XML 49 R11.htm IDEA: XBRL DOCUMENT v2.4.0.6
Suspended Well Costs
3 Months Ended
Mar. 31, 2013
Suspended Well Costs  
Suspended Well Costs

4. Suspended Well Costs

 

The following table reflects the Company’s capitalized exploratory well costs on completed wells as of and during the three months ended March 31, 2013. The table excludes $8.1 million in costs that were capitalized and subsequently expensed during the same period.

 

 

 

Three months
ended

March 31, 2013

 

 

 

(In thousands)

 

Beginning balance

 

$

372,492

 

Additions to capitalized exploratory well costs pending the determination of proved reserves

 

937

 

Reclassification due to determination of proved reserves

 

 

Capitalized exploratory well costs charged to expense

 

(1,705

)

Ending balance

 

$

371,724

 

 

The following table provides aging of capitalized exploratory well costs based on the date drilling was completed and the number of projects for which exploratory well costs have been capitalized for more than one year since the completion of drilling:

 

 

 

March 31, 2013

 

December 31, 2012

 

 

 

(In thousands, except well counts)

 

Exploratory well costs capitalized for a period of one year or less

 

$

56,903

 

$

106,635

 

Exploratory well costs capitalized for a period one to two years

 

215,320

 

179,933

 

Exploratory well costs capitalized for a period three to four years

 

99,501

 

85,924

 

Ending balance

 

$

371,724

 

$

372,492

 

Number of projects that have exploratory well costs that have been capitalized for a period greater than one year

 

7

 

7

 

 

As of March 31, 2013, the projects with exploratory well costs capitalized for more than one year since the completion of drilling are related to Mahogany, Teak-1, Teak-2 and Akasa discoveries in the West Cape Three Points (“WCTP”) Block and the Tweneboa, Enyenra and Ntomme discoveries in the Deepwater Tano (“DT”) Block, which are all in Ghana.

 

Mahogany—Mahogany, a combined area covering parts of the Mahogany East discovery and the Mahogany Deep discovery, was declared commercial in September 2010, and a PoD was submitted to Ghana’s Ministry of Energy as of May 2, 2011. In a letter dated May 16, 2011, the Ministry of Energy did not approve the PoD and requested that the WCTP Block partners take certain steps regarding notifications of discovery and commerciality; and requested other information. The WCTP Block partners believe the combined submission was proper and have held meetings with Ghana National Petroleum Corporation (“GNPC”) which resolved issues relating to the PoD work program. From May 2011, the Ministry of Energy, GNPC and the WCTP Block partners continued working to resolve other differences; however, the WCTP Petroleum Agreement (“PA”) contains specific timelines for PoD approval and discussions, which expired at the end of June 2011. On June 30, 2011, we, as Operator of the WCTP Block and on behalf of the WCTP Block partners, delivered a Notice of Dispute to the Ministry of Energy and GNPC as provided under the WCTP PA, which is the initial step in triggering the formal dispute resolution process under the WCTP PA with the government of Ghana regarding approval of the Mahogany PoD. This Notice of Dispute establishes a process for negotiation and consultation for a period of 30 days (or longer if mutually agreed) among senior representatives from the Ministry of Energy, GNPC and the WCTP Block partners to resolve the matter. We and the WCTP Block partners are in discussions with the Ministry of Energy and GNPC to resolve differences on the PoD.

 

Teak-1 Discovery—Two appraisal wells have been drilled. Following additional appraisal and evaluation, a decision regarding commerciality of the Teak-1 discovery is expected to be made by the WCTP Block partners in 2014. Within six months of such a declaration, a PoD would be prepared and submitted to Ghana’s Ministry of Energy, as required under the WCTP PA.

 

Teak-2 Discovery—We have performed a gauge installation on the well and are reprocessing seismic data. Following additional appraisal and evaluation, a decision regarding commerciality of the Teak-2 discovery is expected to be made by the WCTP Block partners in 2014. Within six months of such a declaration, a PoD would be prepared and submitted to Ghana’s Ministry of Energy, as required under the WCTP PA.

 

Akasa Discovery—We have performed a drill stem test and gauge installation on the well and are analyzing the data. Following additional appraisal and evaluation, a decision regarding commerciality of the Akasa discovery is expected to be made by the WCTP Block partners in 2013. Within six months of such a declaration, a PoD would be prepared and submitted to Ghana’s Ministry of Energy, as required under the WCTP PA.

 

Tweneboa, Enyenra and Ntomme (“TEN”) Discoveries—During 2012, we submitted a declaration of commerciality and PoD over the TEN discoveries and are awaiting approval from the government of Ghana.