XML 39 R26.htm IDEA: XBRL DOCUMENT v3.5.0.2
Regulatory Assets and Liabilities (Tables)
9 Months Ended
Sep. 30, 2016
Regulatory Assets and Liabilities Disclosure [Abstract]  
Schedule of amount of regulatory assets and liabilities
 
    September 30, 2016     Remaining
Recovery/
(in thousands)   Current     Long-Term     Total     Refund Period
Regulatory Assets:                            
Prior Service Costs and Actuarial Losses on Pensions and Other Postretirement Benefits1   $ 7,439     $ 94,671     $ 102,110     see below
Deferred Marked-to-Market Losses1     4,063       7,483       11,546     51 months
Conservation Improvement Program Costs and Incentives2     4,286       3,079       7,365     24 months
Accumulated ARO Accretion/Depreciation Adjustment1           6,031       6,031     asset lives
Big Stone II Unrecovered Project Costs – Minnesota1     619       2,444       3,063     55 months
North Dakota Renewable Resource Rider Accrued Revenues2     1,608       826       2,434     18 months
Debt Reacquisition Premiums1     349       1,278       1,627     192 months
Deferred Income Taxes1           1,157       1,157     asset lives
Minnesota Deferred Rate Case Expenses Subject to Recovery1     748             748     12 months
Big Stone II Unrecovered Project Costs – South Dakota2     101       567       668     80 months
North Dakota Transmission Cost Recovery Rider Accrued Revenues2           544       544     27 months
MISO Schedule 26/26A Transmission Cost Recovery Rider True-up2     474       43       517     27 months
South Dakota Transmission Cost Recovery Rider Accrued Revenues2     225             225     12 months
Minnesota Renewable Resource Rider Accrued Revenues2     46             46     12 months
Total Regulatory Assets   $ 19,958     $ 118,123     $ 138,081      
Regulatory Liabilities:                            
Accumulated Reserve for Estimated Removal Costs – Net of Salvage   $     $ 77,603       77,603     asset lives
Refundable Fuel Clause Adjustment Revenues     2,301             2,301     12 months
North Dakota Transmission Cost Recovery Rider Accrued Refund     638       758       1,396     24 months
Minnesota Transmission Cost Recovery Rider Accrued Refund     1,356             1,356     12 months
Revenue for Rate Case Expenses Subject to Refund – Minnesota     712       385       1,097     19 months
Deferred Income Taxes           918       918     asset lives
Minnesota Environmental Cost Recovery Rider Accrued Refund     370             370     12 months
South Dakota Environmental Cost Recovery Rider Accrued Refund     296             296     12 months
North Dakota Environmental Cost Recovery Rider Accrued Refund     256             256     12 months
Other     5       91       96     207 months
MISO Schedule 26/26A Transmission Cost Recovery Rider True-up           80       80     27 months
Total Regulatory Liabilities   $ 5,934     $ 79,835     $ 85,769      
Net Regulatory Asset Position   $ 14,024     $ 38,288     $ 52,312      

 

1Costs subject to recovery without a rate of return.

2Amount eligible for recovery under an alternative revenue program which includes an incentive or rate of return.

  
    December 31, 2015     Remaining
Recovery/
(in thousands)   Current     Long-Term     Total     Refund Period
Regulatory Assets:                            
Prior Service Costs and Actuarial Losses on Pensions and Other Postretirement Benefits1   $ 7,439     $ 99,293     $ 106,732     see below
Deferred Marked-to-Market Losses1     4,063       10,530       14,593     60 months
Conservation Improvement Program Costs and Incentives2     4,411       4,266       8,677     18 months
Accumulated ARO Accretion/Depreciation Adjustment1           5,672       5,672     asset lives
Big Stone II Unrecovered Project Costs – Minnesota1     942       2,620       3,562     84 months
Debt Reacquisition Premiums1     351       1,539       1,890     201 months
Deferred Income Taxes1           1,455       1,455     asset lives
North Dakota Renewable Resource Rider Accrued Revenues2           1,266       1,266     15 months
MISO Schedule 26/26A Transmission Cost Recovery Rider True-up2     698       355       1,053     24 months
Big Stone II Unrecovered Project Costs – South Dakota2     100       643       743     89 months
Minnesota Transmission Cost Recovery Rider Accrued Revenues2     576             576     12 months
Minnesota Deferred Rate Case Expenses Subject to Recovery1     291             291     12 months
Minnesota Renewable Resource Rider Accrued Revenues2           68       68     see below
South Dakota Transmission Cost Recovery Rider Accrued Revenues2     33             33     12 months
Total Regulatory Assets   $ 18,904     $ 127,707     $ 146,611      
Regulatory Liabilities:                            
Accumulated Reserve for Estimated Removal Costs – Net of Salvage   $     $ 74,948     $ 74,948     asset lives
Refundable Fuel Clause Adjustment Revenues     1,834             1,834     12 months
Revenue for Rate Case Expenses Subject to Refund – Minnesota           1,279       1,279     see below
Deferred Income Taxes           1,110       1,110     asset lives
Minnesota Environmental Cost Recovery Rider Accrued Refund     777             777     12 months
North Dakota Environmental Cost Recovery Rider Accrued Refund     321             321     12 months
South Dakota Environmental Cost Recovery Rider Accrued Refund     185             185     12 months
North Dakota Transmission Cost Recovery Rider Accrued Refund     132             132     12 months
Deferred Gain on Sale of Utility Property – Minnesota Portion     5       95       100     216 months
North Dakota Renewable Resource Rider Accrued Refund     68             68     12 months
Total Regulatory Liabilities   $ 3,322     $ 77,432     $ 80,754      
Net Regulatory Asset Position   $ 15,582     $ 50,275     $ 65,857      

 1Costs subject to recovery without a rate of return.

2Amount eligible for recovery under an alternative revenue program which includes an incentive or rate of return.