Note 12 - Significant Contracts

Note 12 – Significant contracts

 

The Company has contracted with Korea Research Institute of Ships and Ocean Engineering (KRISO) for delivery of Cargo Inspection System (CIS) X-ray Accelerator which worth $945,447 on February 13, 2014. Under the payment term, 80% before shipment and 20% after the delivery, the Company has received 756,000 USD, the 80%, from KIOST on May 23, 2014. The delivery due date was postponed as request from KRISO. It was delivered but not installed, and the final 20% of the whole payment was billed to KRISO as of November 10, 2014. Final 20% was received by RadTek Inc. on 17th of November, 2014. The installation is scheduled in June 2015.

 

The Company also got the delivery contract with KRISO for Temperature Control Unit of the X-ray Accelerator, which worth $25,500, on July 21, 2014. On January 21, 2015, KRISO and the Company contracted for CIS Array Detection System which worth $332,956 . The installation of all two items are scheduled in June, 2015.

 

The Company got sales and delivery contract of its Food Inspection System, which worth 42,900,000 KRW ($38,000) with BIO PORT KOREA INC. on December 4, 2014 and completed the delivery in March 2015.

 

The Company got sales and delivery contract of its Food Inspection System, which worth 79,000,000 KRW ($70,000) with Hanultari Co., Ltd. on December 8, 2014 and completed the delivery in March 2015.

 

The Company contracted with SKTelecom for maintenance service of Korea Customs Service’s ‘Cargo Inspection Center II in Busan New Port.’ The contract ends on Dec 31, 2018 and the amount is 762,685,000 KRW ($672,000).