
cm Centimetre M Million
cm2 Square centimetre m2 Square metre
cm3 Cubic centimetre m3 Cubic metre
d Day masl Metres above sea level
d/a Days per year (annum) mg Milligram
d/wk Days per week mg/l Milligrams per litre
ft Feet mi Mile
ft2 Square foot min Minute (time)
ft3 Cubic foot mL Millilitre
ft3/s Cubic feet per second mm Millimetre
g Gram mo Month
g/cm3 Grams per cubic centimetre Mt Million tonnes
g/L Grams per litre MW Megawatts
g/t Grams per tonne MWh Megawatt hour
GPM US Gallons per minute oz Ounce
h Hour ppb Parts per billion
h/a Hours per year (annum) ppm Parts per million
h/d Hours per day psi Pounds per square inch
h/w Hours per week rpm Revolutions per minute
ha Hectare (10,000 m2) s Second (time)
hp Horsepower t Tonnes (metric - 1,000 kg)
in Inch ton Tons (imperial – 2,000 lb)
in2 Square inch t/a tonnes per year (annum)
in3 Cubic inch USG US Gallons
k Kilo (thousand) V Volt
kg Kilogram wk Week
kg/h Kilograms per hour y Year (annum)
kg/m2 Kilograms per square metre    
km Kilometre    

 

  
Arctic ProjectPage 30
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 2-3:Acronyms and Abbreviations

 

Acronym/Abbreviation Definition
AA Atomic Absorption
AACE Association for the Advancement of Cost Engineering

  
Arctic ProjectPage 31
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Acronym/Abbreviation Definition
AAP Ambler Access Project
AAS Atomic Adsorption Spectroscopy
ABA Acid Base Accounting
ADEC Alaska Department of Environmental Conservation
ADNR Alaska Department of Natural Resources
AES Atomic Emission Spectroscopy
AFD Approved For Design
AHEA Annual Hardrock Exploration Activity
AIDEA Alaska Industrial Development and Export Authority
AMA Arctic Mine Access
AMDIAP Ambler Mining District Industrial Access Project
AMJ Arctic Mine Junction
AMR Aphanitic Metarhyolite
AMLT Alaska Mining License Tax
ANCSA Alaska Native Claims Settlement Act
ANFO Ammonium Nitrate Fuel Oil
ANILCA Alaska National Interest Land Conservation Act
AP Acid Potential
APDES Alaska Pollutant Discharge Elimination System
ARD Acid Rock Drainage
AST Alaska State Income Tax
BCMC Bear Creek Mining Company
BFA Bench Face Angle
BMAL Bulk Mineral Analysis with Liberation
BV Bureau Veritas
BWi Ball Mill Work Index
CC Construction Camp
ChS Chlorite Schist
ChTS Chlorite Talc Schist
CSAMT Controlled Source Audio Magneto Telluric
CuEq Copper Equivalent
CWA Clean water act.
DCF Discounted Cash Flow
DDH Diamond Drill Hole
DGPS Differential GPS
DTY Dalton Transfer Yard
DWi Drop Weight Index
EGL Effective Grinding Length

  
Arctic ProjectPage 32
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Acronym/Abbreviation Definition
EIS Environmental Impact Assessment
EM Electromagnetic
EPCM Engineering, Procurement, and Construction Management
FA Fire Assay
FEL Front End Loaders (Loading)
FOS Factors of Safety
FS Feasibility Study
GISTM Global Industry Standard on Tailings Management
GOH Gross Operating Hours
GPS Global Positioning System
GS Grey Schist
HA Heavy ANFO
HCTs Humidity Cell Tests
HDPE High-density Polyethylene
HR Human Resources
HSEC Health, Safety, Environment and Community
ICP Inductively Coupled Plasma
ICP-MS Inductively Coupled Plasma Mass Spectroscopy
IP Induced Polarization
IPR Instantaneous Penetration Rates
IRA Inter Ramp Angle
IRR Internal Rate of Return
JV Joint Venture
KRC Kennecott Research Centre
LBMA London Bullion Market Association
LiDAR Light Detection and Ranging Survey
LME London Metal Exchange
LOM Life of Mine
MAR Mean Annual Runoff
MIBC Methyl Isobutyl Carbinol
ML Metal Leaching
MLUP Miscellaneous Land Use Permit
MMU Mobile Mixing (Manufacturing) Unit
MO Metso Outotec
MS Massive Sulphide
NAD North American Datum
NEPA natural environmental policy act
NI National Instrument

  
Arctic ProjectPage 33
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Acronym/Abbreviation Definition
NN Nearest Neighbour
NOH Net Operating Hours
NP Neutralization Potential
NPV Net Present Value
NSR Net Smelter Return
NWAB Northwest Arctic Borough
NYSE New York Stock Exchange
OR Operational Readiness
PAF Permanent Accommodations Facility
PAG Potentially Acid Generating
PE Professional Engineer
PEA Preliminary Economic Assessment
PFD Process Flow Diagram
PFS Pre-Feasibility Study
PGA Peak Ground Acceleration
PIMA Portable Infrared Mineral Analyzer
PMF Probable Maximum Flood
PoF Potential of Failure
PP Process Plant
PWTP Potable Water Treatment Plant
QA Quality Assurance
QC Quality Control
QPs Qualified Persons
RAA Resource Associates of Alaska
RF Revenue Factor
RFQ Request for Quotation
RMR Rock Mass Rating
RO Reverse Osmosis
ROD record of decision
ROM Run of Mine
RQD Rock Quality Designation
RTDs Rubber Tire Dozers
S-K 1300 Subpart 229.1300 – Disclosure by Registrants Engaged in Mining Operations in Regulations
SAB SAG/Ball
SAG Semi Autogenous Grind
SG Specific Gravity
SMC SAG Mill Comminution (?)
SMS Semi Massive Sulphide

  
Arctic ProjectPage 34
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Acronym/Abbreviation Definition
SPI Significant Potential Incidents
ST Sodium Tungsten
STP Sewage Treatment Plant
TAC Transportation Association of Canada
TCJA Tax Cuts & Jobs Act
TDEM Time Domain Electromagnetic
THH Top Head Hammer
THPVC Thompson Howarth Precision Versus Concentration
TIC Total Inorganic Carbon
TMF Tailings Management Facilities
ToC Time of Concentration
TS Talc Schist
TSX Toronto Stock Exchange
UCS Unconfined Compressive Strength
UKMP Upper Kobuk Mineral
USACE US Army Corps of Engineers
USFW US Fish and Wildlife
USGS US Geological Survey
UTM Universal Transverse Mercator
VAT Value Added Tax
VHF Very High Frequency
VMS Volcanogenic Massive Sulphide
VWPs Vibrating Wire Piezometers
WGM Watts, Griffis and McOuat
WQS Waste Rock Collection Pond
WQBEL Water Quality-Based Effluent Limits
WRCP Waste Rock Contact Pond
WRF Waste Rock Facility
WTP Water Treatment Plant

  
Arctic ProjectPage 35
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

3PROPERTY DESCRIPTION AND LOCATION

 

3.1Introduction

 

The Property is situated in the Ambler mining district of the southern Brooks Range, in the Northwest Arctic Borough (NWAB) of Alaska (Figure 3-1). The Property is located in Ambler River A-2 quadrangle, Kateel River Meridian T 20N, R 11E, section 2 and T 21N, R 11E, sections 34 and 35.

 

The Property is about 270 km east of the town of Kotzebue, 37 km northeast of the village of Kobuk, and 260 km west of the Dalton Highway, an all-weather State maintained public road, at geographic coordinates N67.17° latitude and W156.39° longitude and Universal Transverse Mercator (UTM) North American Datum (NAD) 83, Zone 4 coordinates 7453080N, 613110E.

 

Figure 3-1: Arctic Project Location Map

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 36
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

3.2Property Ownership

 

The Property is directly held by Ambler Metals, a 50/50 joint venture formed between South32 and Trilogy in February 2020. Upon the formation of the joint venture, Trilogy contributed all of its Alaskan assets, including the Property to Ambler Metals in exchange for a 50% ownership interest and at the same time, South32 contributed $145 million in cash for a 50% ownership interest.

 

Prior to the joint venture formation, the Property was held 100% by a wholly owned subsidiary of Trilogy. Trilogy acquired the Property from NovaGold in 2011. In 2011, NovaGold transferred all copper projects to NovaCopper and subsequently spun-out NovaCopper to its then existing shareholders by way of a Plan of Arrangement in 2012. NovaCopper Inc. subsequently underwent a name change to Trilogy Metals Inc. in 2016.

 

3.3Mineral Tenure

 

The UKMP consists of an approximately 448,217-acre land package containing state, patented and native lands within an area of interest. There are two discrete mineralized belts within the UKMP - the Devonian Ambler Schist Belt and the Devonian Bornite Carbonate Sequence. The Property is located within the Ambler Schist Belt which comprises approximately 231,008 acres (93,446 ha) of State of Alaska mining claims and US Federal patented mining claims in the Kotzebue Recording District. Exclusive of native lands, the UKMP land tenure consists of 2,136 contiguous State claims totalling 230,736 acres (93,336 ha), including 905 40-acre claims, 1,231 160-acre claims, and 18 Federal patented claims comprising 271.9 acres (110 ha) held in the name of Ambler Metals. Claim locations are shown in Figure 3-2 to Figure 3-4 and listed in Appendix A. The Arctic deposit is located near the southern edge of the centre of the claim block shown in Figure 3-5, primarily within the Federal patented claims, which do not expire and provides exclusive rights to the locatable minerals, and in most cases, the surface and all resources.

 

The Federal patented claim corners were located by the US Geological Survey (USGS). In Appendix A, a total of 18 Federal patented claims are reported using the completed mineral survey MS 2245 which includes Federal patent number 50-81-0127 covering16 Federal patented claims (Arctic 1, 2, 4, 9, 11, 13, 15, 17, 19, 23, 24, 25, 26, 27, 28, and 29), and Federal patent number 50-83-0174 covering 2 Federal patented claims (Arctic 10 and 495). Figure 3 4 included the locations of the Federal patented claims. There is no expiration date or labour requirement on the Federal patented claims.

 

The UKMP also consists of lands owned by NANA Regional Corporation, Inc. (NANA), who controls lands granted under the Alaska Native Claims Settlement Act (ANCSA) to the south of the Property boundary. Ambler Metals and NANA are parties to an agreement dated October 19, 2011 (the NANA Agreement) that consolidates the parties' land holdings into an approximately 190,929 ha land package and provides a framework for the exploration and development of the area, including non-exclusive rights for surface access across NANA lands. The NANA Agreement has a term of 20 years, with an option in favour of Ambler Metals to extend the term for an additional 10 years.

 

Rent for each State claim is up to date and is paid annually to the ADNR. An Annual Labour Statement must be submitted to maintain the State claims in good standing.

  
Arctic ProjectPage 37
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 3-2: Upper Kobuk Mineral Projects Lands

 

 

Source: Ambler Metals, 2022.

Note: NANA’s Bornite and ANCSA Lands are not part of the Arctic Property

  
Arctic ProjectPage 38
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Figure 3-3: Arctic Project Mineral Tenure Plan

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 39
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 3-4: Mineral Tenure Layout Plan

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 40
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Figure 3-5: Arctic Deposit Location

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 41
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

3.4Royalties, Agreements and Encumbrances

 

3.4.1Kennecott Agreements

 

The Kennecott Royalty Agreement dated effective January 7, 2010, was entered into by and among Kennecott, Alaska Gold Company and NovaGold. A copy of the Kennecott Agreement was recorded in the Kotzebue Recording District on January 8, 2010, as document no. 2010-000013-0.

 

The Kennecott Royalty Agreement documents a net smelter returns royalty that was reserved to Kennecott in a Purchase and Sale Agreement dated December 18, 2009, whereby Alaska Gold Company and NovaGold acquired mining properties from Kennecott. The mining properties referenced in the Kennecott Royalty Agreement consist of the Federal patented mining claims and many, but not all, of the State mining claims that are the subject of this Report.

 

Under the Kennecott Purchase and Termination Agreement, Kennecott retained a 1% NSR royalty that has been subsequently sold by Kennecott. The 1% NSR runs with the lands and is purchasable at any time from the royalty holder for a one-time payment of $10 million.

 

3.4.2NANA Agreement

 

In 1971, the US Congress passed the ANCSA which settled land and financial claims made by the Alaska Natives and provided for the establishment of 13 regional corporations to administer those claims. These 13 corporations are known as the Alaska Native Regional Corporations (ANCSA Corporations). One of these 13 regional corporations is NANA. ANCSA Lands controlled by NANA bound the southern border of the Arctic Project claim block (refer to Figure 3-5).

 

On October 19, 2011, Trilogy and NANA entered into the NANA Agreement for the cooperative development of their respective resource interests in the Ambler mining district. The NANA Agreement consolidates Trilogy’s and NANA’s land holdings into an approximately 142,831 ha land package and provides a framework for the exploration and development of the area. The NANA Agreement provides that NANA will grant Trilogy the nonexclusive right to enter on, and the exclusive right to explore, the Bornite Lands and the ANCSA Lands (each as defined in the NANA Agreement) and in connection therewith, to construct and use temporary access roads, camps, airstrips, and other incidental works.

 

The NANA Agreement has been assigned by Trilogy to Ambler Metals upon the formation of the joint venture.

 

The NANA Agreement has a term of 20 years, with an option in favour of Ambler Metals to extend the term for an additional 10 years. The NANA Agreement may be terminated by mutual agreement of the parties or by NANA if Ambler Metals does not meet certain expenditure requirements on NANA’s lands.

 

If, following receipt of a feasibility study and the release for public comment of a related draft EIS, Ambler Metals decides to proceed with construction of a mine on the lands subject to the NANA Agreement, Ambler Metals will notify NANA in writing and NANA will have 120 days to elect to either (a) exercise a non-transferrable back-in-right to acquire between 16% and 25% (as specified by NANA) of that specific project; or (b) not exercise its back-in-right, and instead receive a net proceeds royalty equal to 15% of the net proceeds realized by Ambler Metals from such project. The cost to exercise such back-in-right is equal to the percentage interest in the Arctic Project multiplied by the difference between (i) all costs incurred by Ambler Metals or its affiliates on the project, including historical costs incurred prior to the date of the NANA Agreement together with interest on the historical costs; and (ii) $40 million (subject to exceptions). This amount will be payable by NANA to Ambler Metals in cash at the time the parties enter into a joint venture agreement and in no event will the amount be less than zero.

  
Arctic ProjectPage 42
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

In the event that NANA elects to exercise its back-in-right, the parties will, as soon as reasonably practicable, form a joint venture with NANA electing to participate between 16% to 25%, and Ambler Metals owning the balance of the interest in the joint venture. Upon formation of the joint venture, the joint venture will assume all of the obligations of Ambler Metals and be entitled to all the benefits of Ambler Metals under the NANA Agreement in connection with the mine to be developed and the related lands. A party’s failure to pay its proportionate share of costs in connection with the joint venture will result in dilution of its interest. Each party will have a right of first refusal over any proposed transfer of the other party’s interest in the joint venture other than to an affiliate or for the purposes of granting security. A transfer by either party of a net smelter royalty return on the project or any net proceeds royalty interest in a project other than for financing purposes will also be subject to a first right of refusal.

 

In connection with possible development on the Bornite Lands or ANCSA Lands, Ambler Metals and NANA will execute a mining lease to allow Ambler Metals or a joint venture vehicle to construct and operate a mine on the Bornite Lands or ANCSA Lands. The mining lease will provide NANA with a 2% NSR as to production from the Bornite Lands and a 2.5% NSR as to production from the ANCSA Lands.

 

If Ambler Metals decides to proceed with construction of a mine on its own lands subject to the NANA Agreement, NANA will enter into a surface use agreement with Ambler Metals which will afford Ambler Metals access to the Arctic Project along routes approved by NANA (the Surface Use Agreement). In consideration for the grant of such surface use rights, Ambler Metals will grant NANA a 1% NSR on production and an annual payment of $755 per acre (as adjusted for inflation each year beginning with the second anniversary of the effective date of the NANA Agreement) and for each of the first 400 acres and $100 for each additional acre, of the lands owned by NANA and used for access which are disturbed and not reclaimed.

 

Figure 3-5 showed the locations of the Bornite and ANCSA Lands that are included in the NANA Agreement. The Bornite Lands are not considered to be part of the Arctic Project, because the mineralization styles identified to date in the Bornite Lands are distinctly different to the mineralization styles in the Ambler claims, and it is expected that any mining operation in the Bornite Lands would be developed as a stand-alone operation using different infrastructure.

 

3.5State Royalty

 

The owner of a State mining claim or lease will be obligated to pay a production royalty to the State of Alaska in the amount of 3% of net income received from minerals produced from the State mining claims.

 

This royalty does not apply to patented federal mining claims.

 

3.6Surface Rights

 

Surface use of the private land held as Federal patented claims is limited only by reservations in the patents and by generally applicable environmental laws. These do not restrict access or the ability to do work.

 

Surface use of State claims allows the owner of the mining claim to make such use of the surface as is “necessary for prospecting for, extraction of, or basic processing of minerals.”

  
Arctic ProjectPage 43
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

3.7Environmental Considerations

 

Environmental considerations are discussed in Section 17.

 

There may be some environmental liabilities associated with sites explored during the 1950s and 1960s. The exploration camp would require rehabilitation if the Arctic Project is closed.

 

3.8Permits

 

Permitting considerations for the Arctic Project are discussed in Section 17. Permits necessary to advance to the next stage are also discussed in Section 17.

 

There have been no significant violations or fines on the Property.

 

3.9Social Considerations

 

Social considerations for the Arctic Project are discussed in Section 17.

 

3.10Comment on Property Description and Location

 

The QPs consider that there are no other significant factors or material risks that may affect access, mineral tenure, title or the right or ability to perform work on the Property other than what is described in this Report. All mineral tenure, mining leases and crown land title are in good standing. Surface and aerial access to the project site is permitted and well-established. Permits to authorize work program activities are in place and applied for sufficiently in advance of work requirements. It is a reasonable expectation that any additional surface rights that would be required to support Arctic Project development and operations can be obtained through appropriate negotiation.

  
Arctic ProjectPage 44
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

4ACESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE and PHYSIOGRAPHY

 

4.1Accessibility

 

4.1.1Air

 

Primary access to the Property is by air, using both fixed wing aircraft and helicopters.

 

There are four well-maintained, approximately 1,500 m-long gravel airstrips located near the Arctic Project, capable of accommodating charter fixed wing aircraft. These airstrips are located 64 km west at Ambler, 46 km southwest at Shungnak, 37 km southwest at Kobuk, and 34 km southwest at Dahl Creek. There is daily commercial air service from Kotzebue to the village of Kobuk, the closest community to the Arctic Project. During the summer months, the Dahl Creek Camp airstrip is suitable for larger aircraft, such as a C-130 and DC-6.

 

In addition to the four 1,500 m airstrips, there is a 700 m airstrip located at the Bornite Camp. The airstrip at Bornite is suited to smaller aircraft, which support the Bornite Camp with personnel and supplies. There is also a 450 m airstrip (Arctic airstrip) located at the base of Arctic Ridge that can support smaller aircraft.

 

4.1.2Road

 

A winter trail and a one-lane dirt track suitable for high-clearance vehicles or construction equipment links the Bornite Camp to the Dahl Creek airstrip southwest of the Arctic deposit. An unimproved gravel track connects the Arctic airstrip with the Arctic deposit.

 

4.1.3Water

 

There is no direct water access to the Property. During spring runoff, river access is possible by barge from Kotzebue Sound to Ambler, Shungnak, and Kobuk via the Kobuk River.

 

4.2Climate

 

The climate in the region is typical of a sub-arctic environment. Weather conditions on the Property can vary significantly from year to year and can change suddenly. During the summer exploration season, average maximum temperatures range from 10°C to 20°C, while average lows range from -2°C to 7°C (Western Regional Climate Center: WRCC – Alaska Climate Summaries: Kobuk 1971 to 2000). By early October, unpredictable weather limits safe helicopter travel to the Arctic Project. During winter months, the Arctic Project can be accessed by snow machine, track vehicle, or fixed wing aircraft. Winter temperatures are routinely below -25°C and can exceed -50°C. Annual total precipitation (rainfall and snowfall) in the region averages 1,219 mm with the most rainfall occurring from July through September, and the most snowfall occurring from October through February.

 

It is expected that any future mining activity will be conducted on a year-round basis. Past exploration activities are generally confined to the period from late May to late September.

  
Arctic ProjectPage 45
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

4.3Local Resources and Infrastructure

 

The Property is currently isolated from major public infrastructure. Infrastructure assumptions including sources of water and electricity, and the proposed infrastructure layout for the Arctic Project are discussed in Section 15 of the Report.

 

The Property is approximately 270 km east of the town of Kotzebue, on the edge of Kotzebue Sound, 37 km northeast of the village of Kobuk, 260 km west of the Dalton Highway, and 470 km northwest of Fairbanks. Kobuk (population 191; 2020 US Census) is the location of one of the airstrips near the Arctic Project. Several other villages are also near the Arctic Project, including Shungnak located 46 km to the southwest with a population of 272 (2020 US Census) and Ambler, 64 km to the west with a population of 274 (2020 US Census). Kotzebue has a population of 3,102 (2020 US Census) and is the largest population centre in the Northwest Arctic Borough. Kotzebue is a potential source of limited mining-related supplies and labourers, and is the nearest centre serviced by regularly scheduled, large commercial aircraft (via Nome or Anchorage). In addition, there are seven other villages in the region that will be a potential source of some of the workforce for the Arctic Project. Fairbanks (population 32,515; 2020 US Census) has a long mining history and can provide most mining-related supplies and support that cannot be sourced closer to the Property.

 

Drilling and mapping programs are seasonal and have been supported out of the Bornite Camp and Dahl Creek Camp. The Bornite Camp facilities are located on Ruby Creek on the northern edge of the Cosmos Hills. The camp provides office space and accommodations for the geologists, drillers, pilots, and support staff. Power is supplied by two diesel generators. Water was supplied by the permitted artesian well located 250 m from camp; however, a water well was drilled in camp during the 2017 field season that was permitted by 2019 to provide all potable water for the Bornite Camp.

 

There is sufficient area within the Property to host an open pit mining operation, including mine and plant infrastructure, and waste rock and tailings management facilities.

 

4.4Physiography

 

The Property is located along the south slope of the Brooks Range, which separates the Arctic region from the interior of Alaska. Nearby surface water includes Subarctic Creek, the Shungnak and Kogoluktuk Rivers, the Kobuk River, and numerous small lakes. The Property is located at the eastern end of Subarctic Creek, a tributary of the Shungnak River to the west, along a ridge between Subarctic Creek and the Kogoluktuk River Valley. The Property area is marked by steep and rugged terrain with high topographic relief. Elevations range from 30 masl along the Kobuk River to 1,180 masl on a peak immediately north of the Arctic Project area. The divide between the Shungnak and Kogoluktuk Rivers in the Ambler Lowlands is approximately 220 masl.

 

The Kobuk Valley is located at the transition between boreal forest and Arctic tundra. Spruce, birch, and poplar are found in portions of the valley, with a ground cover of lichens (reindeer moss). Willow and alder thickets and isolated cottonwoods follow drainages, and alpine tundra is found at higher elevations. Tussock tundra and low, heath-type vegetation covers most of the valley floor. Intermittent permafrost exists on the Property.

 

Permafrost is a layer of soil at variable depths beneath the surface where the temperature has been below freezing continuously from a few to several thousands of years (Climate of Alaska 2007). Permafrost exists where summer heating fails to penetrate to the base of the layer of frozen ground and occurs in most of the northern third of Alaska as well as in discontinuous or isolated patches in the central portion of the State.

 

Wildlife in the Arctic Project area is typical of Arctic and subarctic fauna (Kobuk Valley National Park 2007). Larger animals include caribou, moose, Dall sheep, bears (grizzly and black), wolves, wolverines, coyotes, lynx and foxes. There are no anadromous fish species in the upper reaches of the Shungnak and Kogoluktuk Rivers due to natural fish barriers. Other fish species such as trout, sculpin, and grayling are common. The caribou seen on the Property belong to the Western Arctic herd that migrate once a year heading south in late August through October from their summer range north of the Brooks Range. The caribou migrate north in March from their winter range along the Buckland River to the north slope of the Brooks Range, a more westerly route and do not cross the Project during that migration.

  
Arctic ProjectPage 46
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

4.5Comments on Accessibility, Climate, Local Resources, Infrastructure and Physiography

 

In the opinion of the QP:

 

The planned infrastructure, availability of staff, power, water, and communications facilities, the design and budget for such facilities, and the methods whereby goods could be transported to the proposed mine, and any planned modifications or supporting studies are reasonably well-established, or the requirements to establish such, are reasonably well understood by Trilogy, and can support the declaration of Mineral Resources and Mineral Reserves.

 

There is sufficient area within the Property to host an open pit mining operation, including mine and plant infrastructure, and waste rock and tailings management facilities.

 

It is a reasonable expectation that any additional surface rights that would be required to support Project development and operations can be obtained through appropriate negotiation.

 

It is expected that any future mining operations will be able to be conducted year-round.

  
Arctic ProjectPage 47
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

5HISTORY

 

5.1Regional History

 

Prospectors in search of gold, travelling up the Kobuk River in 1898-99 (Grinnell, 1901), found several small gold placer deposits in the southern Cosmos Hills, south of the Arctic deposit, which were worked intermittently over the ensuing decades. Around this time, copper mineralization at Ruby Creek and Pardner Hill in the northern Cosmos Hills was explored using small shafts and adits (Smith and Eakin, 1911). In 1947, Rhinehart “Rhiny” Berg staked claims over the Ruby Creek prospects, carried out extensive trenching and the first diamond drilling, and constructed an airstrip for access (alaskamininghalloffame.org 2012). BCMC, an exploration subsidiary of Kennecott, optioned the Ruby Creek property from Berg in 1957. The prospect became known as Bornite and Kennecott conducted extensive exploration over the next decade, culminating in the discovery of the high-grade No. 1 zone and the sinking of an exploration shaft to conduct underground drilling.

 

While exploring the Bornite deposit, BCMC carried out reconnaissance exploration throughout the western Brooks Range, including a large regional stream sediment survey in 1962. Initial follow up did not identify mineralization of interest however in 1965, Riz Bigelow (BCMC) and his team of geologists found boulders of massive sulphides at an anomaly (1400 ppm Cu) located 28 km northeast of Bornite that led to the discovery of outcropping mineralization the following year. The area was subsequently staked and, in 1967, nine core holes were drilled at the Arctic deposit, eight of which yielded massive sulphide intercepts over an almost 500-m strike length.

 

BCMC conducted intensive exploration on the property until 1977 and then intermittently through to 1998. No drilling or additional exploration was conducted on the Property between 1999 and 2003.

 

In addition to drilling and exploration at the Arctic deposit, BCMC also conducted exploration at numerous other prospects in the Ambler Mining District (most notably Dead Creek, Sunshine, Cliff, and Horse). The abundance of Volcanogenic Massive Sulphide (VMS) prospects in the district resulted in a series of competing companies in the area, including Sunshine Mining Company, Anaconda Company, Noranda Exploration Company, GCO Minerals Company, Cominco American Resource Inc. (Cominco), Teck Cominco, Resource Associates of Alaska (RAA), Watts, Griffis and McOuat Ltd. (WGM), and Houston Oil and Minerals Company, culminating into a claim staking war in the district in 1973. Falconbridge and Union Carbide also conducted work later in the district.

 

District exploration by Sunshine Mining Company and Anaconda resulted in two additional significant discoveries in the district; the Sun deposit located 60 km east of the Arctic deposit, and the Smucker deposit located 36 km west of the Arctic deposit. These two deposits are outside the current Property.

 

District exploration continued until the early 1980s on the four larger deposits in the district (Arctic, Bornite, Smucker and Sun) when the district fell into a hiatus due to depressed metal prices.

 

In 1987, Cominco acquired the claims covering the Sun and Smucker deposits from Anaconda. Teck Resources Limited, as Cominco’s successor company, continues to hold the Smucker deposit. In 2007, Andover Mining Corporation purchased a 100% interest in the Sun deposit for $13 million and explored the property through 2013. The Sun deposit and adjacent lands were acquired by Valhalla Metals Inc., a private company, staked over the Sun deposit in 2017 after the creditors for the bankrupt Andover Mining Corporation failed to pay the annual rent of the state claims and submit the Annual Labour Statement.

  
Arctic ProjectPage 48
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

In 1981 and 1983, Kennecott received three US Mineral Survey patents (MS2245 totaling 240 acres over the Arctic deposit – later amended to include another 32 acres; and MS2233 and MS2234 for 25 claims totaling 516.5 acres at Bornite). The Bornite patented claims and surface development were subsequently sold to NANA Regional Corporation, Inc. in 1986.

 

No production has occurred at the Arctic deposit or at any of the other deposits within the Ambler Mining District.

 

5.2Prior Ownership and Ownership Changes – Arctic Deposit and the Ambler Lands

 

BCMC initially staked federal mining claims covering the Arctic deposit area beginning in 1966. The 1960’s drill programs defined a significant high-grade polymetallic resource at the Arctic deposit and, in the early 1970s, Kennecott began the patent process to obtain complete legal title to the Arctic deposit. In 1981, Kennecott received US Mineral Survey patent M2245 covering 16 mining claims totalling 240.018 acres. In 1983, US Mineral Survey patent M2245 was amended to include two additional claims totalling 31.91 acres.

 

With the passage of the Alaska National Interest Lands Conservation Act (ANILCA) in 1980, which expedited native land claims outlined in the ANSCA and State lands claims under the Alaska Statehood Act, both the State of Alaska and NANA selected significant areas of land within the Ambler Mining District. State selections covered much of the Ambler schist belt, host to the VMS deposits including the Arctic deposit, while NANA selected significant portions of the Ambler Lowlands to the immediate south of the Arctic deposit as well as much of the Cosmos Hills including the area immediately around Bornite.

 

In 1995, Kennecott renewed exploration in the Ambler schist belt containing the Arctic deposit patented claims by staking an additional 48 state claims at Nora and 15 state claims at Sunshine Creek. In the fall of 1997, Kennecott staked 2,035 state claims in the belt consolidating their entire land position and acquiring the majority of the remaining prospective terrain in the VMS belt. Five more claims were subsequently added in 1998. After a short period of exploration which focused on geophysics and geochemistry combined with limited drilling, exploration work on the Arctic Project again entered a hiatus.

 

On March 22, 2004, Alaska Gold Company, a wholly-owned subsidiary of NovaGold completed an Exploration and Option Agreement with Kennecott to earn an interest in the Ambler land holdings.

 

5.3Previous Exploration and Development Results – Arctic Deposit

 

5.3.1Introduction

 

Kennecott’s ownership of the Property saw two periods of intensive work from 1965 to 1985 and from 1993 to 1998, before optioning the property to NovaGold in 2004.

 

Though reports, memos, and files exist in Kennecott’s Salt Lake City office, only limited digital compilation of the data exists for the earliest generation of exploration at the Arctic deposit and within the VMS belt. Beginning in 1993, Kennecott initiated a re-evaluation of the Arctic deposit and assembled a computer database of previous work at the Arctic deposit and in the district. A computer-generated block model was constructed in 1995 and an updated resource estimate was preformed using from block model. Subsequently, Kennecott staked a total of 2,035 State of Alaska claims in 1997 and, in 1998 undertook the first field program since 1985.

  
Arctic ProjectPage 49
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Due to the number of companies and the patchwork exploration that occurred as a result of the 1973 staking war, much of the earliest exploration work on the Ambler Schist belt was lost during the post-1980 hiatus in district exploration. The following subsections outline the best documented data at the Arctic deposit as summarized in the 1998 Kennecott exploration report, including the assembled computer database; however, this outline is not considered to be either exhaustive or in-depth.

 

In 1982, geologists with Kennecott, Anaconda and the State of Alaska published the definitive geologic map of the Ambler schist belt (Hitzman et al. 1982).

 

Table 5-1 lists known exploration mapping, geochemical, and geophysical programs conducted for VMS targets in the Ambler Mining District.

  
Arctic ProjectPage 50
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 5-1: Known Mapping, Geochemical, and Geophysical Programs Targeting VMS Prospects in the Ambler Mining District

 

Area Prospects Company Mineralization Mapping Soil Geochem Geophysics Reports
Arctic Center of the Universe (COU) Back Door Arctic BCMC-KEX Two (or more) sulphide bands with thickness up to ~40 m with Zn, Cu, Pb, Ag, Au, ±Ba mineralization. Proffett 1998; Lindberg and others 2004, 2005; NG personnel 2008 at 1:2,000 scale Extensive 2006 NG program (>670 samples) Numerous surveys including the 1998 Dighem EM and Mag aerial surveys, 1998 CSAMT survey, TEM downhole and surface surveys in 2005, TDEM ground survey in 2006 Numerous
COU Back Door, 4th of July Creek NG-Anaconda No exposed or drilled mineralization, target is the projection of the Arctic horizon NG 1:2,000 mapping in 2006 Extensive 2006 NG program 4 TDEM ground surveys in 2005 and 2006 2005 and 2006 NG Progress Reports; Lindberg’s 2005 report
Sunshine Bud CS Sunshine Creek BCMC and BCMC-Noranda Disseminated to semi-massive lens up to 18 m thick. Upper mineralized limb is Ba-rich BCMC 1983; Paul Lindberg 2006; NG 2011 Numerous eras of soil sampling, most recent 1998 by Kennecott (Have data) and 2006 by NG BCMC completed Recon IP survey and Crone vertical shoot back EM in 1977, 2 TDEM surveys to the NW Various BCMC reports; Lindberg’s 2006 Sunshine progress report; 2006 NG Progress report
Bud-CS SMC and TAC Au-rich gossan and 3+ m intercept of 1.7% Cu, 0.4% Pb, 1.5% Zn, 2 oz/ton Ag, 0.017 oz/ton Au Anaconda (TAC) and Sunshine (SMC) SMC soil sampling Anaconda completed downhole resistivity survey in 1981 on Bud 7 1981 through 1983 Anaconda Progress reports

  
Arctic ProjectPage 51
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Area Prospects Company Mineralization Mapping Soil Geochem Geophysics Reports
Dead Creek Shungnak SK Shungnak (Dead Creek) BCMC, Cominco Thin (0.1 to 3 m) disseminated to semi-massive lenses of Cu, Zn, Pb, Ag mineralization Bruce Otto and others 2006; Proffett 1998 NG in 2006 (355 samples); KEX in 1998 (~240 samples) 2 CEM surveys by BCMC at DH with no anomalous responses (do not have data) 2006 NG report; 1982 and 1983 Anaconda Ambler Progress reports
SK GCO and BCMC/GCO-HOMEX JV Mineralized float up to 0.4% Cu, 4.8% Pb, 8.7% Zn, 5 oz/ton Ag BCMC BCMC 1982 soil grid CEM and Max-min completed by BCMC (do not have data) 1982 Annual Progress Report, BCMC; Bruce Otto 2006 Memo
Horse Cliff DH Horse-Cliff DH Horse – BCMC, Cliff SMC, DH – BCMC and BCMC/GCO-HOMEX Disseminate to semi-massive with local massive lens, thicknesses up to tens of feet. KEX 1983 1:1000 prospect map SMC soil surveys 1976-1978 and 1980 No known ground-based survey; occurrences within a large resistivity high 1985 Progress Report BCMC-GCO-Homex J; 1980 Summary of Ambler Field Investigations – Sunshine Mining, Horse Creek Memo – Robinson 1981; 1978 Ellis Geologic Evaluation and Assessment of the Northern Belt Claims

Snow Ambler RB Nani Frost

 

 

 

Snow Cominco Ag-Pb-Zn mineralization as massive and semi-massive bands hosted within thin bands of graphitic schist (GS). Noranda-Cominco scanned map with no 72eochem72enced; Prospect scale KEX Soil gird in 1997 or 1998 No known ground-based survey; Anaconda completed downhole resistivity survey in 1981 on Ambler-4 “Snow Prospect Miscellaneous Notes and Maps.pdf” is only known report

  
Arctic ProjectPage 52
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Area Prospects Company Mineralization Mapping Soil Geochem Geophysics Reports
  Ambler Anaconda TAC Massive, disseminated chalcopyrite and pyrite associated with chert Numerous Anaconda geologists; no digitized maps Only scattered soils in database Max-min surveys, no data is available 1983 Ambler River Memo (Sunshine Progress Report); 1982 Anaconda Progress Report
Nani-Frost BCMC and BCMC-Noranda Outcrops of 2-3 m of 0.8% Cu, 0.4% Pb, 1.2% Zn, 0.05 oz/ton Ag within felsic schist BCMC (do not have data) BCMC identified numerous weak soil anomalies (do not have data) CEM, Max-min, and PEM completed by BCMC (do not have data) 1982 Annual Progress Report, BCMC
Red Nora Nora BCMC/GCO-HOMEX Disseminated chalcopyrite within chlorite altered volcanics in two zones (Sulphide Gulch and Northern Horizon) Generalized geologic map created by WGM for BCMC-GCO-HOMEX No known data Two PEM over the Sulphide Gulch horizon 1984 and 1985 Progress Report BCMC-GCO-Homex JV
Red BCMC Thin discordant bands of sphalerite, chalcopyrite, galena, and pyrrhotite with calcite and fluorite cutting ‘siltites’ and metacarbonates None KEX soil lines 1998 KEX identified EM anomalies 1998, follow-up gravity and Max-min EM; TDEM survey in 2006; DIGHEM helicopter EM and radiometric survey in 2006 Kennecott’s final 1998 field report; 2006 NG Progress Report

  
Arctic ProjectPage 53
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Area Prospects Company Mineralization Mapping Soil Geochem Geophysics Reports
Other BT, Jerri Creek Anaconda, AMC Massive sulphide bands up to 1.5 m thick extend nearly 2.3 km along an E-W strike Hitzman and others Historic soils at Jerri Creek No known surveys. Hitzman thesis and Anaconda (BT) and Bear Creek (Jerri) Assessment reports; 1982 and 1983 Anaconda Ambler Progress reports
Kogo-White Creek Bud – SMC or AMC Discovered by hydrochemistry of high Cu ions in White Creek. SMC? Soil 74eochem surveys by SMC in 1978 and KEX in 1998 Recon IP survey in 1977; Max-Min Mag survey in 1980; Follow-up Max-Min and gravity by KEX in 1998; TDEM by NG in 2006. 1980 Summary of Ambler Field Investigations, SMC; Kennecott’s Final 1998 Field Report
Pipe BCMC and SMC Podiform zones of sulphide mineralization within calc-schists and QMS Schmidt in 1978, SMC in 1982 Kennecott soil grid in 1997-1998 Not known Schmidt’s 1978 report (Part IV) for Anaconda’s (?) annual report

  
Arctic ProjectPage 54
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Area Prospects Company Mineralization Mapping Soil Geochem Geophysics Reports
  Tom Anaconda and SMC 1982 ‘Discovery’ trench by SMC uncovered massive sulphide boulders with up to 6 oz/ton Ag, 5.4% Pb, 6.3% Zn, only 0.2% Cu Sunshine in 1982 (?) SMC soils in 1982 Gamma mag survey by SMC in 1982; TDEM by NG in 2006. 1982 Sunshine Mining Company Memo by E.R. Modroo; Schmidt’s 1978 report (Part IV) for Anaconda’s (?) annual report
Sun Sun-Picnic Creek Anaconda – AMC-Cominco; Valhalla Metals is current owner Three zones of sulphide mineralization varying from 1 to 10 m; Upper zone is Zn-Pb-Ag rich while the two lower zones are Cu rich Various Anaconda geologists Not known, but most likely extensive Not known, but most likely extensive 1981 Anaconda progress report; Anaconda 1977 prefeasibility study (not in NG possession)
Smucker Smucker-Charlie-Puzzle-4B-Patti Anaconda, Cominco, and Bear Creek; now owned by Teck A single mineralized Ag-Zn-Pb-Cu horizon varying from 1 to 8 m in thickness Detailed mapping by Anaconda and BCMC geologists Strong soil 75eochem anomalies in lowlands SE of Smucker horizon; Kennecott soil grid in 1997 or 1998 Not known 1985 Progress Report BCMC-GCO-Homex JV

 

Note: EM = electromagnetic; TDEM = time domain electromagnetic; CSAMT = Controlled Source Audio Magnetotelluric.

  
Arctic ProjectPage 55
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

5.3.2Geochemistry

 

Historical geochemistry for the district, compiled in the 1998 Kennecott database, includes 2,255 soil samples, 922 stream silt samples, 363 rock samples, and 37 panned concentrate samples. Data have been sourced from several companies including Kennecott, Sunshine Mining, RAA, and NANA. Sourcing of much of the data had been poorly documented in the database.

 

During 1998, Kennecott renewed its effort in the district, and, as a follow-up to the 1998 electromagnetic (EM) survey, undertook soil and rock chip sampling in and around EM anomalies generated in the geophysical targeting effort. During this period Kennecott collected 962 soils and 107 rocks and for the first time used extensive multi-element inductively coupled plasma (ICP) analysis.

 

5.3.3Geophysics

 

Prior to 1998, Kennecott conducted a series of geophysical surveys which are poorly documented or are unavailable to Ambler Metals. With the renewed interest in the belt, Kennecott carried out a helicopter-supported airborne EM (five frequency DIGHEM system) and magnetic survey covering approximately a 70 km stretch of the Ambler belt in March 1998. A total 2,509-line kilometres was flown using 400 m line spacing except at the Arctic deposit where 200 m line spacing was used. The Arctic deposit presented a strong 900 Hz EM conductive signature. From the initial interpretation of the airborne EM data a two-year ground follow-up program to evaluate and drill test the best targets was recommended (Fueg, 1998).

 

During the summer of 1998, Kennecott carried out a well-planned and systematic ground follow-up program. Of the 46 EM anomalies that were identified 17 were ranked A and B and were mapped and evaluated in the field: 12 using soil geochemistry, 9 using a combination of ground EM (Maxmin 2 horizontal loop) and gravity (LaCoste and Romberg Model G gravimeter), and two anomalies were drilled. Eight of the 17 anomalies occurred in prospective geology and coincident anomalous geochemistry and two were drilled in the same summer (Kennecott, 1998).

 

At anomaly 98-3, later named East Dead Creek, located approximately 6 km northwest of the Arctic deposit and 2 km east-northeast of the Dead Creek prospect, Kennecott found sub-cropping gossan roughly coincident with the centre of their airborne and ground EM anomalies. A single vertical hole encountered semi-massive sulphides in three intervals in the upper 40 m of the hole, the best being 0.8% Zn, 0.35% Cu and 0.16% Pb over 15 feet (Kennecott, 1998).

 

Based on the results of the 1998 program, Kennecott made the following recommendations: anomaly 98-3 required further drilling, two other anomalies were drill ready, and five other anomalies, including anomaly 98-9, required additional exploration to define a drill target. Despite the encouraging regional exploration results, Kennecott conducted no further field exploration in the district after 1998 and subsequently optioned the property to NovaGold in 2004.

 

In addition to the regional program, Kennecott completed five lines of controlled source audio magneto telluric (CSAMT) data in Subarctic Valley. The Arctic deposit showed an equally strong conductive response in the CSAMT data as was seen in the EM data. As a result of the survey, Kennecott recommended additional CSAMT for the deposit area.

 

5.3.4Drilling

 

Between 1967 and July 1985, Kennecott (BCMC) completed 86 holes (including 14 large diameter metallurgical test holes) totalling 16,080 m. In 1998, Kennecott drilled an additional six core holes totalling 1,492 m to test for:

 

Extensions of the known Arctic mineralization.

  
Arctic ProjectPage 56
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Grade and thickness continuity.

 

EM anomaly 98-3 (East Dead Creek).

 

Drilling for all BCMC/Kennecott campaigns in the Arctic deposit area (1966 to 1998) totals 92 core holes for a combined 17,572 m (refer to Section 7 for additional information).

 

5.3.5Specific Gravity

 

Prior to 1998, no SG measurements were available for the Arctic deposit rocks. A “factored” average bulk density was used to calculate a tonnage factor for resource estimations. A total of 38 samples from the 1998 drilling at the Arctic deposit were measured for SG determinations. Additional information on density determinations is provided in Section 8.

 

5.3.6Petrology, Mineralogy, and Research Studies

 

There have been numerous internal studies done by Kennecott on the petrology and mineralogy of the Arctic deposit that exist as internal memos, file notes, and reports from as early as 1967. These data have been used in support of geological and mineralogical interpretations.

 

Portable infrared mineral analyzer (PIMA) alteration studies by Kennecott on a limited amount of core show that hydrothermal alteration (Na/Ba-rich micas) can still be spectrally recognized despite later regional metamorphism and continued use was recommended to assist in the structural interpretation of the known mineralization and in tracing the ‘ore horizon’.

 

D. Schmandt completed an undergraduate thesis at Smith College in 2009 entitled “Mineralogy and origin of Zn-rich horizons within the Arctic Volcanogenic Massive Sulphide deposit, Ambler District, Alaska”. Jeanine Schmidt completed a doctoral dissertation at Stanford University in 1983 entitled “The Geology and Geochemistry of the Arctic Prospect, Ambler District, Alaska”; and Bonnie Broman completed a master’s thesis at University of Alaska, Fairbanks in 2014 entitled “Metamorphism and Element Redistribution: Investigations of Ag-bearing and associated minerals in the Arctic Volcanogenic Massive Sulphide deposit, SW Brooks Range, NW Alaska”. These studies have provided additional information on geological and mineralogical settings in the Arctic Project area.

 

5.3.7Geotechnical, Hydrogeological and Acid-Base Accounting Studies

 

A series of geotechnical, hydrological, hydrogeological, and acid-base accounting (ABA) studies were conducted prior to the 2020 FS. Rock geotechnical and hydrogeological studies completed after 1998 are listed in Table 5-2. ABA studies completed after 1998 are listed in Section 13.11.1.

 

5.3.7.1Geotechnical and Hydrogeological Studies

 

In December 1998, URSA Engineering prepared a geotechnical study for Kennecott titled “Arctic Project – 1998 Rock Mass Characterization”. Though general in scope, the report summarized some of the basic rock characteristics as follows:

 

Compressive strengths average 6,500 psi for the quartz mica schists, 14,500 psi for the graphitic schists, and 4,000 psi for talc schists.

  
Arctic ProjectPage 57
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Rock mass quality can be described as average to good quality, massive with continuous jointing except the talc schist, which was characterized as poor quality. The rock mass rating (RMR) averages 40 to 50 for most units except the talc schist which averages 30.

 

In 1998, Robertson Geoconsultants, Inc. (Robertson) of Vancouver prepared a report for Kennecott titled “Initial Assessment of Geochemical and Hydrological Conditions at Kennecott’s Arctic Project”. The report presented the results of the acid generation potential of mine waste and wall rock for the Arctic Project in the context of a hydrological assessment of the climate, hydrology, and water balance analyses at the Arctic deposit. Climatic studies at the time were limited to regional analyses as no climatic data had been collected at the Arctic Project site prior to the review. Regional data, most specifically a government installed gauging station about 32 km to the southwest at Dahl Creek, provided information in assessing the hydrology of the Arctic Project at the time. A total of nine regional gauges were utilized to evaluate the overall potential runoff in the area.

 

Table 5-2: Summary of Previous Geotechnical and Hydrogeological Work Completed After 1998

 

  Rock Geotechnical Hydrogeological
Field Investigations

SRK 2020

Completed geotechnical and hydrogeological drill investigation program consisting of nine (9) drill holes.

Detailed geotechnical core logging completed for four (4) drill holes, basic geotechnical logging completed for 5 drill holes.

Laboratory testing conducted.

SRK 2020

Completed geotechnical and hydrogeological drill investigation program consisting of nine (9) drill holes.

Hydraulic conductivity tests, piezometer installations, and extended duration injection tests were completed in five (5) drill holes.

SRK 2017

Completed staged geotechnical field investigation programs in 2015 and 2016. Five HQ3 drill holes were completed for combined geotechnical and hydrogeological data acquisition purposes.

Thirteen drill holes were surveyed using acoustic televiewer.

Laboratory testing was conducted.

SRK 2017

Completed staged geotechnical field investigation programs in 2015 and 2016. Five HQ3 drill holes were completed for combined geotechnical and hydrogeological data acquisition purposes.

Conducted downhole hydraulic conductivity tests and installed standpipe and vibrating wire piezometers.

Tetra Tech 2013

No geotechnical field investigations were completed.

Review of historical geotechnical studies suggests work completed to a high standard.

Tetra Tech 2013

No hydrogeological field investigations were completed.

BGC 2012

Underground focus.

Completed five HQ3 drill holes with lab testing, core logging and lithology descriptions (see Section 3.2).

Completed structural geology mapping.

Completed laboratory strength testing.

BGC 2012

Installed seven (7) vibe wires in five holes (see Section 3.2 for drill hole locations).

Completed hydraulic conductivity testing for various geotechnical units.

Installed one thermistor.

Hydraulic head measurements at selected drill holes.

  
Arctic ProjectPage 58
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

  Rock Geotechnical Hydrogeological
 

URSA 1998

Mapping of major geological structures, faults, and joints.

Completed structural lab strength testing and collected geotechnical data from resource drill holes

 

URSA 1998

No hydrogeological work completed

Technical Findings

SRK 2020

Updated the geotechnical characterization and structural geology model.

Sloped designs were updated based on updated geotechnical assessments. 3-D numerical stability models were utilized to review the influence of talc in the northeast wall.

 

SRK 2020

Hydrogeological assessments were completed for both the open pit and valley bottom water/waste management areas.

Pit inflow and pore pressure conditions were assessed using numerical and analytical tools.

SRK 2017

Established six geotechnical domains based on the rock mass characteristics and structural orientations. Kinematic and 2-D numerical stability analyses were conducted to provide the recommended slope configurations.

The slope design for the east walls that are sub-parallel to the foliation consisted of 60 m high slopes that are stripped along the dip of the foliation fabric. The recommended IRA in the east walls were 26°-30°.

Slope design of other areas of the proposed open pit were controlled by kinematic failure mechanisms.

SRK 2017

Two alternative conceptual hydrogeological models were established – a multiple water system model (regional shallow perched water table in northeast, deeper water table over the pit footprint), and compartmentalized water system model (water levels compartmentalized by faults, talc, and/or permafrost).

A conservative pore pressure conditions were estimated for slope stability analysis.

Tetra Tech 2013

Considers 7 lithogeochemical units; modeled as 3-D volumes (as supplied by Trilogy)

PEA pit with OSA = 43°, triple benched with 5 m benches, 8 m catch berms (single domain/design sector)

 

Tetra Tech 2013

Assumes groundwater levels will follow topography.

No continuous permafrost in area.

  
Arctic ProjectPage 59
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

  Rock Geotechnical Hydrogeological
 

BGC 2012

Two-dimensional geotechnical model using six (6) units combining lithological units of similar rock mass properties (RMR and other criteria defined for each unit).

No 3-D structural model, plan view map only with two regional thrust faults (West Fault at 50° dipping south-southeast and WSFC at 40° dipping to the south).

Mapped strong foliation sets dipping shallowly to the west and moderately to the southwest.

BGC 2012

Conceptual model of ground water flow.

High flow rates in fault zones should be expected, groundwater flow follows topography.

Not enough information to comment on recharge rate due to uncertainty in permafrost.

Permeability data for main geotechnical units ranging from 3 x 10-9 to 6 x 10-7 m/s.

URSA 1998

Developed six (6) geotechnical units based on drill holes and mapping, classified rocks as weak to moderately strong, talc mica schist is worst unit with RMR = 31.

Mapped E-W trending faults with gouge of muscovite and talc and south dipping thrust fault.

Two sets of joint/foliation present that intersect at 25°.

URSA 1998

No hydrogeological analyses completed.

Suggests permafrost not present based on down hole observations

 

5.3.7.2Acid-Base Accounting Studies

 

The 1998 Robertson study first documented ABA results, based on the selection of 60 representative core samples from the deposit. Since then, SRK has advanced the understanding of acid rock drainage potential with studies in 2010, 2013, and 2015-2017 based on an accumulated dataset from over 1550 ABA drill core samples from waste rock and ore, indicating that about 75% of samples were classified as potentially acid generating. Tailings from metallurgical testing in 2017 and 2019 were analysed for ABA and also shown to be potentially acid generating. Kinetic testing studies have subsequently been conducted on waste rock, ore and tailings, to inform rates of acid generation and metal leaching, and are documented in Section 13.11.2.

 

5.3.8Metallurgical Studies

 

Kennecott undertook an extensive series of studies regarding the metallurgy and processing of the Arctic mineralization (refer to summary in Section 10.2 of this Report).

 

5.3.9Development Studies

 

A number of mining and technical studies have been completed over the Arctic Project history, as summarized in Table 5-3.

  
Arctic ProjectPage 60
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 5-3: Mining and Technical Services

 

Company Year Consultant Study
Kennecott 1974 internal Ambler District Evaluation
1976 internal Arctic Deposit Order of Magnitude Evaluation
1978 internal

Arctic Prospect Summary File Report

Arctic Deposit

1981 internal Evaluation of the Arctic and Ruby Creek Deposits
1984 internal Evaluation Update
1985 internal Pre-AFD Report
1990 internal Re-Evaluation
1997 internal Arctic Project Mining Potential
1999 internal Interim Report Conceptual Level Economic Evaluations of the Arctic Resource
1998 SRK Preliminary Arctic Scoping Study
NovaGold 2011 SRK Preliminary Economic Assessment
Trilogy (previously, NovaCopper) 2012 SRK Preliminary Economic Assessment
2013 Tetra Tech Preliminary Economic Assessment
2018 Ausenco Pre-Feasibility Report
Trilogy 2020 Ausenco Feasibility Report
Ambler Metals 2021 Ausenco Tailings Evaluation

  
Arctic ProjectPage 61
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

6GEOLOGICAL SETTING, MINERALIZATION, AND Deposit

 

6.1Deposit Types

 

6.1.1Deposit Model

 

The mineralization at the Arctic deposit and at several other known occurrences within the Ambler Sequence stratigraphy of the Ambler Mining District consists of Devonian age, polymetallic (zinc-copper-lead-silver-gold) VMS-like occurrences.

 

Observations and interpretations at the Arctic deposit such as: 1) the tectonic setting with Devonian volcanism in an evolving continental rift; 2) the geologic setting with bimodal volcanic rocks including pillow basalts and felsic volcanic tuffs; 3) an alteration assemblage with well-defined magnesium-rich footwall alteration and sodium-rich hanging wall alteration; and 4) typical polymetallic base-metal mineralization with massive and semi-massive sulphides, are indicative of a Volcanogenic Massive Sulphide (VMS) deposit that has undergone high strain and complex folding and faulting.

 

A variety of VMS types have been well documented in the literature (Franklin et al., 2005), with the Ambler Schist belt deposits most like deposits associated with bimodal felsic dominant volcanism related to incipient rifting. However, the abundance of volcaniclastic rocks with argillaceous sedimentary rocks and the tabular nature of mineralization are considered by Piercey (2022) to be similar to felsic silicilastic VMS environments.

 

Evidence exists for both exhalation and emplacement on the seafloor and replacement of rocks in the sub-seafloor, either via filling of void space or via dissolution of original rocks and replacement by new minerals (Piercey, 2022). For example, the presence of barite, attributed to the mixing of BaCl2(aq) from hydrothermal fluids with seawater sulphate (SO4(aq)) at the vent-seawater interface supports some of the mineralization at Arctic likely precipitated on the seafloor. In contrast, there is ample textural evidence of subseafloor replacement at Arctic, such as the presence of transitions from massive sulphides into selective replacement of interpreted permeable tuff beds in the hanging wall mudstones.

 

The tonnage, grades, and stratigraphic setting of the Arctic deposit, and its broader tectonostratigraphic setting, are similar to other felsic siliclastic VMS environments globally. The deposit has strong similarities to deposits found the Finlayson Lake VMS district, Yukon, Bathurst district, New Brunswick, and some parts of the Iberian Pyrite Belt, Spain-Portugal (Piercey, 2022).

 

A VMS model is considered applicable for use in exploration targeting in the project area and the interpretation of the geological model supporting the Mineral Resource estimate.

 

6.2Regional Geology – Southern Brooks Range

 

The Ambler Mining District occurs along the southern margin of the Brooks Range within an east-west trending zone of Devonian to Jurassic age submarine volcanic and sedimentary rocks (Hitzman et al., 1986). The district covers both: 1) VMS-like deposits and prospects hosted in the Devonian age Ambler Sequence (or Ambler Schist belt or Schist belt), a group of metamorphosed bimodal volcanic rocks with interbedded tuffaceous, graphitic, and calcareous volcaniclastic metasediments; and 2) epigenetic carbonate-hosted copper deposits occurring in Silurian to Devonian age carbonate and phyllitic rocks of the Bornite Carbonate Sequence. The Ambler Sequence occurs in the upper part of the Anirak Schist, the thickest member of the Schist belt or Coldfoot subterrane (Moore et al., 1994). VMS-like stratabound mineralization can be found along the entire 110 km strike length of the district. Immediately south of the Schist belt in the Cosmos Hills, a time equivalent section of the Anirak Schist that includes the approximately 1 km thick Bornite Carbonate Sequence. Mineralization of both the VMS-like deposits of the Schist belt and the carbonate-hosted deposits of the Cosmos Hills has been dated at 375 to 387 Ma (Selby et al., 2009; McClelland et al., 2006).

  
Arctic ProjectPage 62
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

The Ambler Mining District is characterized by increasing metamorphic grade to the north, perpendicular to the strike of the east-west trending units. The district shows isoclinal folding in the northern portion and thrust faulting to south (Schmidt, 1983). The Devonian to Late Jurassic age Angayucham basalt and the Triassic to Jurassic age mafic volcanic rocks are in low angle over thrust contact with various units of the Ambler Schist belt and Bornite Carbonate Sequence along the northern edge of the Ambler Lowlands.

 

6.2.1Terrane Descriptions

 

The terminology used to describe the terranes in the southern Brooks Range evolved during the 1980s because of the region’s complex juxtaposition of rocks of various compositions, ages and metamorphic grade. Hitzman et al. (1986) divided the Ambler Mining District into the Ambler and Angayucham terranes. Further work (Till et al., 1988; Silberling et al., 1992; Moore et al., 1994) includes the rocks of the previously defined Ambler terrane as part of the regionally extensive Schist belt or Coldfoot subterrane along the southern flank of the Arctic Alaska terrane as shown in Figure 6-1 (Moore et al., 1994). In general, the southern Brooks Range is composed of east-west trending structurally bound allochthons of variable metasedimentary and volcanogenic rocks of Paleozoic age.

  
Arctic ProjectPage 63
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 6-1: Regional Geologic Terranes of the Southern Brooks Range

 

 

Source: Trilogy Metals, 2019.

 

The Angayucham terrane, which lies along the southern margin of the Brooks Range, is locally preserved as a klippen within the eastern Cosmos Hills and is composed of weakly metamorphosed to unmetamorphosed massive-to-pillowed basalt rocks with minor radiolarian cherts, marble lenses and isolated ultramafic rocks. This package of Devonian to Late Jurassic age (Plafker et al., 1977) mafic and ultramafic rocks is interpreted to represent portions of an obducted and structurally dismembered ophiolite that formed in an ocean basin south of the present-day Brooks Range (Hitzman et al., 1986; Gottschalk and Oldow, 1988). Locally, the Angayucham terrane overlies the Schist belt to the north along a poorly exposed south-dipping structure.

 

Gottschalk and Oldow (1988) describe the Schist belt as a composite of structurally bound packages composed of dominantly greenschist facies rocks, including pelitic to semi-pelitic quartz-mica schist with associated mafic schists, metagabbro and marbles. Locally, the Schist belt includes the Upper Silurian to middle Devonian age Bornite Carbonate Sequence, the lower Paleozoic age Anirak pelitic, variably siliceous and graphic schists, and the mineralized Devonian age Ambler sequence consisting of volcanogenic and siliciclastic rocks variably associated with marbles, calc-schists, metabasites and mafic schists (Hitzman et al., 1982; Hitzman et al., 1986). The lithologic assemblage of the Schist belt is consistent with an extensional, epicontinental tectonic origin.

  
Arctic ProjectPage 64
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Structurally overlying the Schist belt to the north is the Central belt. The Central belt is in unconformable contact with the Schist belt along a north-dipping low-angle structure (Till et al., 1988). The Central belt consists of lower Paleozoic age metaclastic and carbonate rocks, and Proterozoic age schists (Dillon et al., 1980). Both the Central belt and Schist belt are intruded by meta-to-peraluminous orthogneisses, which locally yield a slightly discordant U-Pb thermal ionization mass spectrometry zircon crystallization age of middle to late Devonian (Dillon et al., 1980; Dillon et al., 1987). This igneous protolith age is supported by Devonian orthogneiss ages obtained along the Dalton Highway, 161 km to the east of the Ambler Mining District (Aleinikoff et al., 1993).

 

Overlying the Schist belt to the south is the Phyllite belt, characterized in the Ambler mining district as phyllitic black carbonaceous schists of the Beaver Creek Phyllite which may underlie much of the Ambler Lowlands between the Brooks Range and the Arctic deposit to the north and the Cosmos Hills and the Bornite deposit to the south. The recessive weathering nature of the Beaver Creek Phyllite limits the exposure, but the unit is assumed to occur as a thrust sheet overlying the main Schist belt rocks.

 

6.2.2Regional Tectonic Setting

 

Rocks exposed along the southern Brooks Range consist of structurally bound imbricate allochthons that have experienced an intense and complex history of deformation and metamorphism. Shortening in the fold and thrust belt has been estimated by some workers to exceed 500 km (Oldow et al., 1987) based on balanced cross sections across the central Brooks Range. In general, the metamorphic grade and tectonism in the Brooks Range increases to the south and is greatest in the Schist belt. The tectonic character and metamorphic grade decreases south of the Schist belt in the overlying Angayucham terrane.

 

During the late Jurassic to early Cretaceous, the Schist belt experienced penetrative thrust-related deformation accompanied by recrystallization under high-pressure and low-temperature metamorphic conditions (Till et al., 1988). The northward directed compressional tectonics were likely related to crustal thickening caused by obduction of the Angayucham ophiolitic section over a south-facing passive margin. Thermobarometry of schists from the structurally deepest section of the northern Schist belt yield relict metamorphic temperatures of 475°C, ±35°C, and pressures from 7.6 to 9.8 kb (Gottschalk and Oldow, 1988). Metamorphism grades from lower greenschist facies in the southern Cosmos Hills to upper greenschist facies, locally overprinting blueschist mineral assemblages in the Schist belt (Hitzman et al., 1986).

 

Compressional tectonics, which typically place older rocks on younger, does not adequately explain the relationship of young, low-metamorphic-grade over older and higher-grade metamorphic rocks observed in the southern Brooks Range hinterland. Mull (1982) interpreted the Schist belt as a late antiformal uplift of the basement to the fold and thrust belt. More recent models propose that the uplift of the structurally deep Schist belt occurred along duplexed, north-directed, thin-skinned thrust faults, followed by post-compressional south-dipping low angle normal faults along the south flank of the Schist belt, accommodating for an over-steepened imbricate thrust stack (Gottschalk and Oldow, 1988; Moore et al., 1994). Rapid cooling and exhumation of the Schist belt began at the end of the early Cretaceous age at 105 to 103 Ma, based on Ar40/Ar39 cooling ages of hornblende and white mica from near Mount Igikpak, and lasted only a few million years (Vogl et al., 2003). Additional post-extension compressive events during the Paleocene age further complicate the southern Brooks Range (Mull, 1985).

 

6.3Local Geology

 

Rocks that form the Ambler Sequence consist of a lithologically diverse sequence of lower Devonian age carbonate and siliciclastic strata with interlayered mafic lava flows and sills. The clastic strata, derived from terrigenous continental and volcanic sources, were deposited primarily by mass-gravity flow into the sub-wavebase environment of an extending marginal basin.

  
Arctic ProjectPage 65
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

The Ambler Sequence underwent two periods of intense, penetrative deformation. Sustained upper greenschist-facies metamorphism with coincident formation of a penetrative schistosity and isoclinal transposition of bedding marks the first deformation period. Pervasive similar-style folds on all scales deform the transposed bedding and schistosity, defining the subsequent event. At least two later non-penetrative compressional events deform these earlier fabrics. Observations of the structural and metamorphic history of the Ambler Mining District are consistent with current tectonic evolution models for the Schist belt, based on the work of others elsewhere in the southern Brooks Range (Gottschalk and Oldow, 1988; Till et al., 1988; Vogl et al., 2002).

 

Figure 6-2 shows the location and geology of the Ambler mining district and the Schist belt terrane including the Anirak Schist, the Kogoluktuk Schist and the Ambler Sequence, the contemporaneous Bornite Carbonate Sequence in the Cosmos Hills to the south, and the allochthonous overthrust Cretaceous sedimentary rocks and Devonian Angayucham Terrane volcanic rocks.

 

Figure 6-2: Local Geology of the Ambler Mining District

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 66
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

6.3.1General Stratigraphy of the Ambler Sequence

 

Though the Ambler Sequence is exposed over 110 km of strike length, the following descriptions and comments refer to an area between the Kogoluktuk River on the east and the Shungnak River on the west where Trilogy has focused the majority of its exploration efforts over the last decade.

 

The local base of the Ambler Sequence consists of variably metamorphosed carbonates historically referred to as the Gnurgle Gneiss. Trilogy’s joint venture, Ambler Metals interprets these strata as calc-turbidites, perhaps deposited in a sub-wavebase environment adjacent to a carbonate bank. Calcareous schists overlie the Gnurgle Gneiss and host sporadically distributed mafic sills and pillowed lavas. These fine-grained clastic strata indicate a progressively quieter depositional environment up section, and the presence of pillowed lavas indicates a rifting, basinal environment.

 

Overlying these basal carbonates and pillowed basalts is a section of predominantly fine-grained carbonaceous siliciclastic rocks that host most of the mineralization in the district including the Arctic deposit. This quiescent section indicates further isolation from a terrigenous source terrain.

 

Above the stratigraphy hosting the Arctic deposit is a section with voluminous reworked silicic volcanic strata. At the base of this section is the Button Schist, a regionally continuous and distinctive K-feldspar porphyroblastic unit that serves as an excellent marker above the main mineralized stratigraphy. Figure 6-3 shows idealized sections for several different areas in and around the Arctic deposit.

 

Several rock units show substantial changes in thickness and distribution in the vicinity of the Arctic deposit that may have resulted from the basin architecture existing at the time of deposition. Between the Arctic Ridge, geographically above the Arctic deposit, and the Riley Ridge to the west, several significant differences have been documented including:

 

The Gnurgle Gneiss is thickest in exposures along the northern extension of Arctic Ridge and appears to thin to the west.

 

Mafic lavas and sills thicken from east to west. They occur as thick units in upper Subarctic Creek and to the west but are sparsely distributed to the east.

 

The quartzite section within and above the Arctic sulphide horizon does not occur in abundance east of Arctic Ridge; it is thicker and occurs voluminously to the west.

 

Button Schist thickens dramatically to the west from exposures on Arctic Ridge; exposures to the east are virtually non-existent.

 

Greywacke sands do not exist east of Subarctic Creek but occur in abundance as massive, channelled accumulations to the west, centred on Riley Ridge.

 

These data are interpreted by Trilogy’s joint venture, Ambler Metals to define a generally north-northwest-trending depocentre through the central Ambler Mining District. Volcanic debris flow occurrences as well as these formational changes suggest that the depocentre had a fault-controlled eastern margin. The basin deepened to the west; the Riley Ridge section was deposited along a high-energy axis, and the COU section lies to the west-southwest distally from a depositional energy point of view. This original basin architecture appears to have controlled mineralization of the sulphide systems at Arctic and Shungnak (Dead Creek), concentrating fluid flow along structures on the eastern basin margin.

  
Arctic ProjectPage 67
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 6-3: Ambler Sequence Stratigraphy in the Arctic Deposit Area

 

 

Source: Trilogy Metals, 2019.

 

Figure 6-4 is a simplified geologic map of the area between the Kogoluktuk and the Shungnak Rivers.

  
Arctic ProjectPage 68
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 6-4: Generalized Geology of the Central Ambler Mining

 

 

Source: Trilogy Metals, 2022.

 

6.3.2Structural Framework of the Ambler Mining District

 

In addition to the underlying pre-deformational structural framework of the district suggested by the stratigraphic thickening of various facies around the Arctic deposit, the Ambler Sequence is deformed by two penetrative deformational events that significantly complicate the distribution and spatial arrangement of the local stratigraphy.

 

6.3.2.1F1 Deformation

 

The earliest penetrative deformation event is associated with greenschist metamorphism and the development of regional schistosity. True isoclinal folds are developed, and fold noses typically are thickened. The most notable F1 fold is the Arctic antiform that defines the upper and lower limbs of the Arctic deposit. The fold closes along a north-northeast-trending fold axis roughly mimicking the trace of Subarctic Creek and opening to the east. Importantly, the overturned lower limb implies that the permissive stratigraphy should be repeated on a lower synformal isocline beneath the currently explored limbs and would connect with the permissive mineralized stratigraphy to the northwest at Shungnak (Dead Creek). Figure 6-5 shows typical F1 folds developed in calcareous Gnurgle Gneiss.

  
Arctic ProjectPage 69
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 6-5: Typical F1 Isoclinal Folds Developed in Calcareous Gnurgle Gneiss

 

 

Source: Trilogy Metals, 2019.

 

6.3.2.2F2 Deformation

 

The earlier F1 schistosity is in turn deformed by an F2 deformational event that resulted in the local development of an axial planar cleavage. The deformational event is well defined throughout the Schist belt and results in a series of south-verging, open to moderately overturned folds that define a series of east-west trending folds of similar vergence across the entire Schist belt stratigraphy.

  
Arctic ProjectPage 70
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

This event is likely temporally related to the emplacement of the Devonian Angayucham volcanics sequences, the obducted Jurassic ophiolites and Cretaceous sediments within the Schist belt stratigraphy.

 

In addition to the earlier penetrative deformation events, a series of poorly defined non-penetrative deformation events, likely due to Cretaceous extension, are seen as a series of warps or arches across the district.

 

The interplay between the complex local stratigraphy, the isoclinal F1 event, the overturned south verging F2 event and the series of post-penetrative deformational events often makes district geological interpretation extremely difficult at a local scale.

 

6.4Arctic Property Geology

 

Previous workers at the Arctic deposit (Russell 1995 and Schmidt 1983) describe three mineralized horizons: the Main Sulphide Horizon, the Upper South Horizon and the Warm Springs Horizon. The Main Sulphide Horizon was further subdivided into three zones: the southeast zone, the central zone, and the northwest zone. Previous deposit modelling was grade-based resulting in numerous individual mineralized zones representing relatively thin sulphide horizons.

 

Recent work by Ambler Metals defines the Arctic deposit as two or more discrete horizons of sulphide mineralization contained in a complexly deformed isoclinal fold with an upright upper limb and an overturned lower limb hosting the main mineralization. Nearby drilling suggests that a third upright lower limb, likely occurs beneath the currently explored stratigraphy. Figure 6-6 is a generalized geologic map of the immediate Arctic deposit area.

  
Arctic ProjectPage 71
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 6-6: Generalized Geologic Map of the Arctic Deposit

 

 

Source: Trilogy Metals, 2019.

 

6.4.1Lithologies and Lithologic Domain Descriptions

 

Historically, five lithologic groupings were used by Kennecott (URSA Engineering, 1998 and Russell, 1995) to describe the local stratigraphy of the deposit. These groupings of rock types and protoliths include: 1) metarhyolite (Button Schist) or porphyroblastic quartz feldspar porphyry and rhyolitic volcaniclastic and tuffaceous rocks; 2) quartz mica schists composed of tuffaceous and volcaniclastic sediments; 3) graphitic schists composed of carbonaceous sedimentary rocks; 4) base metal sulphide bearing schists; and 5) talc schists composed of talc altered volcanic and sedimentary rocks. Trilogy’s joint venture, Ambler Metals has subsequently re-interpreted and modified the lithological groupings. In 2022, Piercey provided further interpretation of the stratigraphy, lithofacies, alteration and mineralization at Arctic based on a study of core from six holes drilled in 2022 and a field visit to Arctic.

  
Arctic ProjectPage 72
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

The principal lithologic units captured in logging and mapping by Trilogy’s joint venture, Ambler Metals are summarized and described in the following subsections, in broadly chronologically order from oldest to youngest. A summary of the interpretation of geology in cross section is shown in Figure 7-14, Figure 7-15, Figure 7-17 and Figure 7-18. These cross sections illustrate significant mineralized zones encountered on the Property including, a summary of the surrounding rock types, relevant geological controls, and the length, width, depth and continuity of the mineralization.

 

6.4.1.1Greenstone (GNST)

 

Greenstones consists of massive dark-green amphibole and garnet-bearing rocks, differentiated by their low quartz content and dark green colour. Intervals of greenstone range up to 80 m in thickness and are identified as pillowed flows, sills, and dikes. Multiple ages of deposition are implied by the presence of both basal pillowed units as well as intrusive sill and dike-like bodies higher in the local stratigraphy. Textural and colour similarities along with similar garnet components and textures often cause confusion with some metasedimentary greywackes within the Ambler Sequence stratigraphy.

 

6.4.1.2Chlorite Schist (ChS)

 

This unit is likely alteration-related but has been used for rocks where more than half of the sheet silicates are composed of chlorite. In the field, some samples of chlorite schist show a distinctive dark green to blue-green colour, but in drill core the chlorite schists commonly have a lighter green colour. Some intervals of chlorite schist are associated with talc-rich units. The footwall to the Arctic deposit is dominated by this lithofacies which Piercey (2022) describes as variably chlorite (and talc) altered tuffs and lapilli tuffs. Immediately beneath mineralization the rocks are tuffaceous and are strongly and pervasively chlorite and talc (- sericite) altered and, with depth, there are alternating layers of finer chlorite-talc bearing tuffs and quartz and feldspar and/or felsic fragment lapilli tuffs.

 

6.4.1.3Talc Schist (TS)

 

Talc-bearing schists are often in contact with chlorite-rich units and reflect units which contain trace to as much as 30% talc, often occurring on partings. Like the chlorite schist this unit is likely alteration related.

 

6.4.1.4Black to Grey Schist (GS)

 

Black or grey schists appear in many stratigraphic locations particularly higher in the stratigraphy but principally constitute the mineralized permissive stratigraphy of the Arctic deposit lying immediately below the Button Schist (MRP). The schist is typically composed of muscovite, quartz, feldspar, graphite, pyrite and/or pyrrhotite, and sometimes chlorite and/or biotite, interpreted to be an argillite with minor laminae of felsic ash and mm-sized crystals of feldspar and quartz (Piercey, 2022) The texture is phyllitic, variably crenulated, and suggests a pelitic protolith, likely deposited in a basin that was progressively filled with terrigenous fine sediment. This unit is host to the MS and SMS horizons that constitute the Arctic deposit.

 

Piercey (2022) recognized a distinct laminated argillite/mudstone that is more siliceous and 30 cm to several metres in thickness above massive sulphides. This argillite is interlayered with mm to cm scale tuffaceous beds that contain quartz and rhyolite ash and is variably pyritic with flecks and spots of pyrite.

  
Arctic ProjectPage 73
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

6.4.1.5Button Schist (MRP)

 

This rock type consists of quartz-muscovite-feldspar schists with abundant distinctive 1 to 3 cm K-feldspar porphyroblasts of metamorphic origin and occasional 0.5 to 2 cm blue quartz phenocrysts of likely igneous origin. The unit shows a commonly massive to weakly foliated texture, although locally the rocks have a well-developed foliation with elongate feldspars. Piercey (2022) observed the crystals are hosted within a grey to black argillaceous to tuffaceous matrix and interprets the Button Schist to be a crystal-rich lapilli tuff to tuff.

 

6.4.1.6Quartz-Mica-(Feldspar) Schist (QMS/QFMS)

 

This schistose rock contains variable proportions of quartz, muscovite, and sometimes feldspar. The schist usually contains high amounts of interstitial silica, and sometimes have feldspar or quartz porphyroblasts. The texture of the unit shows significant variability and likely represents both altered and texturally distinct felsic tuffs and other volcaniclastic lithologies.

 

Piercey (2022) distinguishes four distinct units within the hanging wall quartz-mica (feldspar) schist: rhyolitic tuff with argillite laminae and wisps; rhyolitic tuffs to lapilli tuffs; clotted feldspar lapilli tuff, and a lapilli tuff with lenticular cm-sized fragments variably replaced by pyrite and sphalerite that is referred to as the lenticular unit. This unit sits directly atop mineralization or stratigraphically above the distinct laminated argillite/mudstone described above.

 

6.4.1.7Debris Flow (DM)

 

This unit contains a range of unsorted, matrix supported polylithic clasts including clasts of the Button Schist, occurring in black to dark grey, very fine-grained graphitic schist. The unit occurs as lenses within other stratigraphic units, and likely represents locally derived debris flows or slumps.

 

6.4.1.8Greywacke (GW)

 

This unit consists of massive green rocks with quartz, chlorite, probably amphibole, feldspar, muscovite, and accessory garnet, biotite, and calcite/carbonate. Voluminous accumulations of medium-grained greywacke occur within, but generally above, the quartz mica schist and are differentiated from texturally similar greenstones by the presence of detrital quartz, fine-grained interbeds, graded bedding and flute casts.

 

6.4.1.9Lithogeochemistry of Immobile Trace Elements

 

In 2007, work by NovaGold suggested that many of the nondescript felsic metavolcanic lithologies were simply alteration and textural variants of the felsic rock units and logging was not adequately capturing true compositional lithological differences between units. Twelker (2008) demonstrated that the use of immobile trace elements, specifically Al2O3:TiO2 (aluminum oxide: titanium dioxide) ratios, could be used to effectively differentiate between different felsic volcanic and sedimentary suites of rocks at the Arctic deposit.

 

Lithogeochemistry shows three major felsic rock suites in the Arctic deposit area: a rhyolite suite; and intermediate volcanic suite and a volcaniclastic suite. These suites are partially in agreement with the logged lithology but in some instances the lithogeochemistry showed that alteration in texture and composition masked actual lithologic differences.

 

Results of the lithogeochemistry have led to a better understanding of the stratigraphic continuity of the various units and have been utilized to model the lithologic domains of the Arctic deposit more accurately.

  
Arctic ProjectPage 74
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

6.4.1.10Lithologic Domains

 

Though a variety of detailed lithologies are logged during data capture, Ambler Metals models the deposit area as two distinct structural plates, an Upper Plate and a Lower Plate separated by the Warm Springs Fault. The Upper and Lower Plates contain similar lithologic domains that are primarily defined by lithogeochemical characteristics but are also consistent with their respective acid-generating capacities and spatial distribution around the fold axes. The domains include the following units: the Button Schist (a meta-rhyolite porphyry - MRP), aphanitic meta-rhyolite (AMR), a series of felsic quartz mica schists (QMS), and carbonaceous schists of the Grey Schist unit (GS). An alteration model was built to adequately characterize the chlorite and talc schists found within the deposit (ChS, ChTS, and TS). The mineralization is modelled as eight distinct zones (Zones 1–8) found both in the Upper and Lower Plates and range from MS to SMS.

 

6.4.2Structure

 

Earlier studies (Russell, 1977, 1995; Schmidt, 1983) concluded mineralization at the Arctic deposit was part of a normal stratigraphic sequence striking northeast and dipping gently southwest. Subsequent reinterpretation by Kennecott in 1998 and 1999 suggested the entire Ambler Sequence could be overturned. Proffett (1999) reviewed the Arctic deposit geology and suggested that a folded model with mineralization as part of an isoclinal anticline opening east and closing west could account for the mapped and logged geology. His interpretation called for an F2 fold superimposed on a north-trending F1 fabric.

 

Lindberg (2004) supported a similar folded model though he considered that the main fold at Arctic to be northwest-closing and southeast-opening. Lindberg named this feature the Arctic antiform and interpreted it to be an F1 fold.

 

Lindberg believed most folding within the deposit occurred in the central part, within a southwest plunging “Cascade zone.” The increased thicknesses of mineralized intervals in this part of the property can in part be explained by the multiple folding of two main mineralized horizons as opposed to numerous individual mineralized beds as shown in the 1995 geologic model. The Cascade zone appears to be confined to the upper sulphide limbs of the Arctic antiform.

 

in 2008, closer spaced drilling across the Cascade zone confirmed the continuity of the two mineralized horizons but did not support the complexity proposed by Lindberg. Dodd et al. (2004) suggested that some of the complexity might be related to minor thrusting. Results of mapping in 2006 supported the interpretation of an F2 fold event that may fold the lower Button Schist back to the north under the deposit in this area (Otto, 2006). To test this concept, deep drilling on the north side of the deposit in 2007 encountered the appropriate upright stratigraphy at depth. Though the target horizon was not reached due to the drill rig limitations, the hole did encounter significant mineralization below the Button Schist immediately above the sulphide-bearing permissive stratigraphy.

 

6.4.3Arctic Deposit Alteration

 

Schmidt (1988) defined three main zones of hydrothermal alteration occurring at the Arctic deposit:

 

A main chloritic zone occurring within the footwall of the deposit consisting of phengite and magnesium-chlorite.

 

A mixed alteration zone occurring below and lateral to sulphide mineralization consisting of phengite and phlogopite together with talc, calcite, dolomite, and quartz.

 

A pyritic zone overlying the sulphide mineralization.

  
Arctic ProjectPage 75
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Field observations conducted by NovaGold in 2004 and 2005 supported by logging and short-wave infrared (SWIR) spectrometry only partially support Schmidt’s observations.

 

Talc and magnesium chlorite are the dominant alteration products associated with the sulphide-bearing horizons. Talc alteration grades downward and outward to mixed talc-magnesium chlorite with minor phlogopite, into zones of dominantly magnesium chlorite, then into mixed magnesium chlorite-phengite with outer phengite-albite alteration zones. Thickness of alteration zones vary with stratigraphic interpretation, but tens of metres for the outer zones is likely, as seen in phengite-albite exposures on the east side of Arctic Ridge. Stratigraphically above the sulphide-bearing horizons significant muscovite as paragonite is developed and results in a marked shift in sodium/magnesium ratios across the sulphide bearing horizons.

 

Piercey (2022) describes footwall alteration dominated by an assemblage of chlorite and talc with lesser sericite, quartz and carbonate with intense, pervasive talc-chlorite alteration extending between 10-50 m into the immediate footwall. Chlorite-talc alteration extends at least +200m into the footwall, decreasing in intensity with depth.

 

Hanging wall alteration extends approximately 50-100 metres into the hanging wall with intense talc-sericite alteration and sulphide replacement in the lenticular unit, decreasing in intensity upwards, to be patchier to semi-pervasive talc-sericite alteration in the upper parts of the stratigraphy (Piercey, 2022).Visual and quantitative determination of many of the alteration products is difficult at best due to their light colours and the well-developed micaceous habit of many of the alteration species. Logging in general has poorly captured the alteration products and the SWIR methodology though far more effective in capturing the presence or absence of various alteration minerals adds little in any quantitative assessment.

 

Of particular note are the barium species including barite, cymrite (a high-pressure barium phyllosilicate), and barium-bearing muscovite, phlogopite and biotite. These mineral species are associated with both alteration and mineralization and demonstrate local remobilization during metamorphism (Schmandt, 2009). Though little has been done to document their distribution to date, they do have a significant impact on bulk density measurements (refer to discussions in Section 10 and Section 11).

 

Talc is of particular importance at the Arctic deposit due to its potential negative impact on flotation characteristics during metallurgical processing, and on pit slope stability. The majority of the talc zones occur between the upper, stratigraphically up-right mineralized zones and the lower, overturned mineralized zones. Piercey (2022) noted that the strong talc alteration prevalent at Arctic is rather unique in this type of setting and may be due to the Mg-rich nature of the calc-silicates and carbonate-bearing rocks in the Anirak Schist underlying the felsic-dominated package.

 

6.4.4Arctic Deposit Mineralization

 

Mineralization occurs as stratiform SMS to MS beds within primarily graphitic schists and fine-grained quartz mica schists. The sulphide beds average 4 m in thickness but vary from less than 1 m up to as much as 18 m in thickness. The sulphide mineralization occurs within eight modelled zones lying along the upper and lower limbs of the Arctic isoclinal anticline. The zones are all within an area of roughly 1 km2 with mineralization extending to a depth of approximately 250 m below the surface. There are five zones of MS and SMS that occur at specific pseudo-stratigraphic levels which make up the bulk of the Mineral Resource estimate. The other three zones also occur at specific pseudo-stratigraphic levels but are too discontinuous.

 

Unlike more typical VMS deposits, mineralization is not characterized by steep metal zonation or massive pyritic zones. Mineralization dominantly consists of sheet-like zones of base metal sulphides with variable pyrite and only minor zonation, usually on a small scale.

  
Arctic ProjectPage 76
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Mineralization is predominately coarse-grained sulphides comprising chalcopyrite, sphalerite, galena, tetrahedrite-tennantite, pyrite, arsenopyrite, and pyrrhotite. Sulphides occur as disseminated (<30%), semi-massive (30 to 50% sulphide) to massive (greater than 50% sulphide) layers. Trace amounts of electrum are also present. Gangue minerals associated with the mineralized horizons include quartz, barite, white mica, chlorite, stilpnomelane, talc, calcite, dolomite and cymrite.

 

6.5Prospects

 

In addition to the Arctic deposit, numerous other VMS-like occurrences are present in the UKMP land package. The most notable of these occurrences are the Dead Creek (also known as Shungnak), Sunshine, Cliff, Horse, and the Snow prospects to the west of the Arctic deposit and the Red, Nora, Tom-Tom and BT prospects to the east. Four kilometres northwest of Arctic is target 98-9 where chalcopyrite and sphalerite associated with pyrrhotite and quartz carbonate veins are found in chlorite-biotite schists. Figure 6-7 shows the UKMP land package and the prospect locations. Figure 6-7 also shows: 1) the Smucker deposit on the far west end of the Ambler Sequence which is currently owned by Teck Alaska Inc.; 2) the Sun deposit at the eastern end of the Ambler Sequence and owned by Valhalla Metals Inc, and 3) carbonate-hosted deposits and prospects in the Bornite Carbonate Sequence controlled by Ambler Metals/NANA.

  
Arctic ProjectPage 77
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 6-7: Major Prospects of the Ambler Mining District

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 78
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

7EXPLORATION

 

7.1Exploration

 

Table 7-1 summarizes the exploration work conducted by NovaGold, Trilogy (formerly, NovaCopper), and Ambler Metals from 2004 to the present. Field exploration was largely conducted during the period between 2004 to 2007 with associated engineering and characterization studies between 2008 and the present.

 

Table 7-1:Summary of NovaGold/Trilogy/Ambler Metals Exploration Activities Targeting VMS-style Mineralization in the Ambler Sequence Stratigraphy and the Arctic Deposit

 

Work Completed Year Details Focus
Geological Mapping
- 2004 - Arctic deposit surface geology
- 2005 - Ambler Sequence west of the Arctic deposit
- 2006 - COU, Dead Creek, Sunshine, Red
- 2015, 2016 SRK Geotechnical Structural Mapping
- 2016 - Arctic deposit surface geology
- 2021 - Snow, Ambler, Nani, DH, Cliff, Sunshine, Dead Creek, BT, 98-9/Pipe, COU, SE Arctic, Nora
- 2022 - Snow, Ambler, Nani, DH, Bud, Sunshine, Dead Creek, BT, 98-9/Pipe, COU, East Arctic, Nora, South Cliff, SK, Cynbad, Z, Tom Tom, Kogo/White Creek
Geophysical Surveys
SWIR Spectrometry 2004 2004 drill holes Alteration characterization
TDEM 2005 2 loops Follow-up of Kennecott DIGHEM EM survey
2006 13 loops District targets
2007 6 loops Arctic extensions
Downhole EM 2007 4 drill holes Arctic deposit
VTEM Plus (Versatile Time Domain Electromagnetic) airborne helicopter geophysical 2019 400m line spacing with 200m infill with tie lines 4000m spacing Ambler Mining District and Cosmos Hills with infill over Arctic, Sunshine and Horse-Cliff

  
Arctic ProjectPage 79
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Work Completed Year Details Focus
ZTEM (Z-Axis Tipper Electromagnetic) airborne helicopter geophysical 2019 400m line spacing with tie lines 4000m spacing Ambler Mining District and Cosmos Hills with infill over Arctic, Sunshine and Horse-Cliff
Geochemistry
- 2005 - Stream silts – core area prospects
- 2006 - Soils – core area prospects
- - Stream silts – core area prospects
- 2007 - Soils – Arctic deposit area
- 2021 - Soils - VTEM 26-29, JA Creek, West Dead Creek, Dead Creek
- 2022 - Soils - Sub Arctic Valley, South Cliff, VTEM 26-29, VTEM-41, VTEM-23 , East and West Sunshine, Tom Tom, Kogo/White Creek, SK, Cynbad, East Arctic,  West Dead Creek, Dead Creek, 98-9/Pipe, Z, Nora, Ambler, Nani
-   Streams silts - Core area prospects
Survey
Collar 2004 to 2011, 2018, 2019, 2021, 2022 DGPS All 2004 to 2019 NovaCopper drill holes
2004, 2008 Resurveys Historical Kennecott drill holes
Photography/Topography 2010 - Photography/topography
LiDAR Survey 2015, 2016 - LiDAR over Arctic deposit
Technical Studies
Geotechnical 2010 BGC Preliminary geotechnical and hazards
ML/ARD 2011 SRK Preliminary ML and ARD
Metallurgy 2012 SGS Preliminary mineralogy and metallurgy
Geotechnical and Hydrology 2012 BGC Preliminary rock mechanics and hydrology
Geotechnical and Hydrology 2015, 2016, 2018, 2019, 2021, 2022 SRK Arctic PFS and FS slope design

  
Arctic ProjectPage 80
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Work Completed Year Details Focus
ML/ARD 2015, 2016, 2017, 2018, 2019 SRK Static kinetic tests and ABA update - ongoing
Metallurgy 2015, 2016, 2017, 2018, 2019, 2021 SGS, ALS Cu-Pb Separation Testwork; Flotation and Variability Testwork; SAG Mill Comminution (SMC) Testwork, filtration Testwork, thickener Testwork, and tailings settling testing
Arctic Project Evaluation
Resource Estimation 2008 SRK Resource estimation
PEA 2011 SRK PEA - Underground
  2012 Tetra Tech PEA – Open Pit
PFS 2018 Ausenco Pre-Feasibility Study
FS 2020 Ausenco Feasibility Study

 

Note:SWIR = short wave infrared; LiDAR = light detection and ranging; ML = metal leaching; BGC = BGC Engineering Inc.; SGS = SGS Canada; ALS = ALS Metallurgy; PEA = preliminary economic assessment.

 

7.1.1Grids and Surveys

 

Survey and data capture during the Kennecott’s programs used the UTM coordinates system Zone 4, NAD27 datum. In 2010, NovaGold converted all historical geology and topographic data for the Arctic deposit into the NAD83 datum for consistency. At that time NovaGold contracted WH Pacific, Inc. (WHPacific) to re-establish project-wide survey control and benchmarks for the Arctic deposit. Current Mineral Resource estimate and geologic models use topography completed in 2010 by PhotoSat Inc. The resolution of the satellite imagery used was at 0.5 m and a 1 m contour map and digital elevation model were generated.

 

Trilogy retained WHPacific (and sub-consultant Quantum Spatial, Inc.) to conduct an aerial LiDAR survey over the Upper Kobuk area during 2015. Due to scheduling difficulties and poor weather conditions only 70% of the survey was completed in 2015. The remaining 30% of the aerial survey, as well as the final post-processing work, was completed between June and October 2016.

 

7.1.2Geological Mapping

 

NovaGold focused its exploration mapping efforts on an area covering approximately 18 km of strike length of the permissive Ambler Sequence rocks of the Schist belt stratigraphy. This area is centred on the Arctic deposit and covers the thickest portion of the Ambler Sequence rocks. The area covers many of the most notable mineralized occurrences including the Red prospect east of the Kogoluktuk River, the Arctic deposit, and the nearby occurrences at the West Dead Creek and Dead Creek prospects, and the CS, Bud and Sunshine prospects west of the Shungnak River.

 

In 2004, mapping focused on the surface geology in and around the Arctic deposit while exploration in 2005 extended the Ambler Sequence stratigraphy to the west. In 2006 with expansion of the exploration focus to encompass the immediate district and to support a major TDEM geophysical program, mapping was extended to include the area between the Sunshine prospect on the west and the Red prospect on the east. Figure 7-1 shows areas mapped by successive campaigns, which resulted in the generalized geological interpretation shown in Figure 6-4.

  
Arctic ProjectPage 81
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-1:Mapping Campaigns in and around the Arctic Deposit

 

 

Source: Trilogy Metals, 2019.

 

SRK was contracted in 2015 to create a structural geology model primarily based on brittle structures of the Arctic deposit for pit design and mine scheduling. The majority of the structural mapping took place along the north-south trending Arctic Ridge, and along the northwest trending ridge above a cirque to the south of the deposit, both of which provided the greatest exposure.

 

Geologic and structural mapping were completed by Trilogy geologists during the 2016 field season. The objectives of the mapping project were threefold; 1) to ground-truth the northeast and north-south trending fault structures identified by SRK in 2015 and to otherwise support SRK’s 2016 geotechnical mapping efforts, 2) field check the outcrops mapped in 2006 and 2008 recorded in the current GIS database, and 3) determine the nature of the Warm Springs Fault by mapping in the immediate hanging wall of this apparent structural feature. The first objective was successfully accomplished and the pending SRK geotechnical structural model was considered to be robust. The two other objectives were partly met during the short field season.

  
Arctic ProjectPage 82
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Geological mapping was completed by Ambler Metals geologists during the 2021 and 2022 field seasons. The mapping and geochemical sampling occurred at numerous prospects throughout the Ambler Belt, including the Snow, Ambler, Nora, Sunshine, Centre of the Universe, Pipe, DH, Cliff, 98-9 and BT prospects. The purpose of geologic mapping and sampling was to increase mapped extents at known prospects, collect mineralized and non-mineralized surface samples for various analyses and evaluate VTEM anomalies identified from the 2019 survey.

 

7.1.3Geochemistry

 

Soil and silt geochemical sampling were used to target many of the VMS prospects in the Ambler Sequence particularly in the core area around the Arctic deposit. Between 2005 and 2007, NovaGold collected 2,272 soils and 278 silt samples. Much of the reconnaissance soil sampling used gridding layouts of 200 m lines and 50 m sample intervals oriented perpendicular to stratigraphy. Results of the sampling were used to refine areas for geophysical surveying, and to define drill targets.

 

Ambler Metals completed soil sampling on numerous prospect areas within the Ambler VMS Belt during the 2021 and 2022 field seasons. In 2021, 731 soil samples were collected at Dead Creek, West Dead Creek, JA Creek, and over four VTEM (anomalies 26-29). Collection points spacing varied by prospect but were generally at 30 m spacing along parallel lines 100-200 m apart oriented to cross-cut stratigraphy. The 2021 program used the same analysis methods as the NovaGold programs.

 

In 2021, soil and silt samples were submitted directly to either ALS Minerals in Fairbanks (a division of ALS Global, formerly ALS Chemex) or Alaska Assay Labs in Fairbanks for sample preparation. The samples were dried and sieved to 80 mesh and forwarded to ALS Minerals for analysis. The samples were analysed using the ME-ICP61 method and a four acid near total digestion with 27 elements measured.

 

7.1.4Geophysics

 

During NovaGold’s tenure, the geophysical surveys were largely focused on ground and downhole EM methods to follow-up on the 1998 DIGHEM airborne EM survey conducted by Kennecott.

 

From 2005 to 2007, NovaGold conducted TDEM surveys and completed 21 different loops targeting the Arctic deposit, extensions to the Arctic deposit and a series of DIGHEM airborne anomalies in and around known prospects and permissive stratigraphy. Table 7-2 summarizes the TDEM loops and locations.

 

Frontier Geosciences of Vancouver, BC completed all of the geophysical programs using a Geonics PROTEM 37 transmitter, a TEM-57 receiver and either a single channel surface coil or a three component BH43-3D downhole probe.

  
Arctic ProjectPage 83
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 7-2:TDEM Loops and Locations

 

Area   2005   2006   2007
Arctic   1   -   6
COU   1   3   -
Dead Creek   -   4   -
Sunshine   -   2   -
Red   -   1   -
Tom   -   1   -
Kogo/Pipe   -   2   -
Total   2   13   6

 

In addition to the TDEM surveys, Frontier Geosciences surveyed four drill holes (AR05-89, AR07-110, AR07-111, and AR07-112). All of the drill holes produced off-hole anomalies, notably AR07-111, which showed evidence of a strong EM conductor north of the hole. Follow-up of this conductor is warranted.

 

In 2019, Trilogy contracted GeoTech Ltd. of Aurora, Ontario to complete VTEM Plus (Versatile Time Domain Electromagnetic) and ZTEM (Z-Axis Tipper Electromagnetic) airborne helicopter geophysical surveys over the Cosmos Hills and the Ambler VMS belt. These survey methods are a significant upgrade over the previous DIGHEM survey flown by Kennecott in 1998 over the VMS belt and the DIGHEM survey flown by NovaGold over the Bornite Sequence in 2006 due to the greater resolution and deeper penetration ability. The magnetic field was also measured using a cesium vapor sensor, though radiometric data were not collected due to snow cover.

 

The program was designed, managed, and results interpreted by Resource Potential, a geophysical consulting company based in Perth, Australia.

 

The VTEM survey was flown at a 400 m line spacing over the Ambler VMS Belt along lines oriented at 20°-200° for the western portion of the belt and along north-south lines for the eastern portion (see Figure 7-2). In-fill lines at 200 m spacing were flown over the Arctic, Sunshine, and Horse-Cliff areas to provide greater resolution in those high priority areas. Tie lines at ~4 km spacing were flown perpendicular to the EM flight lines to provide control for the magnetic survey.

  
Arctic ProjectPage 84
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-2:VTEM Flight Lines Over the Ambler Belt and Cosmos Hill Prospective Areas

 

 

Source: Ambler Metals, 2019.

 

The ZTEM survey was flown along lines with the same orientation as the VTEM survey at 400m line spacing, with tie lines at every 4 km. (Figure 7-3). Resource Potential re-processed the data from GeoTech and provided a 3D EM block model and both plan view depth slices and sectional EM images for the ZTEM survey. Numerous anomalies identified from both the VTEM and ZTEM surveys need further evaluation.

  
Arctic ProjectPage 85
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-3:ZTEM Flight Lines Over the Ambler VMS Belt and the Bornite Deposit

 

 

Source: Trilogy Metals, 2019

 

7.1.5Petrology, Minerology and Research Studies

 

Trilogy supported a series of academic studies of the Arctic deposit. In 2009, Danielle Schmandt completed an undergraduate thesis entitled “Mineralogy and Origin of Zn-rich Horizons within the Arctic Volcanogenic Massive Sulphide deposit, Ambler District, Alaska” for Smith College. The Schmandt thesis focused on a structural and depositional reconstruction of the Arctic deposit with the goal of locating the hydrothermal vents to aid in exploration.

 

Bonnie Broman, a Trilogy geologist, completed a Master of Science thesis in 2014 at the University of Alaska Fairbanks, focusing on the nature and distribution of the silver-bearing mineral species within the Arctic deposit. The thesis is titled “Metamorphism and Element Redistribution: Investigations of Ag-bearing and associated minerals in the Arctic Volcanogenic Massive Sulphide deposit, SW Brooks Range, NW Alaska.”

  
Arctic ProjectPage 86
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

7.2Drilling

 

7.2.1Overview

 

Drilling at the Arctic deposit and within the Ambler Mining District has been ongoing since the initial discovery of mineralization in 1966. Approximately 67,639 m of drilling has been completed within the Ambler Mining District, including 55,038 m of drilling in 285 drill holes sat the Arctic deposit or on potential extensions in 32 campaigns spanning 56 years. Drilling outside the Arctic deposit area is discussed in Section 7.2.2.

 

All of the drill campaigns at the Arctic deposit utilize diamond drill holes and have been run under the supervision of either: 1) Kennecott and its subsidiaries (BCMC), 2) Anaconda, or 3) Trilogy (formerly, NovaCopper) and its predecessor company, NovaGold and its successor joint venture Company, Ambler Metals. Table 7-3 summarizes operators, campaigns, holes, and meters drilled on the Arctic deposit. All drill holes listed in Table 7-3 - except 11 geotechnical holes in 2017, 24 geotechnical holes drilled in 2018, 8 holes from the 2021 program and 34 holes from the 2022 program, for which assay results were not available - were used to validate the geologic model.

 

Table 7-3:Companies, Campaigns, Drill Holes and Meters Drilled at the Arctic Deposit

 

Year   Company   No. of Holes   Metres  
1967   BCMC   7   752  
1968   BCMC   18   3,836  
1969   BCMC   3   712  
1970   BCMC   3   831  
1971   BCMC   1   257  
1972   BCMC   1   407  
1973   BCMC   2   557  
1974   BCMC   3   900  
1975   BCMC   26   4,942  
1976   BCMC, Anaconda   10   805  
1977   BCMC, Anaconda   4   645  
1979   BCMC, Anaconda   3   586  
1980   Anaconda   1   183  
1981   BCMC, Anaconda   2   632  
1982   BCMC, Anaconda   5   677  
1983   BCMC   1   153  
1984   BCMC   2   253  
1986   BCMC   1   184  
1998   Kennecott   6   1,523  
2004   NovaGold   11   2,996  
2005   NovaGold   9   3,393  
2007   NovaGold   4   2,606  
2008   NovaGold   14   3,306  
2011   NovaGold   5   1,193  

  
Arctic ProjectPage 87
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Year   Company   No. of Holes   Metres  
2015   NovaCopper   14   3,055  
2016   NovaCopper   13   3,058  
2017   Trilogy Metals   5   790  
2018   Trilogy Metals   24   906  
2019   Trilogy Metals   9   2,433  
2021   Ambler Metals   18   4,131  
2022   Ambler Metals   47   8,376  
Total   -   272   55,078  

 

Trilogy (formerly, NovaCopper) and its predecessor company, NovaGold and its successor joint venture Company, Ambler Metals, drilled 36,243 m in 173 holes targeting the Arctic deposit and several other prospects within the Ambler Schist belt. Table 7-4 summarizes all the NovaGold/Trilogy/Ambler Metals tenure drilling on the Project.

 

Table 7-4:Summary of NovaGold/Trilogy/Ambler Metals Arctic Deposit Drilling

 

Year   Metres   No. of Drillholes   Sequence   Purpose of Drilling
2004   2,996   11   AR04-78 to 88   Deposit scoping and verification
2005   3,393   9   AR05-89 to 97   Extensions to the Arctic deposit
2006*   3,010   12   AR06-98 to 109   Property-wide exploration drilling
2007   2,606   4   AR07-110 to 113   Deep extensions of the Arctic deposit
2008*   3,306   14   AR08-114 to 126   Grade continuity and metallurgy
2011   1,193   5   AR11-127 to 131   Geotechnical studies
2012*   1,752   4   SC12-014 to 017   Exploration drilling – Sunshine
2015   3,055   14   AR15-132 to 145   Geotechnical-hydrogeological studies, resource infill
2016   3,058   13   AR16-146 to 158   Geotechnical-hydrogeological studies, resource infill
2017**   790   5   AR17-159 to 163   Ore sorting studies
2018   906   24   GT18-AR-01 to 19   Geotechnical studies for site facilities
      MS18-AR-01 to 05  
2019*   2433   9   AR19-0164 to 172   Geotechnical and hydrogeological studies for 2020 FS
  1,357   6   SC19-018 to 023   Exploration drilling – Sunshine
2021**   4,131   18   AR21-0173 to 190   Geotechnical and hydrogeological studies for 2021 FS and In-fill
  2,414   6   Various holes   Property-wide exploration drilling
2022***   8,376   47   AR22-0191 to 237   Geotechnical and infill drilling
  1,644   5   Various holes   Property-wide exploration drilling
Total   46,420   206    -   -

 

Notes: 

*Drilling in 2006, 2012, and some holes in 2019 and 2021 targeted exploration targets elsewhere in the VMS belt. 

**Holes drilled in 2018 are not included in the current resource estimate as they were completed geotechnical site facilities studies. 

***8 holes drilled in 2021 and 2022 are not included in the current resource database and were used to validate the resource model, as the results were not available at the time of updating the resource database.

  
Arctic ProjectPage 88
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Geotechnical holes drilled in 2017 and 2018 are not included in the current resource estimate as they were completed for geotechnical site facilities studies. Assays for 8 out of 18 holes drilled at Arctic in 2021 and 34 out of 34 holes drilled in 2022 were not available for use in grade estimation in the current mineral resource estimate because the assays were not available at the time of resource estimation. Figure 7-4 shows the locations of drill holes in the vicinity of the Arctic deposit.

 

Figure 7-4:Plan Map of Drill Holes coloured by Year in the Vicinity of the Arctic Deposit. Dark Grey is Limits of 2021 Conceptual Pit

 

 

Source: Wood, 2022.

 

Significant exploration drilling has been carried out elsewhere within the UKMP targeting numerous occurrences along the Ambler Schist belt. Table 7-5 summarizes the drilling within the UKMP outside of the Arctic deposit.

 

Figure 7-5 shows the locations of known major prospects and drill collar locations for the Ambler Mining District. Note that none of these drill holes are located within the current Arctic Project and are therefore not included in the resource calculation.

  
Arctic ProjectPage 89
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 7-5:Drill, Meterage and Average Drill Depth for Ambler Sequence VMS Targets

 

Area   Drill Holes
(number)
  Metres   Average
Depth (m)
 
Dead Creek/West Dead Creek   21   3,470   165  
Sunshine/Bud   42   8,468   201  
Snow/Trilogy   11   1,527   139  
Horse/Cliff/DH   22   2,277   104  
Red/Nora/BT   18   2,399   133  
Total   114   18,141   148  

 

Figure 7-5:Collar Locations and Principal Target Areas – Ambler Mining District

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 90
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Exploration in 2006 investigated a series of geophysical anomalies in the central portion of the Ambler Schist belt near the Arctic deposit. In 2012, Trilogy drilled an additional four holes totalling 1,752 m to explore the down dip extension of the Sunshine prospect. Twelve holes totalling 3,100 m were drilled. In 2012, Trilogy drilled an additional four holes totalling 1,752 m to explore the down dip extension of the Sunshine prospect. In 2019, Trilogy drilled 10 holes totalling 3,823 m at four regional targets. Regional drilling is summarized in Table 7-6 and Table 7-7 and in Figure 7-6 to Figure 7-11.

 

Table 7-6:Ambler Metals Exploration Drilling – Ambler Schist Belt

 

Hole
ID
  Area   Target   UTM
East
  UTM
North
  Azimuth
(°)
  Dip
(°)
  Depth
(m)
AR06-98   COU   EM Anomaly   609490   7454374   0   -90   712.6
AR06-99   98-3   EM Anomaly   610111   7458248   0   -90   420.0
AR06-100   98-3   EM Anomaly   609989   7458633   0   -90   225.6
AR06-101   Red   EM Anomaly   618083   7451673   0   -90   141.7
AR06-102   Sunshine   West Extension   601176   7457834   30   -65   97.8
AR06-103   Red   EM Anomaly   618073   7451806   0   -90   209.7
AR06-104   Red   EM Anomaly   617926   7451693   0   -90   183.2
AR06-105   Red   EM Anomaly   618074   7451537   0   -90   136.6
AR06-106   Red   EM Anomaly   618083   7451677   310   -60   185.0
AR06-107   Sunshine   West Extension   601018   7458119   30   -60   294.4
AR06-108   Dead Creek   Downdip Extension   607618   7458406   0   -90   289.0
SC12-014   Sunshine   Sunshine Extension   601948   7457759   20   -57   537.8
SC12-015   Sunshine   Sunshine Extension   601860   7457637   20   -65   477.0
SC12-016   Sunshine   Sunshine Extension   601649   7457637   45   -77   386.2
SC12-017   Sunshine   Sunshine Extension   602063   7457701   20   -60   351.1
SC19-018   Sunshine   Sunshine Infill   601748   7457922   15   -52   296.3
SC19-019   Sunshine   Sunshine Infill   601748.2   7457923   0   -90   160.6
SC19-020   Sunshine   Sunshine Infill   601863.2   7457873   70   -48   230.4
SC19-021   Sunshine   Sunshine Infill   601862.2   7457872   70   -48   212.8
SC19-022   Sunshine   Sunshine Infill   601692.2   7457866   345   -80   203.6
SC19-023   Sunshine   Sunshine Infill   601691.6   7457868   345   -45   253.0
NEN22-001   98-9   Surface occurrence   615906   7456176   90   -55   223.72
NEN22-002   98-9   Surface occurrence   615907   7456178   90   -50   376.12
NEN22-003   98-9   Surface occurrence w/EM anomaly   615881   7456028   109   -45   451.1
NEN22-004   98-9   Surface occurrence w/EM anomaly   615880   7456029   140   -45   348.09
SNO21-001   Snow   Extension of Snow w/coincident EM Anomaly   584650   7462550   340   -80   529.74
SNO21-002   Snow   Extension of Snow w/coincident EM Anomaly   584650   7462551   11   -45   413
XAR21-001   NE Arctic   Extension of Arctic   613803   7453218   135   -45   448.67
XAR21-002   NE Arctic   Extension of Arctic   613805   7453217   135   -80   291.39
XAR21-003   SE Arctic   EM Anomaly   614750   7451885   340   -55   401.42
XAR21-004   SE Arctic   EM Anomaly   614894   7451990   32   -57   339.85
AR06-109   Dead Creek   Stratigraphy Hole   608187.7   7458314.5   0   -90   114.91

  
Arctic ProjectPage 91
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 7-7:2019-2021 Regional Prospect Drilling Significant Intercepts

 

Sunshine Drill Results
1.5% CuEq Cut-off
    Hole   From (m)   To (m)   Length_m   CuEq%   Cu_%   Zn_%   Pb_%   Au_g/t   Ag_g/t   Ba_pct  
Sunshine  SC19-018   139.52   144.76   5.24   3.93   2.08   3.13   0.63   0.154   41.643   -  
  SC19-018   238.72   245.06   6.34   2.38   1.63   1.45   0.09   0.070   13.380   -  
  SC19-018   247.86   255.06   7.20   1.69   0.72   2.18   0.21   0.030   6.640   -  
  SC19-018   260.46   261.60   1.14   1.71   1.53   0.35   0.01   0.027   3.670   -  
  SC19-019   57.00   66.14   9.14   3.95   3.02   1.42   0.27   0.137   24.651   -  
  SC19-019   68.85   72.15   3.30   2.82   1.68   1.77   0.47   0.121   27.573   -  
  SC19-019   98.81   102.54   3.73   5.51   4.74   0.97   0.13   0.153   28.957   -  
  SC19-019   122.36   125.40   3.04   1.63   0.75   1.40   0.35   0.077   21.020   -  
  SC19-019   138.17   146.05   7.88   5.23   2.23   5.62   1.10   0.180   46.947   -  
  SC19-020   176.37   179.74   3.37   6.54   4.15   3.42   0.48   0.258   74.354   -  
  SC19-020   188.55   190.10   1.55   3.77   1.43   1.65   0.40   0.061   23.300   -  
  SC19-020   204.15   209.09   4.94   5.77   4.47   3.42   0.01   0.002   0.117   -  
  SC19-020   219.30   221.98   2.68   3.87   3.70   0.44   0.00   0.002   0.396   -  
  SC19-021   146.62   156.28   9.66   6.10   3.93   3.00   0.77   0.216   73.104   -  
  SC19-022   114.12   115.47   1.35   5.90   2.89   4.87   1.41   0.172   68.300   -  
  SC19-022   130.40   134.61   4.21   1.85   0.34   2.28   1.07   0.066   30.634   -  
  SC19-022   143.73   159.01   15.28   3.08   1.35   2.91   0.78   0.158   32.584   -  
  SC19-023   163.50   168.51   5.01   2.09   0.87   1.92   0.66   0.101   24.687   -  
Northeast Arctic 2021   XAR21-001   421.00   422.52   1.52   0.20   0.07   0.04   0.26   0.014   1.000   -  
  XAR21-001   436.12   436.57   0.45   2.08   0.11   0.02   0.05   0.003   216.000   -  
  XAR21-002   235.65   236.11   0.46   2.14   0.55   1.04   2.77   0.025   23.800   -  
  XAR21-002   239.02   240.10   1.08   0.25   0.09   0.01   0.39   0.009   0.710   -  
  XAR21-003   358.75   359.34   0.59   0.48   0.29   0.10   0.35   0.003   3.710   -  
Snow   SNO21-001   137.87   138.21   0.34   5.85   0.35   5.47   7.04   0.321   99.600   0.16  
  SNO21-001   138.21   140.04   1.83   0.81   0.04   0.96   0.83   0.088   10.500   0.21  
  SNO21-001   137.87   140.04   2.17   1.60   0.09   1.67   1.80   0.125   24.460   0.20  
  SNO21-001   329.59   330.70   1.11   0.92   0.61   0.15   0.51   0.035   6.260   0.16  
  SNO21-002   167.16   167.48   0.32   7.49   0.23   7.25   9.13   0.391   139.000   0.08  
  SNO21-002   167.48   168.26   0.78   1.07   0.09   0.89   1.22   0.147   16.350   0.34  
  SNO21-002   168.26   168.62   0.36   1.22   0.02   1.35   1.66   0.072   10.200   0.29  
  SNO21-002   168.62   169.16   0.54   1.49   0.08   1.55   2.06   0.075   10.000   0.29  

 

*Cu-Eq calculation uses the Trilogy’s 2020 Arctic FS metal prices of $3.00 Cu, $1.10 Zn, $1.00 Pb, $18.00 Ag and $1,300 Au.

  
Arctic ProjectPage 92
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-6:Sunshine Prospect and Drill Hole Locations

 

 

Source: Trilogy Metals, 2020.

  
Arctic ProjectPage 93
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-7:Snow Project and Drill Hole Locations

 

 

Source: Ambler Metals, 2021.

  
Arctic ProjectPage 94
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-8:Northeast and Southeast Arctic and Drill Hole Locations

 

 

Source: Ambler Metals, 2021.

  
Arctic ProjectPage 95
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-9:98-9(NEN) Prospect and Drill Hole Locations

 

 

Source: Ambler Metals, 2021.

  
Arctic ProjectPage 96
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-10:East Dead Creek Prospect and Drill Hole Locations

 

 

Source: Ambler Metals, 2021.

  
Arctic ProjectPage 97
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-11:Plan Map of Drill Holes in the Vicinity of the Arctic Deposit

 

 

Source: Trilogy Metals, 2022.

 

7.2.2Drill Companies

 

Over the Arctic Project’s history, a relatively limited number of drill companies have been used by both Kennecott, NovaGold, Trilogy/NovaCopper and Ambler Metals at the Arctic deposit. During Kennecott’s work programs, Sprague and Henwood, a Pennsylvania-based drilling company was the principal contractor. Tonto Drilling provided services to Kennecott during Kennecott’s short return to the district in the late 1990s. NovaCopper and NovaGold used Boart Longyear as their only drill contractor. Trilogy has used Major Drilling and Tuug Drilling. Ambler Metals used Tuuq Drilling in 2021. Table 7-8 summarizes drill companies and core sizes used.

  
Arctic ProjectPage 98
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 7-8:Drill Contractors, Drill Holes, Meterage and Core Sizes by Drill Campaign at the Arctic Deposit

 

Year   Company   No. of
Drill Holes
  Metres   Core Size   Drill Contractor
1967   Bear Creek   7   752   BX   Sprague and Henwood
1968   Bear Creek   18   3,782   BX   Sprague and Henwood
1969   Bear Creek   3   712   BX   Sprague and Henwood
1970   Bear Creek   3   831   BX   Sprague and Henwood
1971   Bear Creek   2   257   BX   Sprague and Henwood
1972   Bear Creek   1   407   BX   Sprague and Henwood
1973   Bear Creek   2   557   BX   Sprague and Henwood
1974   Bear Creek   3   900   NX and BX   Sprague and Henwood
1975   Bear Creek   26   4,942   NX and BX   Sprague and Henwood
1976   Bear Creek   8   479   NXWL and BXWL   Sprague and Henwood
1977   Bear Creek   3   497   NXWL and BXWL   Sprague and Henwood
1979   Bear Creek   2   371   NXWL and BXWL   Sprague and Henwood
1981   Bear Creek   1   458   NXWL and BXWL   Sprague and Henwood
1982   Bear Creek   4   494   NXWL and BXWL   Sprague and Henwood
1983   Bear Creek   1   153   NXWL and BXWL   Sprague and Henwood
1984   Bear Creek   2   253   NXWL and BXWL   Sprague and Henwood
1986   Bear Creek   1   184   NXWL and BXWL   Sprague and Henwood
1998   Kennecott   6   1,523   HQ   Tonto
2004   NovaGold   11   2,996   NQ and HQ   Boart Longyear
2005   NovaGold   9   3,393   NQ and HQ   Boart Longyear
2007   NovaGold   4   2,606   NQ and HQ   Boart Longyear
2008   NovaGold   14   3,306   NQ and HQ   Boart Longyear
2011   NovaGold   5   1,193   NQ3 and HQ3   Boart Longyear
2015   NovaCopper   14   3,055   NQ and HQ   Boart Longyear
2016   NovaCopper   13   3,058   NQ and HQ   Boart Longyear
2017   Trilogy Metals   5   790   PQ   Major Drilling/Tuuq Drilling
2018   Trilogy Metals   24   906   PQ   Tuuq Drilling
2019   Trilogy Metals   9   2,433   PQ and HQ3   Tuuq Drilling
2021   Ambler Metals   18   4,131   PQ and HQ3   Tuuq Drilling
2022   Ambler Metals   47   8,376   HQ3   Major Drilling

  
Arctic ProjectPage 99
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Sprague and Henwood used company-manufactured drill rigs during their work programs on the Project. Many of their rigs remain at the Bornite deposit and constitute a historical inventory of 1950s and 1960s exploration artifacts. The 2004 to 2011 NovaGold drill programs used a single skid-mounted LF-70 core rig, drilling HQ (63.5 mm core diameter) or NQ (47.6 mm) core. The drill was transported by skid to the various drill pads using a D-8 bulldozer located on site. The D-8 was also used in road and site preparation. Fuel, supplies, and personnel were transported by helicopter. The 2015 and 2016 NovaCopper drill programs used two helicopter-portable LF-70 core rigs, drilling HQ or NQ core. The drill was transported by helicopter to various drill pads. The 2017 Trilogy metallurgical drill program used a helicopter-portable LF-90 core rig, drilling PQ (85 mm) core to be used in future metallurgical testwork. The drill was transported by helicopter to various drill pads. In 2018, Trilogy used a helicopter-portable Duralite 1400N, drilling PQ core to be used for geotechnical studies in plant site facilities. Drilling during 2019 consisted of two helicopter-portable Duralite 1400N core rigs, drilling PQ and HQ core used for geotechnical and hydrogeological studies to support Trilogy’s 2020 FS. The 2021 Ambler Metals program was completed by Tuuq Drilling utilizing three helicopter-portable Duralite 1400N rigs for geotechnical, hydrogeological, resource conversion drilling, and to collect mineralized material for metallurgical testwork. The 2022 Ambler Metals program was completed by Major Drilling utilizing 3 helicopter-portable (2 Discovery EF-75 and 1 Longyear LF-90) rigs for geotechnical, hydrogeological, resource conversion drilling, and to collect mineralized material for metallurgical testwork.

 

7.2.3Drill Core Procedures

 

7.2.3.1BCMC/Kennecott

 

There is only partial knowledge of specific drill core handling procedures used by Kennecott during their drill programs at the Arctic deposit. The drill data collected during the Kennecott drilling programs (1965 to 1998) were logged on paper drill logs, copies of which are stored in the Kennecott office in Salt Lake City, Utah. Electronic scanned copies of the paper logs, in PDF format, are held by Trilogy. Drill core was hydraulically split or cut with half core submitted to various assay laboratories and the remainder stored in Kennecott’s core storage facility at the Bornite Camp. Between 1965 and 1986 analyses were conducted primarily by Union Assay Office Inc. of Salt Lake City, Utah. At least six other labs were also used during that time period, but mostly as check labs or for special analytical work. ALS Minerals was used for analyses submitted by Kennecott in 1998.

 

7.2.3.2NovaGold/Trilogy (formerly, NovaCopper)/Ambler Metals

 

Throughout Trilogy’s work programs, the following standardized core handling procedures have been implemented. Core is slung by helicopter to either the Dahl Creek (2004 to 2008) or Bornite (2011 to 2019) Camp core-logging facilities. Upon receiving a basket of core, geologists and geotechnicians first mark the location of each drilling block on the core box, and then convert footages on the blocks into metres. All further data capture is then based on metric measurements. Geotechnicians or geologists measure the intervals (or “from/to”) for each box of core using the drilling blocks and written measurements on the boxes.

 

Geotechnicians fill out metal tags with the hole ID, box number and “from/to”, and staple them to each core box. Geotechnicians then measure the core to calculate percent recovery and rock quality designation (RQD).

  
Arctic ProjectPage 100
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Geologists then mark sample intervals to capture each lithology or other geologically appropriate intervals. Geologists staple sample tags on the core boxes at the start of each sample interval and mark the core itself with a wax pencil to designate sample intervals. Sample intervals used are well within the width of the average mineralized zones in the resource area. This sampling approach is considered appropriate for the style of mineralization and alteration.

 

Core is logged with lithology and visual alteration features captured on observed interval breaks. Geological and geotechnical parameters are recorded based on defined sample intervals and/or drill run intervals (defined by the placement of a wooden block at the end of a core run). Logged parameters are reviewed annually and slight modifications have been made between campaigns, but generally include rock type, mineral abundance, major structures, SG, point load testing, recovery and rock quality designation measurements, and magnetic susceptibility. Mineralization data, including total sulphide (recorded as percent), sulphide type (recorded as an absolute amount), gangue and vein mineralogy are collected for each sample interval with an average interval of approximately 2 m. Structural data are collected as point data. Geotechnical data (core recovery, RQD) are collected over drill run intervals.

 

Drill hole data are recorded in a digital format and, after a QA/QC review, are forwarded to the Database Manager who then imports them into the master database.

 

After logging, the core is digitally photographed and cut in half using diamond core saws. Specific attention to core orientation is maintained during core sawing to ensure the most representative sampling. Not all core is oriented; however, core that has been oriented is identified to samplers by a line drawn down the core stick. If core was not competent, it was split by using a spoon to transfer half of the core into the sample bag.

 

One-half of the core is returned to the core box for storage on site and the other half is bagged and labelled for sample processing and analysis. Select specific gravity measurements are also taken (refer to 8.1.3).

 

7.2.4Geotechnical and Hydrogeological Drilling

 

Geotechnical and hydrogeological drilling is summarized in Table 7-9 and Table 7-10. The collar locations of the geotechnical drilling and hydrogeological drilling are presented Figure 7-12 and Figure 7-13. The number of holes reported for each year are the holes that were staffed by a geotechnician and/or hydrogeologist at the rig and primary purpose was to gather geotechnical and hydrogeological data. Geotechnical data (besides PLT’s) and hydrogeological installs may have been completed on holes from other programs, such as in-fill or metallurgical holes. Triple tube core barrels were used for geotechnical drill holes in 2015, 2016, and 2019. The geotechnical and hydrogeological field and laboratory testing approach and the results are discussed in Section 13.9 and Section 17.1.5.

 

Table 7-9:Summary of Geotechnical Drilling

 

    2011   2015   2016   2017   2018   2019   2021   2022
Number of Holes   5   2   3   11   24   4   8   5
Oriented core   X   X   X           X   X   X
Water level monitoring   X   X   X   X   X   X   X   X
Falling head packer tests   X                            
Point load tests   X   X   X           X   X   X
Uniaxial compressive strength       X   X           X        
Direct shear testing       X   X           X   X   X
Modulus testing       X   X           X        
Triaxial testing       X   X           X   X   X
Acoustic Televiewer           X                    
Falling Head, Single or Straddle packer tests   X       X                    
Airlift pump test           X                    
Hydraulic conductivity testing (slug testing)               X                
Cohesive and residual shear strength tests on soils               X   X            
Compressive strength test on core and rock               X   X            
Extended duration injection tests                       X        

  
Arctic ProjectPage 101
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 7-10:Summary of Geotechnical Drilling by Year and Purposes

 

Year Purpose
2011 Obtain geotechnical data in areas of the deposit that may host underground infrastructure or could pose issues with underground mining.
2015 Collect geotechnical and hydrogeological data to better understand the wall rock characteristics and hydrogeology within the open pit area.
2016 Complete the 3 drill holes that were deferred/not completed from the 2015 program.
2017 Collect geotechnical and hydrogeological data for tailings management and waste rock facilities within the entire Sub Arctic Creek valley.
2018 Collect geotechnical and hydrogeological data for WRF, TMF, and surface infrastructure in the Upper Sub Arctic Creek Valley.
2019 Provide additional geotechnical and hydrogeological data for pit design for the 2020 FS
2021 Define talc horizons on east side of pit for pit design.
2022 Define extent of lower talc horizons on northeast side of pit for pit design.

  
Arctic ProjectPage 102
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-12:Locations of Geotechnical Drilling

 

 

 

Source: SRK, 2022

  
Arctic ProjectPage 103
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-13:Locations of Hydrogeological Drilling

 

 

Source: SRK, 2022

 

7.2.5Collar Surveys

 

7.2.5.1Kennecott

 

Kennecott provided NovaGold with collar coordinates for all historical holes in UTM coordinates using the NAD27 datum. NovaGold re-surveyed collars of selected historical holes in 2004 and again in 2008. The re-surveys showed little variation compared to the historical surveys.

 

7.2.5.2NovaGold/Trilogy (formerly, NovaCopper)/Ambler Metals

 

Collar location coordinates were determined for the 2004 to 2016 NovaGold/Trilogy drill campaigns with two Ashtech ProMark 2 GPS units using the Riley Vertical Angle Benchmark (VABM; 611120.442E, 7453467.486N) as the base station for all surveys. Raw GPS data were processed with Ashtech Solutions 2.60 software. All surveyed data were collected in the NAD27 datum and later converted to NAD83.

 

A 2010 survey by a Registered Land Surveyor from WHPa observed differences between the 2010 and historical coordinates used for the Riley VABM, which were of the same magnitude (0.5 m east, 0.1 m north and 1.0 m down) as other Arctic drill collars that were re-surveyed for the third time. A correction was applied to all Arctic drill holes based upon the newly established coordinates for the Riley VABM, together with converting from NAD27 to NAD83 datums. All post 2010 surveys are completed in NAD83.

  
Arctic ProjectPage 104
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

During Tetra Tech’s 2013 site visit, nine drill collars were located using a Garmin™ Etrex 20 GPS unit. The difference between reported and measured positions ranged between 3.4 and 7.8 m with an average discrepancy of 4.8 m. These differences are within the tolerances expected for GPS verification.

 

A Registered Land Surveyor, Eric Cousino of Windy Creek Surveys, completed collar coordinate survey locations of the 2019 drilling in August 2019. The Horizontal Datum used on this project for point position determinations was NAD_83(CORS96) (EPOCH 2003), and the Vertical Datum is NAVD88 computed using Geiod09. Data were output into NAD83 Zone 4N (meters) using JAVAD Justin post-processing software.

 

The 2021 collars were surveyed by Layne Lewis, the Ambler Metals drill coordinator, using a Leica GS18 differential GPS system (cm-scale accuracy). Kuna Engineering surveyed the 2022 collar locations using a Trimble R12 GPS/GNSS receiver.

 

7.2.6Downhole Surveys

 

BCMC did not perform downhole surveys prior to 1971 (drill hole AR-32). In 1971, BCMC began to survey selected (mineralized) drill holes using a Sperry-Sun downhole survey camera usually at 30.5 m (100 ft) intervals. BCMC was able to re-enter and survey a few of the older drill holes. BCMC, and later Kennecott, applied a single azimuth (49°) and uniform dip deviation every 15.24 m (50 ft) that flattens with depth to all holes collared vertically that were not surveyed.

 

Downhole surveys from 2004 to 2017 were collected using either a Reflex EZ-shot camera or a Ranger single-shot tool with individual survey readings collected at the drill rig on approximately 30 to 60 m intervals. During the 2019 drill program, downhole surveys were collected using a continuous north seeking gyroscope with readings collected at the drill rig on roughly 30m intervals. Downhole surveys in 2021 were taken every 100 feet (30.5 meters) with a Reflex EZ-Trac multi-shot instrument. The magnetic declination correction from 2004 to 2021 were calculated using the NOAA Magnetic Field Calculator website and the longitude and latitude of the Arctic deposit.

 

The downhole survey data show a pronounced deviation of the drill holes toward an orientation more normal to the foliation.

 

7.2.7Recovery

 

7.2.7.1Kennecott

 

Incomplete Kennecott data exist with regards to overall core recovery but based on 917 intervals of 3.05 m or less in the historical database, the average recovery was 92%. Kennecott RQD measurements in the 1998 program averaged 87.0%. There has been no systematic evaluation of recovery by rock type.

 

7.2.7.2NovaGold/Trilogy (formerly, NovaCopper)/Ambler Metals

 

Core recovery during NovaGold/NovaCopper/Trilogy and Ambler Metals drill programs were good to excellent, resulting in quality samples with little to no bias. There are no other known drilling and/or recovery factors that could materially impact accuracy of the samples during this period.

  
Arctic ProjectPage 105
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 7-11 shows recoveries and RQD for each of the NovaGold/NovaCopper/Trilogy and Ambler Metals campaigns exclusive of the geotechnical drill holes in 2011 and 2021.

 

Table 7-11:Recovery and RQD 2004 to 2008 Arctic Drill Campaigns

 

Year   Metres   Recovery (%)   RQD (%)  
2004   2,996   98.0   73.4  
2005   3,030   96.0   74.4  
2007   2,606   95.7   73.1  
2008   3,306   98.0   80.1  
2011   1,193   96.0   68.8  
2015   3,055   91.3   69.0  
2016   3,058   91.5   69.7  
2017   790   95.5   75.0  
2019   2,433   96.3   77.1  
2021   2,282   95.1   70.3  

 

7.2.8Drill Intercepts

 

All drill holes at the Arctic deposit are collared on surface and are generally vertically oriented, or steeply inclined in a northeast direction. The majority of drill holes are spaced at 75 m to 100 m intervals, but there are instances where drill holes are located within 10 m of one another. Drill holes typically intersect the generally shallow-dipping mineralized horizon at approximately right angles.

 

Drilling at the Arctic deposit covers an area measuring roughly 1,000 m east-west by 1,000 m north south with holes that approach 750 m below surface. Significant results of the distribution of copper in drilling is shown in plan and in vertical cross-sectional views in Figure 7-14 to Figure 7-16. Significant results of the distribution of zinc in drilling is shown in plan and in vertical cross-sectional views in Figure 7-17 to Figure 7-19. These results represent a summary of the QPs interpretation of the exploration information.

  
Arctic ProjectPage 106
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-14:Drill Plan of Arctic Copper Results

 

 

Source: Wood, 2022

  
Arctic ProjectPage 107
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-15:Cross-Section 1 of Arctic Copper Results Looking South

 

 

Source: Wood, 2022

 

Figure 7-16:Cross-Section 2 of Arctic Copper Results Looking South

 

 

Source: Wood, 2022

  
Arctic ProjectPage 108
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-17:Drill Plan of Arctic Zinc Results

 

 

Source: Wood, 2022

  
Arctic ProjectPage 109
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 7-18:Cross-Section 1 of Arctic Zinc Results Looking South

 

 

Source: Wood, 2022

 

Figure 7-19:Cross-Section 2 of Arctic Zinc Results Looking South

 

 

Source: Wood, 2022 

  
Arctic ProjectPage 110
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

8SAMPLE PREPARATION, ANANLYSES AND SECURITY

 

8.1Sample Preparation

 

8.1.1Core

 

The data for the Arctic deposit were generated over three primary drilling campaigns: 1966 to 1986 when BCMC, a subsidiary of Kennecott was the primary operator, 1998 when Kennecott resumed work after a long hiatus, and 2004 to present under NovaGold. Trilogy (formerly, NovaCopper), and Ambler Metals.

 

8.1.1.1Kennecott and BCMC

 

Sampling of drill core prior to 1998 focused primarily on the mineralized zones; numerous intervals of weak to moderate mineralization were not sampled during this period. During the 1998 campaign, Kennecott did sample some broad zones of alteration and weak mineralization, but much of the unaltered and unmineralized drill core was left unsampled. Little documentation on historic sampling procedures is available.

 

8.1.1.2NovaGold/Trilogy (formerly, NovaCopper)

 

Between 2004 and 2005, NovaGold conducted a systematic drill core re-logging and re-sampling campaign of Kennecott and BCMC era drill holes AR-09 to AR-74. NovaGold either took 1 to 2 m samples every 10 m or sampled entire lengths of previously unsampled core within a minimum of 1 m and a maximum or 3 m intervals. The objectives of the sampling were to generate a full (ICP) geochemistry dataset for the Arctic deposit and ensure continuous sampling throughout the deposit.

 

From 2004 to 2019, sample intervals are determined by the geological relationships observed in the core and limited to a 2.5 m maximum length and 1 m minimum length. Sample intervals terminate at lithological and mineralization boundaries. Sampling is generally continuous from the top to the bottom of the drill hole unless otherwise directed by the Exploration Manager. Occasionally, if warranted by the need for better resolution of geology or mineralization, smaller sample intervals may be employed. When the hole is in unmineralized rock, the sample length is generally 2.5 m, whereas in mineralized units, the sample lengths are shortened to 1 to 2 m.

 

After logging, the core was cut in half using diamond core saws. If core was not competent, it was split by using a spoon to transfer half of the core into the sample bag. One-half of the core was returned to the core box for storage on site and the other half was bagged, labelled, and sent to ALS Minerals Laboratories in Vancouver for analysis, via the (ALS preparation facility in Fairbanks Alaska) and the other half was archived in the core storage facility at the Bornite Camp facilities or at the Ambler Metals warehouse in Fairbanks. For the 2021 metallurgical holes, ¼ core was sampled for analysis at ALS, ¼ retained, and ½ sent for metallurgical testing.

 

Standard and Blank control samples were inserted at site into the shipments at the approximate rate of one standard reference material (standard), one blank per 17 core samples. At the Exploration Manager direction, ALS also prepared one coarse duplicate per 17 core samples. A sample tag for these duplicates was inserted into an empty sample bag at site.

  
Arctic ProjectPage 111
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

8.1.2Acid-Base Accounting Sampling

 

In 2010, SRK collected 148 samples from drill core based on their position relative to the massive and semi-massive sulphide mineralization (SRK 2011). Samples were targeted within, immediately adjacent to, adjacent to, and between lenses of mineralization; the sampling program focused on characterization for a potential underground development scenario. Samples were shipped to SGS Canada Inc., Burnaby, BC, for sample preparation and analysis. Samples were analysed for acid base accounting (ABA) and metals. ABA tests were conducted using the Sobek method with sulphur speciation and total inorganic carbon (TIC) analysis. Metal concentrations were determined using aqua regia digestion followed by ICP-MS analysis. In addition, barium and fluorine were analysed by X-ray fluorescence (XRF) following a lithium metaborate fusion.

 

In 2015, Trilogy retained SRK to provide metal leaching (ML) and ARD characterization services for the Arctic deposit. Activities focused on three objectives: 1) construction of on-site barrel tests and parallel humidity cells, 2) expansion of the ABA database to support future evaluation for ARD potential management for open pit mining, and 3) evaluation of the use of proxies for ABA parameters in the exploration database with the purpose of being able to use the exploration database for block modelling of ML/ARD potential, if needed. Barrel test samples were collected during July and August 2015 and eight on-site barrel tests (including two QC tests) were constructed and initiated in late August 2015. Following the set-up of the on-site barrel tests, representative composite rock samples were shipped to Maxxam Analytics of Burnaby, British Columbia and parallel humidity cells were initiated in late October 2015. Trilogy and SRK selected 321 samples to be analysed for a conventional static ABA package with a trace element scan using the same method as the exploration database (four-acid digestion). Samples were analysed by Global ARD Testing Services of Burnaby, British Columbia.

 

In 2016, Trilogy evaluated the distribution of the existing samples to select additional samples in preparation for block modelling of ML/ARD potential. A drill program was designed, and infill samples were collected from holes drilled in 2015 and 2016. This program was completed with 1004 samples analysed for a conventional static ABA package with a trace element scan using the same method as the exploration database. Samples were analysed by Global ARD Testing Services of Burnaby, British Columbia. The resulting data were combined with the previous datasets.

 

In 2018 and 2021, the kinetic test program was expanded to further characterize ML/ARD potential. Samples were selected using the exploration geochemistry database, to target drill core with geochemical characteristics representing the range of compositions present in the database for key parameters such as sulphur and selenium. Kinetic testing was initiated in 2019 and 2021 at Bureau Veritas (previously Maxxam Analytics) of Burnaby, BC, and the kinetic samples were also analysed by static methods at Bureau Veritas for ABA and metals by the same methods as the 2015 and 2016 programs, in addition to metal concentrations determined using aqua regia digestion followed by ICP-MS analysis.

 

As described above, several laboratories were used for acid base accounting studies and associated kinetic testwork as summarized in Table 8-1. Accreditations, where known, are listed below. All the labs are independent of NovaGold, NovaCopper, Trilogy (formerly, NovaCopper), and Ambler Metals.

  
Arctic ProjectPage 112
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 8-1:Analytical Laboratories used for Acid Base Accounting and Kinetic Studies for the Arctic Project

 

Laboratory
Name
Laboratory
Location
Years
Used
Accreditation Comment
SGS Canada Inc. Burnaby, BC 2010 ISO 90001 and ISO/IEC 17025. ABA samples
Global ARD Testing Services Burnaby, BC 2015, 2016 ISO/IEC 17025 ABA samples
ARS Aleut Analytical Anchorage and Fairbanks, AK 2015, 2016, 2017, 2018 Accreditations are not known. Barrel test leachate samples
Bureau Veritas (previously Maxxam Analytics) Burnaby, BC 2015, 2016, 2017, 2018, 2019, 2020, 2021, 2022. ISO/IEC 17025 ABA samples (2015 and 2019), HCTs (2015 to 2022), and barrel test leachate samples (2019-2022)

 

8.1.3Density Determinations

 

Representative (SG) determinations conducted before 1998 for the Arctic deposit are lacking. Little information regarding sample size, sample distribution and SG analytical methodology are recorded for determinations during this period.

 

In 1998, Kennecott collected 38 core samples from that year’s drill core, of which 22 were from mineralized zones and 16 from non-mineralized lithologies. Mineralized samples were defined as MS (more than 50% total sulphides), SMS (less than 50% total sulphides) or lithology samples (non-mineralized country rock containing up to 10% sulphides). SG determinations were conducted by ALS Minerals and Golder and Associates and were based on short (6 to 12 cm) whole core samples. SG was determined based on the water displacement method.

 

In 1999, Kennecott collected 231 samples from pre-1998 drill core for SG analysis. The samples were from NQ- and BQ-sized core and averaged 7.27 cm in length. The samples were shipped to Anchorage but were not forwarded to a laboratory.

 

In 2004, NovaGold forwarded the 231 samples from the pre-1998 drill campaigns stored in Kennecott’s Anchorage warehouse, as well as 33 new samples from the 2004 drill program to ALS Minerals for SG determination.

 

Additionally, in 2004 NovaGold collected 127 usable field SG measurements. Samples were collected from HQ-sized core and averaged 9.05 cm in length. An Ohaus Triple Beam Balance was used to determine a weight-in-air value for dried core, followed by a weight-in-water value. The wet-value was determined by suspending the sample by a wire into a water-filled bucket. The SG value was then calculated using the following formula.

 

 

In 2011, NovaGold geologists stopped collecting short interval “point data” (as described above) within the mineralized zone, and instead collected “full-sample-width” determinations from existing 2008 split core and all of the sampled 2011 whole core. The samples averaged 1.69 m in length. Samples were collected continuously within mineralized zones and within a 2 to 3 m buffer adjacent to mineralized zones. A total of 193 measurements were collected. In 2011, 266 sample pulps were also submitted to ALS Minerals for SG determination by pycnometer analysis.

 

Between 2015 and 2019, Trilogy geologists collected SG data consistent with the 2011 full sample width water immersion campaign. A total of 2,406 specific gravity measurements were collected, with SG values ranging from 2.01 to 4.96. The samples averaged 1.49 m in length. Samples were collected continuously within mineralized zones and within a 2 to 3 m buffer adjacent to mineralized zones.

  
Arctic ProjectPage 113
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

In 2021 Ambler Metals collected 830 SG measurements from half-core intervals ranging from 0.08 to 2.19 m with SG values ranging from 2.01 to 2.88. In 2022, Ambler Metals collected 2,545 SG measurements from half-core intervals ranging from 0.14 m to 2.81 m with SG values ranging from 2.79 to 5.06.

 

8.1.4Sample Security

 

Security measures taken during historical Kennecott and BCMC programs are unknown to NovaGold, Trilogy, or Ambler Metals. Ambler Metals is not aware of any reason to suspect that any of these samples have been tampered with.

 

The 2004 to 2019 samples were always either in the custody of NovaGold personnel or at the assay laboratories, and the chain of custody of the samples is well documented.

 

The site has restricted access with only means of access via charter flight. Core is stored in a core storage yard and warehouse with the perimeter surrounded by a chain-link fence and secure locked gates. Shipment of core samples from site occurred on a drill hole by drill hole basis. Rice bags, containing two to four poly-bagged core samples each, were marked and labelled with the ALS Minerals address, project and hole number, bag number, and sample numbers enclosed. Rice bags were secured with a pre-numbered plastic security tie and a twist wire tie and then assembled into standard fish totes for transport by chartered flights on a commercial airline to Fairbanks, where they were met by a contracted expeditor for delivery directly to the ALS Minerals preparation facility in Fairbanks.

 

8.1.5Assay Laboratories

 

At least six laboratories were used during the Kennecott/BCMC time period, but mostly as check laboratories or for special analytical work. Accreditations are not known. The laboratories were independent of Kennecott/BCMC. Bondar Clegg, now ALS Minerals, was used for analyses conducted by Kennecott. During the BCMC work, analyses were conducted primarily by Union Assay Office Inc. of Salt Lake City, Utah.

 

Since 2004 NovaCopper, NovaGold, Trilogy metals, and Ambler Metals have used ALS Minerals (Fairbanks Alaska for sample preparation and Vancouver British Columbia as the primary laboratory. ALS Minerals is accredited for a number of specific test procedures including fire assay of gold by AA, ICP, or gravimetric finish, multi-element ICP and AA assays for silver, copper, lead and zinc. ALS Minerals is independent of NovaGold, NovaCopper, Trilogy, and Ambler Metals.

 

The laboratories used during the various exploration, infill, and step-out drill analytical programs completed on the Arctic Project are summarized in Table 8-2.

  
Arctic ProjectPage 114
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 8-2:Analytical Laboratories Used by Operators of the Arctic Project

 

Laboratory
Name
Laboratory
Location
Years
Used
Accreditation Comment
Union Assay
Office, Inc.
Salt Lake City, Utah 1968 Accreditations are not known. Primary Assay laboratory
Rocky Mountain
Geochemical Corp.
South Midvale, Utah 1973 Accreditations are not known. Primary and secondary assays
Resource Associates
of Alaska, Inc.
College, Alaska 1973, 1974 Accreditations are not known. Primary and secondary assays
Georesearch
Laboratories, Inc.
Salt Lake City, Utah 1975, 1976 Accreditations are not known. Primary and secondary assays
Bondar-Clegg &
Company Ltd.
North Vancouver, BC 1981, 1982 Accreditations are not known. Primary and secondary assays
Acme Analytical Laboratories Ltd. (AcmeLabs) Vancouver, BC 1998, 2011,

Accreditations are not known. 2012 and 2013 secondary check sample lab
SGS Canada Inc. Burnaby, BC 2010 ISO 90001 and ISO/IEC 17025. 2015 to 2019 secondary check lab
ALS Analytical Lab Fairbanks, Alaska (prep) and Vancouver, BC (analytical)

1998, 2004,
2005, 2006, 2007, 2008, 2011,
2012, 2013 2015, 2016, 2017, 2018, 2019

 

In 2004, ALS Minerals held ISO 9002 accreditations but updated to ISO 9001 accreditations in late 2004. ISO/International Electrotechnical Commission (IEC) 17025 accreditation was obtained in 2005. 2004 - 2019 primary assay laboratory

 

8.1.6Sample Preparation and Analytical Methods

 

Samples from the NovaGold/Trilogy/Ambler Metals programs were logged into a tracking system on arrival at ALS Minerals and weighed. Samples were crushed to 70% passing 2 mm, dried, and a 250 g split pulverized to greater than 85% passing 75 μm.

 

Samples were submitted for multielement analysis of a 0.25 gram sample by ICP MS following a 4-acid digestion, and for gold analysis of a 30 gram sample by FA with an AA finish. Over limit ICP-MS Cu, Pb, and Zn samples were resubmitted for analysis of a 0.4 gram sample by ICP-Atomic Emission Spectroscopy (AES) or AA following a 4 acid digestion. The overlimit value for Cu, Pb, and Zn is 10,000 ppm. Over limit gold results were resubmitted for analysis of a 30 gram sample by FA with a Gravimetric finish. The overlimit value for Au is 10 ppm. The Lower detection limits for Cu, Pb, and Zn by ICP-MS are 0.2 ppm, 0.5 ppm, and 2 ppm respectively. The lower detection limit for Au by FAAA is 0.05 ppm.

  
Arctic ProjectPage 115
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

8.2Quality Assurance/Quality Control

 

8.2.1Database Verification

 

In 1995, Kennecott entered the drill assay data information from the geologic core logs, and the downhole collar survey data into an electronic format. In 2006, NovaGold geologists verified the geologic data from the original paper logs against the Kennecott electronic format, and then merged the data into a Microsoft SQL database.

 

Between December 11th and January 9th, 2013, NovaCopper and GeoSpark Consulting completed a 100% verification of the collar survey, downhole survey, and sample interval data for the Arctic resource area. 20% of the pre-2004 assay data and ~26% of the 2004 to 2008 assay data were also verified at this time. Trilogy also retained GeoSpark to generate QA/QC reports for the NovaGold era 2004 to 2008 and NovaCopper/Trilogy era 2011, 2015, 2016, 2017, and 2019 drill campaigns. All data for the Arctic resource area is stored in the GeoSpark Core Database System created and managed by GeoSpark Consulting.

 

8.2.2NovaGold QA/QC Review of Historical Analytical Results

 

The current assay database contains results for 11,429 sample intervals including 3,077 (27%) historical hole sample intervals. Between 2004 and 2005 NovaGold completed a resampling program of historical drill holes. As a result, 85% of the assay intervals now have recent assay results from ALS Minerals. The re-assay program includes 289 re-assays of previously assayed historical hole sample intervals, representing approximately 17% of the original historical sampling program. In the database reviewed by Wood, the original Cu, Pb, and Zn values from the KCC/Utah laboratory results are given priority over ALS laboratory results for the 289 re-assay intervals. The database reviewed does not distinguish between previously sampled and newly sampled historical intervals or original and new assay values. Wood used the presence and absence of multielement analysis values to establish resampling and re-assay frequency. To determine assay priority used, Wood compared reported values to original logs.

 

Reduced to Major Axis (RMA) charts prepared by Wood (Figure 8-1 and Figure 8-2) which evaluates the paired original historical and re-assay values, indicates there is a 10% high bias in the historical Cu values after exclusion of 15 outliers and a 13% low bias in the historical Pb values after exclusion of 17 outliers. An inflection in the trend of the paired Cu values starting at 1% Cu may indicate the bias is related to an upper detection limit for the original assay procedure and or a change to an overlimit method. The Pb RMA chart shows a cluster of paired data with high biased original results. The low bias indicated by the RMA slope does not change after exclusion of these pairs.

  
Arctic ProjectPage 116
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-1:Historical Cu Re-Assay RMA Chart

 

 

Source: Wood, 2022

  
Arctic ProjectPage 117
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-2:Historical Pb Re-Assay RMA Chart

 

 

Source: Wood, 2022

 

The spatial distribution of the historical samples that remain as primary samples in the database is shown in Figure 8-3. These remaining historical assays are evenly distributed through the deposit area and are surrounded by assay intervals analysed since 2004. Spatial availability of QA/QC data is shown in Figure 8-4.

  
Arctic ProjectPage 118
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-3:          Distribution of Historical Samples with Original Laboratory Results (Original Historic Assay Intervals are Indicated in Magenta, Recent Assays are Indicated in Green)

 

 

Source: Wood, 2022.

  
Arctic ProjectPage 119
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-4:Spatial Availability of QA/QC Data

 

 

Source: Trilogy Metals, 2019.

 

8.2.3NovaGold/Trilogy (2004 to 2019) QA/QC Results Review

 

All core and pulp reject samples submitted to the ALS Minerals laboratory since 2004 were accompanied by standard, blank and duplicate control samples. Secondary laboratory check samples were analysed at Acme in Vancouver or SGS Burnaby. The secondary laboratory check samples were selected to represent the data population using a random selection of 5% of the samples within percentile range groups.

 

GeoSpark has prepared several reports summarizing the control sample results received between 2004 and 2019. The reports include CRM and blank control charts, pulp duplicate absolute difference precision charts and check sample scatter and absolute difference charts. The standard and blank control sample results were defined as failing when results were in excess of plus and minus three standard deviations from the expected mean for the standard. No threshold for check samples was provided in the reports.

 

  
Arctic ProjectPage 120
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Failing blanks or standards were re-analysed along with the adjacent samples to address potential accuracy deficiencies and to maintain quality assays in the database. Initial review of the assay certificates as they were reported identified a few instances of failing standards; for any fails the adjacent samples were also rerun.

 

The following QA/QC sections are based on a review of those reports.

 

8.2.3.12004

 

The 2004 exploration program included drilling and sampling of 11 drill holes amounting to 989 primary samples assayed within 61 assay certificates reported by ALS Minerals. The review of pulp duplicates, blanks and standards, and check control samples results showed acceptable levels of precision, accuracy, and between-laboratory bias.

 

8.2.3.22005

 

The 2005 exploration program included drilling and sampling of nine drill holes, AR05-0089 through AR05-0097, amounting to 1,228 primary samples assayed within 36 assay certificates reported by ALS Minerals.

 

The review of pulp duplicates, blanks and standards, and check samples during allowed for inference of a reasonable level of precision, good accuracy, and insignificant levels of bias within the primary sample results reported by ALS Minerals related to the 2005 data.

 

This detailed QA/QC review on the analytical results reported during 2005 allowed for overall confidence in the analytical result quality.

 

8.2.3.32006

 

The 2006 exploration program included drilling and sampling of 12 drill holes, AR06-98 through AR06-109, amounting to 1,175 primary samples analysed at ALS Minerals.

 

The review of pulp duplicates, blanks and standards, and check samples for the 2006 program allowed for inference of a good level of precision, good accuracy, and insignificant levels of bias within the primary 2006 sample results reported by ALS Minerals.

 

8.2.3.42007

 

The 2007 exploration program included drilling and sampling related to four drill holes, AR07-110 through AR07-113, amounting to 950 primary samples analysed at ALS Minerals.

 

The review of pulp duplicates, blanks and standards, and check samples for the 2007 program allowed for inference of a good level of precision, good accuracy, and insignificant levels of bias within the primary sample results reported by ALS Minerals.

 

8.2.3.52008

 

The 2008 exploration program included drilling and sampling related to 14 drill holes, AR08-0114 through AR08-0126 and drill hole AR08-0117w, amounting to 1,406 primary samples assayed within 44 assay certificates reported by ALS Minerals.

  
Arctic ProjectPage 121
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The review of pulp duplicates, blanks and standards, and check samples for the 2008 program allowed for inference of a reasonable level of precision, good accuracy, and insignificant levels of bias within the primary sample results reported by ALS Minerals.

 

8.2.3.62011 (analysed in 2013)

 

Laboratory assay certificates FA13021131, FA13021132, FA13021133, FA13021134, and FA13021135 included results for six pulp duplicate pairs, six blank instances, and three standards. There were analysed by Geospark.

 

The duplicates for gold, silver, copper, lead, and zinc were found to correlate well with the primary sample results and it can be inferred that the primary results are of good precision.

 

Each of the blanks was analytical values within the control limits for the material. There are no issues with sample contamination and instrumentation difficulties. In addition, the accuracy can be inferred to be acceptable.

 

Each standard returned within the acceptable range for gold, silver, copper, lead, and zinc values; it is inferred that there is strong accuracy within the reported primary sample assay results.

 

A detailed review of secondary laboratory check sample results reported by ALS Minerals for the 2011 drill holes assayed in 2013 showed that the gold, silver, copper, lead, and zinc results indicated no material bias.

 

8.2.3.72015

 

The 2015 exploration program included drilling and sampling related to 14 drill holes, amounting to 1,0971 primary samples primary samples analysed at ALS Minerals. The review of pulp duplicates, blanks and standards, and check control samples results showed acceptable levels of precision, accuracy, and between-laboratory bias.

 

8.2.3.82016

 

The 2016 exploration program included drilling and sampling related to 13 drill holes, amounting to 1,181 primary samples primary samples analysed at ALS Minerals. The review of pulp duplicates, blanks and standards, and check control samples results showed acceptable levels of precision, accuracy, and between-laboratory bias.

 

8.2.3.92017

 

The 2017 exploration program included drilling and sampling related to 5 drill holes, amounting to 313 primary samples primary samples analysed at ALS Minerals. The review of pulp duplicates, blanks and standards, and check control samples results showed acceptable levels of precision, accuracy, and between-laboratory bias.

 

8.2.3.102019

 

The 2017 exploration program included drilling and sampling related to 9 drill holes, amounting to 586 primary samples primary samples analysed at ALS Minerals. The review of pulp duplicates, blanks and standards, and check control samples results showed acceptable levels of precision, accuracy, and between-laboratory bias.

  
Arctic ProjectPage 122
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

8.2.4Density Determination QA/QC

 

8.2.4.1Laboratory vs. Fields Determinations

 

Paired laboratory and field determinations from for mineralized zone SG measurements from 1998 and the 2004 program show very low variation.

 

In 2010, NovaGold measured 50 unwaxed samples representing a full range of SG values for a variety of lithologies and then submitted the samples to ALS Minerals for wet-dry SG determinations after being sealed in wax. The mean difference between the NovaGold unwaxed and the ALS Minerals waxed SG determinations was 0.01.

 

In 2011, NovaGold submitted 266 pulps to ALS Minerals for determination of SG by pycnometer (ALS code OA-GRA08b). Figure 8-5 shows the paired pycnometer and whole core water immersion results compare well. The chart shows the pycnometer results display a slight low bias. Generally, intact samples are considered more acceptable for accurate SG determinations since they more closely resemble the in-situ rock mass.

  
Arctic ProjectPage 123
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-5:Graph showing Good Agreement between Wet-Dry Measured Specific Gravity and Pycnometer Measured Specific Gravity

 

 

Source: West, A., 2014

 

8.2.4.2Stoichiometric Method

 

Trilogy compared full sample length water immersion SG determinations with stoichiometric calculated SG values for 279 sample intervals that have copper, zinc, lead, iron, and XRF barium results, the major constituents of the sulphide and sulphate species for the Arctic deposit. Figure 8-6 shows That overall, there is good correlation between the two SG populations although the stoichiometric estimates are slightly lower with increasing SG.

  
Arctic ProjectPage 124
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-6:Measured vs. Stoichiometric Specific Gravities

 

 

Source: West, A., 2014.

 

8.2.4.3Multiple Regressions Method

 

The best fit to the data was achieved by using the multiple regression tool in Microsoft Excel on barium, iron, zinc, and copper for the entire dataset (Figure 8-7). The estimate correlates very well (R2=0.9678) with observed data and has a sinusoidal pattern that fits the low and moderately high SG very well and has high bias for moderate SG values and a low bias for very high SG values. The resultant SG formula is as follows:

 

SG(Regression)= 2.567 + 0.0048*Cu(wt%) + 0.045*Fe(wt%) + 0.032*Ba(wt%) + 0.023%*Zn(wt%)

  
Arctic ProjectPage 125
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-7:Scatter Plot Showing the Measured Specific Gravity vs. Multiple (Copper, Iron, Zinc, Barium) Regression

 

 

Source: West, A., 2014.

 

8.2.4.4Random Forest Machine Learning Method

 

A random forest classification method was used to assist prediction of SG values for 12,039 sample intervals. Information regarding the inputs to the random forest method were not available for review. A comparison of 8,542 paired predicted and paired measured values shows a reasonable correlation between measured and random forest assisted prediction values but an obvious low bias low bias for predicted values (Figure 8-8). The bias is unexplained but may be a result of insufficient Ba analyses. The Random Forest predicted SG values were used in the current resource estimate and the impact of the bias is discussed in Section 11.5.1.

  
Arctic ProjectPage 126
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 8-8:Reduced to Major Axis (RMA) Scatter Plot Showing the Predicted and Measured SG Values

 

 

Source: Wood, 2022.

 

8.2.4.5Comments on Density Determinations

 

Stoichiometric and multiple regression method results generally produce SG values that compare well with measured results. SG values predicted using random forest methods produce biased results. In the opinion of the QP, use of these predicted SG valued for estimation of SG in the block model may introduce a significant low bias for high SG areas.

 

8.2.5Acid-Base Accounting Sampling QA/QC

 

SRK conducted a QA/QC review of the 2010 ABA dataset for the Arctic Project in July 2011 and concluded that data quality was acceptable.

 

QA/QC of the ABA dataset generated in 2015 and 2016 was conducted by SRK in November 2016 through January 2017 and data quality was concluded to be acceptable.

 

SRK conducted a QA/QC review of the ABA dataset from the various kinetic test samples in July 2019, June 2021, and November 2022, concluding that the data quality was acceptable.

 

SRK conducts monthly QA/QC review of kinetic test leachates for all operating kinetic tests. The kinetic test program also includes duplicate and blank tests. Data are reviewed for ion balance, potential contamination, reproducibility, changes in long-term trends, and anomalous spikes in the data. Where considered necessary by SRK, the laboratory is asked to rerun leachates from kinetic tests to investigate QC concerns.

  
Arctic ProjectPage 127
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

8.3Comments on Sample Preparation, Analyses and Security

 

The drill core sampling procedures at site, the primary laboratory sample preparation and analytical procedures, and the QAQC and security procedures applied by NovaGold and Trilogy for samples collected and analyzed since 2004 are in the QP’s opinion appropriate for the mineralization style observed at Arctic and provide adequate confidence in the reported assay values. Historical copper and lead values (pre 2004) that remain in the primary assay database appear to be biased high and low, respectively. The broad spatial distribution of these original historical samples and density of samples with more recent assay values surrounding these samples in the QP’s opinion reduces the risk associated with these observed biases and are suitable to be used in resource estimation. 

  
Arctic ProjectPage 128
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

9DATA VERIFICATION

 

Wood reviewed database verification and laboratory QA/QC reports and made data entry error spot checks, inspected down hole survey results for anomalous kinks and excessive bends in the drill hole traces, reviewed reports summarizing the results of drill core sampling and assaying completed since 2004, reviewed the assay database for gaps and overlaps, and reviewed the historical re-assay program results. The following two significant issues were observed:

 

A significant high bias in historic Cu and low bias in historic Pb assay results (see Section 8).

 

Apparent low bias in Random Forest assisted specific gravity predictions (see Section 8).

 

Excessive between-survey deviation was observed in 30 historical drill holes and transcription errors related to priority of KCC/Utah laboratory assay results were observed in two randomly selected holes. Database adjustments by NovaGold and NovaCopper include resurvey and transformation of historical hole collar coordinates from UTM NAD27 feet to UTM NAD83 metres, historical down hole survey bearings from quadrant to azimuth and down hole survey depth from feet to metres, and gold and silver results from ounces per ton to grams per tonne. A spot comparison comparing original result documents and the database revealed transcription errors and inconsistencies in data selection priority. In the QP’s opinion, these issues are not expected to have a material impact on the grade estimation but should be resolved in the next model.

 

In the current assay table historical sample interval assay results are given priority over the historic sample interval re-assay results. In the QP’s opinion, this is not expected to have a material impact on the grade estimation but using the re-assay results would further mitigate the risk associated with the observed biases in the historical Cu and Pb values, as discussed in Section 8.

 

There are no QAQC analysis for the deleterious variables (As, Sb, Cd, Hg, Fe, S).

 

Overall, the database verification and management and the laboratory QAQC monitoring completed by NovaGold, Trilogy and Ambler Metals has resulted in a reasonably reliable drill hole database suitable for supporting the Mineral Resource estimated for the Arctic deposit. Some deficiencies exist that when rectified will make the drill hole database even more robust.

 

As referenced in Section 6, the interplay between the complex local stratigraphy, the isoclinal F1 event, the overturned south verging F2 event and the series of post-penetrative deformational events often makes district geological interpretation extremely difficult at a local scale. The current geological model captures the complexity reasonably well, but it is possible there is more variability at the local scale than is modelled. Tight spaced drilling in key areas of the deposit is warranted.

 

9.1Comments on Data Verification

 

It is the QP’s opinion that the drill database and topographic information for the Arctic deposit are reliable and sufficient to support the current estimate of Mineral Resources. 

  
Arctic ProjectPage 129
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

10MINERAL PROCESSING AND METALLURGICAL TESTING

 

10.1Introduction

 

Metallurgical studies have spanned over 30 years with metallurgical testwork campaigns undertaken at the Kennecott Research Centre (KRC) in Salt Lake City, Utah; Lakefield Research Ltd., Lakefield Ontario (Lakefield); SGS Mineral Services, Burnaby, BC (SGS); and ALS Metallurgy, Kamloops, B.C. (ALS Metallurgy). Metallurgical testwork laboratories are typically not accredited. The KRC was not independent of Kennecott at the time the testwork was completed; all other laboratories were and are independent of NovaGold, Trilogy and Ambler Metals.

 

The current accreditation status of the KRC is unknown. Lakefield joined the SGS group in 2002. SGS and ALS Metallurgy conform to the requirements of ISO/IEC 17025 for specific tests as listed on their respective scope of accreditation documents, which can be found at www.scc.ca/en/search/laboratories.

 

The testwork conducted in 2012 through 2019 was under the technical direction of International Metallurgical and Environmental Inc (IME). Testwork prior to 2012 is considered historical in nature and has provided some guidance to the project development but is not used in any predictive manner or used in the generation of design criteria. The testwork was focused on a conventional process flowsheet employing crushing, grinding, bulk flotation of a copper and lead concentrate, flotation of a zinc concentrate and the subsequent separation of copper and lead values via flotation.

 

Various metallurgical testwork programs were conducted in 2021 through 2022 at ALS Metallurgy, SGS, and Metso-Outotec Group (Metso Group). ALS Metallurgy completed several testwork programs, including flotation testing with the pre-flotation circuit only to establish talc performance; further flowsheet development testwork to investigate the benefits of sequential flotation versus the original bulk flow sheet; and a variability testwork to support the development of improved metallurgical recovery models.

 

SGS conducted SAG Power Index (SPI®) tests to investigate the effect of friable ores on the plant throughput.

 

Metso Group conducted talc circuit modelling using the data obtained from the ALS Metallurgy pre-flotation testwork program to investigate the benefits of talc circuit open and closed-circuit cleaning. The Mesto Group also conducted dewatering and filtration testwork on the pre-flotation concentrate and final tailings generated from the pre-flotation testwork program.

 

The LOM average metallurgical performance forecasts, based on recent testwork completed and expected mine production grades is shown in Table 10-1. This overall project metallurgical accounting is based on locked cycle testwork, conducted on a distribution of samples from the deposit. Since 2012, testwork has been focused on optimizing the performance of the recommended flowsheet.

 

  
Arctic ProjectPage 130
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 10-1: Summary of Overall Forecast Metal Recovery – Arctic Deposit

 

      Concentrate Grade   Metal Recoveries 
Process Stream  Mass
%
   Cu
%
   Pb
%
   Zn
%
   Au
g/t
   Ag
g/t
   Cu
%
   Pb
%
   Zn
%
   Au
%
   Ag
%
 
Process Feed   100.0    2.11    0.56    2.90    0.42    31.8    -    -    -    -    - 
Copper Conc.   6.3    30.3    1.7    0.7    3.4    160.5    92.1    19.4    1.6    52.2    32.4 
Lead Conc.   0.6    2.0    53.9    5.9    14.1    2425.8    0.6    61.3    1.3    21.4    48.8 
Zinc Conc.   4.7    1.0    0.5    53.6    0.3    38.3    2.2    4.4    88.4    3.2    5.7 
Tailings   88.4    0.1    0.1    0.3    0.1    4.6    5.1    14.8    8.7    23.2    13.1 

 

A summary of the testwork programs completed for the Arctic Project, dates of testwork and testwork objectives is shown in Table 10-2.

 

Table 10-2:Summary of Testwork Chronology and Reporting

 

Laboratory     Project No.     Report Date     Testwork Objectives  
Historical Testwork
KRC - 1970-1976 Preliminary mineralogy and flotation testing
Testwork from 2012 to 2019
Lakefield - 1999 Preliminary flotation testwork.
SGS Burnaby 50173-001 Oct. 4, 2012 Flotation scoping and locked cycle testing (LCT), Bond work index, (BWi), using 4 large composite samples
ALS Metallurgy KM5000 Mar. 27, 2017 Flotation scoping and LC Testing, BWi, using a master composite and 14 variability samples, preliminary copper/lead separation testwork.
ALS Metallurgy KM5372 July 11, 2017 Additional copper/lead separation testwork and detailed precious metal mineralogy
ALS Metallurgy KM5567 Feb. 26, 2018 Talc optimization testwork and copper/lead separation testwork.
JKTech 18017/P14 July 2018 Drop Weight testing of Comp. sample
JKTech 19017/P16 Sept. 2019 SMC testing of Variability Samples
Inter. Metallurgy - April 22, 2019 Cyanide destruction testwork
Pocock Industrial - August 2019 Thickening and filtration testing
Testwork from 2021 to 2022
Metso-Outotec Group - Nov. 3, 2021 Talc pre-flotation simulations
Metso-Outotec Group 93730- TQ1-TM001-R0

Oct 8, 2021

Dewatering testing for Talc concentrate and final tailings.
Metso-Outotec Group 93720- TQ1-TM001-R1

Oct 13, 2021

Filtration testing for Talc concentrate and final tailings.
ALS Metallurgy KM6442 Dec. 15, 2021 Talc optimization testwork
SGS Burnaby 19157-01 June 3, 2022 SAG Power Index testing on 15 samples
ALS Metallurgy KM6498 May 24, 2022 Flotation development testwork
ALS Metallurgy KM6498 July 14, 2022 Flotation development and Variability testwork

 

Detailed testwork has concluded that the mineralization is well-suited to the production of separate copper, lead and zinc concentrates. There are no significant metallurgical impediments outside of the presence of talc minerals and fluorine levels in the lead concentrates as observed in the various testwork programs. The presence of naturally hydrophobic talc minerals was consistently observed, and talc can be effectively removed from the flotation process prior to base metal flotation. There is little reason to expect concentrates will be impaired by talc contamination as talc can be effectively removed from the base metal flotation process, mitigating the potential of talc diluting the base metal concentrates. Talc and fluorine levels will be managed by optimization of the talc pre-float circuit, effectively removing talc and fluorine to ensure the quality of the lead concentrate.

  
Arctic ProjectPage 131
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The flotation process uses industry standard flotation processes, with three major rougher flotation stages and re-grinding and flotation cleaning of copper/lead bulk concentrates and zinc concentrates. Copper and lead are separated from a bulk copper and lead concentrate. Testwork was broken into separate phases, with copper/lead separation being a key distinct phase of testing in the later stages of the program. The full-scale metal recovery and upgrading process can be well-managed with modern process control and ensuring that variability of feed grades, including talc content, can be accommodated.

 

Ancillary testwork including solid-liquid separation and cyanide detoxification testwork was completed.

 

10.2Historical Testwork Review

 

10.2.1Metallurgical Testing – Kennecott Research Centre (1968 to 1976)

 

Between 1970 and 1976, KRC conducted two initial mineralogical studies to evaluate and identify the potential beneficiation or metallurgical options. This early work was a cornerstone of planning later phases of testwork.

 

In the 1970 mineralogy investigation, KRC reported that the host rock of the mineralization is generally muscovite, chlorite, or talc schist. Principal economic minerals in the deposit were identified as chalcopyrite, sphalerite, and argentiferous galena.

 

The grain sizes of sulphide mineral particles ranged from sub-micron to a maximum of several centimetres; most of the sulphide particles were relatively large (coarser than 74 µm). KRC noted that the target sulphide minerals should be liberated from gangue at a primary grind size of 100% passing 100 mesh.

 

In 1976, KRC conducted preliminary comminution testwork using the standard BWi determination procedure (refer to discussion in Section 10.3.4).

 

Between 1968 and 1976, KRC carried out initial flotation testing. The focus was on selective flotation to provide separate copper, lead, and zinc concentrates for conventional smelting. In 1968, initial amenability testing was conducted on core composites from eight diamond drill holes (which is not available to review). Other tests were conducted in 1972 on four composites from three additional diamond core holes. The laboratory-scale tests conducted between 1968 and 1976 included the conventional selective flotation approach to produce separate lead, copper, and zinc concentrates.

 

The major problem encountered for the tests by KRC was the separation between lead and copper minerals, and the reduction of zinc deportment to the copper and lead concentrates. The copper concentrates produced from open circuit tests contained 30 to 32.4% Cu, 0.45 to 3.48% Zn and 0.15% to 1.31% Pb. The copper recoveries were < 80.7%. The lead concentrate grades were low, ranging from 17.1 to 36.5%.

 

Sphalerite flotation was generally efficient, producing zinc flotation concentrates grading approximately 55% zinc. Because of the low gold content of the test samples, no appraisal was made of gold recoveries.

  
Arctic ProjectPage 132
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

From 1975 and 1976, large diameter cores from 14 drill holes were used for more detailed testing. Two composites labelled as Composite No. 1 (Eastern Zone) and Composite No. 2 (Western Zone), were prepared. The test program included bench-scale testing of various process parameters for sequential flotation, including locked cycle tests. A talc flotation step prior to sulphide flotation was considered to be necessary, as previously established. It was determined that chalcopyrite and sphalerite could be recovered into separate commercial grade copper and zinc concentrates. However, the production of a selective high-grade lead concentrate was not successful.

 

Using zinc sulphate and sodium bisulphate to suppress galena and sphalerite, 90% of the copper was recovered into a concentrate containing 26% Cu, 1.5% Pb, and 6% Zn. KRC indicated that because of close interlocking of chalcopyrite and sphalerite, the zinc content of the copper concentrate could not be reduced to below 6% without sacrifice of copper recovery.

 

Only low-grade silver-bearing lead concentrates were obtained. Under the best test conditions, approximately 65% of the silver reported to the low-grade lead concentrate. Some of the silver in the mineralization occurred as tetrahedrite, which was recovered to the copper concentrate. The KRC testwork did not focus on bulk copper and lead flotation and the attempt to focus on a sequential copper-lead-zinc flowsheet is considered a technical error. Subsequent testwork moved to a bulk copper-lead flotation process and subsequent separation of a bulk concentrate into copper and lead concentrates. Metallurgical results have improved with the change to a bulk copper-lead flowsheet in later testwork.

 

10.2.2Metallurgical Testwork – Lakefield (1998 to 1999)

 

In 1998, Lakefield conducted a metallurgical test program to confirm and improve upon the results from the KRC testwork program. The Lakefield work was carried out on test composites prepared from three separate drill holes. The test composite from the upper portion of AR-72 was identified as being low in talc content; however, composites from the lower portion of AR-72 were high in talc content, as were AR-74 and AR-75. The head analyses for the respective resulting test composites are summarized in Table 10-3.

 

Table 10-3:Head Analysis, Lakefield Research 1999

 

Composite  Talc   Cu
(%)
   Zn
(%)
   Pb
(%)
   Fe
(%)
   Au
(g/t)
   Ag
(g/t)
   ST
(g/t)
 
Hole #72 – Upper  Low    5.28    7.16    1.86    15.6    1.14    72.3    23.4 
Hole #72 – Lower  High    2.68    5.85    1.34    13.0    1.60    75.9    16.9 
Hole #74  High    2.46    4.43    0.90    17.0    1.55    45.1    23.7 
Hole #75  High    2.35    8.36    1.95    15.7    1.23    77.3    21.8 

 

Note:ST = total sulphur.

 

Lakefield conducted a series of five flotation tests using a flowsheet similar to the one adopted in the 2012–2019 testwork and incorporated a bulk copper-lead flotation stage followed by copper and lead separation.

 

The bulk copper-lead rougher concentrate was reground and subjected to two stages of cleaner flotation and one stage of copper and lead separation, using zinc oxide and sodium cyanide to depress the copper while floating the lead. The resulting lead rougher concentrate was upgraded with two stages of cleaner flotation to produce the final lead concentrate. The lead rougher flotation tailings were the final copper concentrate.

  
Arctic ProjectPage 133
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The zinc rougher concentrate was reground and upgraded with two stages of cleaner flotation. The results of the best open circuit flotation test for the low talc composite are summarized in Table 10-4. The test results are indicative of the results obtained later in test programs and optimization of the process would improve these results. Of note, is the high recovery of precious metals to the lead concentrates, which was also confirmed in later testwork programs.

 

Table 10-4:Flotation Test on Ambler Low Talc Composite

 

      Assays   Distribution (%) 
Item  Weight
(%)
   Cu
(%)
   Pb
(%)
   Zn
(%)
   Au
(g/t)
   Ag
(g/t)
   Cu   Pb   Zn   Au   Ag 
Lead Concentrate   2.22    6.5    58.8    3.43    38.9    1,703    2.7    68.1    1.1    48.7    47.3 
Copper Concentrate*   15.76    29.1    1.2    2.61    1.23    73.5    86.8    9.8    5.7    10.9    14.5 
Zinc Concentrate   9.91    0.44    0.36    59.1    0.65    14.7    0.8    1.9    81.1    3.6    1.8 
Zinc Tailings**   61.6    0.11    0.13    0.22    0.4    3.47    1.2    4.3    1.9    13.7    2.7 
Head (Calculation)   100.0    5.28    1.92    7.21    1.78    80.1    100.0    100.0    100.0    100.0    100.0 

 

Notes:

 

*Pb Rougher Tailings

**Does not include intermediate cleaner tailings.

 

Lakefield also conducted flotation tests on each of the high talc composites using a test procedure similar to the one used for the low talc composite, with the exception that carboxymethyl cellulose (CMC) was added as a depressant for talc. The results of these tests showed that the presence of talc had a significant negative impact on the copper and lead mineral recoveries. Lakefield also used talc pre-flotation prior to sulphide flotation in an effort to reduce talc effect on base metal flotation. It appears that the talc pre-flotation improved copper and lead metallurgical performances. However, the test results showed that elevated talc content had a significant effect in copper and lead flotation response.

 

In the test report, Lakefield also concluded that grind particle size as coarse as approximately 80% passing 74 µm provided good results.

 

10.3Mineralogical and Metallurgical Testwork – 2012 to 2019

 

10.3.1Introduction

 

Testwork conducted prior to 2012 is considered relevant to the Arctic Project, but predictive metallurgical performance is best estimated from testwork conducted on sample materials obtained from exploration work under the direction of Trilogy, conducted from 2012 to 2019 (refer to Table 10 2).

 

  
Arctic ProjectPage 134
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

In 2012, SGS conducted a test program on the samples produced from mineralization zones 1, 2, 3, and 5. Drill core samples were composited from each of the zones into four different samples for the SGS testwork which included process mineralogical examination, grindability and flotation tests.

 

SGS used quantitative evaluation of materials by scanning electron microscopy QEMSCAN™, to develop grade limiting/recovery relationships for the composites.

 

Standard Bond grindability tests were also conducted on five selected samples to determine the BWi and abrasion index (Ai).

 

The flotation testwork investigated the effect of various process conditions on copper, lead and zinc recovery using copper-lead bulk flotation and zinc flotation followed by copper and lead separation. The testwork conducted in 2012 at SGS forms the basis for predicting metallurgical performance of the mineralized zone in terms of recovery of copper and lead to a bulk concentrate as well as predicting zinc recovery to a zinc concentrate.

 

In 2017, testwork moved to ALS Metallurgy and was focused on predicting the expected performance of the proposed copper and lead separation process, which required the use of larger test samples. A pilot plant was operated to generate approximately 50 kg of copper and lead concentrate, which became test sample material for use in locked cycle testing of the copper and lead separation process. This testwork allows for the accurate prediction of copper and lead deportment in the process as well as provided detailed analysis of the final copper and lead concentrates, expected from the process. Additional metallurgical testwork in the form of variability samples being subject to grindability and baseline flotation tests was also completed.

 

10.3.2Test Samples

 

The 2012 test program used 90 individual drill core sample intervals totalling 1,100 kg. Individual samples were combined into four composites representing different zones and labelled as Composites Zone 1 & 2, Zone 3, Zone 5, and Zone 3 & 5. The sample materials used in the 2012 test program at SGS were specifically obtained for metallurgical test purposes. The drill cores were stored in a freezer to ensure sample degradation and oxidation of sulphide minerals did not occur.

 

The head grades of the composites from the 2012 SGS testwork program is shown in Table 10-5.

 

Table 10-5:SGS Burnaby Head Grades – Composite Samples – 2012

 

Sample  Cu
(%)
   Pb
(%)
   Zn
(%)
   Fe
(%)
   S
(%)
   Au
(g/t)
   Ag
(g/t)
   MgO
(%)
 
Zone 1 & 2   2.63    0.95    3.43    7.73    8.36    0.79    57.6    5.78 
Zone 3   3.56    1.73    8.58    17.5    25.8    0.67    80.4    1.94 
Zone 3 & 5   4.41    1.60    7.76    16.7    23.5    0.97    82.0    3.96 
Zone 5 B   2.56    1.33    5.68    15.8    21.2    1.16    63.0    0.90 

 

The 2017 test program involved the collection of approximately 4,000 kg of drill core from five drill holes. The core was shipped in its entirety to ALS Metallurgy for use in grinding and flotation testwork. Fifteen separate composites samples were generated by crushing defined intercepts of mineralization. These samples were riffle split to generate 15 individual samples which were separately tested for grindability and flotation response, as well, a large portion of each sample was blended to make a single large composite sample for use in copper-lead separation testwork. The copper-lead separation testwork involved operating a pilot plant for the production of a single sample of copper/lead concentrate which was then used in bench-scale flotation testing, including open circuit flotation tests as well as locked cycle flotation tests.

  
Arctic ProjectPage 135
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The feed grades of samples used in the 2017 testwork program at ALS Metallurgy are shown in Table 10-6.

 

Table 10-6:ALS Metallurgy Head Grades – Composite Samples – 2017

 

Sample ID  Cu
(%)
   Pb
(%)
   Zn
(%)
   Fe
(%)
   S
(%)
   Au
(g/t)
   Ag
(g/t)
  

Mg 

(%) 

 
Var. Comp 1   5.05    1.53    7.40    15.0    24.4    0.68    64    2.69 
Var. Comp 2   2.06    0.25    1.05    4.6    3.68    0.52    34    11.2 
Var. Comp 3   1.67    0.80    2.93    6.6    4.93    0.10    43    7.51 
Var. Comp 4   2.25    0.24    3.15    13.1    16.2    0.20    18    6.26 
Var. Comp 5   3.68    1.01    5.55    10.6    13.9    0.78    69    7.16 
Var. Comp 6   1.02    0.36    1.61    8.0    9.45    0.45    24    1.92 
Var. Comp 7   1.75    0.58    2.71    8.9    12.9    0.21    32    3.46 
Var. Comp 8   3.00    0.68    4.65    10.0    13.3    0.75    56    9.18 
Var. Comp 9   5.46    1.37    6.60    9.2    14.0    0.15    50    5.65 
Var. Comp 10   4.16    1.24    5.63    13.4    22.1    0.06    34    3.58 
Var. Comp 11   2.78    0.40    4.56    12.7    16.9    0.64    40    6.84 
Var. Comp 12   1.53    0.07    0.56    4.4    3.15    0.59    16    10.6 
Var. Comp 13   1.98    0.30    1.48    6.2    6.25    0.26    38    9.61 
Var. Comp 14   2.37    2.43    9.50    15.1    23.7    0.84    62    0.81 
PP Comp.   2.92    0.86    4.66    10.8    13.8    0.56    41    5.93 

 

Shown in Figure 10 1 are the copper and zinc grades of the SGS and ALS Metallurgy testwork samples compared to the designed plant feed grades. The ALS Metallurgy samples are more representative of the expected mine production due to the lower range of copper and zinc grades that are available. There is a strong correlation between copper and zinc grades within the test samples. The metallurgical balance shown in Table 10-1 is based on LOM feed grades and is consistent with the LOM data point shown in Figure 10-1.

 

Shown in Figure 10 2 are the copper and lead grades of the various test samples used in the ALS Metallurgy and SGS test programs. There is a consistent copper to lead ratio of approximately 3.5–4.5 within the test samples and the LOM grades are shown to be within the distribution of test samples.

  
Arctic ProjectPage 136
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 10-1:Cu and Zn Test Sample Grades for ALS Metallurgy/SGS Burnaby Programs

 

 

 

Source: Austin, 2020.

 

Figure 10-2:Cu and Pb Test Sample Grades for ALS Metallurgy/SGS Burnaby Programs

 

 

Source: Austin, 2020.

  
Arctic ProjectPage 137
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The volume of talc observed in the various test samples ranged from a low of zero contained talc to a high of 42% by weight floatable talc. Shown in Figure 10-3 is the distribution of talc within both the SGS and ALS Metallurgy samples. The estimated LOM talc content is estimated at 5.1%. Only one of the SGS test samples exceeded the LOM talc content, while 11 of the 14 ALS Metallurgy samples exceeded the LOM talc content. A composite of the ALS Metallurgy samples was approximately twice the talc content of the expected mine production. Talc, while a significant issue for the flotation process is likely overestimated in terms of its potential negative impact, owing to the large number of high talc samples seen in the ALS Metallurgy sample set. It has also been clearly demonstrated that even high volumes of talc can be effectively removed from the base metal flotation process and remove the impact of talc diluting base metal concentrates.

 

Figure 10-3:Distribution of Talc Content within the 2012 and 2017 Test Samples

 

 

 

Source: Austin, 2020.

 

10.3.3Mineralogical Investigations

 

SGS used QEMSCAN™ to complete a detailed mineralogical study on each composite to identify mineral liberations and associations. The mineral modal abundance for the composites is shown in Table 10-7.

 

The mineralogical results obtained by SGS were typical for the balance of other samples observed in the ALS Metallurgy QEMSCAN analysis and no significant liberation or changes in mineral occurrences were observed in later QEMSCAN work. Metal and talc grades all were observed to be variable in the mineralogical evaluations but did not significantly impact textural relationships.

  
Arctic ProjectPage 138
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 10-7:Mineral Modal Abundance for Composite Samples – SGS Burnaby 2012

 

   Mass (%) 
Mineral  Zone 1 & 2   Zone 3   Zone 3 & 5   Zone 5 
Chalcopyrite   9.2    9.4    12.2    6.4 
Bornite   0.02    0.01    0.03    0.4 
Tetrahedrite   0.1    0.4    0.2    0.2 
Antimony   0.03    0.2    0.005    0.3 
Galena   1.3    2.1    2.1    2.1 
Sphalerite   7.2    14.6    14.3    11.3 
Pyrite   6.7    30.4    23.8    27.8 
Pyrrhotite   2.2    0.2    0.2    1.4 
Arsenopyrite   0.5    0.1    0.6    2.2 
Other Sulphides   0.1    0.1    0.2    0.1 
Quartz   30.2    8.6    9.0    16.6 
Feldspar   0.9    0.2    0.4    0.3 
Magnesium-Chlorite   11.9    3.4    2.8    1.1 
Talc   2.0    0.8    6.3    0.1 
Micas   14.2    1.9    7.0    9.4 
Cymrite   3.5    3.9    1.8    1.9 
Clays   0.6    0.05    0.2    0.1 
Iron Oxides   0.3    0.3    0.5    0.3 
Carbonates   3.4    1.3    4.2    2.0 
Barite   3.0    21.8    13.4    14.5 
Fluorite   1.7    0.1    0.4    1.2 
Other   1.1    0.3    0.4    0.4 
Total   100.0    100.0    100.0    100.0 

 

The mineralogical study showed that the mineralogy of all four composites was similar, but mineral volumes were highly variable between samples. Each composite was composed mainly of pyrite, quartz, and carbonates. However, Composite Zone 1 & 2 contain approximately 30% quartz, compared to 8.6% for Composite Zone 3, and 16.6% for Composite Zone 5. The study also showed that Composite Zone 1 & 2 had the lowest pyrite content (6.7%) while Composites Zone 3 and Zone 5 contained approximately 30.4% and 27.8% pyrite, respectively.

 

In all samples, the major floatable gangue minerals were talc and pyrite. Chalcopyrite was the main copper carrier. Combined bornite, tetrahedrite, and other sulphides accounted for less than 5% of the copper contained in the various samples. Galena was the main lead mineral and sphalerite was the main zinc mineral.

 

All the composites contained a significant amount of talc, which may have the potential to dilute final concentrates. Therefore, SGS recommended that talc removal using flotation be employed prior to base metal flotation and this recommendation was carried throughout all testwork.

  
Arctic ProjectPage 139
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

At a grind size of approximately 80% passing 70 µm, chalcopyrite liberation ranged from approximately 80 to 87% (free and liberated combined) for all composites. The chalcopyrite is mostly free, with 7 to 10% associated with pyrite. For all composites, galena liberation ranged from 54 to 68% (free and liberated combined). Sphalerite liberation varied between 81 to 89%. Sphalerite is mostly free with about 7 to 10% associated with pyrite. Mineral liberation plays a significant role in removing talc during the pre-float stage and finer grinding benefits the removal of talc prior to sulphide flotation and subsequent re-grinding.

 

10.3.4Comminution Testwork

 

KRC completed BWi tests on seven specific samples from the Arctic project in the 1976 testwork program. SGS conducted comminution tests on five selected samples during their testwork program in 2012. The SGS tests included the BWi tests and Ai tests. ALS Metallurgy also conducted BWi determinations on a number of samples during the 2017 to 2019 testwork program and these results from all three programs are summarized in Table 10-8. The BWi values range from 6.5 to 11 kWh/t for the materials sampled. The data indicates that the samples are relatively soft to ball mill grinding. The Ai ranged from 0.017 to 0.072 g, which indicates that the samples are not abrasive.

 

Grinding testwork for semi-autogenous grind (SAG) mill characterization was completed in conjunction with the ALS Metallurgy 2017 work. JKTech completed SMC and DWi testing of samples specifically selected for SAG amenability testing. Additional BWi determinations were also completed on the samples selected for SMC testwork; those BWI test results are included in Table 10-9 with the SMC results. Drill core data for the various SMC samples are contained in Table 10-8.

 

A total of 46 BWi tests were completed.

 

Table 10-8:Bond Ball Mill Work Index and Abrasion Index Test Results

 

Sample  Mesh of
Grind Size
   P80
(µm)
   BWi
(kWh/t)
   Ai
(g)
 
                 
1976 KRC samples
Hole – 11B   150    -    11.96    - 
Hole – 34B   150    -    8.33    - 
Hole – 34B   150    -    5.71    - 
Hole – 34B   150    -    11.3    - 
Hole – 34C   150    -    9.98    - 
Hole – 48A   150    -    10.5    - 
Hole – 48B   150    -    9.60    - 
2012 SGS samples
MET – 1105341   150    88    6.7    0.032 
MET – 1106043   150    88    6.5    0.019 
MET – 1105868   150    85    7.4    0.030 
MET – 1106033   150    87    9.3    0.072 
MET – 1105853   150    89    11.1    0.017 
2017 ALS Metallurgy samples
Composite 1   106    106    9.0    - 
Composite 2   300    228    8.6    - 
Composite 3   300    232    8.1    - 
Composite 4   300    226    6.6    - 
Composite 5   300    233    7.1    - 

  
Arctic ProjectPage 140
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Sample  Mesh of
Grind Size
   P80
(µm)
   BWi
(kWh/t)
   Ai
(g)
 
Composite 6   300    233    6.1    - 
Composite 7   300    223    6.2    - 
Composite 8   300    234    9.0    - 
Composite 9   300    236    6.4    - 
Composite 10   300    237    5.3    - 
Composite 11   300    225    7.2    - 
Composite 12   300    234    10.3    - 
Composite 13   300    229    10.1    - 
Composite 14   300    231    6.4    - 
PP Composite 1   300    231    7.2    - 

 

ALS Metallurgy, in conjunction with the JKTech completed DWi testing and SMC tests on 19 individual samples.

 

SMC testwork was also completed by JKTech, including breakage parameters a x b, BWi, and autogenous grind/SAG mill specific energy (SCSE). The SMC data show the materials to be soft to very soft in terms of SAG milling characteristics. Test results are provided in Table 10-9.

 

Table 10-9:Summary of SMC Test Results and Additional BMI Data

 

Sample  a x b   SCSE
(kWh/t)
   BWi
(kWh/t)
 
SMC - 1   148.9    6.13    10.9 
SMC – 2   NA    NA    11.9 
SMC – 3   239.9    5.31    7.1 
SMC – 4   106.8    6.89    8.5 
SMC – 5   203.5    5.56    6.8 
SMC – 6   272.7    4.71    5.4 
SMC – 7   629.3    3.98    12.5 
SMC – 8   301.8    5.09    11.7 
SMC – 9   220.5    5.11    8.2 
SMC – 10   180.2    5.77    6.4 
SMC – 11   143.8    6.25    10.8 
SMC – 12   150.7    6.15    11.4 
SMC – 13   98.8    7.07    7.6 
SMC – 14   115.2    6.68    9.7 
SMC – 15   182.5    5.77    9.0 
SMC - 16   71.6    8.21    9.9 
SMC – 17   86.2    7.27    10.5 
SMC – 18   94.2    7.26    10.3 
SMC – 19   169.3    5.83    8.4 
Average Value   189.8    6.05    - 

  
Arctic ProjectPage 141
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

10.3.5Flotation Testwork

 

The predictive metallurgical results for the Arctic Project are based on locked cycle flotation testwork which mirrors the performance of an operational plant and accounts for circulating loads and intermediate products. Each research program consisted of a large number of open circuit flotation tests that provided guidance to the selection of operating conditions to be used in locked cycle tests.

 

In 2012, SGS conducted bench-scale flotation testwork to investigate the recovery of copper, lead, zinc, and associated precious metals using bulk copper-lead flotation and zinc flotation, followed by copper and lead separation. Four wide-ranging composite samples were tested for rougher flotation kinetics, cleaner efficiency, and copper and lead separation flotation efficiency. All of the testwork used a phased approach to completing testwork, with a preliminary phase of flotation testwork generating a bulk copper-lead concentrate and a final zinc concentrate. The bulk copper-lead concentrate was typically used in a second phase of testing, which was focused on separation of copper and lead minerals into copper and lead concentrates. The second phase of testwork typically also involved open-circuit flotation tests and locked cycle tests.

 

All flotation testwork either at SGS or ALS Metallurgy had the same froth characteristics.

 

The froth product is typically light in density and can require extensive flotation time. Very high talc recoveries are required to protect the lead concentrate from contamination as the lead concentrate is the destination for mis-reporting talc. Talc levels in test samples ranged from 0.0 to 40% talc on a weight basis, the LOM average for talc is approximately 5.1%.

 

The ratio of copper to lead is approximately four in the feed samples tested and within the Mineral Reserve estimates. This copper and lead concentrate is readily upgraded to provide feed to a copper and lead separation circuit. This froth is heavy and flotation rates for copper and lead are considered fast. In all copper and lead flotation, Cytec reagent 3418A was used as a copper and lead collector.

 

Zinc flotation follows both talc flotation and copper/lead bulk flotation. Zinc is depressed through both stages of talc and copper/lead flotation with the use of zinc sulphate and cyanide. Zinc minerals are activated with the addition of copper sulphate and a xanthate-based collector.

 

Zinc flotation is relatively fast, and froths are generally heavily laden with mineral.

 

The separation of copper and lead is completed using a high-grade concentrate of copper and lead minerals. The basis of the copper and lead separation is the depression of copper minerals using cyanide to render the copper minerals hydrophilic.

 

Locked cycle test results form the basis of metallurgical predictions for the Arctic project and are reported within Table 10-13 for the SGS testwork program and within Table 10-13 for the ALS Metallurgy testwork program.

 

The SGS testwork produced similar metallurgical performances among the composite samples tested and results were consistent with expectations outlined in the various mineralogical examinations and preliminary testwork results. Further optimization testwork would likely have improved the flotation performance of the composite sample for Zone 1 & 2 (LCT6), sample availability was limited for this composite.

 

The SGS flotation testwork points to high recoveries of copper and lead to a bulk concentrate of copper and lead which would be subsequently separated. Copper recoveries were in the range of 90 to 92%. Zinc recoveries were typically in the range of 89 to 92%. The majority of misreporting of copper was to the zinc concentrate and the majority of mis-reporting zinc was to the copper-lead concentrate. Ongoing optimization of the flotation process will likely reduce the misreporting of metals, through changes in reagent additions, grind size optimization and concentrate mass recovery.

  
Arctic ProjectPage 142
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Flotation testwork conducted in 2017 at ALS Metallurgy, was focused on a detailed evaluation of the performance of a copper and lead separation process and included open circuit flotation tests and locked cycle flotation testing of the copper-lead separation process.

 

A master composite was made from 14 variability samples from the deposit. Locked cycle testing for this composite was completed to provide a comparison with the SGS test results.

 

A summary of the locked cycle test results for both the SGS and ALS Metallurgy test programs in contained in Table 10-10.

 

Table 10-10:Summary of Locked Cycle Recovery Data for Composite Sample Testing

 

   Recovery to Bulk Cu/Pb Concentrate or Zinc Concentrate 
Sample  Cu1
(%)
   Pb1
(%)
   Zn2
(%)
   Au1
(g/t)
   Ag1
(g/t)
 
                     
SGS Burnaby 2012
Zone 3   92.5    92.6    93.0    77.6    85.9 
Zone 5   91.3    92.0    89.3    70.9    84.2 
Zone 3&5   91.7    92.3    91.6    75.8    85.0 
Zone 1&2   84.2    94.0    85.7    79.7    84.2 
ALS Metallurgy 2017 
Master Comp.   94.1    88.7    87.8    74.4    85.4 

 

Notes:

 

1.Represents recovery to a bulk concentrate prior to Cu/Pb separation.
2.Represents recovery to a final zinc concentrate.

 

Locked cycle test results for the ALS Metallurgy master composite are contained in Table 10-10 and reports results for the production of a bulk copper-lead concentrate and a zinc concentrate. Table 10-11 provides the results for the SGS testwork program and Table 10-12 includes the results for the ALS Metallurgy testwork program.

  
Arctic ProjectPage 143
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 10-11:Locked Cycle Metallurgical Test Results – SGS Burnaby 2012

 

Test No.             Product              

          Regrind Size          

          80% Passing          

    Weight
%
    Assays   Distribution (%)
  Cu
(%)
  Pb
(%)
  Zn
(%)
  Au
(g/t)
  Ag
(g/t)
  S
(%)
  Cu   Pb   Zn   Au   Ag   S

Zone 3 

LCT-2

Talc Concentrate Cu/Pb Rougher Concentrate: 43 µm;
Zn Rougher Concentrate: 41 µm
1.6   2.39   2.44   4.05   0.51   105.0   9.97   0.4   0.8   0.3   0.4   0.8   0.2
Cu/Pb Cleaner 2 Conc. 12.9 24.7 12.4 3.61 4.73 506 30.5 92.5 92.6 5.5 77.6 85.9 15.4
Zn Cleaner 2 Concentrate 12.9 1.02 0.38 61.4 0.40 41.7 32.9 3.8 2.8 93.0 6.5 7.1 16.5
Zn Cleaner 1 Sc. Tailings 5.9 0.85 0.33 0.86 0.97 35.0 38.7 1.5 1.1 0.6 7.3 2.7 9.0
Zn Rougher Tailings 66.7 0.10 0.07 0.09 0.10 4.01 22.5 1.9 2.7 0.7 8.3 3.5 58.9
Feed 100.0 3.42 1.71 8.43 0.78 75.3 25.4 100.0 100.0 100.0 100.0 100.0 100.0

Zone 5 

LCT-3

Talc Concentrate Cu/Pb Rougher Concentrate: 36 µm;
Zn Rougher Concentrate: 35 µm
1.3 7.15 3.71 2.46 1.22 187.0 13.7 1.2 1.2 0.2 0.3 1.4 0.3
Cu/Pb Cleaner 2 Conc. 9.9 23.8 12.9 5.04 11.2 499 31.5 91.3 92.0 9.1 70.9 84.2 14.7
Zn Cleaner 2 Concentrate 8.3 0.91 0.56 59.1 0.55 46.4 30.5 2.9 3.4 89.3 2.9 6.6 11.9
Zn Cleaner 1 Sc. Tailings 7.1 0.80 0.28 0.56 4.55 30.0 32.4 2.2 1.4 0.7 20.5 3.6 10.7
Zn Rougher Tailings 73.4 0.09 0.04 0.05 0.11 3.38 18.1 2.4 2.0 0.7 5.3 4.2 62.4
Feed 100.0 2.56 1.37 5.47 1.55 58.2 21.1 100.0 100.0 100.0 100.0 100.0 100.0

Zone 3 & 5 

LCT 4

Talc Concentrate Cu/Pb Rougher Concentrate: 45 µm;
Zn Rougher Concentrate: 23 µm
7.3 0.72 0.38 1.37 0.11 17.6 3.01 0.4 0.6 0.4 0.3 0.6 0.3
Cu/Pb Cleaner 2 Conc. 16.0 25.3 9.25 3.13 4.28 408 29.4 91.7 92.3 6.4 73.8 85.0 21.3
Zn Cleaner 2 Concentrate 11.8 1.78 0.39 60.9 0.48 50.7 32.5 4.8 2.9 91.6 6.1 7.8 17.4
Zn Cleaner 1 Sc. Tailings 4.8 1.15 0.38 1.09 2.6 39.8 27.1 1.3 1.1 0.7 13.5 2.5 5.9
Zn Rougher Tailings 60.2 0.14 0.08 0.13 0.1 5.19 20.2 1.9 3.2 1 6.3 4.1 55.1
Feed 100.0 4.41 1.6 7.85 0.93 76.6 22.1 100 100 100 100 100 100

Zone 1 & 2 

LCT-6

Talc Concentrate Cu/Pb Rougher Concentrate: 62 µm;
Zn Rougher Concentrate: 55 µm
4.8 0.67 0.34 0.90 0.40 13.9 1.88 0.4 0.6 0.4 0.8 0.4 0.3
Cu/Pb Cleaner 2 Conc. 9.5 23.7 9.54 5.12 6.65 481 30.2 84.2 94.0 14.3 79.7 84.2 32.5
Zn Cleaner 2 Concentrate 6.4 5.84 0.49 44.5 0.91 101.5 32.8 14.0 3.2 83.7 7.4 12.0 23.9
Zn Cleaner 1 Sc. Tailings 7.4 0.22 0.06 0.17 0.91 12.3 19.6 0.6 0.5 0.4 8.4 1.7 16.4
Zn Rougher Tailings 71.8 0.03 0.02 0.06 0.04 1.34 3.30 0.8 1.7 1.2 3.7 1.8 26.8
Feed 100.0 2.69 0.97 3.42 0.80 54.6 8.8 100.0 100.0 100.0 100.0 100.0 100.0
                                                                                           

Table 10-12:Locked Cycle Metallurgical Test Results – ALS Metallurgy 2017

 

Test No.                    Product                      Regrind Size 80% Passing     Weight %     Assays   Distribution (%)
  Cu
(%)
    Pb
(%)
    Zn
(%)
    Au
(g/t)
    Ag
(g/t)
    S
(%)
    Cu     Pb     Zn     Au     Ag   S

Zone 3

LCT-2

Talc Concentrate Cu/Pb Rougher Concentrate: 43 µm;
Zn Rougher Concentrate: 41 µm
1.6 2.39 2.44 4.05 0.51 105.0 9.97 0.4 0.8 0.3 0.4 0.8 0.2
Cu/Pb Cleaner 2 Conc. 12.9 24.7 12.4 3.61 4.73 506 30.5 92.5 92.6 5.5 77.6 85.9 15.4
Zn Cleaner 2 Concentrate 12.9 1.02 0.38 61.4 0.40 41.7 32.9 3.8 2.8 93.0 6.5 7.1 16.5
Zn Cleaner 1 Sc. Tailings 5.9 0.85 0.33 0.86 0.97 35.0 38.7 1.5 1.1 0.6 7.3 2.7 9.0
Zn Rougher Tailings 66.7 0.10 0.07 0.09 0.10 4.01 22.5 1.9 2.7 0.7 8.3 3.5 58.9
Feed 100.0 3.42 1.71 8.43 0.78 75.3 25.4 100.0 100.0 100.0 100.0 100.0 100.0

  
Arctic ProjectPage 144
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

10.3.6Copper/Lead Separation Testwork

 

SGS performed preliminary open-circuit copper and lead separation tests on the bulk copper-lead concentrates produced from the locked cycle tests in open circuit flotation tests. Sodium cyanide was used to suppress copper minerals; 3418A was used as the lead collector and lime was added to adjust the pulp pH to 10. Table 10-13 summarizes the separation test results. These results were obtained using small concentrate samples of approximately 200 g following the production of bulk concentrates in locked cycle testwork. These results also indicated that the separation of copper and lead was feasible using depression of copper and the flotation of lead minerals. Lead concentrate grades as high as 60% lead were obtained in these preliminary open-circuit tests at SGS and rougher flotation recoveries for lead were observed in the range of 88 to 95%.

 

Additional testwork to provide detailed estimates of the performance of the copper and lead flotation process was conducted at ALS Metallurgy. Approximately 50 kg of bulk copper and lead concentrate was produced in a pilot plant program with the specific objective of completing detailed copper and lead separation testwork. The separation testwork performed very well, however, lower than expected lead concentrate grades were obtained due to talc contamination of the final lead concentrate. This contamination was due to non-optimal talc flotation conditions within the pilot plant.

 

Results for two locked cycle tests using the pilot plant bulk concentrate are shown in Table 10-14. Recovery of lead to a final concentrate was consistent at 88% of the lead contained in the bulk concentrate. Recovery of copper to a final concentrate was consistent at 97.4% of the copper contained in a bulk concentrate.

  
Arctic ProjectPage 145
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 10-13:SGS Burnaby Open Circuit Copper and Lead Separation Test Results

 

Test             Product               Weight
%
    Assays   Distribution (%)
  Cu
(%)
    Pb
(%)
    Zn
(%)
    Ag
(g/t)
    Au
(g/t)
    S
(%)
    Cu     Pb     Zn     Ag     Au   S
Zone 3 & 5
Cu/Pb Separation Feed from LCT-4
(Cycle 2)
Pb 2nd Cleaner Concentrate 8.2 5.99 41.0 2.02 2,330 18.9 13.1 1.9 37.0 6.0 44.7 35.9 3.4
Pb 1st Cleaner Concentrate 22 6.87 37.5 4.34 1,665 13.6 20.6 5.9 90.8 34.8 85.7 69.5 14.3
Pb Rougher Concentrate 37.7 16.4 23.0 3.43 1,033 9.17 26.2 24.1 95.5 47.4 91.3 80.3 31.4
Pb Rougher Tailings (Cu Concentrate) 62.3 31.3 0.65 2.31 59 1.36 34.7 75.9 4.5 52.6 8.7 19.7 68.6
Cu/Pb 2nd Cleaner Concentrate (Head) - 25.7 9.07 2.73 4.27 4.31 31.5 - - - - - -
Zone 3
Cu/Pb Separation from Open Circuit Test (Test F25)
Pb 2nd Cleaner Concentrate 2.1 2.22 58.8 5.58 1,622 0.3 20.8 1.4 74.9 1.4 44.2 1.0 1.8
Pb 1st Cleaner Concentrate 2.9 4.51 48.3 6.94 1,369 0.5 24.1 3.8 83.8 2.4 50.9 2.0 2.8
Pb Rougher Concentrate 4.3 12.4 33.6 6.54 1,026 1.05 26.9 15.3 86.0 3.3 56.3 6.6 4.6
Pb Rougher Tailings (Cu Concentrate) 8.3 31.5 0.29 4.33 231 5.24 33.3 75.1 1.4 4.2 24.5 63.9 11.0
Cu/Pb 2nd Cleaner Concentrate (Head) 12.6 25.0 11.6 5.08 502 3.81 31.1 90.4 87.4 7.5 80.8 70.5 15.5
Zone 5
Cu/Pb Separation Feed from LCT-5
(Cycle 2)
Pb 2nd Cleaner Concentrate 6.6 2.42 69.0 2.68 1,230 1.27 15.8 0.6 41.1 3 17.2 1.8 3.3
Pb 1st Cleaner Concentrate 15.2 3.78 57.6 4.18 993 1.92 20.5 2.3 78.8 11.5 31.9 6.1 9.8
Pb Rougher Concentrate 25.5 10.3 40.3 4.82 778 6.31 25.1 10.5 92.4 22.1 41.9 33.6 20.1
Pb Rougher Tailings (Cu Concentrate) 74.5 30.0 1.13 5.79 369 4.26 34.1 89.5 7.58 77.9 58.1 66.4 79.9
Cu/Pb 2nd Cleaner Concentrate (Head) - 25.0 11.1 5.54 473 4.78 31.8 100.0 100.0 100.0 100.0 100.0 100.0
Zone 1 & 2
Cu/Pb Separation Feed from
LCT-6 (Cycle 2)
Pb 2nd Cleaner Concentrate 7.59 2.4 57.3 5.59 0.54 1,313 15.1 0.76 47.1 8.1 0.7 20.1 3.78
Pb 1st Cleaner Concentrate 16.4 4.38 45.3 7.96 0.77 1,038 19.9 2.98 80.5 24.9 2.2 34.4 10.8
Pb Rougher Concentrate 23.6 9.6 34.3 7.19 1.13 849 22.9 9.4 87.7 32.3 4.6 40.4 17.8
Pb Rougher Tailings (Cu Concentrate) 76.4 28.6 1.49 4.64 7.14 386 32.6 90.6 12.34 67.7 95.4 59.6 82.2
Cu/Pb 2nd Cleaner Concentrate (Head) - 24.1 9.23 5.24 5.72 495 30.3 100.0 100.0 100.0 100.0 100.0 100.0

 

Table 10-14:ALS Metallurgy Locked Cycle Testing of Copper-Lead Separation Process

 

Test             Product               Weight
%
    Assays   Distribution (%)
  Cu
(%)
    Pb
(%)
    Zn
(%)
    Ag
(g/t)
    Au
(g/t)
    Cu     Pb     Zn     Ag   Au
Test 33
Bulk Conc. From Pilot Plant Operation
Pb 2nd Cleaner Concentrate (Pb Conc.) 22.1 2.68 24.2 1.35 960 6.9 2.6 87.3 11.4 70.5 85.1
Pb 1st Cleaner Tail 11.3 25.8 1.64 2.08 138 0.39 12.9 3.0 9.0 5.2 2.5
Pb Rougher Tail 66.6 28.8 0.89 3.11 110 0.33 84.5 9.7 79.5 24.3 12.5
Combined Tailings (Cu Concentrate) 77.9 28.3 1.00 2.96 144 0.34 97.4 12.7 88.6 29.5 14.9
Bulk Cleaner Concentrate (Feed) - 22.7 6.13 2.61 301 1.79 100.0 100.0 100.0 100.0 100.0
Test 34
Bulk Conc. From Pilot Plant Operation
Pb 2nd Cleaner Concentrate (Pb Conc.) 21.9 2.75 23.3 1.29 906 7.33 2.6 86.0 10.8 69.5 85.3
Pb 1st Cleaner Tail 11.2 26.8 1.76 2.02 132 0.44 12.9 3.3 8.7 5.2 2.6
Pb Rougher Tail 66.9 29.4 0.95 3.14 106 0.34 84.5 10.7 80.5 25.3 12.1
Combined Tailings (Cu Concentrate) 78.1 29.4 1.06 2.98 111 0.35 97.4 14.0 89.2 30.5 14.7
Bulk Cleaner Concentrate (Feed) - 23.3 5.93 2.61 285 1.88 100.0 100.0 100.0 100.0 100.0

  
Arctic ProjectPage 146
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

In order to further evaluate the issue of talc contamination of the lead concentrate that was observed in some of the ALS Metallurgy testwork, additional lead concentrate production testwork was undertaken using a variety of samples with moderate to very high talc contents. This testwork was completed as open-circuit tests and involved the production of a bulk concentrate and the subsequent separation of the copper and lead minerals from the bulk concentrate. The objective of this testwork was to demonstrate that when talc recovery was optimized or maximized, the lead concentrate grade target could be readily achieved. These test results are summarized in Table 10-15. The open circuit tests included operating the talc flotation process until no visible talc was being recovered in the talc flotation stage. The results of the locked cycle separation testwork where lead concentrate grades were observed to be low are included in the table. Also shown is the value of the lead concentrate carried in the predictive metallurgical balance for the Arctic Project.

 

Table 10-15:Summary of Lead Concentrate Grades for Various Talc Grades in Feed

 

   Talc Content   Lead Conc Grade   Copper Conc. Grade 
Sample  %   % Pb   % Cu 
Pilot Plant Comp.   12.7    23.5    29.4 
5567-04(test 4)   18.4    61.1    32.3 
5567-14(test 5)   0    61.5    30.2 
5567-1(test 6)   8.5    46.9    30.8 
5567-5(test 7)   30.0    47.1    32.4 
5567-7(test 8)   10.5    48.2    29.2 
5567-9(test 9)   17.7    63.0    31.4 
5567-14(test 10)   0    56.3    29.1 
5567-5(test 11)   31.5    49.6    31.8 
5567-9(test 12)   19.0    60.2    31.0 
LOM Prediction   5.1    55.0    30.3 

 

The lead concentrate grades observed in the testwork summarized in indicates the ability to manage lead concentrate grades by virtue of the efficiency of the talc removal process. This testwork also indicates that lead concentrate quality can be achieved when talc feed grades are several times higher than the LOM estimated talc grade.

 

Table 10-16 provides descriptions of the key metallurgical parameters for the operation of the proposed recovery and upgrading of base and precious metals. These have been estimated from numerous tests and will be modulated during the operation as feed grades and metal ratios dictate.

  
Arctic ProjectPage 147
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 10-16:Summary of Flotation Reagent and Grind Size Objectives

 

Process Stage Parameter Comment
Flotation Feed    
Primary Grind Size P80 70 µm
Zinc Depressant ZnSO4 200/100 g/t
Zinc Depressant NaCN 100 g/t
     
Talc Flotation    
Frothers MIBC 10 – 40 g/t
     
Bulk Cu/Pb Flotation    
Flotation Collector 3418A 25-40 g/t
Frother MIBC 5 – 10 g/t
Re-grind Size P80 40 µm
     
Zinc Flotation    
Zinc Activator CuSO4 100-200 g/t
Zinc Collector SIPX 10 - 50 g/t
Re-grind Size P80 40 µm
     
Cu/Pb Separation    
Copper Depressant NaCN 60 - 120 g/t
Lead Collector 3418A 10 g/t

 

Note:Expected Concentrate Quality.

 

ICP assays were conducted on the copper and lead concentrates produced from the locked cycle tests at ALS Metallurgy and the zinc concentrate from the locked cycle tests at SGS. The samples are thought to represent the expected concentrate quality. The main impurity elements are shown in Table 10-17.

 

The results indicated that key penalty elements, as well as precious metals are typically concentrated into a lead concentrate, leaving the copper concentrate of higher-than-expected quality.

 

Table 10-17:Summary of Lead Concentrate Quality

 

   Pb   Zn   Cu   Au   Ag   As   Sb   Bi   F 
Lead Conc.  %   %   %   g/t   g/t   g/t   g/t   g/t   g/t 
Average Value   55.0*   1.8    6.9    37.3*   2805*   2128    1375    3876    3260 
Sample Max   -    2.83    -    -    -    4400    5370    5140    5900 
Sample Min   -    0.74    -    -    -    125    32    3270    160 

 

* Reported to be consistent with predictive balance.

  
Arctic ProjectPage 148
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The issue of fluorine in the lead concentrate can be an issue for smelters. The level of fluorine in lead concentrates produced in laboratory tests, has been shown to be the result of small volumes of talc mineral that escape the talc pre-float circuit and will report with the lead concentrates. Talc levels and ultimately fluorine levels will be managed by optimization of the talc pre-float circuit, talc and fluorine will be effectively removed to ensure the quality of the lead concentrate. It is recommended that a value of 1,500 g/t F be used in marketing evaluations of the lead concentrate. Bismuth may also be an element that will be an issue with the lead concentrates.

 

Precious metal deportment into the lead concentrate is very high and should benefit the payable levels of precious metals at a smelter.

 

Table 10-18 provides the key features expected in the copper concentrate.

 

Table 10-18:Summary of Copper Concentrate Quality

 

   Cu   Zn   Pb   Au   Ag   As   Sb   Bi   F 
Copper Conc.  %   %   %   g/t   g/t   g/t   g/t   g/t   g/t 
Average Value   30.3*   1.6    0.70    0.8*   138*   1996    1163    175    246 
Sample Max   -    2.98    1.52    -    -    3350    1675    324    330 
Sample Min   -    0.87    0.53    -    -    102    264    115    180 

 

* Reported to be consistent with predictive balance.

 

Copper concentrates are shown to be of high quality with arsenic levels somewhat elevated, but likely below penalty levels. Sulphur levels in copper concentrates are consistent with the mineralization being chalcopyrite at approximately 30–32% sulphur.

 

Table 10-19 shows the predicted key features of the zinc concentrate.

 

Table 10-19:Summary of Zinc Concentrate Quality

 

   Zn   Cu   Pb   Au   Ag   Fe   As   Sb   Cd   Bi   F 
Zinc Conc.  %   %   %   g/t   g/t   %   g/t   g/t   g/t   g/t   g/t 
Average Val.   59.2*   1.3    0.25    0.53*   24.5*   5.47    966    115    3514    60    100 
Sample Max.   -    2.98    0.06    -    -    12.4    7000    570    4000    351    - 
Sample Min.   -    0.87    0.22    -    -    1.93    100    16    2900    11    - 

 

* Reported to be consistent with predictive balance.

 

Zinc concentrates are high grade but have elevated levels of cadmium that may incur economic penalties. Average iron content for the zinc concentrate is considered very good and further optimization of the rejection of pyrite may further reduce these reported iron levels.

  
Arctic ProjectPage 149
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

10.4Mineralogical and Metallurgical Testwork – 2021 to 2022

 

10.4.1Introduction

 

In 2021, ALS Metallurgy conducted a test program on several composites constructed in previous Arctic test programs, followed by testing on composites constructed from the drill core samples generated from the 2021 drill program. The objectives of the test program were the characterization of talc in the composites, and determination of the talc distribution to the flotation flowsheet streams. Most of the flotation testing was completed with the preflotation circuit only to establish talc performance.

 

The generation of final tails for dewatering testing by the Metso Group was completed using a flowsheet which included pre-flotation, bulk, and zinc circuits. Copper-lead separation tests were also completed using the bulk concentrate produced from the tails generation test.

 

The Metso group prepared simulations for different talc pre-flotation circuit options using the ALS Metallurgy testwork results. The models were used to simulate different scenarios and to select the best circuit configuration.

 

In 2022, ALS Metallurgy conducted testwork to investigate bulk and sequential flotation flowsheets with composites formed from two parent composites, and then select a flowsheet for a geometallurgical evaluation through testing with variability samples.

 

The 2022 metallurgical samples were selected using Cancha geometallurgy software, which has unique geostatistical functions to ensure that samples are representative and combined with visualization of drill logs improved sample selection from the Arctic deposit. This software will be utilized along with a review of the material composition and key properties to select representative samples and analyze the metallurgical test results in future testwork programs.

 

The flowsheet development testwork investigated the effect of various process conditions on copper, lead and zinc recovery using copper-lead bulk flotation and zinc flotation followed by copper and lead separation. The testwork demonstrated that the mineralization was amenable to either a bulk flowsheet followed by copper-lead separation, or a sequential flowsheet, both following a pre-flotation stage to remove talc. In addition, Jameson cell cleaner flotation tests were conducted on a single parent composite to provide data to support the sizing and selection of the Jameson cell technology.

 

SGS conducted SAG Power Index (SPI®) testing on 15 samples to expand the comminution dataset and investigate the impact of friable ore types on the plant throughput.

 

Based on economic analysis comparing the bulk and sequential circuit, the bulk circuit flowsheet was selected for the variability testing. Many of the variability samples measured much higher copper, lead, and/or zinc feed grades than the composites tested in the flowsheet development phase. The variability sample selection were not intended to reflect sequences of the mine plan, but instead to represent discrete lithology types from which the results of the flotation testing would be used as inputs for recovery and grade models for the deposit.

 

Ore characterization and process mineralogical examination was conducted on all the flowsheet development and variability samples. The talc content was considered during sample selection to avoid mis-representing the talc content of future samples.

  
Arctic ProjectPage 150
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

10.4.2Test Samples

 

The pre-flotation flow sheet development test program was carried out on a number of composites constructed in previous Arctic test programs, followed by testing on composites constructed with drill core samples received under this test program.

 

Table 10-20 summarizes the assay results for the composites constructed in previous Arctic test programs KM5000 and KM5718, as well as the composites formed in this metallurgical test program.

 

Table 10-20:ALS Head Grades – Pre-Flotation Samples – 2021

 

   Chemical Content 
Composite  Cu (%)    Pb (%)    Zn (%)    Fe (%)    S (%)    Ag (g/t)    Au (g/t)    Mg (%) 
Composite 13 (KM5000)   1.98    0.30    1.48    6.20    6.25    38    0.26    9.14 
PP Composite 1 (KM5000)   2.92    0.86    4.66    10.8    13.8    41    0.56    5.78 
Zone 5 (KM5718)   2.45    1.35    5.59    15.9    22.7    67    1.24    0.61 
Zone 3-5 (KM5718)   4.14    1.55    7.80    16.5    24.0    86    0.99    2.58 
Master Composite 1B (KM5718)   3.16    1.12    5.52    14.0    16.6    48    0.58    5.22 
Constructed under KM6442
Master Composite 2   3.67    1.30    6.50    12.9    19.1    65    0.84    4.15 
HT 1   4.40    0.80    4.79    10.2    14.0    42    0.12    8.54 
HS 2   0.91    0.07    0.38    5.0    3.51    5    0.03    3.57 
HT 2   0.25    0.04    0.39    1.8    0.67    3    0.01    9.11 
FT 1   2.11    0.60    2.72    7.3    9.19    36    0.63    4.28 

 

Initially, two parent composites were constructed for the flowsheet development testing: the Mineralized Composite and Talc Composite. The Mineralized Composite contained about 1.5% talc, while the Talc Composite contained about 55% talc. From these two composites, a range of blends were constructed to generate samples of various talc grades for testing.

 

Table 10-21 summarizes the flow sheet development blends and their calculated talc content.

 

Table 10-21:ALS Flowsheet Development Head Composites – 2021

 

   Proportion of Composite    
Blend Composite  Mineralized Composite   Talc Composite   Talc Content (%) 
Very Low Talc   97    3    3.2 
Low Talc   93    7    5.1 
Average Talc   90    10    6.9 
High Talc   87    13    8.7 

  
Arctic ProjectPage 151
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

   Proportion of Composite     
Blend Composite  Mineralized Composite   Talc Composite   Talc Content (%) 
Very High Talc   83    17    10.5 
11% Talc   82    18    11.4 
15% Talc   74    26    15.5 

 

As would be expected, head assays measured for each of the blend composites were relative to the proportions of each of the two parent composites. A summary of key head assays for each blend is shown in Table 10-22.

 

The Talc Composite contained lower metal contents of Cu, Pb, Zn, Ag and Au, as compared to the mineralized (Pure Min) composite. As a result, samples with increased talc content were also of lower head grade, both of which would be expected to lead to poorer metallurgical response.

 

Some sulphate minerals, as well as organic carbon, were measured in the Pure Min Composite; both were almost negligible in the Talc Composite. The presence of sulphate minerals indicates that a portion of the total sulphur likely would not be recovered via sulphide flotation. Organic carbon, like talc, is usually naturally hydrophobic, so it would be expected to report to the pre-flotation concentrate with the talc.

 

Table 10-22: ALS Flowsheet Development Composites Head Assays – 2021

 

   Chemical Content 
Composite  Cu (%)    Pb (%)    Zn (%)    Fe (%)    S (%)    S(s) (%)   S(SO4) (%)    Ag (g/t)    Au (g/t)    C (%)    TOC    Mg (%) 
Pure min   2.31    0.84    3.57    8.0    10.9    9.82    1.03    39    0.47    0.59    0.14    3.12 
V. Low Talc   2.12    0.78    3.20    7.7    10.2              34    0.47              3.61 
Low Talc   2.17    0.78    3.21    7.6    10.2              35    0.42              4.05 
Avg Talc   2.15    0.75    3.09    7.2    9.54              35    0.42              4.52 
High Talc   2.11    0.76    3.07    7.1    9.44              36    0.44              4.91 
V. High Talc   1.97    0.67    2.78    6.6    8.49              32    0.42              5.30 
11% Talc   1.98    0.66    2.73    6.6    8.74              33    0.32              5.49 
15% Talc   1.81    0.60    2.56    6.1    8.14              32    0.40              6.16 
Pure Talc   0.93    0.09    0.55    2.0    1.51    1.49    0.03    14    0.25    0.43    0.04    15.7 

 

The drill holes from the most recent 2021 Arctic exploration drilling program assessed to construct geometallurgical samples. The length of the geometallurgical sample was taken as short as possible to ensure that the mineralogy and lithology rock texture was consistent throughput the sample.

 

The 2022 variability test program used a total of 34 geometallurgical samples constructed from 11 drill holes and are summarized in Table 10-23. The drill cores were stored in a freezer to ensure sample degradation and oxidation of sulphide minerals did not occur.

  
Arctic ProjectPage 152
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 10-23: ALS Variability Sample Details – 2022

 

Sample ID  Drill Hole  From   To   Length (m)   Zone   Lithology 
ARC-003  AR21-0174   86.9    92.1    5.2    Zone 5    MS 
ARC-004  AR21-0174   92.9    95.1    2.2    Zone 5    MS 
ARC-005  AR21-0176   128    129.4    1.4    Zone 4    SMS 
ARC-006  AR21-0176   129.4    134.4    5    Zone 4    ChTS 
ARC-007  AR21-0176   134.4    138.3    3.9    Zone 3    MS 
ARC-008  AR21-0176   138.3    147.9    9.6    Zone 3    MS 
ARC-010  AR21-0176   165.6    168.7    3.1    Zone 1    QMS 
ARC-017  AR21-0177   94.6    99.8    5.2    Zone 5    GS 
ARC-024  AR21-0182   126.6    127.7    1.1    Zone 5    MS 
ARC-025  AR21-0182   127.7    130.9    3.2    Zone 5    ChTS 
ARC-039  AR21-0182   158.6    162.4    3.8    Zone 3    MS 
ARC-044  AR21-0182   176.3    178.6    2.3    Zone 3    SMS 
ARC-050  AR21-0182   205.1    210.2    5.1    Zone 1    SMS 
ARC-051  AR21-0185   123.5    125.4    1.9    Zone 5    MS 
ARC-052  AR21-0187   85.2    89.7    4.5    Zone 5    MS 
ARC-054  AR21-0181   119.7    121.8    2.1    Zone 5    SMS 
ARC-055  AR21-0181   131.7    134.6    2.9    Zone 4    SMS 
ARC-056  AR21-0181   134.6    136.9    2.3    Zone 4    MS 
ARC-057  AR21-0181   136.9    140.4    3.5    Zone 4    TS 
ARC-058  AR21-0181   140.4    144.8    4.4    Zone 4    MS 
ARC-059  AR21-0181   147.8    149.4    1.6    Zone 4    SMS 
ARC-062  AR21-0181   159.8    163.9    4.1    Zone 3    MS 
ARC-063  AR21-0181   168.3    169.7    1.4    Zone 3    SMS 
ARC-064  AR21-0181   169.7    173.1    3.4    Zone 3    TS 
ARC-068  AR21-0181   177.1    180.4    3.3    Zone 3    SMS 
ARC-069  AR21-0181   187.1    191.1    4    Zone 2    MS 
ARC-072  AR21-0181   203.3    209.1    5.8    Zone 1    MS 
ARC-080  AR21-0184   136.3    139.3    3    Zone 5    QMS 
ARC-084  AR21-0188   222    224.4    2.4    Zone 2    MS 
ARC-086  AR21-0190   141.9    145.1    3.2    Zone 4    SMS 
ARC-087  AR21-0190   145.1    148.7    3.6    Zone 4    MS 
ARC-092  AR21-0190   186.8    189.1    2.3    Zone 2.5    MS 

  
Arctic ProjectPage 153
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Sample ID  Drill Hole  From   To   Length (m)   Zone   Lithology 
ARC-098  AR21-0190   217.9    221.2    3.3    Zone 1    CHS 
ARC-099  AR21-0189   50.4    61.54    11.14    Zone 5    MS 

 

The head grades of the composites from the 2022 ALS variability testwork program are shown in Table 10-24.

 

Many of the variability samples measured much higher copper, lead, and/or zinc feed grades than the composites tested in the flowsheet development phase. The Variability sample selection were not intended to reflect sequences of the mine plan, but instead to represent discrete lithology types from which the results of the flotation testing would be used as inputs for recovery and grade models for the deposit.

 

Table 10-24:ALS Variability Samples Head Assays – 2022

 

   Chemical Content 
Sample ID    Cu (%)    Pb (%)    Zn (%)    Fe (%)    S (%)    Ag (g/t)    Au (g/t)    Sb (g/t)    Barite (%)    Talc (%) 
ARC-003    6.4    2.3    10.0    11.8    24.2    81    1.03    309    33.4    0.1 
ARC-004    6.1    2.0    8.9    15.1    23.9    61    0.53    85    6.1    0.1 
ARC-005    8.1    1.0    4.3    7.2    12.4    127    0.99    315    9.0    11.9 
ARC-006    1.1    0.1    0.1    1.9    1.6    18    0.38    149    0.1    71.3 
ARC-007    5.9    2.5    12.2    14.4    29.1    140    1.33    450    16.0    2.7 
ARC-008    8.9    2.3    9.5    17.4    26.6    120    1.52    445    18.4    0.1 
ARC-010    1.5    1.3    8.2    5.5    8.4    22    0.07    13    0.1    12.6 
ARC-017    0.6    0.1    0.2    4.6    4.8    4    0.16    44    0.1    0.1 
ARC-024    8.6    2.5    13.8    14.7    28.0    133    1.21    57    9.4    2.6 
ARC-025    0.8    0.2    0.3    2.2    1.5    11    0.24    114    0.1    54.0 
ARC-039    4.6    3.7    14.1    19.4    27.6    110    1.48    648    0.1    0.1 
ARC-044    1.8    0.1    0.1    4.9    5.2    18    0.20    82    0.1    0.2 
ARC-050    3.1    0.2    1.0    9.5    8.8    36    0.38    54    0.1    0.5 
ARC-051    3.7    2.3    13.2    15.8    30.6    70    0.52    31    23.8    0.5 
ARC-052    8.5    2.2    13.0    16.7    28.1    120    1.11    227    7.6    0.8 
ARC-054    4.7    1.3    5.9    14.4    23.0    89    0.34    129    21.2    1.1 
ARC-055    2.8    0.8    6.3    10.3    15.2    67    0.43    23    0.1    21.4 
ARC-056    7.4    0.8    7.2    18.5    25.5    109    0.85    198    0.1    7.9 
ARC-057    1.0    0.1    0.2    2.9    1.8    7    0.07    4    0.1    37.2 
ARC-058    6.0    2.4    13.6    19.6    31.0    110    1.31    412    7.9    0.5 
ARC-059    5.3    0.6    6.6    9.3    13.2    70    0.53    14    0.1    12.6 

  
Arctic ProjectPage 154
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

   Chemical Content – percent or g/tonne 
Sample ID    Cu (%)    Pb (%)    Zn (%)    Fe (%)    S (%)    Ag (g/t)    Au (g/t)    Sb (g/t)    Barite (%)    Talc (%) 
ARC-062    2.2    6.5    17.7    10.2    20.6    55    0.28    95    0.4    1.1 
ARC-063    4.0    0.1    2.1    7.3    8.3    13    0.13    4    0.2    38.8 
ARC-064    0.7    0.0    0.4    1.7    1.3    2    0.02    1    0.1    67.1 
ARC-068    2.3    0.1    1.2    7.1    6.4    22    0.16    140    0.1    0.3 
ARC-069    2.9    1.3    9.2    12.6    23.2    55    0.12    40    19.3    7.6 
ARC-072    4.8    0.5    9.0    18.2    24.8    114    1.14    102    0.1    1.8 
ARC-080    1.2    0.1    0.2    2.6    2.7    22    0.34    82    0.1    3.7 
ARC-084    2.4    0.4    5.3    16.1    24.3    29    0.29    9    0.1    1.6 
ARC-086    3.8    1.0    7.0    11.1    21.4    89    1.60    937    51.3    0.3 
ARC-087    10.3    4.2    13.7    12.5    24.3    171    3.36    578    6.0    0.8 
ARC-092    3.9    0.1    5.1    20.2    31.0    22    0.31    44    0.1    3.2 
ARC-098    1.0    0.0    0.1    2.9    1.5    25    0.06    2    0.1    0.7 
ARC-099    5.8    2.3    11.4    12.6    22.3    92    0.33    57    11.2    0.9 

 

Head characterization was completed by ALS Geochemistry North Vancouver on all 34 variability samples including whole rock analysis by fusion and XRF, and multi-element determinations by ICP, ion chromatography, and Bulk Mineral Analysis with Liberation estimation (BMAL).

 

A total 29 samples were submitted for open circuit flotation tests and nine samples were used in locked cycle flotation tests. Eight samples produced sufficient bulk concentrate mass to undertake copper-lead separation testing.

 

Comminution testing was completed only on selected variability samples to extend the historical testwork dataset which included Bond ball mill work index tests and SPI tests. A Bond rod mill work index and Bond Abrasion test was completed with only three of the variability samples.

 

Shown in Figure 10 4 are the copper and lead grades of the ALS Metallurgy testwork samples compared to the designed plant feed grades. The pre-flotation samples are more representative of the expected mine production due to the lower range of copper and lead grades that are available. There is a strong correlation between copper and zinc grades within the pre-flotation samples. The metallurgical balance shown in Table 10-1 is based on LOM feed grades and is consistent with the LOM data point shown in Figure 10 4.

 

Shown in Figure 10 5 are the copper and zinc grades of the various test samples used in the ALS Metallurgy test program. There is a consistent copper to zinc ratio of approximately 3.5–4.5 within the test samples and the LOM grades are shown to be within the distribution of test samples.

  
Arctic ProjectPage 155
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 10-4: Cu and Pb Test Sample Grades for ALS Metallurgy Test Program

 

 

Source: Ausenco, 2022

 

Figure 10-5: Cu and Zn Test Sample Grades for ALS Metallurgy Test Program

 

 

Source: Ausenco, 2022

  
Arctic ProjectPage 156
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

10.4.3Mineralogical Investigations

 

10.4.3.1Talc Optimization Samples

 

The mineral content and elemental deportment of the composites tested in the metallurgical test program were measured by QEMSCAN using Bulk Mineral Analysis (BMA) protocols as well as by semi-quantitative X-Ray Diffraction (XRD). A summary of the mineral content mineral content is presented in Figure 10 6.

 

The talc content varied widely between the composites. Highest talc content at about 21% was measured for the HT1 (High Talc) sample. A second sample HT2, received with the intention of blending as a high talc sample, measured only about 3% as talc and 47% as chlorite by QEMSCAN and was not utilized for testing in this study. The Master Composite 2, which had been prepared using the KM5718 Master Composite 1B and Zone 3-5 Composite, measured about 8% talc, and the FT1 composite which was utilized to generate a talc pre-flotation concentrates and zinc circuit tails for dewatering testwork measured about 14% talc.

 

Magnesium was distributed amongst a number of minerals for the Arctic deposit which included primarily talc, micas, chlorite, and calcium carbonate minerals dolomite and ankerite. The distribution of magnesium to these minerals varied widely between the composites, so magnesium assays on flotation test products would not accurately reflect talc recoveries.

 

To improve the estimate of talc in the deposit a talc predictive algorithm has been developed by South32. The talc algorithm includes aluminium, calcium, potassium, and magnesium to improve the predictability of talc. The predicted talc assay form each of the individual variability composites were compared with the mineralogical analysis of the head sample. The predictive talc algorithm aligned well with the measured talc content. Understanding that the blending of composites reduces the predictability of the talc in the plant feed, the Arctic Project has considered incorporating the predicted talc and metallurgical performance on each of the mine blocks and then weighing the overall metallurgical performance. Future testwork will investigate blends to validate this approach.

 

Copper was contained primarily as chalcopyrite, although low percentages of bornite, tennantite/enargite, covellite, chalcocite, and bornite were also measured.

  
Arctic ProjectPage 157
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 10-6: Talc Optimization Composites Mineral Content

 

 

Source: ALS Metallurgy, 2021.

 

10.4.3.2Flow Sheet Development Samples

 

Particle Mineral Analysis (PMA) and XRD were conducted on each the Pure Min and Talc Composites. The semi-qualitative XRD data confirmed non-sulphide gangue mineral contents reported in the Particle Mineral Analyses. A summary of pertinent mineral content data is shown in Figure 10 7.

  
Arctic ProjectPage 158
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 10-7: Parent Composite Mineral Content

 

 

Source: ALS Metallurgy, 2021

 

As expected, based on the head assays, the sulphide mineral content for the Pure Min Composite was significantly higher than the Talc Composite. Conversely, the Talc Composite contained very high talc content, about 55%, while the Pure Min Composite only measured about 1.5% talc.

 

Copper was measured mostly in the form of chalcopyrite. However, between around 2 and 8% of the copper was in copper arsenic sulphosalts (enargite/tennantite /tetrahedrite group minerals). These copper arsenic sulphosalts are typically recovered by flotation in a similar manner to other copper sulphide minerals. On this basis, elevated arsenic and/or antimony levels in the copper concentrate would be expected.

  
Arctic ProjectPage 159
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Only a small portion of the magnesium in the Pure Min Composite was present in talc and most of the magnesium was measured as chlorite. In the Talc Composite, just over 70% of the magnesium was measured within talc, with chlorite being the main other magnesium bearing mineral. Mica minerals also contributed a lesser, but still significant component of the magnesium in both composites (7 to 21%). Given the presence of magnesium in minerals other than talc, magnesium is likely not a useful proxy for quantifying talc content across the deposit.

 

Sulphur was measured mostly as sulphide minerals in both samples. However, in the Pure Min Composite, around 11% was measured as sulphate minerals (i.e., barite, calcium sulphate, and jarosite).

 

Spectra collected on the sphalerite in the Pure Min and High Talc parent composites measured between 4 and 5 percent iron within the mineral matrix. The iron content within the zinc concentrates produced from the blend composites would be expected to therefore be at least 4%.

 

10.4.3.3Variability Samples

 

A Bulk Mineral Analysis with Liberation estimation (BMAL) by QEMSCAN was conducted at ALS Metallurgy on each of the variability samples to provide mineral composition and estimates of liberation for key sulphide minerals. A summary of the mineral content data is presented in Figure 10 8.

 

Talc content varied widely between the samples, ranging from less than detection limits to as high as about 71% for ARC-006. The average talc content for the variability samples was about 12% which is four times the LOM talc content of 3%. MgO contents, measured by XRF or whole rock analysis, could be used to make a preliminary estimate of talc content, despite magnesium being contained in minerals other than talc. Samples high in MgO but low in talc could be identified based on higher Al2O3 content greater than 10%. Since talc does not contain aluminium, higher Al2O3 content indicates the presence of other potentially magnesium bearing minerals in important concentrations. X-ray spectra collected from talc from the Pure Min and Talc composites did not identify fluorine within the mineral structure. However, based on a trend between fluorine and talc content, it is possible that there is fluorine within talc at low concentrations.

 

Copper was measured predominantly in the form of chalcopyrite. Copper as copper arsenic sulphosalts enargite/tennantite, and tetrahedrite averaged about 3% and measured as high as 14% for ARC-086. Elevated arsenic and/or antimony levels in the copper concentrate would be expected for feeds with higher percentages of copper in these forms.

 

Magnesium in the variability samples was measured primarily within talc, chlorite, and micas. For ARC-050, about one half of the magnesium was associated with amphibole/pyroxenes and magnesite/siderite. A summary of the magnesium deportment is shown in Figure 10-8. Sulphur was measured mostly as sulphide minerals chalcopyrite, sphalerite, pyrite, and galena. About 51% of the feed mass was measured as barite for ARC-086, and about 33% as barite for ARC-003. Barite would be unlikely to be recovered via sulphide flotation techniques.

  
Arctic ProjectPage 160
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 10-8: Mineral Modal Abundance for Variability Samples

 

 

Source: ALS Metallurgy, 2022

 

Liberations were estimated by QEMSCAN BMAL protocols using sub-samples of grind calibrations for each of the variability samples. The analysis was completed over a wide range of primary grind sizes between 50 and 137µm K80 due to the manner in which the grind calibrations were completed. An initial grind calibration targeting 65µm K80 was completed at 18 minutes for variability samples which measured lower talc content, and at 23 minutes for the samples which measured high talc content. A second grind calibration at 30 or 35 minutes was included for a few samples where sizing’s measured greater than 100µm K80.

 

Copper sulphide mineral liberations, estimated from the QEMCSAN BMAL, averaged about 68% for the variability samples which would be considered moderate to adequate for expected copper recovery in the bulk roughers. About 8% of the copper sulphide minerals on average were estimated to be in binary form with either sphalerite or pyrite, with about 10% of the copper sulphides in binary form with non-sulphide gangue.

  
Arctic ProjectPage 161
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

An average galena liberation off 55% was estimated, but an additional 11% of the galena was estimated to be in binary form with copper sulphides which would also be recoverable in the bulk roughers, and as such the galena liberation would also be considered acceptable for good lead recovery in the bulk roughers. About 11% of the galena was estimated to be in binary form with sphalerite.

  

Average sphalerite liberation was estimated to be 72%. This would be expected to lead to high zinc recovery in the zinc roughers. About 9% of the sphalerite, on average, was estimated to be in binary form with copper sulphide minerals which could be potentially recovered in the bulk roughers, but a percentage of this sphalerite could be returned to the zinc roughers after bulk circuit regrinding.

  

10.4.4Comminution Testwork

 

Comminution testing included Bond ball mill work index tests and SPI tests on several samples; a Bond rod mill work index and Bond Abrasion test was completed with only three of the variability samples.

 

ALS Metallurgy completed Bond ball mill work index tests (BWi) on one set of variability samples with a 150-mesh Tyler closing screen (106µm), and for a second set of samples with a 48-mesh Tyler screen (300µm). Several the samples selected for the Bond work index tests completed with the coarser closing screen measured high talc content (ARC-006, ARC-025, ARC-057, and ARC-064). All variability samples selected for Bond ball mill work index testing with the 150-mesh Tyler screen measured low talc content of 1% or less, except for the ARC-069 composite which measured about 8% talc.

  

The highest Bond ball mill work index recorded for those samples tested was about 21 kWh/t, at the coarser screen sizing, for ARC-006 which measured about 71% talc. The high Bond ball mill work index is likely a result of the resistance to breakage of the talc particles which has been observed in previous test programs with Arctic composites. A Bond ball mill work index of less than 12 kWh/t was measured for most of the variability samples tested which would indicate material that was soft in terms of ball milling.

  

Abrasion test results for the three variability samples submitted for testing ranged between 0.01 and 0.05, which would be considered mildly abrasive.

 

Table 10-25 summarizes the bond work comminution test results.

 

Table 10-25: Bond Ball Mill Work Index and Abrasion Index Test Results

 

    Bond Ball Wi      
Sample ID  

@ 300µm

kWh/t

 

@ 106µm

kWh/t

 

@ 1180µm

kWh/t

  Bond Abrasion  
ARC-006   20.8   -   -   -  
ARC-008   -   8.2   -   -  
ARC-017   9.8   -   11.3   0.049  
ARC-025   11.4   -   -   -  
ARC-039   -   8.6   -   -  
ARC-044   -   17.7   -   -  
ARC-050   -   11.8   -   -  
ARC-052   -   9.0   -   -  

  
Arctic ProjectPage 162
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

    Bond Ball Wi      
Sample ID   @ 300µm
kWh/t
  @ 106µm
kWh/t
  @ 1180µm
kWh/t
  Bond Abrasion  
ARC-057   10.3   -   -   -  
ARC-058   -   8.1   -   -  
ARC-062   -   13.1   -   -  
ARC-064   14.7   -   -   -  
ARC-069   -   8.2   -   -  
ARC-072   -   9.1   6.4   0.034  
ARC-099   5.9   -   4.8   0.014  

  

ALS Metallurgy, in conjunction with SGS Lakefield (SGS) conducted SPI tests on 15 selected variability samples during the testwork program in 2022. The SPI test is considered more reliable when estimating specific energy of soft ores.

 

The SPI data show most materials to be very soft in terms of SAG milling characteristics. Test results are provided in Table 10-26.

 

Table 10-26: Summary of SPI Test Results

 

Sample  

SPI 

(min)

 

Hardness

Percentile

  Category  
ARC-017   35.2   15   Soft  
ARC-025   12.8   3   Very Soft  
ARC-044   25.3   8   Very Soft  
ARC-050   19.5   5   Very Soft  
ARC-056   14.0   3   Very Soft  
ARC-057   13.8   3   Very Soft  
ARC-058   10.4   2   Very Soft  
ARC-062   12.5   3   Very Soft  
ARC-063   13.5   3   Very Soft  
ARC-064   5.5   1   Very Soft  
ARC-069   8.2   1   Very Soft  
ARC-072   12.2   3   Very Soft  
ARC-086   5.9   1   Very Soft  
ARC-087   10.7   2   Very Soft  
ARC-099   9.8   2   Very Soft  
Minimum Value   5.5       
Maximum Value   35.2  -    
Average Value   14.0       

  
Arctic ProjectPage 163
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

10.4.5Flotation Testwork

 

10.4.5.1Talc Optimization Testwork

 

Initial testing was completed on composites which had been retained in storage from previous Arctic test programs KM5000 and KM5718 with a flowsheet including pre-flotation rougher and cleaner stages. Table 10-27 summaries the baseline pre-flotation test results.

 

The results of these tests indicated similar pre-flotation circuit performance compared to results from the previous metallurgical test programs. One substantial difference noted was the extremely negative redox potentials measured in the pre-flotation rougher stage recorded for the tests in this program, although this did not appear to affect pre-flotation rougher performance in terms of mass recovery and metals losses to the pre-flotation concentrate.

 

Table 10-27: Summary of Baseline Pre-Flotation Tests

 

Test  

Original Tests

Distribution (%)

 

Current Tests

Distribution (%)

 
  Cu   Pb   Zn   Au   Ag   Cu   Pb   Zn   Au   Ag  
Composite 13 (KM5000)   3.3   3.7   3.0   4.3   4.0   2.7   4.4   2.9   1.3   3.4  
PP Composite 1 (KM5000)   1.0   1.1   0.3   2.4   0.3   1.3   5.1   1.2   1.3   3.3  
Zone 5 (KM5718)   0.4   0.7   0.2   0.3   0.6   0.4   0.7   0.2   0.3   0.6  
Zone 3-5 (KM5718)   0.3   0.9   0.3   1.4   0.8   0.4   0.8   0.4   0.6   0.8  
Composite 1B (KM5718)   1.4   4.8   1.3   1.0   3.7   1.6   3.4   1.6   3.2   2.4  

 

Notes: Values reflect recoveries to pre-flotation rougher for Composite 13, Zone 5, and PP Comp 1, and to pre-flotation cleaner concentrate for Master Composite 1B and Zone 3-5 composite

 

The Master Composite 2 was subjected to a series of eight pre-flotation was conducted which included two stages of cleaners was carried out using a variable screening test matrix. In these tests, whole rock and QEMSCAN mineralogical analyses were completed on the test products. High talc recoveries between 95 and 98% were recorded in all tests, but lower metal losses were recorded at a coarser primary grind sizing.

 

High grade talc concentrates ranging between 88 and 92% talc were measured for all variable screening tests after two cleaner stages. The percentage of the feed talc recovered to the pre-flotation cleaner concentrate varied widely between 61 and 92% and correlated with mass recovery. A total MIBC frother dosage between 55 and 77 g/ton appeared to be required to ensure a stable flotation froth and therefore high mass and talc recoveries. Copper, lead, zinc, and silver recoveries to the pre-flotation cleaner concentrate ranged between 0.5 and 1.0% indicating good rejection from the rougher concentrate by dilution cleaning with potential for recovery in the downstream sulphide flotation circuits Kinetic pre-flotation rougher and cleaner tests were completed with Master Composite 2 to provide flotation kinetic data for modelling by an external laboratory. A high-grade copper concentrate which measured between 22 and 24% copper was recovered to the final pre-flotation rougher concentrate following 8 minutes of initial rougher residence time; these tests were characterized by highly negative redox values in the initial pre-flotation rougher stages which increased to positive values by the final pre-flotation rougher stage.

 

  
Arctic ProjectPage 164
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Kinetic pre-flotation rougher and cleaner tests were completed with Master Composite 2 to provide flotation kinetic data for modelling by Metso Group. A high-grade copper concentrate which measured between 22 and 24% copper was recovered to the final pre-flotation rougher concentrate following 8 minutes of initial rougher residence time; these tests were characterized by highly negative redox values in the initial pre-flotation rougher stages which increased to positive values by the final pre-flotation rougher stage.

 

A 64-kilogram test was carried out in locked-cycle fashion using a bulk flotation flowsheet to generate pre-flotation concentrate and bulk final tails for dewatering and tailing consolidation tests by external laboratories. The bulk concentrate produced from the test was used for copper-lead separation tests using sodium cyanide to depress the copper sulphide minerals.

 

Test results indicated that on average, 93% of the copper was recovered to the lead rougher tails, and about 86% of the lead was recovered to the lead rougher concentrate. Lead losses were very high to the lead cleaner tails, and the flowsheet was more effective recovering talc to the lead cleaner concentrate. As a reverse flotation flowsheet with combined 3rd and 4th lead cleaner tails, about 56% of the lead and 30% of the silver was recovered to a lead concentrate with a calculated grade of about 58% lead and 0.2% silver.

  

10.4.5.2Flowsheet Development Testwork

 

The objective of the program was to investigate bulk and sequential flotation flowsheets with composites formed from two parent composites, and then select a flowsheet for a geometallurgical evaluation through testing with variability samples.

 

The mineralization was amenable to either a bulk flowsheet followed by copper-lead separation, or a sequential flowsheet, both following a pre-flotation stage to remove talc. Table 10-28 shows average performance obtained for the Avg Talc Composite in the Flowsheet Development phase of the testing.

 

Table 10-28: Comparison of Bulk vs. Sequential Locked-Cycle Test Results – ALS 2021

 

Composite   Assays   Distribution (%)  
  Cu
(%)
  Pb
(%)
  Zn
(%)
  Ag
(g/t)
  Au
(g/t)
  Mg
(%)
  Cu   Pb   Zn   Ag   Au  
                                             
Avg Talc Bulk  
Copper concentrate   28.0   0.86   4.27   181   4.17   0.46   87.3   8.3   9.1   36.0   60.9  
Lead concentrate   7.90   39.0   6.30   1124   4.75   1.23   5.1   78.1   2.8   46.0   14.3  
Zinc concentrate   0.87   0.38   55.9   41   0.35   0.04   1.9   2.6   83.3   5.7   3.5  
Avg Talc - Sequential  
Copper concentrate   27.6   0.87   2.05   168   3.23   1.96   90.2   8.9   4.7   34.9   48.7  
Lead concentrate   2.72   49.3   9.71   1360   5.31   1.40   1.2   69.9   3.1   39.4   11.2  

  
Arctic ProjectPage 165
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Composite   Assays   Distribution (%)  
  Cu
(%)
  Pb
(%)
  Zn
(%)
  Ag
(g/t)
  Au
(g/t)
  Mg
(%)
  Cu   Pb   Zn   Ag   Au  
Zinc concentrate   0.98   1.09   54.5   47   0.77   0.17   2.1   7.3   83.5   6.5   7.7  

 

Copper recovery to the copper concentrate was slightly higher for the sequential flowsheet; however, gold recovery to the copper concentrate was substantially lower. The lead concentrate grade for the Avg Talc composite could likely be improved over that shown in Table 10-28 with optimization of copper-lead separation conditions given the higher lead concentrate grade measured with other composites.

 

Zinc circuit performance was similar for the two flowsheets, although higher zinc recovery to the copper concentrate was recorded for the bulk circuit. Magnesium content in the copper concentrate was higher for the sequential circuit, but similar in the lead concentrate for both circuits.

 

10.4.5.3Variability Testwork

 

Based on economic analysis comparing the bulk and sequential circuit, the bulk circuit flowsheet was selected for the Variability testing. A total of 28 variability samples were selected for flotation testing which included open circuit cleaner tests, and 9 of these variability samples were selected for locked-cycle testing. Table 10-29 shows performance obtained for Variability testwork phase of the testing.

 

Most of the variability samples responded well to the developed bulk circuit flowsheet, when adjustments to dosages were made to account for variations in head grades. In the cleaner tests with the bulk flowsheet, an average of 88% of the copper and 76% of the lead was recovered to the bulk concentrate. Average zinc recovery was about 78% to a zinc concentrate which averaged 57% zinc. High zinc rougher recoveries were recorded when the copper sulphate addition in the conditioner stage was ratioed to the zinc feed grade at 100 g/t to 1% feed grade. Further optimization of copper sulphate additions might be possible with additional testing.

  

The variability test phase culminated with locked-cycle testing of 9 variability samples to determine closed-circuit performance. On average, about 93% of the copper and 84% of the lead was recovered to the bulk concentrate which measured 25% copper and 10% lead, on average. Good zinc performance was recorded in these tests with an average zinc recovery of 90% to a zinc concentrate which averaged 55% zinc. Most of the gold and silver was recovered to the bulk concentrate, averaging 74% and 84%, respectively.

 

   

  
Arctic ProjectPage 166
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 10-29: Summary of Variability Open Circuit Flotation Test Results – ALS 2022

 

Test   Product   Regrind Size
80% Passing
  Weight
(%)
  Assays   Distribution (%)  
Cu
(%)
  Pb
(%)
  Zn
(%)
  Au
(g/t)
  Ag
(g/t)
  S
(%)
  Cu   Pb   Zn   Au   Ag   S  

ARC-004

Test 64

  Talc Concentrate  

Flotation Feed: 68 µm;

Cu/Pb Rougher Concentrate: 38 µm;
Zn Rougher Concentrate: 20 µm

  -   -   -   -   -   -   -   -   -   -   -   -   -  
Cu/Pb Cleaner 2 Conc.   20.3   26.0   8.5   7.6   1.85   224   31.9   89.0   79.7   18.3   80.6   75.9   27.0  
Zn Cleaner 2 Concentrate   2.2   1.7   1.0   58.0   0.27   40   32.6   0.6   1.0   15.4   1.3   1.5   3.0  
Zn Cleaner 1 Sc. Tailings   0.9   5.0   2.4   14.6   0.51   106   20.4   0.7   1.0   1.5   1.0   1.5   0.7  
Zn Rougher Tailings   72.4   0.3   0.3   6.1   0.06   8   21.1   3.5   10.4   52.3   9.3   9.5   63.7  
Feed   100.0   5.9   2.2   8.4   0.47   60   24.0   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-007
Test 71
  Talc Concentrate   Flotation Feed: 64 µm;
Cu/Pb Rougher Concentrate: 47 µm;
Zn Rougher Concentrate: 55 µm
  4.6   0.3   0.4   0.5   0.07   16   1.2   0.3   0.6   0.2   0.2   0.5   0.2  
Cu/Pb Cleaner 2 Conc.   19.0   25.9   12.6   3.2   5.63   506   30.9   85.9   89.1   4.8   76.8   69.3   20.0  
Zn Cleaner 2 Concentrate   17.2   0.7   0.2   63.8   0.30   38   33.6   2.0   1.3   85.5   3.7   4.7   19.6  
Zn Cleaner 1 Sc. Tailings   14.6   1.4   0.3   1.4   0.66   91   48.9   3.4   1.7   1.6   6.9   9.6   24.2  
Zn Rougher Tailings   40.0   0.4   0.2   0.5   0.21   12   22.4   2.5   3.4   1.4   6.0   3.5   30.4  
Feed   100.0   5.7   2.7   12.8   1.39   139   29.5   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-008
Test 79
  Talc Concentrate   Flotation Feed: 64 µm;
Cu/Pb Rougher Concentrate: 41 µm;
Zn Rougher Concentrate: 35 µm
  -   -   -   -   -   -   -   -   -   -   -   -   -  
Cu/Pb Cleaner 2 Conc.   28.4   29.4   7.4   2.1   4.42   356   32.4   91.3   90.6   6.0   72.7   81.7   34.3  
Zn Cleaner 2 Concentrate   12.9   0.9   0.3   60.9   0.44   38   33.1   1.2   1.6   80.4   3.3   4.0   15.9  
Zn Cleaner 1 Sc. Tailings   3.0   2.9   0.5   5.6   4.55   121   34.6   1.0   0.6   1.7   7.9   2.9   3.9  
Zn Rougher Tailings   51.6   0.5   0.2   0.4   0.33   10   21.4   2.9   3.6   2.0   9.8   4.2   41.1  
Feed   100.0   9.2   2.3   9.8   1.73   124   26.9   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-024
Test 89
  Talc Concentrate   Flotation Feed: 60 µm;
Cu/Pb Rougher Concentrate: 44 µm;
Zn Rougher Concentrate: 45 µm
  3.3   0.5   0.5   0.6   2.81   24   1.7   0.2   0.5   0.1   7.1   0.6   0.2  
Cu/Pb Cleaner 2 Conc.   27.7   27.1   9.3   1.8   3.36   410   32.6   90.1   91.8   3.5   70.6   81.6   31.1  
Zn Cleaner 2 Concentrate   20.0   0.7   0.2   61.8   0.29   40   33.7   1.8   1.6   86.6   4.4   5.8   23.3  
Zn Cleaner 1 Sc. Tailings   4.5   2.1   0.4   3.3   1.10   49   45.0   1.1   0.7   1.0   3.8   1.6   7.1  
Zn Rougher Tailings   39.7   0.6   0.2   0.7   0.27   13   23.6   2.6   2.4   1.9   8.1   3.7   32.4  
Feed   100.0   8.3   2.8   14.3   1.32   139   28.9   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-039
Test 111
  Talc Concentrate   Flotation Feed: 75 µm;
Cu/Pb Rougher Concentrate: 45 µm;
Zn Rougher Concentrate: 48 µm
  -   -   -   -   -   -   -   -   -   -   -   -   -  
Cu/Pb Cleaner 2 Conc.   21.0   21.3   16.8   6.0   3.44   420   30.3   88.0   87.1   8.3   42.7   83.1   22.6  
Zn Cleaner 2 Concentrate   22.8   0.5   0.4   54.4   0.79   22   33.4   2.3   2.5   81.9   10.7   4.7   27.1  
Zn Cleaner 1 Sc. Tailings   10.3   0.5   0.4   1.0   2.16   15   49.0   1.1   1.0   0.7   13.2   1.5   18.0  
Zn Rougher Tailings   37.0   0.4   0.4   1.1   0.50   11   14.7   3.2   3.6   2.7   11.0   3.8   19.3  
Feed   100.0   5.1   4.0   15.1   1.69   106   28.1   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-044
Test 81
  Talc Concentrate   Flotation Feed: 81 µm;
Cu/Pb Rougher Concentrate: 57 µm
  -   -   -   -   -   -   -   -   -   -   -   -   -  
Cu/Pb Cleaner 2 Conc.   6.0   31.1   0.2   0.3   3.57   260   33.8   96.0   23.9   23.9   79.2   91.4   38.9  
Zn Cleaner 2 Concentrate   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Cleaner 1 Sc. Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Rougher Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Feed   100.0   1.9   0.0   0.1   0.27   17   5.2   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-050
Test 77
  Talc Concentrate   Flotation Feed: 71 µm;
Cu/Pb Rougher Concentrate: 43 µm;
Zn Rougher Concentrate: 46 µm
  -   -   -   -   -   -   -   -   -   -   -   -   -  
Cu/Pb Cleaner 2 Conc.   10.1   31.1   1.0   1.1   3.06   294   33.0   93.3   67.2   9.8   71.5   79.8   37.8  
Zn Cleaner 2 Concentrate   1.8   2.6   0.3   47.1   0.85   92   29.8   1.4   3.7   75.4   3.5   4.4   6.1  
Zn Cleaner 1 Sc. Tailings   9.6   0.2   0.1   0.1   0.18   7   6.0   0.4   3.3   1.2   4.0   1.8   6.5  
Zn Rougher Tailings   73.9   0.1   0.0   0.0   0.08   3   5.3   1.5   20.6   2.6   13.7   6.0   44.2  
Feed   100.0   3.4   0.1   1.1   0.43   37   8.8   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-051
Test 110
  Talc Concentrate   Flotation Feed: 64 µm;
Cu/Pb Rougher Concentrate: 48 µm;
Zn Rougher Concentrate: 50 µm
  1.0   0.3   1.6   0.6   0.06   40   1.9   0.1   0.7   0.0   0.2   0.6   0.1  
Cu/Pb Cleaner 2 Conc.   14.4   24.4   13.0   3.4   1.67   368   31.7   84.2   84.2   3.8   62.4   82.1   15.1  
Zn Cleaner 2 Concentrate   19.5   0.8   0.3   59.0   0.20   10   33.5   3.5   2.7   88.6   10.1   3.0   21.5  
Zn Cleaner 1 Sc. Tailings   12.5   0.6   0.3   0.9   0.18   9   50.4   1.6   1.6   0.8   5.8   1.7   20.8  
Zn Rougher Tailings   47.3   0.3   0.2   0.6   0.08   8   22.9   3.7   4.9   2.2   9.8   5.8   35.6  
Feed   100.0   4.2   2.2   13.0   0.39   65   30.4   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-052
Test 110
  Talc Concentrate   Flotation Feed: 69 µm;
Cu/Pb Rougher Concentrate: 45 µm;
Zn Rougher Concentrate: 43 µm
  1.1   0.6   0.2   0.6   0.01   13   1.7   0.1   0.1   0.0   0.0   0.1   0.1  
Cu/Pb Cleaner 2 Conc.   26.5   29.7   7.2   2.0   3.67   370   32.2   88.1   88.8   3.9   78.8   77.6   29.9  
Zn Cleaner 2 Concentrate   16.2   0.6   0.3   63.8   0.22   24   33.6   1.0   2.0   73.7   2.9   3.1   19.0  
Zn Cleaner 1 Sc. Tailings   4.9   2.3   0.4   7.5   0.57   44   38.6   1.3   0.9   2.6   2.3   1.7   6.6  
Zn Rougher Tailings   43.8   0.5   0.1   0.4   0.08   9   23.3   2.2   2.6   1.1   2.8   3.1   35.8  
Feed   100.0   8.9   2.2   14.0   1.24   126   28.5   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-054
Test 60
  Talc Concentrate   Flotation Feed: 67 µm;
Cu/Pb Rougher Concentrate: 61 µm;
Zn Rougher Concentrate: 38 µm
  2.0   3.6   0.3   0.4   0.15   32   4.8   1.4   0.4   0.1   0.6   0.7   0.4  
Cu/Pb Cleaner 2 Conc.   16.8   28.3   6.4   1.8   1.69   460   33.0   90.3   89.9   5.2   56.8   83.4   24.6  
Zn Cleaner 2 Concentrate   7.3   0.8   0.3   60.2   0.64   38   32.1   1.1   1.9   76.2   9.3   3.0   10.3  
Zn Cleaner 1 Sc. Tailings   1.9   1.4   0.3   6.3   0.39   51   20.4   0.5   0.5   2.1   1.5   1.1   1.7  
Zn Rougher Tailings   68.4   0.2   0.1   0.2   0.09   6   18.9   2.3   2.9   2.0   12.3   4.1   57.3  
Feed   100.0   5.3   1.2   5.7   0.50   93   22.5   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-055
Test 92
  Talc Concentrate   Flotation Feed: 72 µm;
Cu/Pb Rougher Concentrate: 69 µm;
Zn Rougher Concentrate: 54 µm
  26.9   0.4   0.2   0.8   0.01   15   1.9   3.7   6.3   3.5   0.7   6.2   3.5  
Cu/Pb Cleaner 2 Conc.   9.9   26.3   6.4   1.5   3.08   508   29.9   84.9   78.3   2.4   81.5   77.9   20.0  
Zn Cleaner 2 Concentrate   8.9   0.7   0.2   60.0   0.15   18   32.0   2.0   2.1   84.9   3.6   2.5   19.2  
Zn Cleaner 1 Sc. Tailings   2.2   1.0   0.3   2.9   0.57   23   13.7   0.7   0.7   1.0   3.3   0.8   2.0  
Zn Rougher Tailings   48.4   0.2   0.1   0.3   0.01   8   15.5   2.7   7.7   2.4   1.3   6.0   50.4  
Feed   100.0   3.1   0.8   6.3   0.38   65   14.9   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-056
Test 82
  Talc Concentrate   Flotation Feed: 73 µm;
Cu/Pb Rougher Concentrate: 52 µm;
Zn Rougher Concentrate: 29 µm
  11.7   0.7   0.1   0.7   0.10   17   2.1   1.0   2.0   1.0   1.2   1.8   0.9  
Cu/Pb Cleaner 2 Conc.   23.5   30.6   3.0   1.3   3.03   390   33.3   90.5   84.8   3.9   71.1   82.3   30.2  
Zn Cleaner 2 Concentrate   10.7   0.9   0.2   60.4   0.26   20   32.4   1.2   1.9   85.1   2.8   1.9   13.4  
Zn Cleaner 1 Sc. Tailings   1.0   4.3   0.5   7.2   1.51   90   27.7   0.6   0.6   1.0   1.6   0.8   1.1  
Zn Rougher Tailings   49.7   0.5   0.1   0.4   0.28   14   26.2   2.9   6.5   2.7   13.9   6.2   50.1  
Feed   100.0   8.0   0.8   7.6   1.00   112   26.0   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-057
Test 83
  Talc Concentrate   Flotation Feed:132µm;
Cu/Pb Rougher Concentrate: 87 µm
  44.1   0.2   0.0   0.1   0.03   2   0.4   9.1   20.4   14.7   12.3   9.5   10.0  
Cu/Pb Cleaner 2 Conc.   3.9   21.0   0.9   0.2   1.57   184   21.2   80.1   52.1   2.6   56.8   76.7   45.7  
Zn Cleaner 2 Concentrate   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Cleaner 1 Sc. Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Rougher Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Feed   100.0   1.0   0.1   0.2   0.11   9   1.8   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-058
Test 74
  Talc Concentrate   Flotation Feed: 68 µm;
Cu/Pb Rougher Concentrate: 50 µm;
Zn Rougher Concentrate: 44 µm
  0.7   1.6   1.0   0.9   0.42   47   4.1   0.2   0.3   0.0   0.2   0.3   0.1  
Cu/Pb Cleaner 2 Conc.   21.1   26.1   10.2   2.6   4.47   394   32.9   89.5   90.3   3.8   68.0   79.4   22.5  
Zn Cleaner 2 Concentrate   21.8   0.6   0.2   58.0   0.35   22   33.7   2.0   1.9   88.1   5.5   4.6   23.8  
Zn Cleaner 1 Sc. Tailings   4.7   1.3   0.4   2.6   1.67   27   42.8   1.0   0.7   0.8   5.6   1.2   6.4  
Zn Rougher Tailings   46.9   0.3   0.1   0.6   0.21   7   27.4   2.3   2.7   1.9   7.1   3.1   41.5  
Feed   100.0   6.2   2.4   14.4   1.39   105   30.9   100.0   100.0   100.0   100.0   100.0   100.0  

  
Arctic ProjectPage 167
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Test   Product   Regrind Size
80% Passing
  Weight
(%)
  Assays   Distribution (%)  
Cu
(%)
  Pb
(%)
  Zn
(%)
  Au
(g/t)
  Ag
(g/t)
  S
(%)
  Cu   Pb   Zn   Au   Ag   S  
ARC-059
Test 84
  Talc Concentrate   Flotation Feed: 85 µm;
Cu/Pb Rougher Concentrate: 71 µm;
Zn Rougher Concentrate: 69 µm
  16.5   0.9   0.2   0.9   0.96   17   2.1   2.4   4.2   2.2   29.8   3.6   2.6  
Cu/Pb Cleaner 2 Conc.   18.1   29.9   2.9   1.4   1.70   366   32.2   91.0   87.8   4.1   57.9   85.3   45.0  
Zn Cleaner 2 Concentrate   9.9   0.9   0.1   55.0   0.14   22   32.0   1.5   2.2   85.9   2.6   2.8   24.4  
Zn Cleaner 1 Sc. Tailings   2.7   0.7   0.1   1.2   0.56   14   7.4   0.3   0.3   0.5   2.9   0.5   1.6  
Zn Rougher Tailings   48.3   0.1   0.0   0.1   0.01   5   5.5   0.8   2.5   1.1   0.9   3.1   20.6  
Feed   100.0   5.9   0.6   6.3   0.53   77   12.9   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-062
Test 75
  Talc Concentrate   Flotation Feed: 71 µm;
Cu/Pb Rougher Concentrate: 42 µm;
Zn Rougher Concentrate: 43 µm
  1.8   0.8   7.6   1.6   0.14   56   4.3   0.6   2.0   0.1   0.8   1.8   0.4  
Cu/Pb Cleaner 2 Conc.   14.6   13.6   41.0   3.6   1.36   326   21.7   88.2   91.8   2.7   63.2   87.8   16.1  
Zn Cleaner 2 Concentrate   30.7   0.3   0.4   58.6   0.12   6   32.3   4.2   1.7   92.0   11.7   3.4   50.3  
Zn Cleaner 1 Sc. Tailings   4.4   0.7   0.5   3.1   0.61   10   37.1   1.3   0.4   0.7   8.6   0.8   8.4  
Zn Rougher Tailings   44.9   0.1   0.2   0.4   0.04   3   8.2   2.0   1.0   1.0   5.7   2.5   18.7  
Feed   100.0   2.3   6.5   19.5   0.31   54   19.7   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-063
Test 85
  Talc Concentrate   Flotation Feed:117µm;
Cu/Pb Rougher Concentrate: 72 µm;
Zn Rougher Concentrate: 69 µm
  43.1   1.1   0.1   0.7   0.01   6   2.4   11.2   25.3   12.3   6.8   15.2   12.3  
Cu/Pb Cleaner 2 Conc.   11.4   29.3   0.4   0.6   0.36   102   30.4   78.6   56.3   3.0   64.7   68.7   41.5  
Zn Cleaner 2 Concentrate   3.1   1.7   0.1   55.6   0.17   14   32.7   1.2   2.2   73.0   8.4   2.6   12.2  
Zn Cleaner 1 Sc. Tailings   3.2   1.0   0.1   1.4   0.06   7   6.6   0.8   1.9   1.9   3.0   1.3   2.5  
Zn Rougher Tailings   35.3   0.2   0.0   0.2   0.01   2   5.9   1.4   8.3   2.5   5.5   4.2   24.9  
Feed   100.0   4.3   0.1   2.4   0.06   17   8.4   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-068
Test 97
  Talc Concentrate   Flotation Feed: 68 µm;
Cu/Pb Rougher Concentrate: 69 µm;
Zn Rougher Concentrate: 59 µm
  -   -   -   -   -   -   -   -   -   -   -   -   -  
Cu/Pb Cleaner 2 Conc.   8.1   31.4   0.8   0.7   1.36   186   33.7   95.6   71.0   4.4   75.5   72.4   42.9  
Zn Cleaner 2 Concentrate   2.2   0.9   0.1   50.5   0.52   34   32.0   0.7   2.8   84.9   7.9   3.6   11.1  
Zn Cleaner 1 Sc. Tailings   3.4   0.3   0.1   0.4   0.12   18   21.7   0.4   2.1   1.0   2.8   3.0   11.6  
Zn Rougher Tailings   83.3   0.0   0.0   0.1   0.01   4   1.9   0.6   17.4   3.8   5.7   16.0   25.3  
Feed   100.0   2.7   0.1   1.3   0.15   21   6.4   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-069
Test 106
  Talc Concentrate   Flotation Feed: 62 µm;
Cu/Pb Rougher Concentrate: 49 µm;
Zn Rougher Concentrate: 56 µm
  9.6   0.3   0.3   0.7   0.01   16   1.7   0.8   2.4   0.6   0.7   2.7   0.7  
Cu/Pb Cleaner 2 Conc.   10.8   25.7   9.6   2.7   0.58   396   32.8   86.4   83.3   3.0   44.8   74.7   15.0  
Zn Cleaner 2 Concentrate   15.3   0.6   0.2   58.4   0.20   24   33.9   3.0   2.7   91.2   22.0   6.4   22.1  
Zn Cleaner 1 Sc. Tailings   12.2   0.4   0.2   0.7   0.12   12   50.0   1.5   1.7   0.9   10.5   2.6   25.8  
Zn Rougher Tailings   48.5   0.2   0.1   0.3   0.04   9   14.8   3.2   3.9   1.6   13.9   7.6   30.5  
Feed   100.0   3.2   1.2   9.8   0.14   57   23.6   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-072
Test 78
  Talc Concentrate   Flotation Feed: 69 µm;
Cu/Pb Rougher Concentrate: 46 µm;
Zn Rougher Concentrate: 36 µm
  3.0   0.6   0.4   1.3   0.32   57   3.2   0.4   2.7   0.4   0.8   1.6   0.4  
Cu/Pb Cleaner 2 Conc.   16.3   29.3   1.8   3.5   5.38   476   33.6   91.5   70.2   6.1   71.3   71.6   21.9  
Zn Cleaner 2 Concentrate   14.2   0.7   0.2   56.2   0.69   48   33.3   1.8   5.0   85.5   8.0   6.3   18.9  
Zn Cleaner 1 Sc. Tailings   3.8   0.9   0.2   2.1   0.54   51   27.1   0.6   1.8   0.8   1.7   1.8   4.1  
Zn Rougher Tailings   58.8   0.2   0.1   0.2   0.24   19   21.2   2.0   13.9   1.2   11.5   10.3   49.9  
Feed   100.0   5.2   0.4   9.3   1.23   108   25.0   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-080
Test 113
  Talc Concentrate   Flotation Feed: 68 µm;
Cu/Pb Rougher Concentrate: 45 µm
  6.4   0.2   0.0   0.0   0.15   10   0.4   0.9   4.7   1.7   1.6   2.7   1.0  
Cu/Pb Cleaner 2 Conc.   3.6   30.4   1.0   0.4   12.7   426   31.3   88.4   66.5   9.8   77.2   65.0   43.3  
Zn Cleaner 2 Concentrate   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Cleaner 1 Sc. Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Rougher Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Feed   100.0   1.3   0.1   0.2   0.60   24   2.6   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-084
Test 91
  Talc Concentrate   Flotation Feed: 78 µm;
Cu/Pb Rougher Concentrate: 46 µm;
Zn Rougher Concentrate: 43 µm
  2.1   0.5   0.3   0.9   0.04   15   3.9   0.4   1.5   0.3   0.5   1.1   0.3  
Cu/Pb Cleaner 2 Conc.   9.0   25.2   3.0   5.5   1.40   180   35.0   85.8   60.1   9.3   71.7   57.6   13.0  
Zn Cleaner 2 Concentrate   7.5   0.9   0.3   54.6   0.18   42   33.1   2.7   5.3   77.4   7.7   11.3   10.3  
Zn Cleaner 1 Sc. Tailings   2.5   1.3   0.4   3.1   0.18   29   30.2   1.3   2.4   1.5   2.6   2.6   3.2  
Zn Rougher Tailings   75.9   0.2   0.1   0.3   0.01   7   21.9   4.3   22.3   4.4   4.3   18.9   68.9  
Feed   100.0   2.6   0.4   5.3   0.18   28   24.1   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-086
Test 86
  Talc Concentrate   Flotation Feed: 59 µm;
Cu/Pb Rougher Concentrate: 45 µm;
Zn Rougher Concentrate: 35 µm
  0.4   0.3   0.1   0.2   0.81   14   1.7   0.0   0.1   0.0   0.3   0.1   0.0  
Cu/Pb Cleaner 2 Conc.   10.7   28.7   7.1   1.2   6.54   430   33.3   75.9   87.3   1.8   63.0   55.4   15.6  
Zn Cleaner 2 Concentrate   12.4   5.1   0.2   53.8   0.79   176   32.1   15.7   2.4   92.9   8.9   26.4   17.5  
Zn Cleaner 1 Sc. Tailings   3.0   1.8   0.3   2.0   1.53   70   28.2   1.3   0.9   0.8   4.1   2.5   3.7  
Zn Rougher Tailings   71.0   0.1   0.1   0.1   0.18   9   19.1   2.3   4.9   1.2   11.5   7.7   59.6  
Feed   100.0   4.0   0.9   7.2   1.11   83   22.7   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-087
Test 87
  Talc Concentrate   Flotation Feed: 67 µm;
Cu/Pb Rougher Concentrate: 36 µm;
Zn Rougher Concentrate: 31 µm
  1.4   0.9   0.5   0.7   0.21   24   2.0   0.1   0.2   0.1   0.1   0.2   0.1  
Cu/Pb Cleaner 2 Conc.   37.1   26.4   10.4   6.6   6.04   394   30.7   91.9   91.9   16.6   66.5   83.9   47.6  
Zn Cleaner 2 Concentrate   14.1   0.7   0.4   61.7   0.78   30   32.4   0.9   1.3   59.0   3.3   2.4   19.0  
Zn Cleaner 1 Sc. Tailings   2.9   3.3   0.9   13.3   12.2   96   27.1   0.9   0.6   2.6   10.5   1.6   3.3  
Zn Rougher Tailings   36.9   0.6   0.2   0.7   0.61   18   13.1   1.9   1.7   1.8   6.7   3.8   20.2  
Feed   100.0   10.7   4.2   14.7   3.37   174   23.9   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-092
Test 90
  Talc Concentrate   Flotation Feed: 68 µm;
Cu/Pb Rougher Concentrate: 46 µm;
Zn Rougher Concentrate: 29 µm
  5.1   0.5   0.0   0.2   0.03   5   2.6   0.5   1.6   0.2   0.6   1.2   0.4  
Cu/Pb Cleaner 2 Conc.   13.7   29.1   0.4   2.5   1.01   108   34.6   87.6   46.6   6.7   54.3   67.0   15.4  
Zn Cleaner 2 Concentrate   7.8   1.2   0.2   54.4   0.59   24   33.8   2.0   9.0   83.0   18.0   8.4   8.5  
Zn Cleaner 1 Sc. Tailings   1.7   2.6   0.2   3.3   0.06   26   27.0   0.9   2.6   1.1   0.4   1.9   1.5  
Zn Rougher Tailings   68.8   0.3   0.1   0.2   0.04   4   31.8   4.4   31.8   2.8   10.8   12.4   71.0  
Feed   100.0   4.6   0.1   5.1   0.26   22   30.8   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-098
Test 93
  Talc Concentrate   Flotation Feed:103µm;
Cu/Pb Rougher Concentrate: 89 µm
  -   -   -   -   -   -   -   -   -   -   -   -   -  
Cu/Pb Cleaner 2 Conc.   4.0   25.6   0.7   0.8   1.32   578   29.5   97.8   69.9   34.5   75.8   92.6   82.1  
Zn Cleaner 2 Concentrate   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Cleaner 1 Sc. Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Zn Rougher Tailings   -   -   -   -   -   -   -   -   -   -   -   -   -  
Feed   100.0   1.1   0.0   0.1   0.07   25   1.5   100.0   100.0   100.0   100.0   100.0   100.0  
ARC-099
Test 80
  Talc Concentrate   Flotation Feed: 69 µm;
Cu/Pb Rougher Concentrate: 48 µm;
Zn Rougher Concentrate: 41 µm
  2.0   0.9   0.5   0.6   0.04   22   1.8   0.3   0.4   0.1   0.2   0.5   0.2  
Cu/Pb Cleaner 2 Conc.   19.9   28.3   9.9   2.8   0.95   404   31.9   90.4   89.6   4.7   55.9   86.6   29.0  
Zn Cleaner 2 Concentrate   15.7   0.6   0.3   63.2   0.11   18   32.5   1.4   2.1   83.3   5.1   3.0   23.3  
Zn Cleaner 1 Sc. Tailings   4.1   1.8   0.4   7.5   0.71   30   29.1   1.2   0.7   2.6   8.7   1.3   5.5  
Zn Rougher Tailings   54.2   0.2   0.1   0.2   0.10   4   14.7   2.1   2.0   0.8   16.1   2.3   36.4  
Feed   100.0   6.2   2.2   11.9   0.34   93   21.9   100.0   100.0   100.0   100.0   100.0   100.0  

  
Arctic ProjectPage 168
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

10.4.5.4Copper/Lead Separation Testwork

 

A copper-lead separation test was included for the bulk concentrate produced in selected cleaner tests and later cycles of 5 locked-cycle tests. Table 10-30 summarizes the copper/lead separation testwork results.

 

Reasonable separations were achieved for all but ARC-003. For ARC-003, a low-grade lead concentrate which measured only about 16% lead was produced, even when the test was repeated with a much higher sodium cyanide dosage. It is unclear what caused the poor copper-lead separation for ARC-003. For the other 7 samples tested, lead recoveries from the bulk concentrate ranged between 75 and 95% to a lead concentrate with an average grade of about 56% lead in open circuit.

 

Copper-lead separation recoveries from tests on the locked cycle test concentrates were applied to bulk circuit recoveries to calculate overall recoveries. Silver recovery to the lead concentrate averaged about 75%, but gold recoveries in the copper separation tests varied widely and might indicate differences in gold deportment and associations between lithology types.

 

Figure 10 9 summarises the results showing the individual and combined concentrate grades and copper recovery. Figure 10 10 summarises the results showing the individual and combined concentrate grades and lead recovery.

 

Figure 10-9: Variability Composite Copper Recovery vs. Concentrate Grade

 

 

Source: Ausenco, 2022.

  
Arctic ProjectPage 169
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 10-10: Variability Composite Lead Recovery vs. Concentrate Grade

 

 

Source: Ausenco, 2022.

  
Arctic ProjectPage 170
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 10-30: ALS Lead Separation Test Results

 

Test   Product   Weight
(%)
  Assays   Distribution (%)  
Cu
(%)
  Pb
(%)
  Zn
(%)
  Ag
(g/t)
  Au
(g/t)
  S
(%)
  Cu   Pb   Zn   Ag   Au   S  
ARC-051
Cu/Pb Separation Feed from Open Circuit Test (Test 88)
  Pb 3rd Cleaner Concentrate   25.5   5.1   48.4   9.3   1242   4.6   21.5   5.5   86.2   68.2   83.9   75.9   17.7  
Pb 2nd Cleaner Concentrate   30.9   6.9   43.8   9.11   1098   3.94   23.5   9.0   92.0   81.0   90.0   79.7   23.4  
Pb 1st Cleaner Concentrate   37.7   10.0   37.3   8.0   938   3.35   25.3   16   95.8   86.9   93.9   82.8   30.8  
Pb Rougher Concentrate   49.4   14.7   29.1   6.41   734   2.68   27.3   30.6   97.8   91.1   96.2   86.4   43.6  
Pb Rougher Tailings (Cu Concentrate)   50.6   32.4   0.7   0.6   28   0.41   34.5   69.4   2.2   8.9   3.8   13.6   56.4  
Cu/Pb 2nd Cleaner Concentrate (Head)   100.0   23.6   14.7   3.47   377   1.53   31   100   100   100   100   100   100  
ARC-024
Cu/Pb Separation Feed from Open Circuit Test (Test 89)
  Pb 3rd Cleaner Concentrate   14.4   5.2   58.6   5.9   2230   17   18.6   2.8   87.5   47.3   78.5   72.9   8.2  
Pb 2nd Cleaner Concentrate   17.8   8.1   50.5   5.7   1929   14.4   21.0   5.3   93.2   56.4   83.9   76.2   11.5  
Pb 1st Cleaner Concentrate   24.2   13.4   38.5   4.8   1481   11.3   24.4   12.0   96.6   64.6   87.5   81.1   18.2  
Pb Rougher Concentrate   39.3   20.0   24.2   3.3   949   7.4   28.3   29.0   98.2   72.7   90.8   86.5   34.2  
Pb Rougher Tailings (Cu Concentrate)   60.7   31.7   0.3   0.8   62   0.75   35.3   81   1.8   27.3   9.2   13.5   65.8  
Cu/Pb 2nd Cleaner Concentrate (Head)   100.0   27.1   9.7   1.8   410   3.4   32.6   100   100   100   100   100   100  
ARC-007
Cu/Pb Separation Feed from LCT-96
(Cycle 5)
  Pb 3rd Cleaner Concentrate   19.3   2.3   58.6   6.0   1710   0.4   19.9   1.8   93.4   29   57.3   1.7   12.1  
Pb 2nd Cleaner Concentrate   20.8   2.5   55.8   6.04   1629   0.5   21.4   2.2   95.8   31.4   58.8   2.2   14.0  
Pb 1st Cleaner Concentrate   21.9   3.1   53.8   6.04   1574   0.54   21.8   2.8   96.9   33.0   59.6   2.4   15.1  
Pb Rougher Concentrate   24.6   5.6   48.2   5.8   1438   1.05   22.9   5.6   97.9   35.4   61.3   5.4   17.8  
Pb Rougher Tailings (Cu Concentrate)   75.4   30.6   0.3   3.4   296   6.03   34.6   94.4   2.1   64.6   38.7   94.6   82.2  
Cu/Pb 2nd Cleaner Concentrate (Head)   100.0   24.4   12.1   4   577   4.8   31.7   100   100   100   100   100   100  
ARC-099
Cu/Pb Separation Feed from
LCT-100 (Cycle 5)
  Pb 3rd Cleaner Concentrate   20.3   10.7   46.5   5   1420   0.98   22.1   8.6   94.7   18.3   81.2   12.4   14.2  
Pb 2nd Cleaner Concentrate   23.9   13.1   40.2   4.8   1230   0.94   23.8   12.4   96.3   20.7   82.8   14.0   18.0  
Pb 1st Cleaner Concentrate   29.0   15.7   33.6   4.52   1033   0.88   25.5   18.0   97.4   23.6   84.2   15.9   23.4  
Pb Rougher Concentrate   37.6   18.9   26.1   4.3   815   0.96   27.4   28.1   98.2   29.2   86.1   22.4   32.5  
Pb Rougher Tailings (Cu Concentrate)   62.4   29.2   0.3   6.3   79   2.0   34.2   71.9   1.8   70.8   13.9   77.6   67.5  
Cu/Pb 2nd Cleaner Concentrate (Head)   100.0   25.3   10.0   5.5   356   1.6   31.6   100   100   100   100   100   100  
ARC-058
Cu/Pb Separation Feed from
LCT-104 (Cycle 5)
  Pb 3rd Cleaner Concentrate   14.9   3.6   60.7   5.2   2012   8.75   19.2   1.9   83.1   32.1   68.8   37.6   8.8  
Pb 2nd Cleaner Concentrate   19.8   4.7   51.1   5.9   17.1   7.5   22.8   3.4   92.4   47.8   76.9   42.6   13.9  
Pb 1st Cleaner Concentrate   23.2   7.0   45.3   5.6   1523   6.8   24.4   5.8   96.2   53.7   80.8   45.1   17.4  
Pb Rougher Concentrate   31.5   13.7   34.0   4.6   1166   6.1   27.0   15.5   98.1   59.8   84.0   54.9   26.2  
Pb Rougher Tailings (Cu Concentrate)   68.5   34.2   0.3   1.4   102   2.3   35.0   84.5   1.9   40.2   16.0   45.1   73.8  
Cu/Pb 2nd Cleaner Concentrate (Head)   100.0   27.7   10.9   2.4   437   3.5   32.5   100   100   100   100   100   100  
ARC-062
Cu/Pb Separation Feed from
LCT-105 (Cycle 5)
  Pb 3rd Cleaner Concentrate   60.0   4.0   63.4   7.0   482   1.5   17.8   18.3   92.1   74.8   85.6   65.5   45.3  
Pb 2nd Cleaner Concentrate   66.2   5.5   59.3   6.9   454   1.5   19.0   27.8   95.0   81.4   89.0   72.1   53.3  
Pb 1st Cleaner Concentrate   73.2   7.6   54.6   6.6   424   1.7   20.2   42.4   96.7   85.9   91.8   93.1   62.8  
Pb Rougher Concentrate   82.6   10.0   49.1   6.2   389   1.5   21.7   63.2   98.1   90.5   94.9   94.9   75.9  
Pb Rougher Tailings (Cu Concentrate)   17.4   27.6   4.6   3.1   98   0.4   32.6   36.8   1.9   9.5   5.1   5.1   24.1  
Cu/Pb 2nd Cleaner Concentrate (Head)   100.0   13.1   41.3   5.6   338   1.3   23.6   100   100   100   100   100   100  
ARC-069
Cu/Pb Separation Feed from LCT-114 (Cycle 5)
  Pb 3rd Cleaner Concentrate   12.0   2.0   60.4   3.2   2168   0.2   16.5   1.1   75.1   11.1   64.0   4.3   6.2  
Pb 2nd Cleaner Concentrate   16.5   2.2   51.1   4.6   1848   0.23   20.9   1.6   88.0   2.1   75.6   6.6   10.8  
Pb 1st Cleaner Concentrate   20.6   2.8   44.1   5.1   1596   0.25   23.9   2.5   94.6   30.6   81.4   8.7   15.4  
Pb Rougher Concentrate   25.2   5.7   37.1   5.1   1355   0.3   25.3   6.4   97.3   37.7   84.5   12.4   19.9  
Pb Rougher Tailings (Cu Concentrate)   74.8   28.5   0.4   2.9   84   0.7   34.3   93.6   2.7   62.3   15.5   87.6   80.1  
Cu/Pb 2nd Cleaner Concentrate (Head)   100.0   22.7   9.6   3.4   405   0.6   32.0   100   100   100   100   100   100  
ARC-008
Cu/Pb Separation Feed from
LCT-116 (Cycle 5)
  Pb 4th Cleaner Concentrate   5.4   5.1   64.6   3.1   2540   3.1   16.1   1.0   47.2   6.5   39.0   4.3   2.6  
Pb 3rd Cleaner Concentrate   9.3   4.5   62.5   4.0   2298   2.3   17.4   1.5   78.2   14.6   60.5   5.4   4.9  
Pb 2nd Cleaner Concentrate   11.1   5.1   59.5   4.5   2176   2.2   18.4   2.0   88.9   19.4   68.4   6.2   6.1  
Pb 1st Cleaner Concentrate   13.9   8.1   50.5   4.9   1858   2.5   21.0   3.9   94.9   26.8   73.4   8.9   8.8  
Pb Rougher Concentrate   26.2   19.2   27.5   3.5   1060   3.8   27.5   17.6   97.0   36.0   78.7   25.5   21.7  
Pb Rougher Tailings (Cu Concentrate)   73.8   31.9   0.3   2.2   102   4.0   35.2   82.4   3.0   64.0   21.3   47.5   78.3  
                                                       

  
Arctic ProjectPage 171
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

10.5Comment on Mineral Processing and Metallurgical Testwork

 

The materials tested in the metallurgical programs as described in this Section are representative of the LOM production.

 

The bulk flotation flowsheet developed based on the 2012 to 2022 testwork is feasible.

 

Recent grinding and concentrate dewatering testwork have supported the selected flow sheet. Additional concentrate characterization is also recommended for future metallurgical samples to bolster the confidence in the design of the proposed grinding plant.

 

The continuation of the geometallurgical program is recommended to further confirm the flowsheet and better understand the continuity of the Arctic deposit with respect to the metallurgical response. This testwork is recommended to take the form of locked cycle tests using a variety of metallurgical samples representing both lithology types and spatial zones within the deposit. A continuation of a phased approach to additional testwork is recommended to ensure that representative testwork is managed properly.

 

Historical testwork has shown the lead concentrate quality to be impacted by talc flotation efficiency. Recent testwork demonstrated a better understanding of the level of talc in an expected process feed to avoid mis-representing the talc content of future samples. There is little reason to expect concentrates will be impaired by talc contamination as talc can be effectively removed from the base metal flotation process, mitigating the potential of talc diluting the base metal concentrates. Talc and fluorine levels will be managed by optimization of the talc pre-float circuit, effectively removing talc and fluorine to ensure the quality of the lead concentrate.

 

There are no outstanding metallurgical issues related to the production of a copper or zinc concentrate from all of the materials tested.

 

In the QP’s opinion, based on the summarized testwork and predictions made from that testwork in terms of mineralogy, plant design considerations, recovery forecasts, and presence of deleterious elements, the predictions of proposed throughput and metallurgical performance are adequate for the purposes used in the Report.

  
Arctic ProjectPage 172
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

11MINERAL RESOURCE ESTIMATES

 

11.1Introduction

 

In early 2022, Ambler Metals completed an update of the Arctic Mineral Resource model based on all available drill results through to the end of 2021 drilling campaign. Wood’s QP reviewed the model and visited the Arctic Property and core storage sites.

  

The current Mineral Resource was prepared by Ambler Metals using the following:

 

Leapfrog software;

 

Updated geological models including the talc model using the additional drill hole data collected from 2019 and 2021;

 

Updated resource estimation using the additional drill hole data collected from 2019 and 2021 (see Table 11-1, and Section 11.3.3).

 

The Wood QP reviewed and validated the Mineral Resource model.

 

Composites and 3D solid models were constructed using Leapfrog commercial modelling software. The block model is setup in NAD 83 datum and extends a total of 1,910 m in the east-west direction, 1,950 m north-south, and 705 m in the vertical direction. The block model has a parent block size of 10 x 10 x 5 m with a sub-block size of 2 x 2 x 1 m.

 

The Mineral Resource estimate is accepted by Wood’s QP as being current as of November 30, 2022 and is in accordance with the with the standards and definitions required under S-K 1300.  

  

Table 11-1: List of Drill Holes used in 2022 Ambler Metals Resource Model that were Not Included in the 2020 SRK Model

 

Hole ID Geologic Model Resource Model Notes
AR19-0164 Yes Yes -
AR19-0165 Yes Yes -
AR19-0165a Yes Yes -
AR19-0166 Yes Yes -
AR19-0167 Yes Yes -
AR19-0168 Yes Yes -
AR19-0168a Yes Yes -
AR19-0169 Yes Yes -
AR19-0170 Yes Yes -
AR19-0171 Yes Yes -
AR19-0172 Yes Yes -
AR21-0173 Yes Yes -
AR21-0174 Yes Yes -

  
Arctic ProjectPage 173
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Hole ID Geologic Model Resource Model Notes
AR21-0175 Yes Partially missing talc information Talc samples are not interpreted to be in Minzones
AR21-0176 Yes Yes -
AR21-0177 Yes Yes -
AR21-0178 Yes Partially missing talc information Talc intercepts within Minzone
AR21-0179 Yes No -
AR21-0180 Yes Partially missing talc information Talc intercepts within Minzone 3
AR21-0181 Yes No -
AR21-0182 Yes Yes -
AR21-0183 Yes No -
AR21-0184 Yes No -
AR21-0185 Yes Yes -
AR21-0186 Yes Partially missing assays No assay data for Minzone 4, 3, 2.5, 2 and 1
AR21-0187 Yes Partially missing talc information Talc not currently in Minzone, this may change when assays are back
AR21-0188 Yes Partially missing assay information (only below 202.23 meters) No assay data for Minzone 3 and 5
AR21-0189 Yes No -
AR21-0190 Yes No -

 

11.2Drill Hole Database

 

Ambler Metals uses GeoSpark software for the drill hole logging data entries and management. Core logging data is entered directly to the GeoSpark software by core logging geologists, and the data is synchronized to the local server during the field season. After the field season is over, data validation is performed within the GeoSpark software, and the data is transferred to the master server.

 

For the current resource model, the cut-off date for the assay drill hole database is November 30, 2021. The assay database consists of collar, survey, assay, lithology, SG, geology, and geotechnical information. The assay database contains 171 drill holes with 3,224 assay samples, totalling 3,539.73 m.

 

At the assay cut-off date, out of 18 holes drilled in 2021, Ambler Metals had yet to receive assay results for six full holes and six partial holes due to heavy backlog at the assay laboratory.

  

Sample data for copper, lead, zinc, gold, and silver were extracted from this database for use in the generation of this resource estimate.

 

Individual sample intervals range from 0.08 m to 5.85 m in length and average 1.10 m. Drill hole sample interval protocol has varied throughout time at Arctic. Typically, shoulder samples were taken outside the mineralized zones up to 20 m.

 

Table 11-2 shows a summary statistic table of the raw assay.

  
Arctic ProjectPage 174
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-2: Summary Statistics of Assay Database, Length Weighted

 

Element   Unit   Count   Total Length
(m)
  Minimum   Maximum   Mean   Standard
Deviation
  Coefficient
of Variation
 
Ag   g/t   2,983   3,298   0.0   1,155.0   46.1   59.77   1.30  
As   ppm   1,891   2,131   0.6   10,000.0   1,028.1   1,837.60   1.79  
Au   g/t   2,841   3,141   0.00   32.80   0.66   1.60   2.43  
Cd   ppm   1,891   2,131   0.08   1,000.00   198.52   247.27   1.25  
Cu   %   3,000   3,324   0.00   31.00   2.92   3.13   1.07  
Fe   %   1,891   2,131   0.37   32.10   9.69   6.69   0.69  
Hg   ppm   1,176   1,068   0.0   43.9   1.9   2.74   1.47  
Pb   %   2,935   3,246   0.00   21.80   0.86   1.59   1.84  
S   %   1,890   2,130   0.01   30.70   6.14   4.50   0.73  
Sb   ppm   1,891   2,131   0.2   5,210.0   192.3   352.31   1.83  
SG   -   3,184   3,540   2.01   4.99   3.29   0.36   0.11  
Zn   %   2,974   3,294   0.00   30.00   3.95   4.96   1.26  

 

The distribution of copper grades in drill holes proximal to the Arctic deposit is shown from two cross section maps in Figure 11-1.

  
Arctic ProjectPage 175
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 11-1: East-West Cross Section for Copper Drill Hole Data, Looking North (Resource pit depicted in red)

 

 

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 176
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

South32 developed and provided Ambler Metals with an algorithm to calculate talc proxy. The algorithm was applied in the database in 2019 and 2021. The algorithm uses the multi element assay results, mainly Mg, Al and K for the data from 1968 to 2017, and the four-acid digest-ICPMS data collected between 2004 to 2017 and generated calculated talc percent proxy values in the database. The algorithm was applied in the 2021 database to create talc model wireframes and estimate talc grades within the model.

 

11.3Interpretations and Geological Modelling Procedures

 

11.3.1Lithology Modelling

 

In 2019, SRK revised three-dimensional (3D) geological model wireframes generated by Trilogy in 2017. The geological model updates were completed using Leapfrog Geo software. In October of 2021, Ambler further updated the 2019 geological model wireframes using drilling information collected during 2019 and 2021 drilling campaign. Figure 11-2 shows East-West cross-section map of the modelled Arctic geological wireframes including mineralized zones (Minzones). The main lithological units in the Arctic deposit are shown in Table 11-3.

 

Figure 11-2: East-West Cross-Section of the Arctic Geological Model, Looking North

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 177
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-3: Arctic Lithological Units

 

Lithological Unit Codes Lithological Name
QMS Series of felsic quartz mica schists
MRP Meta-rhyolite porphyry
GS Grey schist of the carbonaceous schists
AMR Aphanitic meta-rhyolite

 

11.3.2Talc Modelling

 

Three-dimensional talc model wireframes were generated using the updated talc proxy database using the algorithm provided by South32 by capturing high-grade and low-grade talc intervals. Samples that showed talc proxy percentages above 0% were included in the talc zones. Figure 11-3 shows an East-West cross-section map of the modelled Arctic talc wireframes (green).

 

Figure 11-3: East-West Cross-Section of Talc Model Wireframes, Looking North

 

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 178
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

11.3.3Mineralization Domains

 

The mineralized zone (Minzones) wireframes were updated using new assay data, typically using the 0.5% CuEq cut-off grade, as a guide where data is available. Drill holes that did not have assay results received by the assay database cut-off date were used to update the geological model but not used in the resource model. For these holes, the geological model was updated using the geology logging data to update the mineralized zone wireframes. Only minor revisions of the wireframes were made to the main mineralized zones (Zones 1, 1a, 2, 2.5, 3, 3_sub, 4 and 5) compared to the previous model. The main mineralized zones are Zones 1, 3, and 5. A cross section of mineralized zone wireframes, with estimation domain group and individual domain names, are shown in Figure 11-4. Table 11-4 shows mineralized zone domain codes used in the resource model.

 

Figure 11-4: East-West Cross-Section of the Arctic Deposit Showing Mineralized Zones

 

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 179
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-4: Summary of Mineralized Zone Domains

 

Leapfrog Minzone Domain Estimation Domain
1 Zone 1 Bottom Group
1cz_sub Zone 1 a Bottom Group
2 Zone 2 Bottom Group
2.5 Zone 2.5 Bottom Group
3b Zone 3 Mid Group
3by_sub Zone 3a Mid Group
4 Zone 4 Top Group
5cx Zone 5 Top Group
7 Zone 7b Top Group
7a Zone 7c Top Group
7a_hw Zone 7a hw Top Group
7b_hw Zone 7b hw Top Group
7hw Zone 7c hw Top Group
7_sub Zone 7a Top Group
8 Zone 8c Top Group
8a Zone 8d Top Group
8_sub Zone 8b Top Group
8_subA Zone 8a Top Group

 

11.4Exploratory Data Analysis

 

11.4.1Specific Gravity

 

SG database includes a total of 12,088 SG values, with 3,497 measured SG values and the rest are predicted and assigned values, ranging from 2.01 to 4.99 with average sample length of 2.33 m.

 

Prior to 2019, SG measurement at Arctic was inconsistent and the SG database contained many missing SG intervals, especially within the mineralized zones. In 2019, SRK provided a solution to fill the missing SG intervals by using the Random Forest Regressor to predict SG values in the mineralized zones. Outside of the mineralized zones, within non mineralized lithological units where SG data was not available, Ambler assigned an SG value of 2.78.

 

Since 2019, Ambler Metals collected SG values at a regular interval from both inside and outside of the mineralized zones and it was no longer necessary to use the Random Forest Regressor.

  
Arctic ProjectPage 180
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

From 2019, SG measurements were taken using half cut core and taking dry and water submerged weights to calculate SG value. From 2011 to 2017, SG measurements were taken on whole core prior to cutting. Ambler Metals updated the existing SG database created by SRK with predicted SG values in 2021 with SG measurements collected since 2019.

 

SG was estimated in all mineralized zones and lithologies.

 

Table 11-5 shows summary statistics of SG by Minzone.

 

Wood reviewed 1,850 measured SG values with Random Forest predicted values in the SG database to assess for bias. Table 11-6 shows that there is no significant difference between the means of the measured and predicted SG values, however, the standard deviation of the predicted SG value is slightly smaller. Correlation coefficient of the measured and predicted SG values is 0.930.

 

Table 11-7 shows average measured and predicted SG values within selected bins of measured SG values. A low bias in the predicted SG values is observed and only exceed 5% bias for SG values below 2.7 and above 3.7. Table 11-5 shows that the proportion of blocks with estimated SG below 2.7 and above 3.7 is less than 1%. Small number of samples and number of blocks affected by this is not expected to have any material impact. A capping strategy was used during estimation process of SG values to control the impact of the extreme SG values. No other corrections in the predicted SG were applied for the current resource estimate.

 

Table 11-5: Summary Statistics for SG by Mineralized Zone

 

Minzone   Count   Mean   Min   Max  
Zone 1   646   3.36   2.70   4.96  
Zone 1a   36   3.12   2.75   3.32  
Zone 2   145   3.29   2.74   4.63  
Zone 2.5   89   3.24   2.75   4.39  
Zone 3   762   3.24   2.50   4.46  
Zone 3a   4   3.32   3.31   3.32  
Zone 4   222   3.24   2.70   4.43  
Zone 5   849   3.36   2.01   4.99  
Zone 7a   12   2.93   2.71   3.32  
Zone 7b   32   3.12   2.80   4.00  
Zone 7c   8   3.03   2.73   3.32  
Zone 7a HW   30   2.99   2.70   3.32  
Zone 7b HW   21   2.97   2.72   3.32  
Zone 7c HW   33   3.06   2.73   3.32  
Zone 8a   4   3.32   3.32   3.32  
Zone 8b   5   3.31   3.31   3.32  
Zone 8c   44   3.06   2.72   3.32  
Zone 8 HW   7   3.32   3.31   3.32  

 

  
Arctic ProjectPage 181
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-6: Summary Statistics for SG Measured and SG Predicted

 

    Number of Data   Mean   Min   Max   Std. Dev  
SG Measured   1,849   3.05   2.56   4.99   0.20  
SG Predicted   1,849   3.06   2.65   4.38   0.16  

 

Table 11-7: Mean SG Values for Measured and Predicted by Bins

 

        Mean      
Number of Data   Target SG Value   Measured SG   Predicted SG   % Difference  
5   2.5   2.589   2.708   5%  
754   2.7   2.746   2.788   2%  
238   3   2.982   3.045   2%  
118   3.2   3.2   3.249   2%  
97   3.5   3.49   3.446   -1%  
80   3.7   3.701   3.614   -2%  
64   4   4.01   3.822   -5%  
48   4.1   4.305   4.054   -6%  
18   4.3   4.472   4.208   -6%  
8   4.6   4.574   4.279   -6%  

  
Arctic ProjectPage 182
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 11-5: Cumulative Probability Plot for SG in the Resource Block Model

 

 

Source: Wood, 2022

 

11.4.2Compositing

 

The raw assay database was weighted using SG, meaning the weighted sample length equals sample length times SG times grade. Weighting composites by SG accounts for density having a positive correlation to grade in massive sulphide mineralization. The weighted assays were composited into 2-m intervals broken by lithology and mineralized zones. Residual composites that are less than 1 m were distributed equally into composites that are in the same domain.

 

Figure 11-6 shows a histogram of composite length, with 1.9 m as the average length of the composite.

 

Table 11-8 shows summary statistics of the composite database by mineralized zone.

  
Arctic ProjectPage 183
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 11-6: Histogram of Composite Lengths

 

 

Source: Ambler, 2022.

 

Table 11-8: Summary Statistics of the Composite Database

 

Element   Unit   Count   Total Length
(m)
  Minimum   Maximum   Mean   Standard
Deviation
  Coefficient
of Variation
 
Ag   g/t   1,747   3,328   0.0   578.9   46.5   47.71   1.03  
As   ppm   1,123   2,152   2.1   10,000.0   1,032.7   1,614.66   1.56  
Au   g/t   1,685   3,219   0.00   28.08   0.66   1.32   1.99  
Cd   ppm   1,123   2,152   0.08   1,000.00   201.58   208.44   1.03  
Cu   %   1,753   3,339   0.00   16.35   2.94   2.61   0.89  
Fe   %   1,123   2,152   0.37   27.77   9.78   5.85   0.60  

  
Arctic ProjectPage 184
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Element   Unit   Count   Total Length
(m)
  Minimum   Maximum   Mean   Standard
Deviation
  Coefficient
of Variation
 
Hg   ppm   563   1,077   0.0   13.4   1.9   2.11   1.11  
Pb   %   1,738   3,311   0.00   17.65   0.88   1.35   1.54  
S   %   1,122   2,151   0.01   28.57   6.19   3.94   0.64  
Sb   ppm   1,123   2,152   0.2   2,293.9   192.9   290.37   1.50  
SG   -   1,860   3,540   2.51   4.60   3.30   0.34   0.10  
Zn   %   1,749   3,333   0.00   24.10   3.97   4.14   1.04  

 

11.4.3Grade Capping

 

Probability plots of declustered data (by polygonal) and sensitivity curves were assessed in determining an appropriate capping value for all economic elements and specific gravity in each of the mineralized zones and lithological domains. The capping values used in the current model are the same as the values determined in the previous SRK model and are shown in Table 11-9. Summary statistics comparing mean values before and after the capping values are applied is shown in Table 11-10 for payable metals, and Table 11-11 for non-payable metals.

 

11.4.4Spatial Analysis

 

Experimental and modelled variograms were generated using 2m capped composites to analyse the spatial continuity of mineralization within all mineralized zones. Mineralized zones define the resource estimation domains. Mineralized zones are combined into three groups (bottom, middle, and top) for the variogram analysis. Non-mineralized lithological units are combined into a single group, and the high-grade talc zones are also merged into a single group for the same purpose.

 

Table 11-12 summarizes the estimation domains. Figure 11-7 shows a cross-section of grouped estimation domains.

 

The composites for each combined mineralized zone were unfolded into 2D flattened space for experimental and modelling variograms and final variogram models are reported in GSLib format. Table 11-13 to Table 11-16 show modelled variogram model parameters used in the grade estimations.

  
Arctic ProjectPage 185
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-9: Capping Values

 

Minzone/Lithology   Capping Values  
  Cu
(%)
  Pb
(%)
  Zn
(%)
  Au
(g/t)
  Ag
(g/t)
  SG   As
(ppm)
  Sb
(ppm)
  Cd
(ppm)
  Hg
(ppm)
  Fe
(%)
  S
(%)
 
Zone 1, 1a   8.0   3.00   14.00   2.5   150   4.5   7,000   1,000   800   7.0   25.0   10.0  
Zone 2   6.0   2.80   11.00   2.5   110   4.5   4,000   1,000   600   4.0   20.0   10.0  
Zone 2.5   6.0   2.50   8.00   0.6   90   4.0   1,000   700   400   5.0   20.0   10.0  
Zone 3, SubZone 3   10.0   3.50   16.00   1.5   125   5.0   7,000   1,000   800   5.0   22.0   10.0  
Zone 4   10.0   1.75   13.00   1.5   150   5.0   4,000   400   525   3.0   20.0   10.0  
Zone 5   11.0   3.50   14.00   5.0   150   5.0   5,000   1,000   750   6.0   22.0   10.0  
SubZone 7a, 7b, 7c, 7a HW, 7b HW, 7c HW   2.0   1.00   3.50   0.7   30   3.5   500   300   400   7.0   8.0   5.0  
SubZone 8a, 8b, 8c, 8d, 8c HW   1.2   1.00   4.50   0.8   70   5.0   200   300   200   10.0   8.0   5.0  
Aphanitic Meta-Rhyolite, Meta-Rhyolite Porphyry   0.1   0.10   0.20   0.2   9   3.1   200   30   15   0.3   7.5   9.5  
Grey Schist   0.5   0.20   0.75   0.5   10   3.1   900   100   30   0.5   7.0   9.5  
Quartz Mica Schist   0.8   0.50   0.75   0.5   15   3.1   1,000   100   75   2.0   10.0   9.5  

  
Arctic ProjectPage 186
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-10: Summary Statistics of Uncapped and Capped Values for Payable Metal

 

Zone/
Lithology
  Mean   Mean   Mean   Mean   Mean  
  Cu (%)   Pb (%)   Zn (%)   Au (ppm)   Ag (ppm)  
  Uncapped   Capped   Uncapped   Capped   Uncapped   Capped   Uncapped   Capped   Uncapped   Capped  
Zone 1   2.80   2.76   0.83   0.74   4.12   4.03   0.76   0.73   53.3   51.1  
Zone 1a   0.73   0.73   0.54   0.34   1.96   1.82   0.25   0.25   17.5   17.5  
Zone 2   2.19   2.08   0.63   0.61   3.30   3.19   0.78   0.62   43.3   40.0  
Zone 2.5   1.97   1.90   0.59   0.54   3.20   2.93   0.29   0.26   29.8   29.1  
Zone 3   3.11   3.08   0.86   0.77   3.83   3.81   0.39   0.37   38.1   36.6  
Zone 3a   1.38   1.38   1.06   1.06   6.46   6.46   0.00   0.00   24.7   24.7  
zone 4   2.71   2.62   0.90   0.57   3.46   3.29   0.53   0.51   45.2   42.3  
Zone 5   3.67   3.65   1.18   1.03   4.93   4.87   0.95   0.78   58.0   54.7  
Zone 7a   0.22   0.22   0.07   0.07   0.20   0.20   0.22   0.20   5.2   5.2  
Zone 7b   0.60   0.49   0.52   0.17   2.05   0.84   0.24   0.20   15.9   9.2  
Zone 7c   0.62   0.62   0.04   0.04   0.44   0.44   0.20   0.20   5.6   5.6  
Zone 7a HW   0.24   0.19   0.02   0.02   0.17   0.17   0.02   0.02   4.9   3.0  
Zone 7b HW   0.09   0.09   0.02   0.02   0.21   0.21   0.03   0.03   1.4   1.4  
Zone 7c HW   0.10   0.10   0.02   0.02   0.13   0.13   0.03   0.03   1.8   1.8  
Zone 8a   0.58   0.58   0.21   0.21   2.90   2.90   0.60   0.60   14.2   14.2  
Zone 8b   1.16   0.73   0.85   0.56   3.95   2.31   0.32   0.32   29.4   29.4  
Zone 8c   0.36   0.23   0.22   0.20   1.00   0.83   0.26   0.19   7.9   7.9  
Zone 8 HW   0.70   0.70   0.89   0.72   2.09   2.09   1.30   0.37   115.0   41.8  

  
Arctic ProjectPage 187
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-11: Summary Statistics of Uncapped and Capped Values for Deleterious Elements

 

Zone/
Lithology
  Mean   Mean   Mean   Mean   Mean   Mean  
  As ppm   Sb ppm   Cd ppm   Hg ppm   Fe %   S %  
  Uncapped   Capped   Uncapped   Capped   Uncapped   Capped   Uncapped   Capped   Uncapped   Capped   Uncapped   Capped  
Zone 1   1275.2   1251.7   276.8   264.7   192.91   191.03   2.3   2.2   11.29   11.25   6.58   6.50  
Zone 1a   244.5   246.1   96.6   96.6   111.68   102.64   2.0   1.6   5.91   5.91   4.52   4.52  
Zone 2   939.4   810.5   266.6   241.4   160.18   158.07   1.2   1.1   8.70   8.62   5.26   5.17  
Zone 2.5   403.5   325.2   158.1   126.0   169.01   160.17   1.6   1.4   9.95   9.49   6.44   6.38  
Zone 3   1074.6   1048.7   123.7   119.8   212.05   211.35   1.1   1.1   9.27   9.18   5.69   5.54  
Zone 3a   0.0   0.0   0.0   0.0   0.00   0.00   0.0   0.0   0.00   0.00   0.00   0.00  
zone 4   1169.2   912.9   103.4   88.1   179.17   173.39   1.4   1.2   8.19   8.16   4.96   4.68  
Zone 5   1101.6   1061.3   222.4   213.6   261.36   258.50   2.5   2.5   10.93   10.82   7.53   6.84  
Zone 7a   128.1   128.1   68.8   68.8   13.94   13.94   0.6   0.6   4.71   4.71   3.81   3.81  
Zone 7b   214.2   196.1   105.0   70.8   117.17   68.43   3.8   2.6   6.06   5.04   4.54   3.93  
Zone 7c   209.2   209.2   75.7   75.7   22.07   22.07   1.4   1.4   3.76   3.76   3.08   3.08  
Zone 7a HW   26.6   26.6   11.0   11.0   7.40   7.40   0.9   0.9   2.80   2.77   0.80   0.68  
Zone 7b HW   50.8   50.2   1.6   1.6   3.16   3.16   0.3   0.3   2.17   2.17   0.58   0.58  
Zone 7c HW   64.9   64.9   20.5   20.5   7.23   7.23   0.8   0.7   2.67   2.67   0.74   0.70  
Zone 8a   0.0   0.0   0.0   0.0   0.00   0.00   0.0   0.0   0.00   0.00   0.00   0.00  
Zone 8b   42.3   42.3   19.2   19.2   40.00   40.00   2.2   2.2   3.58   3.58   1.22   1.22  
Zone 8c   154.5   76.6   106.2   66.9   19.55   19.55   1.4   1.4   4.84   4.23   2.07   1.90  
Zone 8 HW   0.0   0.0   0.0   0.0   0.00   0.00   0.0   0.0   0.00   0.00   0.00   0.00  

  
Arctic ProjectPage 188
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-12: Estimation Domains

 

Estimation Domain Minzones or Lithologies
Bottom Group 1, 1a, 2, and 2.5
Mid Group 3, and 3a
Top Group 4, 5, 7a, 7b, 8c, 8a, 8b, 8c, 8 hw, 7a hw, 7b hw, 7c hw
Talc All high-grade talc zones
Lithology (Outside of Minzone) All non-mineralized lithologies

 

Figure 11-7: Cross-Section of Estimation Domains and Talc

 

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 189
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-13: Variogram Models for the Bottom Group

 

Bottom Group Variograms  
    Variogram Model   GSLIB Angles  
Variable   Nugget   Str. No.   Type   CC   X Range
(m)
  Y Range
(m)
  Z Range
(m)
  ANG1
(degree)
  ANG2
(degree)
  ANG3
(degree)
 
Cu   0.10   1   Exponential   0.50   30   70   7.5   30   0   0  
    2   Spherical   0.40   20   200   8.0        
Pb   0.15   1   Exponential   0.50   30   50   7.5   30   0   0  
    2   Spherical   0.35   220   180   10.0        
Zn   0.15   1   Exponential   0.55   40   60   9.0   30   0   0  
    2   Spherical   0.30   240   200   9.0        
Ag   0.15   1   Exponential   0.45   30   75   6.0   30   0   0  
    2   Spherical   0.43   240   180   12.0        
Au   0.15   1   Exponential   0.30   30   40   12.0   30   0   0  
    2   Spherical   0.55   180   140   12.0        
SG   0.05   1   Exponential   0.60   30   60   9.0   30   0   0  
    2   Spherical   0.35   250   20   12.0        
As   0.15   1   Exponential   0.40   40   60   9.0   30   0   0  
    2   Spherical   0.45   26   200   12        
Cd   0.20   1   Exponential   0.65   55   55   9.0   30   0   0  
    2   Spherical   0.15   200   200   9.0        
Fe   0.15   1   Exponential   0.50   40   55   10.5   30   0   0  
    2   Spherical   0.35   250   200   10.5        
Hg   0.20   1   Exponential   0.65   75   75   9.0   30   0   0  
    2   Spherical   0.15   200   200   12.0        
SG   0.10   1   Exponential   0.60   24   51   10.5   30   0   0  
    2   Spherical   0.30   250   200   12.0        
Sb   0.15   1   Exponential   0.48   30   57   12.0   30   0   0  
    2   Spherical   0.37   220   200   15.0        

  
Arctic ProjectPage 190
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-14: Variogram Models for the Middle Group

 

Middle Group Variograms  
    Variogram Model   GSLIB Angles  
Variable   Nugget   Str. No.   Type   CC   X Range
(m)
  Y Range
(m)
  Z Range
(m)
  ANG1
(degree)
  ANG2
(degree)
  ANG3
(degree)
 
Cu   0.15   1   Exponential   0.65   21   21   12.0   60   0   0  
    2   Spherical   0.20   180   140   12.0        
Pb   0.15   1   Exponential   0.62   39   21   12.0   60   0   0  
    2   Spherical   0.23   220   160   15.0        
Zn   0.15   1   Exponential   0.65   60   24   10.5   60   0   0  
    2   Spherical   0.20   220   160   15.0        
Ag   0.15   1   Exponential   0.50   30   21   12.0   60   0   0  
    2   Spherical   0.35   230   150   18.0        
Au   0.10   1   Exponential   0.45   30   21   15.0   60   0   0  
    2   Spherical   0.45   240   160   20.0        
SG   0.05   1   Exponential   0.20   20   20   12.0   60   0   0  
    2   Spherical   0.75   240   160   20.0        
As   0.20   1   Exponential   0.30   75   50   12.0   60   0   0  
    2   Spherical   0.50   240   160   20.0        
Cd   0.15   1   Exponential   0.50   24   49   7.5   60   0   0  
    2   Spherical   0.35   220   140   9.0        
Fe   0.10   1   Exponential   0.30   39   21   9.0   60   0   0  
    2   Spherical   0.60   240   160   20.0        
Hg   0.15   1   Exponential   0.50   39   21   7.5   60   0   0  
    2   Spherical   0.35   240   160   8.0        
SG   0.10   1   Exponential   0.15   39   21   6.0   60   0   0  
    2   Spherical   0.75   22   160   12.0        
Sb   0.05   1   Exponential   0.20   39   21   12.0   60   0   0  
    2   Spherical   0.75   240   180   18.0        

  
Arctic ProjectPage 191
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-15: Variogram Models for the Top Group

 

Top Group Variograms  
    Variogram Model   GSLIB Angles  
Variable   Nugget   Str. No.   Type   CC   X Range
(m)
  Y Range
(m)
  Z Range
(m)
  ANG1
(degree)
  ANG2
(degree)
  ANG3
(degree)
 
Cu   0.05   1   Exponential   0.60   45   33   6.0   60   0   0  
    2   Spherical   0.35   250   160   9.0        
Pb   0.05   1   Exponential   0.55   45   30   4.5   60   0   0  
    2   Spherical   0.40   240   180   9.0        
Zn   0.20   1   Exponential   0.60   45   33   6.0   60   0   0  
    2   Spherical   0.20   250   160   9.0        
Ag   0.10   1   Exponential   0.50   45   33   6.0   60   0   0  
    2   Spherical   0.40   250   180   9.0        
Au   0.30   1   Exponential   0.50   36   36   6.0   60   0   0  
    2   Spherical   0.20   250   200   12.0        
SG   0.00   1   Exponential   0.50   45   45   6.0   60   0   0  
    2   Spherical   0.50   220   160   13.0        
As   0.15   1   Exponential   0.24   45   33   6.0   60   0   0  
    2   Spherical   0.61   250   160   12.0        
Cd   0.15   1   Exponential   0.30   45   33   4.5   60   0   0  
    2   Spherical   0.55   250   160   12.0        
Fe   0.20   1   Exponential   0.15   36   30   6.0   60   0   0  
    2   Spherical   0.65   240   160   12.0        
Hg   0.10   1   Exponential   0.70   105   105   6.0   60   0   0  
    2   Spherical   0.20   250   250   9.0        
SG   0.15   1   Exponential   0.35   45   33   7.5   60   0   0  
    2   Spherical   0.50   250   160   12.0        
Sb   0.05   1   Exponential   0.65   45   33   7.5   60   0   0  
    2   Spherical   0.30   250   160   12.0        

  
Arctic ProjectPage 192
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 11-16: Variogram Model for Talc

 

Talc Variograms  
    Variogram Model   GSLIB Angles  
Variable   Nugget   Str. No.   Type   CC   X Range
(m)
  Y Range
(m)
  Z Range
(m)
  ANG1
(degree)
  ANG2
(degree)
  ANG3
(degree)
 
Talc   0.10   1   Exponentia   0.55   75   50   10   220   -23   0  
    2   Spherical   0.35   150   80   30        

 

11.4.5Block Model Setup

 

The non-rotated block model was set up in UTM coordinate system, Zone 4, NAD 83 datum. The block model has a parent block size of 10 x 10 x 5 m with a sub-block size of 2 x 2 x 1 m. Table 11-17 shows the Arctic block model parameters.

 

The original sub-block model was regularized to 5 x 5 x 5 m for the Reserve estimation.

 

Table 11-17: Arctic Block Model Parameters

 

Block Size (m)   Model Origin UTM   Boundary Size      
Axis   Parent   Sub   Bottom Left Corner   (m)   No. of Parent Blocks  
X   10   2   612,190   1,910   191  
Y   10   2   7,452,095   1,950   195  
Z   5   1   345   705   141  
Rotation   Dip (degree)
 Azi. (degree)
 

0

0

  -  

 

 

11.5Mineral Resource Estimation

 

Inside mineralized zones, payable metals (Cu, Zn, Pb, Ag and Au), deleterious elements, and SG were estimated using ordinary kriging (OK) in three passes with increasing search ellipsoid sizes. Talc was also estimated in the high-grade talc zones using OK with three passes. Outside of mineralized zones, payable metals, deleterious elements, and SG were estimated using inverse distance to the power of two (ID2) with three passes. Sub-blocks receive the estimated grade values of parent blocks. Each mineralized zone is treated as hard boundaries, meaning that the data from one mineralized zone was not used to estimate grades in other zones. Table 11-18 to Table 11-21 show search ellipsoid sizes, and minimum and maximum number of composites used for the block grade estimations.

  
Arctic ProjectPage 193
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 11-18:Search Ellipsoid Parameters Used for Payable Metals (Cu, Zn, Ag, and Au)

 

Search Parameters Payable Metals  
      Search Distances   Composites   Octants  
Minzone/
Lithology
  Method   Pass   Y (m)   X (m)   Z (m)   Min   Max   Max Per DDH*   Min   Min Comps   Max Comps  
Bottom Group   Ordinary Kriging with LVA**   1   125   100   6   3   12   2   2   1   2  
    2   250   200   12   3   16   2   2   1   2  
    3   750   600   36   1   21   2   -   -   -  
Mid Group   Ordinary Kriging with LVA   1   130   80   9   3   12   2   2   1   2  
    2   260   160   18   3   16   2   2   1   2  
    3   780   480   54   1   21   2   -   -   -  
Top Group   Ordinary Kriging with LVA   1   130   90   6   3   12   2   2   1   2  
    2   260   180   12   3   16   2   2   1   2  
    3   780   540   36   1   21   2   -   -   -  
Lithologies   Inverse Distance squared with LVA   1   125   90   7   3   12   2   2   1   2  
    2   250   180   14   2   16   2   2   1   2  
    3   750   540   42   1   21   2   -   -   -  
Talc   Ordinary Kriging with LVA   1   200   100   35   3   12   2   -   -   -  
    2   400   200   70   3   16   2   -   -   -  
    3   4,000   2,000   700   1   21   2   -   -   -  
                                                   

*DDH: Diamond Drill Hole

 

**LA: Locally Varying Anisotropy

  
Arctic ProjectPage 194
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 11-19:Search Ellipsoid Parameters Used for Deleterious Elements

 

Search Parameters Deleterious Elements  
        Search Distances   Composites   Capped   Octants  
Minzone/
Lithology
  Method   Pass   Y (m)   X (m)   Z (m)   Min   Max   Max Per DDH     Min   Min Comp   Max Comp  
Bottom Group   Ordinary Kriging with LVA   1   45   60   6   3   12   2   No   -   -   -  
    2   90   120   12   2   16   2   No   -   -   -  
    3   780   600   36   1   21   2   Yes   -   -   -  
Mid Group   Ordinary Kriging with LVA   1   45   30   9   3   12   2   No   -   -   -  
    2   90   60   18   2   16   2   No   -   -   -  
    3   780   480   54   1   21   2   Yes   -   -   -  
Top Group   Ordinary Kriging with LVA   1   60   45   6   3   12   2   No   -   -   -  
    2   120   90   12   2   16   2   No   -   -   -  
    3   780   510   36   1   21   2   Yes   -   -   -  
Lithologies   Inverse Distance squared with LVA   1   60   45   6   3   12   2   No   -   -   -  
    2   120   90   12   2   16   2   No   -   -   -  
    3   780   510   36   1   21   2   Yes   -   -   -  

 

Table 11-20:Search Ellipsoid Parameters Used for Talc

 

Search Parameters Talc  
        Search Distances   Composites   Octants  
Minzone/
Lithology
  Method   Pass   Y (m)   X (m)   Z (m)   Min   Max   Max Per DDH   Min   Min Comp   Max Comp  
Talc   Ordinary Kriging with LVA   1   200   100   35   3   12   2   -   -   -  
    2   400   200   70   3   16   2   -   -   -  
    3   4,000   2,000   700   1   21   2   -   -   -  

  
Arctic ProjectPage 195
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 11-21:Search Ellipsoid Parameters Used for SG

 

Search Parameters Specific Gravity  
        Search Distances   Composites   Octants  
Minzone/
Lithology
  Method   Pass   Y (m)   X (m)   Z (m)   Min   Max   Max Per DDH   Min   Min Comp   Max Comp  
Bottom Group   Ordinary Kriging with LVA   1   130   100   6   2   12   -   -   -   -  
    2   260   200   12   1   15   -   -   -   -  
    3   780   600   36   1   15   -   -   -   -  
Mid Group   Ordinary Kriging with LVA   1   130   80   9   2   12   -   -   -   -  
    2   260   160   18   1   15   -   -   -   -  
    3   780   480   54   1   15   -   -   -   -  
Top Group   Ordinary Kriging with LVA   1   115   85   6   2   12   -   -   -   -  
    2   230   170   12   1   15   -   -   -   -  
    3   690   510   36   1   15   -   -   -   -  
Lithologies   Inverse Distance squared with LVA   1   125   90   7   2   12   -   -   -   -  
    2   250   180   14   1   15   -   -   -   -  
    3   750   540   42   1   15   -   -   -   -  

  
Arctic ProjectPage 196
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Locally Varying Anisotropy (LVA) was used to orient search ellipsoids at each block centroid location. The LVA parameters were calculated using each mineralized zone top and bottom surfaces. Table 11-10 shows search ellipsoids, at two different block locations, oriented by LVA parameters at each location following the orientation of the mineralized Zone 5 wireframes used for Cu estimation within the mineralized Zone 5.

 

Figure 11-8:LVA Search Ellipsoids Used in Minzone 5 (Red, Top Group) for Cu Estimation

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

 

11.5.1Validation

 

11.5.1.1Visual Inspection

 

A detailed visual inspection of the block model was conducted in both section and plan to compare estimated grades against underlying sample data. This included confirmation of the proper coding of blocks within the respective domains.

 

Figure 11-9 to Figure 11-13 show East-West cross-section maps for the payable metals block grade and composite database used for the estimation. In general, globally, block estimates compared well with composites.

  
Arctic ProjectPage 197
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-9:East-West Cross-Section for Cu Block Model and Composite Data, Looking North (Resource pit depicted in red)

 

 

 

Source: Ambler Metals, 2022.

 

Figure 11-10:East-West Cross-Section for Zn Block Model and Composite Data, Looking North (Resource pit depicted in red)

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 198
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-11:East-West Cross-Section for Pb Block Model and Composite Data, Looking North (Resource pit depicted in red)

 

 

Source: Ambler Metals, 2022.

 

Figure 11-12:East-West Cross-Section for Ag Block Model and Composite Data, Looking North (Resource pit depicted in red)

 

 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 199
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-13:East-West Cross-Section for Au Block Model and Composite Data, Looking North (Resource pit depicted in red)

 

 

 

Source: Ambler Metals, 2022.

 

11.5.1.2Statistical Validation

 

Comparing the basic statistics of the OK block model with the Nearest Neighbour (NN) model help quantify whether the estimate is over or underestimated. In general, Wood considers differences of less than five percent between the two models mean grades is reasonable for validating global grade bias.

 

Summary statistics of payable metal mean grades for the main mineralized zones (Zones 1, 3, and 5) are shown in Table 11-22. Globally, the models validate well as OK estimated block model mean grades and declustered composites (the nearest neighbours model) means are close except for some smaller domains. These smaller domains were estimated with a small number of samples, which needs further investigation. In other minor mineralized domains, some domains show larger differences due to the lack of supporting drill hole data.

 

11.5.1.3Swath Plots

 

Swath plots are used to detect any spatial-geographical bias in an estimated model. Plots compare average grades of the NN and estimated models over swaths that are typically one block wide in all directions.

 

The estimated models (ID2 and OK) and NN estimates swaths should follow the same trend with the NN plot typically experiencing higher highs and lower lows than the smoother estimated models. In areas where there are large discrepancies or deviations from each other, the models should be further investigated to determine the reason and modify as required.

  
Arctic ProjectPage 200
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

There is good correspondence between the models in most areas. The validation results indicate that the OK model is a reasonable reflection of the underlying sample data.

 

Figure 11-14 to Figure 11-18 show swath plots for the payable metals for the main mineralized zones (zone 1, 3 and 5).

  
Arctic ProjectPage 201
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 11-22:Statistics of OK and NN for Payable Metals for the Main Mineralized Zones

 

        Mean Cu
(%)
  Mean Pb
(%)
  Mean Zn
(%)
  Mean Au
(g/t)
  Mean Ag
(g/t)
 
Minzone   No. of Blocks   OK   NN   % Diff   OK   NN   % Diff   OK   NN   % Diff   OK   NN   % Diff   OK   NN   % Diff  
Zone 1   693,631   2.587   2.448   -5   0.736   0.694   -6   3.860   3.636   -6   0.706   0.661   -6   50.022   47.206   -6  
Zone 3   870,408   2.801   2.759   -2   0.684   0.657   -4   3.565   3.494   -2   0.314   0.323   3   33.120   33.283   0  
Zone 5   930,886   3.451   3.287   -5   1.016   0.982   -3   4.808   4.394   -9   0.723   0.709   -2   51.867   50.029   -4  

  
Arctic ProjectPage 202
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-14:Cu Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 203
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-15:Pb Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction

 

(GRAPHIC)

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 204
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-16:Zn Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 205
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-17:Ag Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 206
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-18:Au Swath Plot, OK (Red), NN (Green) and Composite (Black), North-South Direction

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

 

11.5.1.4Validation of Block Model with the New Drill Holes

 

Wood reviewed the new drilling data collected after the closing of the database for the current mineral resource model by displaying copper grades for both the drill holes and the current block model in East-West cross sections.

 

Copper grades in the new drill holes match well with the current block model copper grades visually and confirm mineralization zones defined.

 

  
Arctic ProjectPage 207
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

11.5.2Mineral Resource Classification

 

The Mineral Resources were classified in accordance with the standards and definitions of S-K 1300. The classification parameters are defined relative to the distance between sample data and are intended to encompass zones of reasonably continuous mineralization that exhibit the desired degree of confidence in the estimate.

 

Classification parameters are generally linked to the scale of a deposit: a relatively narrow, high-grade deposit would likely be mined using selective mining methods, at a much lower daily rate than a large, low-grade, bulk mineable deposit. The scale and selectivity of these two examples differs significantly and is reflected in the drill-hole spacing required to achieve the desired level of confidence to define a volume of material that represents, for example, a year of production. Based on engineering studies completed to date, the Arctic deposit is amenable to open pit extraction methods at a production rate of approximately 10,000 t/d. A drill hole spacing study, which tests the reliability of estimates for a given volume of material at varying drill hole spacing, suggests that drilling on a nominal 100 m grid pattern would provide annual estimates of sufficient confidence to classify them in the Indicated category. These results were combined with grade and indicator variograms and other visual observations of the nature of the deposit in defining the criteria for mineral resource classification as described below. At this stage of the Project, there is insufficient density of drilling information to support the definition of Mineral Resources in the Measured category. Manual “smoothing” of the Resource Classification was not performed.

 

The Wood QP expects the majority of Inferred Mineral could be upgraded to Indicated Mineral Resources with additional exploration.

 

Table 11-23 shows the Mineral Resource classification criteria used in the resource model. Figure 11-19 and Figure 11-20 show plan view and cross-section map of the Mineral Resource Classification model.

 

Table 11-23:Mineral Resource Classification and Criteria

 

Resource Classification Criteria
Measured Not used
Indicated Mineralized zones parent block centroid estimated with composites within 100 m of three drill holes.
Inferred Mineralized zones parent block centroid estimated with composites within 150 m of one drill holes.

  
Arctic ProjectPage 208
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 11-19:Oblique View of Mineral Resource Classification Model

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

 

Figure 11-20:Cross-Section of Mineral Resource Classification Model, Looking North

 

 Source: Ambler, 2022.

  
Arctic ProjectPage 209
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

11.5.3Uncertainties Affecting Mineral Resource Confidence Classification

 

Factors that may affect the mineral resource estimate are listed below:

 

·Uncertainties in sampling and drilling methods, data processing and handling

 

·Metal price assumptions.

 

·Uncertainties in the assumptions used to generate the cut-off grade.

 

·Uncertainties in the geological and mineralization shapes, and geological and grade continuity assumptions.

 

·Uncertainties in the historically predicted (estimated) SG values determined by Random Forest Regressor.

 

·Uncertainties in the geotechnical, mining, and metallurgical recovery assumptions.

 

·Uncertainties represented by historical assay values for payable metals.

 

·Uncertainties in the resource estimation process including parameters such as capping values, search ellipsoids, variogram models, number of composites.

 

·Uncertainties to the input and design parameter assumptions that pertain to the conceptual pit constraining the estimates.

 

·Uncertainties in the assumptions made to the concentrate marketability, payability and penalty terms.

 

·Uncertainties in the assumptions regarding the continued ability to access the site, retain mineral and obtain surface rights titles, obtain environment and other regulatory permits, and maintain the social license to operate.

 

The above uncertainties were considered in Mineral Resource classification criteria and in the opinion of the QP all issues relating to all relevant technical and economic factors likely to influence the prospect of economic extraction can be resolved with further work.

 

11.5.4Reasonable Prospects for Economic Extraction

 

The Arctic deposit comprises several zones of relatively continuous moderate to high-grade polymetallic mineralization that extends from surface to depths of over 250 m below surface. The deposit is potentially amenable to open pit extraction methods. The “reasonable prospects for economic extraction” was tested using a floating cone pit shell derived based on a series of technical and economic assumptions considered appropriate for a deposit of this type, scale, and location. These parameters are summarized in Table 11-24.

 

Using these parameters, copper equivalent grades that incorporate contributions of the five different metals present in the deposit were calculated using the following equation:

 

CuEq%= (Cu% x 0.92) +(Zn% x 0.290) + (Pb% x 0.231) + (Au g/t x 0.398) + (Ag g/t x 0.005)

 

Using these parameters and the copper equivalent formula, an open pit marginal cut-off grade of 0.5% CuEq was determined.

 

Table 11-24:Parameters Used to Generate a Resource Constraining Pit Shell

 

Optimization Parameters          
Item   Unit   Value  
Open Pit Mining Cost   $/t   3  
Process Cost + G&A   $/t   35  
Pit Slope   degree   43  
Copper Price   $/lb   3.00  
Lead Price   $/lb   0.90  
Zinc Price   $/lb   1.00  
Gold Price   $/oz   1,300  
Silver Price   $/oz   18  
Metallurgical Recovery:  Copper   %   92  
Lead   %   77  
Zinc   %   88  
Gold   %   63  
Silver   %   56  

 

11.5.4.1                   Basis of Commodity Prices and Cost Assumptions

 

Copper, lead, zinc, gold and silver are exchange-traded contracts on all of the world’s major commodity exchanges.

 

The input costs, recoveries and metal prices used to determine the metal cut-off for the Mineral Resources are based on the Arctic 2020 pre-feasibility study and are within the range of the long-term metal price forecast by mining analysts and investment banks at that time. These metal prices and cost inputs presented in Table 11-24 were fixed over the LOM of 13 years.

 

  
Arctic ProjectPage 210
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

11.5.5Mineral Resource Statement

 

The Mineral Resource estimate inclusive of Mineral Reserves is stated in Table 11-25. The Mineral Resource estimate exclusive of Mineral Reserves is stated in Table 11-26. All Indicated Mineral Resources have been converted to Mineral Reserves. Mineral Resources are reported in place (point of reference) and on a 100% basis; however, Trilogy’s attributable interest is 50% of the tonnes and metal content.

 

Figure 11-21 shows the isometric view of the Arctic resource model.

 

Table 11-25:Mineral Resource Summary Table, Inclusive of Mineral Reserves

 

        Average Grade   Contained Metal Content  
Confidence   Tonnage    Cu   Pb   Zn   Au   Ag   Cu   Pb   Zn   Au   Ag  
Category   (Mt)   (%)   (%)   (%)   (g/t)   (g/t)   (Mlb)   (Mlb)   (Mlb)   (koz)   (Moz)  
Indicated   35.7   2.98   0.79   4.09   0.59   45.2   2,347   621   3,216   675   52  
Inferred   4.5   1.92   0.70   2.93   0.43   35.6   189   69   288   62   5  

Notes:

 

1.Mineral Resources are current as of November 30, 2022 and were verified by a Wood QP.

2.Mineral Resources were prepared in accordance with the standards and definitions of S-K 1300.

3.Mineral Resources stated are contained within a conceptual pit shell developed using metal prices of $3.00/lb Cu, $0.90/lb Pb, $1.00/lb Zn, $1300/oz Au and $18/oz Ag and metallurgical recoveries of 92% Cu, 77% Pb, 88% Zn, 63% Au and 56% Ag and operating costs of $3/t mining and $35/t process and G&A. The assumed average pit slope angle is 43°.

4.The cut-off grade is 0.5% copper equivalent. CuEq = (Cu%x0.92) + (Zn%x0.290) + (Pb%x0.231) + (Au g/tx0.398) + (Ag g/tx0.005).

5.As a result of flattening the north end of the reserve pit to stabilize the pit wall due to the presence of talc, a portion of the reserve pit extended beyond the resource constraining pit shell. Approximately 568kt of 1.72% Cu, 0.77% Pb, 0.23 g/t Au and 21.3 g/t Ag in the Indicated category, and approximately 319 kt of 2.01% Cu, 0.87% Pb, 2.53% Zn, 0.50 g/t Au and 37.5 g/t Ag in the Inferred category were added to the Mineral Resource tabulation.

6.The Mineral Resource estimate is reported inclusive of those Mineral Resource that were converted to Mineral Reserves.

7.Trilogy’s attributable interest is 50% of the tonnage and contained metal stated in the table.

8.Figures may not sum due to rounding.

 

Table 11-26:Mineral Resource Summary Table, Exclusive of Mineral Reserves

 

        Average Grade   Contained Metal Content  
Confidence   Tonnage   Cu   Pb   Zn   Au   Ag   Cu   Pb   Zn   Au   Ag  
Category   (Mt)   (%)   (%)   (%)   (g/t)   (g/t)   (Mlb)   (Mlb)   (Mlb)   (koz)   (Moz)  
Inferred   4.5   1.92   0.70   2.93   0.43   35.6   189   69   288   62   5  

 

Notes:

 

1.Mineral Resources are current as of November 30, 2022 and were verified by a Wood QP.

2.Mineral Resources were prepared in accordance with the standards and definitions of S-K 1300.

3.Mineral Resources stated are contained within a conceptual pit shell developed using metal prices of $3.00/lb Cu, $0.90/lb Pb, $1.00/lb Zn, $1,300/oz Au and $18/oz Ag and metallurgical recoveries of 92% Cu, 77% Pb, 88% Zn, 63% Au and 56% Ag and operating costs of $3/t mining and $35/t process and G&A. The assumed average pit slope angle is 43°.

  
Arctic ProjectPage 211
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

4.As a result of flattening the north end of the reserve pit to stabilize the pit wall due to the presence of talc, a portion of the reserve pit extended beyond the resource constraining pit shell and approximately 319 kt of 2.01% Cu, 0.87% Pb, 2.53% Zn, 0.50 g/t Au and 37.5 g/t Ag in the Inferred category were added to the Mineral Resource tabulation.

5.The cut-off grade is 0.5% copper equivalent. CuEq = (Cu%x0.92) + (Zn%x0.290) + (Pb%x0.231) + (Au g/tx0.398) + (Ag g/tx0.005).

6.The Mineral Resource estimate is reported exclusive of those Mineral Resources that were converted to Mineral Reserves.

7.Trilogy’s attributable interest is 50% of the tonnage and contained metal stated in the table.

8.Figures may not sum due to rounding.

 

Figure 11-21:Isometric View of Arctic Mineral Resource

 

(GRAPHIC) 

 

Source: Ambler Metals, 2022.

  
Arctic ProjectPage 212
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

12MINERAL RESERVE ESTIMATES

 

12.1Introduction

 

Mineral Reserves is classified in accordance with standards and definitions of S-K 1300. Modifying factors were applied to the Indicated Mineral Resources to convert them to Probable Mineral Reserves. Mineral Reserves for the Arctic deposit incorporate appropriate mining dilution and mining recovery estimations for the open pit mining method.

 

The Mineral Reserve estimate for the Arctic deposit is based on the resource block model provided by Ambler Metals, as well as other information provided by Ambler Metals, and information generated by Wood based on the preceding 2020 Feasibility Study.

 

The following sections outlines the procedures used to estimate the Mineral Reserves. The mine plan is based on the detailed mine design derived from the optimal pit shell produced by applying the Pseudoflow algorithm.

 

12.2Basis of Commodity Prices and Cost Assumptions Used in Pit Optimization and Cut-Off Determination

 

To establish the long-term metal price forecast the Wood QP used a combination of information derived from 22 financial institutions, from pricing used in technical reports filed with Canadian regulatory authorities over the previous 12-month period, from pricing reported by major mining companies in public filings such as annual reports in the previous 12-month period, spot pricing, and three-year trailing average pricing. From this assessment the Wood QP considers industry consensus on a long-term price forecast on Mineral Reserves as stated in Table 12-1.

 

The costs stated in Table 12-1 are based on the 2020 Feasibility study and are fixed over the 13-year LOM production.

 

12.3Pit Optimization

 

The pit shell that defines the ultimate pit limit, was derived in Whittle using the Pseudoflow pit optimization algorithm. The optimization procedure uses the block value and pit slopes to determine a group of blocks representing pits of valid slopes that yield the maximum profit. The block value is calculated using information stored in the geological block model, commodity prices, mining and processing costs, process recovery, and the sales cost for the metals produced. The pit slopes are used as constraints for removal precedence of the blocks (Xiaoyu Bai, et al., 2017). Table 12-1 provides a summary of the primary optimization inputs.

 

Table 12-1:Optimization Inputs

 

Parameter   Unit   Value   Cu Conc.   Pb Conc.   Zn Conc.  
                       
Metal Prices  
Copper   $/lb   3.46   -   -   -  
Lead   $/lb   0.91   -   -   -  

  
Arctic ProjectPage 213
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Parameter   Unit   Value   Cu Conc.   Pb Conc.   Zn Conc.  
Zinc   $/lb   1.12   -   -   -  
Gold   $/oz   1,615   -   -   -  
Silver   $/oz   21.17   -   -   -  
Discount Rate   %   8   -   -   -  
Dilution and Mine Losses   %   Estimated in a block-by-block basis, adding up 30% to 40%.  
Mining Cost  
Reference Bench Elevation   m   790   -   -   -  
Base Cost   $/t   2.52   -   -   -  
Incremental Mining Cost           -   -   -  
Uphill (below 790m)   $/t/5m   0.02   -   -   -  
Downhill (above 790m)   $/t/5m   0.012   -   -   -  
Process Costs  
Operating Cost   $/t milled   18.31   -   -   -  
G&A   $/t milled   5.83   -   -   -  
Sustaining Capital   $/t milled   2.37   -   -   -  
Road Toll Cost   $/t milled   8.04   -   -   -  
Closure   $/t milled   4.27   -   -   -  
Processing Rate   kt/d   10   -   -   -  
Process Recovery   
Copper   %   -   89.9   2.4   2.7  
Lead   %   -   8.1   79   2.2  
Zinc   %   -   3.4   0.4   90.6  
Gold   %   -   10.9   62.1   5.4  
Silver   %   -   26.4   63.1   3.4  
Payable – Main Element   %   -   96.5   95   85  
Treatment Cost   $/dmt   -   80   160   215  
Refining Cost  
Copper   $/lb   -   0.08   -   -  
Gold   $/oz   -   5   10   -  
Silver   $/oz   -   0.5   1.25   -  

  
Arctic ProjectPage 214
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Parameter   Unit   Value   Cu Conc.   Pb Conc.   Zn Conc.  
Transport Cost   $/dmt   271   -   -   -  
Concentrate Losses   % weight   0.42   -   -   -  
Insurance Cost   %   0.15   -   -   -  
Representation/Marketing   $/wmt   2.5   -   -   -  
Slope Angles  
Geotechnical Sector 1 (2L-E)   degrees   Variable based on slope dip direction. IRA ranging from 26 to 56.  
Geotechnical Sector 2 (2L-W)   degrees   Variable based on slope dip direction IRA ranging from 38 to 56.  
Geotechnical Sector 3 (2U)   degrees   Variable based on slope dip direction IRA ranging from 29 to 56.  
Geotechnical Sector 4 (3)   degrees   Variable based on slope dip direction IRA ranging from 30 to 56.  
Geotechnical Sector 5 (4L)   degrees   Variable based on slope dip direction IRA ranging from 34 to 56.  
Geotechnical Sector 6 (4U)   degrees   Variable based on slope dip direction IRA ranging from 37 to 56.  
Royalties  
NANA Surface Use   %NSR   1   -   -   -  

 

Wood converted the resource model provided by Ambler Metals from a sub-blocked to a regularized percentage model. The model was imported into the optimization software containing grades, block percentages, material density, slope sectors, rock types, and net smelter return. The optimization run was carried out only using Indicated Mineral Resources to define the optimal mining limits.

 

The optimization run included 46 pit shells defined according to different revenue factors, ranging from a revenue factor of 0.3 to 1.2, where a revenue factor of 1 is the base case. To select the optimal pit shell that defines the ultimate pit limit, Wood conducted a pit-by-pit analysis to evaluate the contribution of each incremental shell to the discounted cash flow (DCF), assuming a processing plant capacity of 10 kt/d and a yearly discount rate of 8% (Figure 12-1). Following this analysis, pit shell 17 (revenue factor of 0.62) was selected. Although the DCF for the Selected pit shell is slightly lower in comparison to the Base Case pit shell, the selected pit shell eliminates mining 39.3 Mt of waste while only losing 1.9 Mt of ore. The DCF does not account for initial capital expenditures.

 

  
Arctic ProjectPage 215
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 12-1:Pit-by-Pit Analysis

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

Following the pit-by-pit analysis, a secondary exercise was performed on the selected pit shell to incorporate a higher level of detail to the slope definition and to force the northeast wall to fully mine areas in the pit where talc zones are problematic for slope stability. As a result of this exercise, material contained within the selected pit shell increases by 13 Mt of waste and 0.8 Mt of ore. The final pit shell to be used as the basis for the ultimate pit and mine planning for the Arctic Project is shown in Figure 12-2.

  
Arctic ProjectPage 216
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 12-2:Selected Pit Shell

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

12.4Dilution and Ore Losses

 

The Mineral Resources for the Arctic Project were reported undiluted. In order to determine Mineral Reserves, dilution was applied to the resource model in two steps: internal dilution and contact dilution.

 

Internal dilution accounts for the waste material entrenched within the deposit at the scale of the selective mining unit (SMU) block size. Contact dilution accounts for the dilution and ore losses caused by a block mixing with its surroundings during the mining process and includes ore losses.

 

For transition points between ore and waste, ore loss and dilution will take place as shown in Figure 12 3. Blocks with diluted grades that fell below the cut-off grade were treated as waste and removed from the Mineral Reserve as ore losses.

 

  
Arctic ProjectPage 217
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 12-3:Contact Dilution Concept

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

Internal dilution was estimated as follows:

 

The resource model was regularized to 5x5x5 m to better approximate mining selectivity. The regularized block model contained the volume percentage within the mineralized zone, and grades and densities for the mineralized zone and host rock.

 

The grades were diluted per each block using the formula:

 

(GRAPHIC) 

 

Contact dilution was estimated as follows:

 

To simulate the concept shown in Figure 12-3, the grade of a given block was diluted by blending it with 20% of the tonnage from each of its four lateral blocks . The tonnage of the diluted block remains unchanged in the block model.

 

For lateral blocks classified as Inferred Mineral Resource, grade was set to zero for dilution purposes.

 

The procedure is illustrated in Figure 12-4.

  
Arctic ProjectPage 218
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 12-4:Contact Dilution Estimation Procedure

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

12.5Cut-Off Definition

 

The cut-off was based on the NSR value. The NSR has been calculated according to the following formulas:

 

(GRAPHIC) 

 

Cost, metal pricing and sales costs are listed in Table 12-1. Variable process recoveries used in the NSR calculation are listed in Table 12-2.

 

The marginal cut-off pays for all the costs except the mining cost and was estimated to be $38.8/t. The economic cut-off pays for all the costs including the mining cost and varies by depth with incremental mining cost between $41.3/t to $ 42.2/t. Ore above the marginal cut-off was included in the Mineral Reserves.

 

Table 12-2: Variable Process Recoveries Used in the NSR Calculation

 

Parameter  Cu Conc   Pb Conc   Zn Conc 
Copper   92.2    0.8    2.1 
Lead   16.0    62.2    4.5 
Zinc   1.9    1.3    87.6 
Gold   47.2    26.1    3.3 
Silver   32.7    48.7    5.8 

 

  
Arctic ProjectPage 219
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

12.6Mineral Reserves Statement

 

Individual blocks captured within the final pit design were identified as either ore or waste by applying the parameters shown in Figure 12 1 with the exception of the metallurgical recoveries which were applied variably on a block-by-block basis. Using the partial block percentages within the final pit design, the ore tonnage and average grades were calculated. The Mineral Reserves statement is shown in Table 12 2. The point of reference for the Mineral Reserves is defined at the point where the ore is delivered to the processing plant. Trilogy’s attributable interest is 50% of the tonnes of the Mineral Reserves.

 

Table 12-3:Mineral Reserve Statement

 

    Tonnage   Average Grade  
Confidence Category   Mt   Cu (%)   Pb (%)   Zn (%)   Au (g/t)   Ag (g/t)  
Probable Mineral Reserves   46.7   2.11   0.56   2.90   0.42   31.8  

 

Notes:

 

1.Mineral Reserves estimates are current as of November 30, 2022 and were prepared by a Wood QP.

2.Mineral Reserves were estimated assuming open pit mining methods and include a combination of internal and contact dilution. Total dilution is expected to be between 30% and 40%. Pit slopes vary by sector and range from 26° to 56°. A marginal NSR cut-off of $38.8 /t is used.

3.Mineral Reserves are based on prices of $3.46/lb Cu, $0.91/lb Pb, $1.12/lb Zn, $1,615/oz Au, and $21.17/oz Ag.

4.Variable process recoveries averaging 92.2% Cu in Cu concentrate, 62.2% Pb in Pb concentrate, 87.6% Zn in Zn concentrate, 16.0% Pb in Cu concentrate, 1.9% Zn in Cu concentrate, 47.2% Au in Cu concentrate, 32.7% Ag in Cu concentrate, 0.8% Cu in Pb concentrate, 1.3% Zn in Pb concentrate, 26.1% Au in Pb concentrate, 48.7% Ag in Pb concentrate, 2.1% Cu in Zn concentrate, 4.5% Pb in Zn concentrate, 3.3% Au in Zn concentrate, 5.8% Ag in Zn concentrate.

5.Mineral Reserves are based on mining cost of $2.52/t incremented at $0.02/t/5m and $0.012/t/5m below and above 790 m elevation, respectively.

6.Costs applied to processed material following: process operating cost of $18.31/t, G&A of $5.83/t, sustaining capital cost of $2.37/t, closure cost of $4.27/t, road toll cost of $8.04/t.

7.Strip ratio (waste:ore) is 7.3:1.

8.Selling terms following: payables of 96.5% of Cu, 95% of Pb and 85% of Zn, treatment costs of $80/t Cu concentrate, $160/t Pb concentrate and $215/t Zn concentrate; refining costs of $0.08/lb Cu in Cu concentrate, and $10/oz Au, $1.25/oz Ag in Pb concentrate; and transport cost $270.98/t concentrate.

9.Fixed royalty percentage of 1% NSR.

10.Trilogy’s attributable interest is 50% of the tonnage stated in the table.

 

12.7Risk Factors that Could Materially Affect the Mineral Reserve Estimates

 

In the opinion of the QP, the Mineral Reserves are subject to the types of risks common to open pit polymetallic mining operations that exist in Alaska and may be materially affected by the following risk factors:

 

Changes in metal prices from what was assumed;

 

Changes to the assumptions used to generate the cut-offs;

 

Changes in local interpretations of mineralization geometry and continuity of mineralized zones;

 

Changes to geological and mineralization shapes, and geological and grade continuity assumptions;

 

Changes to density and domain assignments from what was assumed;

 

Changes to geotechnical, hydrogeological design assumptions;

 

Changes to mining and metallurgical recovery assumptions;

 

Change to the input and design parameter assumptions that pertain to the open pit constraining the estimates;

  
Arctic ProjectPage 220
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Assumptions as to concentrate marketability, payability and penalty terms;

 

Assumptions as to the continued ability to access the site, retain mineral tenure and obtain surface rights titles, obtain environment and other regulatory permits, and maintain the social license to operate.

 

More specifically the presence of certain talc layers in the rock have not been included in the current geological model and could affect the metallurgical recoveries and slope stability. Additionally, there is currently no developed surface access to the Arctic Project area and beyond. Access to the Arctic Project is proposed to be via AAP, a road approximately 340 km (211 miles) long, extending west from the Dalton Highway where it would connect with the proposed Arctic Project area. Construction costs of the road are not yet final. The working assumption is that AIDEA would arrange financing in the form of a public-private partnership to construct and arrange for the construction and maintenance of the access road. AIDEA would charge a toll to multiple mining and industrial users (including the Arctic Project) in order to pay back the costs of financing the AAP. The amount paid in tolls by any user would be affected by the cost of the road, its financing structure, and the number of mines and other users of the road which could also include commercial transportation of materials and consumer items that would use the AAP to ship concentrates to the Port of Anchorage in Alaska and possibly provide goods and commercial materials to villages in the region.

 

The Mineral Reserve estimation assumes toll payments of $5.52/t processed, plus a road maintenance fee of $2.52/t milled processed, resulting in a total road toll and maintenance LOM unit cost of $8.04/t processed. There is a risk that a negotiated road toll agreement may result in higher costs than what has been assumed.

  
Arctic ProjectPage 221
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

13MINING METHODS

 

13.1Overview

 

The following section outlines the parameters and procedures used for the design of the mine as a conventional open pit, estimates of the Mineral Reserves within the open pit mine plan, and establishes a practical mining schedule for this Report. The mine plan is based on the Probable Mineral Reserves presented in Section 12.

 

13.2Mine Design

 

The Arctic Project is designed as a conventional truck-shovel operation with 144 t trucks and 15 m3 shovels. The pit design includes four nested phases to balance stripping requirements while satisfying the concentrator requirements.

 

The design parameters include a ramp width of 30 m, road grades of 10%, bench height of 5 m, targeted mining width between 70 and 100 m, berm interval of 20 m, variable slope angles by sector and a minimum mining width of 30 m.

 

Wood performed a review of the pit geotechnical and hydrogeological assessment performed by SRK. Based on the review of the information provided by SRK, Wood agrees with their conclusions. Figure 13-1 shows the geotechnical slope design domains defined by SRK on the 2020 pit design. Table 13-1 shows a summary of the geotechnical design parameters recommended by SRK.

 

  
Arctic ProjectPage 222
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-1:Geotechnical Slope Design Domains

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

Table 13-1:Geotechnical Design Parameters

 

Slope Design Domain   Face Slope Dip Direction (*)   Bench Height (m)   IRA (°)   Design BFA* (°)   Design Bench Width (m)  
2L-E   330 - 020   10   40   65   7.5  
    20     65   14.5  
  020 - 050   20   56   80   10.0  
  050 - 100   20   45   65   10.5  
  100 - 160   20   38   65   16.0  
  160 - 250   60   26   27   8.0  
  250 - 300   20   38   80   22.0  
  300 - 330   10   50   80   7.5  
    20   55   80   10.5  

  
Arctic ProjectPage 223
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Slope Design Domain   Face Slope Dip Direction (*)   Bench Height (m)   IRA (°)   Design BFA* (°)   Design Bench Width (m)  
2L-W   330 - 020   10   40   65   7.5  
    20     65   14.5  
  020 - 140   20   56   80   10.0  
  140 - 170   20   45   65   10.5  
  170 - 250   60   38   41   8.0  
  250 - 300   20   40   65   14.5  
  300 - 330   10   50   80   7.5  
    20   55   80   10.5  
2U   330 - 020   20   45   65   10.5  
  020 - 140   20   56   80   10.0  
  140 - 170   20   45   65   10.5  
  170 - 250   60   29   31   8.0  
  250 - 300   20   40   65   14.5  
  300 - 330   10   55   80   7.5  
    20     80   10.5  
3   310 - 020   10   38   65   8.0  
    20     65   16.0  
  020 - 050   20   56   80   10.0  
  050 - 100   20   45   65   10.5  
  100 - 140   20   56   80   10.0  
  140 - 220   20   38   65   16.0  
  220 - 310   60   30   32   8.0  
4L   330 - 020   10   40   65   7.5  
    20     65   14.5  
  020 - 050   20   56   80   10.0  
  050 - 100   20   45   65   10.5  
  100 - 140   20   56   80   10.0  
  140 - 180   20   38   65   16.0  
  180 - 300   60   34   37   8.0  
  300 - 330   10   38   65   8.0  
    20     65   16.0  
4U   330 - 020   20   45   65   10.5  
  020 - 050   20   56   80   10.0  
  050 - 100   20   45   65   10.5  
  100 - 140   20   56   80   10.0  
  140 - 180   20   45   65   10.5  
  180 - 260   60   37   40   8.0  
  260 - 300   20   40   65   14.5  
  300 - 330   10   50   80   7.5  
    20   55   80   10.5  

 

*BFA: Bench Face Angle

 

As mentioned in Section 13.9.10 according to the SRK’s geotechnical recommendations, a large talc zone located in the northeast pit slope must be completely removed. To achieve this, a pit optimization giving dummy values to the talc zone blocks was performed. This pit optimization was used as the basis for the mine design.

 

The smoothed final pit design contains approximately 46.7 Mt of ore and 340.2 Mt of waste for a resulting stripping ratio of 7.3:1. Within the 46.7 Mt of ore, the average grades are 2.11% Cu, 2.90% Zn, 0.56% Pb, 0.42 g/t Au and 31.8 g/t Ag. Figure 13-2 shows the ultimate pit design. Figure 13-3 and Figure 13-4 show pit sections comparing the mine design to the selected pit shells for each optimization.

 

  
Arctic ProjectPage 224
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-2:Ultimate Pit Design

 

(GRAPHIC) 

 

Source: Wood, 2022.

  
Arctic ProjectPage 225
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-3:Section 1 Showing Mine Design and Selected Pit Shells (looking NW)

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

Figure 13-4:Section 2 Showing Mine Design and Selected Pit Shells (looking W)

 

(GRAPHIC) 

 

Source: Wood, 2022.

  
Arctic ProjectPage 226
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

13.3Interim Phase Design

 

The deposit is mined in four nested phases, including the ultimate pit limit. During pre-production, the phasing strategy maximizes waste mining while minimizing the ore tonnage. This is primarily due to the lack of space to build ore stockpiles. In addition, the phasing strategy maintains enough exposed ore to guarantee the continuous operation of the process plant during the production. The phase designs are shown in Figure 13-5 to Figure 13-7.

 

Figure 13-5:Phase 1 Design

 

(GRAPHIC) 

 

Source: Wood, 2022.

  
Arctic ProjectPage 227
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-6:Phase 2 Design

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

Figure 13-7:Phase 3 Design

 

(GRAPHIC) 

 

Source: Wood, 2022.

  
Arctic ProjectPage 228
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

13.4Waste Rock Facilities and Stockpile Designs

 

The design and construction of the WRF should ensure physical and chemical stability during and after mining activities. To achieve this, the waste areas and stockpiles are designed to account for benching, drainage, geotechnical stability, and concurrent reclamation.

 

The WRF design criteria include 23.5-m wide benches every 20 m in elevation with 2.5H:1V overall slopes, lifts from 5-m to 20-m high, and a 33% swell factor for estimating volumes. The overburden mined represents approximately 6% of the total waste and it is considered to be encapsulated within the waste rock. Figure 13-8 shows the WRF design.

 

Figure 13-8:Waste Rock Facility

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

A stockpile is required to store the ore mined during the pre-production period. Because this stockpile is depleted at the beginning of the operation, it is located within the WRF footprint and has a total storage capacity of 223,000 m3. This volume is enough to satisfy the maximum stockpiling capacity of approximately 776 kt. Figure 13-9 shows the stockpile design with respect to the WRF at the end of the pre-production period.

  
Arctic ProjectPage 229
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-9:Ore Stockpile

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

13.5Production Schedule

 

The production schedule includes the processing ramp up. The processing plant ramp-up considers the normal inefficiencies related to the start of operations, and includes the tonnage processed as well as the associated recoveries, which increases the design capacity during the second quarter of operation. The mine requires two years of pre-production before the start of operations in the processing plant.

 

The deposit is mined in four nested phases, including the ultimate pit limit. The schedule was developed in months for the pre-production period and the first two years of production, in quarters from Year 3 to Year 5 of production, and annually thereafter. The scheduling constraints set the maximum mining capacity at 35 Mt per year and the maximum number of benches mined per year at ten in each phase.

 

The production schedule based on the Probable Mineral Reserves shows a LOM of 15 years, including two years of pre-production. The amount of rehandled mill feed is 776 kt, which is the ore mined during the pre-production period. The average grades to the mill over the LOM are 2.11% Cu, 2.90% Zn, 0.56% Pb, 0.42 g/t Au, 31.83 g/t Ag and 2.92% Talc. The annual LOM summary schedule is shown in Table 13-2 and Figure 13-10. Figure 13-11 shows the annual tonnage mined by phase.

 

  
Arctic ProjectPage 230
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 13-2: Production Schedule

 

   Tonnage  Average Grade 
   To Mill  Mine to  Total  Cu  Zn  Pb  Au  Ag  Talc 
Period  Direct
(kt)
  Stockpile
(kt)
  Total
(kt)
  Stockpile
(kt)
  Waste
(kt)
  (%)  (%)  (%)  (g/t)  (g/t)  (%) 
Year -2  -  -  -  493  26,907  -  -  -  -  -  - 
Year -1  -  -  -  283  34,761  -  -  -  -  -  - 
Year 1  2,235  776  3,012  -  31,842  2.59  2.87  0.55  0.36  33.07  1.59 
Year 2  3,650  -  3,650  -  30,540  2.06  2.48  0.50  0.38  29.03  3.35 
Year 3  3,650  -  3,650  -  27,365  1.94  2.61  0.56  0.39  28.42  7.46 
Year 4  3,650  -  3,650  -  26,350  1.88  2.82  0.58  0.42  28.03  4.13 
Year 5  3,650  -  3,650  -  25,580  1.87  2.86  0.53  0.33  26.36  32.97 
Year 6  3,650  -  3,650  -  24,913  1.99  2.51  0.49  0.34  28.66  3.31 
Year 7  3,650  -  3,650  -  24,413  2.37  3.11  0.57  0.40  31.75  3.2 
Year 8  3,651  -  3,651  -  19,850  2.00  3.107  0.61  0.44  32.44  1.32 
Year 9  3,650  -  3,650  -  20,350  2.05  2.51  0.39  0.37  28.50  4.56 
Year 10  3,650  -  3,650  -  17,922  2.33  3.09  0.53  0.50  36.80  2.76 
Year 11  3,650  -  3,650  -  15,350  2.41  2.41  0.64  0.56  38.68  21.95 
Year 12  3,650  -  3,650  -  11,629  1.98  3.15  0.66  0.47  34.08  0.59 
Year 13  3,529  -  3,529  -  2,126  2.09  3.20  0.69  0.52  38.39  0.14 
Total  45,915  776  46,691  776  338,726  2.06  2.83  0.55  0.41  31.10  2.89 

  
Arctic ProjectPage 231
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-10: Annual Production Schedule

 

 

Source: Wood, 2022

 

Figure 13-11: Total Tonnage Mined, Scheduled by Phase

 

 

Source: Wood, 2022

  
Arctic ProjectPage 232
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

13.6Waste Material Handling

 

Waste is hauled to the WRF using 144 t trucks. The construction sequence starts at the bottom of the dump by dumping the material in 5-m lifts, leaving a 23.5-m bench every four lifts. The resulting overall slope angle of the dump face is 2.5H:1V.

 

13.7Operating Schedule

 

The Arctic mine is scheduled to operate 24 hours a day, seven days a week utilizing three rotating crews working 12-hour shifts. There are two 12-hour shifts scheduled, consisting of a day shift and a night shift. A number of duties only require work during the dayshift hours. For these duties, two crews rotate to provide seven day-a-week day-shift coverage.

 

For the rotating mine operations crews, approximately three hours are lost per day to standby time, inclusive of two hours for breaks, 20 minutes for fuelling 20 minutes for shift change, and 20 minutes for blast delay (Table 13-3).

 

Over a year, approximately 13 days are lost to poor weather conditions, predominantly in the wintertime. It is assumed that the equipment is manned but delayed during these weather events.

 

Table 13-3: Gross Operating Hours per Year

 

Time Definition  Hydraulic Shovel   Front End
Loaders
   Trucks   Drills 
Calendar Time                    
Calendar Days   365    365    365    365 
Shifts per day   2    2    2    2 
Shift length (h)   12    12    12    12 
Calendar Time (h/a)   8,760    8,760    8,760    8,760 
Available Time                    
Availability   85%   85%   85%   85%
Down time (h/a)   1,314    1,314    1,314    1,314 
Available Time (h/a)   7,446    7,446    7,446    7,446 
Gross Operating Time                    
Operating Standby   -    -    -    - 
Lunch & breaks (min/day)   120    120    120    120 
Fueling (min/day)   20    20    20    30 
Shift change (min/day)   20    20    20    20 
Meetings (min/day)   20    20    20    20 
Blasting (min/day)   -    -    -    20 
Weather (d/a)   13    13    13    13 
Operating Standby (h/a)   1,196    1,196    1,196    1,351 
Gross Operating Hours (h/a)   6,250    6,250    6,250    6,095 

 

Accounting for standby time and weather delays, equipment accumulates on average 6,250 gross operating hours (GOH) per year in the example above. For productivity calculations, it is assumed that following preproduction, the trucks and shovels are in a productive cycle of approximately 50 minutes each hour, or 83% of the time. For drills, the productive utilization is lower and in the range of 65% based on benchmarking with similar mines.

  
Arctic ProjectPage 233
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

As with mine operations, mine maintenance is scheduled to work a 24/7 schedule to allow for continuous maintenance coverage. However, the majority of planned maintenance work is done during the day shift with a skeleton crew scheduled for the night shift.

 

Blasting is only scheduled during the day shift. Two blasting crews rotate on a 12-hour day shift, for seven day-a-week coverage.

 

13.8Mining Equipment

 

A conventional owner-operated truck fleet utilizing a combination of hydraulic shovels and front-end loaders (FELs) is planned. The truck fleet consists of large trucks for waste stripping and for mining the ore zones. The trucks are diesel powered with a combined capacity to mine a maximum of 40 Mt/a operating on a combination of 5 m and 10 m benches. The loading fleet is also diesel powered. Blasting is contract performed with explosives manufactured off-site and delivery to site by trucks.

 

Equipment requirements are estimated annually over the life of the mine. Equipment sizing and numbers are based on the mine plan, the operational factors shown in Table 13-4, and a twenty-four hour per day, seven day a week work schedule.

 

Table 13-4: Equipment Utilization and Efficiency

 

Description  Average Mechanical Availability (%)   Efficiency
(%)
 
171 mm Production Drill   83%   65%
265 t/15 m3 Hydraulic Face Shovel   85%   83%
124 t/12 m3 Front End Loader   85%   83%
144 t Haul Truck   85%   83%
41t Articulated Truck   86%   83%
26 t/5 m3 Front End Loader   86%   83%
68 t/4 m3 Hydraulic Excavator   86%   83%
35 t/1.4 m3 Hydraulic Excavator   85%   83%
74 t/455 kW Track Dozer   85%   83%
50 t/419 kW Rubber Tired Dozer   85%   83%
40 t Articulated Sand Truck   85%   83%
33 t/217 kW Motor Grader   85%   83%
35,000-litre water truck   85%   83%
41t Articulated Fuel/Lube Truck   85%   83%

 

13.8.1Blasting

 

Blasting operations are contracted to a blasting explosives provider who is responsible for the blast design, loading, stemming, and initiation. Bulk emulsion is manufactured off-site. The explosive provider transports explosive material from Fairbanks, Alaska. The explosive is stored in four explosive silos with 80-ton capacity each: two silos for storing Ammonium Nitrate and the other two for storing emulsion produced on site.

  
Arctic ProjectPage 234
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

In performing the explosive services, the blasting contractor is proposing to provide:

 

Two five person blasting crews providing seven day a week coverage

 

Transportation of the explosive from Fairbanks to site

 

Additionally, two (2) Mobile Manufacturing Unit (MMU) trucks and one stemming truck are provided by the mine. The MMU explosive trucks delivers a bulk emulsion product when required.

 

Two types of Heavy ANFO blend (HA) are used: 70% emulsion/30% Ammonium Nitrate Fuel Oil (ANFO) for wet material, and 30% emulsion/70% ANFO for dry material, with specific gravity of 1.25 g/cm3 and 1.23 g/cm3, respectively.

 

The wall control design patters are based on the 2022 Arctic Drill and Blast Study recommendations There are three main types of geotechnical zones within the pit: one group in the North and East walls, where the slope design is governed by the shallower foliation, with IRA lower than 38° and with geotechnical berms every 60 m, other group with IRA of between 38° and 47°, and other group with IRA greater than 47°. Pre-split blasting only used for the third group with IRA greater than 47°. For other zones, multiple stab trim holes are used for face outlining.

 

Table 13-5 shows the design parameters for production and wall control blasting.

 

Table 13-5: Blasting Design Input

 

Description  Units  Waste  Ore Dry  Waste
Wet
  Ore Wet  Trim 1
(1)
  Trim 2
(2)
  Trim 3
(3)
  Pre-split
(3)
 
Rock Density  t/m3  2.76  3.22  2.76  3.22  2.76  2.76  2.76  2.76 
Explosive     HA37   HA37   HA73   HA73   HA37   HA37   HA37   HA37 
Explosive Density  kg/m3  1,230  1,230  1,250  1,250  1,230  1,230  1,230  1,230 
Bench Height  m  10  10  10  10  8.3  10  10  10 
Hole Diameter  m  0.171  0.171  0.171  0.171  0.171  0.171  0.171  0.171 
Burden  m  5.1  4.2  5.1  4.2  6.0  5.3  3.7  1.5 
Spacing  m  5.9  4.8  5.9  4.8  5.5  4.8  3.9  2.5 
Sub drill  m  1.0  1.0  1.0  1.0  0.0  0.1  0.0  0.0 
Stemming  m  3.5  4.0  3.5  4.0  3.8  5.4  5.9  9.6 
Drill length per hole  m  11  11  11  11  8.3  10  10  10 
Rock Volume per hole  m3  301  202  301  202  273  258  143  38 
Rock Tonnage per hole  t  830  649  830  649  755  712  394  104 
Rock Tonnage  t/m  75  59  75  59  91  70  39  10 
Explosive Column  m  7.5  7.0  7.5  7.0  4.5  4.7  4.1  0.4 
Weight of explosive  kg  212  198  215  201  128  133  116  13 
Powder Factor (by rock volume)  kg/m3  0.70  0.98  0.72  1.00  0.47  0.52  0.81  0.33 
Powder Factor  kg/t  0.26  0.30  0.26  0.31  0.17  0.19  0.29  0.12 

  
Arctic ProjectPage 235
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1.Geotechnical zones with IRA below 38 degrees and 60 m bench height. Domains 2L-E, 2L-W and 4L.
2.Geotechnical zones with IRA between 38 and 40 degrees and bench height shorter than 20 m. Domain 3 and 4L.
3.Geotechnical zones with IRA greater than 47 degrees and bench height shorter than 20 m. Domain 2U and 4U.

 

Although material is mined on a combination of 5 and 10 m benches, all material is drilled and blasted on 10 m benches.

 

The powder factor for ore is 0.3 kg/t and 0.26 kg/t for waste. For trim, variable powder factors were used depending on the characteristics of the geotechnical zone. Table 13-6 provides a summary of the material blasted on an annual basis.

 

Table 13-6: Material Blasted Quantities

 

Period  Powder Factor (kg/t)  Waste Blasted (kt)  Ore Blasted (kt)  Trim Blasted(1) (kt)  Total Blasted (kt) 
Year -2  0.26  26,157  493  750  27,400 
Year -1  0.25  30,262  283  4,499  35,044 
Year 1  0.25  29,404  2,235  2,438  34,077 
Year 2  0.25  25,754  3,650  4,786  34,190 
Year 3  0.25  21,939  3,650  5,426  31,015 
Year 4  0.25  22,156  3,650  4,194  30,000 
Year 5  0.25  21,181  3,650  4,669  29,500 
Year 6  0.25  19,687  3,650  5,226  28,563 
Year 7  0.25  20,176  3,650  4,237  28,063 
Year 8  0.25  15,976  3,651  3,873  23,500 
Year 9  0.26  16,856  3,650  3,494  24,000 
Year 10  0.26  15,809  3,650  2,113  21,572 
Year 11  0.26  12,217  3,650  3,133  19,000 
Year 12  0.25  7,949  3,650  3,680  15,280 
Year 13  0.27  -  3,529  2,126  5,655 
Total  0.25  285,524  46,691  54,643  386,859 

 

1.Includes Pre-split.

 

Blasting products consumed on an annual basis are shown in Table 13-7.

 

Table 13-7: Explosives Quantities

 

Period  ANFO (t)  Emulsion Bulk (t)  Detonators Pyrotechnic
(Units)
  Boosters 0.45kg (Units) 
Year -2  3,147  3,669  33,301  33,301 
Year -1  3,980  4,416  42,917  42,917 
Year 1  3,932  4,491  42,135  42,135 
Year 2  3,958  4,369  43,090  43,090 
Year 3  3,596  3,895  39,403  39,403 
Year 4  3,493  3,851  38,027  38,027 

  
Arctic ProjectPage 236
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Period  ANFO (t)  Emulsion Bulk (t)  Detonators Pyrotechnic
(Units)
  Boosters 0.45kg (Units)  
Year 5  3,438  3,752  37,537  37,537  
Year 6  3,331  3,587  36,557  36,557  
Year 7  3,285  3,594  35,920  35,920  
Year 8  2,767  3,004  30,543  30,543  
Year 9  2,836  3,105  31,369  31,369  
Year 10  2,568  2,878  28,298  28,298  
Year 11  2,269  2,457  25,538  25,538  
Year 12  1,847  1,917  21,310  21,310  
Year 13  746  722  9,206  9,206  
Total  45,193  49,708  495,151  495,161  

 

13.8.2Drilling

 

Throughout the project life, drilling is required for both ore control and production blasting. Rock fragmentation achieved through blasting is the overriding design criteria for the drill hole pattern design. The blast hole drilling design from Section 13.8.1 with the drill penetration rates described below are used to estimate drilling requirements.

 

Drill penetration is a function of bit size, bit load, drilling method, and rock strength properties. Wood relied on SRK’s 2022 Pre-Feasibility Study Geotechnical and Hydrogeological Assessment report. SRK completed unconfined compressive testing (UCS) and point load testing on Arctic’s primary rock types. The results of the uniaxial compressive tests for the primary ore hosting rocks (lithological units) are shown in Table 13-8. The weighted average UCS value for the ore hosting rocks is 83 MPa and 59 MPa for the waste areas.

  
Arctic ProjectPage 237
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 13-8: Rock Type Weight and UCS

 

Lithology  UCS (MPa)  Samples (Units) 
Ore Hosting       
Black to Grey Schist (GS)  97  14 
Massive Sulphide (MS)  56  6 
Semi-massive Sulphide (SMS)  68  3 
Average Ore  83  23 
Waste       
Aphanitic Metarhyolite (AMR)  88  5 
Chlorite Schist (CHS)  20  2 
DIKE  62  2 
Debris Flow (DM)  71  3 
Button Schist (MRP)  73  9 
Quartz-Felspar-Mica Schist (QFMS)  64  5 
Quartz- Mica Schist QMS  50  5 
QMSP  62  2 
Talc Schist (TS)  1  2 
CHTS  3  2 
Average Waste  59  37 

 

Instantaneous penetration rates (IPR) were calculated based on UCS data, rock factor and the Workman Szumanski (1996, 1997) formula. Using the Workman Szumanski (1996, 1997) formula Penetration Rate shown in Equation 13-1, and the inputs in Table 13-9, the instantaneous penetration rate (P) for waste and ore were estimated at 67 m/h and 45 m/h, respectively.

 

Equation 13-1: Workman, Szumanski (1996,1997) Formula

 

 

 

Table 13-9: Workman, Szumanski (1996,1997) Inputs

 

Item  Waste  Ore  
RF - Rock factor  148  120  
Sc – UCS (MPa)  59  83  
P – pulldown (lb)  50,000  50,000  
D - Bit Size (mm)  171  171  
P/D - Pulldown (kg/m)  133,000  133,000  
RPM – Revolutions per minute  90  90  
P - Instantaneous Pen Rate (m/h)  67  45  

  
Arctic ProjectPage 238
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The total drilling cycle time accounts for drilling time, tramming time between holes, setup time, and bit change time. Because the CAT MD6250main drill equipment can drill to a 13.6 m depth, no time is required for drill steel addition. The average penetration rate shown in Table 13-10 also assumes 65% productive utilization, or 39 minutes out of 60 minutes that the drill is in the drilling cycle.

 

Table 13-10: Drill Penetration Rates

 

Material   IPR  Drill Hole
Length
  Tram
Time
  Setup
Time
  Bit
Change
  Total
Cycle
  NOH Pen
Rate
  GOH Pen
Rate1
 
Type  (m/h)  (m)  (min)  (min)  (min)  (min)  (m/h)  (m/h)  
Waste  67  11  0.55  3.00  0.38  13.81  47.79  31.1  
Ore  45  11  0.55  3.00  0.38  18.61  35.47  23.1  

 

1Assumes 65% efficiency.

 

Table 13-11 shows the drill requirements, the meters drilled, the hours operated, and the average penetration rate by period. During Year -2, two production drills are required. From Year -1 to Year 7, mining requires three production drills. Following Year 7, drill requirements drop to two and after Year 12, drill requirements drop to one along with a drop in of total tonnes mined. Penetration rates average 29.8 m/h over the LOM.

 

Table 13-11: Drill Requirements and Performance

 

Period  Drills Required (Units  Meters Drilled (m)  Gross Operating Hours
(GOH)
  Average Penetration Rate
(m/h)
 
Year -2  2  375,812  12,795  29.4  
Year -1  3  470,586  15,783  29.8  
Year 1  3  469,235  15,811  29.7  
Year 2  3  472,384  16,299  29.0  
Year 3  3  429,789  14,661  29.3  
Year 4  3  418,968  14,089  29.7  
Year 5  3  413,125  13,742  30.1  
Year 6  3  400,873  13,206  30.4  
Year 7  3  396,514  13,008  30.5  
Year 8  2  335,237  11,659  28.8  
Year 9  2  344,926  11,616  29.7  
Year 10  2  313,880  11,616  27.0  
Year 11  2  278,087  9,218  30.2  
Year 12  2  228,627  7,708  29.7  
Year 13  1  97,266  3,007  32.3  
Total     5,445,309  184,219  29.6  

  
Arctic ProjectPage 239
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The 2022 Arctic Drill and Blast study (Floyd, 2022) recommends 90° presplit for zones with inter-ramp angle greater than 47°, with the same drill hole diameter than the production drill holes. Therefore, only rotary drills are considered at this point. The study also suggests that in case the 90° presplit is not suitable according to field testing, smaller diameters, inclined holes, and a top head hammer (THH) drill with a 121 mm bit will be needed.

 

13.8.3Loading

 

Wood completed an equipment trade-off study based in quantitative and qualitative characteristic of the equipment and vendor’s quotations received. From the trade-off study, the primary loading units selected are two 15 m3 hydraulic shovels. After Year 11 only one hydraulic shovel is required. To assist the hydraulic shovels, two 12 m3 front end loaders (FEL) are scheduled until Year 7 of production, dropping to one until the end of the LOM. The FEL is also used for stockpile rehandling, all of which is scheduled in Year 1. Loading requirements are shown in Table 13-12.

 

Table 13-12: Loading Requirements and Performance

 

   15 m3 shovel  12 m3 FEL  
      Productivity     Productivity  
   Number  (t/GOH)  Number  (t/GOH)  
Year -2   2   1,241   2  829  
Year -1   2   1,698   2  995  
Year 1   2   1,718   2  1,006  
Year 2   2   1,673   2  1,003  
Year 3   2   1,690   2  750  
Year 4   2   1,643   2  738  
Year 5   2   1,630   2  729  
Year 6   2   1,606   2  714  
Year 7   2   1,576   2  698  
Year 8   2   1,501   1  813  
Year 9   2   1,531   1  834  
Year 10   2   1,384   1  734  
Year 11   2   1,224   1  615  
Year 12   1   1,532   1  311  
Year 13   1   675   1  233  
Average     1,488     733  

 

The 15 m3 shovel five-pass loads the 144 t truck in approximately three minutes. The LOM production rate averages 1,488 dry t/GOH, compared to the maximum productivity of 1,923 dry t/GOH shown in Table 13-13. The peak productivity scheduled for the shovel occurs in Years 1, when it is scheduled at 1,718 dry t/GOH.

  
Arctic ProjectPage 240
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 13-13: Hydraulic Shovel Productivity

 

Loader     15 m3 Shovel  
Truck  Unit  144 t Truck  
Bucket Capacity  m3  15  
Bucket Capacity  t  30  
Truck Capacity  m3  94  
Truck Capacity  t  144  
Insitu Bulk Density  t/m3  2.8  
Bulk Factor     1.3  
Loose Density  t/m3  2.15  
Moisture  %  3 %
Fill Factor     0.86  
Effective Bucket Capacity  m3  12.97  
Wet/Loose Density  t/m3  2.22  
Tonnes/Pass  t  28.80  
Theoretical Passes (Volume)     7.25  
Theoretical Passes (Weight)     5.00  
Actual Passes     5  
Truck Load  m3  64.85  
Truck Load  t  144.0  
Truck Fill % (Volume)     69 %
Truck Fill % (Weight)     100 %
Loader Cycle Time  seconds  35  
Loader Spot Time  seconds  30  
Load Time per Truck  seconds  170  
Maximum Truck Loads per hour     21.18  
Maximum Productivity  (wet t/adj. NOH)  3,049  
Maximum Productivity  (wet t/NOH)  2,379  
Maximum Productivity  (wet t/GOH)  1,982  
Maximum Productivity  (dry t/GOH)  1,923Sh  
Maximum Productivity  (wet t/d)  34,460  
Maximum Productivity  (dry t/a)  12,200,469  
Maximum Productivity  (dry t/d)  33,426  

 

The FEL seven-pass loads the 144 t truck in approximately three and a half minutes. The LOM production rate averages 797 dry t/GOH, compared to the maximum productivity of 1,139 dry t/GOH shown in Table 13-14. The peak productivity scheduled for the FELs occurs in Year 1, when the FEL is scheduled at 1,008 dry t/GOH.

  
Arctic ProjectPage 241
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 13-14: Front End Loader Productivity

 

Loader     12 m3 FEL  
Truck  Unit  144 t Truck  
Bucket Capacity  m3  11.7  
Bucket Capacity  t  21.0  
Truck Capacity  m3  94.0  
Truck Capacity  t  144.0  
Insitu Bulk Density  t/m3  2.8  
Bulk Factor     1.3  
Loose Density  t/m3  2.15  
Moisture  %  3.0 %
Fill Factor     0.79  
Effective Bucket Capacity  m3  9.26  
Wet/Loose Density  t/m3  2.22  
Tonnes/Pass  t  20.57  
Theoretical Passes (Volume)     10.15  
Theoretical Passes (Weight)     7.00  
Actual Passes     7.00  
Truck Load  m3  64.85  
Truck Load  t  144.0  
Truck Fill % (Volume)     69 %
Truck Fill % (Weight)     100 %
Loader Cycle Time  seconds  42  
Loader Spot Time  seconds  35  
Load Time per Truck  seconds  287  
Maximum Truck Loads per hour     12.54  
Maximum Productivity  (wet t/adj. NOH)  1,806  
Maximum Productivity  (wet t/NOH)  1,409  
Maximum Productivity  (wet t/GOH)  1,174  
Maximum Productivity  (dry t/GOH)  1,139  
Maximum Productivity  (wet t/d)  20,246  
Maximum Productivity  (dry t/a)  7,168,141  
Maximum Productivity  (dry t/d)  19,639  

 

In addition to the primary loading units, a 5 m3 FEL is paired with two 41 t articulated trucks throughout the mine life for bench development/pioneering work and winter snow removal. A 3.8 m3 excavator is also used to maintain haul roads and scale the pit walls as needed.

  
Arctic ProjectPage 242
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

13.8.4Hauling

 

From the TCO analysis, the primary hauling unit selected for ore and waste mining is a mechanical drive truck with a payload capacity of 144 t wet, assuming a standard body with a full set of liners. The dry capacity is estimated at 140 t, assuming 3% moisture and carry back.

 

Wood estimated truck requirements on a period-by-period basis using travel distances from a road network developed within Minesight®. Haul segment distances were reported for each material type from their location on a mining bench to their final destination. Assuming 2% rolling resistance for haul roads, travel speeds were estimated from the manufacture’s performance curves, and applied to each haul segment to estimate travel time. To better reflect actual speeds in an operating environment, the truck speeds were speed-limited according to Table 13-15.

 

Table 13-15: Truck Speed Limits

 

Segment  Loaded
(kph)
  Empty
(kph)
 
Maximum Overall Speed  45  45  
Maximum Speed within 100 m of dump face and shovel  25  25  
Maximum Speed on a 10% downhill grade  30  30  

 

Table 13-16 provides the adjusted speeds and fuel burns by haul grade used to estimate truck requirements and diesel fuel usage for the 144 t trucks.

 

Table 13-16: Truck Speed Limits

 

Actual
Grade
(%)
  Haul
Loaded
(kph)
  Return
Empty
(kph)
  Fuel
Loaded
(l/h)
  Return
Empty
(l/h)
 
-10%  30  30.0  19.1  19.1  
10%  11.5  27  190.8  190.8  
Flat Ex-pit  45  45  124.9  72.8  
Flat In-pit  25  25  162.0  72.7  
Idle  -  -  19.1  

 

Truck requirements by period are shown in Table 13-17 for 144 t trucks, together with the average one-way haul distance, average fuel consumption, and average truck productivity. Fourteen trucks are commissioned during pre-production. During Year 1 the fleet is ramped up to 15, reaching its peak. After Year 9, truck requirements drop to 14. Following Year 10, the 144 t truck requirements decline with declining mining rates.

  
Arctic ProjectPage 243
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 13-17: Truck Requirements and Performance

 

   Trucks Required  Average one-way Haul
Distance
  Average Fuel Burn  Average Truck
Production
 
   #  (m)  l/GOH  t/GOH  
Year -2  11  2,693  62  384  
Year -1  14  2,558  63  387  
Year 1  15  3,127  64  362  
Year 2  15  2,953  68  356  
Year 3  15  2,874  69  346  
Year 4  15  3,034  73  318  
Year 5  15  3,117  76  316  
Year 6  15  2,962  77  310  
Year 7  15  3,131  80  305  
Year 8  15  3,353  82  275  
Year 9  15  3,734  85  262  
Year 10  14  3,847  88  252  
Year 11  14  4,039  91  222  
Year 12  12  4,206  92  209  
Year 13  4  3,449  87  232  
Average  -  3,173  75  317  

 

13.8.5Support

 

Support equipment includes excavators, track dozers, rubber-tired dozers (RTDs), sand trucks, graders, water trucks, fuel/lube trucks, and water trucks. The major tasks for the support equipment include:

 

Bench and road maintenance

 

Shovel support/clean-up

 

Blasting support/clean-up

 

WRF maintenance

 

Stockpile construction/maintenance

 

Road building/maintenance

 

Pioneering and clearing work

 

Field equipment servicing

 

A description of each support equipment fleet follows:

 

35 t Excavator – One excavator scheduled throughout the mine life. Its primary functions are to support dewatering, maintain pit drainage, break rocks utilizing the rock breaker attachment, and backup the 5 m3 FEL.

  
Arctic ProjectPage 244
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

72t/455 kW track dozers are estimated at 0.5 dozers per production blast hole drill and production loading unit. The dozer fleet peaks at 4 machines in pre-production. Their primary functions are to maintain pit floors, maintain dumps and stockpiles, build pit roads, and clean final pit walls. Due to limited mobility, the 72 t dozers are transported between working areas using a 90 t capacity transport trailer. The transport is also used to transport the 65 t drills and the 35 t excavator.

 

47t/419 kW rubber-tired dozer requirements are estimated at approximately one RTD per hydraulic shovel. Their primary function is to maintain shovel floors, provide drill pattern clean-up, clear rock spillage, and provide backup dump and stockpile maintenance. At peak, two-wheel dozers support two 15 m3 shovels and associated mining areas.

 

41t Articulated Sand Truck – One articulated truck is fitted with a sander and used to support winter operations throughout the LOM.

 

227 kW motor graders are estimated at approximately one grader per 8 trucks. Their primary function is to maintain roads, dump areas, and pit areas. Two graders are scheduled along the life of the mine, dropping to 1 the last year, Y12.

 

Two 35,000 litre water trucks are estimated to support the mine operation. During the winter season, from October to April, water trucks are lightly scheduled. They are primarily used for watering the drills and for fire patrol; nonetheless, even during the winter season roads become dusty. During May to September, when dust suppression requirements are at their highest, the water trucks are fully scheduled.

 

Fuel/lube truck requirements are estimated at a ratio of one lube truck per 10 pieces of tracked field equipment. They are used to fuel and service shovels and other tracked field equipment. At peak, the mine operates one fuel/lube truck.

 

One 1.4 m3 backhoe is scheduled throughout the mine life. Its primary functions are to support dewatering, maintain pit drainage, and break rocks utilizing the rock breaker attachment.

 

Support equipment requirements are shown in Table 13-18.

 

Table 13-18: Support Equipment

 

Period  35 t
Excavator
  Bulldozer -
455 kW
  Wheel dozer -
419 kW
  Motor grader –
217 kW
  Sand Truck -
41 t
  Water Truck -
35000 l
  Fuel / Lube
Truck
  Backhoe -
1.4 m3
 
Year -2  1  4  2  2  1  2  1  1  
Year -1  1  4  2  2  1  2  1  1  
Year 1  1  4  2  2  1  2  1  1  
Year 2  1  4  2  2  1  2  1  1  
Year 3  1  4  2  2  1  2  1  1  
Year 4  1  4  2  2  1  2  1  1  
Year 5  1  4  2  2  1  2  1  1  
Year 6  1  4  2  2  1  2  1  1  
Year 7  1  3  2  2  1  2  1  1  
Year 8  1  3  2  2  1  2  1  1  
Year 9  1  3  2  2  1  2  1  1  
Year 10  1  3  2  2  1  2  1  1  

  
Arctic ProjectPage 245
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Period  35 t
Excavator
  Bulldozer -
455 kW
  Wheel dozer -
419 kW
  Motor grader –
217 kW
  Sand Truck -
41 t
  Water Truck -
35000 l
  Fuel / Lube
Truck
  Backhoe -
1.4 m3
 
Year 11  1  2  1  2  1  2  1  1  
Year 12  1  2  1  2  1  2  1  1  
Year 13  1  2  1  2  1  2  1  1  

 

13.8.6Auxiliary

 

To support mine maintenance and mine operation activities, a fleet of auxiliary equipment is required. The types and numbers of auxiliary equipment are listed in Table 13-19in five-year increments.

 

Table 13-19: Auxiliary Equipment

 

Equipment  Year 1  Year 5  Year 13  
Mine Maintenance           
Truck Mounted 40 t Crane  1  1  1  
100 t Rough Terrain  1  1  1  
5t Rough Terrain Forklift  2  2  2  
10t Forklift  2  2  2  
Mechanic Service Truck  3  3  3  
Small Fuel/Lube truck  1  1  1  
55 kW Skid Steer  1  1  1  
Flatbed Truck  2  2  2  
45t Telehandler  1  1  1  
Mine Operations           
Small backhoe/loader  1  1  1  
Hydraulic hammer/impactor  1  1  1  
90 t Lowboy  1  1  1  
Compactor  1  1  1  
Light Plant  11  8  5  
Transport Tractor  1  1  1  
Tire Handler Truck  1  1  1  
3/4 ton Pickup  4  4  4  
1 ton Pickup  5  4  2  
Crew Bus  5  4  2  
Fleet Management System  1  1  1  
Mine & Geology Software  10  10  10  
Heavy ANFO (blend) Truck  2  2  2  
Stemming Truck  1  1  1  
Laser Scan  2  2  2  
Survey Drones  2  2  2  

  
Arctic ProjectPage 246
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Equipment  Year 1  Year 5  Year 13  
Total Station System  1  1  1  

 

13.8.7Labour

 

Wood developed the staffing plan based on the primary assumptions that the owner will perform the equipment maintenance and the blasting operations will be subcontracted.

 

At peak staffing levels in Year 1, the mine department includes 205 employees including 31 salaried and 174 hourly. The blasting contractor estimated that they will have 10 people on site on two crews including one supervisor, two blaster, two MMU operators per crew.

  
Arctic ProjectPage 247
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The salaried staff is estimated based on level of effort. The hourly staff is estimated on both level of effort and on mobile equipment coverage.

 

Mine maintenance hourly staffing is estimated by multiplying a ratio of mechanic time required by machine-operated hours. Table 13-20 provides a listing of the ratios by machine. Wood used its historical database to estimate ratios for the mine equipment.

 

Table 13-20: Ratio Maintenance Hours to Equipment Operated Hours

 

Equipment  Ratio Maintenance Hours to
Equipment Operated Hours
 
171 mm Production Drill  0.90  
265 t/15 m3 Hydraulic Face Shovel  0.90  
124 t/12 m3 Front End Loader  0.90  
144 t Haul Truck  0.52  
41t Articulated Truck  0.52  
26 t/5 m3 Front End Loader  0.90  
68 t/4 m3 Hydraulic Excavator  0.90  
35 t/1.4 m3 Hydraulic Excavator  0.50  
74 t/455 kW Track Dozer  0.50  
50 t/419 kW Rubber Tired Dozer  0.50  
40 t Articulated Sand Truck  0.50  
33 t/217 kW Motor Grader  0.50  

 

13.9Geotechnical and Hydrogeological Assessments

 

SRK reviewed the previous work and recommendations, identified potential risks and opportunities highlighted in the previous studies and designed the field program and laboratory testing to update the structural, geotechnical and hydrogeological models to support this pre-feasibility study. Detailed slope stability assessments were completed using the previously designed pit shells, dated Nov 2019, and updated slope design recommendations were provided with a focus on the slope stability risk related to potential sliding failure along talc zones in the northeast wall. Wood produced the open pit mine designs that include interim and final phases using these recommendations. SRK completed a geotechnical review of the updated mine designs, which is discussed in Section 13.10. The estimated annual average pit inflow, discussed in Section 13.9.7, has been updated based on the review of the new open pit designs.

  
Arctic ProjectPage 248
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

13.9.1Data Sources

 

SRK has conducted geotechnical and hydrogeological drilling programs to collect information to support the Arctic Project. The locations of the drill holes are presented in Section 7.2.4.

 

13.9.2Geology and Structure

 

The talc alteration occurs as continuous to semi-continuous massive bands that locally host economic mineralization many meters thick to much thinner (2 to 20 cm) bands parallel to the dominant foliation within more competent quartz-mica and quartz-chlorite mica schists. Both occurrences represent potential weak or slip foliation parallel surfaces. Trilogy developed talc wireframes delineating the spatial distribution and extent of the main talc-rich horizons.

 

These wireframes have been updated by SRK as the talc-rich horizons have been further delineated by additional drilling completed in 2021 (Figure 13-12). The focus of the update was to refine the geometry of talc layers that extend behind the northeast and east walls of the designed open pit. The entire talc model is planned to be updated in next phase of the engineering study with the results of the 2022 drill program. These talc wireframes were used in the geotechnical and hydrogeological assessments.

 

Figure 13-12: Isometric View (looking southeast) of Talc Zone Domain Modelled by SRK (2022) Using Leapfrog on the EoY12 design pit

 

 

 

Note: Only talc layers that extend behind the final pit wall are shown. Source: Wood, 2019.

 

Pervasive weathering is present in the upper levels of the Arctic deposit. SRK has reviewed the geotechnical data and core photographs in order to define a base of weathering isosurface that represented the boundary of the upper, more pervasive weathering.

  
Arctic ProjectPage 249
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

In 2019, SRK updated the 3-D structural model by integrating new structural drill hole data into the model, refining existing structures and modelling additional faults. The “structural matrix”, which provides information on the geometry, physical properties and confidence of major and minor structural features, was also updated. The final structural model is shown in Figure 13-13.

 

Figure 13-13: SRK Structural Model (SRK, 2019) used in the Slope Stability Analysis on the EoY12 Design Pit

 

 

  

Source: SRK, 2022.

 

Six structural and geomechanical domains were identified (Figure 13-14). These domains, each containing representative discontinuity sets and major structures, formed the basis of the kinematic assessment.

  
Arctic ProjectPage 250
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-14: Location Plan, Structural and Geomechanical Domains

 

 

  

Source: SRK, 2022.

 

13.9.3Geotechnical Laboratory Testing

 

The historical open pit geotechnical laboratory testing database includes uniaxial compressive strength (UCS) tests, modulus tests for Young’s Modulus and Poisson’s Ratio, triaxial compressive strength (TCS) tests, direct shear (DS) tests, and tilt table tests. The testing programs were directed by SRK (2015, 2016, 2019, 2021), BGC (2012), and URSA (1998) and completed at accredited laboratories in North America that follows industry best practices. SRK reviewed the testing database and utilized reliable and valid test results to derive representative compressive and shear strength values of the intact rock and discontinuities of the Arctic rock mass.

 

Strength anisotropy is known to exist as a result of foliation fabric through the various lithologies in the Arctic rock mass. UCS and TCS tests that have failed primarily along foliation fabric were rejected to minimize the influence of anisotropy to the intact rock strength. The mean and standard deviation values of UCS test results considered for geotechnical assessments are presented in Table 13-21.

  
Arctic ProjectPage 251
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The shear strength of discontinuities and the foliation rock fabric were assessed using DS and tilt table tests (Table 13-22). The test results suggest a variation in the friction angle between different lithologies and discontinuity orientations. After examining the laboratory test results, the peak friction angles of foliation fabric and other discontinuities, respectively, were characterized as 24° and 27°. These values represent the Arctic rock mass excluding the Talc Zone domain.

 

The Talc Zone domain consisting of talc schist (TS) and chlorite-talc schist (ChTS), is the weakest rock type (outside of fault zones) observed at the Arctic deposit. The domain is characterized by low intact rock strength, well developed fabric and low shear strength discontinuity surfaces. The shear strength, extent and persistence of the unit is considered a risk for pit slope stability and was the target of the 2021 and 2022 geotechnical drilling programs.

 

A geotechnical laboratory testing program dedicated to determining the shear strength of the weakest talc layers within the Talc Zone rock mass domain was completed in 2021. The program included both rock and soil TCS and DS tests. Available historical shear strength tests on talc were reviewed using before and after test photographs, and data points interpreted as invalid, or outliers, were removed from the analysis. The assessment indicates that the talc has an approximate peak friction angle of 11° and cohesion of 30 kPa (Figure 13-15). Additional laboratory tests utilizing core samples from the 2022 drilling program is in progress.

 

Table 13-21: Summary of Unconfined Compressive Strength by Lithological Units

 

   Unconfined Compressive Strength 
      UCS (MPa)  Young’s Modulus (GPa)  Poisson’s Ratio 
Litho Code  Valid Results Count  Average  Std Dev  Average  Std Dev  Average  Std Dev 
AMR  5  88  61  22  9  0.19  0.06 
CHS  2  20  -  4  -  0.23  - 
DIKE  2  62  -  19  -  0.25  - 
DM  3  71  -  22  -  0.25  - 
GS  14  97  22  24  11  0.14  0.06 
MRP  9  73  19  18  -  0.21  - 
MS  6  56  20  24  11  0.25  0.04 
QFMS  5  64  15  19  6  0.25  0.05 
QMS  5  50  7  15  6  0.21  0.03 
QMSp  2  62  -  20  -  0.23  - 
SMS  3  68  -  24  -  0.21  - 
TS  2  1* -  0.9  -  -  - 
ChTS  2  13* -  3  -  -  - 

 

* TS and ChTS average UCS values were derived using triaxial confinement test data

 

Source: SRK, 2020

  
Arctic ProjectPage 252
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 13-22: Shear Strength Laboratory Test Results Excluding Talc Samples

 

Hole ID  From (m)  To (m)  Lithology  Test Type(1)  Peak Friction Angle (°)
Natural Surface
  Base Friction
Angle (°) Saw Cut
  Base Friction
Angle (°) Tilt Table
 
AR15-0139  250.66  250.86  CHS  DS  23.7  -  - 
AR15-0139  231.43  231.67  CHS  DS  17.2  -  - 
AR19-0171  103.29  103.52  CHS  DS  7.7  -  - 
AR11-0128  118.18  118.42  GS  DS  22.6  -  - 
AR11-0129  177.12  177.52  GS  DS  32.5  -  - 
AR11-0129  221.67  222.05  GS  DS  34.2  -  - 
AR11-0130  161.04  161.44  GS  DS  23.5  -  - 
AR15-0140  115.97  116.19  GS  SC  -  -  25.3 
AR15-0142  47.20  47.4  GS  SC  -  -  24.1 
AR19-0165A  159.36  159.64  MRP  DS  18  -  - 
AR15-0142  82.46  82.68  MRP  SC  -  22.1  23.3 
AR15-0140  134.39  134.64  MRP  SC  -  -  24.1 
AR15-0143  36.72  36.97  MRP  SC  -  -  24.6 
AR19-0166  286.16  286.39  MRP  SC  -  -  27.0 
AR16-0149  156.80  157.01  MS  DS  24.5  -  - 
AR16-0149  159.93  160.13  MS  DS  29.9  -  - 
AR15-0139  75.30  75.51  QFMS  DS  22.1  -  - 
AR11-0127  150.63  150.88  QFMS  DS  29.1  -  - 
AR19-0168  198.68  198.95  QFMS  DS  25.6  -  - 
AR19-0167  163.03  163.23  QFMS  DS  12  -  - 
AR19-0164  138.78  138.96  QFMS  SC  -  -  29.4 
AR19-0165A  216.69  216.97  QFMS  SC  -  -  25.8 
AR19-0168  50.53  50.75  QFMS  SC  -  -  25.0 
AR19-0168  139.94  140.17  QFMS  SC  -  -  23.0 
AR19-0171  211.59  211.85  QMS  DS  21.8  -  - 
AR15-0139  184.65  184.92  QMS  SC  -  24.1  23.3 
AR15-0137  200.45  200.69  QMS  SC  -  -  26.3 
AR15-0145  219.34  219.57  QMS  SC  -  -  24.0 
AR19-0165A  105.13  105.38  QMS  SC  -  -  26.7 
AR19-0171  129.77  130.02  QMS  SC  -  -  28.2 
AR11-0130  141.10  141.65  QMSp  DS  21.2  -  - 
AR11-0130  149.84  150.29  QMSp  DS  31.4  -  - 
AR16-0149  154.18  154.48  SMS  DS  19.9  -  - 

 

Source: SRK, 2020

  
Arctic ProjectPage 253
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 13-15: Talc Geotechnical Laboratory Testing Results

 

 

 

Source: SRK, 2022

 

13.9.4Rock Mass Assessment

 

Based on similar geotechnical conditions, most lithological units have been grouped together into broad domains represented by the Upper and Lower Plates that are separated by the Warm Springs Fault. The exceptions to these groupings are the weaker talc units, shallow weathered material, and fault zones. The following rock mass domains were defined:

 

Upper Plate

 

Lower Plate

 

Weathered

 

Talc Zone

 

Fault zones

  
Arctic ProjectPage 254
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Mean rock mass parameter values and ranges were defined for each rock mass domain (e.g., fracture frequency, rock mass rating). Particular attention was paid to the assessment of intact rock strength within the defined rock mass domains. Laboratory strength testing, supported by point load testing and empirical field estimates, suggests that strength within the various lithological groups of the Upper and Lower Plates is reasonably homogeneous (Table 13-23).

 

Table 13-23: Summary of Derived Rock Mass Parameter Values per Rock Mass Domain

 

Domain  RQD (%)  FF/m  UCS
MPa
  RMR89 Joint
Condition

(0-30)
  RMR89  GSI  Ei
(GPa)
   mi 
Upper Plate  85-95  1-4  50-60  20  60-70  55-65  18   18 
Lower Plate  75-85  2-5  50-60  19  55-65  50-60  18   18 
Weathered  45-55  10-20  40-50  16  40-50  35-45  18(1)  13(1)
Talc Zone(2)  20-40  25-40  1-10  10  20-30  15-25  4   6 
Faults  0-20  > 40  30-40  16  30-40  25-35  -(3)  -(3)

 

(1) Estimated parameter after BGC (2012) 

(2) The rock mass parameters for Talc Zone are representative of the talc rock mass but not the talc layer itself 

(3) No data available; estimated for stability assessments

 

13.9.5Kinematic Stability Assessment

 

A complete assessment of bench and inter-ramp kinematic stability was undertaken. Full descriptions of toppling, planar, and wedge instability risks were developed per structural domain and design sector.

 

The most significant discontinuity sets, in terms of limiting slope angles, are related to shallow to intermediate dipping S1/S0 (foliation) fabric, which impacts the northeast, east and southeast slopes.

 

13.9.6Hydrogeology

 

Hydrogeological investigations and assessments were completed for both the open pit and valley bottom water/waste management areas.

 

Hydrogeological data are available from 39 boreholes (Figure 7-13); 15 in the area of the open pit area and 24 in the valley bottom area, comprising:

 

Hydrogeologic testing data from 50 packer-based hydraulic tests; 11 slug tests; two pumping tests in valley bottom, each with an observation well; three injection tests in pit area, one of six hours duration and two greater than 24 hours, each with monitoring at nearby vibrating wire piezometers (VWPs) (SRK 2017, SRK 2020, SRK 2022); 122 particle size distributions from test pits in valley floor (SRK 2020).

 

Water level data from 25 VWPs in pit area; 3 standpipe piezometers (a fourth piezometer is planned to be installed in 2022) in the pit area;12 water level dataloggers in valley bottom (SRK 2017, SRK 2020, SRK 2022).

 

Dedicated ground temperature cables at six locations in valley floor; temperature from all VWP sensors, including those in the open pit area (SRK 2020).

 

22 monitoring wells and two pumping wells in valley bottom; three standpipe piezometers in pit area (SRK 2020).

  
Arctic ProjectPage 255
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

These data were collected following industry best practices. The data collected using the techniques described above have been used to develop conceptual models for the project area and hydrostratigraphic units:

 

Overburden is thickest in the valley bottom, typically ranging between 10 m to 20 m with localized areas of 25 m or more. It is comprised of colluvium and glacial till. On the valley sides, and in the area of the pit, overburden thickness is relatively minor, typically around 5 m or less. In the open pit area, the hydraulic conductivity (K) of the overburden ranges between 6x10-7 and 9x10 5 m/s, with a geomean of 4x10-6 m/s. In the valley bottom the K varies between 6x10-7 and 9x10-5 m/s, with a geomean of 5x10-6 m/s.

 

Weathered bedrock, defined as bedrock with enhanced permeability due to weathering or isostatic rebound post-glaciation, typically ranges between 0 m to 60 m thickness based on available drill hole data. Specific testing of weathered bedrock was completed in valley bottom drill holes; presence of weathered bedrock in the pit area was inferred from logging. The K in the weathered bedrock in both the open pit and valley bottom ranges between 6x10 8 m/s and 4x10-5 m/s, with a geomean of 5x10 7 m/s.

 

Competent bedrock encompasses all lithologic units, in both the valley bottom and pit areas, with sub-units that include upper and lower fractured bedrock (upper and lower are relative to talc position); talc unit; fault barriers; fault conduits. In the open pit area, the K varies between 2x10-9 m/s and 5x10-5 m/s with a geomean of 7x10 8 m/. In the valley bottom area, the K is interpreted to be primarily related to fractures and ranges between 2x10-9 m/s and 4x10-5 m/s, with a geomean of 7x10 8 m/s.

 

The talc unit is present in the pit area, with relatively low hydraulic conductivity and is considered an aquitard, but the aquitard is likely discontinuous based on talc distribution and thickness.

 

Testing of specific geological structures was completed in the pit area. Results range from similar to surrounding bedrock to higher or lower permeability (K). No continuous, relatively high or relatively low permeability structures were identified.

 

The hydrogeological conceptual model for valley bottoms is relatively simple. Overall water flow directions are similar to the topography, with the majority of water flow at relatively shallow depth in overburden or weathered bedrock flowing towards valley bottoms. In the valley bottom, overburden heterogeneity exists, with flow occurring within relatively coarser grained, higher hydraulic conductivity units and weathered bedrock. The majority of groundwater flow in the Subarctic Creek watershed is assumed to discharge to Subarctic Creek. Flow within competent bedrock is much lower in magnitude.

 

In the valley bottom, the outstanding data gap is hydrogeological characterization of overburden and fractured rock in the specific area of the proposed valley bottom groundwater seepage interception system. The characterization program should include completion of monitoring wells down gradient of this system to allow for development of baseline groundwater quality conditions.

 

Figure 13-16 presents the conceptual hydrogeological model for the pit area. Overall flow directions follow topography, with flow systems all within the competent bedrock hydrostratigraphic unit, with the talc, upper and lower fractured bedrock and structures sub-units present. Hydraulic gradients are downwards from the upper fractured bedrock sub-unit to the lower fractured bedrock unit, separated by the talc aquitard. The lower fractured bedrock unit is confined at lower elevations, with the potentiometric surface above the talc sub-unit. Water levels are assumed to vary seasonally, with highest levels occurring as a result of freshet snow melt and or spring/summer precipitation.

  
Arctic ProjectPage 256
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 13-16: Summarized Hydrogeological Conceptual Model for Pit Area

 

 

 

Source: SRK, 2022

 

13.9.7Pit Inflow

 

Pit inflow and pore pressure conditions for the 2019 mine designs were assessed using numerical and analytical tools. Comparison of the 2019 mine designs with 2022 mine design showed relatively minor differences, focused primarily in the area where the pit floor will be mined below the talc for slope stability purposes.

 

Considering the relatively minor differences, inflow estimates for the 2022 mine design were scaled from previous estimates using comparisons of the footprints, elevations, and bottom depths for open pit designs at different phases. Table 13-24 summarizes estimated pit inflow for three cases reflecting the range of hydraulic conductivity and groundwater recharge that could be expected based on data and modelling. The “Base Case” estimate reflects groundwater model runs with parameters calibrated to average stream baseflow conditions. “Low Case” and “High Case” estimates reflect model runs with parameters calibrated to minimum and maximum baseflow conditions, respectively. Estimates of pit wall runoff, reflecting direct precipitation on the pit, were obtained from the site wide water balance model, using a runoff coefficient of 0.9. The presented values are annual averages; shorter duration higher peak flows and periods of lower inflow can be expected to occur.

 

Pit inflows are expected to be low magnitude, relative to many other projects worldwide, and flows of this magnitude can be handled with in-pit sumps. It was assumed that sumps would be positioned at the lowest elevation points in the pit. Perimeter dewatering wells are not considered necessary for this scale of flow. A trend of increasing hydraulic conductivity with depth appears to occur at this site. As the pit advances into later years and gets deeper, in-pit dewatering wells may be beneficial.

  
Arctic ProjectPage 257
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Detailed design of dewatering capacity needs to consider:

 

Normal duty pumping capacity based on estimated pit inflow rates.

 

Event pumping capacity based on the highest of design hydrological event (e.g., 1 in 20, 24-hour precipitation), annual freshet flow, or 2x normal duty capacity.

 

Pit sumps sized based on event pumping capacity/volume.

 

It is the QP’s opinion that characterization of and assumptions for aquifer and aquitard parameters (i.e., permeability, recharge) used in groundwater models used to estimate inflows follow industry best practice, have an acceptable water balance and are appropriate for this level of study.

 

Table 13-24: Estimate Pit Inflow

 

    Average Yearly Pit Groundwater Inflow (m3/d)      
Mining Year   Low Case   Base Case   High Case   Pit Wall Runoff
(m3/d)
  Base Case Total Inflow
(m3/d)
 
02   130   300   650   1890   2190  
05   150   350   770   2410   2760  
07   160   370   830   2830   3200  
09   160   400   900   3140   3540  
11   170   420   950   3320   3740  
13   180   440   990   3320   3760  

 

13.9.8Pore Pressure

 

Pore pressure influences on slope stability analyses were assessed through combinations of hydrogeological modelling and geotechnical stability modelling. Pore pressures were estimated with four 2-D cross-sectional models that represented the four geotechnical sections used to evaluate slope stability. Conservative model assumptions were used considering the risks posed by the low shear strength of the talc, and uncertainties with hydrogeological conditions (i.e., lateral extent of the hydrostratigraphic zones above the talc, vertical leakage rates between units above and below the talc, and presence of geological structures acting as barriers or conduits).

 

Sensitivity to model assumptions were tested including variations to hydraulic conductivity of the fractured rock, specific storage, specific yield, as well as to anisotropy within the fractured rock and presence of impermeable geological structures. Results suggested highest sensitivity (as measured via changes in water table distribution and hydraulic head) related to anisotropy and the addition of impermeable geological structures.

 

Based on slope stability assessments, it is the QP’s opinion that pore pressures could pose stability risks under two conditions:

 

Stability analyses indicate that slopes along geotechnical section E (SRK, 2022), in the northeast and east walls of the pit are sensitive to potential planar sliding on talc or foliation. Elevated pore pressures in these areas would exacerbate this condition. If pore pressure in these areas does not drain naturally as mining advances, active depressurization should be implemented.

  
Arctic ProjectPage 258
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Compartmentalization by sub-vertical structures could impede natural drainage of the slopes, potentially leading to localized stability issues. Specific areas where this could occur have not been identified in the available data but are possible.

 

A conceptual pore pressure monitoring system and mitigation plan for the area of geotechnical section E was developed and is presented in Figure 13-17. Assumptions used for this plan are based on the hydrogeological conceptual model and results of hydrogeological testing. The system must be capable of maintaining pore pressure targets during freshet high flow conditions and operate under winter freezing conditions. The plan is sufficient to support the current level of study but should be reviewed as additional information becomes available, and mitigation efforts adapted as appropriate to achieve pore pressure reduction needs.

 

Figure 13-17: Pore Pressure Management Assumptions for East and Northeast Pit Walls

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 259
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

13.9.9Stability Modelling

 

The minimum acceptable factor of safety (FoS) for the planned Arctic open pit varies depending on the pit slope component. Based upon the current plans, there is no major infrastructure set to be constructed proximal to any pit walls. If this were to change, it would be necessary to examine the selected acceptance criteria.

 

Table 13-25 summarizes the selected acceptance criteria for the Arctic pit slope design.

 

Table 13-25: Selected Slope Stability Acceptance Criteria

 

   Acceptance Criteria (1) 
   Static   Dynamic 
Slope
Component
  Minimum
FoS
   Maximum PoF
Displayed as Probability of
FoS ≤ 1 (%)
   Minimum
FoS
   Maximum PoF
Displayed as Probability of
FoS ≤ 1 (%)
 
Bench   1.1   50%  NA   50%
Inter-ramp   1.3   10%  1.1   10%
Overall   1.3   5%  1.1   5%

 

(1) FoS = Factor of Safety and PoF = Probability of Failure

 

Two dimensional (2-D) RS2 modelling, carried out on four sections around the pit, validated the findings from the kinematic assessment and showed that existence of talc layers in the slopes are geotechnical risks. The models suggest that final pit wall slopes are sensitive to the pore pressure when the talc layers are exposed in the pit walls and relatively insensitive to pore pressure in other scenarios. A seismic hazard assessment was incorporated considering the annual exceedance probability of 10% chance of being exceeded in 50 years indicating a peak ground acceleration of 0.26 g for the region of the proposed Artic Pit. The peak ground acceleration used to evaluate the 2-D sections was a conservative 66% of the estimated regional peak ground acceleration for this region, or 0.17 g.

 

Three dimensional (3-D) RS3 modelling focused on analyzing the stability of the east and northeast walls that are designed to be mined to foliation fabric and contain talc layers. These slope areas did not meet the stability design criteria in 2-D but it was anticipated that confinement in 3D would improve slope performance. The effect of pore pressures was not analyzed in 3-D due to limitations with the software when modelling complex groundwater conditions. As with the results of the 2-D findings, the absence of pore pressure in the 3-D model was assumed to be representative if the pore pressure management plan successfully drains the groundwater above the talc zones.

 

The 3-D analysis result suggests that the area in the northeast wall above the Cz Talc Zone is, in terms of stability, the most sensitive slope to shear strength reduction. The resulting SRF of 1.3, although meeting the design criteria, represents an optimistic estimation of the factor of safety as the strengths of the talc zone and foliation could be lower.

  
Arctic ProjectPage 260
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

13.9.10Slope Design

 

Slope design recommendations were based on the findings of the kinematic evaluation, with additional adjustments from the numerical modelling analyses. Hydrogeological influences were considered in the 2-D numerical stability analyses using the predictions of phreatic surfaces in the interim and final pit phases. The models suggested that stability of the northeast and east wall was dependent on full excavation of the talc domains and successful management of the pore water pressures. Inter-Ramp slope design angles were determined for each slope design domain as seen in Figure 13-18.

  
Arctic ProjectPage 261
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 13-18: Recommended Inter-Ramp Angles by Slope Design Domains Projected on EOY12 Design Pit

 

 

 

Source: SRK, 2019.

  
Arctic ProjectPage 262
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

13.10Geotechnical Review of Open Pit Design

 

Wood updated the open pit mine designs to support the Report. The updated design includes four nested phases including the ultimate pit. The notable geotechnical recommendations considered for the mine design update include:

 

Where slopes are oriented sub-parallel to foliation, conventional bench-berm designs have been adjusted to excavate along foliation design

 

Slope angle of north wall, above 900 m elevation, has been optimized to account for more favourable orientation of foliation

 

The east and northeast walls of the interim mining phases do not expose the talc domain

 

Talc domains are fully excavated in the northeast and east walls of final mining phase

 

13.10.1Slope Stability Risks

  

Based on a high-level geotechnical review, SRK believes that the updated open pit mine designs have honoured the geotechnical slope design recommendations. The review also identified potential slope stability risks for the various mining phases, shown in Figure 13-19, that were assessed using 3D finite element numerical models with simplified geometries and groundwater conditions. It is recommended that these potential risks are considered in the next stages of the Arctic Project.

 

Potential sliding failure along talc domains and fault structures in the northwest and east walls of Phase01 pit. The 3D stability model results suggest that the east wall in the interim mining phase is stable in dry conditions but the factor of safety falls below the design acceptance criteria when the pore pressures become elevated above the talc domains which could occur seasonally during freshet. This highlights the importance of pit water management plan as well as controlling the amount of snow accumulating within the potential areas of risk. Flexibility in mine sequencing may be required to accelerate the excavations above the talc domains if pore pressures can’t be controlled.

 

Interaction of talc domains and discontinuities to form potentially unstable multi-bench wedges in the south walls of Phase02, Phase03 and Final pit designs. 3D numerical model results show that multi-bench scale failure is unlikely but elevated pore pressures could exacerbate the conditions. Localized blocks could fail along the bench crest and rockfall risk should be considered in these areas.

 

Sliding failures along foliation are expected where the slope orientation changes abruptly in the final east wall. Slope design adjustment is recommended to remove any convex slope shapes in the elevated risk areas.

  
Arctic ProjectPage 263
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 13-19: Potential Areas of Slope Instability Risks in the 2022 Open Pit Designs

 

 

  

Source: SRK, 2022

  
Arctic ProjectPage 264
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

13.11Geochemistry Assessment

 

13.11.1Acid Base Accounting Studies

 

Five geochemical sampling campaigns in 1998, 2010, 2013, 2015 and 2016 resulted in accumulation of a dataset of 1,557 samples tested using various methods. In January 2017, following a large (1004 sample) infill sampling campaign in 2016, Trilogy consolidated the databases, which enabled SRK to use the geochemical database and mineralogical data to develop site-specific methods for acid potential (AP) and neutralization potential (NP) (SRK 2019).

 

About 75% of samples were classified as potentially acid generating (PAG), which is defined as total sulphur content >0.1% and NP/AP<2 where NP and AP are calculated using site-specific methods. Acid rock drainage (ARD) potential occurs in all rock types to varying degrees. Ore and the associated Gray Schist have the strongest ARD potential, followed by felsic schists. The rock types with weaker ARD potential are chlorite talc schist and metarhyolite porphyry.

 

In 2017 2019, and 2022 tailings generated by metallurgical testing were tested for acid-base accounting (ABA) methods and found to have potential for acid generation.

 

13.11.2Geochemical Kinetic Studies

 

13.11.2.1Waste Rock Program

 

Geochemical kinetic testing using six rock type composites was initiated in 2015. The composites were used to fill seven barrels (including one duplicate) at the site with 240 to 270 kg of waste rock in each test. Leachates from the barrels were collected and tested once in 2015 and three to five times during each summer from 2016 through 2019, and 2021 to 2022. Parallel laboratory humidity cells were also initiated in 2015 and are evaluating the weathering behaviour of the composites. Three of the humidity cells are still operating and had reached 370 weeks as of November 30, 2022, and three of the humidity cells were terminated in 2021/2022 as weathering rates were stable.

 

An additional 10 waste rock humidity cell tests (HCTs) were initiated in 2019, and a further two were initiated in 2021. While the tests initiated in 2015 generally represented typical compositions of the main waste rock types in terms of sulphur content, the tests initiated in 2019 and 2021 were designed to represent the range of compositions present for key parameters such as selenium and sulphur, including some tests that would represent “worst case” conditions. The humidity cells initiated in 2019 had been operating for 184 weeks as of November 14, 2022, with the exception of three of the tests which were terminated in 2021/2022 as weathering rates were stable. The tests initiated in 2021 had been operating for 92 weeks as of November 14, 2022.

 

All of the kinetic samples (from the 2015, 2019 and 2021 programs) have the potential to generate acid. To date, ten HCTs have generated acid (pH<5) including samples from all the main rock types. A further four tests had pHs that were most recently between pH 5.0 and 6.5 indicating that carbonate minerals have likely been exhausted and acid generation is buffered by silicate minerals. pH is expected to continue declining in the tests. The remaining four tests had recent pHs around 7.0 and were likely still buffered by carbonate minerals. The testwork has provided data on metal release rates under acidic and non-acidic conditions which have been used to estimate waste rock contact water composition.

  
Arctic ProjectPage 265
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

13.11.2.2Tailings Program

 

Kinetic testing of tailings from the 2017 metallurgical test program was completed late in 2020 (conducted for 193 weeks). Tailings from the 2019 and 2022 metallurgical test programs has been in operation for 172 weeks and 30 weeks respectively (as of November 14, 2022). Testing includes HCTs, and the 2019 and 2022 tailings are also undergoing subaqueous column testing. None of the tests have generated acid and recent pHs are above 7.0. The HCT testwork has provided data on metal release rates under non-acidic conditions which have been used to estimate contact water composition of tailings upon exposure to subaerial weathering. Subaqueous column results are used for predicting tailings water chemistry during operations and upon closure as water is drawn down in the TMF and porewater is released during tailings consolidation.

 

13.11.2.3Ore Program

 

Kinetic testing of ore composites was initiated in 2019 and 2022. The 2019 HCT was terminated in 2021 after 112 weeks of operation. The test initiated in 2022 had been operating for 30 weeks as of November 14, 2022. The samples had not generated acid and pHs were above 7.0. The testwork has provided data on metal release rates under non-acidic conditions which have been used to estimate the ore contact water composition. 

  
Arctic ProjectPage 266
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

14Processing and Recovery Methods

 

14.1Overview

 

The current process plant design is updated from the 2020 Arctic Feasibility Study Technical Report (2020 FS) by considering the verification testwork conducted by ALS in 2022, along with process optimization based on Ausenco’s benchmark database. The process plant will operate two 12-hour shifts per day, 365 day a year, with an overall plant availability of 92%. The process plant will produce three concentrates: 1) copper concentrate, 2) zinc concentrate, and 3) lead concentrate. Gold and silver are expected to be payable at a smelter and are recovered in both the copper and lead concentrates.

 

The process is developed to treat the MS and SMS ores from the Arctic deposit hosted in the Ambler Sequence within a VMS belt. The deposit mineralisation occurs as stratiform SMS to MS beds within graphitic chlorite schists and quartz mica schists. The mined material will be comminuted via a primary crushing circuit and a grinding circuit configured in semi-autogenous ball (SAB) mode. Due to the significant levels of talc contained in the mined materials (2.92% in the plant feed), a talc flotation is required to remove the mineral. This is then followed by a bulk flotation of a copper and lead concentrate, and the subsequent separation of copper and lead concentrate. At this stage, flotation of a zinc concentrate process takes place to produce the three flotation concentrates. The talc flotation concentrate and the zinc tailings will be combined and thickened before discharged to the tailings storage facility.

 

The overall circuit consisting of crushing, grinding and flotation to generate the respective metallic concentrates is based on the optimal process route to produce saleable concentrates from the ores in the Arctic deposit. This process flowsheet is shown in Figure 14-1. Figure 14-2 shows a plan of the overall plant area and Figure 14-3 shows a general arrangement of the process plant area. 

 

14.2Process Flowsheet and Area Plan

 

The process plant will consist of the following unit operations:

 

Primary (jaw) crushing;

 

Course ore stockpile;

 

SAG and ball mill grinding:

 

primary grinding using an open circuit semi-autogenous grinding (SAG) mill; and

 

secondary grinding using a closed-circuit ball mill.

 

Talc pre-flotation;

 

Bulk copper and lead flotation;

 

Copper and lead separation flotation;

 

Zinc flotation;

 

Thickening, filtration, and loading of copper, lead, and zinc concentrates;

 

Cyanide destruction; and

 

Tailings thickening and disposal.

  
Arctic ProjectPage 267
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 14-1: Process Plant Flowsheet

 

 

  

Source: Ausenco, 2022.

  
Arctic ProjectPage 268
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 14-2:Overall Plant Area Plan

 

 

 

Source: Ausenco, 2022.

 

  
Arctic ProjectPage 269
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Figure 14-3:Process Plant Plan

 

 

 

Source: Ausenco, 2022.

 

  
Arctic ProjectPage 270
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

 

14.3 Process Design Criteria

 

The process plant is designed for a throughput of 10,000 t/d, equivalent to 3,650,000 t/a. The key process design criteria considered for the design and selection of equipment for the processing facilities are listed in Table 14-1 and the comminution parameters are provided in Table 14-2. The process plant design is based on a robust metallurgical flowsheet developed for optimum recovery.

 

Table 14-1: Process Design Criteria - Overview

 

Criteria   Unit   Value
Plant Design Capacity   t/a   3,650,000
  t/d   10,000
Operating Availability - Crushing   %   65
- Grinding and Flotation   %   92
- Concentrate and Tailings Filtration   %   84
Process Plant capacity, nominal @ 92% availability   t/h   453
ROM Specific Gravity   -   3.25
Plant Feed Grades - Copper, Design   %   3.00
- Lead, Design   %   0.74
- Zinc, Design   %   4.20
- Gold, LOM Average   g/t   0.47
- Silver, LOM Average   g/t   35
- Talc, LOM Average   %   8

 

Table 14-2: Comminution Design Criteria

 

Criteria   Unit   Value
Crushing (Single Stage)        
Availability   %   65
Primary Crusher   Type   Jaw Crusher
Crushing Feed Size, 80% Passing   mm   504
Crushing Circuit Product Size, 80% Passing   mm   80
Grinding        
Availability   %   92
Circuit Type   -   SAG Mill, Ball Mill
Bond Ball Mill Work Index, Design   kWh/t   11.6
Bond Abrasion Index, Design   g   0.038
A x b, design   -   109
Feed Particle Size, F80   mm   80
Product Particle Size, P80   µm   70
Regrinding Circuit Product Size, 80% Passing - Bulk Rougher Concentrate   µm   40

  
Arctic ProjectPage 271
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Design criteria for the flotation plant were determined from the testwork conducted by ALS Metallurgy (described in Section 13) and is summarized in Table 14-3.

 

Table 14-3: Flotation Plant Design Criteria

 

Criteria   Unit   Value
Feed Rate   t/h   453
Pre-Flotation        
Cell Type   Type   Conventional Tank Cells
Stage Recovery to concentrate, mass   % flotation feed   21.5-25.7
Stage Recovery, talc   %   88.6
Copper-Lead Bulk Rougher Flotation        
Cell Type   Type   Jameson Cell
Stage Recovery to concentrate, mass   % flotation feed   12.7-15.0
Regrind Mill        
Type       Ball Mill
Feed Rate, design   t/h   68
Feed Particle Size, F80   µm   63
Product Particle Size, P80   µm   40
Specific Grinding Energy (SGE)   kWh/t   9.2
Copper-Lead Cleaners       3 stages
Cell Type   Type  

Conventional Tank Cell – Stage 1 & 2

Jameson Cell – Stage 3

Stage Recovery to Concentrate, mass   % Flotation feed   16.1-18.6
Stage Recovery, Copper   %   92.1
Stage Recovery, Gold   %   52.0
Stage Recovery, Silver   %   32.5
Lead Rougher Flotation        
Cell Type       Conventional Tank Cells
Stage Recovery to concentrate, mass   % flotation feed   1.7-2.5
Lead Cleaners       3 Stages
Cell Type       Conventional Tank Cell
Stage Recovery to concentrate, mass       2.6-3.6
Stage Recovery, Lead   %   61.3
Stage Recovery, Gold   %   21.6
Stage Recovery, Silver   %   48.6
Zinc Rougher Flotation        
Cell Type       Conventional Tank Cell
Stage Recovery to Concentrate, mass   % flotation feed   7.4-8.8

  
Arctic ProjectPage 272
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Criteria   Unit   Value
Zinc Regrind Mill        
Type       Ball Mill
Feed Rate, design   t/h   40
Feed Particle Size, F80   µm   63
Product Particle Size, P80   µm   40
Specific Grinding Energy (SGE)   kWh/t   9.2
Zinc Cleaners       3 Stages
Cell Type      

Conventional Tank Cell – Stage 1 & 2

Jameson Cell – Stage 3

Stage Recovery to concentrate, mass       11.
Stage Recovery, Zinc   %   88.5
Stage Recovery, Gold   %   3.3
Stage Recovery, Silver   %   5.7
Concentrate Handling        
Copper Concentrate        
Type       Hi-rate
Unit Area Thickening rate, design   t/m2.h   0.25
Thickener Underflow Density   %w/w   65
Copper Concentrate Filter        
Type       Horizontal plate pressure filter
Filtration Rate   kg/m2/h   575
Nominal Filter Cake Moisture   %w/w   6
Lead Concentrate        
Type       Hi-rate
Unit Area Thickening rate, design   t/m2.h   0.2
Thickener Underflow Density   %w/w   65
Lead Concentrate Filter        
Type       Horizontal plate pressure filter
Filtration Rate   kg/m2/h   800
Nominal Filter Cake Moisture   %w/w   6
Zinc Concentrate        
Type       Hi-rate
Unit Area Thickening rate, design   t/m2.h   0.25
Thickener Underflow Density   %w/w   65
Zinc Concentrate Filter        
Type       Horizontal plate pressure filter
Filtration Rate   kg/m2/h   555
Nominal Filter Cake Moisture   %w/w   6

  
Arctic ProjectPage 273
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

14.4Plant Description

 

14.4.1Crushing Plant

 

Run-of-mine ore will be trucked to the crushing station and dumped into a 200-t receiving bin protected with a 1,000-mm-aperture stationary grizzly. Ore will be reclaimed from the bin with an apron feeder and scalped of fines with a 75-mm-aperture vibrating grizzly. The grizzly oversize will be passed to the primary jaw crusher. The selected conventional jaw crusher will operate with a closed side setting of 100 mm. The crushed material together with the grizzly undersize, with a P80 of 80 mm, will be discharged to the conveyor. A tramp metal magnet will be installed at the head end of the conveyor to remove tramp metal.

 

Crushed ore will be sent to a single covered conical stockpile via the stockpile feed conveyor.

 

The major equipment in the crushing circuit will include:

 

One apron feeder, installed power 30 kW;

 

One vibrating grizzly, installed power 30kW; and

 

One single toggle jaw crusher, installed power 160 kW.

 

14.4.2Coarse Ore Storage

 

The coarse ore stockpile will have a live capacity of 5,000 t, equivalent to approximately 12 h of mill feed at the nominal mill feed rate. The stockpile total capacity will be approximately 20,000 t. The coarse ore stockpile will be a covered facility to mitigate freezing of the stockpiled material, which will be also equipped with a dust collecting system. The coarse ore stockpile building will have sufficient space to allow for the operation of mobile equipment as required. Reclaim of ore from the stockpile will be accomplished using two 1,000-mm-wide by 4,800-mm-long apron feeders at a nominal rate of 226 t/h per feeder. Reclaimed material from the apron feeders will be discharged onto the SAG mill feed conveyor.

 

The major equipment of the coarse ore storage area will include:

 

Two apron feeders, unit installed power 11 kW.

 

14.4.3Grinding and Classification

 

14.4.3.1Primary Grinding and Classification

 

The grinding circuit will consist of a SAG mill followed by a ball mill arranged in a closed circuit with a hydrocyclone cluster. The nominal feed throughput of the circuit will be approximately 453 t/h. The SAB circuit will reduce the crushed ore particle size from a P80 of 80 mm to 70 µm.

 

SAB circuit is selected by considering the low competence of the ore materials. The SAG mill will be a grate discharge type with 12 mm apertures and no pebble ports. As required, steel balls will be added to the SAG mill to maintain mill power. The SAG mill product will discharge onto a trommel screen. Trommel screen undersize will report to a hydrocyclone feed pumpbox and the oversize to a scats bunker.

  
Arctic ProjectPage 274
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

The ball mill discharge will report to the hydrocyclone feed pumpbox, where it will be combined with the SAG mill trommel undersize prior to feeding the hydrocyclone cluster. Process water will be added to the SAG mill feed chute and hydrocyclone feed pumpbox to maintain a target slurry density. The hydrocyclone underflow will feed the ball mill by gravity, while the hydrocyclone overflow, with a solids content of 37%, will gravitate to the flotation circuit. The ball mill circulating load will be 350%.

 

The major equipment of the grinding and classification circuit will include:

 

One SAG mill, 6.1 m in diameter (20 ft) by 4.9 m (16 ft) EGL, installed power 3,000 kW;

 

One ball mill, ;6.1 m diameter (20 ft) by 9.1 m (30 ft) EGL, installed power 6,000 kW;

 

Two 55 kW slurry pumps to pump hydrocyclone feed, with one pump in operation and one in standby; and

 

One hydrocyclone cluster with fourteen 400 mm hydrocyclones, nine in operation, four in standby and one blank.

 

14.4.4Flotation

 

The flotation plant will produce a talc concentrate for disposal, as well as three payable base metal concentrates for shipment to market and sale. The talc concentrate will be produced prior to base metal flotation to minimize dilution of the base metal concentrates. A standard bulk copper and lead concentrate followed by the flotation of a zinc concentrate will be used in the flotation circuit. The copper and lead in the bulk concentrate will be separated by floating the lead from the bulk concentrate to produce individual copper and lead concentrates.

 

14.4.4.1Talc Pre-Flotation

 

The ball mill hydrocyclone overflow will feed the talc rougher circuit. The talc flotation will be composed of rougher and cleaner flotation stages to float the talc mineral and reject any entrained payable sulphide minerals. The rougher flotation will be performed in the conventional forced-air cells and the cleaner flotation will be performed in a Jameson cell. The talc cleaner concentrate will be pumped to the final tailings.

 

The major equipment in the talc pre-flotation circuit will include:

 

Four 120 m3 tank cells, unit installed power 93 kW

 

One Jameson cell (B4500/12).

 

14.4.4.2Copper – Lead Bulk Flotation and Regrinding

 

The talc pre-flotation tailings will be pumped to the copper/lead bulk flotation conditioning tanks where copper and lead mineral collectors will be added. The conditioned slurry will undergo rougher flotation in conventional tank flotation cells for recovery of a bulk copper and lead concentrate.

 

The bulk rougher concentrate will be reground in a 600 kW regrind ball mill configured in reverse, closed circuit with hydrocyclones. The bulk rougher concentrate will be reduced to a particle size of 80% passing 40 μm prior to being further upgraded by two stages of cleaner flotation.

 

The 1st bulk cleaner and cleaner scavenger flotation will be conducted in conventional tank cells. The 1st cleaner flotation tailings will gravitate for scavenging of residual copper and lead minerals. Concentrate from the cleaner-scavenger flotation will be pumped to the regrind hydrocyclone feed pumpbox for further regrinding, while the cleaner-scavenger tailings will join the rougher flotation tailings for pumped transfer to the zinc flotation conditioners. The 2nd bulk cleaner flotation will be performed in a Jameson cell to upgrade the concentrate obtained from the last stage. The 2nd cleaner tailings will be reprocessed in the 1st cleaner flotation stage.

  
Arctic ProjectPage 275
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Copper-lead bulk cleaner flotation dilution water and launder sprays will be supplied by a dedicated process-water system. The supply for this system will be a combination of copper/lead bulk thickener overflow and main plant process water.

 

The major equipment in the bulk flotation and regrinding circuit will include:

 

Five 81 m3 bulk rougher flotation tank cells, unit installed power 75 kW;

 

One regrind ball mill, 3.0 m diameter by 5.3 m EGL, installed power 600 kW;

 

Four 37 m3 bulk 1st cleaner flotation tank cells, unit installed power 45 kW;

 

Three 37 m3 bulk cleaner scavenger flotation tank cells, unit installed power 45 kW; and

 

One bulk 2nd cleaner flotation Jameson cell (B4500/12).

 

14.4.4.3Copper and Lead Separation Flotation Circuit

 

The bulk 2nd cleaner concentrate will be pumped to the copper-lead separation flotation conditioning tank, where sodium cyanide and lime will be added to supress copper minerals. Lead flotation will be conducted at a pH ranging from 9.0 to 9.5. The conditioned slurry will flow to the conventional lead rougher flotation cells. Frother will be added in the rougher and cleaner flotation cells and lead promoter will be added in the lead rougher concentrate pumpbox to collect lead minerals.

 

The lead rougher concentrate will be further upgraded in three stages of cleaner flotation to produce the final lead concentrate that will report to the lead concentrate thickener. Tailings from the 2nd and 3rd stages of cleaner flotation will gravity flow to the proceeding flotation cell feed boxes. Tailings from the 1st cleaner flotation will be combined with the tailings from the lead rougher flotation to produce the final copper concentrate, which will report to the copper concentrate thickener.

 

The major equipment in the lead flotation circuit will include:

 

Five 6 m3 lead rougher flotation cells, unit installed power 11 kW;

 

Five 4 m3 1st cleaner flotation cells, unit installed power 7.5 kW;

 

Two 4 m3 2nd cleaner flotation cells, unit installed power 7.5 kW; and

 

One 4 m3 3rd cleaner flotation cell, unit installed power 7.5 kW.

 

14.4.4.4Zinc Flotation and Regrind

 

The copper-lead bulk rougher tailings will be further floated to recover zinc in the zinc flotation circuit, along with the copper-lead bulk cleaner scavenger tailings. The circuit will consist of feed slurry conditioning, rougher/scavenger flotation, zinc rougher concentrate regrind, and two stages of cleaner flotation. A cleaner scalper stage will be installed when the plant feed zinc grade are expected to be higher.

  
Arctic ProjectPage 276
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Tailings from the copper-lead bulk flotation circuit will be conditioned with lime (to a pH above 10.5, to depress pyrite) and copper sulphate (to activate zinc minerals), and then sent to the head cell of a bank of zinc rougher flotation cells. Zinc rougher concentrate will report to the regrinding circuit; zinc rougher tailings will be combined with the Talc concentrate and pumped to the tailings thickener. Thickened tails will be pumped to the Tailings Storage Facility (TSF).

 

The zinc rougher and cleaner scavenger concentrates will be reground in a 355 kW regrind ball mill configured in, closed circuit with hydrocyclones. The zinc concentrates will be reduced to a particle size of 80% passing 40 μm prior to being further processed by the zinc 1st cleaner flotation circuit.

 

The zinc cleaner circuit will operate at a pH of 11 or above to reject pyrite. The 1st cleaner concentrate will be further upgraded in the 2nd stage of cleaner flotation to produce the final zinc concentrate. The 1st cleaner flotation tailings will be further floated in the cleaner scavenger flotation cells. Concentrate from the cleaner scavenger flotation will return to the zinc regrind circuit. The cleaner scavenger tailings will also report to the final tailings pump box, joined by the zinc rougher tailings and talc flotation cleaner concentrate.

 

The main equipment used for the zinc flotation circuit will include:

 

Five 81 m3 zinc rougher flotation tank cells, unit installed power 75 kW;

 

One regrind ball mill, 2.7 m diameter by 4.1 m EGL, installed power 355 kW;

 

Four 23 m3 1st cleaner flotation tank cells, unit installed power 37 kW; 

 

Two 23 m3 cleaner scavenger flotation tank cells, unit installed power 37 kW;

 

One Jameson flotation cell (E4232/10), Year 1 and Year 7 as 2nd cleaner flotation cell and repurposed to cleaner scalper flotation cell after Year 7; and

 

One Jameson flotation cell (E2532/6), future installation on Year 7 as 2nd cleaner flotation cell.

 

14.4.5Product Dewatering

 

The copper, lead, and zinc concentrates will report to separate higher-rate thickeners, where flocculant will be added to assist in the settling of the solids. The thickened slurries will be further dewatered by using pressure filters to a design moisture content of 6%. Two identical tower press filters are recommended for the concentrate filtration duties, including one common unit for lead and zinc concentrates dewatering; while another unit is dedicated to dewater the copper concentrate.

 

14.4.5.1Copper Concentrate Dewatering

 

The copper concentrate will be pumped to a 15 m diameter high-rate thickener which is covered for outdoor application. The thickener overflow water will be reused in the lead flotation circuit, along with overflow from lead concentrate thickener. The excess overflow will be treated by a sulphur dioxide-air procedure to destroy residual cyanide Neutralized overflow will be pumped to the tailings thickener, where the thickener overflow will report to the process pond before recycling back to the plant process water system.

 

The copper concentrate thickener underflow at approximately 65% solids density by weight will be pumped to an agitated concentrate stock tank with 24 hours storage capacity prior to the filtration process. The final filter cake design moisture is 6% considering the site climate conditions. The copper concentrate will be discharged into a stockpile, from which front end loaders will load concentrate onto containers for shipment. Filtrate will return to the copper concentrate thickener. The stockpile will be capable of storing up to 4 days of copper concentrate production in case of potential truck haulage interruptions.

  
Arctic ProjectPage 277
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

The main equipment in the copper concentrate dewatering circuit will include:

 

One 15-m-diameter high-rate thickener, installed power 3.7 kW;

 

One 84 m2 copper concentrate tower filter press, installed power 105 kW; and

 

Two 44 m3 cyanide destruction tanks.

 

14.4.5.2Lead Concentrate Dewatering

 

Lead concentrate will be blended with the flocculant solution and discharged to a 6 m diameter high-rate thickener. The thickener underflow containing approximately 65% solids will be pumped to an agitated concentrate stock tank prior to pressure filtration. The concentrate stock tank will have the capacity to contain lead concentrate production for 24 hours. The thickener overflow will be directed to the lead separation circuit for reuse.

 

Lead concentrate will be filtered in a pressure filter which will be designed to alternate between lead and zinc filtration. Use of a single filter, for 2 products, will require automation to ensure there is no lead-zinc cross contamination. The filter discharge will fall on a reversable conveyor which will send the product to the lead concentrate storage area. The filtrated lead concentrate cake with 6% design moisture will be loaded onto concentrate containers for shipment. The filtrate from the filter will return to the lead concentrate thickener feed well. The in-plant lead concentrate storage facility will be capable of storing at least 4 days of lead concentrate production.

 

The main equipment in the lead concentrate dewatering circuit will include:

 

One 6-m-diameter high-rate thickener, installed power 1.5 kW; and

 

One 84 m2 tower filter press, shared with zinc concentrate filtration, installed power 105 kW.

 

14.4.5.3Zinc Concentrate Dewatering

 

The final zinc concentrate will be pumped to a 14 m diameter high-rate thickener. Flocculant will be added to improve settling of the concentrate. The thickener underflow, with a solid density of 65%, will be stored in an agitated concentrate stock tank prior to pressure filtration. Thickener overflow will be delivered to the zinc rougher feed. The concentrate stock tank is designed to be capable of containing zinc concentrate production for 24 hours.

 

Zinc concentrate will be filtered in a pressure filter which will be designed to alternate between lead and zinc filtration. Use of a single filter, for 2 products, will require automation to ensure there is no lead-zinc cross contamination. The filter discharge will fall on a reversable conveyor which will send the product to the zinc concentrate storage area. The final filter cake design moisture is 6%. Filtrate from the filtration will return to the zinc concentrate thickener. The zinc concentrate will be loaded onto concentrate containers for shipment. The zinc concentrate storage facility will be capable of storing at least 4 days of zinc concentrate production in case of potential transport interruptions.

 

The main equipment in the zinc concentrate dewatering circuit will include:

 

One 14-m-diameter high-rate thickener, installed power 5.5 kW; and

 

One 84 m2 tower filter press, shared with lead concentrate filtration, installed power 105 kW.

  
Arctic ProjectPage 278
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

14.4.6Tailings Disposal

 

The final flotation tailings consist of the talc flotation concentrate, zinc rougher flotation tailings and zinc cleaner scavenger flotation tailings. The final flotation tailings will be directed to a 32 m diameter high-rate thickener. Flocculant will be added to improve settling of the tailings. Thickener underflow with a solid density of 47% will be pumped towards the tailings storage facility. Thickener overflow will be delivered to the Process Pond, from where it will be pumped to the process water tank for distribution to the plant.

 

Water pump barge will be installed to in the tailings pond to reclaim water Tailings water will be pumped to the Process Pond. Water barge pumps will be installed in the Process Pond and will be able to send water to the process water tank or the WTP. Tailings management is discussed further in Section 15.

 

14.4.7Reagent Handling and Storage

 

Various chemical reagents will be added to the grinding and flotation circuits to modify the mineral particle surfaces and enhance the floatability of the valuable mineral particles into the concentrate products. The reagents will be prepared and stored in a separate, self-contained area inside the process plant and delivered by individual metering pumps or centrifugal pumps to the addition points. All reagents will be prepared using WRCP water via a bulk reagent handling system, mixing and holding tanks.

 

Estimated annual reagent consumptions are provided in Table 14-4.

 

Table 14-4:Annual Reagent Consumption

 

Reagent   Unit   Value  
Flocculant   t/a   104  
SIPX   t/a   69  
3418A   t/a   102  
MIBC   t/a   301  
Lime   t/a   3,424  
Descalant   t/a   36  
Cyanide   t/a   1,324  
ZnSO4   t/a   529  
CuSO4   t/a   690  
SMBS   t/a   917  

 

14.4.7.1Collectors

 

Sodium isopropyl xanthate (SIPX) in pellets form will be shipped to the mine site in bulk-bags. The SIPX will be diluted to 20% w/w solution strength in a mixing tank and stored in a holding tank, before being dosed to the copper-lead bulk flotation circuit and the zinc flotation circuit via metering pumps.

 

Collector 3418A will be received as a liquid in Intermediate Bulk Containers (IBC) totes. It will be delivered to the copper-lead bulk flotation circuit via metering pumps without dilution.

  
Arctic ProjectPage 279
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

14.4.7.2Frother

 

MIBC frother will be received as a liquid in IBC totes. The reagent will be used at the supplied solution strength. Metering pumps will deliver the frother to the talc, copper, lead, and zinc flotation circuits.

 

14.4.7.3Lime

 

Lime will be trucked to the site as unslaked pebbles and stored in a 100-t-capacity bulk lime silo. Lime will be conveyed to the lime slaker and slaked with water. The slaked lime will be stored in an agitated mixing tank and distributed to the addition points via a lime slurry loop, to the zinc flotation circuits and WTP. The slaker will be controlled automatically based on the lime slurry levels in the holding tank.

 

14.4.7.4Flocculant

 

Solid flocculant will be prepared in a packaged preparation system, including a screw feeder, a flocculant educator, and mixing devices. Flocculant will be diluted to a 0.5% w/v solution strength and added via metering pumps to the copper, lead, zinc and final tailings thickeners’ feed wells where the reagent will be further diluted.

 

14.4.7.5Other Reagents

 

Sodium cyanide, sodium metabisulphite (SMBS), zinc sulphate, and copper sulphate will be supplied in powder/solid form and will be dissolved and diluted by WRCP water. The strength of the reagent solutions will be approximately 15–20%. Cyanide monitoring/alarm systems will be installed at the cyanide preparation areas. Emergency medical stations and emergency cyanide detoxification chemicals will be provided at the areas as well.

 

Anti-scaling chemicals may be required to minimize scale build-up in the reclaim or recycle water lines. These chemicals will be delivered in liquid form and metered directly into the intake of the reclaim water pumps or process water tank.

 

Storage tanks will be equipped with level indicators and instrumentation to ensure that spills do not occur during normal operation. Appropriate ventilation, fire and safety protection equipment and devices will be provided at reagent preparation areas.

 

14.4.8Power Supply

 

Plant power will be generated on site, with no utility interconnection using diesel generator sets that will be installed to operate in parallel (four operating and one on standby). Each generator will be rated 13.8 kV, 5.5 MW, and the total power output capacity will be 21.6 MW excluding the redundant unit.

 

The total connected load for the plant will be 25.9 MW with a normal operating load of 21.0 MW (~167 GWh/a).

 

14.4.9Water Supply

 

There will be three separate water supply systems: a fresh water system, a WRCP water supply system, and a process water supply system. The contact water will originate principally from the Waste-Rock Control Pond. The total water usage for the process plant is 42,240 m3/d.

  
Arctic ProjectPage 280
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

14.4.9.1Fresh Water Supply System

 

Fresh water will be used for fire water and potable water applications that will be supplied from ground water wells. A 350 m3 fresh water/fire water storage tank will hold well water, with a live capacity of 4 hours.

 

14.4.9.2WRCP Water Supply System

 

WRCP water will be fed to the TMF during winter months and treated and discharged in the summer. Additional process water will be supplied from the WRCP to the TMF through the winter months to meet mill water demands and provide water stored in the TMF as a contingency for dry years. Contact water will also be supplied form the WRCP, which will feed the potable water and gland water tanks.

 

14.4.9.3Process Water Supply System

 

Process water will mainly come from the Process Pond which is fed by tailings thickener overflow and reclaimed water from TMF. In addition, contact water is also another process water source as makeup water. Process water will be stored in a 14-m-diameter x 14-m-high tank, from where the water will be distributed to the process plant and other service locations. The process water consumption is 40,326 m3/d.

 

14.4.10Air Supply

 

Air service systems will supply air to various applications throughout the plant, as follows:

 

A separate high-pressure air service system will supply air to the crushing plant by a dedicated air compressor. The air will be provided for dust suppression and equipment services.

 

Flotation and Cyanide Destruction: low-pressure air will be provided for flotation tank cells and cyanide destruction tank by air blowers.

 

Filtration Circuit: wet high-pressure air will be provided for filtration and drying by air compressors.

 

Plant Air Service: wet high-pressure air will be provided for various services by dedicated air compressors.

 

Instrumentation Air: dry high-pressure air will come from the plant air compressors; it will be dried and stored in a dedicated air receiver.

 

14.4.11Assay/Metallurgical Laboratory and Quality Control

 

The final concentrate and intermediate streams will be monitored by one on-stream sample analyser with three multiplexers to analyse a total of 16 streams for metal contents. The measured data will be fed back to the central control room and used to optimize the process operation. Routine samples of head, intermediate products, tailings, and final products will be collected and assayed in the assay laboratory, where standard assays will be performed. The data obtained will be used for product quality control and routine process optimization.

 

The site assay laboratory will consist of a sample preparation facility, a metallurgical laboratory and a full set of assay instruments for base metal analysis as well as gold and silver assays. The metallurgical laboratory will perform metallurgical tests for quality control and process flowsheet optimization. The laboratory will be equipped with laboratory crushers, ball mills, particle size analysis devices, laboratory flotation cells, balances, and pH metres. The assay laboratory will be equipped with the following equipment, including:

  
Arctic ProjectPage 281
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Fire assay equipment;

 

An Atomic Adsorption Spectroscopy (AAS);

 

An ICP for the routine assay laboratory;

 

An ICP-MS for the environmental laboratory;

 

A Leco furnace;

 

Other determination instruments such as pH and redox potential meters and experimental balances.

 

14.5Personnel

 

The number of process operations and maintenance personnel is provided in Section 18.2.3.4.

  
Arctic ProjectPage 282
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15INFRASTRUCTURE

 

15.1Introduction

 

The proposed Arctic mine is a greenfield site, remote from existing infrastructure. Infrastructure that will be required for the mining and processing operations will include:

 

Open pit mine

 

Stockpiles and WRF

 

Truck workshop, truck wash, mine offices, mine dry facility and warehouse

 

Power house

 

Administration building

 

Mill dry facility

 

Plant workshop and warehouse

 

Primary crushing building

 

Fine ore stockpile building

 

Process plant and laboratory

 

Concentrate loadout building

 

Reagent storage and handling building

 

TMF

 

Diversion and collection channels, culverts, and containment structures

 

WRCP

 

Process water pond

 

Water treatment plants (WTPs)

 

Camp

 

Figure 15-1 shows the proposed site layout and Figure 15-2 shows the proposed locations of the processing plant, truck workshop and mine offices (collectively referred to as the mine infrastructure area) and administration buildings.

  
Arctic ProjectPage 283
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 15-1: Proposed Site Layout

 

 

Source: Ausenco, 2022.

  
Arctic ProjectPage 284
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 15-2: Proposed Location of the Processing Plant and Other Buildings

 

 

 

Source: Ausenco, 2022.

  
Arctic ProjectPage 285
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.2Access Roads

 

The Arctic Project site will be accessed through a combination of State of Alaska owned highways, a proposed AIDEA owned private AAP road, and proposed Trilogy-owned access roads.

 

15.2.1Ambler Mining District Industrial Access Road

 

The Arctic Project assumes that the ADIEA will construct a road connecting the Arctic Project to the rest of Alaska’s transportation infrastructure. The access road is referred to as the AMDIAP or the AAP.

 

There is currently no road access to the Arctic Project area. Access to the Arctic Project area is proposed to be via the AAP road, which is approximately 340 km (211 miles) long, extending west from the Dalton Highway where it would connect with the proposed Arctic Project area. The AAP road will be permitted as a private road with restricted access for industrial use and received a Federal Record of Decision on July 23, 2020, by the Bureau of Land Management (BLM) and the National Park Service (Joint Record of Decision or JROD). Lawsuits were filed shortly thereafter by a coalition of national and Alaska environmental non-government organizations in response to the BLM’s issuance of the JROD for the AAP.

 

On January 6, 2021, BLM, the National Park Service and AIDEA signed Right-of-Way agreements giving AIDEA the ability to cross federally owned and managed lands along the route for the AAP approved in the JROD. During the second quarter of 2021, AIDEA signed a land access agreement with Doyon Limited to conduct feasibility and permitting activities to advance the AAP and in September 2021 AIDEA signed a land access agreement with NANA Regional Corporation, Inc. to conduct similar activities.

 

On February 22, 2022, the United States Department of the Interior (DOI) filed a motion to remand the Final Environmental Impact Statement (EIS) and suspend the right-of-way permits issued to AIDEA for the AAP and in mid-March, the BLM and DOI suspended the right-of-way grant and the right-of-way permit over federal lands.

 

On September 20, 2022, the BLM published in the Federal Register a Notice of Intent that it will prepare a Supplemental Environmental Impact Statement (SEIS) for the proposed Ambler Mining District Industrial Access Road. The BLM anticipates publishing a draft SEIS during the second quarter of calendar year 2023 and a final SEIS within the fourth quarter of calendar year 2023.

 

The lawsuits have been temporarily suspended pending the additional work to be performed by the BLM on the EIS.

 

Figure 15-3 shows the proposed route of the AAP road.

  
Arctic ProjectPage 286
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 15-3: Proposed Route of AAP Road

 

 

Source: Ambler Access Website, 2018.

  
Arctic ProjectPage 287
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.2.2Arctic Access Road

 

The Arctic Project envisions the development of two access roads to support the proposed Arctic mine: a southern route that will connect the Dahl Creek airport to the AAP road, and a northern route that will connect the AAP road to the Arctic Mine, as seen in Figure 15-4. Development will include upgrading existing roads and trails and construction of new road segments where they currently do not exist. The roads will be designed to accommodate the types of vehicles expected to serve the intended mine and process plant operations.

 

The south route will be 21.4 km long and will be used to transport employees and air freight from the Dahl Creek airport to the Arctic mine. The first 17 km will generally follow the alignment of the existing road between the airport and the existing exploration camp. The remaining 4.5 km to the junction with the AAP road will require new construction.

 

The north route will be 22 km long and will support operations at the Arctic mine by transporting employees, mining equipment, supplies, and ore concentrate to and from the mine site. Approximately the first 8.8 km of the north route will be new construction across the Ambler lowlands. The remaining 13 km will upgrade an existing undeveloped summer/winter trail, including 7.7 km that extend up a narrow and steep valley to the Arctic mine site.

  
Arctic ProjectPage 288
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 15-4: Arctic Access Road

 

 

Source: Trilogy Metals, 2019.

  
Arctic ProjectPage 289
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.3Airstrip

 

The Dahl Creek airport is situated approximately 32 km south of the Arctic deposit. The airport would need to be upgraded with a lighting system and an automated weather observation system to be functional for Project purposes. These upgrades would support the use of Dash 8 aircraft for transporting crew to and from the Fairbanks International airport. The Dahl Creek airport is owned by the State of Alaska, and it is assumed that the upgrades would be accepted if funded by the Arctic Project.

 

New infrastructure that would be associated with the airstrip would include:

 

Pre-fabricated 90 m2 passenger building to accommodate personnel waiting to depart the site.

 

Fabric structure approximately 175 m2 in area to accommodate snow-removal and aircraft service equipment.

 

Precision approach pathway indicators on each end of the runway to aid pilots in acquiring and maintaining the correct approach.

 

Local utilities such as generator power and water services.

 

15.4Camps

 

The Arctic Project will require the use of three different accommodation camps, with one remaining for permanent operations. Each camp will generally be self-contained and have its own power generation and heating capabilities, potable WTP (PWTP), garbage incineration and sewage treatment plant (STP).

 

15.4.1Bornite Exploration Camp

 

The existing Bornite Camp, which is currently used for exploration, is envisioned to be utilized initially for the Arctic Project. The Bornite Camp can currently hold approximately 90 persons. The Bornite Camp will be used to support the initial construction of the Arctic Access Road, and for the initial construction camp. It is anticipated that the camp will be temporarily expanded with seasonal accommodations to allow for about 30 additional persons during construction. Any improvements or expansion will be based on the same airlift transportation logistics as currently utilized to support the Bornite Camp.

 

15.4.2Construction Camp

 

This initial Construction Camp (CC) will be constructed along the Arctic Mine Access Road approximately 8 km from the intersection of the AAP road and Arctic access road, across the road from the Arctic Mine Junction (AMJ) Logistics Yard. The camp will be constructed to provide room and board for 250 persons. The camp will be designed to operate 365 d/a, and of a modular type that can be transported to the site via the Dalton Highway on a semi-prepared AAP road route prior to full truck access being available to the site. The camp will be self-contained and will be integrated and operated as part of the Permanent Accommodations Facility (PAF). It is anticipated that the CC will be demobilized or shuttered upon the commencement of mill operations and the construction phase requirements completed. The transportation and construction of the CC will include the construction of the permanent PWTP, STP, and Garbage Incinerator that will be eventually used to support both the CC and PAF with a combined total occupancy of 650 persons.

  
Arctic ProjectPage 290
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.4.3Permanent Accommodations Facility

 

The PAF will be constructed on the same pad as CC. The PAF will be constructed when the AAP road is available for the transport of the modules, and the pad is upgraded for the permanent construction. The PAF will be located approximately 8 km from the intersection of the AAP road and Arctic access road, and 12 km from the process plant area. The PAF will be operating for approximately 2 years prior to the commissioning of the Arctic mill and production of concentrates. During this period, it will be used to accommodate both construction personnel and the initial Ambler Metals Mine Operations and support personnel required for pre-production mining.

 

An indicative breakdown of personnel onsite during operations is shown in Table 15-1.

 

Table 15-1: Personnel Onsite during Operations

 

Personnel Description   Number of Personnel Onsite
Owner Personnel    
General and Administration   30
Mill Operations   47
Mill Maintenance   101
Mine Operations and Maintenance   135
Contractor Personnel    
Concentrate Trucking Contractor   21
Camp Contractor   29
Other Contractor   8
Other Guests and Non-Employees   7
Total Personnel   378

 

15.5Fuel Supply, Storage and Distribution

 

Diesel will be stored onsite in double-walled steel tanks for use in the power plant at the processing facility and for use in the mine fleet vehicles with a capacity of 30,000 US gallons. A total of 12 horizontal tanks will be used, four tanks within the mine infrastructure area for mine fleet fuel requirements, and eight tanks adjacent to the power plant for generator fuel.

 

The volume stored at the mine infrastructure area will represent nine days of storage and the volume stored at the power plant will represent seven days of storage.

 

15.6Power Generation

 

The plant power supply will be generated on site, with no utility interconnection. A total of five diesel generator sets will be installed to operate in parallel with four operating and one on standby. Each generator will be rated 13.8 kV, 5.5 MW, and the total power output capacity will be 21.6 MW excluding the redundant unit. All five generators will be housed within a shared power plant building; the area adjacent to the building has been left free to allow for addition of a sixth generator in the future if required.

  
Arctic ProjectPage 291
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.7Electrical System

 

The primary power distribution will be at 13.8 kV and will run via above ground cable trays to the area electrical rooms. There will be a total of four major electrical rooms, one of which will be part of the power plant building. The remaining three will be prefabricated modularized type buildings that will be shipped with all equipment pre-installed; these will be placed in the grinding, process and crushing areas. The smaller electrical room for the reclaim water barge will be supplied integral with the barge.

 

The total connected load for the plant will be 25.9 MW with a normal operating load of 21.0 MW.

 

15.8Surface Water Management

 

The proposed mine development is in the upper reach of Subarctic Creek valley, a tributary of the Shungnak River. The combination of the climate, terrain, soils and sparse vegetation result in high runoff potential, especially in May and June when soils are still frozen.

 

The catchment area of Subarctic Creek is approximately 25.8 km2. All mine infrastructure and mine affected water is within the Subarctic Creek valley. A surface water management system will be constructed to segregate contact and non-contact water. Non-contact water will be diverted around mine infrastructure to Sub-Arctic Creek. Contact water will be collected and treated prior to discharge to Subarctic Creek.

 

The objectives of the water management system are to:

 

Ensure sufficient water quantity is available to support processing.

 

Manage contact and non-contact water separately to minimize volume of contact water collected on site.

 

Collect and treat contact and high-sediment water that could otherwise impair the water quality of the receiving streams.

 

Protect mine infrastructure from damage of unmanaged run-off.

 

Reduce suspended solid loading in surface runoff prior to discharge.

 

Store process water to provide for mill water needs

 

Water on site will be managed as one of the following:

 

Non-contact water: non-contact water will be diverted away from mine infrastructure to the extent possible to reduce infiltration into the WRF, TMF inflows, and pit inflows. Non-contact water will be discharged to Subarctic Creek during operations and closure.

 

Contact water: Contact water will be generated when precipitation or run-on comes in contact with mine waste rock, tailings or is collected in the pit. Contact water is treated prior to discharge to Subarctic Creek.

 

High-sediment water: High-sediment water (i.e., surface flows from pads and topsoil stockpiles) is collected and conveyed to downstream ponds to treat prior to discharge in Subarctic Creek, during operations and closure.

 

Figure 15-5 and Figure 15-6 illustrate the water management plan for the initial construction phase and the LOM footprint of the Arctic Project.

  
Arctic ProjectPage 292
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 15-5: Surface Water Management Plan During Operations (Year 2)

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 293
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

 

Figure 15-6: Surface Water Management Plan at the End of LOM (Year 13)

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 294
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.8.1Process Water Supply

 

Process water, gland water, and reagent make-up water will be supplied from the Process Pond and TMF reclaim. Additional process water will be supplied from the WRCP to the TMF through the winter months to meet mill water demands and provide water stored in the TMF as a contingency for dry years. Table 15-2 summarizes mill water supply throughout the year. The TMF dam, WRCP, and Process Pond will be constructed prior to the processing of ore. A water volume of 1.6 Mm3 will be collected in the TMF prior to operations to supply the mill during start-up. Water that accumulates in the WRCP during construction may need to be treated for suspended solids by a temporary water treatment system.

 

Table 15-2: Process Water Supply Summary

 

Months Supply Source Comments
January to April Process Pond, TMF reclaim water and WRCP Water from the WRCP is pumped to the TMF from January to April. This water is accumulated from groundwater flows during the winter months.
May to December Process Pond and TMF reclaim water No WRCP water is pumped to the TMF. From May to December WRCP water is treated and discharged to Sub-Arctic Creek.

 

15.8.2Water Management Infrastructure

 

Stormwater will be managed within the Arctic Project boundaries by capturing and conveying contact and high sediment water for treatment and diverting non-contact water away from developed areas. Water conveyance and storage facilities proposed include the following structure types:

 

Diversion and collection channels.

 

Drop structures, diversion pipes and culverts.

 

Collection ponds.

 

Soils found within the Arctic Project limits consist of alluvial sands and gravels, with limited fines. Runoff from the overburden stockpile and mill site areas should be mitigated by temporarily seeding or using material to create durable less erodible surfaces to prevent or reduce erosion. In addition, water could be recirculated into the TMF or mill flow stream in extreme circumstances. Sediment that accumulates in the Process Pond will be removed periodically to maintain the design capacity.

 

15.8.2.1Diversions and Collection Channels

 

The steep mountainous terrain and compact development footprint will require additional geotechnical and geochemical studies to confirm soil and bedrock depths along the proposed conveyance alignments and acid rock drainage/metal leaching potential. Bedrock is expected to be relatively shallow creating challenges for construction, however shallow bedrock may increase the collection efficiency of surface and shallow sub-surface water interception. In addition, construction of channels within bedrock may eliminate the need for riprap protection while reducing potential seepage through soils in the channel bottom.

  
Arctic ProjectPage 295
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Diversion channels will be constructed around the perimeter of the TMF and WRF, above the overburden stockpiles, and above the mill site infrastructure area. The channels will convey non-contact water runoff to Subarctic Creek. Runoff from haul roads is anticipated to be managed within the road footprint via roadside ditches with runoff reporting to the WRCP. The main purpose of the diversion channels is to reduce the amount runoff contacting mined materials. The diversion of non-contact water will reduce water treatment costs, and storage volume requirements. Channel construction will be phased during the construction period, and prior to commencement of mining to maximize non-contact water diversion.

 

Non-contact and contact water diversions are designed to convey the peak flow from a 100-year 24-hour rain-on-snow event. All channels will have a minimum depth and width of 1.0 m with lining either consisting of bedrock or riprap to provide erosion protection. Riprap will be sized to provide a stable non-erodible conveyance route, with riprap of reasonable size sourced locally on-site (max median particle size, D50 ≤ 300-450 mm). The riprap thickness is specified at two times the D50 and will be placed on geotextile fabric to limit erosion below the armour and reduce sediment loading downstream. Channel depths will include a minimum freeboard of 0.3 m above the design peak flow depth to accommodate potential ice or sediment accumulation, unforeseen climatic events, or other uncertainties.

 

A 4-m wide access road will be located adjacent to each of the channels to provide access during construction and then for maintenance and cleaning of ice and sediment accumulation during operations and closure.

 

Localized seeps are anticipated to be encountered along the alignments during construction. A thorough survey prior to development of engineered design is required to identify areas of potential seep locations and accommodate mitigation measures as needed. Seepage collection and management may require widening of channels in the immediate area to allow for ice build-up during the late fall as conditions change from flowing to frozen water, or to intercept and manage subsurface flowing water within talus slopes. Maintenance of these seeps during the winter could prove challenging during freeze-up and prior to freshet. Prior to freshet flows, channel maintenance will be critical to ensure that adequate freeboard is available, and run-off is contained within the channels.

 

15.8.2.2Culverts

 

Culverts will be required to manage contact water intercepted on the haul roads, and to pass diverted non-contact water through access and haul road corridors. The haul road corridors will traverse the hillside above the WRCP, between the pit and the WRF. The switch-backing layout of the haul roads will present a challenge to manage contact water for each of the small catchment areas, which will change throughout the project life. However, the location of the WRCP immediately down slope of the haul road corridor will allow for contact water to be collected in roadside channels and discharge downslope towards the WRCP for collection. The location and sizing of the culverts along the haul road should be incorporated into the haul road design. A small allowance has been included in the capital expenditures for culvert construction.

 

A major pipe structure (the eastern diversion pipe) will be located above the haul road corridors on the eastern edge of the Arctic Project. This pipe will collect and convey non-contact water collected upslope of diversion channels DV-4 and DV-5 and discharge into Subarctic creek via DV-6 through the Process Pond spillway. Concrete inlet or drop structures will be constructed at the terminus of the channels connecting to the diversion pipe.

 

A temporary diversion channel and pipe (upper reaches of DV-1) will be constructed during the pre-operations period on the western boundary of the WRF. The temporary diversion channel will terminate in an excavated sump, pre-cast manhole or constructed concrete manhole. A pipe will be installed in the sump/manhole conveying water immediately downslope into a receiving channel. The temporary diversion channel pipe, and sump will be buried at the end of the pre-operations period. The temporary channel will be breached periodically at the boundary of the WRF to prevent contact water entering the non-contact water system downstream.

  
Arctic ProjectPage 296
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

All pipe structures are designed to accommodate the 100 year, 24-hour rain-on-snow event. The culverts will be trenched in and backfilled with engineered fill. Diversion pipes located on hillsides will be stabilized by burial or mounding of soils sourced in the immediate area, trenching and backfill, or placed on a prepared bed and secured with concrete thrust block anchors if bedrock depths prevent conventional trenching or burial anchors. All pipes will discharge onto a stabilized rip-rap apron to reduce erosion potential.

 

15.8.2.3Collections Ponds

 

Contact and high sediment water will be routed to the WRCP. Water collected in the WRCP will be pumped to the WTP or TMF for use as mill make-up water. Water collected in the Process Pond will be used as make-up water to the mill.

 

15.8.3Waste Rock Collection Pond

 

The WRCP will be located directly below the toe of the WRF. The pond will collect seepage from the WRF, runoff from the WRF and haul road corridor area, runoff from the ore stockpile on the ROM pad, and water pumped from the pit. The pond is sized to store the 100-year, 24-hour rain-on-snow storm volume plus two days of average snow melt runoff and operational volume. The pond capacity will be approximately 700,000 m³ to the spillway invert of 640.5 masl with a crest height of 642 masl.

 

Water from the WRCP will be pumped to the TMF for reuse as process water or to the treatment plant to be treated and discharged to Sub-Arctic Creek. The WTP operates from May to December during operations but may be operated year-round if needed during extreme water years.

 

The dam will be constructed using overburden and bedrock material from the WRCP footprint or a suitable borrow source. Excess overburden will be stockpiled for use during closure activities.

 

Overburden material below the footprint of the dam will be removed and backfilled with well drained soils (as needed) to provide foundation stability. The excavation limit and dam foundation design requires additional geotechnical investigation. The design presented assumes all material upstream of the embankment centreline will be excavated to bedrock and material downstream excavated to suitable soils. The embankment will be constructed in 300 mm lifts, or as determined by the engineer. The downstream face of the dam will be constructed to 3H:1V while the upstream face will be 2.5H:1V. The upstream face of the pond will be lined with a geomembrane liner connected to a concrete plinth (curb) and grouted curtain wall to maximize interception of surface water and shallow groundwater.

 

A concrete-lined spillway will be constructed to manage flows up to the potential maximum flood (PMF) event. The spillway will include an intake weir and collection throat prior to discharging in the spillway. A stilling basin will be located at the outfall of the spillway, to reduce flows to non-erosive velocities. The spillway length could be reduced by using one of various methods of energy dissipation within the channel; however, energy reduction in the channel generally requires additional depth of flow, resulting in larger concrete requirements. The construction cost would likely be similar. A riprap-lined spillway was investigated; however, steep terrain, lack of geotechnical information, and the channel configuration would likely result in a large costly excavation that could encroach on the haul road located up-slope of the WRCP.

 

Figure 15-7, Figure 15-8, and Figure 15-9 illustrate the proposed design of the WRCP and process water pond.

  
Arctic ProjectPage 297
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 15-7: WRCP and Process Pond Plan

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 298
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 15-8: WRCP and Process Pond

 

 

Source: SRK, 2022.

 

Figure 15-9: WRCP and Process Pond

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 299
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.8.4Process Pond

 

The Process Pond will be located directly below the process plant. The pond will retain water from the tailings thickener overflow for a minimum of 10 days. The pond capacity will be approximately 300,000 m³ to the spillway invert of 584 masl with a crest height of 586 masl.

 

The dam will be constructed using the overburden and bedrock material stripped from within the Process Pond footprint or a suitable borrow source. Excess overburden will be stockpiled for use during closure activities.

 

Overburden material below the footprint of the dam will be removed and backfilled with well drained soils (as needed) to provide foundation stability. The excavation limit and dam foundation design requires additional geotechnical investigation. The design presented assumes all material upstream of the embankment centerline will be excavated to bedrock and material downstream excavated to suitable soils. The embankment will be constructed in 300 mm lifts, or as determined by the engineer. The down-stream face of the dam will be constructed to 3H:1V while the upstream face will be 2.5H:1V. The pond will be lined to crest level with 80-mil primary and 60-mil secondary LLDPE geomembrane liners. A geonet or similar drainage layer will be installed above the secondary liner to convey any leak through the primary liner to a leak collection and recovery sump (LCRS). An underdrain will be constructed beneath the process pond to convey any shallow groundwater below the pond and prevent liner uplift.

 

A concrete-lined spillway will be constructed to manage flows up to the potential maximum flood (PMF) event. The spillway will include an intake weir and collection throat prior to discharging in the spillway. A stilling basin will be located at the outfall of the spillway, to reduce flows to non-erosive velocities. The spillway length could be reduced by using one of various methods of energy dissipation within the channel; however, energy reduction in the channel generally requires additional depth of flow, resulting in larger concrete requirements. The construction cost would likely be similar. A riprap-lined spillway was investigated; however, steep terrain, lack of geotechnical information, and the channel configuration would likely result in a large costly excavation that could encroach on the haul road located up-slope of the WRCP.

 

15.8.5Groundwater Management System

 

Results from the preliminary water and load balance model suggest that small amounts of groundwater could bypass the WRCP, and a cut-off wall may need to be constructed to prevent degradation of water quality in Subarctic Creek. A groundwater interception system was designed downgradient of the WRCP. This system would include:

 

Shallow collector trench across the Sub-Arctic valley bottom for overburden water.

 

Small diameter collector pumping wells completed in bedrock for deep water bypass.

 

Downgradient performance monitoring wells with completions in overburden, weathered bedrock and competent bedrock.

 

A second system located downgradient of all site water management infrastructure was included as a contingency for the closure period, when the open pit contains water and leakage from mine components could bypass the primary system. This system includes small diameter collector pumping wells completed in bedrock, and downgradient performance monitoring wells.

 

Groundwater management system operation would be guided under an adaptive management plan or trigger action response plan.

  
Arctic ProjectPage 300
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.8.6Site Water and Load Balance

 

The water balance model is based on the current water management plan and was used to predict water use, surpluses, and deficits for the site and mine water management infrastructure (TMF reclaim pond, Process Pond, and WRCP) over the 13-year mine life through to closure and post-closure. Mine facility footprints vary according to the mine plan over the LOM. The model evaluated the following hydrological conditions:

 

Average hydrological conditions with mean annual precipitation of 1,219 mm/a over the LOM.

 

Consecutive 1-in-25 year wet years with annual precipitation of 1,816 mm/a in years 12 and 13.

 

Consecutive 1-in-25 year dry years with annual precipitation of 743 mm/a in years 12 and 13.

 

The load balance integrated source terms with the water balance. Source terms define the water chemistry of each water type. For potentially acid generating materials in the WRF and pit, two source terms were developed:

 

Operations source terms prior to onset of acid generation.

 

Closure source terms post-onset of acid generation.

 

PAG waste rock was assumed to generate acid at closure. This change in source terms increased the mass leaching from the WRF and pit during closure.

 

New and existing source terms will need to be updated to incorporate the revised water management plan and updated hydrology assessment. Loading from sources requiring updates are estimated to contribute less than 20% of the total load to the WTP for constituents of concern during operations and Phase 1 of closure but may account for up to 25% to 60% of the total load to the WTP in Phase 2 of closure. This indicates the model may underpredict WTP influent concentrations in Phase 2 of closure. Subsequent revisions of the model will incorporate updated source terms.

 

Constituent mass loads and flows were mixed to estimate concentrations at various locations on the site and in the receiving environment. Contact water will be treated to the Alaskan Water Quality Standards (WQS; 18 AAC 70), as described in Alaska Water Quality Criteria Manual for Toxic and Other Deleterious Organic and Inorganic Substances (ADEC 2008) prior to being discharged to Subarctic Creek.

 

The results from the water and load balance indicate that during operations, excess water from the WRCP will need to be treated prior to discharge to the receiving environment. During closure, the WRCP and water from dewatering of the TMF will be pumped to the pit and will also need to be treated for selenium and other constituents prior to discharge to the receiving environment (see description in Section 17.3).

 

15.9Water Treatment Plant

 

The results from the water and load balance were used to develop a water treatment strategy. The treatment processes were defined based on the approximately 25 parameters predicted in the load balance to be present in WTP influent at peak concentrations above their WQS in the Subarctic Creek or the Shungnak River, including pollutants with a range of treatment mechanisms—cationic metals (such as cadmium and copper), anions (sulphate, fluoride), forms of nitrogen (ammonia, cyanide, and nitrate), selenium, other oxyanions (such as arsenic), and temperature.

  
Arctic ProjectPage 301
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Key aspects of the selected water management overall approach include:

 

Assume the site will be assigned water quality-based effluent limits matching the state’s WQS for the nearby Creek or River. Therefore, design the WTP to treat to all parameters to the WQS applicable to Subarctic Creek, so that site is not reliant on receiving a permit allowing a mixing zone for compliance.

 

Provide a single WTP, built in stages.

 

oThe WTP will initially consist of a chemical/physical plant with reverse osmosis (RO). In the Operations phase, when the TMF is in use, the RO reject will be sent to the TMF, and only RO permeate will be discharged to the Creek. The plant will include:

 

Chemical treatment: Includes addition of caustic, soda ash, ferric chloride, and polymer into mixed reactor tanks. Solids formed are then settled out and removed in a clarifier. This step removes a significant portion of cationic metals such as cadmium and zinc. Liquid chemicals will be stored in tanks; soda ash will be stored in silos.

 

Ultrafilter: Protects the RO system by removing suspended solids carrying over from the chemical treatment system.

 

RO: Concentrates contaminants into the RO reject stream. Permeate water quality will be within WQS.

 

Reconstitution: RO permeate is reconstituted prior to discharge to Subarctic Creek. A calcite contactor tank dissolves carbonate into the discharge water to maintain alkalinity greater than 20 mg/L as calcium carbonate. Caustic and hydrochloric acid are provided as needed for pH adjustment.

 

oWhen the TMF is closed at the end of the Operations phase, a biological/chemical/physical plant will be added to treat the RO reject. This phased approach provides multiple benefits, including allowing time to gain insight on the site’s true wastewater flow and quality so that the RO reject treatment design can be improved upon. This treatment train will include:

 

Gypsum clarifier: Reduces sulphate concentration in the reject treatment stream train to the gypsum saturation limit by adding lime stored in silos. The system will also remove cationic metals such as cadmium and zinc.

 

Anaerobic biological treatment: Biochemically reduces nitrate to nitrogen gas and selenate and selenite to elemental selenium (a solid). Selenium and metal solids removed in the sludge are settled out and removed by the biological ballasted clarifier.

 

Aerobic biological treatment: Polishes residual organics added in the upstream anaerobic biological treatment. Solids are separated via a membrane filter with iron coprecipitation for polishing selenium.

 

oDuring the Closure phase, the WTP will either be run year-round or for partial year based on water storage requirements. During the Operations phase, mill water demands will affect site water flows such that the WTP can be shut down and the discharge eliminated during roughly half of the year (winter).

 

oDuring Operations, sludge from the WTP will be disposed of at the TMF. During Closure, sludge from the WTP will be disposed in filter bags on a lined area which will decant solution back to the pit.

 

This WTP will operate in perpetuity.

  
Arctic ProjectPage 302
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

15.10Tailings Management Facility

 

15.10.1General Description

 

The TMF will be located at the headwaters of Subarctic Creek, in the upper-most portion of the creek valley (refer to Figure 15-6). The maximum storage capacity of the facility will be about 40.7 Mm³ (tailings and process water) at an elevation of 889.5 m plus an additional 2.5 m of freeboard. The 59 ha footprint of the TMF will be fully lined with a geomembrane liner.

 

Tailings containment will be provided by an engineered dam, buttressed by the WRF constructed immediately downstream of the TMF, and the natural topography on the valley sides. A starter dam will be constructed to elevation 805 m two years prior to mine start up and then increased to 830 m by the end of the construction period. Three subsequent raises will bring the final dam crest elevation to 892 m, which is 98 m lower than the final elevation of the WRF. The expected maximum tailings production rate is 8,900 t/d and the TMF is designed to store approximately 37.4 Mm3 (41.2 Mt) of tailings over the 13-year mine life, 3.3 Mm3 of additional pond water, as well as 1.5 times the probable maximum flood (PMF). Instruments installed in the tailings dam are anticipated to include piezometers, settlement monuments, and shape arrays.

 

Tailings will be deposited as thickened slurry from the dam crest by multiple spigots. In the winter, other deposition methods, such as subaqueous deposition and/or single point discharge, may be needed to minimize ice entrainment in the tailings. At the time of this report, detailed laboratory analysis of thickened tailings is underway. For this report, a dry density of 1.1 t/m3 was used to estimate the storage capacity of the facility. The final consolidated tailings dry density is assumed to be 1.25 t/m3 based on simple 2 D consolidation calculations (SRK 2020). To further reduce the duration of tailings consolidation, a drainage system should be evaluated, that would be installed above the TMF liner, convey seepage from the tailings to a sump at the upstream toe of the TMF dam, and then pump the seepage into the reclaim water system.

 

15.10.2Design Criteria

 

The basis of the TMF design is provided in Table 15-3. Values were determined from project-specific information, judgment, and experience with other projects.

 

The TMF design was performed in accordance with the following guidelines, standards, and regulations:

 

Guidelines for Cooperation with the Alaska Dam Safety Program, July 2017.

 

Alaska Administrative Code Title 11, Chapter 93, Article 3 Dam Safety.

 

State of Alaska Mining Laws and Regulations, Alaska Department of Natural Resources Division of Land and Water, 2014.

 

Canadian Dam Association, 2019. Technical Bulletin: Application of Dam Safety Guidelines to Mining Dams.

 

Global Industry Standard on Tailings Management (GISTM), 2020.

  
Arctic ProjectPage 303
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 15-3: TMF Design Parameters and Design Criteria

 

Design Item Criteria Reference
Operational life of TMF 13 years Wood
Total tailings 41.2 Mt Wood
Annual tailings production (solids) 3 Mm3/a Wood
Tailings percent solids (in the slurry pipeline) 47% (Ms/(Ms+Mw)) Ausenco
Tailings solids specific gravity 3.0 SRK
Tailings settled dry density 1.1 t/m3 SRK
Expected tailings deposition angles* 1.0 % SRK (2020)
Tailings deposition Spigots from dam crest (summer) SRK
Target tailings storage requirement 37.4 Mm3 SRK
Dam hazard classification Class I ADSP (2017)
Minimum freeboard above tailings 2.5 m SRK
Tailings dam crest width 30 m SRK
Tailings dam max elevation (height) 892 masl (192 m) SRK
Design earthquake return period and ground motion 1:10,000 year, PGA = 0.374 ADSP (2017), GISTM (2020)
Stability Factors of Safety (FOS) (minimum) 1.0 (pseudostatic) to 1.5 (static) CDA (2019)
Maximum allowable seismic displacement 0.5 m SRK
Dam construction materials Waste rock compacted in 1 m lifts SRK
Dam downstream and upstream slopes 2.5H:1V (maximum) SRK
Starter dam storage capacity (elevation) 1.5 Mm3, Year -1, (805 masl) SRK
End of construction capacity (elevation) 6.5 Mm3, Year 0, (830 masl) SRK
Dam Raise 1 storage capacity (elevation) 13.9 Mm3, Year 1, (850 masl) SRK
Dam Raise 2 storage capacity (elevation) 24.8 Mm3, Year 4, (870 masl) SRK
Dam Raise 3 storage capacity (elevation) 40.7 Mm3, Year 7, (892 masl) SRK
Storm inflow design flood without overtopping 1.5 x Probable Maximum Flood (PMF) SRK, ADSP (2017), GISTM (2020)

 

Notes: *Values from 2020 Trilogy Feasibility Study, based on whole slurry tailings.

 

The design criteria were based on site conditions as of August 2019, on assumptions interpreted from review of available information, and on pre-feasibility-level field investigations and associated reporting. Where data were not available, pre-feasibility-level assumptions were made.

 

15.10.3Overburden Geotechnical Investigation

 

An overburden geotechnical investigation was carried out in 2017 (SRK, 2017) and 2018 (SRK, 2018) to provide overburden characterization in support of waste facility siting evaluation and geotechnical design of the WRF and TMF.

  
Arctic ProjectPage 304
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Surficial deposits mapped in the project area include glacial, aeolian, and fluvial deposits, with colluvium-covered slopes. Most morainal deposits at the site are from the late Pleistocene Walker Lake glaciation, and consist of drift deposits characterized by boulders, cobbles, and gravels in a fine-grained matrix, as well as outwash deposits of silty sand. The Subarctic Creek valley mainly consists of well-graded silty sand and gravel colluvium and alluvium, with some zones of large cobbles and boulders. Overburden thickness within the Subarctic Creek valley generally increases down-valley towards the Shungnak River valley.

 

In the proposed TMF and starter dam footprints, groundwater was encountered during drilling and test pitting at depths between 0.2 and 4.9 m. Groundwater was encountered at depths between 6 and 21 m below ground in the bedrock around the perimeter of the TMF. Based on groundwater elevation records in these areas, the planned facilities will be located in groundwater recharge zones.

 

In the planned WRF footprint, groundwater was encountered during drilling and test pitting at depths between 0.8 m and 13.5 m. Groundwater levels are generally near the surface on the western and central parts of the footprint and deeper on the eastern side of the footprint. Drill holes on both sides of the valley appear to be located in groundwater recharge zones. The center of the valley may correspond to both recharge and discharge zones.

 

The groundwater depth within the footprint of each planned infrastructure within the Subarctic Creek valley is relatively shallow. The average groundwater depth is 1.5 m and seems to correspond to the weathered bedrock–overburden contact. The water depth seems to be relatively constant despite varying surface slope angles.

 

15.10.4Site Selection

 

The TMF site was selected in August 2017 during a workshop (Ausenco 2017) to evaluate locations for the TMF and WRF.

 

A weighting system was applied to four broad categories including environmental concerns, permitting, capital costs, and operating costs.

 

The site was reviewed again in 2021 during a tailings alternative review and found to be the preferred alternative. This work included a thorough review of the GISTM (2020) and the review found the proposed design to be compliant with GISTM.

 

15.10.5Starter Dam

 

Overburden in the TMF starter dam area is characterized as thin well-graded silty sand with gravel or silty gravel with sand (SM or GM). The contact with the underlying fractured weathered bedrock occurs at depths varying between 0.2 and 3.1 m in the TMF and between 1.0 and 9.1 m in the starter dam area. The thicker overburden occurs in the center of the valley, south of the toe of the starter dam. The overburden is interpreted to be colluvial in origin. Bedrock crops out at the north end of the TMF.

 

The overburden will be excavated underneath the footprint of the starter dam and removed to reduce potential settlement and deformation of the TMF dam; overburden removal will therefore reduce the potential for underperformance of the liner that will be installed on the dam’s upstream face.

 

The topsoil and overburden material will be stockpiled below the pit and WRF, respectively, for use in future reclamation of the waste facilities.

  
Arctic ProjectPage 305
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The starter dam will be constructed in two phases to an ultimate lined elevation of 830 m, which will allow for storage of the pre-production water and approximately one year of storage (~1.6 Mm3) to supply the mill during start-up. The upstream and downstream faces of the starter dam will be constructed at 2.5H:1V and constructed entirely of waste rock from the open pit. Waste rock will be placed in 1 m lifts and compacted by the mine fleet haul trucks. Figure 15-10 shows a cross section through the complete TMF and WRF, illustrating the starter dam in relation to the final dam and the downstream WRF.

 

The TMF footprint and the upstream face of the dam will be lined with a textured geomembrane, placed over geotextile on prepared subgrade. To prepare for liner installation, the TMF area will be cleared, grubbed, and stripped of topsoil prior to grading and placement of the geotextile. The face of the dam will be covered with bedding material to protect the liner against puncture from potential sharp edges in the waste rock.

  
Arctic ProjectPage 306
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 15-10: Cross Section of the TMF & WRF showing Starter Dam to Elevation 805 m

 

 

Source: SRK, 2022.

 

Figure 15-11: Cross Section of the TMF and Raises to Final Design Evaluation

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 307
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

15.10.6Dam Raises and Final Dam

 

Three dam raises will be completed to reach the final dam height of 892 m. The construction for these raises will be completed in Years 1, 4, and 7 to elevations 850 m, 870 m and 892 m respectively. Construction will be completed using the downstream method and will connect the structural fill in the tailings dam with the uncompacted WRF. Tailings deposition will be required from the perimeter of the TMF during the construction sequence of the dam crest. The dam crest will be constructed to a width of 30 m at the end of each construction campaign.

 

An upstream slope of 2.5H:1V will be maintained throughout the construction of the dam to facilitate the placement of the bedding layer and the installation of the liner. The downstream portion of the dam will about the WRF at each stage of dam raising. Construction material for the dam will be waste rock compacted in 1 m lifts.

 

Additional liner will be placed within the expanded TMF footprint using the same procedures as for the initial starter dam. The TMF area will be cleared, grubbed, and stripped, and bedding material and geotextile placed prior to the geomembrane being laid down and seamed to the existing liner.

 

Figure 15-11 shows a cross section of the complete TMF and the raises constructed to reach the final design elevation.

 

15.10.7TMF Water Pool and Water Return

 

Under normal situations, the pool will be maintained deeper towards the north portion of the TMF away from the deposition spigots. Recycle water will be obtained using a floating barge and pipeline system situated on the pool.

 

Tailings deposition in winter will be managed to limit ice formation in the tailings, for example, by subaqueous deposition and/or single point discharge of the tailings.

 

Thickened tailings may necessitate modification of pond and deposition management.

 

15.10.8Tailings Delivery and Return Systems

 

The tailings delivery system will transport slurried tailings from the processing plant to the TMF. This will consist of one three-kilometre pipeline, with two kilometres of this being 500 mm (20 inch) diameter carbon steel rubber lined pipeline and the remaining one kilometre being 600 mm (24 inch) HDPE. This pipeline will transport up to 1,843 m3/h of tailings to the TMF.

 

The return water delivery system for recycle water from the TMF has been sized on the basis of 1,308 m3/h of water being pumped from the TMF to the process water pond. This system will consist of a barge pump and a 3 km-long pipeline, run adjacent to the tailings pipeline. The pipeline will consist of 2 kms of 450 mm (18 inch) diameter carbon steel pipeline, with the remaining 1 km being 500 mm (20 inch) HDPE.

 

Both pipelines will be heat-traced to prevent freezing.

 

15.11Waste Rock Facility and Overburden Stockpiles

 

The WRF will be developed north of the planned Arctic pit in the upper part of the Subarctic valley. The waste rock placed in the northernmost portion of the WRF will be compacted to provide structural fill for the TMF.

  
Arctic ProjectPage 308
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

There will also be three stockpiles to store the stripped topsoil and overburden from the TMF footprint.

 

15.11.1Waste Rock Facility

 

The overburden in the WRF area is characterized as well-graded silty sand with gravel or silty gravel with sand (SM or GM) and angular cobbles interpreted to be colluvial in origin. Overburden is slightly thicker on the west side of the valley (± 10 m) than on the east side of the valley (± 6 m), and ranges between 3.0 and 5.6 m in the centre of the valley. Based on exposed bedrock, overburden is inferred to thin on the valley sides.

 

The total volume of waste rock is expected to be 162.6 m3 (340 Mt); however, there is potential for expanded volume in the waste if placement density is < 2.0 t/m³. Most of the waste rock is anticipated to be PAG and there will be no separation of waste based on acid generation potential. Rather, seepage from the WRF will be collected and treated. An underdrain at the base of the WRF will be built to collect and manage the seepage.

 

The WRF is planned to be constructed in 5 m lifts with benches set back at 23.5 m after every fourth lift, to achieve an overall slope of 2.5H:1V. The final design is expected to have variations in the slope aspect, to best manage overland flow, resulting in a transitioning convex to concave shape of the WRF face.

 

The maximum stacking height (above existing grade) of the WRF is planned at 340 m to an elevation of 990 masl. The effective normal stress for potential critical failure surfaces at the base could reach values up to 5,000 kPa, which is higher than the weathered bedrock’s unconfined resistance (on the order of 3,000 kPa) and significantly lower that the competent bedrock resistance (± 32,000 kPa). These values were obtained from uniaxial compressive strength (UCS) tests. Considering the potentially mobilized zone under the stress (and potential strains) imposed by the stacked material, crushing of the waste rock should be expected. A sensitivity analysis was performed to assess the effect of finer-grained, granular waste rock on WRF stability.

 

A rockfill underdrain will be constructed under the WRF in the current Subarctic Creek channel. The underdrain will be excavated into overburden prior to WRF construction and will be capable of handling base flow through the Subarctic Creek valley. Water will be collected in the WRCP at the base of the WRF and held for treatment. The underdrain system will be used to maintain the phreatic water level as low as practicable within the WRF to increase the stability of the facility.

 

15.11.2Overburden and Topsoil Stockpiles

 

Three stockpiles will be developed to store topsoil and overburden materials for use in final site reclamation. The topsoil stockpile will be placed in between the haul roads west of the planned pit and will store up to 325,000 m³. The overburden stockpiles will be located south of the WRF and will store up to 2,200,000 m³. The overburden stockpile geometries may be modified to act as or integrate with avalanche deflection berms.

 

15.12Compressed Air Supply

 

High-pressure compressed air will be provided by three duty and one standby screw compressors and a duty plant air receiver. The instrument air will be dried and then stored in a dedicated air receiver. The plant air will be fed directly from the plant air receiver.

 

High-pressure air for the concentrate filters will come from a dedicated system of two duty and one standby screw compressors and a concentrate filtration area air receiver.

  
Arctic ProjectPage 309
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Low-pressure air for flotation-cell air requirements will be provided by four duty and one standby centrifugal blower.

 

15.13Site Communications

 

External communications, including voice and data, will use a satellite connection with a line-of-sight to an orbiting geostationary satellite. Earth stations are expected to be located at the process plant area, camp area, contractor laydown yard proposed to be located at the road junction between the planned mine access road and the proposed AAP road, and the Dahl Creek airport. There will be separate systems for business operations and personal use.

 

Radio communications around the operation will be a very high frequency (VHF) Hi-Band system with radios in all mobile equipment and operations offices. There will be multiple frequencies with a frequency assigned to a specific operational group. The Dahl Creek airport will have a UHF radio to communicate with in-bound aircraft.

 

It is expected that there will be cell phone access for personal use in a limited area. This system will be installed and maintained by a communications service provider.

 

Communications for truck operators on the AAP road will be with VHF radios utilizing a system that will be installed as part of the AAP road.

 

15.14Fire Protection

 

The firewater distribution network will be maintained under a constant pressure with a jockey pump and will be looped and sectionalized to minimize loss of fire protection during maintenance. Where run outside buildings, fire water piping will be above ground and be heat traced and insulated.

 

Yard hydrants will be limited to the fuel storage tank area. Wall hydrants will be used in lieu of yard hydrants, and these will be located on the outside walls of the buildings in heated cabinets.

 

Fire protection within buildings will include standpipe systems, sprinkler systems and portable fire extinguishers. Standpipe systems will be provided in structures that exceed 14m in height and additionally where required by regulations, local authorities or the insurance underwriter.

 

Camp modules will be purchased with fire detection; fire rated walls and will use separation as a means of fire protection. Handheld extinguishers will be located throughout the buildings.

 

Fire protection of the generators will be provided by a water mist system. Gas detection will be provided to detect dangerous levels of diesel gas within the generator building.

 

15.15Plant Buildings

 

15.15.1Truck Shop and Mine Offices

 

The mine truck shop and mine offices area will be 2,400 m2 in area and will be positioned on an upper pad adjacent to the fuel storage area. This building will consist of the truck workshop, truck wash, mine offices, and mine dry. The truck workshop will have lifting and handling activities fulfilled by an overhead gantry crane. This building will be a pre-engineered steel frame and metal-clad building. The building will be heated using a system that will use waste heat produced from the diesel generators.

  
Arctic ProjectPage 310
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

15.15.2Laboratory

 

The laboratory will be 300 m2 in area and will be situated adjacent to the process building. The building will house all laboratory equipment for the daily operational process control including the metallurgical and environmental requirements. Any mechanical items associated with the dust collection equipment will be located external to the building. The building will be constructed as a single-storey modular wood-frame building. This building will be heated using an air handler system that using waste heat produced from the diesel generators.

 

15.15.3Administration Building

 

The administration building will consist of HR, accounting and senior site management. The building will have an approximate area of 850 m2. The building will be constructed as a single-storey modular wood-frame building. This building will be heated using an air handler system that will use waste heat produced from the diesel generators.

 

15.15.4Mill Dry Facility

 

The mill dry facility will consist of plant change rooms for the process plant area. The building will be approximately 400 m2 in area. These facilities will have clean and dirty areas and will be complete with showers, basins, toilets, and lockers. The building will be constructed as a single-storey modular wood-frame building. This building will be heated using an air handler system that will use waste heat produced from the diesel generators.

 

15.15.5Plant Workshop and Warehouse

 

The plant workshop will be used to perform maintenance on process equipment and equipment spares. The plant workshop will be approximately 780 m2 in area. This building will be a pre-engineered steel frame and metal-clad building. This building will be heated using an air handler system that utilizes waste heat produced from the diesel generators.

 

15.15.6Primary Crushing

 

The primary crushing area will feature a fabric structure approximately 70 m2 in area that will be located above and adjacent to the crusher dump pocket to assist with dust collection measures.

 

15.15.7Crushed Ore Stockpile

 

A geodesic dome will be used over the crushed ore stockpile to keep the ore dry during the winter. The building will be approximately 2,700 m2 in area.

 

15.15.8Process Plant

 

The process plant building will have an approximate area of 4,800 m2, and will house all of the milling, flotation and concentrate thickening equipment. The building will be divided into two sections. The first section will contain the mill and will have dimensions of 30 x 24 m; the second section will contain the flotation, regrind and thickening equipment and will be 36 x 98 m in size. Both sections will be serviced by overhead cranes.

  
Arctic ProjectPage 311
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

This building will be a pre-engineered steel frame and metal-clad building with internal insulation to reduce heat loss. This building will be heated using an air handler system that utilizes waste heat produced from the diesel generators.

 

15.15.9Concentrate Loadout

 

The concentrate loadout building will house process equipment and provide a covered area for loading the concentrate on to the trucks. This building will be separated from the process plant building to minimize the building volume that requires process ventilation equipment. The building will be approximately 1,700 m2 in area, will be a fabric structure and will not be heated to assist in drying out the concentrate prior to transport.

 

15.15.10Reagent Storage and Handling

 

The reagent storage and handling building will be located outside the process plant building. The building will have an approximate area of 680 m2. This building will be pre-engineered steel frame and metal-clad building. This building will be heated using an air handler system that will use waste heat produced from the diesel generators.

 

15.15.11Water Supply

 

The water supply building will be located at the fresh water source and house the pumping equipment. The building will be 36 m2 in area and will be a pre-engineered modular building. It will be heated using electric unit heaters.

 

15.16Concentrate Transportation

 

Concentrate will be shipped from the Arctic mine site to the Port of Alaska in Anchorage in specialized 20ft intermodal bulk shipping containers for direct loading into bulk carrier vessels for ocean transport to the smelter or refinery. Containers will be trucked to Fairbanks, and then transferred to rail for delivery to the Anchorage port terminal.

 

A concentrate trucking contractor will be responsible for loading the containers in the concentrate storage building using a wheeled loader. Containers will be loaded with net 28.1 wmt of concentrate, resulting in 31.2 t gross weight per container. Based on a daily production of 1,289 wmt of concentrates (470,586 wmt per year), approximately 46 containers will be loaded per day and shipped from the Arctic site.

 

The base for the trucking operation will be at the junction where the road to the Arctic Mine would intersect the proposed AAP road, hereafter referred to as the Arctic Mine Junction (AMJ). This would be the primary laydown yard for concentrate containers. The trucking contractor would have a maintenance facility at AMJ, and mobile maintenance trucks along the AAP; however, most major equipment maintenance work is expected to be performed at the concentrate trucking contractor’s Fairbanks operating base.

 

The trucking of the containers to Fairbanks is planned to be undertaken in three stages:

 

Load trucking containers at the Arctic mine concentrate storage building and then transport the container to the AMJ.

  
Arctic ProjectPage 312
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The containers would be trucked from AMJ using the AAP road to the Dalton Transfer Yard (DTY) facility. The DTY would be located near the intersection of the AAP road with the Dalton Highway and would be operated by the concentrate trucking contractor. A Super B-train configuration will be used on the AAP road, with each truck hauling two containers. At DTY, each truck will offload the two containers and return to the mine with two empty containers. This will require approximately 23 trips per day. Drivers would be based at either the Arctic site or AAP road and will complete one return trip per day from AMJ to DTY.

 

The concentrate trucking contractor would use a Fairbanks-based fleet to move the containers using a single trailer configuration from the DTY to a depot in Fairbanks. When the trucks undertake the trip from Fairbanks to DTY, each truck would transport one empty container.

 

In Fairbanks, the containers would be loaded on railcars for transport to the Port of Alaska. At the port, the containers would be staged for direct loading into marine vessels using fixed shore cranes and a container rotator attachment. Concentrate would be shipped from Alaska in 10,000 dmt parcels for copper and zinc, and 5,000 dmt parcels for lead.

 

Table 15-4 provides details of the planned concentrate movement.

 

Table 15-4:          Mode of Transport and Distances for Concentrate Shipping

 

Segment  Mode  Distance (km)  Trips/Day  Trips/Week 
1 Arctic Site to AMJ  Truck – Single Trailer  16  46  322 
2 AMJ to DTY  Truck – Double Trailer  324  23  161 
3 DTY to Fairbanks  Truck – Single Trailer  391  46  322 
4 Fairbanks to Port of Alaska  Rail  573  -  3 
5 Port of Alaska to Asian Port  Marine Bulk Carrier  9,000  -  - 

 

Concentrate shipping containers would be sourced from one of several suppliers and leased. It is expected that a fleet of approximately 1,770 containers would be required.

  
Arctic ProjectPage 313
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

16MARKET STUDIES

 

16.1Introduction

 

The proposed operations will produce copper, zinc and lead concentrates from the Arctic deposit on site, which will then be transported to be sold in the Asia Pacific area. There are currently no contracts in place with any buyers for the concentrate.

 

16.2Metal Prices

 

Metal prices are defined daily by several commodity markets via contract trading, some of which include the London Metal Exchange (LME), the Commodity Exchange (COMEX), the New York Mercantile Exchange (NYMEX), the Chicago Mercantile Exchange (CME), and the London Bullion Market Association (LBMA).

 

Prices are typically set each day, except weekends and holidays. Closing contract values, either based on spot pricing or based on AM/PM demand, are used to define future and expected commodity prices.

 

Metal price projections for use in the Report are guided by three-year trailing average commodity prices and long-term price forecasts from analysts as published by CIBC and approved by Trilogy Management as of November 30, 2022, as summarized in Table 16-1. The metal price assumptions used in the Technical Report Summary economic analysis are:

 

Copper: $3.65/lb

 

Zinc: $1.15/lb

 

Lead: $1.00/lb

 

Gold: $1,650/oz

 

Silver: $21/oz

 

Metal price assumptions used for inputs to Mineral Resources are described in Section 11 and for Mineral Reserves in Section 12.

 

Table 16-1: Average Metal Prices (Data from S&P Market Intelligence and CIBC, 2022)

 

Average Price  Copper ($/lb)   Zinc ($/lb)   Lead ($/lb)   Gold ($/oz)   Silver ($/oz)  
November 2022   3.45   1.24   0.91   1,628   18.92  
1-year trailing   4.10   1.60   0.99   1,808   21.93  
3-year trailing   3.62   1.31   0.93   1,775   22.19  
5-year trailing   3.32   1.29   0.95   1,591   19.67  
CIBC long-term consensus   3.63   1.14   0.91   1,641   21.35  
Report economic analysis   3.65   1.15   1.00   1,650   21.00  

 

Figure 16-1 to Figure 16-5 illustrate historical pricing for the commodities above over the last 5 years, supporting the long-term metal price assumptions used in the Report.

  
Arctic ProjectPage 314
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

 

Figure 16-1: 5-year Average Daily Closing Price for Copper

 

 

 

Source: Data from S&P Market Intelligence, 2022.

 

Figure 16-2: 5-year Average Daily Closing Price for Zinc

 

 

 

Source: Data from S&P Market Intelligence, 2022.

  
Arctic ProjectPage 315
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 16-3: 5-year Average Daily Closing Price for Lead

 

 

Source: Data from S&P Market Intelligence, 2022.

 

Figure 16-4: 5-year Average Daily Closing Price for Gold

 

 

Source: Data from S&P Market Intelligence, 2022.

  
Arctic ProjectPage 316
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 16-5: 5-year Average Daily Closing Price for Silver

 

 

Source: Data from S&P Market Intelligence, 2022.

 

16.3Markets and Contracts

 

A marketing review for the three Arctic concentrates, dated January 5, 2023, was conducted by StoneHouse Consulting based on the expected concentrate assays as provided by Trilogy.

 

Assumptions as to concentrate quality are based on the results of inductively coupled plasma (ICP) analysis of copper and lead concentrates produced from locked cycle tests at ALS Metallurgy and the zinc concentrate from locked cycle tests at SGS. The samples are thought to represent the expected concentrate quality. On the basis of this analysis, it has been assumed that the concentrates will be sent to Asian ports for smelting and refining.

 

No contracts have been entered into as of November 30, 2022 for mining, concentrating, smelting, refining, transportation, handling, sales and hedging, and forward sales contracts or arrangements. It is expected that the sale of concentrate will include a mixture of long-term and spot contracts.

 

Most concentrate is traded on the basis of term contracts. Generally, a term contract is a frame agreement under which a specified tonnage of material is shipped from mine to smelter, with treatment and other charges negotiated at regular intervals (typically annually).

 

Spot contracts are normally a one-off sale of a specific quantity of concentrate to a merchant or smelter. The material is paid for in much the same way as a concentrate shipped under a term contract. Merchant business is a mixture of one-off contracts with smelters and long-term contracts with both miners and smelters.

 

Often terms of sale for a term contract between miners and smelters are at “benchmark terms”, which is the consensus annual terms for the sale of concentrate and negotiated annually. Spot sales are made at spot terms, negotiated on a contract-by-contract basis.

  
Arctic ProjectPage 317
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

16.3.1Chinese Import Restrictions

 

The significance of the Chinese market for concentrate cannot be understated. China imports more than 1.5 Mt of zinc contained in concentrate per year, over 5 Mt of copper contained in concentrate, and over 700,000 t of lead contained in concentrates. China represents between 55- 75% of the traded spot concentrate business in the world. Being excluded from the Chinese market would be unfortunate for a new Project.

 

China is the only country that has national import quality standards for concentrates. Chinese import restrictions can dramatically affect the ability to sell concentrate in that country. For copper, zinc and lead concentrates the current import limits are indicated in Table 16-2 below.

 

Table 16-2:          Chinese Import Restrictions for Copper, Zinc, and Lead Concentrates

 

Current Standard - Maximum Allowed (%)  
Concentrate   Pb     As     F    Cd     Hg 
Copper   6.0    0.5    0.1    0.05    0.01 
Zinc   -    0.6    -    0.3    0.06 
Lead   -    0.7    -    -    0.05 
Zinc/Lead Bulk   -    0.45    -    0.4    0.05 

 

16.3.2Copper Concentrate

 

Trilogy will have the option of selling some portion of the Arctic copper concentrate under long term contracts directly to smelters in China, Japan, and Korea, with the balance being sold under shorter term or spot contracts to the trade, with the same delivery points. The concentrate production at Arctic is too large to rely on the spot market for all its sales volume, although a portion sold under generally more favourable spot terms is recommended.

 

Arctic copper concentrate can be sold directly into China in the spot market and, as such, will be subject to better terms (lower TC) and lower penalty items. This material will not have to blended, but instead will be a quality that would be attractive for trading companies that need to blend down impurities in other concentrates.

 

US origin copper concentrates may be subject to Chinese import duties, which might limit the areas in where Arctic copper concentrate can be sold.

 

16.3.3Zinc Concentrate

 

Because of the elevated level of cadmium, China will not be a market for the zinc concentrate. It is unlikely China will officially increase the Cd limit for imported concentrates, and Trilogy should not rely on exemptions at this point in the planning cycle to import Arctic zinc into China.

 

Even without the Chinese market Arctic zinc concentrate can still be sold to a number of smelters. Many zinc mines that have come onto the market over the past decade contain certain elements that are causing problems for smelters, principally iron, silica, manganese, selenium, and mercury. The most important aspects of Arctic zinc are the medium zinc, low silica, iron and mercury, and good copper levels. Smelters recover copper in zinc concentrates, and the 1.3% content in Arctic will be valued. The low silica, iron and mercury levels will be very attractive to many smelters in Asia and in Canada.

  
Arctic ProjectPage 318
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

With respect to silver recovery, the two zinc plants in Korea, Onsan and Sukpo, several plants in Japan including Dowa’s plant at Akita, Teck’s plant in Trail, the Penoles plant in Torreon, Mexico and the Nyrstar plants in Europe all have good silver recovery and value silver content in zinc concentrates. Other plants have limited silver recovery, or specifically require high-grade, low-impurity zinc concentrate to limit residue production. These plants include Nyrstar facilities at Clarksville (US) and Budel (the Netherlands), and the Valleyfield smelter (Canada).

 

The balance of the smelters fall somewhere in between, with the desire for silver-bearing materials and the need for high-grade, low-impurity concentrates. With respect to Arctic zinc concentrate, even plants that have good silver recovery have impurity limits that could disqualify a high silver zinc concentrate, and these smelters would value some high zinc, low impurity concentrates like Arctic to blend the typically lower grade silver-bearing zinc concentrates. Smelters take a whole menu of concentrates, and they strive to create a feed blend that matches its technical capabilities. Arctic zinc concentrate would be a good fit in the blending portfolio of essentially every Western zinc plant.

 

However, given that most Japanese, Korean, and Canadian smelters are relatively well supplied in the current market, spot market opportunities for Arctic zinc will be limited. It is recommended that most Arctic zinc concentrate be sold under long-term contracts to Asian smelters, and perhaps to the Teck Trail smelter in Canada.

 

It may not be necessary for Arctic to consider shipments to Europe, although larger volume shipments to the Korea Zinc smelter in Australia might be cost effective.

 

16.3.4Lead Concentrate

 

Over the past decade, smelters have become more sensitive to impurity levels for certain elements. For example, most lead plants have restrictions on arsenic, fluorine, selenium, chlorine, mercury, and thallium inputs. The increased vigilance on environmental issues is the primary reason for heightened scrutiny, although processing issues are also a concern with fluorine, chlorine, and selenium.

 

Selenium, at 0.55%, is 400% higher than the level of the next highest selenium in a lead concentrate (Peñasquito). Many smelters do not recover selenium and find selenium contamination a real problem. Some stand-alone lead smelters recover selenium, but most integrated (Zn/Pb) smelters cannot.

 

Korea Zinc, in particular, has tightened its internal controls on impurities in incoming feed. This is largely due to increased environmental enforcement in Korea, which has resulted in a forced temporary closure of a related zinc smelter. It is unlikely that Korea Zinc will be interested in this concentrate. Teck’s Trail smelter will not purchase Peñasquito lead concentrate, which contains 0.07 - 0.15% selenium, so it will not be interested in Arctic lead concentrate. The Stolberg lead smelter in Germany, now owned by Trafigura, has a selenium limit that is much lower than the level in Arctic concentrates. These three smelters- Korea Zinc Onsan plant, Trail, and Stolberg- all have significant precious metals treatment capability but will be uninterested or unable to purchase this concentrate.

 

While high by market standards, fluorine, at 1,500 ppm, can generally be accounted for with a penalty. Fluorine at the high end of the specification, 3,260 ppm, is at a level that would likely require the concentrate to be blended with some low fluorine material to make a saleable concentrate. The cost of blending is borne by the more complex concentrate provider- in this case Arctic. The penalty for fluorine will be significant and will contain a higher per unit penalty above a certain threshold.

  
Arctic ProjectPage 319
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

China remains the best market for this lead concentrate. China produces approximately 75% of the world’s primary lead. Since the production volume of lead concentrate at Arctic will not be high, the concentrate may be a good fit at stand-alone Chinese lead smelters that can handle the selenium.

 

Assuming that Chinese smelters are interested in purchasing the lead concentrate for the precious metals content, there are other issues with selling the concentrate into China, depending on how it is characterized. As the concentrate does not exceed Chinese quality import limits, it could be sold directly into China as a lead concentrate. The silver content in an imported lead concentrate is charged a 13% VAT tax that is payable by the receiving smelter. The silver level in Arctic lead concentrate is high, but just below the 2,500 g/t threshold when it could be sold as a silver concentrate in China and not subject to this VAT. Ignoring the quality concerns with fluorine and selenium, smelters would be less interested in purchasing Arctic lead concentrate than some other materials with less silver content. This reluctance can generally overcome with a higher TC to compensate for the VAT disadvantage.

 

The challenge is to find an appropriate smelter that can value the silver and gold content but at the same time handle the fluorine and selenium impurities. As mentioned above, sales of this concentrate into China will have taxation implications based on the value of the silver content.

 

The copper content in the lead concentrate is good and adds to the value of the concentrate. As this concentrate will likely need to be blended due to the fluorine and selenium, the copper content, when blended, will be a value-added benefit to the smelter.

 

The current indication is that Arctic lead will also contain between 4 and 6% magnesium, presumably as MgO. As this is such a significant impurity the impact on a lead smelter should be evaluated. The QP’s expectation is that the MgO will harmlessly slag off in the furnace, but each smelter may have different sensitivities, so the impact of the high Mg needs to be further evaluated.

 

Significant penalties have been assigned to fluorine, selenium and MgO, but penalty payments alone may not incentivize smelters to purchase this material.

 

At this time, it is felt that the best strategy is to sell the concentrate to trading companies who can blend with other lead concentrate containing low silver and selenium. In this way, the silver gets diluted, reducing the VAT impact, and the selenium gets reduced to an acceptable level.

 

Alternatively, the concentrate gets sold under a silver tolling licence and neither silver nor gold are subject to VAT. One issue with this strategy is that silver cannot fall under 2,500 g/t or else the concentrate will be improperly classified. For Arctic lead concentrate to be sold in this manner, silver needs to be the highest valued component in the concentrate. Depending on the prices of silver and gold, this might not always be the case.

 

It is recommended that a study be conducted to confirm marketability of this product. Smelters should be consulted so that Arctic can get some direction as to whether the elevated levels of fluorine and selenium can be managed.

 

16.4Smelter Term Assumptions

 

Smelter terms were applied for the delivery of copper, zinc and lead concentrate. It was assumed that delivery of all concentrates would be to an East Asian smelter at currently available freight rates. These terms are forecasts and are considered to be in line with current market conditions. No contracts have been entered into at the Report effective date for mining, concentrating, smelting, refining, transportation, handling, sales and hedging, and forward sales contracts or arrangements.

  
Arctic ProjectPage 320
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

16.4.1Copper

 

The contracts for the copper concentrate will generally include the following payment terms:

 

Copper: pay 96.5% of the content, subject to a minimum deduction of 1 percentage unit, at the LME price for copper less a refining charge of $0.08 per payable pound. The minimum deduction applies to Cu grades less than 28.5% and is therefore not applicable to Arctic copper concentrate.

 

Gold credit: If the gold grade is greater than 1 g/dmt and less than 5 g/dmt, then payment is 90% of the content less a refining charge of $5 per payable ounce at the LBMA gold price.

 

Silver credit: If silver content is greater than 30 g/dmt, then the payment is 90% of the content less a refining charge of $0.50 per payable ounce.

 

Treatment charge: $80 per dmt of concentrates

 

Penalty charges:

 

$3.00 for each 1% that the zinc plus the lead grade exceeds 3%

 

$0.50 for each 100 ppm that the antimony grade is above 500 ppm

 

$2.00 for each 0.1% that the arsenic grade is above 0.1%

 

$2.00 for each 100 ppm that the selenium level exceeds 300 ppm

 

16.4.2Zinc

 

The contracts for the zinc concentrate are assumed to generally include the following payment terms:

 

Zinc: pay 85% of content, subject to minimum deduction of eight percentage units at the LME price for zinc. The minimum deduction applies to Zn grades less than 53.3% and is therefore not applicable to Arctic zinc concentrate.

 

Gold credit: none.

 

Silver credit: deduct 3 oz/dmt from the silver grade and pay for 70% of the balance at the LBMA price for silver.

 

Treatment charge: $215/dmt of concentrate delivered; no price participation.

 

Penalty charges:

 

$2 for each 0.1% that the cadmium content exceeds 0.3%

 

16.4.3Lead

 

The contracts for the lead concentrate are assumed to include the following payment terms:

 

Lead: pay 95% of the content subject to a minimum deduction of three percentage units at the LME price for lead. The minimum deduction applies to Pb grades less than 60%.

 

Gold credit: pay 95% of content, subject to a minimum deduction of 1 g/dmt, less a refining charge of $20/payable oz at the LBMA price for gold.

 

Silver credit: pay 95% of content, subject to a minimum deduction of 50 g/t less a refining charge of $1.25/payable oz. The minimum deduction applies to Ag grades less than 1,000 g/dmt and therefore does not apply to Arctic lead concentrate.

  
Arctic ProjectPage 321
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Treatment charge: $160/dmt of concentrate delivered.

 

Penalty charges:

 

$5.00 for each 1,000 ppm that the bismuth content exceeds 1,000 ppm

 

$4.00 for each 100 ppm that the selenium content exceeds 500 ppm

 

$2.00 for each 100 ppm that the fluorine content exceeds 500 ppm, plus $5.00 for each 100 ppm above 1,000 ppm, plus $10 for each 100 ppm above 2,000 ppm

 

$2.00 for each 0.1% that the MgO content exceeds 2%

 

16.5Transportation and Logistics

 

Transportation cost assumptions for the concentrate are summarized in Table 16-3.

 

Table 16-3:          Concentrate Transport Costs

 

Description  $/dmt 
Container cost   7.80 
Arctic Mine to Fairbanks (truck)   215.89 
Fairbanks to Port of Anchorage (rail)   33.92 
Port Terminal & Handling   24.21 
Ocean Freight to Asian Port   42.55 
Total Concentrate Transport Costs   324.37 

 

16.6Insurance

 

An assumed insurance rate of 0.15% was applied to the recovered value of the concentrates less refining, smelting, penalties, and treatment charges.

 

16.7Representation and Marketing

 

An allowance of $2.50/wmt of concentrate was applied as an allowance for marketing and representation.

 

16.8Comments on Market Studies and Contracts

 

The QP has reviewed the information on marketing, payable and penalty assumptions and metal price assumptions, and considers that they are acceptable for use to support the Mineral Reserve estimates in Section 12 and the economic analysis in Section 19.

  
Arctic ProjectPage 322
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

17ENVIRONMENTAL STUDIES, PERMITTING, AND Plans, Negotiations, or Agreements with Local Individuals or Groups

 

17.1Environmental Studies

 

The Arctic Project area includes the Ambler Lowlands and Subarctic Creek within the Shungnak River drainage. A significant amount of baseline environmental data collection has occurred in the area including surface and ground water quality sampling, surface hydrology monitoring, hydrogeology studies, meteorological monitoring, wetlands mapping, aquatic life surveys, avian and mammal habitat surveys, cultural resource surveys, and metal leaching and acid rock drainage (ML/ARD) studies.

 

17.1.1Hydrology

 

The Arctic Project hydrology studies are ongoing. Shaw Environmental collected water quality samples in 2007, 2008, and 2009 and measured stream flow at 13 stations on the Shungnak River, Subarctic Creek, Arctic Creek, and the Kogoluktuk River as seen in Figure 17-1 (Shaw, 2007, 2008, 2009).

 

Tetra Tech performed baseline studies in July 2010 to characterize stream flow and water quality that could be potentially impacted by the construction and operation of a proposed access road between the Bornite and Arctic airstrips, and the existing road between the Arctic airstrip and the Arctic deposit. Tetra Tech collected water quality and flow data at 14 sites (Tetra Tech, 2010a).

 

Two hydrologic gauging stations were installed on the Shungnak River (SRGS site) and Sub-Arctic Creek (SCGS site) respectively by DOWL HKM in July 2012. Each station is powered by dual solar panels and a battery, and continually measures and records water depth, temperature, pH, and conductivity. A third hydrologic gauging station was established at the Lower Ruby Creek Gauging Site (RCDN) by WHPacific in June 2013. The RCDN station was moved upstream in 2017 due to a beaver dam. An additional hydrologic gauge (SCMET) was installed near the proposed waste rock collection pond in July 2021. All four of these stations have remained in operation since their installation. Dave Brailey, a contracted hydrologist, has used the depth data to generate rating curves and daily discharge calculations for the SRGS, SCGS, and RCDN sites.

 

Ambler Metals staff have measured instantaneous stream flow and other standard field parameters (YSI 556 multi-parameter unit) during seasonal sampling events from 2013 to 2019, 2021, and 2022 to present in Sub-Arctic Creek, Ruby Creek, the Shungnak River, and select tributaries to these drainages. The baseline water quality and hydrology program were expanded in 2016 from seven to over 20 sampling sites, with additional locations in Cabin Creek, Riley Creek, Wesley Creek, and the Kogoluktuk River (Craig, 2016). Additional locations on Camp Creek and Sub-Arctic Creek were added in 2019.

  
Arctic ProjectPage 323
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 17-1: Current Water Quality and Hydrology Stations’ Location Map

 

 

Source: Craig, 2022.

 

A snow survey was conducted in March 2018 around the site area in the upper reaches of the Sub-Arctic Creek watershed. The survey consisted of 52 locations using a Federal Snow Sampling tube. The purpose of the snow survey was to determine the snow water equivalent of various representative locations in the Subarctic Valley (Craig, 2018).

 

Additional snow surveys were conducted in March 2021 and April 2022 using similar methodology (Stockert, 2021 & 2022).

 

SRK (2020) reviewed existing baseline hydrological data for the Arctic Project site and prepared a regional hydrology analysis. SRK conducted an update in 2022 to include the most recent precipitation and hydrologic data (SRK, 2022).

 

Project and publicly available data were used to estimate mean annual precipitation (MAP) and mean annual runoff (MAR) at the Arctic Project and extend the available record period. The 2020 analysis predicted a MAP of 1,294 mm and a MAR of 1,089 mm for the Sub-Arctic Valley. The increase in estimated MAP from the SRK 2018 investigation is mainly due to incorporating a precipitation undercatch correction developed based on the snow survey data collected in 2018. The 2022 update predicted a MAP of 1,219 mm and a MAR of 1,130 mm for the Sub-Arctic Valley. The Arctic Project’s evaporation estimates were also updated in 2022 using climatic records and an empirical relationship. Evaporation estimates are stable and have not changed since SRK’s 2018 climate and hydrology review (SRK, 2018).

  
Arctic ProjectPage 324
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Three precipitation gauges were installed in July 2021 by Boreal Services in the Sub-Arctic Valley. The precipitation gauges functioned properly through the winter of 2021/2022 and measured the precipitation from rain and snowfall. In addition, a snow monitoring gauge was installed to measure the weight of the snow at the Sub-Arctic Valley Meteorological Station. The additional sensors will help to improve the MAP and MAR estimates of the Sub-Arctic Valley drainage.

 

An evaporation pan was installed in July 2021 to measure the actual evaporation during the summer months. Winter evaporation is assumed to be negligible.

 

Unit measured flows at the nearby USGS Dahl Creek and the Kobuk River at Kiana stations were compared to unit measured flows at the SRGS and SCGS hydrologic gauging stations for a concurrent monitoring period Flows measured in Dahl Creek closely resemble unit flows at the Arctic Project (Brailey 2019 & SRK 2022).

 

17.1.1.1Recommendations

 

The Arctic Project should add additional transducers to the Geonor precipitation gauges to guard against transducer failure or drift and to provide more certainty regarding the data quality.

 

Frequent checks and equipment calibration are necessary to maintain quality data collection and ensure correct instrumentation functioning. Annual reporting of instrumentation checks and data quality reviews should be completed.

 

17.1.2Water Management

 

Water quality monitoring was conducted in the area over the past eleven years. The baseline monitoring data was supplemented with publicly available regional data to evaluate long-term trends.

 

In July 2010, Tetra Tech performed baseline studies to characterize flow and water quality in several streams that could be potentially impacted by construction and operation of a proposed access road between the Bornite airstrip and the Arctic airstrip, and the existing road between the Arctic airstrip and the Arctic deposit. Tetra Tech collected water quality and flow data at 14 sites. The results of the Tetra Tech sampling program indicate that, in general, the water quality for all sites meets applicable Alaska State water quality standards (WQS) for the parameters analyzed. Water quality sampling was conducted by Trilogy from 2012 to the present. Small sampling programs were performed from 2012-2015 during the summer field season. The water quality sampling program was expanded in 2016 to include more sample locations in the Shungnak River, Subarctic Creek, Ruby Creek, Riley Creek, Wesley Creek, and the Kogoluktuk River and to include sampling throughout the year. Several seeps in the Subarctic Creek drainage near the Arctic Project were sampled.

 

Samples were analyzed for both total and dissolved metals, mercury, cyanide, chloride, fluoride, nitrates, sulphate, acidity, alkalinity, total suspended solids, conductivity, pH, total dissolved solids, total organic carbon, and total phosphorus. The information will be used in the permitting and facilities design.

  
Arctic ProjectPage 325
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

17.1.3Wetlands Data

 

Tetra Tech performed a program of jurisdictional wetlands identification in a portion of the Arctic Project area in 2010, as part of a study to identify potential road alignment alternatives between the Bornite and Arctic airstrips. The work included data review, vegetation mapping, aerial photographic interpretation (segmentation), and field soil surveys. The work is summarized as follows.

 

The area between the Bornite and Arctic airstrips consists of a wide valley containing the Ambler lowlands and the Shungnak River. Wetlands are prevalent throughout much of the Ambler lowlands. Most of the wetlands within the area occur within tundra vegetation communities composed primarily of ericaceous shrubs, such as Alpine blueberry (Vaccinium uliginosum) and Northern-Mountain Cranberry (V. vitis-ideae) and graminoids, such as Tussock Cotton-Grass (Eriophorum vaginatum) and sedges such as Two-Color Sedge (Carex bigelowii) and Leafy Tussock Sedge (C. aquatilis). Forests of White Spruce (Picea glauca) and Black Spruce (P. mariana) and shrub birch communities of Swamp Birch (Betula nana) and Resin Birch (B. glandulosa) make up most of the upland communities.

 

In 2015, Trilogy engaged DOWL to perform additional wetlands mapping and generate two preliminary wetlands determinations for a 5,910-acre study area (DOWL, 2016). The study area included the entire Subarctic Creek drainage and the majority of the areas that could be directly impacted by the proposed Arctic open pit and mine facilities. The broad study area comprises 715 acres of potentially jurisdictional wetlands, 40 acres of Waters of the United States and 5,155 acres of non-jurisdictional uplands. According to DOWL (2016), the field work was performed in accordance with Part IV of the Corps of Engineers 1987 Wetlands Delineation Manual and the Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Alaska Region (Version 2.0, 2007). Wetlands were classified and grouped according to the Class Level and system guidelines outlined in Classification of Wetlands and Deepwater Habitats of the United States (1979). The functional rating of potentially jurisdictional areas was determined using the criteria outlined in the 2009 Alaska Regulatory Guidance Letter, ID No. 09-10, the Cowardin Class, and observed hydrology. Ten ecological attributes were examined to subsequently rank wetland habitats as having low, moderate, or high functional ecological services. Riverine habitats (rivers and streams) perform vastly different functions compared to wetlands. Accordingly, riverine systems were evaluated based on the presence or absence of 17 functions according to the criteria outlined in the U.S. Department of the Interior Bureau of Land Management, Technical Report 1737-15, Riparian Area Management: A User Guide to Assessing Proper Functioning Condition and the Supporting Science for Lotic Areas.

 

Additional wetlands delineation work was done by DOWL in 2016, 2018 and 2019 to provide wetlands delineation of the entire proposed Arctic Project footprint including access roads, camps, stockpiles, mining, and waste storage facilities.

 

17.1.4Aquatic Life Data

 

A biological consultant (Tetra Tech) performed aquatic life studies in 2010 in the area between the Bornite and Arctic airstrips, and along the Arctic deposit road in Subarctic Creek. The purpose of this study was to characterize the aquatic life within the Shungnak River and select tributaries. Opportunistic observations were also collected in the Kogoluktuk River. Fish species documented included Arctic grayling (Thymallus arcticus), round whitefish (Prosopium cylindraceum), slimy sculpin (Cottus cognatus), and Dolly Varden (Salvenlinus malma). Fish and macroinvertebrate data were collected from July 8 to 14, 2010.

 

In 2016 Trilogy engaged Alaska Department of Fish and Game (ADF&G) to complete aquatic studies as an extension of the work done by consultants in prior years. ADF&G has performed aquatic biomonitoring surveys at several large hardrock mines in Alaska, and has performed aquatic surveys onsite from 2016-Present except in 2020 due to the COVID-19 pandemic. Each year, ADF&G sampled for periphyton, aquatic invertebrates, and fish. Fish were captured using minnow traps and fyke nets. A subset of fish were retained for whole body element analysis. Sample sites have been added and refined over the years, and in 2022 ten sites in the Shungnak River drainage were sampled, including two in Ruby Creek and two in Subarctic Creek. An additional site on Riley Creek in the Kogoluktuk River drainage was also sampled for a total of 11 sites (Figure 17-2).

  
Arctic ProjectPage 326
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 17-2:          2021 Aquatics Sampling Sites

 

 

Source: ADF&G, 2021

 

Some of ADF&G’s results show that Subarctic Creek, which drains the Arctic deposit area contained relatively low background concentrations of zinc and copper, as well as low total dissolved solids (TDS). Upper Subarctic Creek had the highest number of aquatic invertebrates but also had the lowest species richness with a total of 11 taxa identified. Lower Subarctic Creek had a significantly lower average number of aquatic invertebrates but more diversity than upper Subarctic Creek.

  
Arctic ProjectPage 327
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Periphyton, or attached micro-algae, are sensitive to changes in water quality and are often used as evidence of in-situ productivity. The concentrations of chlorophyll-a are determined to estimate periphyton standing crop. Typically, Upper Ruby Creek has the highest concentrations of chlorophyll-a.

 

The aquatic invertebrate samples are sorted and identified to the lowest taxonomic level. Because invertebrates belonging to the orders Ephemeroptera (mayflies), Plecoptera (stoneflies), and Tricoptera (caddisflies) (EPT) are more sensitive to water quality, the proportion of EPT at each site was calculated and compared to other groups of aquatic invertebrates. Macroinvertebrate density for each sample was also calculated. In 2021, Upper Ruby Creek and Upper Subarctic Creek had the highest aquatic invertebrate densities. Lower Subarctic Creek and Lower Red Rock Creek had the highest proportion of EPT.

 

Despite being isolated from the Kobuk River by a large waterfall preventing migrations of anadromous fish, the Shungnak River drainage supports self-sustaining populations of Arctic grayling, Dolly Varden, round whitefish, longnose suckers, Alaska blackfish, and slimy sculpin. Minnow trap catches in Subarctic, Red Rock, and Center of the Universe creeks are dominated by Dolly Varden. Slimy sculpin is the majority of the catch in minnow traps in Ruby Creek (Clawson 2022a). The fyke nets at the mouth of Ruby Creek primarily capture Arctic grayling and round whitefish, although in 2017 large numbers of longnose suckers were also captured.

 

In 2021 and 2022, winter sampling for fish presence was conducted in March/April. Dolly Varden was captured at Upper Subarctic Creek, Center of the Universe Creek, and middle Subarctic Creek, demonstrating that at least some fish overwinter in these drainages instead of dropping down to the Shungnak River. The groundwater inputs into these streams are a steady temperature all winter and prevent the streams from freezing solid, enabling fish to survive over winter.

 

Over the six years of baseline data collection, different fish species have been sampled at different locations, therefore comparisons between sample results for fish whole body element concentrations must be evaluated accordingly. Generally, cadmium concentrations are highest in fish from Subarctic and Red Rock creeks and lowest in Ruby Creek fish. Whole body copper, selenium, and zinc concentrations are similar at all sample sites. Mercury concentrations are lowest in fish from the Subarctic and Red Rock creek drainages and highest in fish from Ruby Creek. Element concentrations fall within the range documented in fish from other drainages throughout the.

 

17.1.5Hydrogeology Data

 

In total, from all programs over the last 10+ years, hydrogeological data is available from:

 

monitoring wells including two pumping wells in the valley bottom area; 12 boreholes with single or multiple vibrating wire piezometers (i.e., 25 VWP sensors in total) and seven standpipe piezometers in proposed pit area;

 

39 boreholes; 15 in the area of the proposed open pit and 24 in the valley bottom area;

 

Hydrogeologic testing data from 74 packer-based hydraulic tests; 19 slug tests; two pumping tests in valley bottom, each with an observation well; three extended injection tests in planned open pit area, one of six hours duration and two greater than 24 hours, each with monitoring at nearby vibrating wire piezometers (VWPs); 122 particle size distributions from test pits in valley floor;

 

Groundwater level series data from 24 VWPs and two standpipe piezometers in pit area; 20 water level dataloggers in valley bottom, and manual observations from the monitoring wells;

 

Dedicated ground temperature cables at six locations in valley floor; temperature from all VWP sensors, including those in the planned open pit area;

  
Arctic ProjectPage 328
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Groundwater quality data from eleven monitoring wells, collected quarterly to once per year, depending on access and location. Most wells are within the Subarctic Creek valley bottom, upgradient, within and down gradient of the mine footprint.

 

Data were compiled into conceptual models for the planned valley bottom WRF and water management areas, as well as for the open pit area. Hydraulic head data indicate that groundwater flow is topographically driven, with recharge in the uplands and discharge in the valley bottom. At the large scale, hydrostratigraphic units include overburden, weathered bedrock and competent bedrock.

 

In the valley bottom, overburden, where coarse grained, and weathered bedrock are the primary aquifer units. Flow within competent bedrock is restricted to open fractures and generally has a lower hydraulic conductivity. Flow is in a down-valley direction, with groundwater divides generally aligned with the surrounding ridges.

 

In the planned pit area, the hydrostratigraphy is dominated by competent bedrock, with sub-units including upper and lower fractured rock, talc and geological structures. Talc may represent an aquitard located between the upper and lower fractured rock units. Water levels from the fractured rock units show a downwards gradient across the talc; the talc acts as a confining unit with the potentiometric surface for the lower fractured rock typically above the talc. Geological structures are present and can act as conduits or barriers to flow. There were no structures showing consistent barrier or conduit characteristics over the scale of the proposed pit. Compartmentalization is a possibility.

 

In the valley bottom, WRF and water management structures are designed to reduce release of contact water towards the down gradient receiving environment. Groundwater bypass of these systems could occur, though would be expected to be of low quantity as it would likely occur through the competent bedrock hydrostratigraphic unit. Groundwater moving down the valley can be assumed to largely discharge to Subarctic Creek before the creek enters the Shungnak River valley.

 

17.1.6Cultural Resources Data

 

In 2016, Trilogy contracted WHPacific to perform a cultural resource assessment of the project area. WHPacific’s assessment included a literature review, archival research, stakeholder meetings in the communities of Shungnak and Kobuk, and an archaeological field survey of the Arctic Project. WHPacific’s literature and archival review included reviewing confidential Alaska Heritage Resource Survey Site information, which revealed that no archaeologic sites have been recorded in the project area (WHPacific, 2016). Stakeholder meetings with local community members indicated that the areas near the Arctic Project were not used by local residents in the past due to the lack of resources and passages to areas north, west, and east, where other resources and trading opportunities existed.

 

WHPacific’s field survey was conducted by two archaeologists and included an initial aerial reconnaissance of all 2,327 acres of the survey area, executed through the use of helicopter overflights at low elevation for observation by the archaeologists. As a result of this flyover, WHPacific determined that the majority of the Project area had a low probability of containing cultural resources due to saturated and marshy terrain and dense vegetation. Areas of low to moderate probability included dryer areas of elevated terrain, lower valley slopes, ridges, flat areas overlooking valleys, and terraces along the waterways. Of the total Arctic Project acreage, WHPacific conducted pedestrian survey of 530 acres and excavated a total of 13 shovel probes on NANA-managed lands. No cultural resources were found in the survey area. WHPacific did note that late 20th century mining exploration is in evidence in the project area as seen by roads, abandoned equipment, and the airfield (outside of the direct survey area). These are of an age that is on the cusp of being considered historical period resources (50 years or older) according to the National Historic Preservation Act. However, these resources are not unique within northern Alaska or for 20th century mining materials.

  
Arctic ProjectPage 329
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

WHPacific’s (2016) recommendation based on their literature review, community interviews, and fieldwork was that no further cultural resources work was required, and that Project work associated with the proposed Arctic pit, facilities, tailings, and access road corridor project should proceed as planned.

 

Subsequent to WHPacific’s investigation, Trilogy has made several minor additions to the Arctic Project, such as road corridors and material sites. To provide complete archaeological coverage for all areas of planned development, Trilogy contracted additional cultural resource fieldwork in 2018 by Kuna Engineering (2018) and in 2019 Walking Dog Archaeology (2020). These efforts included literature reviews and field investigations of the remaining areas potentially impacted by the project footprint including camps, access roads and material sites. Neither of these two investigations resulted in the identification of previously undocumented cultural resources.

 

17.1.7Subsistence Data

 

Access to the Arctic Project area includes travel over private lands owned by NANA. Subsistence is important to local residents, and as a result, a Subsistence Committee comprised of locally appointed residents from five potentially-affected communities in the region has been formed to review and discuss subsistence issues related to activities within the UKMP, including the Arctic Project and to develop future compliance plans. Representatives from NANA and Ambler Metals facilitate the meetings and report a summary of the discussions and recommendations provided by the Subsistence Committee to the Oversight Committee, as defined by the NANA Agreement. The Subsistence Committee meets twice annually and discusses development plans and potential subsistence issues.

 

In 2012, Stephen R. Braund & Associates completed a subsistence data-gap memo under contract to the Alaska Department of Transportation and Public Facilities as part of the baseline studies associated with the proposed road to the Ambler Mining District. The purpose of this analysis was to identify what subsistence research had been conducted for the potentially affected communities, determine if subsistence uses and use areas overlap with or may be affected by the access road project, and identify what, if any, additional information (i.e., data gaps) needed to be collected to accurately assess potential effects to subsistence. Among other topics, the report outlined historic subsistence uses including maps and a literature review, and provided a synopsis, by village, including those villages closest to the Arctic Project, and suggested further study.

 

An ADF&G report titled, “Wild Food Harvests in 3 Upper Kobuk River Communities: Ambler, Shungnak, and Kobuk 2012-2013” (ADF&G 2015) provides a comprehensive analysis of subsistence food sources and their usage by the three Upper Kobuk villages. The report detailed the ethnographic history, contemporary usage, common species harvest methods, and abundance.

 

Previous sampling efforts established the presence of various salmon species, northern pike and sheefish in the lower Kogoluktuk River. Sampling efforts in the Shungnak River have established the presence of northern pike. The presences of fish are good indicators of the possibility of subsistence use of these rivers, but boat access is limited due to waterfalls and rapids. In comparison, the Kobuk River, a wide and easily navigable river on which the communities of the region exist, supports the bulk of subsistence fishing.

 

Determining the presence and distribution of caribou is complex because of seasonal and annual variability in migration patterns. The ADF&G and National Parks Service employ a radio collar monitoring program as well as aerial photography to estimate herd size and migration patterns. The ADF&G also estimates mortality rates for cows, calves, and bulls, as well as other biomonitors for health such as body fat and predator populations.

 

The Northwest Arctic Borough (NWAB), through its Title 9 Conditional Use permit, regulates the Arctic Project with respect to caribou interactions to assure the migration is minimally affected by mining and exploration activities. To this end, Ambler Metals has communicated with the ADF&G wildlife biologists, who monitor caribou herd movements in the spring and fall in proximity to the Arctic Project by using radio-collared caribou. Summary maps of those movements constructed from years of radio collar information indicate three main migration corridors to the west of the Arctic Project area for the Western Arctic caribou herd. The nearest herd is approximately 48 km west of the project area.

  
Arctic ProjectPage 330
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

DOWL (2016) performed a large mammal habitat survey in the project area. Historic maps of caribou migration included in their report show that the project area is outside of main caribou corridor routes and calving areas, but that data from 1988-2007 suggested that the area may be used for wintering habitat.

 

17.1.8Endangered Species, Migratory Birds, and Bald and Golden Eagle protection

 

In 2016, Trilogy engaged WHPacific, through subcontractor ABR, Inc., to perform aerial surveys of nesting raptors in the project area, including the Bornite area located some 24 km southwest of the project area. ABR (2017) identified a total of 26 nests, of which 18 were in the Bornite area and eight were in the project area. Fifteen of the totals were occupied in the initial occupancy survey; nine were occupied by rough-legged hawks, with three peregrine falcon nests and three raven nests. In the later productivity survey ABR observed that only one rough-legged hawk nest had a (single) nestling, one peregrine falcon nest had two young and an unhatched egg, and two raven nests had young (not counted).

 

In 2017, Trilogy engaged WHPacific to review requirements that would be necessary to comply with the Endangered Species Act, the Migratory Bird Treaty Act and the Bald and Golden Eagle Protection Act. WHPacific (2017) concluded that there are no endangered species or critical habitat in the project area. Further they reported that nine avian species of conservation concern are expected to occur or could potentially be affected by activities in the project area. They provided the timing guidelines for vegetation clearing that are meant to protect these species during nesting activities and advised that if impacts to migratory species are unavoidable for the Arctic Project that the US Fish and Wildlife Service (USFW) must be consulted. They also recommended that Trilogy request a project review from USFW when the Arctic Project is closer to initiation.

 

17.1.9Metal Leaching / Acid Base Accounting Data

 

Drill core samples were used to characterize the acid generation potential of the mine waste for the Arctic Project. In 1998, Robertson collected 60 representative core samples from the deposit for their ABA characteristics; these samples provided a broad assessment of ARD potential at the Arctic deposit with a focus on characterization for surface development. In 2010, SRK collected 148 samples and prepared a preliminary analysis of the ML/ARD potential of waste rock at the Arctic deposit (SRK 2011). The SRK report focused on characterization for underground development rather than an open pit scenario; however, it did provide a more refined analysis of ARD potential based on advances that have been made in understanding the importance of sulphide mineralogy in assessing ARD potential. The criteria used for classifying ARD potential also differed slightly from the Robertson era work.

 

In 2015, Trilogy retained SRK to provide on-going ML/ARD characterization services for the Arctic Project. Activities in 2015 through 2018 focused on three objectives: 1) set up and on-going monitoring of on-site barrel tests (kinetics), 2) initiation and on-going monitoring of parallel laboratory humidity cell tests (kinetics), and 3) expansion of the ABA database (statics). Barrel test leachate samples were routinely collected during 2016 through 2018 and analyzed by ARS Aleut Analytical. Humidity cell tests were monitored on a weekly basis by Maxxam Analytics of Burnaby, British Columbia. Trilogy and SRK selected 1,119 samples to be analyzed for a conventional static ABA package with a multi element scan using the same methods as the exploration database. Samples were analyzed by Global ARD Testing Services of Burnaby, British Columbia.

  
Arctic ProjectPage 331
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

In 2017, tailings humidity cell testing was initiated to investigate the ML potential of unsaturated tailings. Monitoring was as described above for the waste rock humidity cell tests.

 

Activities in 2019 focused on expanding the kinetic testing program to characterize the metal leaching potential of the range of geochemical compositions present in each of the main waste rock units, in addition to testing ore. New lab kinetic tests were initiated, and monitoring of the lab kinetic tests initiated in 2015 also continued, with all tests operating at Maxxam Analytics of Burnaby, British Columbia. Barrel test leachates were sampled routinely in 2019 and analyzed by Maxxam Analytics, to maintain consistency in detection limits between laboratory and field kinetic tests.

 

Additional kinetic tests were also started on tailings in 2019, including a further humidity cell, and a subaqueous column to investigate ML in subaqueous conditions. Tests were monitored on a weekly basis by Bureau Veritas Labs (BV; previously Maxxam Analytics) of Burnaby, British Columbia.

 

Static testing of overburden also occurred in 2019, including static leach tests, to investigate ARD/ML potential of freshly excavated overburden. Samples were collected from previous test pits and drill core used for geotechnical investigations.

 

In 2020, additional humidity cell tests were initiated on AMR at BV to improve the representivity of kinetic tests on this unit and to investigate the suitability of near-surface AMR for construction use. Monitoring of previous humidity cells and the tailings subaqueous column continued.

 

In 2021, monitoring of previous kinetic tests at BV labs continued except for three tests which were completed. Barrel test leachates were also sampled routinely in 2021 and analyzed at BV labs.

 

In 2022, additional humidity cell tests were initiated on ore and tailings and a subaqueous column was initiated on tailings, all at BV labs. Monitoring of previous kinetic tests at BV labs continued with six tests reaching completion in December 2022. Barrel test leachates were sampled routinely in 2022 and analyzed at BV labs.

 

17.2Operational Site Monitoring

 

Requirements and plans for waste and tailings disposal during operations can be found in Sections 15.8.5 and 15.10.1. Information regarding water management during operations can be found in Section 15.8.

 

17.3Mine Reclamation and Closure

 

17.3.1Reclamation and Closure Plan

 

Mine reclamation and closure considerations are largely driven by State regulations (11 AAC 86.150, 11 AAC 97.100-910, and 18 AAC 70) and statutes (AS 27.19) that specify that a mine must be reclaimed concurrent with mining operations to the greatest extent possible and then closed in a way that leaves the site stable in terms of erosion and avoids degradation of water quality from acid rock drainage or metal leaching on the site. A detailed reclamation plan will be submitted to the State agencies for review and approval in the future, during the formal mine permitting process. For this report a preliminary reclamation and closure plan was developed by SRK. This is considered adequate for this stage of study as closure is delayed by the operations period and numerous studies will be developed during operations that will further inform the final reclamation and closure plan.

  
Arctic ProjectPage 332
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The approval process for the plan varies somewhat depending on the land status for any particular mine. Owing to the fact that the Arctic Project is likely to have facilities on a combination of private (patented mining claims and native land) and State land, it is likely that the reclamation plan will be submitted and approved as part of the plan of operations, which is approved by the ADNR. However, since the reclamation plan must meet regulations of both ADNR and the ADEC, both agencies will review and approve the Reclamation Plan. In addition, private landowners must formally concur with the portion of the reclamation plan for their lands so that it is compatible with their intended post-mining land use.

 

17.3.2Closure Objectives and Closure Criteria

 

The overall closure objective is to establish stable chemical and physical conditions that protect the environment and human health. To the extent practicable, rehabilitation efforts will endeavour to return the site to a condition which generally conforms with the surrounding terrain. The site will be monitored and maintained post-closure in order to demonstrably meet these conditions.

 

The following general closure objectives were considered:

 

Demolish and remove all construction, camp and industrial facilities and reclamation of affected footprints.

 

Achieve long-term slope stability of the pit, WRF, and TMF.

 

Meet water quality criteria for all mine water and seeps prior to discharge to the environment.

 

Prevent intrusion and migration of tailings porewater and water from the pit into the regional groundwater.

 

Prevent and limit to the greatest extent practical, contact of humans and wildlife with the mine waste (waste rock and tailings).

 

Establish adequate vegetation density to ensure erosion protection of the soil slopes.

 

Re-establish vegetation or stabilized surface on areas returned to normal land use.

 

17.3.3Closure Activities

 

Closure activities will be undertaken at the end of mine life to bring the mine facilities in a state consistent with the stated closure objectives and compliant with the regulations for closure and reclamation. Major activities planned for the various mine components and facilities are detailed as follows. The closure plan will be conducted in two phases. Phase One (first 15 years) will include reclamation of the majority of the site and time to allow the majority of the tailings consolidation to occur, while Phase Two (16+ years) will include closure of the TMF and long term maintenance of the site. Both phases will include water treatment as discussed in Section 17.3.4. Figure 17-3 and Figure 17-4 illustrate the closure phases.

  
Arctic ProjectPage 333
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 17-3: Phase One Closure

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 334
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 17-4: Phase Two Closure

 

 

Source: SRK, 2022.

  
Arctic ProjectPage 335
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

17.3.3.1Open Pit Workings

 

The pit wall is expected to be geotechnically stable in the long-term, and therefore no in-pit work is required at closure. The pit perimeter straddles a steep mountainous ridgeline: installation of typical preventative safety measures such as fencing, or warning berms are not practical to install. Clear signage will be installed to warn of existing dangers, such as highwall presence and falling rock in areas which could potentially be accessed by the public.

 

Once operations are completed, the water in the pit will be allowed to rise and the pit will be used as storage for the WTP. Seepage water from consolidation of the tailings, infiltration through the tailings cover, and seepage from the WRF will report to the open pit for seasonal treatment. Sludge generated from water treatment will be filtered through filter bags on a lined portion of the tailings area and filtrate solution will be returned to the pit to be treated through the WTP.

 

The pit lake will not be allowed to overflow, and the elevation will be carefully monitored to provide storage of the freshet volume and probable maximum precipitation event. Further hydrological and geotechnical studies are required to determine the maximum elevation to which water could be stored in the pit to prevent seepage through bedrock and into the environment. A conservative approach assumes that the maximum pit lake elevation will be maintained 40 m below the top of competent bedrock surface. An emergency spillway will be constructed.

 

17.3.3.2Waste Rock Facility and Tailings Management Facility

 

It is anticipated that the WRF will be PAG after closure and into the foreseeable future. The face of the WRF will be regraded at closure for long-term stability at an overall slope of approximately 2.5H:1V. Efforts will be made to create a convex shape on the WRF face, which is the predominant shape of natural slopes in mature landscapes in the area. This shape together with installation of intermittent diversion berms on the face of the WRF slope will reduce rilling and erosion from uncontrolled runoff. The diversion berms on the WRF face will divert water to the perimeter. There, geosynthetic-lined and armoured perimeter channels will be installed at the interface of the existing ground and the WRF. The lined channels will limit infiltration of collected runoff both from the WRF surface and upstream run-on, limiting the volume of seepage reporting to the WRCP which requires treatment. Upon completion of grading, all surface areas of the WRF will be covered with geomembrane overlain by approximately 830 mm of overburden and 170 mm of growth media, for a full cover thickness of approximately one meter. Modelling of the geomembrane cover showed a significant reduction in the amount of water that would need to be treated.

 

In the later years of operation, water maintained in tailings will be kept at a minimum. The eastern half of tailings will be used as a WTP sludge storage area. The eastern side of the tailings dam will drain into the pit which, in turn, will be used to feed the WTP. An engineered drainage layer will be place on the eastern side of tailings so that equipment can be operate on top while consolidation solution can still drain to the pit. Equipment will be used to place pipes and filter bags. Sludge from the WTP will be pumped into the filter bags. Sludge will be retained in the bags and filtrate solution, along with tailings consolidation solution, will return to the pit. As bags fill, they will be taken off-line and allowed to dry. When the eastern half of tailings has been filled with one layer of bags, they will be covered with engineered drainage material and second layer of filter bags will be filled on top and the process will be repeated. As the level of filter bags and drainage material increases, the western side will be covered with geomembrane overlain by 830 mm of overburden and 170 mm of growth media to reduce the volume of water needing to be treated. Tailings consolidation is expected to continue for up to 100+ years but, the majority of the consolidation is expected to occur in the first 15–20 years post closure.

  
Arctic ProjectPage 336
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The western side of tailings will not be needed for sludge storage, so waste rock will be relocated the western half of the tailings surface to provide positive drainage towards the western diversion channel. Upon completion of grading and placement of waste rock, the western half of the TMF will be covered with 830 mm of overburden and 170 mm of growth media, for a full cover thickness of approximately one meter.

 

An engineered spillway will be installed between the east side of the TMF and the pit at the completion of mining. The spillway is designed to safely convey the probable maximum flood event from the TMF to the pit, both during Phase One and Phase Two closure.

 

Material for covering the WRF and TMF will be relocated from the overburden and topsoil stockpiles. Once all material has been relocated, the footprints will be reclaimed, and the Process Pond will be reclaimed and revegetated.

 

All disturbed areas will stabilized and seeded with native species of grasses and shrubs to re-establish vegetation. A revegetation and cover study must be conducted to verify plant survival at the elevations proposed of the waste rock dump and reclaimed tailings facility. Efforts to work with the Alaska Plants Material Center should be taken to maximize the potential for sustainable regrowth. The elevation, climate and latitude will likely limit the early growth success and trials should be conducted throughout the LOM to determine the management practices for revegetation and stabilization at this site. Although, revegetation is the preferred method of stabilization for many projects, other methods of stabilization could be implemented such as a non-reactive, durable rock cover.

 

17.3.3.3Buildings and Equipment

 

The WTP and a modified power generation plant will be left in place, together with all appurtenant facilities and utilities. All other steel frame buildings including the mill, the truck shop, and the conveyors will be demolished selectively by removing the roof and siding and then dismantling the steel frames and trusses. Resulting debris will be disposed of in an approved landfill that will be located on the WRF. Concrete walls, pillars, and beams will be demolished to the ground and concrete foundations will be covered in place. Controlled blasting may be used to help with the demolition. All sumps and cavities will be backfilled to ground level. The rock fill pads underlying all buildings and equipment will be re-graded to prevent permanent ponding.

 

Non-hazardous and hazardous waste will be segregated. Hazardous waste will be placed in suitable containers and hauled to a licensed disposal facility, while non-hazardous waste will be placed in the landfill.

 

Any unwanted mobile or stationary equipment will be stripped of electronics and batteries, drained of all fluids (fuels, lubricants, coolants), decontaminated by power washing, and placed in the landfill for final disposal.

 

17.3.3.4Mine Infrastructure

 

Mine support infrastructure will consist of internal access roads, haul roads, and rock fill pads underlying the site buildings and facilities.

 

All bridges and culverts associated with the haul roads and internal access roads will be removed and natural drainage will be restored. Swales will be created where needed, to allow continued use of the roads into post-closure water treatment, monitoring, and maintenance. Roads that are not needed in post-closure will be ripped and re-vegetated.

 

The surface of the rockfill pads underlying some of the buildings and facilities on site will be re-graded and/or crowned as necessary to prevent ponding of water. The pads will be scarified and re-vegetated. Additional overburden up to 300 mm may be applied, as needed, to promote revegetation.

  
Arctic ProjectPage 337
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The site access road will be maintained as long as water treatment is occurring on site.

 

17.3.3.5Landfill

 

An unlined non-hazardous landfill will be located in the WRF. Demolition waste and other non-hazardous waste will be placed in the landfill and consolidated to minimize the occupied volume. The waste will then be covered with at least 1 m of waste rock. The final surface will then be graded to prevent permanent ponding and will be covered similarly to the rest of the WRF cover.

 

17.3.3.6Water Management System

 

The water management system consisting of the pit lake, Process Pond, diversion channels, and various pipelines will be largely decommissioned. The Process Pond will be breached, regraded and re-vegetated. New diversion channels along the perimeter of the WRF will be created to manage surface runoff on and around the TMF and the WRF, as well as intake and discharge pipelines between the pit and the WRCP. Runoff from the WRF cover is expected to meet water quality standards and will be discharged to the environment. Seepage from the WRF will report to the WRCP and be pumped to the pit for treatment. As the pit fills naturally, water levels will be managed by treating and discharging treated water for the long-term.

 

The WRCP will collect seepage from the WRF in perpetuity. The expected seepage volume reporting to the WRCP in closure is approximately 800 m³ per day. All contact water will be sent to the pit for storage prior to treatment. Water treatment is expected to occur year-round, beginning in May of the first year of closure.

 

17.3.4Closure Water Treatment

 

When the TMF is closed at the end of the Operations phase, a biological/chemical/physical plant will be added to treat the RO reject. This phased approach provides multiple benefits, including allowing time to gain insight on the site’s true wastewater flow and quality so that the RO reject treatment design can be improved upon. This treatment train will include:

 

Gypsum clarifier: Reduces sulphate concentration in the reject treatment stream train to the gypsum saturation limit by adding lime stored in silos. The system will also remove cationic metals such as cadmium and zinc.

 

Anaerobic biological treatment: Biochemically reduces nitrate to nitrogen gas and selenate and selenite to elemental selenium (a solid). Selenium and metal solids removed in the sludge are settled out and removed by the biological ballasted clarifier.

 

Aerobic biological treatment: Polishes residual organics added in the upstream anaerobic biological treatment. Solids are separated via a membrane filter with iron coprecipitation for polishing selenium.

 

During the Closure phase, the WTP will either be run year-round or for partial year based on water storage requirements. During the Operations phase, mill water demands will affect site water flows such that the WTP can be shut down and the discharge eliminated during roughly half of the year (winter).

 

During Operations, sludge from the WTP will be disposed of at the TMF. During Closure, sludge from the WTP will be disposed in filter bags on a lined area which will decant solution back to the pit.

  
Arctic ProjectPage 338
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

17.3.5Post-Closure

 

Continued presence at site will be required in the post-closure period for as long as water treatment is necessary. During the post-Closure phase, the WTP will either be run year-round or for part of the year based on water storage requirements. If operated for part of the year, during the winter months, the RO portion of the plant would be shut down and the bacteria in the biologic portion of the plant will be maintained with the feed of a concentrated brine solution from the RO plant. This will eliminate the need to bring large quantities of reagents to site during winter, eliminate winter operational issues, and reduce the cost of winter road maintenance. Generators and mobile equipment will also be required for the WTP operations as well as sampling and monitoring activities.

 

In the short-term (up to 10 years following closure) monitoring to confirm that the closure objectives are met will be based on the following requirements:

 

The site should be visually inspected by a qualified Professional Engineer annually for three consecutive years and less frequently thereafter for up to 10 years to ensure that erosion-prone areas have stabilized.

 

The cover systems over the WRF and the TMF should be regularly inspected by a qualified inspector to ensure the physical integrity of the cover is maintained. Inspection intervals should be by-annually for the first 10 years after construction.

 

The site should be inspected by a vegetation specialist to confirm suitability of the revegetation efforts. Inspections should be completed at the following intervals, unless otherwise recommended by the vegetation expert: Year 1, Year 3, Year 7 and Year 10 post-closure.

 

The WRCP and TMF dams will need a Periodic Safety Inspection by a qualified engineer every three years per ADSP (2017) for perpetuity.

 

In the long-term, continuous water quality monitoring will be implemented at sampling frequencies prescribed by future discharge permits.

 

Maintenance will be performed on areas that monitoring identifies as needing repairs. Water treatment in perpetuity will likely require a well-defined set of discharge quality criteria to be determined at the later stages of permitting and design

 

17.3.6Closure Cost Estimate

 

17.3.6.1General

 

The estimated closure costs are determined from unit rates based on projects located in Alaska. The indirect costs were included as percentages of the estimated direct costs. Indirect percentages are based on reclamation and closure guidelines for Alaska.

 

Long-term water treatment and maintenance of certain water management facilities were calculated separately, and an NPV value is provided for the first 100 years of closure, at a discount rate of 4.3%. The discount rate is the mutually agreed upon rate developed by the State of Alaska to be used for all financial assurance closure costs.

 

A summary of Trilogy’s estimated closure and reclamation costs, for all items except water treatment, are provided in Table 17-1. Closure costs for the water treatment are captured separately in Section 17.3.6.2.

  
Arctic ProjectPage 339
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 17-1: Summary of Closure and Reclamation Costs

 

Cost Items  Subtotals Closure Costs ($M) 
DIRECT CLOSURE COSTS     
Waste Rock Facility  $69.9 
Yards and Laydown Areas  $0.2 
Buildings and Equipment  $4.0 
TMF Spillway (Phase 1)  $4.9 
Surface Water Management (Phase 1)  $7.7 
Ponds and Stockpiles  $0.2 
Roads and Diversion Channel Regrade  $0.2 
Hazardous Waste and Solid Waste Disposal  $0.7 
Camp and Turn-around Costs  $2.2 
Subtotal Direct Closure Cost  $90.1 
INDIRECT CLOSURE COSTS     
Contingency (25%)  $22.5 
Engineering Redesign (3%)  $2.7 
Contract Administration (7%)  $6.3 
Performance Bond (3%)  $2.7 
Liability Insurance (0.5%)  $0.5 
Subtotal Indirect Closure Cost  $34.6 
Total Closure Cost  $124.7 
POST-CLOSURE COSTS (100 years)     
Water Quality Sampling  $8.3 
Annual Reporting  $2.7 
Post-Closure Monitoring and Inspections  $10.9 
Vegetation and Cover Maintenance  $5.7 
Camp and Road Maint.  $21.0 
Mobile Equipment and Operating  $13.9 
TMF Reclamation & Diversions (Phase 2)  $48.8 
Sludge Repository Construction  $5.5 
Sludge Management Crew and Camp Support  $4.6 
Sludge Filtration  $10.0 
Subtotal Post-Closure Costs (undiscounted)  $131.4 
Post-Closure Costs NPV (4.3% Discount)  $46.1 
Discounted General Closure Cost  $170.8 

  
Arctic ProjectPage 340
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

17.3.6.2Closure Water Treatment Costs

 

Annual undiscounted costs associated with long-term operations of the WTP are estimated to be $11.7 million in Phase 1 closure (15-years post-closure) and $10.8 million in Phase 2 closure (85 years thereafter), amounting to $1,095 million over the 100-year closure period. These costs equate to $258 million when discounted at 4.3% p.a. to the first year of post-production.

 

17.3.7Reclamation and Closure Financial Assurance

 

In the absence of activities on Federal Land in the mine area and excluding the access road to the district from the Dalton Highway, there would not be any financial assurance requirements from the Federal government for the mine.

 

There are three State of Alaska agencies that require financial assurance in conjunction with approval and issuance of large mine permits.

 

The ADNR, under authority of Alaska Statute 27.19, requires a reclamation plan be submitted prior to mine development and requires financial assurance, typically prior to construction, to assure reclamation of the site. The ADNR Dam Safety Unit also requires a financial assurance sufficient to cover the cost of decommissioning dams or the cost for long term maintenance and monitoring of dams that will remain in-place. The ADEC requires financial assurance both during and after operations, and to cover short and long-term water treatment, if necessary, as well as reclamation costs, monitoring, and maintenance needs. The State requires that the financial assurance amount also include the property holding costs for a one-year period.

 

The final financial assurance amount will be calculated through the process of reviewing and approving the Arctic Project reclamation plan during the formal permitting process. In general, the approach is to combine the reclamation costs, post-closure monitoring costs and the long-term annual water treatment costs into a financial amount that includes deriving the NPV of the long-term costs and combining that with the reclamation cost. The costs assume that a third-party contractor will perform and manage the Arctic Project. The estimate required for bonding is likely to be similar to the estimate provided above. Until actual Owner operating costs are known, the internal closure liability cannot readily be reduced.

 

Ambler Metals may satisfy the State financial assurance requirement by providing any of the following: (1) a surety bond, (2) a letter of credit, (3) a certificate of deposit, (4) a corporate guarantee that meets the financial tests set in regulation by the ADNR commissioner, (5) payments and deposits into the trust fund established in AS 37.14.800, or (6) for the dam-or ADEC-related obligation - any other form of financial assurance that meets the financial test or other conditions set in regulation by the ADNR or ADEC commissioners.

 

The adequacy of the reclamation plan, and the amount of the financial assurance, are reviewed by the State agencies at a minimum of every five years and must be updated whenever there is a significant change to the mine plan of operations, or other costs that could affect the reclamation plan costs.

  
Arctic ProjectPage 341
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

17.4 Permitting Considerations

 

17.4.1Exploration Permits

 

Current mineral exploration activities are conducted at the Arctic deposit under State of Alaska and Northwest Arctic Borough (NWAB) permits. The State of Alaska Miscellaneous Land Use Permit (MLUP) and the NWAB Permit both expires at the end of 2022 and will be renewed.

 

Cumulative surface disturbance for exploration activities on the Arctic Project remains less than 5 acres (excluding historic disturbance that includes roads and camp disturbances) and therefore there are currently no State requirements for reclamation bonding for the Arctic Project.

 

Ambler Metals also has NWAB Title 9 Conditional Use Permits authorizing exploration and bulk fuel storage, use of airstrips, operation of a landfill and gravel extraction expires on December 31, 2022. No bonding is required for the borough permits.

 

Ambler Metals obtained several other permits for camp-support operations. These permits include a drinking water permit, a domestic wastewater discharge permit, camp establishment permits, and construction and operation of a Class III Camp Municipal Landfill, all of which are issued by the Alaska Department of Environmental Conservation (ADEC). Temporary water-use authorizations were issued by the ADNR, a Title 16 Fish Habitat permit, and a wildlife hazing permit were issued by the ADF&G.

 

17.4.2Major Mine Permits

 

The following discussion identifies the major permits and approvals that will likely be required for development of the Arctic deposit.

 

Permits would be required from Federal, State, and Regional agencies, including: the US Army Corps of Engineers (USACE), ADEC, ADF&G, ADNR, and the NWAB. The State of Alaska permit for exploration on the Arctic Project, the Annual Hardrock Exploration Activity (AHEA) Permit, is obtained and renewed every five years through the ADNR – Division of Mining, Land and Water.

 

The types of major mine permits required by the Arctic Project are largely driven by the underlying land ownership; regulatory authorities vary depending on land ownership. The Arctic Project area includes patented mining claims (private land under separate ownership by Ambler Metals and NANA), State of Alaska land, and NANA land (private land). The mine pit would situated mostly on patented land while the mill, TMF and WRF would be largely on State land. Other facilities, such as the camp, would be on NANA land. Federal land would likely underlie portions of an access road between the Dalton Highway and the project area. However, permits associated with such an access road are being investigated in a separate action by the State of Alaska and are not addressed in this report. A list of likely major mine permits is included in Table 17-2.

 

Because the infrastructure for the Arctic Project is situated to a large extent on State land, it will likely be necessary to obtain a Plan of Operation Approval (which includes the Reclamation Plan) from the ADNR. The Arctic Project will also require certificates to construct and then operate a dam(s) (tailings and water storage) from the ADNR (Dam Safety Unit) as well as water use authorizations, an upland mining lease and a mill site lease, as well as several minor permits including those that authorize access to construction material sites from ADNR.

  
Arctic ProjectPage 342
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

The ADEC would authorize waste management under an integrated waste management permit, air emissions during construction and then operations under an air permit, and require an Alaska Pollution Discharge Elimination System (APDES) permit for any wastewater discharges to surface waters, and a Multi-Sector General Permit for stormwater discharges. The ADEC would also be required to review the USACE Section 404 permit to certify that it complies with Section 401 of the Clean Water Act (CWA).

 

The ADF&G would have to authorize any culverts or bridges that are required to cross fish-bearing streams or other impacts to fish-bearing streams that result in the loss of fish habitat.

 

The USACE would require a CWA Section 404 permit for dredging and filling activities in Waters of the United States, including jurisdictional wetlands. The USACE Section 404 permitting action would require the USACE to comply with National Environmental Policy Act (NEPA ) and, for a project of this magnitude, the development of an Environmental Impact Statement (EIS) is anticipated. The USACE would likely be the lead federal agency for the NEPA process. The NEPA process will require an assessment of direct, indirect and cumulative impacts of the Arctic Project and the identification of project alternatives, and include consultation and coordination with additional federal agencies, such as the US Fish and Wildlife Service (if endangered or threatened species are present) and National Marine Fisheries Service (if essential fish habitat is present), and with the State Historic Preservation Office and Tribal Governments under Section 106 of the Historical and Cultural Resources Protection Act.

 

As part of the Section 404 permitting process, the Arctic Project will have to meet USACE wetlands guidelines to avoid, minimize and mitigate impacts to wetlands. The USACE may require Ambler Metals to develop a compensatory wetlands mitigation plan for mitigating unavoidable wetlands impacts.

 

The Arctic Project will also have to obtain approval for a Master Plan from the NWAB. In addition, actions will have to be taken to change the borough zoning for the Arctic Project area from Subsistence Conservation and General Conservation to Resource Development.

 

The overall timeline required for permitting would be largely driven by the time required for the NEPA process, which is triggered by the submission of the Sec. 404 permit application to the USACE. The timeline includes the development and publication of a draft and final EIS and ends with a Record of Decision (ROD), and 404-permit issuance. In Alaska, the EIS and other State and Federal permitting processes are generally coordinated so that permitting and environmental review occurs in parallel. The NEPA process could require between two to three years to complete and could potentially take longer.

 

Table 17-2: Major Mine Permits Required for the Arctic Project

 

Agency Authorization
State of Alaska
ADNR Plan of Operations Approval (including Reclamation Plan)
Upland Mining Lease
Mill Site Lease
Reclamation Bond
Certificate of Approval to Construct a Dam
Certificate of Approval to Operate a Dam
Water Rights Permit to Appropriate Water

  
Arctic ProjectPage 343
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Agency Authorization
ADF&G Title 16 Permits for Fish Passage (authorize stream crossings)
ADEC APDES Water Discharge Permit
Alaska Multi-Sector General Permit (MSGP) for Stormwater
Stormwater Discharge Pollution Prevention Plan (part of MSGP)
Section 401 Water Quality Certification of the CWA Section 404 Permit
Integrated Waste Management Permit
Air Quality Control – Construction Permit
Air Quality Control – Title V Operating Permit
Reclamation Bond
Federal Government
EPA Spill Prevention, Control, and Countermeasure (SPCC) Plan (fuel transport and storage)
USACE CWA Section 404 Dredge and Fill Permit
NWAB
NWAB Master Plan Approval and rezoning lands from Subsistence Conservation to Resource Extraction

 

Note: “Major” permits generally define critical permitting path. Additional “minor” permits are also required.

 

17.5                Social or Community Considerations

 

The Arctic Project is located approximately 40 km northeast of the villages of Shungnak and Kobuk, and 65 km east-northeast of the community of Ambler. The population in these villages are 151 in Kobuk (2020 Census), 210 in Shungnak (2020 Census), and 275 in Ambler (2020 Census). Residents largely live a subsistence lifestyle with incomes supplemented by guiding, local development projects, employment through tribal and city councils, government aid, and employment both in and outside of their home villages.

 

The Arctic Project has the potential to significantly improve work opportunities for residents during the exploration phase, construction, and during full operation. Trilogy’s joint venture, Ambler Metals works directly with the Upper Kobuk villages and communities throughout the region to employ residents as mechanics, geotechnicians, core cutters, administrative staff, camp services, heavy equipment operators, drill helpers, and environmental technicians.

 

Stakeholder outreach and community meetings in the region by the Arctic Project’s owners over many years have provided the opportunity to engage with residents, provide updated information on the Arctic Project and future plans for the UKMP, hear concerns, answer questions, and build relationships.

 

This engagement has also identified various hurdles residents have faced when applying for employment. Opportunities have been created for NANA shareholders to apply and receive educational scholarships, participate in job shadowing at Bornite, driver’s license courses, and heavy equipment operator training sponsored by the Arctic Project’s owners.

 

It is the company’s goal to continue and grow these efforts throughout the permitting process and the life of the Arctic Project – encouraging and supporting education, job training, employment, and economic growth.

  
Arctic ProjectPage 344
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

17.6                Comment on Environmental Studies, Permitting, and Plans, Negotiations, or Agreements with Local Individuals or Groups

 

In the QP’s opinion, the current plans are adequate to address any issues related to environmental compliance, permitting, and local individuals or groups.

  
Arctic ProjectPage 345
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

18CAPITAL AND OPERATING COSTS

 

18.1Capital Costs

 

18.1.1Introduction

 

The capital cost estimate for the Artic Project was developed at PFS-level study under S-K 1300 standards with an accuracy of +/-15% using the Association for the Advancement of Cost Engineering (AACE) Class 3 estimate standards with a contingency ≤15%. The estimate included the cost to complete the design, procurement, construction, and commissioning, of all the identified facilities.

 

The breakdown of the responsibilities for the capex by facility is as follows:

 

Ausenco

 

Process Plant

 

Onsite Infrastructure

 

Wood

 

Mining Fleet

 

Mine Development

 

Haul Roads

 

Brown & Caldwell

 

Reverse Osmosis Water Treatment Plant

 

Trilogy

 

Main Access Roads

 

Tailings Storage Facilities

 

WRF

 

Water Management

 

Reclamation & Closure

 

Owners Costs

 

This estimate collectively presents the entire costs for the Arctic Project.

 

18.1.2Arctic Project Execution

 

The estimate was based on the traditional engineering, procurement, and construction management (EPCM) approach where the EPCM contractor will oversee the delivery of the completed project from detailed engineering and procurement to handover of working facility. The EPCM contractor would engage and coordinate several subcontractors to complete all work within the given scopes. Typical vertical and/or horizontal contract packages were identified and aligned with different pricing models such as, but not limited to:

  
Arctic ProjectPage 346
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Schedule of rates (unit price)

 

This contract pricing model is based on estimated quantities of items included in the scope and their unit prices. The final contract price is dependent on the quantities needed to complete the work under the contract.

 

Time and materials

 

Time and materials (T&M) fixes rates for labour and material expenditures, with the contractor paid on the basis of actual labour hours (time), usually at specified hourly rates, actual cost of materials and equipment usage, and an agreed upon fixed add-on to cover the contractor’s overheads and profit.

 

Design and construct

 

With this option one entity will provide design and construction services for an awarded scope of work. A higher degree of price certainty can be achieved when a lump sum arrangement is used; this method also provides a single point of accountability and an improved integration of the design with construction.

 

18.1.3Work Breakdown Structure

 

The estimate was arranged by major area, area, major facility, and facility. Each sub-area was further broken down into disciplines such as earthworks, concrete etc. Each discipline line item was defined into resources such as labour, materials, equipment, etc., so that each line comprises all the elements required to complete each task.

 

The work breakdown structure (WBS) was developed in sufficient detail to provide the required level of confidence and accuracy and also to provide the basis for further development as the Arctic Project moves into execution phase.

 

18.1.4Estimate Summary

 

The estimate is derived from a number of fundamental assumptions as shown on the PFDs, 3D model, mechanical equipment list, electrical equipment list, material take offs, scope definition and WBS, it includes all associated infrastructure as defined within the scope of works.

 

The Capital Cost Estimate has been summarized at the levels indicated with a base date of Q3/Q4-2022 with no provision for forward escalation. A summary of the capital costs estimate by Major Facilities and Major Disciplines are defined in Table 18-1 and Table 18-2 respectively.

 

Table 18-1: Estimate Summary Level 1 Major Facility

 

WBS
Level 1
   WBS Level 1 Description    Initial
Capex
($ M)
   Sustaining
Capex
($ M)
   Total
Capex
($ M)
 
1000   Mining    296.7   17.5   314.2 
2000   Crushing    42.5   0   42.5 
3000   Process Plant    158.0   1.3   159.3 
4000   Tailings    88.3   32.4   120.7 
5000   On-site Infrastructure    172.8   35.1   207.9 
6000   Off-site Infrastructure    75.8   0   75.8 
Sub-total Direct Costs    834.1   86.3   920.4 
7000   Indirects    177.4   15.1   192.5 
8000   Contingency (~12% of total project cost)    138.5   13.0   151.5 
9000   Owner Costs    26.8   0   26.8 
Sub-total Indirect Costs      342.7   28.1   370.8 
Arctic Project Total     1,176.8   114.4   1,291.2 

  
Arctic ProjectPage 347
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 18-2: Initial Estimate by Major Discipline

 

Discipline
Code
    Discipline Description    Initial
Capex
($ M)
   Sustaining
Capex
($ M)
   Total
Capex
($ M)
 
A    Architectural - Buildings   61.4   9.8   71.2 
A    Architectural – Permanent Camp Facility   45.4   0   45.4 
B    Earthworks   28.6   0.9   29.5 
C    Concrete   42.1   4.6   46.7 
S    Structural Steel   20.1   0   20.1 
F    Platework   6.6   0   6.6 
M    Mechanical Equipment   102.2   1.8   104.0 
P    Piping & Fittings   51.3   0   51.3 
L    Electrical Bulks   16.8   0   16.8 
E    Electrical Equipment   42.6   0   42.6 
I    Instrumentation   4.8   0   4.8 
N    Mobile Equipment   7.6   0   7.6 
R    Third Party   404.6   69.2   473.8 
Sub-total Direct Costs   834.1   86.3   920.4 
O    Owners Costs   26.8   0   26.8 
T    Project Delivery   90.0   14.3   104.3 

  
Arctic ProjectPage 348
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Discipline
Code
    Discipline Description    Initial
Capex
($ M)
   Sustaining
Capex
($ M)
   Total
Capex
($ M)
 
U    Filed Indirects   76.9   0.9   77.8 
V    Spares/ First Fills / Vendor Reps   10.4   0   10.4 
Y    Contingency (~12% of total project cost)   138.5   13.0   151.5 
Sub-total Indirect Costs   342.7   28.1   370.8 
Arctic Project Total        1,176.8   114.4   1,291.2 

 

18.1.5Definition

 

18.1.5.1Definition of Costs

 

The estimate is broken out into direct and indirect capital costs.

 

Initial capital is the capital expenditure required to start up a business to a standard where it is ready for initial production.

 

Sustaining capital is the capital cost associated with the periodic addition of new plant, equipment or services that are required to maintain production and operations at their existing levels.

 

Direct costs are those costs that pertain to the permanent equipment, materials and labour associated with the physical construction of the process facility, infrastructure, utilities, buildings, etc. Contractor’s indirect costs are contained within each discipline’s all-in rates.

 

Indirect costs include all costs associated with implementation of the plant and incurred by the owner, engineer or consultants in the design, procurement, construction, and commissioning of the Arctic Project.

 

18.1.5.2General Methodology

 

The estimate is developed based on a mix of detailed material take-offs and factored quantities and costs, detailed unit costs supported by contractor bids and budgetary quotations for major equipment supply as outlined in Ausenco’s requirements.

 

The structure of the estimate is a build-up of the direct & indirect cost of the current quantities; this includes the installation/construction hours, unit labour rates and contractor distributable costs, bulk and miscellaneous material and equipment costs, any subcontractor costs, freight and growth.

 

The methodology applied and source data used to develop the estimate included:

 

Define the scope of work.

 

Quantify the work in accordance with standard commodities.

 

Organize the estimate structure in accordance with an agreed WBS.

  
Arctic ProjectPage 349
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Calculate “all in” labour rates for construction work.

 

Determine the purchase cost of equipment and bulk materials.

 

Determine the installation cost for equipment and bulks.

 

Establish requirements for freight.

 

Determine the costs to carry out detailed engineering design and project management.

 

Determine foreign exchange content and exchange rates.

 

Determine growth allowances for each estimate line item.

 

Determine the estimate contingency value by probabilistic method (if required).

 

Undertake internal peer review, finalize the estimate, estimate basis and obtain sign off by the Project Manager and Qualified Professional.

 

18.1.5.3Basic Information

 

The following basic information pertains to the estimate:

 

The estimate base date is Q3/Q4-2022.

 

The estimate is expressed in United States Dollars ($).

 

18.1.5.4Exchange Rates

 

The exchange rates in Table 18-3 were obtained from the XE.com website as of November 8, 2022 and confirmed for use the capital cost estimate by Trilogy.

 

Table 18-3: Estimate Exchange Rates

 

Exchange Rate    $ 
AUD 1.430   1.000 
EUR 0.940   1.000 
CAD 1.300   1.000 

 

Notes: AUD = Australian Dollar, EUR = Euro, CAD = Canadian Dollar

 

18.1.5.5Market Availability

 

The pricing and delivery information for quoted equipment, material and services was provided by suppliers based on the market conditions and expectations applicable at the time of developing the estimate.

 

The market conditions are susceptible to the impact of demand and availability at the time of purchase and could result in variations in the supply conditions. The estimate in this Report was based on information provided by suppliers and assumes there are no problems associated with the supply and availability of equipment and services during the execution phase.

  
Arctic ProjectPage 350
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

18.1.6Mining (WBS 1000)

 

The total mine capital cost estimated to develop the Arctic Project is $294.9 M (Table 18-4). The initial capital costs add a total of $277 M, including $150 M in capitalized preproduction mining operating costs for a two-year preproduction period, $90 M in initial capital expenditures for mobile equipment, $7 M in initial equipment spares, $1 M for the explosive storage and transfer site, and $29 M for haul roads construction. Following preproduction, a sustaining capital cost of $18 M is required primarily for additions to truck mining fleet, and to replace equipment beyond its manufacturer’s recommended service life. An additional $40 M are estimated as a contingency for the initial capital cost. Equipment purchase payment has been estimated to be done in the period before it is required to account for the following payment schedule: 10% at order placement, 70% at shipping from ex-work, and 20% at site arrival.

 

Table 18-4: Mining Initial and Sustaining Capital Cost

 

Cost Area    Initial
Capex
($ M)
  Sustaining
Capex
($ M)
  Total Capex
($ M)
Pre-Production Mining   149.9  0.0   149.9
Engineering and Management   4.0  1.1   5.1
Drilling   7.6  0.0   7.6
Blasting   2.0  0.0   2.0
Loading   16.3  0.6   16.9
Hauling   43.8  1.8   45.6
Support   18.9  9.3   28.2
Maintenance   6.0  4.7   10.7
Road Construction   28.8  0.0   28.8
Sub-total Mining Cost   277.4  17.5   294.9

 

Table 18-5 provides an overview of the annual sustaining capital expenditures. Approximately $0.05/t mined is spent as sustaining capital. Capital expenditures are restricted during the last two years of mining.

  
Arctic ProjectPage 351
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 18-5: Sustaining Capital Cost Distribution

 

Period    $ M 
Year 1   0.05 
Year 2   - 
Year 3   - 
Year 4   1.46 
Year 5   - 
Year 6   0.75 
Year 7   0.85 
Year 8   0.20 
Year 9   8.91 
Year 10   1.93 
Year 11   0.32 
Year 12   3.05 
Year 13   - 
Total Sustaining Capital   17.5 

 

Figure 18-1 provides a distribution of initial mining capital expenditures by cost area.

  
Arctic ProjectPage 352
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 18-1: Initial Mining Capital Cost Distribution by Cost Centre

 

 

Source: Wood, 2022.

 

18.1.6.1Mining Capital Cost Basis of Estimate

 

The basis of estimate for the mining equipment, ancillary equipment, capital spares, and other capital costs are provided in the following sub-sections.

 

18.1.6.2Mining Equipment

 

The equipment capital costs were provided by multiple suppliers as part of a budgetary request for quotation process. The capital costs are inclusive of transport to Fairbanks, Alaska, assembly, training, tires, and options for cold weather operations. For example, Table 18-6 provides a capital cost buildup for the 141 t trucks.

  
Arctic ProjectPage 353
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Table 18-6: 141t Truck Capital Pricing

 

Capital Pricing 141t Truck    $ M 
Base Price   2.1 
Tires   0.1 
Freight and Duty to Fairbanks, AK   0.1 
Assembly   0.2 
Total Purchase Price   2.5 

 

In addition to capital pricing, equipment suppliers provided machine operational lives and mechanical availability, which were adjusted by Wood based on experience with similar type of equipment at other operating mines. Table 18-7 provides the basic inputs used to estimate mine equipment capital cost.

 

Table 18-7: Mine Equipment Capital Cost Inputs

 

Equipment  Capital Cost
($ M)
   Machine Life
(GOH)
   Mechanical Availability (%) 
171 mm Production Drill  2.36   100,000   83%
265 t/15 m3 Hydraulic Face Shovel  4.40   100,000   85%
124 t/12 m3 Front End Loader  2.08   80,000   85%
144 t Haul Truck  2.52   100,000   85%
41t Articulated Truck  0.88   42,000   86%
26 t/5 m3 Front End Loader  0.55   60,000   86%
68 t/4 m3 Hydraulic Excavator  1.08   60,000   86%
35 t/1.4 m3 Hydraulic Excavator  0.59   48,000   85%
74 t/455 kW Track Dozer  1.38   60,000   85%
50 t/419 kW Rubber Tired Dozer  1.46   60,000   85%
40 t Articulated Sand Truck  0.88   42,000   85%
33 t/217 kW Motor Grader  1.39   60,000   85%
35,000-litre water truck  1.34   42,000   85%
41t Articulated Fuel/Lube Truck  1.05   42,000   85%

 

  
Arctic ProjectPage 354
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

18.1.6.3Ancillary Equipment

 

Ancillary equipment capital costs are estimated from a variety of sources including equipment supplier budgetary quotes, Wood’s data base, and CostMine® costing service. Table 18-8 shows the ancillary equipment pricing and sourcing.

 

Table 18-8: Ancillary Equipment Capital Cost Inputs

 

Equipment    Source   Cost Each ($ M) 
Truck Mounted 40 t Crane   Vendor   0.5 
100t Rough Terrain   CostMine   1.4 
5t Forklift   Vendor   0.1 
10t Forklift   Vendor   0.4 
Mechanic Service Truck   CostMine   0.2 
Small Fuel/Lube truck   CostMine   0.2 
55kW Skid Steer   Vendor   0.1 
Flatbed Truck   CostMine   0.1 
45t Telehandler   Vendor   0.8 
Small backhoe/loader   Vendor   0.2 
Hydraulic Hammer   Vendor   0.2 
90t Lowboy   CostMine   0.3 
Compactor   CostMine   0.2 
Light Plant   Vendor   0.3 
Transport Tractor   Wood   0.2 
Tire Handler Truck   Vendor   0.4 
3/4-ton Pickup   CostMine   0.5 
1 ton Pickup   CostMine   0.6 
Crew Bus   CostMine   0.6 
Fleet Management System   Vendor   0.7 
Mine & Geology Software   Vendor   0.5 
MMU - Heavy ANFO (blend) truck   CostMine   0.3 
Stemming Truck   CostMine   0.1 
Laser Scan   Wood   0.02 
Survey Drones   Wood   0.01 
Total Station   Wood   0.03 

  
Arctic ProjectPage 355
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

18.1.6.4 Capital Spares

 

Capital spares are listed in Table 18-9. The capital spares are purchased during pre-production to minimize down time due to waiting for long lead time repair parts and wear items. Included in the capital spares are buckets, tires, and major and minor components. The capital spare costs for buckets and tires are supplier-provided. For minor and major components, an allowance of 5% of the initial purchase price was applied for each equipment fleet.

 

Table 18-9: Capital Spares

 

Description    $ M 
Spare Bed - 144 t Haul Truck   0.2 
Start Up Spares - 144 t Haul Truck   0.1 
Spare Tires (2) - 144 t Haul Truck   0.04 
FMS - 144 t Haul Truck   0.2 
Spare Tires (2) - 41t Articulated Truck   0.01 
Start Up Spares - 41t Articulated Truck   0.04 
Spare Bucket- 265 t/15 m3 Hydraulic Face Shovel   0.3 
Startup Spares- 265 t/15 m3 Hydraulic Face Shovel   0.2 
FMS - Komatsu 265 t/15 m3 Hydraulic Face Shovel   0.04 
Spare Bucket- 68 t/4 m3 Hydraulic Excavator   0.1 
Startup Spares- 68 t/4 m3 Hydraulic Excavator   0.05 
FMS - 68 t/4 m3 Hydraulic Excavator   0.01 
Spare Bucket- 124 t/12 m3 Front End Loader   0.1 
Startup Spares- 124 t/12 m3 Front End Loader   0.1 
FMS - 124 t/12 m3 Front End Loader   0.04 
Spare Bucket- 26 t/5 m3 Front End Loader   0.2 
Startup Spares- 26 t/5 m3 Front End Loader   0.03 
FMS - 26 t/5 m3 Front End Loader   0.01 
Startup Spares- 171 mm Production Drill   0.1 
FMS - 171 mm Production Drill   0.07 
Startup Spares- 35 t/1.4 m3 Hydraulic Excavator   0.03 
Startup Spares- 74 t/455 kW Track Dozer   0.07 
Startup Spares- 50 t/419 kW Rubber Tired Dozer   0.07 
Startup Spares- 41 t Articulated Sand Truck   0.04 
Startup Spares- 33 t/217 kW Motor Grader   0.07 
Startup Spares- 35,000-litre water truck   0.07 
Startup Spares- 41t Articulated Fuel/Lube Truck   0.05 
FMS - Service Equipment   0.03 

  
Arctic ProjectPage 356
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

18.1.6.5Other Capital Costs

 

Other capital cost includes haul roads construction, equipment shipment from Fairbanks to site, and explosive storage facilities and transfer site.

 

Haul roads were estimated by Wood. The additional freight cost from Fairbanks, Alaska to site was estimated at $9,395/load during the preproduction period, $8,541/load during the production period, for loads less than 10’6” wide and 60,000 lbs. Heavier and wider loads, like trucks and shovels, were quoted separately. All freight costs were based on an in-state logistics quote. Explosive silos and transfer site cost was provided by the explosive supplier and an additional covered area of 10mx10m for blasting storage was estimated and costed using a unit rate of 3,500 $/m2 provided by Ausenco.

 

Table 18-10 shows the summary of the capital cost mentioned above.

 

Table 18-10: Other Capital Costs

 

Description    $ M 
Haul Roads Construction   28.8 
Equipment Freight Fairbanks to Site   3.23 
Explosive Silos and Transfer Site*   1.03 
Blasting Explosive Storage Building   0.35 
Equipment Rental for Assembly   0.44 

 

*Note: Does not include earthworks, only infrastructure.

 

18.1.7Crushing and Process Plant (WBS 2000 & 3000)

 

A summary of the crushing and process plant (WBS 2000 & 3000) capital cost estimate is presented in Table 18-11.

 

Table 18-11:Crushing and Process Plant Capital Costs

 

WBS
Level 1
   WBS Level 1 Description    Initial
Capex
($ M)
   Sustaining
Capex
($ M)
   Total
Capex
($ M)
 
2100   Primary Crushing   13.3   0.0   13.3 
2200   Ore Stockpile and Reclaim   24.6   0.0   24.6 
2900   Crushing General   4.6   0.0   4.6 
3100   Process Plant Building   31.2   0.0   31.2 
3200   Grinding and Screening   29.0   0.0   29.0 

  
Arctic ProjectPage 357
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

WBS
Level 1
   WBS Level 1 Description    Initial
Capex
($ M)
   Sustaining
Capex
($ M)
   Total
Capex
($ M)
 
3300   Flotation and Regrind   44.9   0.0   44.9 
3400   Concentrate Thickening   9.4   0.0   9.4 
3500   Concentrate Filtration, Storage, Loadout   13.7   0.0   13.7 
3600   Reagents   7.8   0.0   7.8 
3700   Process Services   9.4   0.0   9.4 
3800   Process Control System   1.6   0.0   1.6 
3900   Process Plant General   11.0   1.3   12.3 
Sub-total Crushing and Process Plant Costs   200.5   1.3   201.8 

 

The capital cost estimate for the process plant included provision for all mechanical and electrical equipment, mobile equipment, buildings as well as quantities for bulks such as earthworks, concrete, steel, piping, electrical and instrumentation.

 

All major processing equipment were sized based on the process design criteria. Once the mechanical equipment list was outlined, mechanical scopes of work were derived and sent to the market for firm and budgetary pricing by local and international equipment suppliers. Once the price quotations were reviewed and integrated, majority of the major mechanical and electrical equipment packages were sourced from firm and budgetary quotations, with the remainder of the minor process equipment pricing sourced from other recent reference projects and studies.

 

Additional indirect costs were included to cover field indirects, process capital spares, process vendor representatives, process commissioning support, process first fills, EPCM, construction camps, camp catering & maintenance, personnel transportation, fuel, heavy craneage and other miscellaneous construction services and temporary support costs.

 

18.1.8Tailings Management Facility (WBS 4000)

 

The capital cost estimate for the TMF included provision for constructing the initial starter dam of the TMF to an elevation of 830 m, which is sufficient to store the first year of tailings production. The TMF would be constructed using waste rock material for the adjacent WRF and compacted in 1 m lifts. As the rock is already being delivered to the WRF, no allowance was provided for spreading and compacting the material as it is assumed that the dozers already on the WRF will handle that activity and the 1 m lifts would be compacted by haul truck traffic.

 

An allowance was made for excavating the overburden encountered beneath the starter dam footprint and portions of the WRF. This material will be stockpiled and used in reclamation activities at the end of mine life. Costs were estimated for the general foundation preparation within the footprint of the tailings impoundment in advance of the liner placement. Supply and installation of the geotextile and geomembrane was only considered in the capital cost estimate for placement up to the starter dam elevation of 830 m.

  
Arctic ProjectPage 358
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 
   

  

The storage capacity of the TMF will be increased through three additional raises of the dam in Years 1, 4 and 7 to an ultimate elevation of 892 m. Sustaining capital has been estimated for each of these raises to accommodate construction of access roads around the TMF, placement of underliner material, and installation of geosynthetics.

 

A summary of TMF capital costs is provided in Table 18-12. 

 

Table 18-12: TMF Capital Costs 

 

WBS
Level
   WBS Description  Initial Capex
($ M)
   Sustaining Capex
($ M)
   Total Capex
($ M)
 
4110   Site Civil Infrastructure   13.3    0.0    13.3 
4120   Water Systems   4.9    0.0    4.9 
4130   Sewage, Waste and Water Systems   4.9    0.0    4.9 
4140   Electrical Services   9.3    0.0    9.3 
4910   IT & Communications   56.0    32.4    88.4 
Sub-total TMF Costs   75.8    88.3    32.4 

 

18.1.9Onsite Infrastructure (WBS 5000)

 

18.1.9.1Water Treatment Plant

 

Costs for major equipment items were based on vendor budgetary quotations solicited specifically for the Arctic Project, minor equipment costs sourced from similar recent projects.

 

A factor-based methodology was then used to estimate the total capital investment for the WTP. The factors used to convert the delivered equipment costs to total fixed capital investment are based on estimating norms established using experience from past projects. The cost estimate includes a total of 5,600 m2 of heated buildings, built in phases as the elements of the WTP are built. A line item, to account for costs not itemized in other cost categories and contingency, of 30% was applied. B&C estimated the cost of the treatment system (equipment, piping, electrical systems, control systems, structural, yard improvements and freight); and Ausenco estimated the cost of the building, building foundation and civil works, and pipelines and utilities outside the building.

 

18.1.9.2Other Onsite Infrastructure Costs

 

Other onsite infrastructure costs included provisions for civil infrastructure, electrical services, IT and communications, ancillary buildings, fuel storage and mobile equipment. A summary of onsite infrastructure costs is provided in Table 18-13.

 

Table 18-13: Onsite Infrastructure Costs 

 

WBS
Level 1
   WBS Level 1 Description  Initial Capex
($ M)
   Sustaining Capex
($ M)
   Total Capex
($ M)
 
5100   Site Civil Infrastructure   12.8    0.0    12.8 
5200   Water Systems   25.3    0.0    25.3 
5300   Sewage, Waste and Water Systems   55.8    35.1    90.8 
5400   Electrical Services   47.7    0.0    47.7 
5500   IT & Communications   0.1    0.0    0.1 
5600   Ancillary Buildings   12.4    0.0    12.4 
5700   Diesel Storage and Distribution   2.1    0.0    2.1 
5800   Plant Mobile Equipment   7.6    0.0    7.6 
5900   Onsite Infrastructure General   9.1    0.0    9.1 
Sub-total Onsite Infrastructure Costs   75.8    172.8    35.1 

 

  
Arctic ProjectPage 359
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

 
   

 

18.1.10Offsite Infrastructure (WBS 6000)

 

18.1.10.1Main Access Road

 

The total estimate for the main site access road is $20M. The access road includes approximately 8 km of road between the Bornite Camp and the Arctic intersection. The estimate included the access road design and construction package, stream crossings and drainage structures, road surfacing, project delivery costs, and contingency.

 

18.1.10.2Other Offsite Infrastructure Costs

 

Other offsite infrastructure costs included provisions for an airstrip, logistics compound and PAF. A summary of offsite infrastructure costs is provided in Table 18-14.

 

Table 18-14: Offsite Infrastructure Costs

 

WBS
Level 1
   WBS Level 1 Description  Initial Capex
($ M)
   Sustaining Capex
($ M)
   Total Capex
($ M)
 
7100   Site Access Road   20.0    0.0    20.0 
7200   Airstrip   4.6    0.0    4.6 
7300   Logistics Compound   2.1    0.0    2.1 
7400   PAF   48.6    0.0    48.6 
7900   General Offsite Infrastructure   0.4    0.0    0.4 
Sub-total Offsite Infrastructure Costs   75.8    0.0    75.8 

 

18.1.11Indirects (WBS 7000)

 

Indirect costs were estimated to include:

 

·Project preliminaries (field indirects) such as temporary construction facilities, temporary utilities, construction support, construction equipment, material storage and site office costs

 

·Construction camp and catering costs

 

·EPCM costs to cover such items as engineering and procurement services, construction management services, project office facilities, IT, staff transfer expenses, secondary consultants, field inspection and expediting, corporate overhead and fees

 

·Spares (operational, capital, commissioning) and first fills

 

·Costs for vendor representatives

 

·Contractor support for commissioning activities to make minor modifications or provide labour assistance during commissioning

 

Table 18-15 summarizes the indirect capital costs for the Arctic Project.

 

Table 18-15: Indirect Capital Costs

 

WBS
Level 1
   WBS Level 1 Description  Initial Capex
($ M)
   Sustaining Capex
($ M)
   Total Capex
($ M)
 
7100   Project Preliminaries   18.7    0.0    18.7 
7200   Temporary Facilities   4.3    0.0    4.3 
7300   Temporary Services   11.8    0.8    12.6 
7400   Camps   39.4    0.0    39.4 
7500   Cranage   2.6    0.0    2.6 
7600   EPCM Costs   89.8    14.3    104.1 
7700   Commissioning Support   1.1    0.0    1.1 
7800   First fills/spares   7.5    0.0    7.5 
7900   Vendors   2.1    0.0    2.1 
Sub-total Indirect Costs   177.4    15.1    192.5 

 

  
Arctic ProjectPage 360
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

 
   

 

18.1.12Provisions / Contingency (WBS 8000)

 

Provisions are included in the cost estimate to account for growth allowances based on the level of definition of the study and estimate contingency. Estimate contingency is included to address anticipated variances between the specific items contained in the estimate and the final actual project cost.

 

The estimate contingency does not allow for the following:

 

·Abnormal weather conditions

 

·Changes to market conditions affecting the cost of labour or materials

 

·Changes of scope withing the general production and operating parameters

 

·Effects of industrial disputes

 

A summary of the estimate contingency is provided in Table 18-16, broken down by scope owner, totaling $138.5 M of initial capital costs, or ~12% of the total Arctic Project initial capital cost.

 

Table 18-16: Estimate Contingency

 

WBS Area   Initial Capex
($ M)
    Sustaining Capex
($ M)
    Total Capex
($ M)
 
Crushing, Process Plant, Off-site Infrastructure     68.7       13.0       81.7  
Mining     39.6       0.0       39.6  
Tailings Management Facility     12.4       0.0       12.4  
On-site Infrastructure     16.3       0.0       16.3  
Owner’s Cost     1.6       0.0       1.6  
Sub-total Contingency     138.5       13.0       151.5  

 

  
Arctic ProjectPage 361
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

 
   

 

18.1.13Owner’s Costs (WBS 9000)

 

A breakdown of owner’s costs is shown in Table 18-17.

 

Table 18-17: Owner’s Costs

 

Description  Initial Capex
($ M)
   Sustaining Capex
($ M)
   Total Capex
($ M)
 
Owner’s Project Management   11.3    0.0    11.3 
Health & Safety   3.3    0.0    3.3 
Start-up   12.2    0.0    12.2 
Sub-total Owner’s Costs   26.8    0.0    26.8 

 

  
Arctic ProjectPage 362
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

 

18.1.14Sustaining Capital and Closure Costs

 

Sustaining capital costs include expenditure related to additions to the truck mining fleet, to replace equipment beyond its manufacturer’s recommended service life, processing plant equipment, onsite infrastructure (largely comprising the cost of the Reverse Osmosis Reject WTP towards the end of the mine life) and miscellaneous indirect costs. In addition, sustaining costs are carried for the three TMF dam raises. However, costs associated with placement and compaction of the material for dam raises, being achieved through building up of the WRF, are captured as mining operating costs.

 

Table 18-18 summarizes the sustaining capital and closure costs. The total closure cost of $428 million includes $124.7 million in closure costs, $46.1 million in post-closure costs and $258 million in post-closure water treatment costs. Further details related to the closure cost total are provided in Section 17.3.6.

 

Table 18-18: Sustaining Capital and Closure Costs

 

WBS Level 1   WBS Description    Sustaining
Capex
($ M)
 
1000   Mining   17.5 
2000   Crushing   0 

  
Arctic ProjectPage 363
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

WBS Level 1   WBS Description    Sustaining
Capex
($ M)
 
3000   Process Plant   1.3 
4000   Tailings   32.4 
5000   On-Site Infrastructure   35.1 
6000   Off-Site Infrastructure   0 
    Sub-Total Direct Costs   86.3 
7000   Indirects   15.1 
8000   Provisions (Contingency)   13.0 
9000   Owners Costs   0 
Sub-Total Indirect Costs   28.1 
Arctic Project Total – Sustaining Capital   114.4 
Arctic Project Total – Closure Costs   428.4 

 

18.2 Operating Cost Estimate

 

The operating cost estimate is within the ± 25% cost accuracy for a PFS-level study under S-K 1300 standards.

 

18.2.1Operating Cost Summary

 

An average operating cost was estimated for the Arctic Project based on the proposed mining schedule. These costs included, mining, processing, G&A, surface services, and road toll costs. The average LOM operating cost for the Arctic Project is estimated to be $59.83/t milled.

 

The processing plant throughput is designed to operate at approximately 10,000 t/d, or 3,650,000 t/a. The proposed mining schedule ramps up in Year 1 and ramps down in Year 13 resulting in a LOM average of approximately 3,592,000 t/a processed. Total throughput is estimated to be 46,691,000 t over the 13-year LOM. The breakdown of costs in Table 18-19 is based on the 3,650,000 t/a mill feed rate.

  
Arctic ProjectPage 364
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 18-19:          Overall Operating Cost Estimate

 

Description  LOM Average Unit Operating Cost
($/ t milled)
  LOM Average
Annual
Cost ($ M/a)
  Percentage of Total Annual
Operating Costs
 
Mining*  22.49   82.1  37.6 %
Processing  22.60  

82.5

  37.8 %
G&A  5.85   21.3  9.8 %
Road Toll and Maintenance  7.72   28.2  12.9 %
Water Treatment  1.17   4.3  2.0 %
Total Operating Cost  59.83   218.4  100 %

 

* Excludes pre-production costs.

 

18.2.2Mining Operating Cost Estimate

 

The mining operating cost averages $2.40/t (moved) during preproduction and $3.24/t (moved) during production. The total tonnage moved includes 0.78 Mt of stockpile rehandle and 386.9 Mt of primary production. Figure 18-2 presents the operating cost distribution, where mine haulage accounts for 36% of the mine operating costs, open pit blasting accounts for 19% of the mine costs, followed by loading, services, and drilling each at 16%, 15%, and 6%, respectively. The Others category in the figure includes costs for engineering, geology, operations, and management overheads. The stockpile rehandling cost is minor due to the small amount of material rehandled along the life of the mine. Table 18-21 shows the operating cost break down by cost centre.

 

Figure 18-2:Costs by Cost Centre

 

(GRAPHIC) 

 

Source: Wood, 2022.

  
Arctic ProjectPage 365
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Personnel costs are the largest cost items for the mine, followed by maintenance and repair supplies, fuel, and blasting explosives. The study diesel price is $1.04/l. The Others category shown in Figure 18-3 includes costs for: drilling supplies, auxiliary equipment, contract services, ground engaging tools, blasting accessories and lubricants.

 

Figure 18-3:Costs by Cost Item

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

Figure 18-4 provides an overview of the tonnage mined and the mine operating costs per tonne mined. During Year -2 and Year -1, the mining costs are at the lowest due to the short haul distances and high mining rates. From Year 1 to Year 4, the mining costs increase as the haul cycles increase with the deepening of the Phase 1 and Phase 2 lay backs and the mining of the upper zones of Phase 3. Mining costs then decrease in Year 5 as a new exit of the pit is used, decreasing the haulage distances. An increase in the following years can be noticed as Phase 2 and Phase 3 start deepening. After Year 9, only Phase 4 (final phase) is mined and the cost increases with the deepening of the pit and a reduction in the total tonnage mined.

  
Arctic ProjectPage 366
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 18-20 summarizes the average mining operating cost over the LOM.

 

Table 18-20: Mining Operating Cost Summary by Cost Centre

 

Cost Centre  LOM Average Annual
Cost
($ M/a)
   LOM Average Unit
Operating Cost
($/t milled)
 
OP Management   0.4    0.12 
OP Operations O/H   2.9    0.79 
OP Engineering   2.0    0.55 
OP Geology   1.5    0.41 
OP Drilling   5.2    1.42 
OP Blasting   14.9    4.08 
OP Loading   13.0    3.56 
OP Hauling   30.1    8.25 
OP Stockpile Rehandle   0.1    0.02 
OP Services   12.0    3.29 
Total Operating Cost   82.1    22.49 

Note: Figures may not add up due to rounding. OP – open pit

 

Average annual LOM mining costs are summarized in Table 18-21.

 

Table 18-21:Operating Cost Summary by Cost Centre

 

    Preproduction   Production   Total Mining Cost  
Cost Centre   ($M)   ($/t mined)   ($/t moved)   ($M)   ($/t mined)   ($/t moved)   ($M)   ($/t mined)   ($/t moved)  
OP Management   0.85   0.01   0.01   5.42   0.02   0.02   6.27   0.02   0.02  
OP Operations O/H   5.77   0.09   0.09   37.04   0.11   0.11   42.81   0.11   0.11  
OP Engineering   4.43   0.07   0.07   25.79   0.08   0.08   30.22   0.08   0.08  
OP Geology    3.27   0.05   0.05   19.22   0.06   0.06   22.49   0.06   0.06  
OP Drilling    11.15   0.18   0.18   66.21   0.20   0.20   77.36   0.20   0.20  
OP Blasting   34.82   0.56   0.56   190.32   0.59   0.59   225.14   0.58   0.58  
OP Loading   25.07   0.40   0.40   166.22   0.51   0.51   191.29   0.49   0.49  
OP Hauling   43.14   0.69   0.69   385.42   1.19   1.19   428.56   1.11   1.11  
OP Stockpile Rehandle    -    -    -   0.74    0.00    0.00   0.74    0.00    0.00  
OP Services   21.40   0.34   0.34   153.62   0.47   0.47   175.02   0.45   0.45  
Operating Cost   149.9   2.40   2.40   1,050.0   3.24   3.23   1,199.90   3.10   3.10  
Tonnes Mined   62.4 Mt   324.4 Mt   386.9 Mt  
Tonnes Rehandled   -   0.8 Mt   0.8 Mt  
Tonnes Total   62.4 Mt   325.2 Mt   387.7 Mt  

 

Note: Figures may not sum due to rounding. OP – open pit.

  
Arctic ProjectPage 367
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Figure 18-4:Total Material Mined and Mine Operating Cost

 

(GRAPHIC) 

 

Source: Wood, 2022.

 

Table 18-22 provides a summary of the annual mining costs and unit mining costs for both primary production and total material mined.

 

Table 18-22:Annual Mine Expenditure

 

    Mining Cost   Primary Production   Total Material Moved*  
Period   ($ M)   (kt)   ($/t)   (kt)   ($/t)  
Year -2   0.07    27,400   2.53    27,400   2.53  
Year -1   0.08    35,044   2.30    35,044   2.30  
Year 1   0.10    34,077   2.80    34,853   2.74  
Year 2   0.09    34,190   2.66    34,190   2.66  
Year 3   0.09    31,015   2.95    31,015   2.95  
Year 4   0.09    30,000   3.07    30,000   3.07  
Year 5   0.09    29,500   2.88    29,500   2.88  
Year 6   0.09    28,563   3.27    28,563   3.27  

  
Arctic ProjectPage 368
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

    Mining Cost   Primary Production   Total Material Moved*  
Period   ($ M)   (kt)   ($/t)   (kt)   ($/t)  
Year 7   0.09    28,063   3.04    28,063   3.04  
Year 8   0.08    23,500   3.51    23,500   3.51  
Year 9   0.09    24,000   3.55    24,000   3.55  
Year 10   0.07    21,572   3.51    21,572   3.51  
Year 11   0.07    19,000   3.62    19,000   3.62  
Year 12   0.06    15,280   4.22    15,280   4.22  
Year 13   0.04    5,655   6.98    5,655   6.98  
Total   1.20   386,859   3.10   387,635   3.10  

 

Note: Total Material Moved is inclusive of rehandle

 

18.2.2.1Mining Operating Cost Basis of Estimate

 

The basis for the study unit costs and the consumption estimates are detailed in the following sub-sections.

 

18.2.2.2Personnel Costs

 

Salaries were based on Wood’s database for similar projects, and benchmarking with publicly available salary ranges for mining job positions in Alaska. For hourly labour, Wood relied on local labour costs provided by Trilogy detailing expected hourly and salaried annual rates. Labour rates are inclusive of a 38% burden. Wood applied the labour rates to the staffing plan to estimate total labour costs.

 

  
Arctic ProjectPage 369
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 
   
   

 

18.2.2.3Maintenance and Repair Cost

 

Equipment suppliers provided equipment maintenance and repair cost estimates in quotations obtained in 2022. Table 18-23 provides a listing of the average maintenance and repair costs for each major machine-type. Within the cost model a variable maintenance and repair cost was assigned every 6,000-hour increments.

 

The maintenance and repair costs provided by the equipment suppliers assume owner performed maintenance and include costs for:

 

Planned maintenance, i.e., routine service and lubrication.

 

Major repair and rebuilds including parts and rebuild bench labour.

 

Routine minor repairs.

 

Table 18-23: Maintenance and Repair Cost

 

Equipment   Cost
($/h)
 
171 mm Production Drill   106  
265 t/15 m3 Hydraulic Face Shovel   125  
124 t/12 m3 Front End Loader   66  
144 t Haul Truck   81  
41t Articulated Truck   21  
26 t/5 m3 Front End Loader   36  
68 t/4 m3 Hydraulic Excavator   29  
35 t/1.4 m3 Hydraulic Excavator   21  
74 t/455 kW Track Dozer   72  
50 t/419 kW Rubber Tired Dozer   63  
40 t Articulated Sand Truck   21  
33 t/217 kW Motor Grader   31  
35,000-litre water truck   21  

  
Arctic ProjectPage 370
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Equipment   Cost
($/h)
 
40t Articulated Fuel/Lube Truck   21  

 

18.2.2.4Diesel and Fuel Consumption

 

Wood relied on a diesel fuel price of $1.04/L ($3.92/gal) provided by Ausenco - based on the 3-year trailing average weekly U.S. No 2 diesel ultra low sulphur retail price, adjusted for delivery to the project site. Diesel consumption for the haul trucks is estimated based on duty cycles. For all other machines, Wood used either the diesel consumption rates provided by equipment suppliers, or a consumption rate from the CAT Handbook Version 49 (Caterpillar, 2019). Consumption per operated hour for each machine is provided in Table 18-24.

 

Table 18-25 provides the annual diesel fuel requirements. Diesel fuel consumption peaks in Year 7 at 14.6 ML consumed.

 

Table 18-24: Equipment Fuel Burn Rates

 

Equipment   liters/op hour  
171 mm Production Drill   83  
265 t/15 m3 Hydraulic Face Shovel   172  
124 t/12 m3 Front End Loader   90  
144 t Haul Truck   76  
41t Articulated Truck   22  
26 t/5 m3 Front End Loader   21  
68 t/4 m3 Hydraulic Excavator   40  
35 t/1.4 m3 Hydraulic Excavator   18  
74 t/455 kW Track Dozer   63  
50 t/419 kW Rubber Tired Dozer   45  
40 t Articulated Sand Truck   35  
33 t/217 kW Motor Grader   30  
35,000-litre water truck   35  
40t Articulated Fuel/Lube Truck   35  

  
Arctic ProjectPage 371
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 18-25:Annual Diesel Consumption

 

Period  Hauling
(ML)
  Loading
(ML)
  Support
(ML)
  Drilling
(ML)
  Blasting
(ML)
  Total
(ML)
 
Year -2   4.6   3.7   2.3   1.1   0.2  11.9  
Year -1   5.8   3.7   2.3   1.3   0.3  13.4  
Year 1   6.3   3.6   2.3   1.3   0.3  13.8  
Year 2   6.7   3.6   2.3   1.3   0.3  14.2  
Year 3   6.4   3.6   2.3   1.2   0.3  13.7  
Year 4   7.0   3.5   2.3   1.2   0.3  14.3  
Year 5   7.3   3.5   2.3   1.1   0.3  14.5  
Year 6   7.2   3.5   2.3   1.1   0.3  14.3  
Year 7   7.5   3.5   2.3   1.1   0.2  14.6  
Year 8   7.2   2.9   2.0   1.0   0.2  13.3  
Year 9   7.9   2.9   2.0   1.0   0.2  14.1  
Year 10   7.6   2.9   2.0   1.0   0.2  13.7  
Year 11   7.9   2.9   2.0   0.8   0.2  13.8  
Year 12   6.9   3.0   1.6   0.6   0.1  12.2  
Year 13   2.3   1.9   1.6   0.2   0.1  6.0  
Total   98.5   48.7   31.8   15.2   3.4  197.6  

 

18.2.2.5Explosives Cost

 

A multinational explosives service company provided explosives product costs as part of the RFQ process. Costs for explosive products and the monthly service cost is shown in Table 18-26. Operating fee includes $228k/month for personnel and $2.5k/month for forklift equipment costs rental. Other blasting equipment such as mobile mixing units (MMU) and stemming trucks were incorporated as part of the mine auxiliary equipment. Transfer site cost was included as part of the mine capital cost.

  
Arctic ProjectPage 372
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 18-26:Blasting Explosives and Accessories Cost and Service Fee

 

Item  Unit  Value  
Blasting Product        
ANFO (Ammonium Nitrate – Fuel Oil)  $/t  1,282  
Bulk Emulsion  $/t  2,042  
Blasting Accessories        
Non-electric detonator  $/ea  14.00  
Surface delays  $/ea  8.50  
Booster 450 gram  $/ea  8.45  
Booster 900 gram  $/ea  16.14  
Monthly Service Fee        
Operating Fee  $/month  230,625  

 

18.2.2.6Tires Cost

 

Tire pricing was provided by equipment vendors as part of the RFQ process. Tire pricing is shown in Table 18-27 along with tire lives used for estimating tire costs during operations.

 

Table 18-27: Tire Sizes, Pricing, and Life

 

Machine  Tires/machine  Size  Price each ($)  Life (operating h)  
124 t/12 m3 Front End Loader  4.00  45/65R45  43,750  5,000  
144 t Haul Truck  6.00  33.00R51  20,214  5,000  
41t Articulated Truck  6.00  29.5R25  5,560  5,000  
26 t/5 m3 Front End Loader  4.00  26.5R25  18,559  5,000  
50 t/419 kW Rubber Tired Dozer  4.00  35/56-33  12,787  4,000  
40 t Articulated Sand Truck  6.00  29.5R25  5,560  4,500  
33 t/217 kW Motor Grader  6.00  23.5R25  3,495  4,000  
35,000-litre water truck  6.00  29.5R25  5,560  4,500  
40t Articulated Fuel/Lube Truck  6.00  29.5R25  5,560  4,500  

  
Arctic ProjectPage 373
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

During the preproduction period, the 144-t truck tire lives were derated to 3,000 hours in Year -2 and 4,000 hours in Year-1 to account for poor road, pit, and dump conditions anticipated in the early years of the operation.

 

18.2.2.7Other Operating Costs

 

Other operating costs account for 7.57% of the total operating costs. The other cost items are listed in Table 18-28.

 

Table 18-28:Other Operating Costs

 

Cost Item  Percentage of Total
(%)
   LOM Cost
($ M)
   $/t Mined 
Drilling Supplies  1.14%  14.13   0.04 
Auxiliary Equipment  2.65%  32.8   0.08 
Ground Engaging Tools  1.26%  15.8   0.04 
Equipment, Supplies, Materials  0.03%  0.39   0.00 
Lubricants  2.33%  28.86   0.07 
Other Miscellaneous Costs  0.16%  1.97   0.01 
Total Cost  7.57%  93.74   0.24 

 

18.2.3Processing Operating Cost Estimate

 

The LOM average process operating cost is $22.60/t milled. This estimated unit cost was based on the designed 10,000 t/d throughput rate. Table 18-29 summarizes the processing operating cost estimates. Labour costs based on a detailed staffing plan and local rates.

 

Operating costs include all regular, recurring costs of production, such as:

 

Processing

 

Power consumption

 

Operating Consumables

 

General Maintenance and

 

General and administration (G&A)

 

The operating cost estimates were calculated based on the following assumptions:

 

Plant capacity per day of 10,000 t/d over LOM.

 

Crushing and mill plant availabilities at 65% and 92%, respectively.

 

Cost estimates were based on the third quarter (Q3) of 2022 pricing without allowances for inflation.

 

Relevant exchange rates were used to convert to the base currency of US dollars ($)

  
Arctic ProjectPage 374
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

A diesel cost of $3.92/gal was based on the 3-year trailing average weekly U.S. No 2 diesel ultra low sulphur retail price, adjusted for delivery to the project site.

 

The power consumption cost was derived from the diesel cost at $0.289/kWh.

 

Labour will mainly be sourced from Alaska.

 

Operating and maintenance consumables were provided by different vendors such as Univar, Molycop, Metso-Outotec, etc.

 

Processing costs were determined based on labour, light vehicles and mobile equipment, operating and maintenance consumables and processing power requirements.

 

Road maintenance and road toll costs were provided by Trilogy.

 

Table 18-29: Summary of Processing Operating Cost Estimates

 

Description  Average Annual LOM
Operating Cost
($ M)
   Average Annual LOM
Operating Cost
($/t milled)
 
Plant Operations Labour  7.0   2.86 
Plant Maintenance Labour  7.5   3.06 
Power Supply (Mill and Tailings)  25.2   10.24 
Processing Consumables  12.7   5.16 
Maintenance Consumables  2.9   1.18 
Light Vehicles & Mobile Equipment  0.3   0.10 
Total (Processing)  55.5   22.60 

 

18.2.3.1Power

 

Power costs were calculated from an estimate of annual power consumption and using a unit cost of $0.289/kWh.

 

The processing power draw was based on the average power utilisation of each motor on the electrical load list for the process plant and services. Diesel generators along with the fuel will be transported to the site to service the facilities at the site.

 

Annual energy consumption is estimated at 129,546 MWh/a, costing an annual average of $25.2 M/a over LOM.

 

18.2.3.2Consumables

 

Processing reagent and consumable costs were estimated based on the throughput. All costs include freight charges to site.

 

The operating consumables costs were developed with the following basis:

 

Liner consumptions for the jaw crusher, SAG mill, Ball mill and regrind mill were determined based on the comminution and breakage data and Ausenco’s calculations and in-house database.

  
Arctic ProjectPage 375
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Grinding media consumption were based on the internal Ausenco calculations.

 

Reagent consumption was estimated from metallurgical testwork.

 

Filter cloth consumption were established by benchmarking different Ausenco projects.

 

All costs associated with operating consumables not stated above were determined using quotations and commercial proposals provided by vendors

 

18.2.3.3Maintenance Consumables

 

Annual maintenance consumable costs were calculated based on a total installed mechanical capital cost by area using a weighted average factor from 3% to 4%. The factor was applied to mechanical equipment, platework and piping. The total maintenance consumables operating costs is $1.18/t of feed.

 

18.2.3.4Labour

 

Labour includes all processing and maintenance labour costs.

 

Processing production labour was provided by Trilogy and includes operation departments such as metallurgy, mill operations, maintenance, and the assay lab.

 

Each position was defined and classified as Salary and Wages. Costs included taxes and benefits. The annual cost is $10.3 M/a for process operations labour and $11.0 M/a for process maintenance labour. The estimated labour force for plant operations and plant maintenance was estimated at 69 and 74 people respectively. The estimate was based on providing a labour force to support continuous operations at 24 hr/d, 365 d/a.

 

Annual maintenance supplies costs were estimated as a percentage of major capital equipment costs plus an allowance for freight charges.

 

18.2.4General and Administrative and Surface Services Cost Estimates

 

The LOM average G&A costs were estimated to be $5.85/t milled. These estimated costs were developed by Trilogy and Ausenco and include:

 

Labour cost for the 57 administrative staff (27 hourly, and 30 salaried), with approximately 42 of these administrative staff onsite. These numbers included the 16 personnel (15 hourly and 1 salaried) surface operations crew.

 

Service cost for safety, training, medical and first aid expenditure, computer supplies and software, human resources services, and entertainment/membership.

 

Asset operations costs including operating vehicles, and warehouse costs.

 

Contract services expenditures, including insurance, consulting, relocation expenses, recruitment, auditing and legal services.

 

Camp costs and personnel transport.

 

Operation and maintenance of the airport.

  
Arctic ProjectPage 376
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Asset operations including heating, site services for general maintenance, general road maintenance, and ground transportation.

 

Other expenses including road dust suppression.

 

Other costs, including liaisons to local communities, sustainability costs, and an allowance for regional taxes and licenses.

 

Table 18-30 shows a summary of the G&A cost estimate.

 

Table 18-30:          G&A Cost Estimates

 

Cost Description  Annual Costs
($ M)
 
Labour Costs – Salaried Staff  4.67 
Labour Costs – Hourly Staff  3.92 
Airport Operation  0.15 
General Office Expense  0.11 
Medical and First Aid  0.11 
Environment  0.16 
Travel  0.11 
Training and Safety  0.16 
Computer Supplies Including Software  0.11 
Entertainment/Membership  0.06 
Vehicles  0.31 
Warehouse  0.22 
Communications  0.44 
Insurance  2.20 
Consulting/External Assays  0.06 
Relocation Expense  0.02 
Recruitment  0.02 
Audit  0.11 
Legal Services  0.06 
Rotational Travel and Camp  7.19 
Surface Operations G&A  0.58 
Surface Equipment  0.38 
Liaison Committee/Sustainability  0.11 
Other  0.11 
Total (G&A)  21.3 

  
Arctic ProjectPage 377
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

18.2.5Road Toll Cost Estimate

 

Trilogy will pay road toll costs to use the AAP that is proposed to be built by AIDEA. AIDEA anticipates that there will be multiple users of the access road for multiple purposes with significantly different levels of use. These variables make it difficult to accurately project, at this time, what the estimated road toll will be for the Arctic Project. Trilogy provided Ausenco with the company’s view of the likely costs.

 

There is currently no road access to the project area. Access to the project area is proposed to be via the AAP road, which is approximately 340 km (211 miles) long, extending west from the Dalton Highway where it would connect with the proposed project area.

 

The working assumption for the 2020 FS report was that AIDEA would arrange financing in the form of a public-private partnership to arrange for the construction and maintenance of the access road. AIDEA would charge a toll to multiple mining and industrial users (including the Arctic Project) to pay back the costs of financing the AAP. This model is very similar to what AIDEA undertook when the DeLong Mountain Transportation System (also known as the Red Dog Mine Road and Port facilities) was constructed in the 1980s. The amount paid in tolls by any user would be affected by the cost of the road, its financing structure, and the number of mines and other users of the road which could also include commercial transportation of materials and consumer items that would use the AAP to ship concentrates to the Port of Anchorage in Alaska and possibly provide goods and commercial materials to villages in the region. This model has not changed in this Report.

 

For the purposes of this Report the $22M/a cost of the AAP toll is escalated from the 2020 FS, with an annual maintenance cost of an additional $9.1M/a. The final toll payments will be negotiated with AIDEA and the public-private partnership owners of the access road at some point in the future. A credit of $44M is applied towards road tolls payable in the first 2 years of operation to account for a pre-existing $35M investment, with an 8.0% annual interest rate, from Trilogy to AIDEA during the project development phase.

 

This equates to an average road toll and maintenance cost of $28.2 M annually over the LOM, or $7.72/t milled over the LOM.

 

18.2.6Water Treatment Costs

 

Water treatment costs during the production period average $1.17/t milled over the LOM, or $4.2 M annually. These costs include Operation (labour, reagents, power) and maintenance costs for the RO WTP during plant operation. Reagents and chemical prices used are developed on a constant Q3/Q4 2022 basis, delivered to the project site. Operating costs for post-closure water treatment are captured under closure costs in Section 17.3.6.

 

  
Arctic ProjectPage 378
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

19ECONOMIC ANALYSIS

 

19.1Forward-Looking Information Cautionary Statements

 

Trilogy is subject to the reporting requirements of the Exchange Act and this filing and other U.S. reporting requirements are governed by Subpart 1300 of Regulation S-K promulgated by the SEC. The results of the economic analyses discussed in this section represent forward-looking statements within the meaning of applicable securities laws relating to Trilogy Metals. These statements by their nature involve substantial risks and uncertainties. Statements involving the foregoing results of economic analysis are forward-looking statements. Without limiting the generality of the foregoing, words such as “may”, “anticipate”, “intend”, “could”, “estimate”, or “continue” or the negative or other comparable terminology are intended to identify forward-looking statements. Should one or more of these risks or uncertainties materialize or should the underlying assumptions prove incorrect, actual outcomes and results could differ materially from those indicated in the forward-looking statements. Information that is forward-looking includes the following:

 

Probable Mineral Reserves that have been modified from Indicated Mineral Resource estimates.

 

Assumed commodity prices and exchange rates.

 

Proposed mine and process production plan.

 

Projected mining and process recovery rates.

 

Ability to market the three types of concentrate on favourable terms.

 

Ability to control the levels of deleterious elements in some of the concentrate batches.

 

Sustaining costs and proposed operating costs.

 

Assumptions as to closure costs and closure requirements, including WTP requirements.

 

Assumptions as to development of the AMDIAP, timeframe of such development and assumed toll charges.

 

Assumptions as to ability to permit the project.

 

Assumptions about environmental, permitting and social risks.

 

Additional risks to the forward-looking information include:

 

Unrecognized environmental risks.

 

Unanticipated reclamation expenses.

 

Unexpected variations in quantity of mineralization, grade or recovery rates.

 

Geotechnical or hydrogeological considerations during operations being different from what was assumed

 

Failure of mining methods to operate as anticipated.

 

Failure of plant, equipment or processes to operate as anticipated.

  
Arctic ProjectPage 379
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Changes to assumptions as to the generation of electrical power, and the power rates used in the operating cost estimates and financial analysis.

 

Ability to maintain the social licence to operate.

 

Accidents, labour disputes and other risks of the mining industry.

 

Changes to interest rates.

 

Changes to tax rates.

 

Changes to applicable laws.

 

Receipt of all required permits.

 

19.2Methodology

 

An economic model was developed to estimate annual pre-tax and post-tax cash flows and sensitivities of the Arctic Project based on an 8% discount rate.

 

Years shown in the economic analysis are provided for conceptual purposes only. Permits still must be obtained in support of operations; and approval to proceed is still required from the Arctic Project’s owners.

 

19.3Financial Model Parameters

 

The Arctic Project will consist of a three-year pre-production construction period, followed by 13 years of production. Year -3 represents construction of a pioneer road and early purchases of equipment in preparation for site activities that occur in Year -2 and Year -1. The NPV and IRR were calculated at the beginning of the construction period in Year -3.

 

The cost and revenue estimates were assembled using real dollars, treating Year-3 as the base year. No escalation was applied to any of the estimates beyond this date.

 

The long-term consensus metal price assumptions were included in Section 16.2.

 

The LOM material tonnages and payable metal production used in the cash flow model are included in Table 19-1.

 

Table 19-1: Mine and Payable Metal Production for the Arctic Mine

 

Description  Units  Value  
Total Tonnes Mined  kt  390,189  
Mill Feed  kt  46,691  
Concentrate  
Cu Concentrate  kt  2,995  
Zn Concentrate  kt  2,228  

  
Arctic ProjectPage 380
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Description  Units  Value  
Pb Concentrate  kt  298  
Payable Metal  
Payable Cu  '000'lb  1,932,882  
Payable Zn  '000'lb  2,243,771  
Payable Pb  '000'lb  334,785  
Payable Au  '000'oz  423  
Payable Ag  '000'oz  36,047  

 

19.4Economic Analysis

 

19.4.1Pre-Tax Financial Analysis

 

19.4.1.1Basis of Pre-Tax Financial Evaluation

 

The pre-tax financial model incorporated the production schedule and smelter term assumptions to produce annual recovered payable metal, or gross revenue, in each concentrate stream by year. Off-site costs, including the applicable refining and treatment costs, penalties, concentrate transportation charges, and marketing and representation fees, and royalties were then deducted from gross revenue to determine the NSR. Further details of the smelter terms used to calculate the recovered metal value and off-site operating costs can be found in Section 16. Royalties are discussed in Section 3.

 

The operating cash flow was produced by deducting annual mining, processing, G&A, surface services, and road toll & maintenance charges (Section 18.2) from the NSR.

 

Initial and sustaining capital (Section 18.1) was deducted from the operating cash flow in the years they occur, to determine the net cash flow before taxes.

 

Initial capital cost included all estimated expenditures in the construction period, from Year -3 to Year -1 inclusive. First production would occur at the beginning of Year 1. Sustaining capital expenditure includes all capital expenditures purchased after first production, including mine closure and rehabilitation.

 

Under the NANA Agreement, NANA has the right, following a construction decision, to elect to purchase a 16% to 25% direct interest in the Arctic Project or, alternatively, to receive a 15% Net Proceeds Royalty (refer to Section 3). This financial analysis was carried out on a 100% ownership basis and does not include any future potential impact on the Arctic Project interest if NANA elects to purchase an interest of between 16% and 25% in the Arctic Project under the NANA Agreement or, alternatively, the impact on the Arctic Project interest if the 15% net proceeds royalty becomes applicable. The financial analysis does include the 1.0% NSR to be granted to NANA under the NANA Agreement in exchange for a surface use agreement.

  
Arctic ProjectPage 381
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

The financial analysis was carried out on a 100% Arctic Project ownership basis, of which Trilogy’s share is currently 50%.

 

19.4.1.2Pre-Tax Financial Results

 

A summary of the pre-tax financial results is provided in Table 19-2. The presentation is on a 100% project ownership basis of which Trilogy currently holds a 50% interest.

 

Table 19-2:Summary of Pre-Tax Financial Results

 

Description  Unit  LOM Value  
Recovered Metal Value        
Copper  $ million  7,055.0  
Lead  $ million  334.8  
Zinc  $ million  2,580.3  
Gold  $ million  697.8  
Silver  $ million  757.0  
Total Recovered Metal Value  $ million  11,424.9  
Off-Site Operating Costs        
Royalties, Refining and Treatment Charges, Penalties, Insurance, Marketing and Representation & Concentrate Transportation  $ million  2,969.1  
On-Site Operating Costs        
Mining  $/t milled  22.49  
Processing  $/t milled  22.60  
G&A  $/t milled  5.85  
Water Treatment   $/t milled  1.17  
Road Toll  $/t milled  7.72  
Total Operating Cost over LOM  $/t milled  59.83  
Total Operating Cost  $ million  2,793.6  
Capital Expenditure        
Initial Capital  $ million  1,176.8  

  
Arctic ProjectPage 382
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Description  Unit  LOM Value  
Sustaining Capital  $ million  114.4  
Mine Closure & Reclamation  $ million  428.4  
Total Capital Expenditure  $ million  1,719.6  
Financial Summary        
Pre-tax Undiscounted Cash Flow  $ million  3,942.6  
Pre-Tax NPV at 8%  $ million  1,500.3  
Cash Costs, Net of By-product Credits  $/lb Cu payable  0.72  
All-in Cost*, Net of By-product Credits  $/lb Cu payable  1.61  
Pre-Tax IRR  %  25.8  
Pre-Tax Payback Period  years  2.9  

 

Note: *All-in cost includes all operating and sustaining capital costs

 

19.4.2Post-Tax Financial Analysis

 

The following tax regimes were incorporated in the post-tax analysis as provided by EY: US Federal Income Tax, Alaska State Income Tax (AST), and Alaska Mining License Tax (AMLT). Taxes were calculated based on currently enacted United States and State of Alaska tax laws and regulations, including the US Federal enactment of the Tax Cuts & Jobs Act (TCJA) on December 22, 2017, and the Coronavirus Aid, Relief and Economic Security Act (CARES Act) on March 27, 2020.

 

The Alaska Production Royalty tax of 3% is not applicable to the Arctic Project as the Arctic Project’s claims are all federal mining patented claims.

 

19.4.2.1US Federal Tax

 

For tax years beginning on or after January 01, 2018, the US Federal income tax corporate rate is 21% of taxable income, as opposed to a 35% rate which was applicable to prior tax years. Taxable income is calculated as revenues less allowable costs. In addition to other allowable costs, Alaska State Income Tax, AMLT, tax depreciation and the greater of the cost depletion or percentage depletion can be deducted. Cost depletion is the ratable recovery of cost basis as units are produced and sold, however, as noted, cost depletion is not calculated in the model because the initial cost basis of the mineral property has not been provided. IRC §613(a) governs percentage depletion and provides that the deduction for depletion shall be a statutorily prescribed percentage of the taxpayer’s gross income from the mineral property during the taxable year. Such allowance shall not exceed 50% of the taxpayer’s taxable income from the property that is mining related. Relevant statutorily prescribed percentages are 15% for gold, silver and copper, and 22% for lead and zinc. As a result of the TCJA, losses incurred for tax years beginning on or after January 01, 2018, are not eligible to be carried back to prior tax years but may be carried forward indefinitely. However, losses generated under the TCJA are only eligible to offset 80% of taxable income in future years.

  
Arctic ProjectPage 383
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

For the purposes of this Report, as a stand-alone project, it was assumed that the initial adjusted cost base of the depletable and depreciable property was zero and that the initial loss carry-forwards were zero.

 

19.4.2.2Alaska State Tax

 

Alaska State Taxes (AST) are determined on a basis similar to US federal tax. AST is calculated using a graduated rate table times taxable income with 9.4% being the highest applicable rate, where taxable income is calculated on the same basis as US federal tax (except that State tax is not deductible). The Alaskan Alternative Minimum Tax (“AMT”) statutes are tied to the federal AMT statutes; therefore, the repeal of federal corporate AMT has effectively repealed Alaskan State AMT for tax years beginning on or after January 1, 2018.

 

19.4.2.3Alaska Mining License Tax

 

The Alaska Mining Licence Tax (AMLT) is an income-based tax imposed on the mining income calculated for AST purposes, before any deduction of AMLT, except the percentage depletion is the lower of 15% of net metal revenues and 50% of net income before depletion. No loss carry-forwards or carry-backs are applied when calculating income subject to AMLT. No AMLT tax is charged for the first 3.5 years following commencement of production. In each year, AMLT can be reduced by up to 50% through the application of “Exploration Incentive Credits” (EICs); however, the credits may not exceed $20m in the aggregate for a mining operation and the credits must be utilized within 15 years. Note the EICs can be utilized against AST as well.

 

For the purposes of this Report, as a stand-alone project evaluated at the project level, it was assumed that the initial EIC balance is zero even though the Trilogy has a history of exploration at the Arctic Project. It was also assumed that no EICs would be earned over the life of the Arctic Project.

 

19.4.2.4Post-Tax Financial Results

 

At the base case metal prices used for the Report, the total estimated taxes payable on the Arctic Project profits are $922.7 million over the 13-year mine life.

 

The post-tax financial results are summarized in Table 19-3.

 

Table 19-3:Summary of Post-Tax Financial Results

 

Description  Unit  LOM Value  
Financial Summary        
Income Tax  $ million  922.7  
Post-Tax Undiscounted Cash Flow  $ million  3,019.9  
Post-tax NPV at 8%  $ million  1,108.1  
Post-Tax IRR  %  22.8  
Post-Tax Payback Period  years  3.1  

 

19.5Cash Flow

 

The annual production schedule and estimated cash flow forecast for the Arctic Project can be found in Table 19-4. The presentation is on a 100% Arctic Project ownership basis. Trilogy holds 50% interest in Ambler Metals.

  
Arctic ProjectPage 384
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Table 19-4:Pre and Post-Tax Arctic Project Production and Cashflow Forecast

 

Arctic Project  Units  LOM   Year
-3
   Year
-2
   Year
-1
   Year
1
   Year
2
   Year
3
   Year
4
   Year
5
   Year
6
   Year
7
   Year
8
   Year
9
   Year
10
   Year
11
   Year
12
   Year
13
   Year
14
 
Mill Feed  ktonnes  46,691    -   -   -   3,012   3,650   3,650   3,650   3,650   3,650   3,650   3,651   3,650   3,650   3,650   3,650   3,529   - 
Cu  %  2.11    -   -   -   3.32   2.18   1.94   1.88   1.87   1.99   2.37   2.00   2.05   2.33   2.41   1.98   2.09   - 
Zn  %  2.90    -   -   -   3.62   2.59   2.61   2.82   2.86   2.51   3.11   3.07   2.51   3.09   3.41   3.15   3.20   - 
Pb  %  0.56    -   -   -   0.75   0.46   0.56   0.58   0.53   0.49   0.57   0.61   0.39   0.53   0.64   0.66   0.69   - 
Au  %  0.42    -   -   -   0.43   0.31   0.39   0.42   0.33   0.34   0.40   0.44   0.37   0.50   0.56   0.47   0.52   - 
Ag  %  31.83    -   -   -   39.30   29.44   28.42   28.03   26.36   28.66   31.75   32.44   28.50   36.80   38.68   34.08   38.39   - 
Concentrate                                                               
Cu Concentrate  ktonnes  2,995    -   -   -   232.4   227.7   223.4   213.4   210.7   221.9   258.0   219.9   226.8   252.4   265.3   221.9   221.2   - 
Cu Recovery  %  92.1    -   -   -   92.1   92.1   92.1   92.1   92.1   92.1   92.1   92.1   92.1   92.1   92.1   92.1   92.1   - 
Cu Concentrate Grade  %  30.3    -   -   -   30.3   30.3   30.3   30.3   30.3   30.3   30.3   30.3   30.3   30.3   30.3   30.3   30.3   - 
Cu Payable  %  96.5    -   -   -   96.5   96.5   96.5   96.5   96.5   96.5   96.5   96.5   96.5   96.5   96.5   96.5   96.5   - 
Ag Concentrate Grade  g/t  161    -   -   -   161.3   161.3   161.3   161.3   161.3   161.3   161.3   161.3   161.3   161.3   161.3   161.3   161.3   - 
Ag Payable  %  90.0    -   -   -   90.0   90.0   90.0   90.0   90.0   90.0   90.0   90.0   90.0   90.0   90.0   90.0   90.0   - 
Zn Concentrate  ktonnes  2,228    -   -   -   142.2   149.8   156.6   169.7   172.6   152.1   186.0   184.9   151.3   184.8   203.3   189.4   185.7   - 
Zn Recovery  %  88.5    -   -   -   88.5   88.5   88.5   88.5   88.5   88.5   88.5   88.5   88.5   88.5   88.5   88.5   88.5   - 
Zn Concentrate Grade  %  53.7    -   -   -   53.7   53.7   53.7   53.7   53.7   53.7   53.7   53.7   53.7   53.7   53.7   53.7   53.7   - 
Zn Payable in Concentrate  %  85.0    -   -   -   85.0   85.0   85.0   85.0   85.0   85.0   85.0   85.0   85.0   85.0   85.0   85.0   85.0   - 
Pb Concentrate  ktonnes  298    -   -   -   19.7   21.3   23.3   23.5   21.7   20.8   24.1   24.4   17.7   22.7   26.4   26.2   26.4   - 
Pb Recovery  %  61.3    -   -   -   61.3   61.3   61.3   61.3   61.3   61.3   61.3   61.3   61.3   61.3   61.3   61.3   61.3   - 
Pb Concentrate Grade  %  53.9    -   -   -   53.9   53.9   53.9   53.9   53.9   53.9   53.9   53.9   53.9   53.9   53.9   53.9   53.9   - 
Pb Payable  %  95.0    -   -   -   95.0   95.0   95.0   95.0   95.0   95.0   95.0   95.0   95.0   95.0   95.0   95.0   95.0   - 
Ag Concentrate Grade  g/t  2,424    -   -   -   2,424   2,424   2,424   2,424   2,424   2,424   2,424   2,424   2,424   2,424   2,424   2,424   2,424   - 
Ag Payable  %  95.0    -   -   -   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   - 
Au Concentrate Grade  g/t  14    -   -   -   14.2   14.2   14.2   14.2   14.2   14.2   14.2   14.2   14.2   14.2   14.2   14.2   14.2     
Au Payable  %  95.0    -   -   -   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   95.00   - 
Payable Metal                                                               
Payable Cu  (‘000’lb)  1,932,882    -   -   -   151,175   146,013   142,583   137,387   134,852   141,803   167,411   142,499   143,517   163,112   173,249   144,427   144,855   - 
Payable Zn  (‘000’lb)  2,243,771    -   -   -   143,256   149,381   156,519   170,411   173,700   151,480   188,011   186,782   150,724   186,729   206,931   191,688   188,157   - 
Payable Pb  (‘000’lb)  334,785    -   -   -   21,068   23,396   26,443   27,266   24,590   22,721   26,400   28,209   18,325   24,684   29,618   30,845   31,220   - 

  
Arctic ProjectPage 385
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Arctic
Project
  Units  LOM   Year
-3
   Year
-2
   Year
-1
   Year
1
   Year
2
   Year
3
   Year
4
   Year
5
   Year
6
   Year
7
   Year
8
   Year
9
   Year
10
   Year
11
   Year
12
   Year
13
   Year
14
 
Payable Au   (‘000’oz)   423       -     -     -     22     29     31     34     26     26     30     34     28     38     45     38     40     -  
Payable Ag   (‘000’oz)   36,047       -     -     -     2,362     2,530     2,593     2,541     2,355     2,512     2,755     2,877     2,446     3,179     3,449     3,112     3,336     -  
Recovered Metal Value                                                                                                                  
Recovered Metal Value   $ M   11,424.9       -     -     -     824.2     828.9     833.0     833.8     809.4     810.3     961.8     880.4     813.4     964.6     1,046.7     906.2     912.2     -  
Off-Site Charges       -                                                                                                          
Royalties, Insurance, Marketing and Representation Fees, Refining, Treatment, Concentrate Transport, and Penalties   $ M   2,969.1       -     -     -     210.2     213.4     216.9     219.4     217.8     211.4     250.8     232.1     210.8     246.8     266.8     237.3     235.4     -  
Capital Costs                                                                                                                  
Mining   $ M   314.2       97.0     111.5     88.2     0.1     -     -     1.5     -     0.8     0.8     0.2     8.9     1.9     0.3     3.0     -     -  
Crushing   $ M   42.5       -     14.2     28.4     -     -     -     -     -     -     -     -     -     -     -     -     -     -  
Processing   $ M   159.3       -     79.5     78.5     -     -     0.2     0.2     0.2     0.2     0.2     0.2     0.2     -     -     -     -     -  
Tailings   $ M   120.7       -     38.4     49.9     7.9     -     2.7     8.2     -     1.2     12.4     -     -     -     -     -     -     -  
On-Site Infrastructure   $ M   207.9       19.0     61.7     92.1     -     -     -     -     -     -     -     -     -     17.5     17.5     -     -     -  
Off-Site Infrastructure   $ M   75.8       20.1     31.1     24.6     -     -     -     -     -     -     -     -     -     -     -     -     -     -  
Indirects   $ M   192.5       60.9     62.9     53.5     -     -     -     -     -     -     -     -     -     7.6     7.6     -     -     -  
Owner’s Cost   $ M   26.8       7.9     9.4     9.4     -     -     -     -     -     -     -     -     -     -     -     -     -     -  
Mine Closure   $ M   428.4       -     -     -     -     -     -     -     -     -     -     -     -     -     -     -     -     428.4  
Contingency   $ M   151.5       23.5     69.1     46.0     -     -     -     -     -     -     -     -     -     6.5     6.5     -     -     -  
Total Capital Costs   $ M   1,719.6       234.4     473.2     469.2     8.0     -     2.8     9.9     0.2     2.1     13.4     0.4     9.1     33.5     31.9     3.0     -     428.4  
Operating Costs                                                                                                                  
Mining   LOM - $/t mined   22.49       -     -     -     31.71     24.92     25.08     25.20     23.30     25.59     23.36     22.62     23.36     20.75     18.84     17.67     11.19     -  
   $ M   1,050.0       -     -     -     95.5     91.0     91.5     92.0     85.1     93.4     85.2     82.6     85.3     75.7     68.8     64.5     39.5     -    
Processing   LOM - $/t milled   22.60       -     -     -     23.91     22.33     22.50     22.50     22.50     22.50     22.50     22.50     22.50     22.50     22.50     22.50     22.77     -  
  $ M    1,055.2       -     -     -     72.0     81.5     82.1     82.1     82.1     82.1     82.1     82.1     82.1     82.1     82.1     82.1     80.3     -  
Water Treatment   LOM - $/t milled   1.17       -     -     -     1.40     1.15     1.15     1.15     1.15     1.15     1.15     1.15     1.15     1.15     1.15     1.15     1.19     -  
  $ M    54.7       -     -     -     4.2     4.2     4.2     4.2     4.2     4.2     4.2     4.2     4.2     4.2     4.2     4.2     4.2     -  
G&A   LOM - $/t milled   5.85       -     -     -     6.97     5.75     5.75     5.75     5.75     5.75     5.75     5.75     5.75     5.75     5.75     5.75     5.95     -  
  $ M    273.0       -     -     -     21.0     21.0     21.0     21.0     21.0     21.0     21.0     21.0     21.0     21.0     21.0     21.0     21.0     -  
Road Toll   LOM - $/t milled   7.72       -     -     -     3.03     2.50     8.53     8.53     8.53     8.53     8.53     8.53     8.53     8.53     8.53     8.53     8.82     -  
    $ M    360.6       -     -     -     9.1     9.1     31.1     31.1     31.1     31.1     31.1     31.1     31.1     31.1     31.1     31.1     31.1     -  

  
Arctic ProjectPage 386
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Arctic Project  Units  LOM   Year
-3
   Year
-2
   Year
-1
   Year
1
   Year
2
   Year
3
   Year
4
   Year
5
   Year
6
   Year
7
   Year
8
   Year
9
   Year
10
   Year
11
   Year
12
   Year
13
   Year
14
 
Total Operating Costs   LOM - $/t milled   59.83     -     -     -     67.02     56.65     63.02     63.14     61.24     63.52     61.29     60.56     61.30     58.69     56.78     55.61     49.92     -  
  $ M    2,793.6     -     -     -     201.8     206.8     230.0     230.5     223.5     231.9     223.7     221.1     223.7     214.2     207.3     203.0     176.1     -  
Undiscounted Pre-Tax Cash Flow   $ M   3,942.6     (234.4 )   (473.2 )   (469.2 )   404.3     408.7     383.3     374.1     367.9     364.9     473.8     426.9     369.7     470.1     540.7     462.9     500.6     (428.4 )
Discounted Pre-Tax Cash Flow at 8% Discount Rate   $ M   1,500.3     (217.0 )   (405.7 )   (372.4 )   297.1     278.1     241.5     218.3     198.8     182.5     219.5     183.1     146.8     172.8     184.1     145.9     146.1     (115.8 )
Income Tax   $ M   -922.7     -     -     -     -10.4     -11.3     -30.0     -61.2     -64.6     -67.7     -106.4     -90.5     -76.6     -112.6     -132.3     -101.2     -57.9     -  
Undiscounted Post-Tax Cash Flow   $ M   3,019.9     -234.4     -473.2     -469.2     393.8     397.3     353.3     312.9     303.3     297.2     367.5     336.5     293.0     357.5     408.4     361.7     442.7     -428.4  
Discounted Post-Tax Cash Flow at 8% Discount Rate   $ M   1,108.1     -217.0     -405.7     -372.4     289.5     270.4     222.6     182.6     163.9     148.6     170.2     144.3     116.4     131.5     139.0     114.0     129.2     -115.8  

  
Arctic ProjectPage 387
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

19.6Sensitivity Analysis

 

Ausenco investigated the sensitivity of the Arctic Project’s pre-tax NPV, and IRR to several project variables. The following variables were elected for this analysis:

 

Copper price

 

Zinc price

 

Lead price

 

Gold price

 

Silver price

 

Capital costs

 

On-site operating costs

 

Off-site operating costs (royalties, refining and treatment charges, penalties, insurance, marketing, and representation fees, and concentrate transportation).

 

Each variable was changed in increments of 10% between -20% to +20% while holding all other variables constant. Figure 19-1, Figure 19-2 and Table 19-5 show the results of the pre-tax sensitivity analysis.

 

The metal grade is not presented in these sensitivity graphs because the impacts of changes to metal grade mirror those of metal prices.

  
Arctic ProjectPage 388
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Table 19-5: Pre-Tax Sensitivity Summary

 

Pre-Tax Sensitivity Tables 
Pre-Tax NPV Sensitivity To On-Site Opex    Pre-Tax IRR Sensitivity To On-Site Opex 
 On-Site Opex    Commodity Price    On-Site Opex    Commodity Price 
$1,500    (20.0)%   (10.0)%   --    10.0%   20.0%   26%   (20.0)%   (10.0)%   --    10.0%   20.0%
 (20.0)%  $693   $1,233   $1,773   $2,314   $2,854    (20.0)%   17.4%   23.2%   28.4%   33.1%   37.5%
 (10.0)%  $556   $1,097   $1,637   $2,177   $2,717    (10.0)%   15.8%   21.8%   27.1%   31.9%   36.4%
 --   $420   $960   $1,500   $2,041   $2,581    --    14.1%   20.4%   25.8%   30.7%   35.2%
 10.0%  $283   $824   $1,364   $1,904   $2,444    10.0%   12.2%   18.8%   24.4%   29.5%   34.1%
 20.0%  $147   $687   $1,227   $1,767   $2,308    20.0%   10.3%   17.3%   23.1%   28.2%   32.9%

 

Pre-Tax NPV Sensitivity To Off-Site Opex    Pre-Tax IRR Sensitivity To Off-Site Opex 
 Off-Site Opex    Commodity Price    Off-Site Opex    Commodity Price 
$1,500    (20.0)%   (10.0)%   --    10.0%   20.0%   26%   (20.0)%   (10.0)%   --    10.0%   20.0%
 (20.0)%  $702   $1,243   $1,784   $2,326   $2,867    (20.0)%   17.5%   23.3%   28.4%   33.1%   37.5%
 (10.0)%  $561   $1,102   $1,642   $2,183   $2,724    (10.0)%   15.8%   21.8%   27.1%   31.9%   36.4%
 --   $420   $960   $1,500   $2,041   $2,581    --    14.1%   20.4%   25.8%   30.7%   35.2%
 10.0%  $279   $819   $1,358   $1,898   $2,437    10.0%   12.2%   18.8%   24.4%   29.4%   34.1%
 20.0%  $138   $677   $1,216   $1,755   $2,294    20.0%   10.2%   17.2%   23.0%   28.2%   32.9%

 

Pre-Tax NPV Sensitivity To Initial Capex    Pre-Tax IRR Sensitivity To Initial Capex 
 Initial Capex    Commodity Price    Initial Capex    Commodity Price 
$1,500    (20.0)%   (10.0)%   --    10.0%   20.0%   26%   (20.0)%   (10.0)%   --    10.0%   20.0%
 (20.0)%  $623   $1,163   $1,703   $2,243   $2,784    (20.0)%   18.5%   25.5%   31.6%   37.2%   42.3%
 (10.0)%  $521   $1,062   $1,602   $2,142   $2,682    (10.0)%   16.1%   22.7%   28.5%   33.6%   38.5%
 --   $420   $960   $1,500   $2,041   $2,581    --    14.1%   20.4%   25.8%   30.7%   35.2%
 10.0%  $318   $859   $1,399   $1,939   $2,479    10.0%   12.3%   18.3%   23.5%   28.2%   32.5%
 20.0%  $217   $757   $1,297   $1,838   $2,378    20.0%   10.8%   16.6%   21.5%   26.0%   30.1%

 

Source: Ausenco, 2022.

 

  
Arctic ProjectPage 389
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

  

   
   

  

Figure 19-1: Pre-Tax NPV Sensitivity Analysis

 

 

 

Source: Ausenco, 2022.

 

As shown in Figure 19-1, the Arctic Project’s NPV at 8% discount rate is most sensitive to changes in copper price, followed by off-site operating costs, on-site operating costs, zinc price, capital costs, silver price, gold price and lead price. On-site operating costs follow closely the off-site operating costs.

  
Arctic ProjectPage 390
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 19-2: Pre-Tax IRR Sensitivity Analysis

 

 

Source: Ausenco, 2022.

 

As shown in Figure 19-2 the Arctic Project’s IRR is most sensitive to changes in copper price and capital cost, followed by off-site operating costs and on-site operating costs, and in then decreasing order, zinc price, silver price, gold price, and lead price. On-site operating costs follow closely the off-site operating costs.

  
Arctic ProjectPage 391
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

Table 19-6 shows the results of the post-tax sensitivity analysis.

 

Table 19-6: Post-Tax Sensitivity Summary

 

Post-Tax Sensitivity Tables

 

Post-Tax NPV Sensitivity To On-Site Opex   Post-Tax IRR Sensitivity To On-Site Opex 
On-Site Opex   Commodity Price   On-Site Opex   Commodity Price 
$1,108    (20.0)%   (10.0)%   --    10.0%   20.0%   23%   (20.0)%   (10.0)%   --    10.0%   20.0%
 (20.0)%  $481   $897   $1,297   $1,690   $2,082    (20.0)%   15.3%   20.5%   24.9%   29.0%   32.7%
 (10.0)%  $376   $797   $1,204   $1,598   $1,990    (10.0)%   13.8%   19.3%   23.9%   28.0%   31.8%
 --   $269   $695   $1,108   $1,506   $1,899    --    12.3%   18.0%   22.8%   27.1%   30.9%
 10.0%  $161   $591   $1,009   $1,413   $1,807    10.0%   10.6%   16.6%   21.7%   26.1%   30.0%
 20.0%  $51   $485   $907   $1,318   $1,714    20.0%   8.9%   15.2%   20.5%   25.1%   29.1%

 

Post-Tax NPV Sensitivity To Off-Site Opex    Post-Tax IRR Sensitivity To Off-Site Opex 
Off-Site Opex   Commodity Price    Off-Site Opex    Commodity Price 
$1,108    (20.0)%   (10.0)%   --    10.0%   20.0%   23%   (20.0)%   (10.0)%   --    10.0%   20.0%
 (20.0)%  $496   $916   $1,318   $1,713   $2,107    (20.0)%   15.4%   20.6%   25.1%   29.1%   32.9%
 (10.0)%  $383   $805   $1,214   $1,609   $2,003    (10.0)%   13.9%   19.3%   24.0%   28.1%   31.9%
 --   $269   $695   $1,108   $1,506   $1,899    --    12.3%   18.0%   22.8%   27.1%   30.9%
 10.0%  $155   $583   $999   $1,402   $1,795    10.0%   10.5%   16.6%   21.6%   26.0%   29.9%
 20.0%  $40   $470   $889   $1,297   $1,691    20.0%   8.7%   15.1%   20.3%   24.9%   28.9%

 

Post-Tax NPV Sensitivity To Initial Capex    Post-Tax IRR Sensitivity To Initial Capex  
Initial Capex   Commodity Price    Initial Capex   Commodity Price 
$1,108    (20.0)%   (10.0)%   --    10.0%   20.0%   23%   (20.0)%   (10.0)%   --    10.0%   20.0%
 (20.0)%  $448   $869   $1,278   $1,672   $2,064    (20.0)%   16.4%   22.7%   28.1%   32.9%   37.3%
 (10.0)%  $359   $782   $1,193   $1,589   $1,981    (10.0)%   14.2%   20.1%   25.3%   29.7%   33.8%
 --   $269   $695   $1,108   $1,506   $1,899    --    12.3%   18.0%   22.8%   27.1%   30.9%
 10.0%  $179   $607   $1,022   $1,422   $1,816    10.0%   10.6%   16.1%   20.8%   24.8%   28.5%
 20.0%  $88   $518   $936   $1,338   $1,733    20.0%   9.2%   14.5%   18.9%   22.8%   26.3%

Source: Ausenco, 2022.

 

  
Arctic ProjectPage 392
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

20ADJACENT PROPERTIES

 

This section is not relevant to this report.

  
Arctic ProjectPage 393
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

21OTHER RELEVANT DATA AND INFORMATION

 

21.1Project Execution Plan

 

Key considerations for the execution of the Arctic Project are as noted below.

 

21.1.1Constraints and Interfaces

 

The Arctic Project will be an integrated development with several consultants contributing to the overall design process. Specialist contractors will most likely be engaged for specific packages, such as the Arctic access road, and the construction camps, generally on a “design and construct” basis.

 

It is essential that these parties work together to ensure data being used is both current and meaningful. Data transfer between parties shall be strictly controlled and in accordance with Document Control protocols.

 

The early design interfaces for the Arctic Project will include at least:

 

Mine development

 

Waste Rock placement and Tails Dam

 

Water management and treatment

 

Arctic Access Road design and construction, in particular the pioneer road necessary to allow earliest possible access to the Mine pre-assembly construction site

 

Bornite, Construction and Permanent Camps.

 

The Interface Management procedures will be developed to ensure services at the battery limits are clearly defined and understood by all parties affected.

 

21.1.2Key Project Milestones

 

Key project milestones will be developed once the Arctic Project is committed to construction and the required permits are in hand.

 

The mine requires nominally two years of pre-strip operations, tailings pond starter dam development and water accumulation before actual production mining operations can commence.

 

For that pre-strip work to start, the Arctic access road from the AAP intersection to the mine site will have to be constructed to at least a pioneer road condition that will allow the mine fleet and the support facilities to be delivered, built and made operational.

 

Tailings pond construction must be to a height to allow natural collection of water in quantities that will allow plant operations to commence.

  
Arctic ProjectPage 394
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Figure 21-1 shows a project execution schedule that covers key milestones and activities in the 3-year construction period.

 

Figure 21-1:        Project Execution Schedule

 

 

 

Source: Ausenco, 2022.

 

  
Arctic ProjectPage 395
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

  

21.1.3Proven Technology

 

The Arctic Project will utilize proven technology and equipment that can be built, operated and maintained under adverse weather conditions.

 

The Design Criteria, Technical Specifications and Data sheets shall reflect the location, the environmental and initial logistics constraints that may affect the procurement and construction effort.

 

21.1.4Engineering, Procurement and Construction Management Approach

 

Two EPCM strategies have been identified that are structured to account for the abnormally long pre-strip mining operation. The first option is the basis for the capital and operating cost estimate.

 

21.1.4.1Early Engineering Only with 2-Stage Procurement

 

There is a need to establish the mine facilities and assemble the Mine Fleet in time to allow the pre-strip operation to start some two years before the Process Plant receives its first ore. This means that there will be a significant amount of detailed engineering requiring completion well in advance of the time required for conventional engineering, procurement, and construction of just the process plant and supporting infrastructure. This has been assessed as requiring detailed engineering to start some four years before the process plant starts production.

 

In particular, the pioneer access road design and contracts and civil design for the Mine Support facilities will be required early in the schedule. By default, the rest of the civil design would need to attach to that early works for simple plant layout and construction coordination purposes. For that to occur the plant layout will be required to be established at an early stage. That in turn is dependent on sizing and selection of the major process equipment items and the receipt of vendor data to complete the plant layout.

 

Effectively, the detailed design phase will need to follow the conventional approach and run its course but started at a time that meets the early works schedule requirements. Everything other than the mine support facilities will be designed some two years in advance of when it is needed.

 

With the early equipment order placement, the supply phase could become inordinately long, extending over three years in most cases, when in fact the equipment is not likely to be needed until the last eighteen months prior to plant start-up.

 

An unorthodox but proven option to this extended design, supply and construction schedule is to have the EPCM Contractor procure the major equipment in two steps:

 

Step 1: Procure only the vendor certified engineering data to allow detailed engineering to continue to completion but hold the manufacturing functions until later in the overall schedule, effectively a delay of around twelve to fifteen months.

 

Step 2: Based on agreed vendor manufacturing durations, apply a “late” release of the equipment for manufacture with deliveries effectively becoming a “Just-in Time” logistics operation.

 

This strategy provides the following advantages:

 

Engineering can start and continue to completion using critical vendor data without the need for an extended “standby” involvement.

  
Arctic ProjectPage 396
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Procurement functions can work in parallel with the engineering group with no disconnect between the two disciplines.

 

The procurement team can generally disband early in the schedule with just key personnel retained to provide continuity of support.

 

The expediting team can mobilise later in the schedule to drive manufacture and delivery in a concerted campaign.

 

Equipment deliveries can be orchestrated to suit the conditions at the time with everything consolidated into a transit compound for coordinated shipping to site.

 

Reduced cashflow demands.

 

Potential issues to be mitigated with this approach are:

 

The vendors need to be clearly briefed as to their manufacturing and delivery schedule.

 

A payments formula needs to be in place to account for a delayed delivery strategy.

 

Some vendors have difficulty in determining just what their actual engineering costs are.

 

21.1.4.2Early EPCM Leading to Plant Care and Maintenance

 

Under this approach, the EPCM would work to conventional design and construction schedule, starting to suit the Mine access requirements but following on to completion without interruption. That would bring the total process plant and supporting infrastructure to a mechanical completion condition nominally twelve to fifteen months before it is able to start work.

 

The plant could not be commissioned through lack of ore and would have to be placed into care and maintenance mode until ore became available. This has an inherent advantage in that if the pre-strip operation was completed earlier than scheduled, and sufficient water is accumulated, the plant operations would be able to take advantage of the fact the plant was already mechanically complete. The care and maintenance requirements in that environment for that duration will require close assessment. 

  
Arctic ProjectPage 397
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

22INTERPRETATIONS AND CONCLUSIONS

 

22.1Introduction

 

The QPs note the following interpretations and conclusions in their respective areas of expertise, based on the review of data available for this Report. The level of study was completed to a minimum of a PFS under the standards and definitions of S-K 1300.

 

22.2Mineral Tenure, Surface Rights, Royalties and Agreements

 

Information from legal experts supports that the mining tenure held is valid and is sufficient to support declaration of Mineral Resources and Mineral Reserves.

 

Kennecott holds a 1% NSR royalty that is purchasable at any time for a one-time payment of $10 million. This royalty covers the patented federal mining claims and many, but not all, of the State mining claims.

 

The NANA Agreement between NovaCopper US and NANA, assigned to Ambler Metals in 2020, granted certain rights, for consideration, which include an exclusive right to explore for minerals and a nonexclusive right to enter upon and use certain NANA lands for various purposes including access to NovaCopper’s Ambler mining properties. The NANA Agreement further provides that if NovaCopper completes a Feasibility Study and a Draft Environmental Impact Statement for a project to develop the Ambler properties, NANA will become entitled elect to purchase an interest in the Arctic Project by exercising a back-in right to acquire an undivided interest of between 16% and 25% (at NANA’s option) of the mining project. If this back-in right were to be exercised by NANA the two parties would form a Joint Venture to proceed with the Arctic Project. The Joint Venture would lease the mining properties from NovaCopper US Inc. in exchange for a 1% NSR royalty and NANA would enter into a surface use agreement with the Joint Venture in exchange for a 1% NSR royalty. In the alternative, should NANA elect not to exercise this back-in right, the Joint Venture would not be formed, and NANA would instead become entitled to a 15% net proceeds royalty. As noted above, this agreement has been assigned to Ambler Metals.

 

The owner of a State mining claim or lease will be obligated to pay a production royalty to the State of Alaska in the amount of 3% of net income received from minerals produced from the State mining claims. The Arctic Project is not on State lands; thus, the State of Alaska production royalty is not applicable.

 

22.3Geology and Mineralization

 

The Arctic deposit is considered to be an example of a VMS system.

 

Knowledge of the deposit settings, lithologies, mineralization style and setting, and structural and alteration controls on mineralization is sufficient to support Mineral Resource and Mineral Reserve estimation.

 

22.4Exploration, Drilling and Analytical Data Collection in Support of Mineral Resource Estimation

 

The quantity and quality of the lithological, geotechnical, collar and downhole survey data collected in the exploration and infill drill programs conducted is sufficient to support Mineral Resource and Mineral Reserve estimation.

  
Arctic ProjectPage 398
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Analytical and density data are suitable to support Mineral Resource and Mineral Reserve estimation.

 

NovaGold, Trilogy and Ambler Metals sample security procedures met industry standards. Current sample storage procedures and storage areas are consistent with industry standards.

 

Data collected have been sufficiently verified that they can support Mineral Resource and Mineral Reserve estimation and be used for mine planning purposes.

 

22.5Metallurgical Testwork

 

Metallurgical studies have spanned over 30 years.

 

Testwork conducted prior to 2012 is considered relevant to the Arctic Project, but predictive metallurgical results are considered to be best estimated from testwork conducted on sample materials obtained from exploration work under the direction of Trilogy conducted in 2012 and 2017 and Ambler Metals conducted in 2021.

 

To the extent known, the metallurgical samples are representative of the styles and types of mineralization and the mineral deposit as a whole.

 

Concentrate quality test results indicated that key penalty elements, as well as precious metals are typically concentrated into a lead concentrate, leaving the copper concentrate of higher-than-expected quality given the levels of impurities seen in the test samples. The lead concentrate may have penalties for the high arsenic and antimony concentrations seen in the results of this testwork. Precious metal deportment into a lead concentrate is very high and should benefit the payable levels of precious metals at a smelter. Silicon dioxide and fluoride assays should be conducted on the concentrates to determine whether or not they are higher than the penalty thresholds.

 

Talc will be managed through a pre-flotation step to minimize reporting to the metal concentrates.

 

In general, the flowsheet developed in the 2012 test program and further tested in the 2017 and 2021 testwork programs at ALS Metallurgy is feasible for the Arctic deposit mineralization. Further geometallurgical testwork is recommended to confirm and optimize the flowsheet. There are no outstanding metallurgical issues related to the production of a copper or zinc concentrate from all of the materials tested.

 

22.6Mineral Resource Estimates

 

Mineral Resources have been prepared using industry-standard methods and software.

 

Mineral Resources have had reasonable prospects of economic extraction considerations applied and assume an open pit mining method.

 

Mineral Resources were prepared in accordance with the standards and definitions of S-K 1300.

 

Factors that may affect the Mineral Resource estimate include: metal price assumptions; changes to the assumptions used to generate the CuEq cut-off grade that constrains the estimate; changes in local interpretations of mineralization geometry and continuity of mineralized zones; changes to geological and mineralization shapes and volumes; geological and grade continuity assumptions; geological and structural complexity assumptions; density and domain assignments; changes to the predicted SG values; changes to the Mineral Resource estimation parameters for the payable and deleterious metals; changes to geotechnical, mining, and metallurgical recovery assumptions; changes to the input and design parameter assumptions that pertain to the conceptual pit constraining the estimates; assumptions as to concentrate marketability, payability and penalty terms; assumptions as to the continued ability to access the site, retain mineral tenure and obtain surface rights titles, obtain environment and other regulatory permits, and maintain the social license to operate; assumptions as to future site access.

  
Arctic ProjectPage 399
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Wood’s QP recommends the followings tasks completed for the next model update:

 

Review identified issues in the current database and update the database

 

Review identified issues in the current geology model wireframes and update using the 2021 and 2022 drilling results.

 

Review identified issues in the current talc model wireframes and update using the 2021 and 2022 drilling results.

 

Investigate the predicted SG values in the current SG database that were generated by the Random Forest Regressor machine learning method. This is to mitigate the apparent bias identified in the predicted SG values. Use all available measured SG data collected to update the SG model.

 

Investigate and update the historical assay values that shows apparent bias.

 

Update variogram models for the payable and deleterious metals, and SG used in the current models by using all the available data including the 2021 and 2022 drilling results.

 

Review and update the resource estimation parameters for the payable and deleterious metals, and SG.

 

Plan for a tight drilling within the first 5-year pit production area to better understand the complexity of the deposit geology and provide higher confidence during the payback period.

 

22.7Mineral Reserve Estimates

 

The 2022 mine plan is based on Probable Mineral Reserves resulting from modifying factors being applied to a subset of the Indicated Mineral Resource estimates.

 

Mineral Reserves were prepared in accordance with the standards and definitions of S-K 1300.

 

Risks that may affect the Mineral Reserve estimates include: metal price assumptions; changes to the assumptions used to generate the NSR cut-offs that constrains the estimate; changes in local interpretations of mineralization geometry and continuity of mineralized zones; changes to geological and mineralization shapes, and geological and grade continuity assumptions; density and domain assignments; changes to geotechnical and hydrological assumptions, changes to mining and metallurgical recovery assumptions; changes to the input and design parameter assumptions that pertain to the conceptual pit constraining the estimates; assumptions as to concentrate marketability, payability and penalty terms; assumptions as to the continued ability to access the site, retain mineral tenure and obtain surface rights titles, obtain environment and other regulatory permits, and maintain the social license to operate.

 

There is a risk to the estimate if the AMDIAP road is not constructed, or in the time frame envisaged, or that the toll charges assumed in this Report are not the final charges levied.

 

The northeast wall has been forced to fully mine the talc zones, which has pushed the wall, increased the footprint of the pit, and added waste material to mine plan. Any change to the talc shapes can modify the pit design, and therefore, the amount of material mined. Talc horizons that may not have been included in the geological model could affect slope stability and recoveries in the process plant and therefore could be a risk to the Mineral Reserves.

  
Arctic ProjectPage 400
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

22.8Mining Recovery

 

Wood selected conventional open-pit mining because of the deposit’s geometry and proximity to surface. The deposit will be mined in four nested phases, including the ultimate pit limit.

 

An Owner-operated and maintained conventional truck–shovel operation was specified, with outside service providers supporting mine operations.

 

The planned open pit will operate for 13 years, and an additional two years of pre-production.

 

Proper management of groundwater will be important to maintaining pit slope stability; the east wall is highly sensitive to several geotechnical parameters, and talc horizons that may not have been included in the geological model might also affect its stability.

 

22.9Recovery Methods

 

Recovery is planned using a conventional crushing, grinding and flotation circuit to produce metal concentrates. A 10,000 t/d throughput rate is envisaged, with an overall plant availability of 92%.

 

The process plant will produce three concentrates: 1) copper concentrate, 2) zinc concentrate, and 3)lead concentrate. Gold and silver are expected to be payable at a smelter; silver is expected to be payable in the copper and lead concentrates, with gold expected to be payable in the lead concentrate only.

 

While there are deleterious elements reporting to the concentrates at levels which would incur penalties, such as talc at 2.92% in the feed to the plant, special processing provisions have been included in the flowsheet to make a readily saleable concentrate.

 

22.10Infrastructure

 

The planned mine will be a greenfield site and require construction of camp, mine and process-related infrastructure. Access roads in and around the project site will be required.

 

Site access assumes that the AAP road will be constructed.

 

Power generation will be provided by four diesel generators.

 

Process water will be supplied from the Process Pond, TMF reclaim, and WRCP. TMF dewatering must start towards the end of operations to prevent the TMF from exceeding the maximum storage capacity. Stormwater will be managed within the Arctic Project boundaries by capturing and conveying contact and impacted water for treatment and diverting non-contact water away from developed areas. Well water will be used for potable purposes.

  
Arctic ProjectPage 401
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

A single WTP, built in stages, will be used. During the operations phase, the WTP will treat effluent from the WRCP, and during Closure phase effluent from the pit. The WTP will initially consist of chemical/physical treatment with RO. In the Operations phase, when the TMF is in use, the RO reject will be sent to the TMF, and only RO permeate will be discharged to the Creek. When the TMF is closed at the end of the Operations phase, a biological/chemical/physical plant will be added to treat the RO reject so that it can be mixed with the RO permeate and discharged.

 

The TMF will be a thickened tailings facility. The maximum storage capacity of the facility will be approximately 40.7 Mm³ (tailings and process water) plus an additional 2.5 m of freeboard. The 59 ha footprint of the TMF will be fully lined with a geomembrane liner. Three dam raises will be completed.

 

22.11Environmental, Permitting and Social

 

To date, a moderate amount of baseline environmental data collection has occurred in the area including surface water quality sampling, surface hydrology monitoring, wetlands mapping, stream flow monitoring, aquatic life surveys, avian and mammal habitat surveys, cultural resource surveys, hydrogeology studies, meteorological monitoring, and ML/ARD studies.

 

The Arctic Project will be subject to a mine permitting process typical for a mine of its size in Alaska. In order to support this process, Trilogy will have to broaden their existing baseline environmental program and complete a number of studies that will support the permit applications.

 

The Arctic Project is dependent on obtaining an APDES permit to discharge water that meets Alaska Water Quality Standards..

 

Ambler Metals has formally started engaging the Arctic Project stakeholders and recognizes the need to earn their trust and support by making the Arctic Project directly beneficial to them throughout the Arctic Project life and closure/post-closure periods.

 

Trilogy will be required to develop a Mine Reclamation and Closure Plan that is protective of the environment during mining operations as well as reclamation and closure.

 

Closure activities will be undertaken at the end of mine life to bring the mine facilities in a state consistent with the stated closure and post-closure objectives and compliant with the regulations for closure and abandonment.

 

22.12Market Studies and Contracts

 

Metal pricing was provided by Trilogy, guided by long-term price forecasts from analysts as published by CIBC.

 

The long-term consensus metal price assumptions selected for the economic analysis in this Report were:

 

Copper: $3.65/lb

 

Zinc: $1.15/lb

 

Lead: $1.00/lb

 

Gold: $1,650/oz

 

Silver: $21.00/oz

  
Arctic ProjectPage 402
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

A marketing review for the three Arctic concentrates was conducted by StoneHouse Consulting in January 2023 based on the expected concentrate assays as provided by Trilogy.

 

The three Arctic concentrates – copper, zinc and lead – will need to be marketed differently but will likely be sold within the Asia Pacific area.

 

The copper concentrate is relatively high grade with low penalty impurities. The quality can be sold directly into China, Japan or Korea, and therefore will have the advantage of the most competitive terms. There is payable silver content, and potential penalties for zinc, lead and antimony will be low. The copper concentrate contains arsenic and selenium levels that are close to the threshold for allowable import into China. Overall, this is a good quality concentrate with few elements for which a penalty can be applied.

 

The zinc concentrate has a cadmium content that is above the current import limit set by the Chinese government so at this time cannot be sold into China. The obvious markets for this quality would be to smelters in Korea, Japan, Australia and Canada. The concentrate contains high grade zinc with relatively low iron. As the market is currently long in high silica and high manganese concentrates, this quality will be a welcome feed to blend down those impurities. Not all smelters will fully value a high zinc grade material as it is expensive per unit of zinc, so sales will need to be spread among several smelters.

 

The lead concentrate contains most of the payable gold and silver from the Arctic deposit. Unfortunately, the impurities, in particular fluorine and selenium, will limit the number of smelters interested in this concentrate, regardless of the smelter’s capacity to recover precious metals. The best strategy is to sell the concentrate to trading companies who can blend with other lead concentrate containing low silver and selenium. In this way, the silver gets diluted and the selenium gets reduced to an acceptable level. It is recommended that a study be conducted to confirm marketability of this product. Smelters should be consulted so that Trilogy can get some direction as to whether the elevated levels of fluorine and selenium can be managed.

 

22.13Capital Costs

 

Total capital costs are estimated at $1,291 million with initial capital of $1,177 million and sustaining capital costs of $114 million. Closure costs are estimated at an additional $428 million. The estimate accuracy is ±15% and developed at a Q3/Q4-2022 US dollars basis with a contingency less than 15%.

 

22.14Operating Costs

 

The average LOM operating cost for the Arctic Project is estimated to be $59.83/t milled.

 

There is a risk to the capital and operating cost estimates if the toll road is not built in the time frame required for the Arctic Project, the design basis for the road cost estimate changes (for example from a single lane roadway as assumed in this Report to a dual lane), or if the annual toll charges that will be levied are significantly different from what was assumed.

  
Arctic ProjectPage 403
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

22.15Economic Analysis

 

Based on $1,177 million of initial capital costs, sustaining capital costs of $114 million, closure costs of $428 million, $2,969 million in LOM off-site operating costs and $2,794 million in LOM on-site operating costs, pre-tax financial results show an IRR of 25.8% and an NPV of $1,500 million at an 8% discount rate and a 2.9-year payback period. Post-tax financial results show an IRR of 22.8% and an NPV of $1,108 million at an 8% discount rate and a 3.1-year payback period.

 

22.16Conclusions

 

The Arctic deposit will be mined at a maximum annual rate of 35 Mt/a with an overall stripping ratio of 7.3. Ore will be processed by conventional methods to annually produce 234 kt of copper, 23 kt of lead, and 174 kt of zinc, all in concentrates for provision to third party refiners. Waste and tailings materials will be stored in surface facilities, which will be closed and reclaimed at the end of the mine; contact water will be treated and discharged to the environment throughout the LOM. Precious metals attendant with the concentrates will be largely payable. While there are deleterious elements reporting to the concentrates at levels that could incur penalties, special processing provisions have been included in the flowsheet to make a readily saleable concentrate.

 

In terms of project execution, the mine requires nominally two years of pre-strip operations, tailings pond starter dam development and water accumulation before actual production mining operations can commence.

 

For that pre-strip work to start, the Arctic access road from the AMDIAP intersection to the mine site will have to be constructed to at least a pioneer road condition that will allow the mine fleet and the support facilities to be delivered, built, and made operational.

 

Positive financial results support the declaration of Mineral Reserves.

 

22.17Risks and Opportunities

 

22.17.1Permitting

 

Mine development permitting will be largely driven by the underlying land ownership; regulatory authorities vary depending on land ownership. The Arctic Project is situated to a large extent on State land, it will be necessary to obtain a Plan of Operation Approval (which includes the Reclamation Plan) from the ADNR. The overall timeline required for permitting would be largely driven by the time required for the NEPA process.

 

There is a risk to the capital and operating cost estimates, the financial analysis, and the Mineral Reserves if the NEPA process, Plan of Operation Approval and ancillary permits to support operations cannot be obtained in the timeframe envisioned for project start-up.

 

22.17.2Mining

 

Mining through voids during open pit operations is a generally manageable risk where such voids are known to exist. However, unidentified voids may exist, and present a risk to mine and production plans if alternate schedules have to be derived, or new safety measures implemented.

 

Further data collection and interpretation tasks are recommended to fill in geotechnical data gaps to support future stages of design. A numerical groundwater flow model should be calibrated and developed under transient conditions to inform subsequent geotechnical evaluations and depressurization assumptions.

 

Grade control and mining near the ore contacts present a risk of potentially mining too much dilution material or losing high-grade material. Performance of grade control methods and mining techniques should be continually evaluated to manage this risk.

 

The support equipment fleet will be responsible for the usual road, pit and WRF maintenance requirements, but due to the climate conditions expected, will have a larger role in snow removal and water management. This is considered an important, but manageable operating risk to meet production targets.

 

22.17.3Geotechnical

 

The Talc Zone domain represents the weakest geotechnical domain observed at the Arctic deposit. The extent and persistence of the unit is of concern to the pit slope stability. This extent has been further investigated during the 2022 investigation program. The 3D talc model should be updated to include all available drilling and laboratory testing data. Based on the updated geometries, a geotechnical review should be completed to update the slope designs.

  
Arctic ProjectPage 404
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Potential slope instability risks have been identified in the interim and final mining phases of the pre-feasibility open pit design. The risks include potential sliding failure along talc domains and fault structures in the east wall of Phase01 pit, localized wedge failures in the south wall of the Phase02, Phase03 and Final pits, and sliding failures along foliation in the final pit design. These risks, discussed in detail in Section 9.7.1.8, should be considered in the next stages of the Arctic Project.

 

The seismic impact on the slope design should be re-evaluated using the site-specific assessment of the potential seismicity.

 

Once mining begins, regular pit wall mapping is recommended as the new rock faces are exposed to enable a reconciliation against the geotechnical information used in the slope design. Foliation mapping will be critical for the short-term planning in the NE, E and SE slope sectors. The foliation model should be constantly updated as pit wall mapping is being undertaken and be utilized for making ongoing adjustments to the short-term slope design and mining plan.

 

The geotechnical evaluations identified that existence of talc layers in the slopes are significant geotechnical risks. Constant delineation of talc will be important to maintain stability of the pit slopes. As additional information, such as drilling and mapping, become available the talc model should be updated and incorporated into the mining plan.

 

The pore pressure monitoring system and mitigation plan would be critical in managing the slope stability risks during the interim mining phases. The open pit water management plan should include vertical in-pit monitoring piezometers, vertical in-pit pumping wells, and horizontal drain holes. This plan should be reviewed as additional data becomes available and mitigation efforts should be adopted as appropriate to achieve pore pressure reduction needs. This will be particularly important during the earlier phases of the open pit mining when the areas above the talc layers have not been excavated and the compartmentalized water system above the talc layers may exacerbate the geotechnical risks related to the foliation and talc.

 

Ongoing structural geology mapping should be undertaken so that these can be reconciled against the model used in the slope design to identify any potential risks or opportunities. It is the QP’s opinion this structural model should be updated on a regular basis during operation, the risks assessed, and the designs and mining approaches adapted to manage these risks.

 

22.17.4Hydrogeology

 

The hydrogeological conceptual model for the pit and valley areas should be updated over time as more data becomes available and designs are revised. For the pit, the potential effects of seasonal or rapid and high amplitude recharge events (i.e. freshet) on pore pressures and sump sizing need to be considered and opportunities for pit sump locations that could promote drainage from below talc layers should be identified. Where feasible, runoff into the pit should be reduced by drainage ditches around and set back from the pit perimeter, and internal ditching that directs water to pit sumps or out of the pit. Snow removal or clearing off of high elevation portions of the pit may need to be considered to reduce seasonal freshet increases in groundwater recharge and pore pressures.

 

For the valley bottom groundwater seepage interception system (SIS), data should be collected to characterize overburden and fractured rock properties in the specific area of the system and the conceptual model updated. Estimates of potential groundwater bypass of the WRCP should be updated and the groundwater SIS design updated as appropriate. Baseline monitoring of groundwater quality in this area should be initiated as soon as possible to provide a dataset for environmental permitting and to support performance monitoring of the groundwater SIS once in operation.

  
Arctic ProjectPage 405
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

It is the QP’s opinion the pit Groundwater Management Plan should be updated as mine design advances and implemented at the start of mining. Continued water level monitoring, updated interpretations of seasonal variation and development of baseline for comparison with slope monitoring are needed to assess drainage performance. Provisions should be included in the next level of study for groundwater monitoring and drainage works on the east/northeast slope and to install general pit perimeter groundwater monitoring on the north, south and west sides of the pit.

 

22.17.5Tailings Management, Waste Rock and Water Management Facilities

 

The following are risks and opportunities to be evaluated:

 

The increase in tailings volume decreases the volume available for water storage toward the end of operations.

 

The current TMF capacity does not account for entrainment of ice in excess of tailings porosity – ice entrainment needs to be minimized through operational practices and/or accounted for in TMF capacity.

 

To reduce the duration of tailings consolidation, a drainage system installed above the TMF liner should be evaluated.

 

A TMF underdrain system may be needed to convey shallow groundwater below the TMF liner to the WRF rock drain.

 

An underdrain system may be needed below the Process Pond to convey natural groundwater seepage into Subarctic Creek.

 

A protective layer may be needed to prevent ice damage to the geomembrane liner in the tailings pool area.

 

Waste rock placement in the WRF during operation should be optimized to minimize cuts for the western and eastern channels, which provide surface drainage from the TMF after closure.

 

The capture and storage of non-acid-generating waste rock from the pit and overburden in the Subarctic Creek valley bottom in the early stages of construction may be optimized to maximize quantities of non-reactive material for closure and other construction needs. In addition, boulders that may need to be removed from liner subgrade and dam abutments for the TMF, WRCP, and Process Pond may be considered for use as rip-rap and/or sources for crushed aggregate.

 

Geometries for the WRCP and Process Pond dams may be optimized to reduce earthwork costs. In particular, adjusting the WRCP dam crest so that the alignment is straight would reduce material quantities and complexity.

 

Alternative channel linings or profiles may be evaluated to seek reduction in WRCP and Process Pond spillway costs.

 

Continuing the East Diversion Pipe along the east bank of the Process Pond may reduce the cross-sectional area of and armouring requirements for the Div-6 diversion channel.

 

The overburden stockpiles may be integrated with avalanche mitigation structures.

 

It is the QP’s opinion that further geotechnical and hydrogeological investigations should be completed in the foundations of the TMF, WRF, WRCP, and Process Pond including borehole drilling and laboratory testing to support design objectives, including the following:

 

Improve accuracy of overburden thickness and excavation volume estimates.

  
Arctic ProjectPage 406
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Characterize construction materials, including underliner and pond embankment materials.

 

Assess liquefaction susceptibility of overburden.

 

Characterize the rock mass below the facilities to a depth equivalent to embankment height.

 

Evaluate strength properties of pond cut slope materials.

 

Assess suspected slope movements near waste or pond facilities.

 

Characterize ground water regimes under the waste facilities, ponds, and seepage collection system.

 

Characterize geotechnical properties of waste rock, including effect of talc content and physical/chemical degradation.

 

In addition, further engineering studies on the WRF and TMF design should include:

 

Dam Breach Assessment.

 

Finite element consolidation and seepage modelling of the TMF to better understand drainage, long-term settlement, and effects on capacity and closure.

 

Tailings deposition planning and water balance update to account for additional tailings volume, thickened tailings, plan for pool management and winter deposition, and timing of tailings dewatering towards end of mine life.

 

Update WRF, TMF, WRCP, and Process Pond stability analyses (including liquefaction assessment) based on additional field investigation results and lab testing.

 

Evaluate whether heat or gas generation during oxidation of waste rock may adversely affect the closure cover.

 

22.17.6Hydrology

 

Hydrology parameters are based on the rating curve development and resulting discharge timeseries conducted by Brailey Hydrologic Consultants LLC (Brailey 2022). They are assumed to have undergone exhaustive review.

 

The climate parameters presented by SRK are measured at discrete stations but are assumed to represent the general catchment area (SRK, 2022).

 

Regional stations of assumed reasonable representativeness and gridded reanalysis were used to derive long-term records to calculate statistics such as extreme precipitation because of the limited site-specific record availability.

 

SRK used gap-filling methods to fill missing records in the site-specific hydrometric records. Pairing methods are limited, assuming the frequency distribution developed is based on a concurrent record and consistent throughout the long-term record.

 

It is the QP’s opinion that additional baseline studies and environmental permitting activities should be undertaken, including:

 

Low flow measurements should be collected at the SRGS, SCGS, and RCDN hydrologic gauging stations to improve low flow and baseflow estimates.

 

Snow course surveys should continue to be conducted annually to progress the understanding of freshet and peak flow timing.

 

A monitoring gauging station was installed closer to headwaters of Sub-Arctic Creek. Once sufficient data has been collected, predicted Sub-Arctic Creek flows should be calibrated in the water and load balance.

  
Arctic ProjectPage 407
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

22.17.7Water and Load Balance

 

It is the QP’s opinion that the water and load balance be updated as the project design is advanced in order to refine the understanding of the effluents to be treated during operations and at closure, and to refine the water treatment design and closure cost estimates.

 

Other items that require evaluation are:

 

·Surface run-off from cuts for roads is assumed to be non-contact water, however geochemical characterization of road cuts should be conducted to confirm this.

 

·Water quality predictions for the construction phase (Year -3 to -1) were not evaluated. Source terms for waste rock and pit wall run-off for the construction phase have not yet been incorporated in the water and load balance.

 

·There are 17 new source terms that have been developed (including those for the construction phase referenced in the previous point) but have not been incorporated into the model. New and existing source terms do not account for the most recent changes to the mine plan and water management plan, such as an additional year of operations, updated hydrology, and the inclusion of geomembrane covers.

 

·The new source terms (referenced in the above point) were developed to include annual values that account for differences in the geometry and volume of each facility over the mine life, include rock type specific mine scheduling information, and covering the full timeline over which all rock types will turn acidic. As above, these do not incorporate the most recent changes to the mine plan and have not been incorporated into the model.

 

·Based on kinetic data available to date, there is uncertainty with prediction of when waste rock and pit wall will transition from neutral pH to acidic conditions, and how long the transition will take.

 

·The impact of geomembranes on source terms for the WRF and TMF in closure have not been evaluated. As closure planning is refined, the water and load balance model will need to be updated based on revised waste management plans.

 

·Source terms should be updated to include the most recent changes to the mine plan and water management plan, refinement of source terms for road cuts and construction materials, and should incorporate all available data from on-going kinetic tests on waste rock, ore, and tailings.

 

·Baseline water quality source terms for Subarctic Creek and the Shungnak River should be updated to include data collected since 2019 and evaluated for seasonal variability.

 

·Inherent risk associated with assuming the groundwater interception system needs to be 100% efficient in order to prevent any seepage from impacting Subarctic Creek (and the Shungnak River).

 

·Uncertainty remains in predicted groundwater and seepage flows as these are a function of hydraulic conductivity and bedrock thickness which is only known at specific coordinates. It is the QP’s opinion that these uncertainties can be reduced by the investigations described in this document (Section 22.17.3 and Section 23.5).

 

·Uncertainty in estimated tailings porewater release rate during closure phase of the Arctic Project. Further consolidation testwork should be carried out. Testwork should be done to confirm residence time required for the mill reagents to degrade. Water in the Process Pond has a residence time of 10 to 12 days. If this is insufficient, the pond design will need to be revised with additional capacity.

 

·The volume of water that accumulates prior to operations in the TMF for use during mill startup may exceed the TMF liner elevation as designed. If the liner raise cannot happen sooner than proposed, this surplus of water may be directed to the Process Pond. Any additional volume not required for mill startup will either be sent to the WRCP for treatment or directly to Subarctic Creek if it is non-contact runoff.

  
Arctic ProjectPage 408
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

·The model was not evaluated for the hydrological condition where the site experiences a 1 in 25 dry year in the early years of operations. This scenario may result in the inability to meet mill water demands for part of the year if the dry year occurs prior to a sufficient reserve volume of water accumulates in the TMF. There is the potential to install groundwater wells to supplement mill water and mitigate this risk.

 

·For the model scenario involving two consecutive 1 in 25 wet years in Years 12 and 13 of operations, the WRCP alone does not have sufficient capacity in peak runoff months. The TMF and WTP operating year-round have sufficient capacity to manage this water surplus, but modelled pond volumes require further optimization. Cryo-concentration may impact WTP influent chemistry when the plant is operated year-round in operations.

 

·Climate change impacts should be incorporated into model and results should be assessed.

 

22.17.8Metallurgical Testwork

 

Flowsheet development, locked cycle and variability testwork has shown the process flowsheet to be robust and stable at the study level under laboratory conditions. The ability to produce saleable metallic concentrates has been confirmed.

 

The process design assumed for this report has some risks identified that could impact delivery or economics and these need to be managed and mitigated by additional testwork and studies. The key aspects of the Arctic Project presenting most execution risk are:

 

·Performance of the flotation circuits at less than proven testwork results, which can be mitigated by further pilot level testing

 

·Metal recoveries not achieving proven testwork levels, which can be mitigated by further geometallurgical testwork, e.g: perform additional metallurgical testwork on the bulk Cu-Pb concentrate to determine if the Pb recovery can be increased and to better define the Au-Ag recovery

 

·Areas of low recovery in the pit, which can be mitigated by variability testing in several areas of the put to better define these zones based on updated recovery formulas

 

  
Arctic ProjectPage 409
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

23RECOMMENDATIONS

 

23.1Introduction

 

A work program is recommended to continue developing the Arctic Project through engineering and de-risking, and into construction at a total cost of $14.4 million.

 

Table 23-1 and the following sections summarize the key recommendations arising from a review of each major area of investigation completed as part of this study to improve the base case design. and described below.

 

Table 23-1: Summary of Recommended Work Packages

 

Description  Cost ($) 
Mining   1,073,000 
Geology and Resource Models   10,190,000 
Open Pit Geotechnical Work   150,000 
Hydrogeology   490,000 
Tailings Management Facility   1,420,000 
Closure   250,000 
Water Treatment   170,000 
Metallurgical Testing   175,000 
Recovery Methods   350,000 
Operational Readiness Plan   120,000 
Total   14,388,000 

 

23.2Mining

 

·Perform a SMU study to define an optimal block size that can support the envisioned production rate while minimizing dilution. Estimated cost of $50,000.

 

·Requote explosives in the future. Ammonium nitrate prices are currently in record highs due to the conflict Ukraine-Russia. Since ammonium nitrate is the main raw material used to produce blasting explosives such as ANFO and emulsion, it has a significant impact on the blasting cost of the operation. Estimated cost of $5,000.

 

·Assess the use of alternate fuel sources for the mine mobile equipment including LNG. Estimated cost of $18,000.

  
Arctic ProjectPage 410
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

·Confirm the location, thickness, and continuity of the talc layers near to the northeast wall of the final pit. The northeast wall has been forced to fully mine the talc zones, which has pushed the wall, increased the footprint of the pit, and added waste material to mine plan. Any change to the talc shapes can modify the pit design, and therefore, the amount of material mined. Estimated cost $1,000,000.

 

23.3Geology and Resource Models

 

No issues were identified that are expected to have a material impact of the current Mineral Resource estimate. The following recommendations are made to confirm assumptions that non-material issues identified are not likely to materially impact the outcome of the resource estimate, but if addressed, they are expected to reduce potential risk associated with these minor issues and assist in more efficient and timely due diligence reviews in the future.

 

·Bias in historical copper and lead assays - Compare the current Mineral Resource estimate with an estimate prepared using a correction factor applied to the historic Cu and Pb assay values that remain in the assay database or an estimate that does not use these historical intervals. This work is expected to cost $5,000. If this work identifies a significant difference, then a continuation of the re-assay program may be warranted. The re-assay program is expected to cost $80,000.

 

·Bias in predicted SG values – A review of the methodology and dataset used to generate the predicted SG values is recommended and investigate to minimize or mitigate the apparent bias. Total estimated cost is $5,000.

 

·Mineral Resource Classification confidence related to geological complexity – To mitigate the risk of complex geology within the first 5 years of production area, consider putting additional in-fill holes around 25 m or less in drill grids. This is recommended to classify Measured Resources which can then be converted to Proven Mineral Reserves and provide high confidence in the production plan at project start and payback period. Estimated cost $10,000,000.

 

·Update the geological and resource model using all available data including the data collected during the 2022 drilling program. Total estimated cost is $80,000.

 

Review and update variogram models for all metals and SG, using all available data, especially for the payable metals.

 

Review and update the resource model estimation parameters for all metals and SG, especially for the minimum and maximum number of composites and number of composites used per drill hole.

 

Review the current compositing length of 1m that is more in agreement with the average sample length.

 

Update the geological model wireframes including talc wireframes with all available data.

 

·Address the following minor database issues. Total estimated cost is $25,000.

 

Complete and document a quantified transcription error check of collar, down hole survey, logging data and assays, especially for pre-2004 data.

 

Remove the few downhole survey measurements that are causing excessive deviation.

 

Prepare a document supporting applied detection limit decisions confirming high detection limits for legacy assays that remain in the database are not inadvertently adding economic value.

 

Include fields in the sample interval table indicating sample interval year, assay value year, and a flag to indicate if the value is supported by QC.

  
Arctic ProjectPage 411
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

23.4Open Pit Geotechnical work

 

It is the QP’s recommendation that the following open pit geotechnical work be undertaken:

 

·The Talc Zone domain represents the weakest geotechnical domain observed at the Arctic deposit. The extent and persistence of the unit is of concern to the pit slope stability. The 3D talc model should be updated to include all available drilling and laboratory testing data. Based on the updated geometries, a geotechnical review should be completed to update the slope designs.

 

·Potential slope instability risks have been identified in the interim and final mining phases of the open pit design. The risks include potential sliding failure along talc domains and fault structures in the east wall of Phase01 pit, localized wedge failures in the south wall of the Phase02, Phase03 and Final pits, and sliding failures along foliation in the final pit design. These risks should be considered in the next stages of the Arctic Project.

 

·The seismic impact on the slope design should be re-evaluated using the site-specific assessment of the potential seismicity.

 

·The pore pressure monitoring system and mitigation plan would be critical in managing the slope stability risks during the interim mining phases. This plan should be reviewed as additional data becomes available and mitigation efforts should be adopted as appropriate to achieve pore pressure reduction needs.

 

Estimated total cost of $150,000.

 

23.5Hydrogeology

 

It is the QP’s recommendation that the following hydrogeology work be undertaken:

 

·In general, update the hydrogeological conceptual model for the pit and valley areas over time as more data becomes available and designs are revised.

 

·For the pit,

 

Continue water level monitoring

 

Assess the potential effects of seasonal or rapid and high amplitude recharge events (i.e., freshet) on pore pressure and on sump sizing needs.

 

Assess pit sump locations that could promote drainage from below talc layers.

 

Where feasible, assess drainage ditches around and set back from the pit perimeter to reduce runoff inflow, and internal ditching that directs water to pit sumps or out of the pit.

 

Consider snow removal or clearing off high elevation portions of the pit to reduce seasonal freshet increases in groundwater recharge and pore pressures.

 

Update the pit Groundwater Management Plan as mine design advances and plan to implement at the start of mining.

 

Estimated cost for points above of $40,000.

 

Install general pit perimeter groundwater monitoring on the north, south and west sides of the pit. Estimated cost $300,000

 

  
Arctic ProjectPage 412
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

·For the valley bottom,

 

Conduct hydrogeological drilling at location of the groundwater seepage interception system (SIS) to characterize overburden and fractured rock properties in the specific area of the system

 

Update conceptual model

 

Update estimates of potential groundwater bypass of the WRCP and the groundwater SIS design as appropriate.

 

Initiate baseline monitoring of groundwater quality around groundwater SIS as soon as possible to provide a dataset for environmental permitting and to support performance monitoring of the groundwater SIS once in operation.

 

Estimated cost of $150,000.

 

23.6Tailings Management Facility

 

It is the opinion of the QP, further engineering studies required for the TMF design include:

 

·Geotechnical and hydrogeological investigations to be completed in the foundations of the TMF, WRF, WRCP, and Process Pond including borehole drilling and laboratory testing to support design objectives, including the following. Estimated Cost $1,000,000.

 

·Dam Breach Assessment, based on site specific hazard assessment, for the TMF, the WRCP and Process pond. Estimated cost of $85,000.

 

·Finite element consolidation and seepage modelling of the TMF to better understand drainage, long-term settlement, and effects on capacity and closure. Estimated cost $75,000.

 

·Tailings deposition planning and water balance update to account for additional tailings volume, thickened tailings, plan for pool management and winter deposition, and timing of tailings dewatering towards end of mine life. Estimated cost $50,000.

 

·Evaluation of Tailings consolidation and requirement for an underdrain system. Estimated cost $25,000.

 

·Update WRF, TMF, WRCP, and Process Pond stability analyses (including liquefaction assessment) based on additional field investigation results and lab testing. Estimated Cost $150,000.

 

·Evaluate whether heat or gas generation during oxidation of waste rock may adversely affect the closure cover. Estimated cost $35,000.

 

23.7Closure

 

It is the QP’s opinion that a revegetation and cover study should be conducted to verify plant survival at the elevations proposed of the waste rock dump and reclaimed tailings facility. Trials should be conducted during operations to develop a revegetation program to meet 11 AAC 97.200 – Land Reclamation and Performance Standards. Alaska Statute AS 27.19.020 requires that the site be left in a stable condition. Generally, revegetation is the preferred method of stabilization, however other methods of stabilization could be implemented such as a non-reactive, durable rock cover.

 

Thriving plant communities at the proposed elevations are limited to localized areas with deeper growth media, and water availability. Much of the surrounding area is talus rock with minimal plant cover. The study should include climactic variables such as persistence of snow, limited rainfall, soil erosion or low temperature at altitude which may (or many not) limit plant survival. The proponent should consult with the Alaska Plant Materials Center to develop a revegetation program utilizing native species to determine the optimal growth media depth, amendments, and soil cover to optimize plant survival.

  
Arctic ProjectPage 413
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Estimated cost of $250,000.

 

23.8Water Treatment

 

The following actions are recommended to further define the water treatment strategy. The cost of the first four items are already included in the estimated cost for the WTP:

 

·As the discharge permitting advances and the actual permitted discharge criteria become more defined, review and adjust the WTP design accordingly to target compliance with the criteria.

 

·Continue to track and address identified project risks and opportunities.

 

·Implement technology confirmation testing such as bench-scale and pilot-scale treatment tests to confirm the high treatment rates required to meet the WQS will be achieved and to right-size treatment equipment. Based on the outcome of influent water quality projections and these treatability studies, the system design can be refined. The RO reject treatment train can be evaluated once real mine-impacted water is generated during the operation phase.

 

·Refine the acids and bases used in the WTP to reduce the risk of TDS WQS compliance issues. This refinement can be done in later design phases.

 

·Continue to refine the WTP influent water quality predictions, which will include advancing the source term predictions. Estimated cost $170,000.

 

23.9Metallurgical testing

 

Additional testwork is proposed to further refine metallurgical performance and recovery estimates for the selected flowsheet, including the following at an estimated cost of $175,000:

 

·Variability testing on samples with characteristics that match the LOM feed material to improve the recovery and concentrate grade models

 

·Investigate circuit flowsheet modifications to improve concentrate quality and reduce deleterious elements

 

·Comminution testing on new samples to increase the database of results to optimize comminution power

 

23.10Recovery Methods

 

Further process plant activities to be considered for the next phase include capital cost optimization and a thorough review of equipment sizing/selection based on the geometallurgy outcomes. Estimated cost of $350,000.

 

23.11Operational Readiness Plan

 

A robust OR plan would benefit the Arctic Project given the inherent risks and challenges associated with operating at a remote site. Estimated cost $120,000.

  
Arctic ProjectPage 414
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

·Review project and operating assumptions to take into consideration the impacts of labour availability, logistical challenges with availability of equipment and associated goods/services and long lead times.

 

·Create a start-up/operational risk register to highlight issues for decisions taken during detailed design and for items related to the pre-operations/commissioning phase.

 

·Take into account specific development and implementation considerations in the OR plan for the remote cold-weather project site with limited access.

 

·Identify contingencies and challenge assumptions regarding supply, transportation and logistics for reagents, concentrate, and any other goods to develop potentially better alternatives.

 

·Identify strategies to track environment and operations-related permits to avoid other costly alternatives.

 

·Explore opportunities in the region to develop synergies with existing businesses and to understand what is available, as well as what needs to be developed to build the “industrial base” required to sustain mining and processing operations.

 

·Identify vendors and develop strategies to support contracts, parts, warehousing, training and first fills that will result in savings and positively impact human resource (HR) planning.

 

·Consider strategic HR staffing decisions such as innovative labour scheduling and local sourcing.

 

·Identify HSEC policies and procedures for a remote site to leverage local resources and other tie-ins where possible.

 

·Mobilize key technical functions early, such as an assay lab and asset management functions to support mining and operations.

  
Arctic ProjectPage 415
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

24REFERENCES

 

[ADEC] Alaska Department of Environment and Conservation. 2008. Alaska Water Quality Criteria Manual for Toxic and Other Deleterious Organic and Inorganic Substances.

 

[ADEC] Alaska Department of Environment and Conservation. 2018. Alaska Water Quality Standards: 18 AAC 80.

 

ABR, 2017, Aerial Surveys of Nesting Raptors in the Upper Kobuk Mineral Project Area, Alaska, 2016, Consultant Report for WHPacific and Ambler Metals, Inc., January.

 

ABR, 2018, Aerial Surveys of Nesting Raptors in the Upper Kobuk Mineral Project Area, Alaska, 2017, Consultant Report for WHPacific and Ambler Metals, Inc., January.

 

ADFG, 2011, Caribou Management Report - Species Management Report, Alaska Department of Fish and Game, Division of Wildlife Conservation, Patricia Harper Editor, 2011.

 

ADFG, 2015, Caribou Management Report - Species Management Report, Alaska Department of Fish and Game, Division of Wildlife Conservation, ADFG Report 2015-4.

 

Alaska Industrial Development and Export Authority, AIDEA, and Alaska Energy Authority, 2013, Interior Energy Project Feasibility Report. Proposed Project – North Slope LNG Plant, July.

 

Albers, D.A., 2004, Arctic Project Status Report: NovaGold Internal report.

 

Aleinikoff, J. N., Moore, T. E., Walter, M., and Nokleberg, W. J., 1993, U-Pb ages of zircon, monazite, and sphene from Devonian Metagranites and Metafelsites, Central Brooks Range, Alaska: U.S. Geological Survey Bulletin, v. B 2068, p. 59-70.

 

Ambler Metals Inc., 2020: Arctic Feasibility Study – AMDIAP Road Toll Costs: memorandum prepared for Ausenco, dated September 23, 2020.

 

Austin, J., 2019, Memorandum on the Cyanide Destruction Testwork and Tailings Solutions Production.

 

BGC Engineering, 2012, Ambler Project, Arctic Deposit, Sub-Arctic Creek, Alaska, Rock Mechanics and Hydrogeology Study, Consultant Report for NovaCopper U.S. Inc., October.

 

Broadbent, C.D. 1981, Evaluation of Arctic and Ruby Creek Deposits: Kennecott Exploration Internal report

 

Broman, B.N., 2014, Metamorphism and Element Redistribution: Investigations of Ag-bearing and associated minerals in the Arctic Volcanogenic Massive Sulphide Deposit, SW Brooks Range, NW Alaska, University of Alaska Fairbanks.

 

Brown, W.J., 1985, Pre-AFD Report.

 

Chutas, N., 2006, Preliminary report on the Button Schist: NovaGold Internal report.

 

CIBC Global Mining Group, Analyst Consensus Commodity Price Forecasts, Consensus Forecast Summary, November 1, 2022.

  
Arctic ProjectPage 416
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

Clark, L.A. and Sweeney, M.J., 1976, Volcanic Stratigraphy, Petrology, and Trace Metal Geochemistry, Arctic Deposit: Kennecott Exploration Internal report.

 

Clark, L.A., 1972, Petrographic Problem Studies Report, Arctic Deposit: Kennecott Exploration Internal report.

 

Craig, C., 2012, 2012 UKMP Water Quality Report, Internal Report by NovaCopper US Inc., January.

 

Craig, C., 2013, 2013 UKMP Water Quality Report, Third Quarter, Internal Report by NovaCopper US Inc., October.

 

Craig, C., 2014, 2014 UKMP Water Quality Report, Third Quarter, Internal Report by NovaCopper US Inc., October.

 

Craig, C., 2015, 2015 UKMP Water Quality Report, Third Quarter, Internal Report by NovaCopper US Inc., October.

 

Craig, C., 2016, 2016 UKMP Water Quality Report, Fourth Quarter, Internal Report by Ambler Metals Inc., January 2017.

 

Craig, C., 2016, 2016 UKMP Water Quality Report, Third Quarter, Internal Report by Ambler Metals Inc., July 2017.

 

Craig, C., 2017, 2017 UKMP Water Quality Report, April 21st – 24th, Internal Report by Ambler Metals Inc., June.

 

Craig, C., 2017, 2017 UKMP Water Quality Report, May 17th, Internal Report by Ambler Metals Inc., June.

 

Dillon, J. T., Pessel, G. H., Chen, J. H., and Veach, N. C., 1980, . Middle Paleozoicmagmatism and Orogenesis in the Brooks Range, Alaska: Geology, v. 8, p. 338-343.

 

Dillon, J. T., Tilton, G. R., Decker, J., and Kelley, M. J., 1987, Resource Implications of Magmatic and Metamorphic Ages for Devonian Igneous Rocks in the Brooks Range, in Tailleur, I. L., and Weimer, P., Alaskan North Slope Geology, Pacific Section, Society of Economic Paleontologists and Mineralogists, p. 713-723.

 

Dimock, R.R., 1984, Arctic Evaluation Update: Kennecott Exploration Internal report.

 

Dodd, S. P., Lindberg, P. A., Albers, D. F., Robinson, J. D., Prevost, R., 2004, Ambler Project, 2004 Summary Report, Unpublished Internal Report, Alaska Gold Company.

 

DOWL HKM, 2013, NovaCopper Final Year-End Report 2012, Consultant Report prepared for NovaCopper under Work Order 60816, March.

 

DOWL, 2016, Large Mammal Survey, Consultant Report for Ambler Metals, Inc. December.

 

DOWL, 2016, Ambler Metals Upper Kobuk Mining Project, Preliminary Wetlands Determination, Consultant Report for Ambler Metals Inc., November.

 

DOWL, 2020, Dahl Creek Airstrip Feasibility Study, February 2020.

 

Earnshaw, J., 1999, Interim Report Conceptual Level Economic Evaluations of the Arctic Resource: Kennecott Exploration Internal report.

  
Arctic ProjectPage 417
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Ellis, W.T., 1978, Geologic Evaluation and Assessment of the “North Belt” Claims Ambler District: Sunshine Mining Company Internal report.

 

Ernst & Young LLP, 2023: Tax Module Build Arctic Project, January 20, 2023.

 

Exploration Agreement and Option to Lease between NovaCopper US Inc. and NANA Regional Corporation, Inc. dated October 19, 2011, as amended.

 

Franklin, J.M., Gibson, H.L., Jonasson, I.R., and Galley, A.G., 2005, Volcanogenic Massive Sulphide Deposits, in Hedenquist, J.W., Thompson, J.F.H., Goldfarb, R.J., and Richards, J.P., eds., Economic Geology 100th Anniversary Volume: The Economic Geology Publishing Company, p. 523-560.

 

Fueg, J., Arctic/Ambler District Geophysical Work Plan, Kennecott Exploration Internal memorandum.

 

Gottschalk, R. R., and Oldow, J. S., 1988, Low-angle Normal Faults in the South-central Brooks Range Fold and Thrust Belt, Alaska, Geology, 16, p. 395-399.

 

Grinnell, J.G., 1901, Gold Hunting in Alaska (E. Grinnell, Ed.), David C. Cook Publishing Company.

 

Gustin, M. M. and Ronning, P., 2013, NI 43-101 Technical Report on the Sun Project, prepared by Mine Development Associates of Reno, Nevada for Andover Mining Corp.

 

Hale, C., 1996, 1995 Annual Ambler District Report: Kennecott Exploration Internal report.

 

Halls, J.L. 1974, Ambler District Evaluation: Kennecott Exploration Internal report.

 

Halls, J.L. 1976, Arctic Deposit Order of Magnitude Evaluation: Kennecott Exploration Internal report.

 

Halls, J.L. 1978, Arctic Deposit: Kennecott Exploration Internal report.

 

Hammitt, J.W., 1985, 1985 Annual Progress Report – Ambler District: Kennecott Corporation Internal Report.

 

Hitzman, M. W., Proffett, J. M., Schmidt, J. M., and Smith, T. E., 1986, Geology and Mineralization of the Ambler District, Northwestern Alaska: Economic Geology v. 81, p. 1592-1618.

 

Hitzman, M. W., Smith, T. E., and Proffett, J. M., 1982, Bedrock Geology of the Ambler District, Southwestern Brooks Range, Alaska: Alaska Division of Geological and Geophysical Surveys Geologic Report 75, scale 1:250,000.

 

Hunt, G.A., 1999, PIMA alteration mapping and structural interpretation of drill core from the Arctic Deposit, Alaska, a report prepared for Rio Tinto Mining and Exploration Ltd, 10 p.

 

Jacobsen, W.L., 1997, Arctic Project Mining Potential: Kennecott Exploration Internal report

 

Journel A., Huijbregts, C. J., 1978, Mining Geostatics. London: Academic Press.

 

Kennecott Research Center, August 1972, Amenability Testing of Samples from Bear Creek Mining Company’s Arctic Deposit, TR 72-12.

 

Kennecott Research Center, January 1997, Process Selection for Arctic Deposit, Technical Report RTR 77-4.

  
Arctic ProjectPage 418
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Kennecott Research Center, September 1968, Amenability Testing of Diamond Drill Core Samples from Arctic, Alaska Project, TR 68-20.

 

Kennecott Research Center, September 1976, Recovery of Mineral Values Arctic Prospect, RTR 76¬22.

 

Kennecott, 1977, Annual Report Arctic Deposit: Unpublished in-house report.

 

Kennecott, 1995, Re-Evaluation of the Arctic Deposit, Ambler District, Alaska: Unpublished in-house report.

 

Kennecott, 1998, Arctic Deposit and Ambler District Field Report: Unpublished in-house report (R. Presnell & J. Fueg).

 

Kobuk Valley National Park, 2007, www.kobuk.valley.national-park.com/info.htm#env.

 

Lakefield Research Limited, January 7, 1999, An Investigation of the Recovery of Lead, Zinc & Precious Metals from Samples of the Arctic Project Ore submitted by Kennecott Minerals, Progress Report No.1.

 

Lindberg, P. A., 2004, Structural Geology of the Arctic Cu-Zn-Pb-Ag Sulphide Deposit: Alaska Gold Company Unpublished Report.

 

Lindberg, P. A., 2005, A Preliminary Attempt to Unfold the Arctic Volcanogenic Ore Deposit and Determine it’s Original Metal Zonation: Alaska Gold Company Unpublished Report.

 

Marten, B.E., 1999, Structure of the Arctic Polymetallic VHMS Deposit, Ambler District, Alaska: Report on Fieldwork, Rio Tinto Mining and Exploration Internal Report.

 

Mathers, N., 2017, Site Infrastructure Location Workshop 1 August 2017.Metz, P.A., 1978, Arctic Prospect Summary File Report, prepared for US Bureau of Mines by Mineral Research Laboratory, University of Alaska – Fairbanks.

 

McClelland, W.C., Schmidt, J.M., and Till, A.B., 2006, New U-Pb SHRIMP ages from Devonian felsic volcanic and Proterozoic plutonic rocks of the southern Brooks Range, AK: Geologic Society of America Abstracts with Programs, v. 38, n. 5, p. 12.

 

Modroo, E.R., 1980, Ambler River Project Project Memorandum Field Investigations: Sunshine Mining Company Internal report.

 

Modroo, E.R., 1982, Ambler River Project Project Memorandum Field Investigations: Bear Creek Mining Company Internal report.

 

Modroo, E.R., 1983, Ambler River Project Project Memorandum Field Investigations: Sunshine Mining Company Internal report.

 

Moore, T. E., Wallace, W. K., Bird, K. J., Karl, S. M., Mull, C. G., and Dillon, J. T., 1994, Geology of Northern Alaska, in Plafker, G., and Berg, H. C., eds., The Geology of Alaska: Boulder, Colorado, Geological Society of America, The Geology of North America, v. G1, p. 49-140.

 

Moore, T.E., 1992, The Arctic Alaska Superterrane, p. 238-244, in Bradley, D.C., and Dusel-Bacon, C., eds., Geologic Studies in Alaska by the U.S. Geological Survey, 1991: U.S. Geological Survey Bulletin 2041.

  
Arctic ProjectPage 419
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Moore, T.E., Wallace, W.K, Bird, K.J., Karl, S.M., Mull, C.G., and Dillon, J.T., 1994, Geology of northern Alaska, in Plafker, G., and Berg, H.C., eds., The Geology of Alaska: Boulder, Colorado, Geologic Society of America, The Geology of North America, v. G-1.

 

Mull, C. G., 1982, Tectonic Evolution and Structural Style of the Brooks Range, Alaska; an Illustrated Summary, in Geologic Studies of the Cordilleran Thrust Belt, Rocky Mt. Assoc. Geol., Denver, CO, United States, USA, p. 1-45.

 

Mull, C. G., 1985, Cretaceous Tectonics, Depositional Cycles, and the Nanushuk Group, Brooks Range and Arctic Slope, Alaska, U.S. Geol. Soc. Bull., 1614, p. 7-36.

 

Newberry, R.J., Crafford, T.C., Newkirk, S.R., Young, L.E., Nelson, S.W., and Duke, N.A., 1997, Volcanogenic massive sulphide deposits of Alaska, in Goldfarb, R.J., and Miller, L.D., eds., Mineral deposits of Alaska: Economic Geology Monograph 9, p. 120-150.

 

Oldow, J. S., Seidensticker, C. M., Phelps, J. C., Julian, F. E., Gottschalk, R. R., Boler, K. W., Handschy, J. W., and Ave Lallemant, H. G., 1987, Balanced Cross Sections Through the Central Brooks Range and North Slope, Arctic Alaska, AAPG, p. 19, 8 plates.

 

Otto, B. R., 2006, Personal Communication.

 

Otto,B., 2006, Arctic Progress Report: NovaGold Internal Report.

 

Parker, Bradley, 2017, Aquatic Biomonitoring at the Arctic-Bornite Prospect, 2016, Alaska Department of Fish and Game

 

Plafker, G., Jones, D.L., and Pessagno, E.A., Jr., 1977, A Cretaceous accretionary flysch and mélange terrane along the Gulf of Alaska margin in Blean, K.M. ed., The USGS in Alaska Accomplishments during 1976: USGS Survey Circ 751-B, p. B52-B54.

 

Piercey, S.J., Report on August 2022 Field Visit Study of the Arctic VMS Deposit and Other Targets within the Ambler Belt, Alaska, unpublished report prepared by SJPGeoConsulting and Department of Earth Sciences, Memorial University of Newfoundland for Ambler Metals.

 

Proffett, J. M., 1999, Summary of Conclusions on Geology of the Arctic Deposit, AK: Kennecott Minerals Company Unpublished Report.

 

Randolph, M. P., August 29, 1990, Internal Kennecott Memo to T. J. Stephenson, Arctic Deposit.

 

Rubin, C.M.,1982, Ambler Project Annual Report: Anaconda Metals Company Internal report.

 

Russell, R. H., 1977, Annual Report, Arctic Deposit: Bear Creek Mining Company Unpublished Report.

 

Russell, R. H., 1995, Arctic Project 1995 Evaluation Report, Geologic Report: Kennecott Corporation Unpublished Report.

 

Schmandt, D., 2009, Mineralogy and Origin of Zn-rich horizons within the Arctic Volcanogenic Massive Sulphide deposit, Ambler District, Alaska. Undergraduate Thesis, Smith College, 59 p.

 

Schmidt, J. M., 1983, Geology and Geochemistry of the Arctic Prospect, Ambler District, Alaska: Unpublished Ph.D. dissertation, Stanford University.

  
Arctic ProjectPage 420
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Schmidt, J. M., 1986, Stratigraphic Setting and Mineralogy of the Arctic Volcanogenic Massive Sulphide Prospect, Ambler District, Alaska: Economic Geology v. 81. p. 1619-1643.

 

Schmidt, J. M., 1988, Mineral and Whole Rock Compositions of Seawater-Dominated Hydrothermal Alteration at the Arctic Volcanogenic Massive Sulphide Prospect, Alaska: Economic Geology v.83, p. 822-842.

 

Shaw Alaska Inc., 2008, Hydraulics Data Report July 2008 Event Final, Shaw Environmental, Inc.

 

Shaw Environmental Inc., 2007, Ambler Project, 2007 Environmental Baseline Sampling, Shaw Environmental, Inc.

 

Shaw Environmental Inc., 2008, Water Quality Report July 2008 Event Final, Shaw Environmental, Inc.

 

Shaw Environmental Inc., 2009, Hydraulics Data Report July 2009 Event Draft, Shaw Environmental, Inc.

 

Shaw Environmental Inc., 2009, Water Quality Report July 2009 Event Final, Shaw Alaska, Inc.

 

Silberling, N.J., et al., 1992, Lithotectonic terrange map of the North American Cordillera, USGS.

 

SRK Consulting (Canada) Inc. (2017). Pre-Feasibility Slope Geotechnical and Hydrogeological Report for the Arctic Deposit (2016), Report prepared for Trilogy Metals Inc., SRK Project 2CN032.001, February 2017.

 

SRK Consulting (Canada) Inc. (2020). Geotechnical and Hydrogeological Feasibility Report for the Arctic Deposit, Report prepared for Trilogy Metals Inc., SRK Project 2CT031.000, September 2020.

 

SRK Consulting (Canada) Inc. (2022). Ambler Prefeasibility Study Geotechnical and Hydrogeological Assessments, Report prepared for Ambler Metals LLC, SRK Project CAPR000764 , January 2022.

 

SRK Consulting (Canada) Inc. (2018). Technical Report on the Arctic Project for PFS level Waste Management, Water Management & Closure Design, report prepared for Ambler Metals Inc., SRK Project Number 1CT030.001, February.

 

SRK Consulting (Canada) Inc. (2019). Arctic Project: Plan for Further Characterization of Acid Rock Drainage and Metal Leaching Potential; Project 1CN024.004. Report prepared for Ambler Metals Inc. May 2019.

 

SRK Consulting (Canada) Inc. (2020). Technical Report on the Arctic Project for FS level Waste Management, Water Management & Closure Design, report prepared for Ambler Metals Inc., SRK Project Number 1CT030.003, (Draft).

 

SRK Consulting (Canada) Inc.. 2017 Arctic Project Pre-feasibility Study: Overburden Site Investigation, report prepared for Ambler Metals Inc., SRK Project Number 1CT030.001, Report Date October, 2017.

 

SRK Consulting (Canada) Inc.. 2018 Technical Report on the Arctic Project for PFS level Waste Management, Water Management & Closure Design, report prepared for Ambler Metals Inc., SRK Project Number 1CT030.001, Report Date March 2018.

 

SRK, 1998, Arctic Project Preliminary Scoping Study. Prepared by SRK Consulting, U.S., Inc. for NovaCopper. Report Date March 9, 2012. 276 pages.

 

SRK, 2012, NI 43-101 Preliminary Economic Assessment Ambler Project Kobuk, AK, SRK Consulting (U.S.), Inc., March.

  
Arctic ProjectPage 421
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

SRK, 2012, NI 43-101 Preliminary Economic Assessment, Ambler Project, Kobuk, AK. Prepared by SRK Consulting Inc. for Kennecott Minerals Company. Report Date November, 1998. 69 pages.

 

SRK, 2016, Pre-Feasibility Slope Geotechnical and Hydrogeological Report for the Arctic Deposit (2016), SRK Consulting (Canada), Inc., February 2017.

 

Stephen R. Braund & Associates, 2012, Ambler Mining District Access Road Subsistence Data Gap Memo, Prepared for the Alaska Department of Transportation and Public Facilities, May.

 

Stephens, J.D., and Cameron, J.W., 1970, Arctic Alaska Project – Mineralogic Study of Diamond Drill Core Samples: Technical Report 70-01. Kennecott Research Center – Metal Mining Division, 21 p.

 

Stevens, M.G., 1982, Ambler District Generalized District Petrology: Bear Creek Mining Company Internal report.

 

StoneHouse Consulting Inc.: Arctic Concentrate Marketing, prepared for Trilogy Metals Inc., dated January 5, 2023.

 

Tetra Tech, 2010a, Arctic Deposit Access Environmental Baseline Data Collection - Hydrology, Ambler Mining District, Alaska, December.

 

Tetra Tech, 2010b, Arctic Deposit Access Environmental Baseline Data Collection - Wetlands & Vegetation, Ambler Mining District, Alaska, November.

 

Tetra Tech, 2011, Arctic Deposit Access Environmental Baseline Data Collection – Aquatics, Ambler Mining District, Alaska, January 20.

 

Tetra Tech, 2013, Preliminary Economic Assessment Report on the Arctic Project, Ambler Mining District, Northwest Alaska, September.

 

Till, A. B., Schmidt, J. M., and Nelson, S. W., 1988, Thrust Involvement of Metamorphic Rocks, Southwestern Brooks Range, Alaska: Geology, v. 16, p. 930-933.

 

Twelker, E., 2008, Progress Report: Immobile element lithogeochem work at Arctic: NovaGold Internal Report

 

URSA Engineering, 1998, Arctic Project Rock Mass Characterization, Prepared for: Kennecott Minerals, Co., Unpublished Report, p. 49.

 

Vallat, C., 2013a, Memo to NovaCopper Inc. “Historic Pre-NovaGold, 2004, Arctic Assay Validations and Updates Within NovaCopper Database”: GeoSpark Consulting Inc. April 22, 2013.

 

Vallat, C., 2013b, “Quality Assurance and Quality Control Review on Analytical Results Related to the NovaCopper Inc. Arctic Project, pre-NovaGold, pre-2004, ”: GeoSpark Consulting Inc. unpublished report for NovaCopper Inc. April 22, 2013.

 

Vallat, C., 2013c, “Quality Assurance and Quality Control Review on Analytical Results Related to the NovaCopper Inc. 2004 Arctic Project”: GeoSpark Consulting Inc. unpublished report for NovaCopper Inc. June 6, 2013.

 

Vallat, C., 2013d, “Quality Assurance and Quality Control Review on Analytical Results Related to the NovaCopper Inc. 2005 Arctic Project”: GeoSpark Consulting Inc. unpublished report for NovaCopper Inc. June 6, 2013.

  
Arctic ProjectPage 422
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

Vallat, C., 2013e, “Quality Assurance and Quality Control Review on Analytical Results Related to the NovaCopper Inc. 2006 Arctic Project”: GeoSpark Consulting Inc. unpublished report for NovaCopper Inc. June 6, 2013.

 

Vallat, C., 2013f, “Quality Assurance and Quality Control Review on Analytical Results Related to the NovaCopper Inc. 2007 Arctic Project”: GeoSpark Consulting Inc. unpublished report for NovaCopper Inc. June 6, 2013.

 

Vallat, C., 2013g, “Quality Assurance and Quality Control Review on Analytical Results Related to the NovaCopper Inc. 2008 Arctic Project”: GeoSpark Consulting Inc. unpublished report for NovaCopper Inc. June 6, 2013.

 

Vallat, C., 2013h, Memo to NovaCopper Inc. “Arctic Projects 2011 Drill Program Assays Reported in 2013 – QAQC” GeoSpark Consulting Inc. May 31, 2013.

 

Vallat, C., 2015, Quality Assurance and Quality Control Review on Analytical Results on the Arctic Project, unpublished report prepared for NovaCopper Inc.

 

Vallat, C., 2016, Quality Assurance and Quality Control Review on Analytical Results on the Arctic Project, unpublished report prepared for NovaCopper Inc.

 

Stonehouse Consulting, 2020, Reliance Letter for Metal Pricing Content of the 2020 Ambler NI 43-101 Technical Report, dated September 14 2020.

 

Vogl, J. J., Calvert, A. J., Gans, P. B., 2003, Mechanisms and Timing of Exhumation of Collision-Related Metamorphic Rocks, Southern Brooks Range, Alaska: Insights from Ar, 40, / Ar, 39, Thermochronology, Tectonics, v 21, No 3, p. 1-18.

 

Website: http://alaskamininghalloffame.org/inductees/berg.php, February 14, 2012.

 

West, A., 2013, Memo to E. Workman & GeoSpark Consulting Inc. “NovaCopper Arctic Project Database Verification”: Internal NovaCopper Inc. Memo, January 8, 2013.

 

West, A., 2014, Identified 2013 Erroneous SG Measurements, internal memo prepared for NovaCopper.

 

West, A., 2020, Metallurgical Test materials used in the 2020 Ambler Feasibility Study.

 

WHPacific, 2016, Cultural Resources Assessment of the Proposed Arctic Pit and Support Facilities Project in Northwest Arctic Borough, Alaska, Consultant Report for Ambler Metals Inc., December 19.

 

XE.com. Currency Exchange Rates, Accessed November 30, 2022. [Online: https://www.xe.com/]

 

Zieg, G. A., et al., 2005, Ambler Project 2005 Progress Report, Unpublished Internal Report, Alaska Gold Company.

  
Arctic ProjectPage 423
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

25RELIANCE ON INFORMATION PROVIDED BY THE REGISTRANT

 

25.1Introduction

 

The QPs have relied on information provided by Trilogy Metals (the registrant) including expert reports, in preparing its findings and conclusions regarding the following modifying factors: macroeconomic information, marketing information, legal matters, environmental matters, accommodations the registrant commits or plans to provide to local individuals or groups in connection with its mine plans, and governmental factors.

 

The QPs consider it reasonable to rely on Trilogy Metals for this information since they have obtained opinion from appropriate experts.

 

25.2Legal Matters

 

The QPs have not independently reviewed ownership of the Project area and any underlying property agreements, mineral tenure, surface rights, or royalties. The QPs have fully relied upon, and disclaim responsibility for, information derived from Trilogy Metals and legal experts retained by Trilogy Metals for this information through the following documents:

 

·Kennecott Exploration Company, Kennecott Arctic Company, Alaska Gold Company and NovaGold Resources Inc., 2010: Net Smelter Returns Royalty Agreement dated effective January 7, 2010: 51 p.

 

·NovaCopper US Inc. and NANA Regional Corporation Inc., 2011: Exploration Agreement and Option to Lease, dated effective October 19, 2011: 144 p.

 

·NovaCopper US Inc. and NANA Regional Corporation Inc., 2012: Amending Agreement, dated effective May 10, 2012: 7 p.

 

·Reeves, J.N., 2018: Arctic Project: legal opinion prepared by Holmes Weddell & Barcott for Trilogy Metals Inc., 4 April 2018, 58 p.

 

·NovaCopper US Inc, Trilogy Metals Inc. and Ambler Metals LLC, 2020: Contribution Agreement, effective as of February 11, 2020: 39 p.

 

This information is used in Section 3 of the Report. The information is also used in support of the Mineral Resource estimate in Section 11, the Mineral Reserve estimate in Section 12 and the economic analysis in Section 19.

 

25.3Taxation

 

The QPs have not independently reviewed the Arctic Project taxation position. The QPs have fully relied upon, and disclaim responsibility for, taxation information supplied by Ernst & Young LLP who was retained for this information. Arctic Project taxation information has been provided through:

 

·Ernst & Young LLP, 2023: Tax Module Build Arctic Project, January 20, 2023.

 

This information is used in the economic analysis in Section 19 of the Report.

  
Arctic ProjectPage 424
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

25.4Environmental Matters and Community Accommodations

 

The QPs have fully relied upon, and disclaim responsibility for, information supplied by Trilogy Metals and experts retained by Trilogy Metals for information related to environmental (including tailings and water management) permitting, permitting, closure planning and related cost estimation, and social and community impacts as follows:

 

·Alaska Department of Environment and Conservation. 2008. Alaska Water Quality Criteria Manual for Toxic and Other Deleterious Organic and Inorganic Substances.

 

·Craig, C., 2012, 2012 UKMP Water Quality Report, Internal Report by NovaCopper US Inc., January.

 

·DOWL, 2016, Ambler Metals Upper Kobuk Mining Project, Preliminary Wetlands Determination, Consultant Report for Ambler Metals Inc., November.

 

·Shaw Environmental Inc., 2007, Ambler Project, 2007 Environmental Baseline Sampling, Shaw Environmental, Inc.

 

·Shaw Environmental Inc., 2008, Water Quality Report July 2008 Event Final, Shaw Environmental, Inc.

 

·Shaw Environmental Inc., 2009, Hydraulics Data Report July 2009 Event Draft, Shaw Environmental, Inc.

 

·Shaw Environmental Inc., 2009, Water Quality Report July 2009 Event Final, Shaw Alaska, Inc.

 

This information is used in Section 17 of the Report. The information is also used in support of the Mineral Resource estimate in Section 11, the Mineral Reserve estimate in Section 12, capital and operating costs in Section 18 and the economic analysis in Section 19.

 

25.5Marketing Information

 

The QPs have not independently reviewed the market studies, pricing or contract information. The QPs have fully relied upon, and disclaim responsibility for, information derived from Trilogy Metals and experts retained by Trilogy Metals for this information through the following documents:

 

·CIBC Global Mining Group, Analyst Consensus Commodity Price Forecasts, Consensus Forecast Summary, November 1, 2022.

 

·StoneHouse Consulting Inc.: Arctic Concentrate Marketing, prepared for Trilogy Metals Inc., dated January 5, 2023.

 

Metals price forecasting is a specialized business requiring knowledge of supply and demand, economic activity and other factors that are highly specialized and requires an extensive global database that is outside of the purview of a QP. The QPs consider it reasonable to rely upon Trilogy Metals to provide metal price forecasts and marketing information on the base metal concentrates as they sought expert input for this information.

 

This information is used in Section 16 of the Report. The information is also used in support of the Mineral Resource estimate in Section 11, the Mineral Reserve estimate in Section 12, and economic analysis in Section 19.

  
Arctic ProjectPage 425
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

  

 

Appendix A – Mineral Claims

 

To Affidavit of Annual Labor for Labor Year Ending September 1, 2022

 

Ambler Metals LLC

 

State of Alaska Mining Claims

 

Kateel River Meridian, Kotzebue Recording District

 

  ADL Claim Name Township Range Section 1/4 Section
1 540543 Arctic 40A 21N 11E 35 SW
2 540544 Arctic 496A 21N 11E 34 SE
3 540545 Arctic 1001 21N 11E 34 SE
4 540546 Arctic 1002 21N 11E 34 SE & SW
5 540549 Arctic 1005 21N 11E 35 SW
6 546144 SC 24 21N 10E 16 SW & SE
7 546145 SC 25 21N 10E 16 SW, SE, NW & NE
8 546146 SC 26 21N 10E 16 NW & NE
9 546147 SC 34 21N 10E 16 SE
10 546148 SC 35 21N 10E 16 SE & NE
11 546149 SC 36 21N 10E 16 NE
12 546150 SC 44 21N 10E 15; 16 SW; SE
13 546151 SC 45 21N 10E 15; 16 SW & NW; SE & NE
14 546152 SC 46 21N 10E 15; 16 NW; NE
15 546153 SC 54 21N 10E 15 SW
16 546154 SC 55 21N 10E 15 SW & NW
17 546155 SC 56 21N 10E 15 NW
18 546156 SC 64 21N 10E 15 SW & SE
19 546157 SC 65 21N 10E 15 SW, SE, NW & NE
20 546158 SC 66 21N 10E 15 NW & NE
21 590853 AM 63-165 21N 9E 14 NW
22 590854 AM 63-166 21N 9E 14 NW
23 590855 AM 63-167 21N 9E 14 NE
24 590856 AM 63-168 21N 9E 14 NE
25 590857 AM 63-169 21N 9E 13 NW
26 590858 AM 63-170 21N 9E 13 NW
27 590859 AM 63-171 21N 9E 13 NE
28 590860 AM 63-172 21N 9E 13 NE
29 590874 AM 64-165 21N 9E 14 NW

  
Arctic ProjectPage 426
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

30 590875 AM 64-166 21N 9E 14 NW
31 590876 AM 64-167 21N 9E 14 NE
32 590877 AM 64-168 21N 9E 14 NE
33 590878 AM 64-169 21N 9E 13 NW
34 590879 AM 64-170 21N 9E 13 NW
35 590880 AM 64-171 21N 9E 13 NE
36 590881 AM 64-172 21N 9E 13 NE
37 590895 AM 65-165 21N 9E 11 SW
38 590896 AM 65-166 21N 9E 11 SW
39 590897 AM 65-167 21N 9E 11 SE
40 590898 AM 65-168 21N 9E 11 SE
41 590899 AM 65-169 21N 9E 12 SW
42 590900 AM 65-170 21N 9E 12 SW
43 590901 AM 65-171 21N 9E 12 SE
44 590902 AM 65-172 21N 9E 12 SE
45 590916 AM 66-165 21N 9E 11 SW
46 590917 AM 66-166 21N 9E 11 SW
47 590918 AM 66-167 21N 9E 11 SE
48 590919 AM 66-168 21N 9E 11 SE
49 590920 AM 66-169 21N 9E 12 SW
50 590921 AM 66-170 21N 9E 12 SW
51 590922 AM 66-171 21N 9E 12 SE
52 590923 AM 66-172 21N 9E 12 SE
53 590940 AM 67-165 21N 9E 11 NW
54 590941 AM 67-166 21N 9E 11 NW
55 590942 AM 67-167 21N 9E 11 NE
56 590943 AM 67-168 21N 9E 11 NE
57 590944 AM 67-169 21N 9E 12 NW
58 590945 AM 67-170 21N 9E 12 NW
59 590946 AM 67-171 21N 9E 12 NE
60 590947 AM 67-172 21N 9E 12 NE
61 590998 AM 56-186 21N 10E 27 NW
62 590999 AM 56-187 21N 10E 27 NE
63 591000 AM 56-188 21N 10E 27 NE
64 591001 AM 56-189 21N 10E 26 NW
65 591002 AM 56-190 21N 10E 26 NW
66 591003 AM 56-191 21N 10E 26 NE
67 591004 AM 56-192 21N 10E 26 NE
68 591005 AM 56-193 21N 10E 25 NW
69 591006 AM 56-194 21N 10E 25 NW
70 591007 AM 56-195 21N 10E 25 NE
71 591008 AM 57-176 21N 10E 19 SE
72 591009 AM 57-177 21N 10E 20 SW
73 591010 AM 57-178 21N 10E 20 SW

  
Arctic ProjectPage 427
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

74 591011 AM 57-179 21N 10E 20 SE
75 591012 AM 57-180 21N 10E 20 SE
76 591013 AM 57-181 21N 10E 21 SW
77 591014 AM 57-182 21N 10E 21 SW
78 591015 AM 57-183 21N 10E 21 SE
79 591016 AM 57-184 21N 10E 21 SE
80 591017 AM 57-185 21N 10E 22 SW
81 591018 AM 57-186 21N 10E 22 SW
82 591019 AM 57-187 21N 10E 22 SE
83 591020 AM 57-188 21N 10E 22 SE
84 591021 AM 57-189 21N 10E 23 SW
85 591022 AM 57-190 21N 10E 23 SW
86 591023 AM 57-191 21N 10E 23 SE
87 591024 AM 57-192 21N 10E 23 SE
88 591025 AM 57-193 21N 10E 24 SW
89 591026 AM 57-194 21N 10E 24 SW
90 591027 AM 57-195 21N 10E 24 SE
91 591028 AM 58-176 21N 10E 19 SE
92 591029 AM 58-177 21N 10E 20 SW
93 591030 AM 58-178 21N 10E 20 SW
94 591031 AM 58-179 21N 10E 20 SE
95 591032 AM 58-180 21N 10E 20 SE
96 591033 AM 58-181 21N 10E 21 SW
97 591034 AM 58-182 21N 10E 21 SW
98 591035 AM 58-183 21N 10E 21 SE
99 591036 AM 58-184 21N 10E 21 SE
100 591037 AM 58-185 21N 10E 22 SW
101 591038 AM 58-186 21N 10E 22 SW
102 591039 AM 58-187 21N 10E 22 SE
103 591040 AM 58-188 21N 10E 22 SE
104 591041 AM 58-189 21N 10E 23 SW
105 591042 AM 58-190 21N 10E 23 SW
106 591043 AM 58-191 21N 10E 23 SE
107 591044 AM 58-192 21N 10E 23 SE
108 591045 AM 58-193 21N 10E 24 SW
109 591046 AM 58-194 21N 10E 24 SW
110 591047 AM 59-176 21N 10E 19 NE
111 591048 AM 59-177 21N 10E 20 NW
112 591049 AM 59-178 21N 10E 20 NW
113 591050 AM 59-179 21N 10E 20 NE
114 591051 AM 59-180 21N 10E 20 NE
115 591052 AM 59-181 21N 10E 21 NW
116 591053 AM 59-182 21N 10E 21 NW
117 591054 AM 59-183 21N 10E 21 NE

  
Arctic ProjectPage 428
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

118 591055 AM 59-184 21N 10E 21 NE
119 591056 AM 59-185 21N 10E 22 NW
120 591057 AM 59-186 21N 10E 22 NW
121 591058 AM 59-187 21N 10E 22 NE
122 591059 AM 59-188 21N 10E 22 NE
123 591060 AM 59-189 21N 10E 23 NW
124 591061 AM 59-190 21N 10E 23 NW
125 591062 AM 59-191 21N 10E 23 NE
126 591063 AM 59-192 21N 10E 23 NE
127 591064 AM 59-193 21N 10E 24 NW
128 591065 AM 60-176 21N 10E 19 NE
129 591066 AM 60-177 21N 10E 20 NW
130 591067 AM 60-178 21N 10E 20 NW
131 591068 AM 60-179 21N 10E 20 NE
132 591069 AM 60-180 21N 10E 20 NE
133 591070 AM 60-181 21N 10E 21 NW
134 591071 AM 60-182 21N 10E 21 NW
135 591072 AM 60-183 21N 10E 21 NE
136 591073 AM 60-184 21N 10E 21 NE
137 591074 AM 60-185 21N 10E 22 NW
138 591075 AM 60-186 21N 10E 22 NW
139 591076 AM 60-187 21N 10E 22 NE
140 591077 AM 60-188 21N 10E 22 NE
141 591078 AM 60-189 21N 10E 23 NW
142 591079 AM 60-190 21N 10E 23 NW
143 591080 AM 60-191 21N 10E 23 NE
144 591081 AM 60-192 21N 10E 23 NE
145 591082 AM 60-193 21N 10E 24 NW
146 591083 AM 61-176 21N 10E 18 SE
147 591084 AM 61-177 21N 10E 17 SW
148 591085 AM 61-178 21N 10E 17 SW
149 591086 AM 61-179 21N 10E 17 SE
150 591087 AM 61-180 21N 10E 17 SE
151 591088 AM 61-181 21N 10E 16 SW
152 591089 AM 61-182 21N 10E 16 SW
153 591090 AM 61-183 21N 10E 16 SE
154 591091 AM 61-184 21N 10E 16 SE
155 591092 AM 61-185 21N 10E 15 SW
156 591093 AM 61-186 21N 10E 15 SW
157 591094 AM 61-187 21N 10E 15 SE
158 591095 AM 61-188 21N 10E 15 SE
159 591096 AM 61-189 21N 10E 14 SW
160 591097 AM 61-190 21N 10E 14 SW
161 591098 AM 61-191 21N 10E 14 SE

  
Arctic ProjectPage 429
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

162 591099 AM 61-192 21N 10E 14 SE
163 591100 AM 61-193 21N 10E 13 SW
164 591101 AM 62-176 21N 10E 18 SE
165 591102 AM 62-177 21N 10E 17 SW
166 591103 AM 62-178 21N 10E 17 SW
167 591104 AM 62-179 21N 10E 17 SE
168 591105 AM 62-180 21N 10E 17 SE
169 591106 AM 62-181 21N 10E 16 SW
170 591107 AM 62-182 21N 10E 16 SW
171 591108 AM 62-187 21N 10E 15 SE
172 591109 AM 62-188 21N 10E 15 SE
173 591110 AM 62-189 21N 10E 14 SW
174 591111 AM 62-190 21N 10E 14 SW
175 591112 AM 62-191 21N 10E 14 SE
176 591113 AM 62-192 21N 10E 14 SE
177 591114 AM 62-193 21N 10E 13 SW
178 591115 AM 63-173 21N 10E 18 NW
179 591116 AM 63-174 21N 10E 18 NW
180 591117 AM 63-175 21N 10E 18 NE
181 591118 AM 63-176 21N 10E 18 NE
182 591119 AM 63-177 21N 10E 17 NW
183 591120 AM 63-178 21N 10E 17 NW
184 591121 AM 63-179 21N 10E 17 NE
185 591122 AM 63-180 21N 10E 17 NE
186 591123 AM 63-181 21N 10E 16 NW
187 591124 AM 63-182 21N 10E 16 NW
188 591125 AM 63-187 21N 10E 15 NE
189 591126 AM 63-188 21N 10E 15 NE
190 591127 AM 63-189 21N 10E 14 NW
191 591128 AM 63-190 21N 10E 14 NW
192 591129 AM 63-191 21N 10E 14 NE
193 591130 AM 63-192 21N 10E 14 NE
194 591131 AM 63-193 21N 10E 13 NW
195 591132 AM 64-173 21N 10E 18 NW
196 591133 AM 64-174 21N 10E 18 NW
197 591134 AM 64-175 21N 10E 18 NE
198 591135 AM 64-176 21N 10E 18 NE
199 591136 AM 64-177 21N 10E 17 NW
200 591137 AM 64-178 21N 10E 17 NW
201 591138 AM 64-179 21N 10E 17 NE
202 591139 AM 64-180 21N 10E 17 NE
203 591140 AM 64-181 21N 10E 16 NW
204 591141 AM 64-182 21N 10E 16 NW
205 591142 AM 64-183 21N 10E 16 NE

  
Arctic ProjectPage 430
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

206 591143 AM 64-184 21N 10E 16 NE
207 591144 AM 64-185 21N 10E 15 NW
208 591145 AM 64-186 21N 10E 15 NW
209 591146 AM 64-187 21N 10E 15 NE
210 591147 AM 64-188 21N 10E 15 NE
211 591148 AM 64-189 21N 10E 14 NW
212 591149 AM 64-190 21N 10E 14 NW
213 591150 AM 64-191 21N 10E 14 NE
214 591151 AM 64-192 21N 10E 14 NE
215 591152 AM 64-193 21N 10E 13 NW
216 591153 AM 65-173 21N 10E 7 SW
217 591154 AM 65-174 21N 10E 7 SW
218 591155 AM 65-175 21N 10E 7 SE
219 591156 AM 65-176 21N 10E 7 SE
220 591157 AM 65-177 21N 10E 8 SW
221 591158 AM 65-178 21N 10E 8 SW
222 591159 AM 65-179 21N 10E 8 SE
223 591160 AM 65-180 21N 10E 8 SE
224 591161 AM 65-181 21N 10E 9 SW
225 591162 AM 65-182 21N 10E 9 SW
226 591163 AM 65-183 21N 10E 9 SE
227 591164 AM 65-184 21N 10E 9 SE
228 591165 AM 65-185 21N 10E 10 SW
229 591166 AM 65-186 21N 10E 10 SW
230 591167 AM 65-187 21N 10E 10 SE
231 591168 AM 65-188 21N 10E 10 SE
232 591169 AM 65-189 21N 10E 11 SW
233 591170 AM 65-190 21N 10E 11 SW
234 591171 AM 65-191 21N 10E 11 SE
235 591172 AM 65-192 21N 10E 11 SE
236 591173 AM 65-193 21N 10E 12 SW
237 591174 AM 66-173 21N 10E 7 SW
238 591175 AM 66-174 21N 10E 7 SW
239 591176 AM 66-175 21N 10E 7 SE
240 591177 AM 66-176 21N 10E 7 SE
241 591178 AM 66-177 21N 10E 8 SW
242 591179 AM 66-178 21N 10E 8 SW
243 591180 AM 66-179 21N 10E 8 SE
244 591181 AM 66-180 21N 10E 8 SE
245 591182 AM 66-181 21N 10E 9 SW
246 591183 AM 66-182 21N 10E 9 SW
247 591184 AM 66-183 21N 10E 9 SE
248 591185 AM 66-184 21N 10E 9 SE
249 591186 AM 66-185 21N 10E 10 SW

  
Arctic ProjectPage 431
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

250 591187 AM 66-186 21N 10E 10 SW
251 591188 AM 66-187 21N 10E 10 SE
252 591189 AM 66-188 21N 10E 10 SE
253 591190 AM 66-189 21N 10E 11 SW
254 591191 AM 66-190 21N 10E 11 SW
255 591192 AM 66-191 21N 10E 11 SE
256 591193 AM 66-192 21N 10E 11 SE
257 591194 AM 66-193 21N 10E 12 SW
258 591195 AM 67-173 21N 10E 7 NW
259 591196 AM 67-174 21N 10E 7 NW
260 591197 AM 67-175 21N 10E 7 NE
261 591198 AM 67-176 21N 10E 7 NE
262 591199 AM 67-177 21N 10E 8 NW
263 591200 AM 67-178 21N 10E 8 NW
264 591201 AM 67-179 21N 10E 8 NE
265 591202 AM 67-180 21N 10E 8 NE
266 591203 AM 67-181 21N 10E 9 NW
267 591204 AM 67-182 21N 10E 9 NW
268 591205 AM 67-183 21N 10E 9 NE
269 591206 AM 67-184 21N 10E 9 NE
270 591207 AM 67-185 21N 10E 10 NW
271 591208 AM 67-186 21N 10E 10 NW
272 591209 AM 67-187 21N 10E 10 NE
273 591210 AM 67-188 21N 10E 10 NE
274 591211 AM 67-189 21N 10E 11 NW
275 591212 AM 67-190 21N 10E 11 NW
276 591213 AM 67-191 21N 10E 11 NE
277 591214 AM 67-192 21N 10E 11 NE
278 591215 AM 67-193 21N 10E 12 NW
279 591216 AM 67-194 21N 10E 12 NW
280 591217 AM 67-195 21N 10E 12 NE
281 591218 AM 67-196 21N 10E 12 NE
282 591219 AM 49-206 21N 11E 33 SW
283 591220 AM 49-207 21N 11E 33 SE
284 591221 AM 49-208 21N 11E 33 SE
285 591222 AM 49-209 21N 11E 34 SW
286 591223 AM 49-210 21N 11E 34 SW
287 591224 AM 49-214 21N 11E 35 SW
288 591225 AM 49-215 21N 11E 35 SE
289 591226 AM 49-216 21N 11E 35 SE
290 591227 AM 49-217 21N 11E 36 SW
291 591228 AM 49-218 21N 11E 36 SW
292 591229 AM 49-219 21N 11E 36 SE
293 591230 AM 49-220 21N 11E 36 SE

  
Arctic ProjectPage 432
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

294 591231 AM 50-206 21N 11E 33 SW
295 591232 AM 50-207 21N 11E 33 SE
296 591233 AM 50-208 21N 11E 33 SE
297 591234 AM 50-209 21N 11E 34 SW
298 591235 AM 50-210 21N 11E 34 SW
299 591236 AM 50-211 21N 11E 34 SE
300 591237 AM 50-213 21N 11E 35 SW
301 591238 AM 50-214 21N 11E 35 SW
302 591239 AM 50-215 21N 11E 35 SE
303 591240 AM 50-216 21N 11E 35 SE
304 591241 AM 50-217 21N 11E 36 SW
305 591242 AM 50-218 21N 11E 36 SW
306 591243 AM 50-219 21N 11E 36 SE
307 591244 AM 50-220 21N 11E 36 SE
308 591245 AM 51-206 21N 11E 33 NW
309 591246 AM 51-207 21N 11E 33 NE
310 591247 AM 51-208 21N 11E 33 NE
311 591248 AM 51-209 21N 11E 34 NW
312 591249 AM 51-210 21N 11E 34 NW
313 591250 AM 51-211 21N 11E 34 NE
314 591251 AM 51-212 21N 11E 34 NE
315 591252 AM 51-213 21N 11E 35 NW
316 591253 AM 51-214 21N 11E 35 NW
317 591254 AM 51-215 21N 11E 35 NE
318 591255 AM 51-216 21N 11E 35 NE
319 591256 AM 51-217 21N 11E 36 NW
320 591257 AM 51-218 21N 11E 36 NW
321 591258 AM 51-219 21N 11E 36 NE
322 591259 AM 51-220 21N 11E 36 NE
323 591260 AM 52-206 21N 11E 33 NW
324 591261 AM 52-207 21N 11E 33 NE
325 591262 AM 52-208 21N 11E 33 NE
326 591263 AM 52-209 21N 11E 34 NW
327 591264 AM 52-210 21N 11E 34 NW
328 591265 AM 52-211 21N 11E 34 NE
329 591266 AM 52-212 21N 11E 34 NE
330 591267 AM 52-213 21N 11E 35 NW
331 591268 AM 52-214 21N 11E 35 NW
332 591269 AM 52-215 21N 11E 35 NE
333 591270 AM 52-216 21N 11E 35 NE
334 591271 AM 52-217 21N 11E 36 NW
335 591272 AM 52-218 21N 11E 36 NW
336 591273 AM 52-219 21N 11E 36 NE
337 591274 AM 52-220 21N 11E 36 NE

  
Arctic ProjectPage 433
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

338 591275 AM 53-206 21N 11E 28 SW
339 591276 AM 53-207 21N 11E 28 SE
340 591277 AM 53-208 21N 11E 28 SE
341 591278 AM 53-209 21N 11E 27 SW
342 591279 AM 53-210 21N 11E 27 SW
343 591280 AM 53-211 21N 11E 27 SE
344 591281 AM 53-212 21N 11E 27 SE
345 591282 AM 53-213 21N 11E 26 SW
346 591283 AM 53-214 21N 11E 26 SW
347 591284 AM 53-215 21N 11E 26 SE
348 591285 AM 53-216 21N 11E 26 SE
349 591286 AM 53-217 21N 11E 25 SW
350 591287 AM 53-218 21N 11E 25 SW
351 591288 AM 53-219 21N 11E 25 SE
352 591289 AM 53-220 21N 11E 25 SE
353 591290 AM 54-206 21N 11E 28 SW
354 591291 AM 54-207 21N 11E 28 SE
355 591292 AM 54-208 21N 11E 28 SE
356 591293 AM 54-209 21N 11E 27 SW
357 591294 AM 54-210 21N 11E 27 SW
358 591295 AM 54-211 21N 11E 27 SE
359 591296 AM 54-212 21N 11E 27 SE
360 591297 AM 54-213 21N 11E 26 SW
361 591298 AM 54-214 21N 11E 26 SW
362 591299 AM 54-215 21N 11E 26 SE
363 591300 AM 54-216 21N 11E 26 SE
364 591301 AM 54-217 21N 11E 25 SW
365 591302 AM 54-218 21N 11E 25 SW
366 591303 AM 54-219 21N 11E 25 SE
367 591304 AM 54-220 21N 11E 25 SE
368 591305 AM 55-206 21N 11E 28 NW
369 591306 AM 55-207 21N 11E 28 NE
370 591307 AM 55-208 21N 11E 28 NE
371 591308 AM 55-209 21N 11E 27 NW
372 591309 AM 55-210 21N 11E 27 NW
373 591310 AM 55-211 21N 11E 27 NE
374 591311 AM 55-212 21N 11E 27 NE
375 591312 AM 55-213 21N 11E 26 NW
376 591313 AM 55-214 21N 11E 26 NW
377 591314 AM 55-215 21N 11E 26 NE
378 591315 AM 55-216 21N 11E 26 NE
379 591316 AM 55-217 21N 11E 25 NW
380 591317 AM 55-218 21N 11E 25 NW
381 591318 AM 55-219 21N 11E 25 NE

  
Arctic ProjectPage 434
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

382 591319 AM 55-220 21N 11E 25 NE
383 591320 AM 56-206 21N 11E 28 NW
384 591321 AM 56-207 21N 11E 28 NE
385 591322 AM 56-208 21N 11E 28 NE
386 591323 AM 56-209 21N 11E 27 NW
387 591324 AM 56-210 21N 11E 27 NW
388 591325 AM 56-211 21N 11E 27 NE
389 591326 AM 56-212 21N 11E 27 NE
390 591327 AM 56-213 21N 11E 26 NW
391 591328 AM 56-214 21N 11E 26 NW
392 591329 AM 56-215 21N 11E 26 NE
393 591330 AM 56-216 21N 11E 26 NE
394 591331 AM 56-217 21N 11E 25 NW
395 591332 AM 56-218 21N 11E 25 NW
396 591333 AM 56-219 21N 11E 25 NE
397 591334 AM 56-220 21N 11E 25 NE
398 591335 AM 57-206 21N 11E 21 SW
399 591336 AM 57-207 21N 11E 21 SE
400 591337 AM 57-208 21N 11E 21 SE
401 591338 AM 57-209 21N 11E 22 SW
402 591339 AM 57-210 21N 11E 22 SW
403 591340 AM 57-211 21N 11E 22 SE
404 591341 AM 57-212 21N 11E 22 SE
405 591342 AM 57-213 21N 11E 23 SW
406 591343 AM 57-214 21N 11E 23 SW
407 591344 AM 57-215 21N 11E 23 SE
408 591345 AM 57-216 21N 11E 23 SE
409 591346 AM 57-217 21N 11E 24 SW
410 591347 AM 57-218 21N 11E 24 SW
411 591348 AM 57-219 21N 11E 24 SE
412 591349 AM 57-220 21N 11E 24 SE
413 591350 AM 58-206 21N 11E 21 SW
414 591351 AM 58-207 21N 11E 21 SE
415 591352 AM 58-208 21N 11E 21 SE
416 591353 AM 58-209 21N 11E 22 SW
417 591354 AM 58-210 21N 11E 22 SW
418 591355 AM 58-211 21N 11E 22 SE
419 591356 AM 58-212 21N 11E 22 SE
420 591357 AM 58-213 21N 11E 23 SW
421 591358 AM 58-214 21N 11E 23 SW
422 591359 AM 58-215 21N 11E 23 SE
423 591360 AM 58-216 21N 11E 23 SE
424 591361 AM 58-217 21N 11E 24 SW
425 591362 AM 58-218 21N 11E 24 SW

  
Arctic ProjectPage 435
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

426 591363 AM 58-219 21N 11E 24 SE
427 591364 AM 58-220 21N 11E 24 SE
428 591365 AM 59-202 21N 11E 20 NW
429 591366 AM 59-203 21N 11E 20 NE
430 591367 AM 59-204 21N 11E 20 NE
431 591368 AM 59-205 21N 11E 21 NW
432 591369 AM 59-206 21N 11E 21 NW
433 591370 AM 59-207 21N 11E 21 NE
434 591371 AM 59-208 21N 11E 21 NE
435 591372 AM 59-209 21N 11E 22 NW
436 591373 AM 59-210 21N 11E 22 NW
437 591374 AM 59-211 21N 11E 22 NE
438 591375 AM 59-212 21N 11E 22 NE
439 591376 AM 59-213 21N 11E 23 NW
440 591377 AM 59-214 21N 11E 23 NW
441 591378 AM 59-215 21N 11E 23 NE
442 591379 AM 59-216 21N 11E 23 NE
443 591380 AM 59-217 21N 11E 24 NW
444 591381 AM 59-218 21N 11E 24 NW
445 591382 AM 60-202 21N 11E 20 NW
446 591383 AM 60-203 21N 11E 20 NE
447 591384 AM 60-204 21N 11E 20 NE
448 591385 AM 60-205 21N 11E 21 NW
449 591386 AM 60-206 21N 11E 21 NW
450 591387 AM 60-207 21N 11E 21 NE
451 591388 AM 60-208 21N 11E 21 NE
452 591389 AM 60-209 21N 11E 22 NW
453 591390 AM 60-210 21N 11E 22 NW
454 591391 AM 60-211 21N 11E 22 NE
455 591392 AM 60-212 21N 11E 22 NE
456 591393 AM 60-213 21N 11E 23 NW
457 591394 AM 60-214 21N 11E 23 NW
458 591395 AM 60-215 21N 11E 23 NE
459 591396 AM 60-216 21N 11E 23 NE
460 591397 AM 60-217 21N 11E 24 NW
461 591398 AM 60-218 21N 11E 24 NW
462 591399 AM 61-202 21N 11E 17 SW
463 591400 AM 61-203 21N 11E 17 SE
464 591401 AM 61-204 21N 11E 17 SE
465 591402 AM 61-205 21N 11E 16 SW
466 591403 AM 61-206 21N 11E 16 SW
467 591404 AM 61-207 21N 11E 16 SE
468 591405 AM 61-208 21N 11E 16 SE
469 591406 AM 61-209 21N 11E 15 SW

  
Arctic ProjectPage 436
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

470 591407 AM 61-210 21N 11E 15 SW
471 591408 AM 61-211 21N 11E 15 SE
472 591409 AM 61-212 21N 11E 15 SE
473 591410 AM 61-213 21N 11E 14 SW
474 591411 AM 61-214 21N 11E 14 SW
475 591412 AM 61-215 21N 11E 14 SE
476 591413 AM 61-216 21N 11E 14 SE
477 591414 AM 61-217 21N 11E 13 SW
478 591415 AM 61-218 21N 11E 13 SW
479 591416 AM 62-202 21N 11E 17 SW
480 591417 AM 62-203 21N 11E 17 SE
481 591418 AM 62-204 21N 11E 17 SE
482 591419 AM 62-205 21N 11E 16 SW
483 591420 AM 62-206 21N 11E 16 SW
484 591421 AM 62-207 21N 11E 16 SE
485 591422 AM 62-208 21N 11E 16 SE
486 591423 AM 62-209 21N 11E 15 SW
487 591424 AM 62-210 21N 11E 15 SW
488 591425 AM 62-211 21N 11E 15 SE
489 591426 AM 62-212 21N 11E 15 SE
490 591427 AM 62-213 21N 11E 14 SW
491 591428 AM 62-214 21N 11E 14 SW
492 591429 AM 62-215 21N 11E 14 SE
493 591430 AM 62-216 21N 11E 14 SE
494 591431 AM 62-217 21N 11E 13 SW
495 591432 AM 62-218 21N 11E 13 SW
496 591433 AM 63-202 21N 11E 17 NW
497 591434 AM 63-203 21N 11E 17 NE
498 591435 AM 63-204 21N 11E 17 NE
499 591436 AM 63-205 21N 11E 16 NW
500 591437 AM 63-206 21N 11E 16 NW
501 591438 AM 63-207 21N 11E 16 NE
502 591439 AM 63-208 21N 11E 16 NE
503 591440 AM 63-209 21N 11E 15 NW
504 591441 AM 63-210 21N 11E 15 NW
505 591442 AM 63-211 21N 11E 15 NE
506 591443 AM 63-212 21N 11E 15 NE
507 591444 AM 64-202 21N 11E 17 NW
508 591445 AM 64-203 21N 11E 17 NE
509 591446 AM 64-204 21N 11E 17 NE
510 591447 AM 64-205 21N 11E 16 NW
511 591448 AM 64-206 21N 11E 16 NW
512 591449 AM 64-207 21N 11E 16 NE
513 591450 AM 64-208 21N 11E 16 NE

  
Arctic ProjectPage 437
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

514 591451 AM 64-209 21N 11E 15 NW
515 591452 AM 64-210 21N 11E 15 NW
516 591453 AM 64-211 21N 11E 15 NE
517 591454 AM 64-212 21N 11E 15 NE
518 591455 AM 65-202 21N 11E 8 SW
519 591456 AM 65-203 21N 11E 8 SE
520 591457 AM 65-204 21N 11E 8 SE
521 591458 AM 65-205 21N 11E 9 SW
522 591459 AM 65-206 21N 11E 9 SW
523 591460 AM 65-207 21N 11E 9 SE
524 591461 AM 65-208 21N 11E 9 SE
525 591462 AM 65-209 21N 11E 10 SW
526 591463 AM 65-210 21N 11E 10 SW
527 591464 AM 65-211 21N 11E 10 SE
528 591465 AM 65-212 21N 11E 10 SE
529 591466 AM 66-202 21N 11E 8 SW
530 591467 AM 66-203 21N 11E 8 SE
531 591468 AM 66-204 21N 11E 8 SE
532 591469 AM 66-205 21N 11E 9 SW
533 591470 AM 66-206 21N 11E 9 SW
534 591471 AM 66-207 21N 11E 9 SE
535 591472 AM 66-208 21N 11E 9 SE
536 591473 AM 66-209 21N 11E 10 SW
537 591474 AM 66-210 21N 11E 10 SW
538 591475 AM 66-211 21N 11E 10 SE
539 591476 AM 66-212 21N 11E 10 SE
540 591477 AM 67-197 21N 11E 7 NW
541 591478 AM 67-198 21N 11E 7 NW
542 591479 AM 67-199 21N 11E 7 NE
543 591480 AM 67-200 21N 11E 7 NE
544 591481 AM 67-201 21N 11E 8 NW
545 591482 AM 67-202 21N 11E 8 NW
546 591483 AM 67-203 21N 11E 8 NE
547 591484 AM 67-204 21N 11E 8 NE
548 591485 AM 67-205 21N 11E 9 NW
549 591486 AM 67-206 21N 11E 9 NW
550 591487 AM 67-207 21N 11E 9 NE
551 591488 AM 67-208 21N 11E 9 NE
552 591489 AM 67-209 21N 11E 10 NW
553 591490 AM 67-210 21N 11E 10 NW
554 591491 AM 67-211 21N 11E 10 NE
555 591492 AM 67-212 21N 11E 10 NE
556 591493 AM 68-208 21N 11E 9 NE
557 591494 AM 68-209 21N 11E 10 NW

  
Arctic ProjectPage 438
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

558 591495 AM 68-210 21N 11E 10 NW
559 591496 AM 68-211 21N 11E 10 NE
560 591497 AM 68-212 21N 11E 10 NE
561 591498 AM 69-208 21N 11E 4 SE
562 591499 AM 69-209 21N 11E 3 SW
563 591500 AM 69-210 21N 11E 3 SW
564 591501 AM 69-211 21N 11E 3 SE
565 591502 AM 69-212 21N 11E 3 SE
566 591503 AM 49-221 21N 12E 31 SW
567 591504 AM 49-222 21N 12E 31 SW
568 591505 AM 49-223 21N 12E 31 SE
569 591506 AM 49-224 21N 12E 31 SE
570 591507 AM 49-225 21N 12E 32 SW
571 591508 AM 49-226 21N 12E 32 SW
572 591509 AM 49-227 21N 12E 32 SE
573 591510 AM 49-228 21N 12E 32 SE
574 591511 AM 49-229 21N 12E 33 SW
575 591512 AM 49-230 21N 12E 33 SW
576 591513 AM 50-221 21N 12E 31 SW
577 591514 AM 50-222 21N 12E 31 SW
578 591515 AM 50-223 21N 12E 31 SE
579 591516 AM 50-224 21N 12E 31 SE
580 591517 AM 50-225 21N 12E 32 SW
581 591518 AM 50-226 21N 12E 32 SW
582 591519 AM 50-227 21N 12E 32 SE
583 591520 AM 50-228 21N 12E 32 SE
584 591521 AM 50-229 21N 12E 33 SW
585 591522 AM 50-230 21N 12E 33 SW
586 591523 AM 51-221 21N 12E 31 NW
587 591524 AM 51-222 21N 12E 31 NW
588 591525 AM 51-223 21N 12E 31 NE
589 591526 AM 51-224 21N 12E 31 NE
590 591527 AM 51-225 21N 12E 32 NW
591 591528 AM 51-226 21N 12E 32 NW
592 591529 AM 51-227 21N 12E 32 NE
593 591530 AM 51-228 21N 12E 32 NE
594 591531 AM 51-229 21N 12E 33 NW
595 591532 AM 51-230 21N 12E 33 NW
596 591533 AM 52-221 21N 12E 31 NW
597 591534 AM 52-222 21N 12E 31 NW
598 591535 AM 52-223 21N 12E 31 NE
599 591536 AM 52-224 21N 12E 31 NE
600 591537 AM 52-225 21N 12E 32 NW
601 591538 AM 52-226 21N 12E 32 NW

  
Arctic ProjectPage 439
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

602 591539 AM 52-227 21N 12E 32 NE
603 591540 AM 52-228 21N 12E 32 NE
604 591541 AM 52-229 21N 12E 33 NW
605 591542 AM 52-230 21N 12E 33 NW
606 591543 AM 53-221 21N 12E 30 SW
607 591544 AM 53-222 21N 12E 30 SW
608 591545 AM 53-223 21N 12E 30 SE
609 591546 AM 53-224 21N 12E 30 SE
610 591547 AM 54-221 21N 12E 30 SW
611 591548 AM 54-222 21N 12E 30 SW
612 591549 AM 54-223 21N 12E 30 SE
613 591550 AM 54-224 21N 12E 30 SE
614 591551 AM 55-221 21N 12E 30 NW
615 591552 AM 55-222 21N 12E 30 NW
616 591553 AM 55-223 21N 12E 30 NE
617 591554 AM 55-224 21N 12E 30 NE
618 591555 AM 56-221 21N 12E 30 NW
619 591556 AM 56-222 21N 12E 30 NW
620 591557 AM 56-223 21N 12E 30 NE
621 591558 AM 56-224 21N 12E 30 NE
622 591575 AM 37-226 20N 12E 16 SW
623 591576 AM 37-227 20N 12E 16 SE
624 591577 AM 37-228 20N 12E 16 SE
625 591578 AM 37-229 20N 12E 15 SW
626 591579 AM 37-230 20N 12E 15 SW
627 591590 AM 38-226 20N 12E 16 SW
628 591591 AM 38-227 20N 12E 16 SE
629 591592 AM 38-228 20N 12E 16 SE
630 591593 AM 38-229 20N 12E 15 SW
631 591594 AM 38-230 20N 12E 15 SW
632 591605 AM 39-226 20N 12E 16 NW
633 591606 AM 39-227 20N 12E 16 NE
634 591607 AM 39-228 20N 12E 16 NE
635 591608 AM 39-229 20N 12E 15 NW
636 591609 AM 39-230 20N 12E 15 NW
637 591620 AM 40-226 20N 12E 16 NW
638 591621 AM 40-227 20N 12E 16 NE
639 591622 AM 40-228 20N 12E 16 NE
640 591623 AM 40-229 20N 12E 15 NW
641 591624 AM 40-230 20N 12E 15 NW
642 591635 AM 41-225 20N 12E 9 SW
643 591636 AM 41-226 20N 12E 9 SW
644 591637 AM 41-227 20N 12E 9 SE
645 591638 AM 41-228 20N 12E 9 SE

  
Arctic ProjectPage 440
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

646 591639 AM 41-229 20N 12E 10 SW
647 591640 AM 41-230 20N 12E 10 SW
648 591648 AM 42-223 20N 12E 8 SE
649 591649 AM 42-224 20N 12E 8 SE
650 591650 AM 42-225 20N 12E 9 SW
651 591651 AM 42-226 20N 12E 9 SW
652 591652 AM 42-227 20N 12E 9 SE
653 591653 AM 42-228 20N 12E 9 SE
654 591654 AM 42-229 20N 12E 10 SW
655 591655 AM 42-230 20N 12E 10 SW
656 591661 AM 43-221 20N 12E 8 NW
657 591662 AM 43-222 20N 12E 8 NW
658 591663 AM 43-223 20N 12E 8 NE
659 591664 AM 43-224 20N 12E 8 NE
660 591665 AM 43-225 20N 12E 9 NW
661 591666 AM 43-226 20N 12E 9 NW
662 591667 AM 43-227 20N 12E 9 NE
663 591668 AM 43-228 20N 12E 9 NE
664 591669 AM 43-229 20N 12E 10 NW
665 591670 AM 43-230 20N 12E 10 NW
666 591676 AM 44-219 20N 12E 7 NE
667 591677 AM 44-220 20N 12E 7 NE
668 591678 AM 44-221 20N 12E 8 NW
669 591679 AM 44-222 20N 12E 8 NW
670 591680 AM 44-223 20N 12E 8 NE
671 591681 AM 44-224 20N 12E 8 NE
672 591682 AM 44-225 20N 12E 9 NW
673 591683 AM 44-226 20N 12E 9 NW
674 591684 AM 44-227 20N 12E 9 NE
675 591685 AM 44-228 20N 12E 9 NE
676 591686 AM 44-229 20N 12E 10 NW
677 591687 AM 44-230 20N 12E 10 NW
678 591693 AM 45-217 20N 12E 6 SW
679 591694 AM 45-218 20N 12E 6 SW
680 591695 AM 45-219 20N 12E 6 SE
681 591696 AM 45-220 20N 12E 6 SE
682 591697 AM 45-221 20N 12E 5 SW
683 591698 AM 45-222 20N 12E 5 SW
684 591699 AM 45-223 20N 12E 5 SE
685 591700 AM 45-224 20N 12E 5 SE
686 591701 AM 45-225 20N 12E 4 SW
687 591702 AM 45-226 20N 12E 4 SW
688 591703 AM 45-227 20N 12E 4 SE
689 591704 AM 45-228 20N 12E 4 SE

  
Arctic ProjectPage 441
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

690 591705 AM 45-229 20N 12E 3 SW
691 591706 AM 45-230 20N 12E 3 SW
692 591712 AM 46-217 20N 12E 6 SW
693 591713 AM 46-218 20N 12E 6 SW
694 591714 AM 46-219 20N 12E 6 SE
695 591715 AM 46-220 20N 12E 6 SE
696 591716 AM 46-221 20N 12E 5 SW
697 591717 AM 46-222 20N 12E 5 SW
698 591718 AM 46-223 20N 12E 5 SE
699 591719 AM 46-224 20N 12E 5 SE
700 591720 AM 46-225 20N 12E 4 SW
701 591721 AM 46-226 20N 12E 4 SW
702 591722 AM 46-227 20N 12E 4 SE
703 591723 AM 46-228 20N 12E 4 SE
704 591724 AM 46-229 20N 12E 3 SW
705 591725 AM 46-230 20N 12E 3 SW
706 591731 AM 47-217 20N 12E 6 NW
707 591732 AM 47-218 20N 12E 6 NW
708 591733 AM 47-219 20N 12E 6 NE
709 591734 AM 47-220 20N 12E 6 NE
710 591735 AM 47-221 20N 12E 5 NW
711 591736 AM 47-222 20N 12E 5 NW
712 591737 AM 47-223 20N 12E 5 NE
713 591738 AM 47-224 20N 12E 5 NE
714 591739 AM 47-225 20N 12E 4 NW
715 591740 AM 47-226 20N 12E 4 NW
716 591741 AM 47-227 20N 12E 4 NE
717 591742 AM 47-228 20N 12E 4 NE
718 591743 AM 47-229 20N 12E 3 NW
719 591744 AM 47-230 20N 12E 3 NW
720 591745 AM 48-217 20N 12E 6 NW
721 591746 AM 48-218 20N 12E 6 NW
722 591747 AM 48-219 20N 12E 6 NE
723 591748 AM 48-220 20N 12E 6 NE
724 591749 AM 48-221 20N 12E 5 NW
725 591750 AM 48-222 20N 12E 5 NW
726 591751 AM 48-223 20N 12E 5 NE
727 591752 AM 48-224 20N 12E 5 NE
728 591753 AM 48-225 20N 12E 4 NW
729 591754 AM 48-226 20N 12E 4 NW
730 591755 AM 48-227 20N 12E 4 NE
731 591756 AM 48-228 20N 12E 4 NE
732 591757 AM 48-229 20N 12E 3 NW
733 591758 AM 48-230 20N 12E 3 NW

  
Arctic ProjectPage 442
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

734 622359 Eggplant 1 21N 10E 26 NW
735 622360 Eggplant 2 21N 10E 26 NW
736 622361 Eggplant 3 21N 10E 26 NE
737 622362 Eggplant 4 21N 10E 26 NE
738 622363 Eggplant 5 21N 10E 25 NW
739 622364 Eggplant 6 21N 10E 25 NW
740 622365 Eggplant 7 21N 10E 26 SW
741 622366 Eggplant 8 21N 10E 26 SE
742 622367 Eggplant 9 21N 10E 25 SW
743 622368 Eggplant 10 21N 10E 34 NW
744 622369 Eggplant 11 21N 10E 34 NE
745 622370 Eggplant 12 21N 10E 35 NW
746 622371 Eggplant 13 21N 10E 35 NE
747 622372 Eggplant 14 21N 10E 36 NW
748 622373 Eggplant 15 21N 10E 36 NE
749 622374 Eggplant 16 21N 11E 31 NW
750 622375 Eggplant 17 21N 11E 31 NE
751 622376 Eggplant 18 21N 11E 32 NW
752 622377 Eggplant 19 21N 10E 34 SW
753 622378 Eggplant 20 21N 10E 34 SE
754 622379 Eggplant 21 21N 10E 35 SW
755 622380 Eggplant 22 21N 10E 35 SE
756 622381 Eggplant 23 21N 10E 36 SW
757 622382 Eggplant 24 21N 10E 36 SE
758 622383 Eggplant 25 21N 11E 31 SW
759 622384 Eggplant 26 21N 11E 31 SE
760 622385 Eggplant 27 21N 11E 32 SW
761 622386 Eggplant 28 21N 11E 32 SE
762 622387 Eggplant 29 21N 11E 33 SW
763 622388 Eggplant 30 21N 11E 33 SW
764 626222 LUK 1 22N 10E 8 NW
765 626223 LUK 2 22N 10E 8 NE
766 626224 LUK 3 22N 10E 9 NW
767 626225 LUK 4 22N 10E 9 NE
768 626226 LUK 5 22N 10E 10 NW
769 626227 LUK 6 22N 10E 10 NE
770 626228 LUK 7 22N 10E 11 NW
771 626229 LUK 8 22N 10E 11 NE
772 626230 LUK 9 22N 10E 8 SE
773 626231 LUK 10 22N 10E 9 SW
774 626232 LUK 11 22N 10E 9 SE
775 626233 LUK 12 22N 10E 10 SW
776 626234 LUK 13 22N 10E 10 SE
777 626235 LUK 14 22N 10E 11 SW

  
Arctic ProjectPage 443
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

778 626236 LUK 15 22N 10E 11 SE
779 626237 LUK 16 22N 10E 15 NE
780 626238 LUK 17 22N 10E 14 NW
781 626239 LUK 18 22N 10E 14 NE
782 626240 LUK 19 22N 10E 13 NW
783 626241 LUK 20 22N 10E 13 NE
784 626242 LUK 21 22N 10E 14 SW
785 626243 LUK 22 22N 10E 14 SE
786 626244 LUK 23 22N 10E 13 SW
787 626245 LUK 24 22N 10E 13 SE
788 626246 LUK 25 22N 10E 23 NE
789 626247 LUK 26 22N 10E 24 NW
790 626248 LUK 27 22N 10E 24 NE
791 626249 LUK 28 22N 11E 19 NW
792 626250 LUK 29 22N 11E 19 NE
793 626251 LUK 30 22N 10E 23 SE
794 626252 LUK 31 22N 10E 24 SW
795 626253 LUK 32 22N 10E 24 SE
796 626254 LUK 33 22N 11E 19 SW
797 626255 LUK 34 22N 11E 19 SE
798 626256 LUK 35 22N 10E 27 NE
799 626257 LUK 36 22N 10E 26 NW
800 626258 LUK 37 22N 10E 26 NE
801 626259 LUK 38 22N 10E 25 NW
802 626260 LUK 39 22N 10E 25 NE
803 626261 LUK 40 22N 11E 30 NW
804 626262 LUK 41 22N 11E 30 NE
805 626263 LUK 42 22N 11E 29 NW
806 626264 LUK 43 22N 11E 29 NE
807 626265 LUK 44 22N 11E 28 NW
808 626266 LUK 45 22N 11E 28 NE
809 626267 LUK 46 22N 10E 27 SE
810 626268 LUK 47 22N 10E 26 SW
811 626269 LUK 48 22N 10E 26 SE
812 626270 LUK 49 22N 10E 25 SW
813 626271 LUK 50 22N 10E 25 SE
814 626272 LUK 51 22N 11E 30 SW
815 626273 LUK 52 22N 11E 30 SE
816 626274 LUK 53 22N 11E 29 SW
817 626275 LUK 54 22N 11E 29 SE
818 626276 LUK 55 22N 11E 28 SW
819 626277 LUK 56 22N 11E 28 SE
820 626278 LUK 57 22N 10E 34 NE
821 626279 LUK 58 22N 10E 35 NW

  
Arctic ProjectPage 444
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

822 626280 LUK 59 22N 10E 35 NE
823 626281 LUK 60 22N 10E 36 NW
824 626282 LUK 61 22N 10E 36 NE
825 626283 LUK 62 22N 11E 31 NW
826 626284 LUK 63 22N 11E 31 NE
827 626285 LUK 64 22N 11E 32 NW
828 626286 LUK 65 22N 11E 32 NE
829 626287 LUK 66 22N 11E 33 NW
830 626288 LUK 67 22N 11E 33 NE
831 626289 LUK 68 22N 11E 34 NW
832 626290 LUK 69 22N 11E 34 NE
833 626291 LUK 70 22N 11E 35 NW
834 626292 LUK 71 22N 11E 35 NE
835 626293 LUK 72 22N 11E 36 NW
836 626294 LUK 73 22N 11E 36 NE
837 626295 LUK 74 22N 10E 34 SE
838 626296 LUK 75 22N 10E 35 SW
839 626297 LUK 76 22N 10E 35 SE
840 626298 LUK 77 22N 10E 36 SW
841 626299 LUK 78 22N 10E 36 SE
842 626300 LUK 79 22N 11E 31 SW
843 626301 LUK 80 22N 11E 31 SE
844 626302 LUK 81 22N 11E 32 SW
845 626303 LUK 82 22N 11E 32 SE
846 626304 LUK 83 22N 11E 33 SW
847 626305 LUK 84 22N 11E 33 SE
848 626306 LUK 85 22N 11E 34 SW
849 626307 LUK 86 22N 11E 34 SE
850 626308 LUK 87 22N 11E 35 SW
851 626309 LUK 88 22N 11E 35 SE
852 626310 LUK 89 22N 11E 36 SW
853 626311 LUK 90 22N 11E 36 SE
854 626312 LUK 91 21N 10E 3 NE
855 626313 LUK 92 21N 10E 2 NW
856 626314 LUK 93 21N 10E 2 NE
857 626315 LUK 94 21N 10E 1 NW
858 626316 LUK 95 21N 10E 1 NE
859 626317 LUK 96 21N 11E 6 NW
860 626318 LUK 97 21N 11E 6 NE
861 626319 LUK 98 21N 11E 5 NW
862 626320 LUK 99 21N 11E 5 NE
863 626321 LUK 100 21N 11E 4 NW
864 626322 LUK 101 21N 11E 4 NE
865 626323 LUK 102 21N 11E 3 NW

  
Arctic ProjectPage 445
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

866 626324 LUK 103 21N 11E 3 NE
867 626325 LUK 104 21N 11E 2 NW
868 626326 LUK 105 21N 11E 2 NE
869 626327 LUK 106 21N 11E 1 NW
870 626328 LUK 107 21N 11E 1 NE
871 626329 LUK 108 21N 12E 6 NW
872 626330 LUK 109 21N 12E 6 NE
873 626331 LUK 110 21N 10E 1 SW
874 626332 LUK 111 21N 10E 1 SE
875 626333 LUK 112 21N 11E 6 SW
876 626334 LUK 113 21N 11E 6 SE
877 626335 LUK 114 21N 11E 5 SW
878 626336 LUK 115 21N 11E 5 SE
879 626337 LUK 116 21N 11E 4 SW
880 626338 LUK 117 21N 11E 4 NW of SE
881 626339 LUK 118 21N 11E 4 SW of SE
882 626340 LUK 119 21N 11E 4 NE of SE
883 626341 LUK 120 21N 11E 3 NW of SW
884 626342 LUK 121 21N 11E 3 NE of SW
885 626343 LUK 122 21N 11E 3 NW of SE
886 626344 LUK 123 21N 11E 3 NE of SE
887 626345 LUK 124 21N 11E 2 SW
888 626346 LUK 125 21N 11E 2 SE
889 626347 LUK 126 21N 11E 1 SW
890 626348 LUK 127 21N 11E 1 SE
891 626349 LUK 128 21N 12E 6 SW
892 626350 LUK 129 21N 12E 6 SE
893 626351 LUK 130 21N 10E 12 NW of NW
894 626352 LUK 131 21N 10E 12 NE of NW
895 626353 LUK 132 21N 10E 12 NW of NE
896 626354 LUK 133 21N 10E 12 NE of NE
897 626355 LUK 134 21N 11E 7 NW of NW
898 626356 LUK 135 21N 11E 7 NE of NW
899 626357 LUK 136 21N 11E 7 NW of NE
900 626358 LUK 137 21N 11E 7 NE of NE
901 626359 LUK 138 21N 11E 8 NW of NW
902 626360 LUK 139 21N 11E 8 NE of NW
903 626361 LUK 140 21N 11E 8 NW of NE
904 626362 LUK 141 21N 11E 8 NE of NE
905 626363 LUK 142 21N 11E 9 NW of NW
906 626364 LUK 143 21N 11E 9 NE of NW
907 626365 LUK 144 21N 11E 9 NW of NE
908 626366 LUK 145 21N 11E 11 NW
909 626367 LUK 146 21N 11E 11 NE

  
Arctic ProjectPage 446
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

910 626368 LUK 147 21N 11E 12 NW
911 626369 LUK 148 21N 11E 12 NE
912 626370 LUK 149 21N 12E 7 NW
913 626371 LUK 150 21N 12E 7 NE
914 626372 LUK 151 21N 11E 12 SW
915 626373 LUK 152 21N 11E 12 SE
916 626374 LUK 153 21N 12E 7 SW
917 626375 LUK 154 21N 12E 7 SE
918 626376 LUK 155 21N 12E 18 NW
919 626377 LUK 156 21N 12E 18 NE
920 626378 LUK 157 21N 12E 17 NW
921 626379 LUK 158 21N 12E 17 NE
922 626380 LUK 159 21N 12E 16 NW
923 626381 LUK 160 21N 12E 16 NE
924 626382 LUK 161 21N 12E 15 NW
925 626383 LUK 162 21N 12E 15 NE
926 626384 LUK 163 21N 12E 14 NW
927 626385 LUK 164 21N 12E 14 NE
928 626386 LUK 165 21N 12E 18 SW
929 626387 LUK 166 21N 12E 18 SE
930 626388 LUK 167 21N 12E 17 SW
931 626389 LUK 168 21N 12E 17 SE
932 626390 LUK 169 21N 12E 16 SW
933 626391 LUK 170 21N 12E 16 SE
934 626392 LUK 171 21N 12E 15 SW
935 626393 LUK 172 21N 12E 15 SE
936 626394 LUK 173 21N 12E 14 SW
937 626395 LUK 174 21N 12E 14 SE
938 626396 LUK 175 21N 12E 20 NW
939 626397 LUK 176 21N 12E 20 NE
940 626398 LUK 177 21N 12E 21 NW
941 626399 LUK 178 21N 12E 21 NE
942 626400 LUK 179 21N 12E 22 NW
943 626401 LUK 180 21N 12E 22 NE
944 626402 LUK 181 21N 12E 23 NW
945 626403 LUK 182 21N 12E 23 NE
946 626404 LUK 183 21N 12E 24 NW
947 626405 LUK 184 21N 12E 24 NE
948 626406 LUK 185 21N 13E 19 NW
949 626407 LUK 186 21N 13E 19 NE
950 626408 LUK 187 21N 12E 20 SW
951 626409 LUK 188 21N 12E 20 SE
952 626410 LUK 189 21N 12E 21 SW
953 626411 LUK 190 21N 12E 21 SE

  
Arctic ProjectPage 447
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

954 626412 LUK 191 21N 12E 22 SW
955 626413 LUK 192 21N 12E 22 SE
956 626414 LUK 193 21N 12E 23 SW
957 626415 LUK 194 21N 12E 23 SE
958 626416 LUK 195 21N 12E 24 SW
959 626417 LUK 196 21N 12E 24 SE
960 626418 LUK 197 21N 13E 19 SW
961 626419 LUK 198 21N 13E 19 SE
962 626420 LUK 199 21N 12E 29 NW
963 626421 LUK 200 21N 12E 29 NE
964 626422 LUK 201 21N 12E 28 NW
965 626423 LUK 202 21N 12E 28 NE
966 626424 LUK 203 21N 12E 27 NW
967 626425 LUK 204 21N 12E 27 NE
968 626426 LUK 205 21N 12E 26 NW
969 626427 LUK 206 21N 12E 26 NE
970 626428 LUK 207 21N 12E 25 NW
971 626429 LUK 208 21N 12E 25 NE
972 626430 LUK 209 21N 13E 30 NW
973 626431 LUK 210 21N 13E 30 NE
974 626432 LUK 211 21N 13E 29 NW
975 626433 LUK 212 21N 13E 29 NE
976 626434 LUK 213 21N 13E 28 NW
977 626435 LUK 214 21N 13E 28 NE
978 626436 LUK 215 21N 12E 29 SW
979 626437 LUK 216 21N 12E 29 SE
980 626438 LUK 217 21N 12E 28 SW
981 626439 LUK 218 21N 12E 28 SE
982 626440 LUK 219 21N 12E 27 SW
983 626441 LUK 220 21N 12E 27 SE
984 626442 LUK 221 21N 12E 26 SW
985 626443 LUK 222 21N 12E 26 SE
986 626444 LUK 223 21N 12E 25 SW
987 626445 LUK 224 21N 12E 25 SE
988 626446 LUK 225 21N 13E 30 SW
989 626447 LUK 226 21N 13E 30 SE
990 626448 LUK 227 21N 13E 29 SW
991 626449 LUK 228 21N 13E 29 SE
992 626450 LUK 229 21N 13E 28 SW
993 626451 LUK 230 21N 13E 28 SE
994 626452 LUK 231 21N 12E 33 NE
995 626453 LUK 232 21N 12E 34 NW
996 626454 LUK 233 21N 12E 34 NE
997 626455 LUK 234 21N 12E 35 NW

  
Arctic ProjectPage 448
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

998 626456 LUK 235 21N 12E 35 NE
999 626457 LUK 236 21N 12E 36 NW
1000 626458 LUK 237 21N 12E 36 NE
1001 626459 LUK 238 21N 13E 31 NW
1002 626460 LUK 239 21N 13E 31 NE
1003 626461 LUK 240 21N 13E 32 NW
1004 626462 LUK 241 21N 13E 32 NE
1005 626463 LUK 242 21N 13E 33 NW
1006 626464 LUK 243 21N 13E 33 NE
1007 626465 LUK 244 21N 13E 34 NW
1008 626466 LUK 245 21N 13E 34 NE
1009 626467 LUK 246 21N 13E 35 NW
1010 626468 LUK 247 21N 13E 35 NE
1011 626469 LUK 248 21N 12E 33 SE
1012 626470 LUK 249 21N 12E 34 SW
1013 626471 LUK 250 21N 12E 34 SE
1014 626472 LUK 251 21N 12E 35 SW
1015 626473 LUK 252 21N 12E 35 SE
1016 626474 LUK 253 21N 12E 36 SW
1017 626475 LUK 254 21N 12E 36 SE
1018 626476 LUK 255 21N 13E 31 SW
1019 626477 LUK 256 21N 13E 31 SE
1020 626478 LUK 257 21N 13E 32 SW
1021 626479 LUK 258 21N 13E 32 SE
1022 626480 LUK 259 21N 13E 33 SW
1023 626481 LUK 260 21N 13E 33 SE
1024 626482 LUK 261 21N 13E 34 SW
1025 626483 LUK 262 21N 13E 34 SE
1026 626484 LUK 263 21N 13E 35 SW
1027 626485 LUK 264 21N 13E 35 SE
1028 626486 LUK 265 20N 12E 3 NE
1029 626487 LUK 266 20N 12E 2 NW
1030 626488 LUK 267 20N 12E 2 NE
1031 626489 LUK 268 20N 12E 1 NW
1032 626490 LUK 269 20N 12E 1 NE
1033 626491 LUK 270 20N 13E 6 NW
1034 626492 LUK 271 20N 13E 6 NE
1035 626493 LUK 272 20N 13E 5 NW
1036 626494 LUK 273 20N 13E 5 NE
1037 626495 LUK 274 20N 13E 4 NW
1038 626496 LUK 275 20N 13E 4 NE
1039 626497 LUK 276 20N 13E 3 NW
1040 626498 LUK 277 20N 13E 3 NE
1041 626499 LUK 278 20N 13E 2 NW

  
Arctic ProjectPage 449
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1042 626500 LUK 279 20N 13E 2 NE
1043 626501 LUK 280 20N 13E 1 NW
1044 626502 LUK 281 20N 13E 1 NE
1045 626503 LUK 282 20N 14E 6 NW
1046 626504 LUK 283 20N 14E 6 NE
1047 626505 LUK 284 20N 14E 5 NW
1048 626506 LUK 285 20N 14E 5 NE
1049 626507 LUK 286 20N 12E 3 SE
1050 626508 LUK 287 20N 12E 2 SW
1051 626509 LUK 288 20N 12E 2 SE
1052 626510 LUK 289 20N 12E 1 SW
1053 626511 LUK 290 20N 12E 1 SE
1054 626512 LUK 291 20N 13E 6 SW
1055 626513 LUK 292 20N 13E 6 SE
1056 626514 LUK 293 20N 13E 5 SW
1057 626515 LUK 294 20N 13E 5 SE
1058 626516 LUK 295 20N 13E 4 SW
1059 626517 LUK 296 20N 13E 4 SE
1060 626518 LUK 297 20N 13E 3 SW
1061 626519 LUK 298 20N 13E 3 SE
1062 626520 LUK 299 20N 13E 2 SW
1063 626521 LUK 300 20N 13E 2 SE
1064 626522 LUK 301 20N 13E 1 SW
1065 626523 LUK 302 20N 13E 1 SE
1066 626524 LUK 303 20N 14E 6 SW
1067 626525 LUK 304 20N 14E 6 SE
1068 626526 LUK 305 20N 14E 5 SW
1069 626527 LUK 306 20N 14E 5 SE
1070 626528 LUK 307 20N 13E 7 NE
1071 626529 LUK 308 20N 13E 8 NW
1072 626530 LUK 309 20N 13E 8 NE
1073 626531 LUK 310 20N 13E 9 NW
1074 626532 LUK 311 20N 13E 9 NE
1075 626533 LUK 312 20N 13E 10 NW
1076 626534 LUK 313 20N 13E 10 NE
1077 626535 LUK 314 20N 13E 11 NW
1078 626536 LUK 315 20N 13E 11 NE
1079 626537 LUK 316 20N 13E 12 NW
1080 626538 LUK 317 20N 13E 12 NE
1081 626539 LUK 318 20N 14E 7 NW
1082 626540 LUK 319 20N 14E 7 NE
1083 626541 LUK 320 20N 14E 8 NW
1084 626542 LUK 321 20N 14E 8 NE
1085 626543 LUK 322 20N 14E 9 NW

  
Arctic ProjectPage 450
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1086 626544 LUK 323 20N 14E 9 NE
1087 626545 LUK 324 20N 14E 10 NW
1088 626546 LUK 325 20N 14E 10 NE
1089 626547 LUK 326 20N 14E 11 NW
1090 626548 LUK 327 20N 14E 11 NE
1091 626549 LUK 328 20N 14E 12 NW
1092 626550 LUK 329 20N 14E 12 NE
1093 626551 LUK 330 20N 15E 7 NW
1094 626552 LUK 331 20N 13E 9 SW
1095 626553 LUK 332 20N 13E 9 SE
1096 626554 LUK 333 20N 13E 10 SW
1097 626555 LUK 334 20N 13E 10 SE
1098 626556 LUK 335 20N 13E 11 SW
1099 626557 LUK 336 20N 13E 11 SE
1100 626558 LUK 337 20N 13E 12 SW
1101 626559 LUK 338 20N 13E 12 SE
1102 626560 LUK 339 20N 14E 7 SW
1103 626561 LUK 340 20N 14E 7 SE
1104 626562 LUK 341 20N 14E 8 SW
1105 626563 LUK 342 20N 14E 8 SE
1106 626564 LUK 343 20N 14E 9 SW
1107 626565 LUK 344 20N 14E 9 SE
1108 626566 LUK 345 20N 14E 10 SW
1109 626567 LUK 346 20N 14E 10 SE
1110 626568 LUK 347 20N 14E 11 SW
1111 626569 LUK 348 20N 14E 11 SE
1112 626570 LUK 349 20N 14E 12 SW
1113 626571 LUK 350 20N 14E 12 SE
1114 626572 LUK 351 20N 15E 7 SW
1115 626573 LUK 352 20N 13E 14 NW
1116 626574 LUK 353 20N 13E 14 NE
1117 626575 LUK 354 20N 13E 13 NW
1118 626576 LUK 355 20N 13E 13 NE
1119 626577 LUK 356 20N 14E 18 NW
1120 626578 LUK 357 20N 14E 18 NE
1121 626579 LUK 358 20N 14E 17 NW
1122 626580 LUK 359 20N 14E 17 NE
1123 626581 LUK 360 20N 14E 16 NW
1124 626582 LUK 361 20N 14E 16 NE
1125 626583 LUK 362 20N 14E 15 NW
1126 626584 LUK 363 20N 14E 15 NE
1127 626585 LUK 364 20N 14E 14 NW
1128 626586 LUK 365 20N 14E 14 NE
1129 626587 LUK 366 20N 14E 13 NW

  
Arctic ProjectPage 451
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1130 626588 LUK 367 20N 14E 13 NE
1131 626589 LUK 368 20N 15E 18 NW
1132 626590 LUK 369 20N 13E 14 SW
1133 626591 LUK 370 20N 13E 14 SE
1134 626592 LUK 371 20N 13E 13 SW
1135 626593 LUK 372 20N 13E 13 SE
1136 626594 LUK 373 20N 14E 18 SW
1137 626595 LUK 374 20N 14E 18 SE
1138 626596 LUK 375 20N 14E 17 SW
1139 626597 LUK 376 20N 14E 17 SE
1140 626598 LUK 377 20N 14E 16 SW
1141 626599 LUK 378 20N 14E 16 SE
1142 626600 LUK 379 20N 14E 15 SW
1143 626601 LUK 380 20N 14E 15 SE
1144 626602 LUK 381 20N 14E 14 SW
1145 626603 LUK 382 20N 14E 14 SE
1146 626604 LUK 383 20N 14E 13 SW
1147 626605 LUK 384 20N 14E 13 SE
1148 626606 LUK 385 20N 15E 18 SW
1149 626607 NORA 1 20N 12E 19 NW
1150 626608 NORA 2 20N 12E 19 NE
1151 626609 NORA 3 20N 12E 20 NW
1152 626610 NORA 4 20N 12E 20 NE
1153 626611 NORA 5 20N 12E 21 NW
1154 626612 NORA 6 20N 12E 21 NE
1155 626613 NORA 7 20N 12E 22 NW
1156 626614 NORA 8 20N 12E 22 NE
1157 626615 NORA 9 20N 12E 23 NW
1158 626616 NORA 10 20N 12E 23 NE
1159 626617 NORA 11 20N 12E 24 NW
1160 626618 NORA 12 20N 12E 19 SW
1161 626619 NORA 13 20N 12E 19 SE
1162 626620 NORA 14 20N 12E 20 SW
1163 626621 NORA 15 20N 12E 20 SE
1164 626622 NORA 16 20N 12E 21 SW
1165 626623 NORA 17 20N 12E 21 SE
1166 626624 NORA 18 20N 12E 22 SW
1167 626625 NORA 19 20N 12E 22 SE
1168 626626 NORA 20 20N 12E 23 SW
1169 626627 NORA 21 20N 12E 23 SE
1170 626628 NORA 22 20N 12E 24 SW
1171 626629 NORA 23 20N 12E 24 SE
1172 626630 NORA 24 20N 13E 19 SW
1173 626631 NORA 25 20N 12E 28 NW

  
Arctic ProjectPage 452
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1174 626632 NORA 26 20N 12E 28 NE
1175 626633 NORA 27 20N 12E 27 NW
1176 626634 NORA 28 20N 12E 27 NE
1177 626635 NORA 29 20N 12E 26 NW
1178 626636 NORA 30 20N 12E 26 NE
1179 626637 NORA 31 20N 12E 25 NW
1180 626638 NORA 32 20N 12E 25 NE
1181 626639 NORA 33 20N 13E 30 NW
1182 626640 NORA 34 20N 13E 30 NE
1183 626641 NORA 35 20N 13E 29 NW
1184 626642 NORA 36 20N 13E 29 NE
1185 626643 NORA 37 20N 13E 28 NW
1186 626644 NORA 38 20N 13E 28 NE
1187 626645 NORA 39 20N 13E 27 NW
1188 626646 NORA 40 20N 13E 27 NE
1189 626647 NORA 41 20N 12E 28 SW
1190 626648 NORA 42 20N 12E 28 SE
1191 626649 NORA 43 20N 12E 27 SW
1192 626650 NORA 44 20N 12E 27 SE
1193 626651 NORA 45 20N 12E 26 SW
1194 626652 NORA 46 20N 12E 26 SE
1195 626653 NORA 47 20N 12E 25 SW
1196 626654 NORA 48 20N 12E 25 SE
1197 626655 NORA 49 20N 13E 30 SW
1198 626656 NORA 50 20N 13E 30 SE
1199 626657 NORA 51 20N 13E 29 SW
1200 626658 NORA 52 20N 13E 29 SE
1201 626659 NORA 53 20N 13E 28 SW
1202 626660 NORA 54 20N 13E 28 SE
1203 626661 NORA 55 20N 13E 27 SW
1204 626662 NORA 56 20N 13E 27 SE
1205 626663 NORA 57 20N 12E 35 NW
1206 626664 NORA 58 20N 12E 35 NE
1207 626665 NORA 59 20N 12E 36 NW
1208 626666 NORA 60 20N 12E 36 NE
1209 626667 NORA 61 20N 13E 31 NW
1210 626668 NORA 62 20N 13E 31 NE
1211 626669 NORA 63 20N 13E 32 NW
1212 626670 NORA 64 20N 13E 32 NE
1213 626671 NORA 65 20N 13E 33 NW
1214 626672 NORA 66 20N 13E 33 NE
1215 626673 NORA 67 20N 13E 34 NW
1216 626674 NORA 68 20N 13E 34 NE
1217 626675 NORA 69 20N 12E 35 SW

  
Arctic ProjectPage 453
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1218 626676 NORA 70 20N 12E 35 SE
1219 626677 NORA 71 20N 12E 36 SW
1220 626678 NORA 72 20N 12E 36 SE
1221 626679 NORA 73 20N 13E 31 SW
1222 626680 NORA 74 20N 13E 31 SE
1223 626681 NORA 75 20N 13E 32 SW
1224 626682 NORA 76 20N 13E 32 SE
1225 626683 NORA 77 20N 13E 33 SW
1226 626684 NORA 78 20N 13E 33 SE
1227 626685 NORA 79 20N 13E 34 SW
1228 626686 NORA 80 20N 13E 34 SE
1229 629003 Mo 1 20N 15E 7 SE
1230 629004 Mo 2 20N 15E 8 SW
1231 629005 Mo 3 20N 15E 8 SE
1232 629006 Mo 4 20N 15E 9 SW
1233 629007 Mo 5 20N 15E 9 SE
1234 629008 Mo 6 20N 15E 10 SW
1235 629009 Mo 7 20N 15E 10 SE
1236 629010 Mo 8 20N 15E 11 SW
1237 629011 Mo 9 20N 15E 11 SE
1238 629012 Mo 10 20N 15E 12 SW
1239 629013 Mo 11 20N 15E 12 SE
1240 629014 Mo 12 20N 16E 7 SW
1241 629015 Mo 13 20N 16E 7 SE
1242 629016 Mo 14 20N 16E 8 SW
1243 629017 Mo 15 20N 16E 8 SE
1244 629018 Mo 16 20N 15E 18 NE
1245 629019 Mo 17 20N 15E 18 NW
1246 629020 Mo 18 20N 15E 17 NE
1247 629021 Mo 19 20N 15E 16 NW
1248 629022 Mo 20 20N 15E 16 NE
1249 629023 Mo 21 20N 15E 15 NW
1250 629024 Mo 22 20N 15E 15 NE
1251 629025 Mo 23 20N 15E 14 NW
1252 629026 Mo 24 20N 15E 14 NE
1253 629027 Mo 25 20N 15E 13 NW
1254 629028 Mo 26 20N 15E 13 NE
1255 629029 Mo 27 20N 16E 18 NW
1256 629030 Mo 28 20N 16E 18 NE
1257 629031 Mo 29 20N 16E 17 NW
1258 629032 Mo 30 20N 16E 17 NE
1259 629033 Mo 31 20N 15E 18 SE
1260 629034 Mo 32 20N 15E 17 SW
1261 629035 Mo 33 20N 15E 17 SE

  
Arctic ProjectPage 454
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1262 629036 Mo 34 20N 15E 16 SW
1263 629037 Mo 35 20N 15E 16 SE
1264 629038 Mo 36 20N 15E 15 SW
1265 629039 Mo 37 20N 15E 15 SE
1266 629040 Mo 38 20N 15E 14 SW
1267 629041 Mo 39 20N 15E 14 SE
1268 629042 Mo 40 20N 15E 13 SW
1269 629043 Mo 41 20N 15E 13 SE
1270 629044 Mo 42 20N 16E 18 SW
1271 629045 Mo 43 20N 16E 18 SE
1272 629046 Mo 44 20N 16E 17 SW
1273 629047 Mo 45 20N 16E 17 SE
1274 629048 Mo 46 20N 15E 19 NE
1275 629049 Mo 47 20N 15E 20 NW
1276 629050 Mo 48 20N 15E 20 NE
1277 629051 Mo 49 20N 15E 21 NW
1278 629052 Mo 50 20N 15E 21 NE
1279 629053 Mo 51 20N 15E 22 NW
1280 629054 Mo 52 20N 15E 22 NE
1281 629055 Mo 53 20N 15E 23 NW
1282 629056 Mo 54 20N 15E 23 NE
1283 629057 Mo 55 20N 15E 24 NW
1284 629058 Mo 56 20N 15E 24 NE
1285 629059 Mo 57 20N 16E 19 NW
1286 629060 Mo 58 20N 16E 19 NE
1287 629061 Mo 59 20N 16E 20 NW
1288 629062 Mo 60 20N 16E 20 NE
1289 629063 Mo 61 20N 16E 21 NW
1290 629064 Mo 62 20N 16E 21 NE
1291 629065 Mo 63 20N 16E 19 SE
1292 629066 Mo 64 20N 15E 20 SW
1293 629067 Mo 65 20N 15E 20 SE
1294 629068 Mo 66 20N 15E 21 SW
1295 629069 Mo 67 20N 15E 21 SE
1296 629070 Mo 68 20N 15E 22 SW
1297 629071 Mo 69 20N 15E 22 SE
1298 629072 Mo 70 20N 15E 23 SW
1299 629073 Mo 71 20N 15E 23 SE
1300 629074 Mo 72 20N 15E 24 SW
1301 629075 Mo 73 20N 15E 24 SE
1302 629076 Mo 74 20N 16E 19 SW
1303 629077 Mo 75 20N 16E 19 SE
1304 629078 Mo 76 20N 16E 20 SW
1305 629079 Mo 77 20N 16E 20 SE

  
Arctic ProjectPage 455
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1306 629080 Mo 78 20N 16E 21 SW
1307 629081 Mo 79 20N 16E 21 SE
1308 629082 Mo 80 20N 15E 30 NE
1309 629083 Mo 81 20N 15E 29 NW
1310 629084 Mo 82 20N 15E 29 NE
1311 629085 Mo 83 20N 15E 28 NW
1312 629086 Mo 84 20N 15E 28 NE
1313 629087 Mo 85 20N 15E 27 NW
1314 629088 Mo 86 20N 15E 27 NE
1315 629089 Mo 87 20N 15E 26 NW
1316 629090 Mo 88 20N 15E 26 NE
1317 629091 Mo 89 20N 15E 25 NW
1318 629092 Mo 90 20N 15E 25 NE
1319 629093 Mo 91 20N 16E 30 NW
1320 629094 Mo 92 20N 16E 30 NE
1321 629095 Mo 93 20N 16E 29 NW
1322 629096 Mo 94 20N 16E 29 NE
1323 629097 Mo 95 20N 16E 28 NW
1324 629098 Mo 96 20N 16E 28 NE
1325 629099 Mo 97 20N 16E 27 NW
1326 629100 Mo 98 20N 16E 27 NE
1327 629101 Mo 99 20N 16E 26 NW
1328 629102 Mo 100 20N 16E 26 NE
1329 629103 Mo 101 20N 15E 30 SE
1330 629104 Mo 102 20N 15E 29 SW
1331 629105 Mo 103 20N 15E 29 SE
1332 629106 Mo 104 20N 15E 28 SW
1333 629107 Mo 105 20N 15E 28 SE
1334 629108 Mo 106 20N 15E 27 SW
1335 629109 Mo 107 20N 15E 27 SE
1336 629110 Mo 108 20N 15E 26 SW
1337 629111 Mo 109 20N 15E 26 SE
1338 629112 Mo 110 20N 15E 25 SW
1339 629113 Mo 111 20N 15E 25 SE
1340 629114 Mo 112 20N 16E 30 SW
1341 629115 Mo 113 20N 16E 30 SE
1342 629116 Mo 114 20N 16E 29 SW
1343 629117 Mo 115 20N 16E 29 SE
1344 629118 Mo 116 20N 16E 28 SW
1345 629119 Mo 117 20N 16E 28 SE
1346 629120 Mo 118 20N 16E 27 SW
1347 629121 Mo 119 20N 16E 27 SE
1348 629122 Mo 120 20N 16E 26 SW
1349 629123 Mo 121 20N 16E 26 SE

  
Arctic ProjectPage 456
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1350 629124 Mo 122 20N 14E 36 NW
1351 629125 Mo 123 20N 14E 36 NE
1352 629126 Mo 124 20N 15E 31 NW
1353 629127 Mo 125 20N 15E 31 NE
1354 629128 Mo 126 20N 15E 32 NW
1355 629129 Mo 127 20N 15E 32 NE
1356 629130 Mo 128 20N 16E 34 NW
1357 629131 Mo 129 20N 16E 34 NE
1358 629132 Mo 130 20N 16E 35 NW
1359 629133 Mo 131 20N 16E 35 NE
1360 629134 Mo 132 20N 14E 36 SW
1361 629135 Mo 133 20N 14E 36 NE
1362 629136 Mo 134 20N 15E 31 SW
1363 629137 Mo 135 20N 15E 31 SE
1364 629138 Mo 136 20N 15E 32 SW
1365 629139 Mo 137 20N 15E 32 SE
1366 629189 WK112 23N 06E 29 NW
1367 629190 WK113 23N 06E 29 NE
1368 629191 WK114 23N 06E 28 NW
1369 629192 WK115 23N 06E 28 NE
1370 629193 WK116 23N 06E 27 NW
1371 629194 WK117 23N 06E 27 NE
1372 629195 WK137 23N 05E 27 SW
1373 629196 WK138 23N 05E 27 SE
1374 629197 WK139 23N 05E 26 SW
1375 629198 WK140 23N 05E 26 SE
1376 629199 WK141 23N 05E 25 SW
1377 629200 WK142 23N 05E 25 SE
1378 629201 WK143 23N 06E 30 SW
1379 629202 WK144 23N 06E 30 SE
1380 629203 WK145 23N 06E 29 SW
1381 629204 WK146 23N 06E 29 SE
1382 629205 WK147 23N 06E 28 SW
1383 629206 WK148 23N 06E 28 SE
1384 629207 WK149 23N 06E 27 SW
1385 629208 WK150 23N 06E 27 SE
1386 629209 WK151 23N 06E 26 SW
1387 629210 WK152 23N 06E 26 SE
1388 629211 WK153 23N 06E 25 SW
1389 629212 WK154 23N 06E 25 SE
1390 629213 WK155 23N 07E 30 SW
1391 629214 WK156 23N 07E 30 SE
1392 629215 WK157 23N 07E 29 SW
1393 629216 WK158 23N 07E 29 SE

  
Arctic ProjectPage 457
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1394 629217 WK159 23N 07E 28 SW
1395 629218 WK160 23N 07E 28 SE
1396 629219 WK161 23N 07E 27 SW
1397 629220 WK162 23N 07E 27 SE
1398 629221 WK163 23N 07E 26 SW
1399 629222 WK172 23N 05E 34 NW
1400 629223 WK173 23N 05E 34 NE
1401 629224 WK174 23N 05E 35 NW
1402 629225 WK175 23N 05E 35 NE
1403 629226 WK176 23N 05E 36 NW
1404 629227 WK177 23N 05E 36 NE
1405 629228 WK178 23N 06E 31 NW
1406 629229 WK179 23N 06E 31 NE
1407 629230 WK180 23N 06E 32 NW
1408 629231 WK181 23N 06E 32 NE
1409 629232 WK182 23N 06E 33 NW
1410 629233 WK183 23N 06E 33 NE
1411 629234 WK184 23N 06E 34 NW
1412 629235 WK185 23N 06E 34 NE
1413 629236 WK186 23N 06E 35 NW
1414 629237 WK187 23N 06E 35 NE
1415 629238 WK188 23N 06E 36 NW
1416 629239 WK189 23N 06E 36 NE
1417 629240 WK190 23N 07E 31 NW
1418 629241 WK191 23N 07E 31 NE
1419 629242 WK192 23N 07E 32 NW
1420 629243 WK193 23N 07E 32 NE
1421 629244 WK194 23N 07E 33 NW
1422 629245 WK195 23N 07E 33 NE
1423 629246 WK196 23N 07E 34 NW
1424 629247 WK197 23N 07E 34 NE
1425 629248 WK198 23N 07E 35 NW
1426 629249 WK199 23N 07E 35 NE
1427 629250 WK208 23N 05E 34 SW
1428 629251 WK209 23N 05E 34 SE
1429 629252 WK210 23N 05E 35 SW
1430 629253 WK211 23N 05E 35 SE
1431 629254 WK212 23N 05E 36 SW
1432 629255 WK213 23N 05E 36 SE
1433 629256 WK214 23N 06E 31 SW
1434 629257 WK215 23N 06E 31 SE
1435 629258 WK216 23N 06E 32 SW
1436 629259 WK217 23N 06E 32 SE
1437 629260 WK218 23N 06E 33 SW

  
Arctic ProjectPage 458
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1438 629261 WK219 23N 06E 33 SE
1439 629262 WK220 23N 06E 34 SW
1440 629263 WK221 23N 06E 34 SE
1441 629264 WK222 23N 06E 35 SW
1442 629265 WK223 23N 06E 35 SE
1443 629266 WK224 23N 06E 36 SW
1444 629267 WK225 23N 06E 36 SE
1445 629268 WK226 23N 07E 31 SW
1446 629269 WK227 23N 07E 31 SE
1447 629270 WK228 23N 07E 32 SW
1448 629271 WK229 23N 07E 32 SE
1449 629272 WK230 23N 07E 33 SW
1450 629273 WK231 23N 07E 33 SE
1451 629274 WK232 23N 07E 34 SW
1452 629275 WK233 23N 07E 34 SE
1453 629276 WK234 23N 07E 35 SW
1454 629277 WK235 23N 07E 35 SE
1455 629278 WK236 23N 07E 36 SW
1456 629279 WK237 23N 07E 36 SE
1457 629280 WK238 23N 08E 31 SW
1458 629281 WK239 22N 05E 03 NW
1459 629282 WK240 22N 05E 03 NE
1460 629283 WK241 22N 05E 02 NW
1461 629284 WK242 22N 05E 02 NE
1462 629285 WK243 22N 05E 01 NW
1463 629286 WK244 22N 05E 01 NE
1464 629287 WK245 22N 05E 03 SW
1465 629288 WK246 22N 05E 03 SE
1466 629289 WK247 22N 05E 02 SW
1467 629290 WK248 22N 05E 02 SE
1468 629291 WK249 22N 05E 01 SW
1469 629292 WK250 22N 05E 01 SE
1470 629293 WK251 22N 05E 10 NW
1471 629294 WK252 22N 05E 10 NE
1472 629295 WK253 22N 05E 11 NW
1473 629296 WK254 22N 05E 11 NE
1474 629297 WK255 22N 05E 12 NW
1475 629298 WK256 22N 05E 12 NE
1476 629299 WK257 22N 05E 10 SW
1477 629300 WK258 22N 05E 10 SE
1478 629301 WK259 22N 05E 11 SW
1479 629302 WK260 22N 05E 11 SE
1480 629303 WK261 22N 05E 12 SW
1481 629304 WK262 22N 05E 12 SE

  
Arctic ProjectPage 459
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1482 629305 WK263 22N 05E 15 NW
1483 629306 WK264 22N 05E 15 NE
1484 629307 WK265 22N 05E 14 NW
1485 629308 WK266 22N 05E 14 NE
1486 629309 WK267 22N 05E 13 NW
1487 629310 WK268 22N 05E 13 NE
1488 629311 WK269 22N 05E 15 SW
1489 629312 WK270 22N 05E 15 SE
1490 629313 WK271 22N 05E 14 SW
1491 629314 WK272 22N 05E 14 SE
1492 629315 WK273 22N 05E 13 SW
1493 629316 WK274 22N 05E 13 SE
1494 629317 WK275 22N 05E 22 NW
1495 629318 WK276 22N 05E 22 NE
1496 629319 WK277 22N 05E 23 NW
1497 629320 WK278 22N 05E 23 NE
1498 629321 WK279 22N 05E 24 NW
1499 629322 WK280 22N 05E 24 NE
1500 629323 WK281 22N 05E 22 SW
1501 629324 WK282 22N 05E 22 SE
1502 629325 WK283 22N 05E 23 SW
1503 629326 WK284 22N 05E 23 SE
1504 629327 WK285 22N 05E 24 SW
1505 629328 WK286 22N 05E 24 SE
1506 629329 WK287 22N 05E 27 NW
1507 629330 WK288 22N 05E 27 NE
1508 629331 WK289 22N 05E 27 SW
1509 629332 WK290 22N 05E 27 SE
1510 629333 WK291 22N 05E 34 NW
1511 629334 WK292 22N 05E 34 NE
1512 629335 WK293 22N 05E 34 SW
1513 629336 WK294 22N 05E 34 SE
1514 634110 EDC 1 21N 10E 12 SW
1515 634111 EDC 2 21N 10E 12 SE
1516 634112 EDC 3 21N 10E 12 SE
1517 634113 EDC 4 21N 11E 7 SW
1518 634114 EDC 5 21N 11E 7 SW
1519 634115 EDC 6 21N 11E 7 SE
1520 634116 EDC 7 21N 11E 7 SE
1521 634117 EDC 8 21N 11E 8 SW
1522 634118 EDC 9 21N 10E 12 SW
1523 634119 EDC 10 21N 10E 12 SE
1524 634120 EDC 11 21N 10E 12 SE
1525 634121 EDC 12 21N 11E 7 SW

  
Arctic ProjectPage 460
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1526 634122 EDC 13 21N 11E 7 SW
1527 634123 EDC 14 21N 11E 7 SE
1528 634124 EDC 15 21N 11E 7 SE
1529 634125 EDC 16 21N 11E 8 SW
1530 634126 EDC 17 21N 10E 13 NW
1531 634127 EDC 18 21N 10E 13 NE
1532 634128 EDC 19 21N 10E 13 NE
1533 634129 EDC 20 21N 11E 18 NW
1534 634130 EDC 21 21N 11E 18 NW
1535 634131 EDC 22 21N 11E 18 NE
1536 634132 EDC 23 21N 11E 18 NE
1537 634133 EDC 24 21N 11E 17 NW
1538 634134 EDC 25 21N 10E 13 NW
1539 634135 EDC 26 21N 10E 13 NE
1540 634136 EDC 27 21N 10E 13 NE
1541 634137 EDC 28 21N 11E 18 NW
1542 634138 EDC 29 21N 11E 18 NW
1543 634139 EDC 30 21N 11E 18 NE
1544 634140 EDC 31 21N 11E 18 NE
1545 634141 EDC 32 21N 11E 17 NW
1546 634142 EDC 33 21N 10E 13 SW
1547 634143 EDC 34 21N 10E 13 SE
1548 634144 EDC 35 21N 10E 13 SE
1549 634145 EDC 36 21N 11E 18 SW
1550 634146 EDC 37 21N 11E 18 SW
1551 634147 EDC 38 21N 11E 18 SE
1552 634148 EDC 39 21N 11E 18 SE
1553 634149 EDC 40 21N 11E 17 SW
1554 634150 EDC 41 21N 10E 13 SW
1555 634151 EDC 42 21N 10E 13 SE
1556 634152 EDC 43 21N 10E 13 SE
1557 634153 EDC 44 21N 11E 18 SW
1558 634154 EDC 45 21N 11E 18 SW
1559 634155 EDC 46 21N 11E 18 SE
1560 634156 EDC 47 21N 11E 18 SE
1561 634157 EDC 48 21N 11E 17 SW
1562 634158 EDC 49 21N 10E 24 NW
1563 634159 EDC 50 21N 10E 24 NE
1564 634160 EDC 51 21N 10E 24 NE
1565 634161 EDC 52 21N 11E 19 NW
1566 634162 EDC 53 21N 11E 19 NW
1567 634163 EDC 54 21N 11E 19 NE
1568 634164 EDC 55 21N 11E 19 NE
1569 634165 EDC 56 21N 11E 20 NW

  
Arctic ProjectPage 461
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1570 634166 EDC 57 21N 10E 24 NW
1571 634167 EDC 58 21N 10E 24 NE
1572 634168 EDC 59 21N 10E 24 NE
1573 634169 EDC 60 21N 11E 19 NW
1574 634170 EDC 61 21N 11E 19 NW
1575 634171 EDC 62 21N 11E 19 NE
1576 634172 EDC 63 21N 11E 19 NE
1577 634173 EDC 64 21N 11E 20 NW
1578 634174 EDC 65 21N 10E 24 SE
1579 634175 EDC 66 21N 10E 24 SE
1580 634176 EDC 67 21N 11E 19 SW
1581 634177 EDC 68 21N 11E 19 SW
1582 634178 EDC 69 21N 11E 19 SE
1583 634179 EDC 70 21N 11E 19 SE
1584 634180 EDC 71 21N 11E 20 SW
1585 634181 EDC 72 21N 11E 20 SW
1586 634182 EDC 73 21N 11E 20 SE
1587 634183 EDC 74 21N 11E 20 SE
1588 634184 EDC 75 21N 11E 21 SW
1589 634185 EDC 76 21N 10E 24 SE
1590 634186 EDC 77 21N 11E 19 SW
1591 634187 EDC 78 21N 11E 19 SW
1592 634188 EDC 79 21N 11E 19 SE
1593 634189 EDC 80 21N 11E 19 SE
1594 634190 EDC 81 21N 11E 20 SW
1595 634191 EDC 82 21N 11E 20 SW
1596 634192 EDC 83 21N 11E 20 SE
1597 634193 EDC 84 21N 11E 20 SE
1598 634194 EDC 85 21N 11E 21 SW
1599 634195 EDC 86 21N 10E 25 NE
1600 634196 EDC 87 21N 11E 30 NW
1601 634197 EDC 88 21N 11E 30 NW
1602 634198 EDC 89 21N 11E 30 NE
1603 634199 EDC 90 21N 11E 30 NE
1604 634200 EDC 91 21N 11E 29 NW
1605 634201 EDC 92 21N 11E 29 NW
1606 634202 EDC 93 21N 11E 29 NE
1607 634203 EDC 94 21N 11E 29 NE
1608 634204 EDC 95 21N 11E 28 NW
1609 650291 HOSS 01 22N 10E 18 NW
1610 650292 HOSS 02 22N 10E 18 NE
1611 650293 HOSS 03 22N 10E 17 NW
1612 650294 HOSS 04 22N 10E 17 NE
1613 650295 HOSS 05 22N 10E 16 NW

  
Arctic ProjectPage 462
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1614 650296 HOSS 06 22N 10E 16 NE
1615 650297 HOSS 07 22N 10E 15 NW
1616 650298 HOSS 08 22N 10E 18 SW
1617 650299 HOSS 09 22N 10E 18 SE
1618 650300 HOSS 10 22N 10E 17 SW
1619 650301 HOSS 11 22N 10E 17 SE
1620 650302 HOSS 12 22N 10E 16 SW
1621 650303 HOSS 13 22N 10E 16 SE
1622 650304 HOSS 14 22N 10E 15 SW
1623 650305 HOSS 15 22N 10E 19 NW
1624 650306 HOSS 16 22N 10E 19 NE
1625 650307 HOSS 17 22N 10E 20 NW
1626 650308 HOSS 18 22N 10E 20 NE
1627 650309 HOSS 19 22N 10E 21 NW
1628 650310 HOSS 20 22N 10E 21 NE
1629 650311 HOSS 21 22N 10E 22 NW
1630 650312 HOSS 22 22N 10E 19 SW
1631 650313 HOSS 23 22N 10E 19 SE
1632 650314 HOSS 24 22N 10E 20 SW
1633 650315 HOSS 25 22N 10E 20 SE
1634 650316 HOSS 26 22N 10E 21 SW
1635 650317 HOSS 27 22N 10E 21 SE
1636 650318 HOSS 28 22N 10E 22 SW
1637 650319 HOSS 29 22N 10E 30 NW
1638 650320 HOSS 30 22N 10E 30 NE
1639 650321 HOSS 31 22N 10E 29 NW
1640 650322 HOSS 32 22N 10E 29 NE
1641 650323 HOSS 33 22N 10E 28 NW
1642 650324 HOSS 34 22N 10E 28 NE
1643 650325 HOSS 35 22N 10E 27 NW
1644 651152 ZED 1 20N 12E 10 NE
1645 651153 ZED 2 20N 12E 11 NW
1646 651154 ZED 3 20N 12E 11 NE
1647 651155 ZED 4 20N 12E 10 SE
1648 651156 ZED 5 20N 12E 11 SW
1649 651157 ZED 6 20N 12E 11 SE
1650 651158 ZED 7 20N 12E 12 SW
1651 651159 ZED 8 20N 12E 12 SE
1652 651160 ZED 9 20N 12E 15 NE
1653 651161 ZED 10 20N 12E 14 NW
1654 651162 ZED 11 20N 12E 14 NE
1655 651163 ZED 12 20N 12E 13 NW
1656 651164 ZED 13 20N 12E 13 NE
1657 651165 ZED 14 20N 13E 18 NW

  
Arctic ProjectPage 463
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1658 651166 ZED 15 20N 13E 18 NE
1659 651167 ZED 16 20N 13E 17 NW
1660 651168 ZED 17 20N 13E 17 NE
1661 651169 ZED 18 20N 13E 16 NW
1662 651170 ZED 19 20N 13E 16 NE
1663 651171 ZED 20 20N 13E 15 NW
1664 651172 ZED 21 20N 13E 15 NE
1665 651173 ZED 22 20N 12E 15 SE
1666 651174 ZED 23 20N 12E 14 SW
1667 651175 ZED 24 20N 12E 14 SE
1668 651176 ZED 25 20N 12E 13 SW
1669 651177 ZED 26 20N 12E 13 SE
1670 651178 ZED 27 20N 13E 18 SW
1671 651179 ZED 28 20N 13E 18 SE
1672 651180 ZED 29 20N 13E 17 SW
1673 651181 ZED 30 20N 13E 17 SE
1674 651182 ZED 31 20N 13E 16 SW
1675 651183 ZED 32 20N 13E 16 SE
1676 651184 ZED 33 20N 13E 15 SW
1677 651185 ZED 34 20N 13E 15 SE
1678 651186 ZED 35 20N 12E 24 NE
1679 651187 ZED 36 20N 13E 19 NW
1680 651188 ZED 37 20N 13E 19 NE
1681 651189 ZED 38 20N 13E 20 NW
1682 651190 ZED 39 20N 13E 20 NE
1683 651191 ZED 40 20N 13E 21 NW
1684 651192 ZED 41 20N 13E 21 NE
1685 651193 ZED 42 20N 13E 22 NW
1686 651194 ZED 43 20N 13E 22 NE
1687 651195 ZED 44 20N 13E 19 SE
1688 651196 ZED 45 20N 13E 20 SW
1689 651197 ZED 46 20N 13E 20 SE
1690 651198 ZED 47 20N 13E 21 SW
1691 651199 ZED 48 20N 13E 21 SE
1692 651200 ZED 49 20N 13E 22 SW
1693 651201 ZED 50 20N 13E 22 SE
1694 651202 ZED 51 20N 13E 23 NW
1695 651203 ZED 52 20N 13E 23 NE
1696 651204 ZED 53 20N 13E 24 NW
1697 651205 ZED 54 20N 13E 24 NE
1698 651206 ZED 55 20N 14E 19 NW
1699 651207 ZED 56 20N 14E 19 NE
1700 651208 ZED 57 20N 14E 20 NW
1701 651209 ZED 58 20N 14E 20 NE

  
Arctic ProjectPage 464
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1702 651210 ZED 59 20N 14E 21 NW
1703 651211 ZED 60 20N 14E 21 NE
1704 651212 ZED 61 20N 14E 22 NW
1705 651213 ZED 62 20N 14E 22 NE
1706 651214 ZED 63 20N 14E 23 NW
1707 651215 ZED 64 20N 14E 23 NE
1708 651216 ZED 65 20N 14E 24 NW
1709 651217 ZED 66 20N 14E 24 NE
1710 651218 ZED 67 20N 15E 19 NW
1711 651219 ZED 68 20N 13E 23 SW
1712 651220 ZED 69 20N 13E 23 SE
1713 651221 ZED 70 20N 13E 24 SW
1714 651222 ZED 71 20N 13E 24 SE
1715 651223 ZED 72 20N 14E 19 SW
1716 651224 ZED 73 20N 14E 19 SE
1717 651225 ZED 74 20N 14E 20 SW
1718 651226 ZED 75 20N 14E 20 SE
1719 651227 ZED 76 20N 14E 21 SW
1720 651228 ZED 77 20N 14E 21 SE
1721 651229 ZED 78 20N 14E 22 SW
1722 651230 ZED 79 20N 14E 22 SE
1723 651231 ZED 80 20N 14E 23 SW
1724 651232 ZED 81 20N 14E 23 SE
1725 651233 ZED 82 20N 14E 24 SW
1726 651234 ZED 83 20N 14E 24 SE
1727 651235 ZED 84 20N 15E 19 SW
1728 651236 ZED 85 20N 13E 26 NW
1729 651237 ZED 86 20N 13E 26 NE
1730 651238 ZED 87 20N 13E 25 NW
1731 651239 ZED 88 20N 13E 25 NE
1732 651240 ZED 89 20N 14E 30 NW
1733 651241 ZED 90 20N 14E 30 NE
1734 651242 ZED 91 20N 14E 29 NW
1735 651243 ZED 92 20N 14E 29 NE
1736 651244 ZED 93 20N 14E 28 NW
1737 651245 ZED 94 20N 14E 28 NE
1738 651246 ZED 95 20N 14E 27 NW
1739 651247 ZED 96 20N 14E 27 NE
1740 651248 ZED 97 20N 14E 26 NW
1741 651249 ZED 98 20N 14E 26 NE
1742 651250 ZED 99 20N 14E 25 NW
1743 651251 ZED 100 20N 14E 25 NE
1744 651252 ZED 101 20N 15E 30 NW
1745 651253 ZED 102 20N 13E 26 SW

  
Arctic ProjectPage 465
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1746 651254 ZED 103 20N 13E 26 SE
1747 651255 ZED 104 20N 13E 25 SW
1748 651256 ZED 105 20N 13E 25 SE
1749 651257 ZED 106 20N 14E 30 SW
1750 651258 ZED 107 20N 14E 30 SE
1751 651259 ZED 108 20N 14E 29 SW
1752 651260 ZED 109 20N 14E 29 SE
1753 651261 ZED 110 20N 14E 28 SW
1754 651262 ZED 111 20N 14E 28 SE
1755 651263 ZED 112 20N 14E 27 SW
1756 651264 ZED 113 20N 14E 27 SE
1757 651265 ZED 114 20N 14E 26 SW
1758 651266 ZED 115 20N 14E 26 SE
1759 651267 ZED 116 20N 14E 25 SW
1760 651268 ZED 117 20N 14E 25 SE
1761 651269 ZED 118 20N 15E 30 SW
1762 651270 PAL 1 21N 10E 25 NE
1763 651271 PAL 2 21N 10E 25 NE
1764 651272 PAL 3 21N 11E 30 NW
1765 651273 PAL 4 21N 11E 30 NW
1766 651274 PAL 5 21N 11E 30 NE
1767 651275 PAL 6 21N 11E 30 NE
1768 651276 PAL 7 21N 11E 29 NW
1769 651277 PAL 8 21N 11E 29 NW
1770 651278 PAL 9 21N 11E 29 NE
1771 651279 PAL 10 21N 11E 29 NE
1772 651280 PAL 11 21N 11E 28 NW
1773 651289 PAL 20 21N 10E 25 SE
1774 651290 PAL 21 21N 11E 30 SW
1775 651291 PAL 22 21N 11E 30 SE
1776 651292 PAL 23 21N 11E 29 SW
1777 651293 PAL 24 21N 11E 29 SE
1778 651294 PAL 25 21N 11E 28 SW
1779 651296 PAL 27 21N 11E 32 NE
1780 651297 PAL 28 21N 11E 33 NW
1781 651299 GAP 1 22N 8E 28 NW
1782 651300 GAP 2 22N 8E 28 NE
1783 651301 GAP 3 22N 8E 27 NW
1784 651302 GAP 4 22N 8E 27 NE
1785 651303 GAP 5 22N 8E 26 NW
1786 651304 GAP 6 22N 8E 26 NE
1787 651305 GAP 7 22N 8E 25 NW
1788 651306 GAP 8 22N 8E 25 NE
1789 651307 GAP 9 22N 9E 30 NW

  
Arctic ProjectPage 466
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1790 651308 GAP 10 22N 9E 30 NE
1791 651309 GAP 11 22N 9E 29 NW
1792 651310 GAP 12 22N 8E 28 SW
1793 651311 GAP 13 22N 8E 28 SE
1794 651312 GAP 14 22N 8E 27 SW
1795 651313 GAP 15 22N 8E 27 SE
1796 651314 GAP 16 22N 8E 26 SW
1797 651315 GAP 17 22N 8E 26 SE
1798 651316 GAP 18 22N 8E 25 SW
1799 651317 GAP 19 22N 8E 25 SE
1800 651318 GAP 20 22N 9E 30 SW
1801 651319 GAP 21 22N 9E 30 SE
1802 651320 GAP 22 22N 9E 29 SW
1803 651321 GAP 23 22N 9E 29 SE
1804 651322 GAP 24 22N 9E 28 SW
1805 651323 GAP 25 22N 9E 28 SE
1806 651324 GAP 26 22N 9E 27 SW
1807 651325 GAP 27 22N 8E 34 NE
1808 651326 GAP 28 22N 8E 35 NW
1809 651327 GAP 29 22N 8E 35 NE
1810 651328 GAP 30 22N 8E 36 NW
1811 651329 GAP 31 22N 8E 36 NE
1812 651330 GAP 32 22N 9E 31 NW
1813 651331 GAP 33 22N 9E 31 NE
1814 651332 GAP 34 22N 9E 32 NW
1815 651333 GAP 35 22N 9E 32 NE
1816 651334 GAP 36 22N 9E 33 NW
1817 651335 GAP 37 22N 9E 33 NE
1818 651336 GAP 38 22N 9E 34 NW
1819 651337 GAP 39 22N 9E 34 NE
1820 651338 GAP 40 22N 9E 35 NW
1821 651339 GAP 41 22N 9E 35 NE
1822 651340 GAP 42 22N 9E 36 NW
1823 651341 GAP 43 22N 9E 36 NE
1824 651342 GAP 44 22N 10E 31 NW
1825 651343 GAP 45 22N 10E 31 NE
1826 651344 GAP 46 22N 10E 32 NW
1827 651345 GAP 47 22N 10E 32 NE
1828 651346 GAP 48 22N 10E 33 NW
1829 651347 GAP 49 22N 10E 33 NE
1830 651348 GAP 50 22N 10E 34 NW
1831 651349 GAP 51 22N 10E 30 SW
1832 651350 GAP 52 22N 10E 30 SE
1833 651351 GAP 53 22N 10E 29 SW

  
Arctic ProjectPage 467
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1834 651352 GAP 54 22N 10E 29 SE
1835 651353 GAP 55 22N 10E 28 SW
1836 651354 GAP 56 22N 10E 28 SE
1837 651355 GAP 57 22N 10E 27 SW
1838 651356 GAP 58 22N 8E 34 SE
1839 651357 GAP 59 22N 8E 35 SW
1840 651358 GAP 60 22N 8E 35 SE
1841 651359 GAP 61 22N 8E 36 SW
1842 651360 GAP 62 22N 8E 36 SE
1843 651361 GAP 63 22N 9E 31 SW
1844 651362 GAP 64 22N 9E 31 SE
1845 651363 GAP 65 22N 9E 32 SW
1846 651364 GAP 66 22N 9E 32 SE
1847 651365 GAP 67 22N 9E 33 SW
1848 651366 GAP 68 22N 9E 33 SE
1849 651367 GAP 69 22N 9E 34 SW
1850 651368 GAP 70 22N 9E 34 SE
1851 651369 GAP 71 22N 9E 35 SW
1852 651370 GAP 72 22N 9E 35 SE
1853 651371 GAP 73 22N 9E 36 SW
1854 651372 GAP 74 22N 9E 36 SE
1855 651373 GAP 75 22N 10E 31 SW
1856 651374 GAP 76 22N 10E 31 SE
1857 651375 GAP 77 22N 10E 32 SW
1858 651376 GAP 78 22N 10E 32 SE
1859 651377 GAP 79 22N 10E 33 SW
1860 651378 GAP 80 22N 10E 33 SE
1861 651379 GAP 81 22N 10E 34 SW
1862 651380 GAP 82 21N 8E 3 NE
1863 651381 GAP 83 21N 8E 2 NW
1864 651382 GAP 84 21N 8E 2 NE
1865 651383 GAP 85 21N 8E 1 NW
1866 651384 GAP 86 21N 8E 1 NE
1867 651385 GAP 87 21N 9E 6 NW
1868 651386 GAP 88 21N 9E 6 NE
1869 651387 GAP 89 21N 9E 2 NW
1870 651388 GAP 90 21N 9E 2 NE
1871 651389 GAP 91 21N 9E 1 NW
1872 651390 GAP 92 21N 9E 1 NE
1873 651391 GAP 93 21N 10E 6 NW
1874 651392 GAP 94 21N 10E 6 NE
1875 651393 GAP 95 21N 10E 5 NW
1876 651394 GAP 96 21N 10E 5 NE
1877 651395 GAP 97 21N 10E 4 NW

  
Arctic ProjectPage 468
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1878 651396 GAP 98 21N 10E 4 NE
1879 651397 GAP 99 21N 10E 3 NW
1880 651398 GAP 100 21N 9E 2 SW
1881 651399 GAP 101 21N 9E 2 SE
1882 651400 GAP 102 21N 9E 1 SW
1883 651401 GAP 103 21N 9E 1 SE
1884 651402 GAP 104 21N 10E 6 SW
1885 651403 GAP 105 21N 10E 6 SE
1886 651404 GAP 106 21N 10E 5 SW
1887 651405 GAP 107 21N 10E 5 SE
1888 651406 GAP 108 21N 10E 4 SW
1889 651407 GAP 109 21N 10E 4 SE
1890 651408 GAP 110 21N 10E 3 SW
1891 651409 GAP 111 21N 10E 3 SE
1892 651410 GAP 112 21N 10E 2 SW
1893 651411 GAP 113 21N 10E 2 SE
1894 651412 GAP 114 21N 9E 11 NW
1895 651413 GAP 115 21N 9E 11 NW
1896 651414 GAP 116 21N 9E 11 NE
1897 651415 GAP 117 21N 9E 11 NE
1898 651416 GAP 118 21N 9E 12 NW
1899 651417 GAP 119 21N 9E 12 NW
1900 651418 GAP 120 21N 9E 12 NE
1901 651419 GAP 121 21N 9E 12 NE
1902 651420 GAP 122 21N 10E 7 NW
1903 651421 GAP 123 21N 10E 7 NW
1904 651422 GAP 124 21N 10E 7 NE
1905 651423 GAP 125 21N 10E 7 NE
1906 651424 GAP 126 21N 10E 8 NW
1907 651425 GAP 127 21N 10E 8 NW
1908 651426 GAP 128 21N 10E 8 NE
1909 651427 GAP 129 21N 10E 8 NE
1910 651428 GAP 130 21N 10E 9 NW
1911 651429 GAP 131 21N 10E 9 NW
1912 651430 GAP 132 21N 10E 9 NE
1913 651431 GAP 133 21N 10E 9 NE
1914 651432 GAP 134 21N 10E 10 NW
1915 651433 GAP 135 21N 10E 10 NW
1916 651434 GAP 136 21N 10E 10 NE
1917 651435 GAP 137 21N 10E 10 NE
1918 651436 GAP 138 21N 10E 11 NW
1919 651437 GAP 139 21N 10E 11 NW
1920 651438 GAP 140 21N 10E 11 NE
1921 651439 GAP 141 21N 10E 11 NE

  
Arctic ProjectPage 469
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1922 651440 GAP 142 21N 9E 5 NW
1923 651441 GAP 143 21N 9E 5 NE
1924 651442 GAP 144 21N 9E 4 NW
1925 651443 GAP 145 21N 9E 4 NE
1926 651444 GAP 146 21N 9E 3 NW
1927 651445 GAP 147 21N 9E 3 NE
1928 651446 GAP 148 21N 8E 3 SE
1929 651447 GAP 149 21N 8E 2 SW
1930 651448 GAP 150 21N 8E 2 SE
1931 651449 GAP 151 21N 8E 1 SW
1932 651450 GAP 152 21N 8E 1 SE
1933 651451 GAP 153 21N 9E 6 SW
1934 651452 GAP 154 21N 9E 6 SE
1935 651453 GAP 155 21N 9E 5 SW
1936 651454 GAP 156 21N 9E 5 SE
1937 651455 GAP 157 21N 9E 4 SW
1938 651456 GAP 158 21N 9E 4 SE
1939 651457 GAP 159 21N 9E 3 SW
1940 651458 GAP 160 21N 9E 3 SE
1941 651459 GAP 161 21N 8E 10 NE
1942 651460 GAP 162 21N 8E 11 NW
1943 651461 GAP 163 21N 8E 11 NE
1944 651462 GAP 164 21N 8E 12 NW
1945 651463 GAP 165 21N 8E 12 NE
1946 651464 GAP 166 21N 9E 7 NW
1947 651465 GAP 167 21N 9E 7 NE
1948 651466 GAP 168 21N 9E 8 NW
1949 651467 GAP 169 21N 9E 8 NE
1950 651468 GAP 170 21N 9E 9 NW
1951 651469 GAP 171 21N 9E 9 NE
1952 651470 GAP 172 21N 9E 10 NW
1953 651471 GAP 173 21N 9E 10 NE
1954 651472 GAP 174 21N 8E 10 SE
1955 651473 GAP 175 21N 8E 11 SW
1956 651474 GAP 176 21N 8E 11 SE
1957 651475 GAP 177 21N 8E 12 SW
1958 651476 GAP 178 21N 8E 12 SE
1959 651477 GAP 179 21N 9E 7 SW
1960 651478 GAP 180 21N 9E 7 SE
1961 651479 GAP 181 21N 9E 8 SW
1962 651480 GAP 182 21N 9E 8 SE
1963 651481 GAP 183 21N 9E 9 SW
1964 651482 GAP 184 21N 9E 9 SE
1965 651483 GAP 185 21N 9E 10 SW

  
Arctic ProjectPage 470
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

1966 651484 GAP 186 21N 9E 10 SE
1967 651485 GAP 187 21N 8E 15 NE
1968 651486 GAP 188 21N 8E 14 NW
1969 651487 GAP 189 21N 8E 14 NE
1970 651488 GAP 190 21N 8E 13 NW
1971 651489 GAP 191 21N 8E 13 NE
1972 651490 GAP 192 21N 9E 18 NW
1973 651491 GAP 193 21N 9E 18 NE
1974 651492 GAP 194 21N 9E 17 NW
1975 651493 GAP 195 21N 9E 17 NE
1976 651494 GAP 196 21N 9E 16 NW
1977 651495 GAP 197 21N 9E 16 NE
1978 651496 GAP 198 21N 9E 15 NW
1979 651497 GAP 199 21N 9E 15 NE
1980 655537 ZED 119 20N 12E 12 NW
1981 655538 ZED 120 20N 12E 12 NE
1982 655539 ZED 121 20N 13E 7 NW
1983 655540 ZED 122 20N 13E 7 SW
1984 655541 ZED 123 20N 13E 7 SE
1985 655542 ZED 124 20N 13E 8 SW
1986 655543 ZED 125 20N 13E 8 SE
1987 655648 KG 1 21N 11E 11 SW
1988 655649 KG 2 21N 11E 11 SE
1989 655650 KG 3 21N 11E 14 NW
1990 655651 KG 4 21N 11E 14 NE
1991 655652 KG 5 21N 11E 13 NW
1992 655653 KG 6 21N 11E 13 NE
1993 655654 KG 7 21N 11E 13 SE
1994 655655 KG 8 21N 11E 24 NE
1995 714584 East DH 1 22N 10E 15 SE
1996 714585 East DH 2 22N 10E 22 NE
1997 714586 East DH 3 22N 10E 23 NW
1998 714587 East DH 4 22N 10E 22 SE
1999 714588 East DH 5 22N 10E 23 SW
2000 714589 COBRE 1 22N 7E 2 NW
2001 714590 COBRE 2 22N 7E 2 NE
2002 714591 COBRE 3 22N 7E 1 NW
2003 714592 COBRE 4 22N 7E 1 NE
2004 714593 COBRE 5 22N 8E 6 NW
2005 714594 COBRE 6 22N 8E 6 NE
2006 714595 COBRE 7 22N 8E 5 NW
2007 714596 COBRE 8 22N 8E 5 NE
2008 714597 COBRE 9 22N 7E 2 SW
2009 714598 COBRE 10 22N 7E 2 SE

  
Arctic ProjectPage 471
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

2010 714599 COBRE 11 22N 7E 1 SW
2011 714600 COBRE 12 22N 7E 1 SE
2012 714601 COBRE 13 22N 8E 6 SW
2013 714602 COBRE 14 22N 8E 6 SE
2014 714603 COBRE 15 22N 8E 5 SW
2015 714604 COBRE 16 22N 8E 5 SE
2016 714605 COBRE 17 22N 7E 11 NW
2017 714606 COBRE 18 22N 7E 11 NE
2018 714607 COBRE 19 22N 7E 12 NW
2019 714608 COBRE 20 22N 7E 12 NE
2020 714609 COBRE 21 22N 8E 7 NW
2021 714610 COBRE 22 22N 8E 7 NE
2022 714611 COBRE 23 22N 8E 8 NW
2023 714612 COBRE 24 22N 8E 8 NE
2024 714613 COBRE 25 22N 8E 9 NW
2025 714614 COBRE 26 22N 8E 9 NE
2026 714615 COBRE 27 22N 8E 7 SE
2027 714616 COBRE 28 22N 8E 8 SW
2028 714617 COBRE 29 22N 8E 8 SE
2029 714618 COBRE 30 22N 8E 9 SW
2030 714619 COBRE 31 22N 8E 9 SE
2031 714620 COBRE 32 22N 8E 17 NW
2032 714621 COBRE 33 22N 8E 17 NE
2033 714622 COBRE 34 22N 8E 16 NW
2034 714623 COBRE 35 22N 8E 16 NE
2035 714624 COBRE 36 22N 8E 15 NW
2036 714625 COBRE 37 22N 8E 15 NE
2037 714626 COBRE 38 22N 8E 17 SE
2038 714627 COBRE 39 22N 8E 16 SW
2039 714628 COBRE 40 22N 8E 16 SE
2040 714629 COBRE 41 22N 8E 15 SW
2041 714630 COBRE 42 22N 8E 15 SE
2042 714631 COBRE 43 22N 8E 21 NW
2043 714632 COBRE 44 22N 8E 21 NE
2044 714633 COBRE 45 22N 8E 22 NW
2045 714634 COBRE 46 22N 8E 22 NE
2046 714635 COBRE 47 22N 8E 23 NW
2047 714636 COBRE 48 22N 8E 23 NE
2048 714637 COBRE 49 22N 8E 21 SW
2049 714638 COBRE 50 22N 8E 21 SE
2050 714639 COBRE 51 22N 8E 22 SW
2051 714640 COBRE 52 22N 8E 22 SE
2052 714641 COBRE 53 22N 8E 23 SW
2053 714642 COBRE 54 22N 8E 23 SE

  
Arctic ProjectPage 472
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

2054 714643 West Horse 1 22N 9E 12 SW
2055 714644 West Horse 2 22N 9E 12 SE
2056 714645 West Horse 3 22N 10E 7 SW
2057 714646 West Horse 4 22N 10E 7 SE
2058 714647 West Horse 5 22N 10E 8 SW
2059 714648 West Horse 6 22N 9E 13 NW
2060 714649 West Horse 7 22N 9E 13 NE
2061 714650 West Horse 8 22N 9E 13 SW
2062 714651 West Horse 9 22N 9E 13 SE
2063 714652 West Horse 10 22N 9E 24 NW
2064 714653 West Horse 11 22N 9E 24 NE
2065 714654 West Horse 12 22N 9E 24 SW
2066 714655 West Horse 13 22N 9E 24 SE
2067 714656 West Horse 14 22N 9E 27 NE
2068 714657 West Horse 15 22N 9E 26 NW
2069 714658 West Horse 16 22N 9E 26 NE
2070 714659 West Horse 17 22N 9E 25 NW
2071 714660 West Horse 18 22N 9E 25 NE
2072 714661 West Horse 19 22N 9E 27 SE
2073 714662 West Horse 20 22N 9E 26 SW
2074 714663 West Horse 21 22N 9E 26 SE
2075 714664 West Horse 22 22N 9E 25 SW
2076 714665 West Horse 23 22N 9E 25 SE
2077 714748 AM 37-225 20N 12E 16 SW
2078 714749 AM 38-225 20N 12E 16 SW
2079 714750 AM 39-225 20N 12E 16 NW
2080 714751 AM 40-225 20N 12E 16 NW
2081 714752 AM 41-223 20N 12E 8 SE
2082 714753 AM 41-224 20N 12E 8 SE
2083 714754 AM 43-219 20N 12E 7 NE
2084 714755 AM 43-220 20N 12E 7 NE
2085 714756 AM 38-217 20N 12E 18 SW

  
Arctic ProjectPage 473
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

2086 714757 AM 38-219 20N 12E 18 SE
2087 714758 AM 38-221 20N 12E 17 SW
2088 714759 AM 38-223 20N 12E 17 SE
2089 714760 AM 42-219 20N 12E 7 SE
2090 714761 AM 42-221 20N 12E 8 SW
2091 714762 AM 44-217 20N 12E 7 NW
2092 714763 AM 40-217 20N 12E 18 NW
2093 714764 AM 40-219 20N 12E 18 NE
2094 714765 AM 40-221 20N 12E 17 NW
2095 714766 AM 40-223 20N 12E 17 NE
2096 714767 AM 42-217 20N 12E 7 SW
2097 714768 KG 9 21N 12E 19 NW
2098 714769 KG 10 21N 12E 19 NE
2099 714770 KG 11 21N 12E 19 SW
2100 714771 KG 12 21N 12E 19 SE
2101 715147 Cobre 55 23N 7E 14 SW
2102 715148 Cobre 56 23N 7E 14 SE
2103 715149 Cobre 57 23N 7E 13 SW
2104 715150 Cobre 58 23N 7E 23 NW
2105 715151 Cobre 59 23N 7E 23 NE
2106 715152 Cobre 60 23N 7E 24 NW
2107 715153 Cobre 61 23N 7E 24 NE
2108 715154 Cobre 62 23N 8E 19 NW
2109 715155 Cobre 63 23N 7E 23 SE
2110 715156 Cobre 64 23N 7E 24 SW
2111 715157 Cobre 65 23N 7E 24 SE
2112 715158 Cobre 66 23N 8E 19 SW
2113 715159 Cobre 67 23N 8E 19 SE
2114 715160 Cobre 68 23N 7E 26 NE
2115 715161 Cobre 69 23N 7E 25 NW
2116 715162 Cobre 70 23N 7E 25 NE
2117 715163 Cobre 71 23N 8E 30 NW
2118 715164 Cobre 72 23N 8E 30 NE
2119 715165 Cobre 73 23N 8E 29 NW
2120 715166 Cobre 74 23N 8E 29 NE
2121 715167 Cobre 75 23N 7E 26 SE
2122 715168 Cobre 76 23N 7E 25 SW
2123 715169 Cobre 77 23N 7E 25 SE
2124 715170 Cobre 78 23N 8E 30 SW
2125 715171 Cobre 79 23N 8E 30 SE
2126 715172 Cobre 80 23N 8E 29 SW
2127 715173 Cobre 81 23N 8E 29 SE
2128 715174 Cobre 82 23N 7E 36 NW
2129 715175 Cobre 83 23N 7E 36 NE

  
Arctic ProjectPage 474
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

   
   

 

2130 715176 Cobre 84 23N 8E 31 NW
2131 715177 Cobre 85 23N 8E 31 NE
2132 715178 Cobre 86 23N 8E 32 NW
2133 715179 Cobre 87 23N 8E 32 NE
2134 715180 Cobre 88 23N 8E 31 SE
2135 715181 Cobre 89 23N 8E 32 SW
2136 715182 Cobre 90 23N 8E 32 SE

  
Arctic ProjectPage 475
S-K 1300 Technical Report SummaryNovember 30, 2022
  

 

 

   
   

 

Date and Signature Page

 

This technical report summary (the TRS), entitled “Technical Report Summary on the Arctic Project, Ambler Mining District, Alaska” is current as at November 30, 2022 and has been prepared by:

 

Qualified Person or
Consulting Firm
Responsible for the following
sections
Signature Date
Ausenco Engineering Canada Ltd 1.1, 1.3, 1.4, 1.9, 1.13, 1.14.1, 1.14.2, 1.14.3, 1.14.4, 1.15, 1.17, 1.18, 1.19, 1.20.8, 1.20.9, 1.20.10, 2, 3.1, 3.2, 3.10, 4, 5.3.8, 10, 14, 15.1, 15.2, 15.3, 15.4, 15.5, 15.6, 15.7, 15.10.8, 15.12, 15.13, 15.14, 15.15, 15.16, 16, 18.1.1, 18.1.2, 18.1.3, 18.1.4, 18.1.5, 18.1.7, 18.1.9, 18.1.10, 18.1.11, 18.1.12, 18.1.13, 18.1.14, 18.2.1, 18.2.3, 18.2.4, 18.2.5, 18.2.6, 19, 21, 22.1, 22.2, 22.5, 22.9, 22.10, 22.12, 22.13, 22.14, 22.15, 22.16, 22.17.8, 22.17.9, 23.1, 23.9, 23.10, 23.11, 24, 25.1, 25.3, 25.5 “signed” Feb 13, 2023
Brown & Caldwell 1.14.9, 1.20.7, 2.3, 15.9, 17.3.4, 17.3.6.2, 18.1.9.1, 18.2.6, 23.8, 25.2 “signed” Feb 13, 2023
SRK Consulting (Canada) Inc. 1.14.6, 1.14.7, 1.14.8, 1.16.3, 1.20.3, 1.20.4, 1.20.5, 1.20.6, 2.3, 2.4, 3.7, 3.8, 3.9, 3.10, 5.3.7, 7.2.4, 8.1.2, 8.2.5, 13.9, 13.10.1, 13.11, 15.8, 15.10.1, 15.10.2, 15.10.3, 15.10.4, 15.10.5, 15.10.6, 15.10.7, 15.11, 17.3.1, 17.3.2, 17.3.3, 17.3.5, 17.6, 22.17.3, 22.17.4, 22.17.5, 22.17.6, 22.17.7, 23.4, 23.5, 23.6, 23.7, 25.2, 25.4 “signed” Feb 13, 2023
Wood Canada Limited 1.2.1, 1.5, 1.6, 1.7, 1.8, 1.10, 1.11, 1.12, 1.14.5, 1.20.1, 1.20.2, 2.3, 2.4, 2.5, 2.6, 3.3, 3.4, 3.5, 3.6, 3.10, 6, 7.1, 7.2.1, 7.2.2, 7.2.3, 7.2.5, 7.2.6, 7.2.7, 7.2.8, 8.1.1, 8.1.3, 8.1.4, 8.1.5, 8.1.6, 8.2.1, 8.2.2, 8.2.3, 8.2.4, 8.3, 9, 11, 12, 13.1, 13.2, 13.3, 13.4, 13.5, 13.6, 13.7, 13.8, 13.10, 17.1, 17.2, 18.1.6, 18.2.2, 22.2, 22.3, 22.4, 22.6, 22.7, 22.8, 22.17.1, 22.17.2, 23.2, 23.3, 25.2, 25.4, 25.5 “signed” Feb 13, 2023

 

  
Arctic ProjectPage 476