Property, Plant and Equipment, net
3 Months Ended
Mar. 31, 2012
Property, Plant and Equipment, net  
Property, Plant and Equipment, net

(6) Property, Plant and Equipment, net

        The Company capitalized $265.8 million and $416.8 million in plant modernization and other capital costs for the three months ended March 31, 2012 and the year ended December 31, 2011, respectively. These amounts include capitalized interest of $3.8 million and $7.5 million, respectively.

        Capital expenditures under the Company's initial modernization and expansion efforts, including the accelerated start-up of the Molycorp Mountain Pass facility ("Project Phoenix Phase 1"), and the Company's second phase capacity expansion plan ("Project Phoenix Phase 2"), and other capital projects related to operations at Molycorp Mountain Pass totaled $253.6 million and $388.5 million for the three months ended March 31, 2012 and the year ended December 31, 2011, respectively, on an accrual basis and excluding capitalized interest.

        At March 31, 2012 and December 31, 2011, property, plant and equipment consisted of the following (in thousands):

 
  March 31,
2012
  December 31,
2011
 

Land

  $ 11,350   $ 11,059  

Land improvements

    15,912     15,748  

Buildings and improvements

    26,376     23,677  

Plant and equipment

    85,752     68,441  

Vehicles

    1,548     1,235  

Computer software

    4,425     3,002  

Furniture and fixtures

    635     464  

Construction in progress

    683,860     436,547  

Mineral properties

    24,790     24,692  
           

Property, plant and equipment at cost

    854,648     584,865  

Less accumulated depreciation

    (26,932 )   (23,237 )
           

Property, plant and equipment, net

  $ 827,716   $ 561,628