Rate and Regulatory Matters (Detail Textuals)
$ in Millions
9 Months Ended
Sep. 30, 2016
USD ($)
kV
mi
Otter Tail Power Company | Big Stone South - Brookings MVP  
Regulatory Matters [Line Items]  
Project costs incurred to date | $ $ 56.4
Percentage of assets of project 100.00%
Expanded capacity of projects | kV 345
Extended distance of transmission line | mi 70
Otter Tail Power Company | Big Stone South - Ellendale MVP | Minimum  
Regulatory Matters [Line Items]  
Extended distance of transmission line | mi 160
Otter Tail Power Company | Big Stone South - Ellendale MVP | Maximum  
Regulatory Matters [Line Items]  
Extended distance of transmission line | mi 170
Otter Tail Power Company | Big Stone South - Ellendale MVP | Federal Energy Regulatory Commission  
Regulatory Matters [Line Items]  
Project costs incurred to date | $ $ 39.8
Percentage of assets of project 100.00%
Expanded capacity of projects | kV 345
Big Stone AQCS Project BART - compliant AQCS  
Regulatory Matters [Line Items]  
Project costs incurred to date | $ $ 199.3
Capacity Expansion 2020 | Otter Tail Power Company | Brookings Project  
Regulatory Matters [Line Items]  
Investment to acquire ownership interest | $ $ 26.3
Percentage of ownership interest acquired in transmission line 4.80%
Distance of transmission line | mi 250
Capacity Expansion 2020 | Otter Tail Power Company | Fargo-Monticello Project  
Regulatory Matters [Line Items]  
Investment to acquire ownership interest | $ $ 81.5
Percentage of ownership interest acquired in transmission line 14.20%
Distance of transmission line | mi 240
Percentage of assets of project 100.00%