Commitments and Contingencies Commitments and Contingencies
Aircraft-Related Commitments and Financing Arrangements

The Company’s contractual purchase commitments consist primarily of aircraft and engine acquisitions through manufacturers and aircraft leasing companies. On April 3, 2024, the Company entered into Amendment No. 7 (the "Amendment") to the A320 NEO Family Purchase Agreement, dated as of December 20, 2019 (the "Airbus Purchase Agreement") with Airbus S.A.S. ("Airbus"). The Amendment (i) defers all aircraft on order that are scheduled to be delivered in the second quarter of 2025 through the end of 2026 to 2030-2031, and (ii) adjusts the delivery periods of option aircraft from 2027-2029 to 2029-2031. On July 30, 2024, the Company entered into a direct lease transaction (the “Direct Lease Transaction”) with AerCap Holdings N.V. (“AerCap”) for 36 aircraft scheduled for delivery between 2027 and 2028 (the “Leased Aircraft”) which were originally part of the Company’s order book. Under the terms of the transaction, AerCap will assume the delivery positions for the Leased Aircraft and related pre-delivery payment ("PDP") obligations. AerCap has agreed to lease each Leased Aircraft to the Company upon delivery by Airbus. Each of the leases will have fixed rent payments.

As of September 30, 2024, the Company's total firm aircraft orders consisted of 56 A320 family aircraft with Airbus, including A320neos and A321neos, with deliveries expected through 2031. As of September 30, 2024, the Company had secured financing for four aircraft scheduled for delivery from Airbus through 2025, which will be financed through sale leaseback transactions. As of September 30, 2024, the Company did not have financing commitments in place for the remaining 52 Airbus aircraft on firm order through 2031. However, the Company has a financing letter of agreement with Airbus which provides backstop financing for a majority of the aircraft included in the Airbus Purchase Agreement. The agreement provides a standby credit facility in the form of senior secured mortgage debt financing. The contractual purchase amounts for all aircraft orders from Airbus as of September 30, 2024 are included within the purchase commitments below. In addition, rent commitments related to aircraft that will be financed through sale leaseback transactions are included within the aircraft rent commitments below.
In connection with the Direct Lease Transaction, on July 30, 2024, the Company entered into a transaction (the “PDP Transaction”) whereby certain PDPs with respect to 52 aircraft currently scheduled for delivery between 2029 and 2031 (the “Other Aircraft”), subject to the Airbus Purchase Agreement were paid to the Company (the “Funded PDPs”) at closing of the
PDP Transaction. The Direct Lease Transaction and the PDP Transaction, in the aggregate, resulted in approximately $186 million of additional cash paid to the Company.

During the third quarter of 2021, the Company entered into an Engine Purchase Support Agreement that requires the Company to purchase a certain number of spare engines in order to maintain a contractual ratio of spare engines to aircraft in the fleet. As of September 30, 2024, the Company is committed to purchase 16 PW1100G-JM spare engines, with deliveries through 2031.

As of September 30, 2024, purchase commitments for the Company's aircraft and engine orders, including estimated amounts for contractual price escalations and pre-delivery payments, were expected to be $56.4 million for the remainder of 2024, $143.9 million in 2025, $12.3 million in 2026, $183.0 million in 2027, $297.8 million in 2028 and $2,982.1 million in 2029 and beyond.

During the third quarter of 2019, the United States announced its decision to levy tariffs on certain imports from the European Union, including commercial aircraft and related parts. These tariffs include aircraft and other parts that the Company is already contractually obligated to purchase including those reflected above. In June 2021, the United States Trade Representative announced that the United States and European Union had agreed to suspend reciprocal tariffs on large civilian aircraft for five years, pending discussions to resolve their trade dispute.

In addition to the Airbus Purchase Agreement, as of September 30, 2024, the Company had agreements in place for 41 A320neos and A321neos to be financed through direct leases with third-party lessors with deliveries scheduled from the remainder of 2024 through 2028. As of September 30, 2024, aircraft rent commitments for future aircraft deliveries to be financed under direct leases from third-party lessors and sale leaseback transactions were expected to be approximately $1.8 million for the remainder of 2024, $33.8 million in 2025, $40.5 million in 2026, $101.7 million in 2027, $196.6 million in 2028 and $2,538.6 million in 2029 and beyond.
Interest commitments related to the secured debt financing of 69 delivered aircraft as of September 30, 2024 were $21.6 million for the remainder of 2024, $81.8 million in 2025, $75.3 million in 2026, $67.9 million in 2027, $59.0 million in 2028 and $246.2 million in 2029 and beyond. As of September 30, 2024, interest commitments related to the Company's 8.00% senior secured notes, convertible debt financing, unsecured term loans and revolving credit facility were $25.3 million for the remainder of 2024, $89.4 million in 2025, $5.9 million in 2026, $3.4 million in 2027, $3.4 million in 2028, and $7.1 million in 2029 and beyond. For principal commitments related to the Company's debt financing, refer to Note 13, Debt and Other Obligations.
Other Commitments
The Company is contractually obligated to pay the following minimum guaranteed payments for its reservation system and other miscellaneous subscriptions and services as of September 30, 2024: $9.6 million for the remainder of 2024, $39.0 million in 2025, $21.7 million in 2026, $18.0 million in 2027, $2.0 million in 2028 and $0.1 million in 2029 and thereafter. The Company's reservation system contract expires in 2028.
 
Litigation and Assessments
The Company is subject to commercial litigation claims and to administrative and regulatory proceedings and reviews that may be asserted or maintained from time to time. The Company believes the ultimate outcome of such lawsuits, proceedings and reviews will not, individually or in the aggregate, have a material adverse effect on its financial position, liquidity or results of operations. In making a determination regarding accruals, using available information, the Company evaluates the likelihood of an unfavorable outcome in legal or regulatory proceedings and assessments to which the Company is a party and records a loss contingency when it is probable a liability has been incurred and the amount of the loss can be reasonably estimated. These subjective determinations are based on the status of such legal or regulatory proceedings, the merits of the Company's defenses, and consultation with legal counsel. Actual outcomes of these legal and regulatory proceedings may materially differ from the Company's current estimates. It is possible that resolution of one or more of the legal matters currently pending or threatened could result in losses material to the Company's condensed consolidated results of operations, liquidity or financial condition.
In 2017, the Company was sued in the Eastern District of New York ("EDNY") in a purported class action, Cox, et al. v. Spirit Airlines, Inc., alleging state-law claims of breach of contract, unjust enrichment and fraud relating to the Company's practice of charging fees for ancillary products and services. In June 2023, the Company reached a tentative settlement in mediation for a maximum amount of $8.3 million. The EDNY issued a preliminary approval order on September 21, 2023, and the final approval hearing was held on December 11, 2023. The total amount to be paid depends on a number of factors, including participation of class members and any conditions on the settlement approved by the EDNY. As of December 31, 2023, the Company's best estimate of the probable loss associated with the settlement was $6.0 million recorded in other operating expenses within its condensed consolidated statements of operations. During the first and third quarters of 2024, the estimated probable loss recorded was reduced by $1.4 million and $0.3 million, respectively. As of September 30, 2024, the total obligation of $4.3 million related to this matter has been paid.
On February 27, 2023, ALPA filed a grievance against the Company claiming that it violated the collective bargaining agreement (“CBA”) by excluding its pilots from the Company's retention award programs granted as part of the former Frontier Merger Agreement and the former JetBlue Merger Agreement. On September 8, 2023, the Company filed a motion to dismiss the grievance, as it does not believe that ALPA filed the grievance within the timeline set forth in the CBA. As of September 30, 2024, the grievance is postponed indefinitely. The potential outcome of this claim cannot be determined, and an estimate of the reasonably possible loss or range of loss cannot be made.
Following an audit by the Internal Revenue Service ("IRS") related to the collection of federal excise taxes on optional passenger seat selection charges covering the period of the second quarter of 2018 through the fourth quarter of 2020, on March 31, 2022, the Company was assessed $34.9 million. On July 19, 2022, the assessment was reduced to $27.5 million. The Company believes it has defenses available and intends to challenge the assessment; therefore, the Company believes a loss in this matter is not probable and has not recognized a loss contingency.
Credit Card Processing Arrangements
The Company has agreements with organizations that process credit card transactions arising from the purchase of air travel, baggage charges and other ancillary services by customers. As is standard in the airline industry, the Company's contractual arrangements with credit card processors permit them, under certain circumstances, to retain a holdback or other collateral, which the Company records as restricted cash, when future air travel and other future services are purchased via credit card transactions. The required holdback is the percentage of the Company's overall credit card sales that its credit card processors hold to cover refunds to customers if the Company fails to fulfill its flight obligations.
The Company's credit card processors require the Company to maintain cash collateral, provided that the Company satisfies certain liquidity and other financial covenants. Failure to meet these covenants would provide the processors the right to place a holdback resulting in a commensurate reduction of unrestricted cash. As of September 30, 2024 and December 31, 2023, the Company's credit card processors were holding back no remittances.
The maximum potential exposure to cash holdbacks by the Company's credit card processors, based upon advance ticket sales and Spirit Saver$ Club® memberships as of September 30, 2024 and December 31, 2023, was $484.1 million and $408.3 million, respectively.
On July 2, 2024, the Company entered into a letter agreement that modified its existing credit card processing agreement to, among other things, extend the term until December 31, 2025, including automatic extensions for two successive one-year terms (subject to the right of either party to opt out of any extension term by written notice to the other within a specified period of time prior to the commencement of any extension term); provided that if the Company’s senior secured notes due 2025 are not extended or refinanced by September 20, 2024 (the “2025 Notes Extension Deadline”), in a specified minimum outstanding principal amount thereof, then the term will revert to December 31, 2024 (the “Early Maturity Date”). Based on the terms of the agreement, in July 2024, the Company deposited $200.0 million into a deposit account and deposited $50.0 million into a restricted account. The $200.0 million deposited into the deposit account is considered a compensating balance arrangement that does not legally restrict the Company's use of this cash. As such, the balance of the deposit account is included in cash and cash equivalents within the Company's condensed consolidated balance sheets, and the $50.0 million in the restricted account is included in restricted cash within the Company's condensed consolidated balance sheets going forward.
On September 9, 2024, the Company entered into a letter agreement which modified its existing credit card processing agreement to extend the 2025 Notes Extension Deadline from September 20, 2024 to October 21, 2024.

On October 11, 2024, the Company entered into a letter agreement (the “Credit Card Processing Amendment”) which modified its existing credit card processing agreement to extend (i) the 2025 Notes Extension Deadline from October 21, 2024 to December 23, 2024 and (ii) the Early Maturity Date from December 31, 2024 to March 3, 2025.

Pursuant to the Credit Card Processing Amendment, the filing of the Chapter 11 Cases on November 18, 2024 constitutes a breach of contract, subject to the automatic stay resulting from the Chapter 11 Cases. For additional information on the Company's ongoing bankruptcy proceedings and its related automatic stay and other protections, refer to Note 14, Subsequent Events.
Employees
The Company has six union-represented employee groups that together represented approximately 85% of all employees as of September 30, 2024. The table below sets forth the Company's employee groups and status of the CBAs.
Employee GroupsRepresentative
Amendable Date (1)
Percentage of Workforce
PilotsAir Line Pilots Association, International ("ALPA")March 202428%
Flight AttendantsAssociation of Flight Attendants ("AFA-CWA")January 202644%
DispatchersProfessional Airline Flight Control Association ("PAFCA")August 20261%
Ramp Service AgentsInternational Association of Machinists and Aerospace Workers ("IAMAW")November 20263%
Passenger Service AgentsTransport Workers Union of America ("TWU")February 20273%
Aircraft Maintenance Technicians
Aircraft Mechanics Fraternal Association ("AMFA") (2)
N/A (2)
6%

(1) Subject to standard early opener provisions.
(2) CBA is currently under negotiation.

In August 2022, the Company's aircraft maintenance technicians ("AMTs") voted to be represented by AMFA as their collective bargaining agent. In November 2022, AMFA notified the Company of its intent to negotiate a CBA and began negotiations. In October 2023, AMFA filed for mediation with the National Mediation Board (“NMB”). In May 2024, the parties began negotiations with a NMB mediation, and those discussions are ongoing. As of September 30, 2024, the Company had approximately 670 AMTs.

In May 2023, PAFCA provided notice to the Company that it intends to amend its CBA with its dispatchers. The parties began negotiating changes to the CBA on July 12, 2023. In February 2024, PAFCA filed for mediation with the NMB. In April 2024, the parties began negotiations with a mediator. In July 2024, the Company reached an agreement with PAFCA for a new two-year agreement, which was ratified by PAFCA members on August 10, 2024. The ratified agreement includes increased pay rates.

In March 2024, ALPA provided notice to the Company that it intends to amend its CBA with its pilots. In July 2024, the parties began negotiations, and those discussions are ongoing.

In addition, to ensure that it has the right level of resources to meet its reduced aircraft capacity levels, primarily related to the increased AOG days due to GTF engine issues, the Company furloughed approximately 170 pilots, effective September 1, 2024. During the third quarter of 2024, the Company recorded $1.4 million in expenses related to the furloughs. These expenses were recorded within salaries, wages and benefits on the Company’s condensed consolidated statements of operations.