Suspended Well Costs
6 Months Ended
Jun. 30, 2016
Suspended Well Costs  
Suspended Well Costs

6. Suspended Well Costs

 

The following table reflects the Company’s capitalized exploratory well costs on completed wells as of and during the six months ended June 30, 2016. The table excludes $2.3 million in costs that were capitalized and subsequently expensed during the same period.

 

 

 

 

 

 

 

 

June 30,

 

 

    

2016

 

 

 

(In thousands)

 

Beginning balance 

 

$

426,881

 

Additions to capitalized exploratory well costs pending the determination of proved reserves 

 

 

293,518

 

Reclassification due to determination of proved reserves 

 

 

 —

 

Capitalized exploratory well costs charged to expense 

 

 

 —

 

Ending balance 

 

$

720,399

 

 

The following table provides an aging of capitalized exploratory well costs based on the date drilling was completed and the number of projects for which exploratory well costs have been capitalized for more than one year since the completion of drilling:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

    

June 30, 2016

    

December 31, 2015

 

 

 

(In thousands, except well counts)

 

Exploratory well costs capitalized for a period of one year or less

 

$

359,596

 

$

199,486

 

Exploratory well costs capitalized for a period of one to two years

 

 

151,103

 

 

17,702

 

Exploratory well costs capitalized for a period of three to seven years

 

 

209,700

 

 

209,693

 

Ending balance

 

$

720,399

 

$

426,881

 

Number of projects that have exploratory well costs that have been capitalized for a period greater than one year

 

 

4

 

 

3

 

 

As of June 30, 2016, the projects with exploratory well costs capitalized for more than one year since the completion of drilling are related to the Mahogany, Teak (formerly Teak-1 and Teak-2) and Akasa discoveries in the West Cape Three Points (“WCTP”) Block and the Wawa discovery in the DT Block, which are all located offshore Ghana, and the Greater Tortue discovery which crosses the Mauritania and Senegal maritime border.

 

Mahogany and Teak Discoveries — In November 2015, we signed the Jubilee Field Unit Expansion Agreement with our partners to allow for the development of the Mahogany and Teak discoveries through the Jubilee FPSO and infrastructure. The expansion of the Jubilee Unit becomes effective upon approval by Ghana’s Ministry of Petroleum of the Greater Jubilee Full Field Development Plan (“GJFFDP”), which was submitted to the government of Ghana in December 2015. The GJFFDP encompasses future development of the Jubilee Field, in addition to future development of the Mahogany and Teak discoveries, which were declared commercial during 2015. We are currently in discussions with the government of Ghana concerning the GJFFDP. Upon approval of the GJFFDP by the Ministry of Petroleum, the Jubilee Unit will be expanded to include the Mahogany and Teak discoveries and revenues and expenses associated with these discoveries will be at the Jubilee Unit interests. The WCTP Block partners have agreed they will take the steps necessary to transfer operatorship of the remaining portions of the WCTP Block to Tullow after approval of the GJFFDP by Ghana’s Ministry of Petroleum.

 

Akasa Discovery — We are currently in discussions with the government of Ghana regarding additional technical studies and evaluation that we want to conduct before we are able to make a determination regarding commerciality of the discovery. If we determine the discovery to be commercial, a declaration of commerciality would be provided and a PoD would be prepared and submitted to Ghana’s Ministry of Petroleum, as required under the WCTP petroleum contract. The WCTP Block partners have agreed they will take the steps necessary to transfer operatorship of the remaining portions of the WCTP Block, including the Akasa Discovery, to Tullow after approval of the GJFFDP by Ghana’s Ministry of Petroleum.

 

Wawa Discovery — In February 2016, we requested the Ghana Ministry of Petroleum to approve the enlargement of the areal extent of the TEN development and production area to capture the resource accumulation located in the Wawa Discovery Area for a potential future integrated development with the TEN development project. In April 2016, the Ghana Ministry of Petroleum approved our request to enlarge the TEN development and production area subject to continued subsurface and development concept evaluation, along with the requirement to integrate the Wawa Discovery into the TEN PoD.

 

Greater Tortue Discovery — In May 2015, we completed the Tortue-1 exploration well in Block C8 offshore Mauritania which encountered hydrocarbon pay. Two additional wells have been drilled. Following additional evaluation, a decision regarding commerciality will be made.