XML 23 R10.htm IDEA: XBRL DOCUMENT v3.5.0.2
Rate and Regulatory Matters
9 Months Ended
Sep. 30, 2016
Rate and Regulatory Matters [Abstract]  
Rate and Regulatory Matters

3. Rate and Regulatory Matters

 

Below are descriptions of OTP’s major capital expenditure projects that have had, or will have, a significant impact on OTP’s revenue requirements, rates and alternative revenue recovery mechanisms, followed by summaries of specific electric rate or rider proceedings with the Minnesota Public Utilities Commission (MPUC), the North Dakota Public Service Commission (NDPSC), the South Dakota Public Utilities Commission (SDPUC) and the Federal Energy Regulatory Commission (FERC), impacting OTP’s revenues in 2016 and 2015.

 

Major Capital Expenditure Projects

 

Big Stone Plant Air Quality Control System (AQCS)—OTP completed construction and testing of the Big Stone Plant AQCS in the fourth quarter of 2015 and placed the AQCS into commercial operation on December 29, 2015. OTP’s capitalized cost of the project, excluding Allowance for Funds Used During Construction (AFUDC), as of September 30, 2016 was approximately $199.3 million.

 

Fargo–Monticello 345 kiloVolt (kVCapacity Expansion 2020 (CapX2020) Project (the Fargo Project)—OTP has invested approximately $81.5 million and has a 14.2% ownership interest in the jointly owned assets of this 240-mile transmission line, and owns 100% of certain assets of the project. The final phase of this project was energized on April 2, 2015.

 

Brookings–Southeast Twin Cities 345 kV CapX2020 Project (the Brookings Project)—OTP has invested approximately $26.3 million and has a 4.8% ownership interest in this 250-mile transmission line. The MISO approved the Brookings Project as a Multi-Value Project (MVP) under the MISO Open Access Transmission, Energy and Operating Reserve Markets Tariff (MISO Tariff) in December 2011. MVPs are designed to enable the region to comply with energy policy mandates and to address reliability and economic issues affecting multiple areas within the MISO region. The cost allocation of MVPs is designed to ensure the costs of transmission projects with regional benefits are properly assigned to those who benefit. The final segments of this line were energized on March 26, 2015.

 

The Big Stone South–Brookings MVP and CapX2020 Project—This 345 kV transmission line, currently under construction, will extend approximately 70 miles between a substation near Big Stone City, South Dakota and the Brookings County Substation near Brookings, South Dakota. OTP and Northern States Power – MN, a subsidiary of Xcel Energy Inc., jointly developed this project with obligations to have equal ownership interest in the transmission line portion of the project. MISO approved this project as an MVP under the MISO Tariff in December 2011. Construction began on this line in the third quarter of 2015 and the line is expected to be in service in fall 2017. OTP’s capitalized cost of this project as of September 30, 2016 was approximately $56.4 million, which includes assets that are 100% owned by OTP.

 

The Big Stone South–Ellendale MVP—This 345 kV transmission line will extend 160 to 170 miles between a substation near Big Stone City, South Dakota and a substation near Ellendale, North Dakota. OTP jointly developed this project with Montana-Dakota Utilities Co., a division of MDU Resources Group, Inc. (MDU) with obligations of having equal ownership interest in the transmission line portion of the project. Construction began on this line in the second quarter of 2016 and is expected to be completed in 2019. OTP’s capitalized cost of this project as of September 30, 2016 was approximately $39.8 million, which includes assets that are 100% owned by OTP.

 

Recovery of OTP’s major transmission investments is through the MISO Tariff (several as MVPs) and, currently, Minnesota, North Dakota and South Dakota Transmission Cost Recovery (TCR) Riders.

 

Minnesota

 

2016 General Rate Case—On February 16, 2016 OTP filed a request with the MPUC for an increase in revenue recoverable under general rates in Minnesota. In its filing, OTP requested an allowed rate of return on rate base of 8.07% and an allowed rate of return on equity of 10.4% based on an equity ratio of 52.5% of total capital. On February 26, 2016 the Minnesota Department of Commerce (MNDOC) concluded that the filing was complete. On April 14, 2016 the MPUC issued an order approving an interim rate increase of 9.56% to the base rate portion of customers’ bills, as modified and subject to refund. The request and interim rate information is detailed in the table below:

 

    Annualized or     Actual Through September 30, 2016  
($ in thousands)   Test Year     Three Months Ended     Nine Months Ended  
Revenue Increase Requested   $ 19,296                  
Increase Percentage Requested     9.80 %                
Jurisdictional Rate Base   $ 483,000                  
Interim Revenue Increase (subject to refund)   $ 16,816     $ 3,818     $ 6,875  

 

The major components of the requested rate increase are summarized below:

 

Revenue Requirement Deficiency Cost Factors (in thousands)   2016 Test Year
Allocation
 
Increased Rate Base   $ 10,000  
Increased Expenses     7,700  
Other     1,596  
Total Requested Revenue Increase   $ 19,296  
Excluded from Interim Rates: Rate Base Effect of Prepaid Pension Asset     (2,480 )
Approved Interim Revenue Increase (subject to refund)   $ 16,816  

 

The deadline for submission of intervenor direct testimony was August 16, 2016. Direct testimony of the MNDOC included a recommendation for an 8.86% allowed rate of return on equity and direct testimony of the Minnesota Office of the Attorney General (OAG) included a recommendation for a 6.96% allowed rate of return on equity. In response, in rebuttal testimony, OTP modified its request to provide for an allowed rate of return on equity of 10.05%. In rebuttal testimony, the MNDOC revised its recommendation to an 8.66% allowed rate of return on equity, and the Minnesota OAG revised its recommendation to a 7.14% allowed rate of return on equity. The deadline for submission of surrebuttal testimony was September 28, 2016. Hearings before the Administrative Law Judge (ALJ) occurred on October 13, 14 and 17, 2016.

 

Based on OTP’s modifications to its original request and other expected outcomes in the aforementioned rate case, OTP has recorded an estimated interim rate refund of $2.3 million as of September 30, 2016.

 

Expected dates for next steps in the procedural schedule:

 

· Report of ALJ ─ January 5, 2017
· Final order ─ March 16, 2017

 

2010 General Rate Case—OTP’s most recent general rate increase in Minnesota of approximately $5.0 million, or 1.6%, was granted by the MPUC in an order issued on April 25, 2011 and effective October 1, 2011. Pursuant to the order, OTP’s allowed rate of return on rate base increased from 8.33% to 8.61% and its allowed rate of return on equity increased from 10.43% to 10.74%.

 

Minnesota Conservation Improvement Programs (MNCIP)—OTP recovers conservation-related costs not included in base rates under the MNCIP through the use of an annual recovery mechanism approved by the MPUC. OTP requested approval for recovery of its 2014 MNCIP financial incentive and 2014 program costs not included in base rates from the MPUC in an April 1, 2015 filing. On July 9, 2015 the MPUC granted approval of OTP’s 2014 financial incentive of $3.0 million along with an updated surcharge with an effective date of October 1, 2015. Based on results from the 2015 MNCIP program year, OTP recognized a financial incentive of $4.2 million in 2015. The 2015 MNCIP program resulted in a 39% increase in energy savings compared to 2014 program results. On April 1, 2016 OTP requested approval for recovery of its 2015 MNCIP program costs not included in base rates, a $4.3 million financial incentive and an update to the MNCIP surcharge from the MPUC. On July 19, 2016 the MPUC issued an order approving OTP’s request with an effective date of October 1, 2016.

 

The MNDOC has proposed changes to the MNCIP financial incentive mechanism. On May 25, 2016 the MPUC adopted the MNDOC’s proposed changes to the MNCIP financial incentive. The new model will provide utilities an incentive of 13.5% of 2017 net benefits, 12% of 2018 net benefits and 10% of 2019 net benefits, assuming the utility achieves 1.7% savings compared to retail sales. OTP estimates the impact of the new model will reduce the MNCIP financial incentive by approximately 50% compared to the previous incentive mechanism.

 

The MNDOC opened an additional docket to investigate how investor-owned utilities calculate their avoided costs pertaining to generation capacity, energy, transmission and distribution. Avoided costs are the basis of MNCIP program benefits which going forward will establish OTP’s financial incentive. On May 23, 2016 the MNDOC accepted OTP’s 2017 avoided costs calculation, but is requiring Minnesota investor-owned utilities to undergo an analysis of transmission and distribution avoided costs for 2018 and 2019 with results to be submitted to the MNDOC by January 31, 2017.

 

Transmission Cost Recovery RiderThe Minnesota Public Utilities Act provides a mechanism for automatic adjustment outside of a general rate proceeding to recover the costs, plus a return on investment at the level approved in a utility’s last general rate case, of new transmission facilities that meet certain criteria. On February 18, 2015 the MPUC approved OTP’s 2014 TCR rider annual update with an effective date of March 1, 2015. OTP filed an annual update to its Minnesota TCR rider on September 30, 2015 requesting revenue recovery of approximately $7.8 million. A supplemental filing to the update was made on December 21, 2015 to address an issue surrounding the proration of accumulated deferred income taxes and, in an unrelated adjustment, the TCR rider update revenue request was reduced to $7.2 million. On March 9, 2016 the MPUC issued an order approving OTP’s annual update to its TCR rider, with an effective date of April 1, 2016. OTP filed an update to its TCR rider on April 29, 2016 to incorporate the impact of bonus depreciation for income taxes, an adjusted rate of return on rate base and allocation factors to align with its 2016 general rate case request. On July 5, 2016 the MPUC issued an order approving the proposed rates on a provisional basis, as recommended by the MNDOC. The proposed rate changes went into effect on September 1, 2016. The MPUC granted an extension to the MNDOC to file initial comments in this docket until November 1, 2016.

 

Environmental Cost Recovery Rider—On December 18, 2013 the MPUC granted approval of OTP’s Minnesota Environmental Cost Recovery (ECR) rider for recovery of OTP’s Minnesota jurisdictional share of the revenue requirements of its investment in the Big Stone Plant AQCS effective January 1, 2014. The ECR rider recoverable revenue requirements include a current return on the project’s construction work in progress (CWIP) balance at the level approved in OTP’s most recent general rate case. The MPUC approved OTP’s 2014 ECR rider annual update request on November 24, 2014 with an effective date of December 1, 2014. OTP filed its 2015 annual update on July 31, 2015, with a request to keep the 2014 annual update rate in place. On December 21, 2015 OTP filed a supplemental filing with updated financial information. The MPUC issued an order on March 9, 2016 approving OTP’s request to leave the 2014 annual update rate in place. OTP filed an update to its Minnesota ECR rider on April 29, 2016 to incorporate the impact of bonus depreciation for income taxes, an adjusted rate of return on rate base and allocation factors to align with its 2016 general rate case request, with an effective date of September 1, 2016. On July 5, 2016 the MPUC issued an order approving the proposed rates on a provisional basis and granted an extension to the MNDOC to file initial comments in this docket until November 1, 2016.

 

North Dakota

 

General Rates—OTP’s most recent general rate increase in North Dakota of $3.6 million, or approximately 3.0%, was granted by the NDPSC in an order issued on November 25, 2009 and effective December 2009. Pursuant to the order, OTP’s allowed rate of return on rate base was set at 8.62%, and its allowed rate of return on equity was set at 10.75%.

 

Renewable Resource Adjustment—OTP has a North Dakota Renewable Resource Adjustment (NDRRA) rider which enables OTP to recover the North Dakota share of its investments in renewable energy facilities it owns in North Dakota. This rider allows OTP to recover costs associated with new renewable energy projects as they are completed along with a return on investment. On March 25, 2015 the NDPSC approved OTP’s 2014 annual update to the NDRRA rider, including a change in rate design from an amount per kilowatt-hour consumed to a percentage of a customer’s bill, with an effective date of April 1, 2015. OTP submitted its 2015 annual update to the NDRRA rider rate on December 31, 2015 with a requested implementation date of April 1, 2016. On February 25, 2016 OTP made a supplemental filing to address the impact of bonus depreciation for income taxes and related deferred tax assets on the NDRRA, as well as an adjustment to the estimated amount of Federal Production Tax Credits used. The NDPSC approved the NDRRA 2015 annual update on June 22, 2016 with an effective date of July 1, 2016. The updated NDRRA reflects a reduction in the return on equity (ROE) component of the rate from 10.75%, approved in OTP’s most recent general rate case, to 10.50%.

 

Transmission Cost Recovery Rider—North Dakota law provides a mechanism for automatic adjustment outside of a general rate proceeding to recover jurisdictional capital and operating costs incurred by a public utility for new or modified electric transmission facilities. For qualifying projects, the law authorizes a current return on CWIP and a return on investment at the level approved in the utility's most recent general rate case. The NDPSC approved OTP’s 2014 annual update to its TCR rider rate on December 17, 2014 with an effective date of January 1, 2015. On August 31, 2015 OTP filed its 2015 annual update to its North Dakota TCR rider rate requesting recovery of approximately $10.2 million for 2016 compared with $8.5 million for 2015, including costs assessed by the MISO as well as new costs from the Southwest Power Pool (SPP) that OTP began incurring January 1, 2016. These new costs are associated with OTP’s load connected to the transmission system of Central Power Electric Cooperative (CPEC). OTP’s load became subject to SPP transmission-related charges when CPEC transmission assets were added to the SPP. The NDPSC approved OTP’s 2015 annual update to its TCR rider rate on December 16, 2015, with an effective date of January 1, 2016. On September 1, 2016 OTP filed its annual update to the TCR rider requesting a revenue requirement of $5.7 million, which includes a reduction of $2.6 million for a projected over-collection for 2016. Primary drivers of the decrease from the 2015 updated rider rate include the impact of federal bonus depreciation and unresolved MISO ROE complaint proceedings. OTP filed a supplemental filing on September 14, 2016, requesting that the current true-up over-collection balance be spread over the next two years for purposes of reducing the volatility of the rates from year to year. An informal hearing is scheduled for November 30, 2016.

 

Environmental Cost Recovery RiderOn February 8, 2013 OTP filed a request with the NDPSC for an ECR rider to recover OTP’s North Dakota jurisdictional share of the revenue requirements associated with its investment in the Big Stone Plant AQCS. On December 18, 2013 the NDPSC approved OTP’s North Dakota ECR rider based on revenue requirements through the 2013 calendar year and thereafter, with rates effective for bills rendered on or after January 1, 2014. The ECR provides for a current return on CWIP and a return on investment at the level approved in OTP’s most recent general rate case. The NDPSC approved OTP’s 2014 ECR rider annual update request on July 10, 2014 with an August 1, 2014 implementation date. On March 31, 2015 OTP filed its annual update to the ECR. This update included a request to increase the ECR rider rate from 7.531% to 9.193% of base rates. The NDPSC approved the annual update on June 17, 2015 with an effective date of July 1, 2015, along with the approval of recovery of OTP’s North Dakota jurisdictional share of Hoot Lake Plant Mercury and Air Toxics Standards (MATS) project costs.

 

On March 31, 2016 OTP filed its annual update to the ECR rider requesting a reduction in the rate from 9.193% to 7.904% of base rates, or a revenue requirement reduction from $12.2 million to $10.4 million, effective July 1, 2016. The rate reduction request was primarily due to the Company’s 2015 bonus depreciation election for income taxes, which reduces revenue requirements. The filing was approved on June 22, 2016.

 

Reagent Costs and Emission Allowances—On July 31, 2014 OTP filed a request with the NDPSC to revise its Fuel Clause Adjustment (FCA) rider in North Dakota to include recovery of new reagent and emission allowance costs. On February 25, 2015 the NDPSC approved recovery of these costs through modification of the ECR rider, instead of recovery through the FCA as OTP had proposed. The ECR rider reagent and emissions allowance charge became effective May 1, 2015.

 

South Dakota

 

2010 General Rate Case—OTP’s most recent general rate increase in South Dakota of approximately $643,000 or approximately 2.32% was granted by the SDPUC in an order issued on April 21, 2011 and effective with bills rendered on and after June 1, 2011. Pursuant to the order, OTP’s allowed rate of return on rate base was set at 8.50%.

 

Transmission Cost Recovery Rider—South Dakota law provides a mechanism for automatic adjustment outside of a general rate proceeding to recover jurisdictional capital and operating costs incurred by a public utility for new or modified electric transmission facilities. The SDPUC approved OTP’s 2014 annual update on February 13, 2015 with an effective date of March 1, 2015. OTP filed its 2015 annual update on October 30, 2015 with a proposed effective date of March 1, 2016. A supplemental filing was made on February 3, 2016 to true-up the filing to include the impact of bonus depreciation elected for 2015, the inclusion of a deferred tax asset relating to a net operating loss and the proration of accumulated deferred income taxes. This update included the recovery of new SPP transmission costs OTP began to incur on January 1, 2016. On February 12, 2016 the SDPUC approved OTP’s annual update to its TCR rider, with an effective date of March 1, 2016.

 

Environmental Cost Recovery Rider—On November 25, 2014 the SDPUC approved OTP’s ECR rider request to recover OTP’s South Dakota jurisdictional share of revenue requirements associated with its investment in the Big Stone Plant AQCS and Hoot Lake Plant MATS projects, with an effective date of December 1, 2014. On August 31, 2015 OTP filed its annual update to the South Dakota ECR requesting recovery of approximately $2.7 million in annual revenue. The SDPUC approved the request on October 15, 2015 with an effective date of November 1, 2015. On August 31, 2016 OTP filed its 2016 update to the ECR rider, requesting recovery of approximately $2.3 million in annual revenue. The SDPUC approved the request on October 26, 2016 with an effective date of November 1, 2016. This year’s lower revenue requirement is a result of the implementation of federal bonus depreciation taken on the Big Stone Plant AQCS.

 

Reagent Costs and Emission Allowances—On August 1, 2014 OTP filed a request with the SDPUC to revise its FCA rider in South Dakota to include recovery of reagent and emission allowance costs. On September 16, 2014 the SDPUC approved OTP’s request to include recovery of these costs in its South Dakota FCA rider.

 

Revenues Recorded under Rate Riders

The following table presents revenue recorded by OTP under rate riders in place in Minnesota, North Dakota and South Dakota:

 

    Three Months Ended
September 30,
    Nine Months Ended
September 30,
 
Rate Rider (in thousands)   2016     2015     2016     2015  
Minnesota                                
Conservation Improvement Program Costs and Incentives1   $ 2,839     $ 1,970     $ 7,554     $ 5,508  
Transmission Cost Recovery     779       1,141       4,188       3,968  
Environmental Cost Recovery     3,127       2,565       9,362       7,722  
North Dakota                                
Renewable Resource Adjustment     2,170       2,073       6,151       5,898  
Transmission Cost Recovery     1,950       1,565       6,155       4,912  
Environmental Cost Recovery     2,762       2,312       8,344       7,233  
South Dakota                                
Transmission Cost Recovery     335       267       1,397       911  
Environmental Cost Recovery     691       461       1,951       1,484  
Conservation Improvement Program Costs and Incentives     135       234       418       464  

 

1Includes MNCIP costs recovered in base rates.

 

FERC

 

Multi-Value Transmission ProjectsOn December 16, 2010 the FERC approved the cost allocation for a new classification of projects in the MISO region called MVPs. MVPs are designed to enable the region to comply with energy policy mandates and to address reliability and economic issues affecting multiple transmission zones within the MISO region. The cost allocation is designed to ensure that the costs of transmission projects with regional benefits are properly assigned to those who benefit. On October 20, 2011 the FERC reaffirmed the MVP cost allocation on rehearing.

 

Effective January 1, 2012 the FERC authorized OTP to recover 100% of prudently incurred CWIP and Abandoned Plant Recovery on two projects approved by MISO as MVPs in MISO’s 2011 Transmission Expansion Plan: the Big Stone South–Brookings MVP and the Big Stone South–Ellendale MVP.

 

On November 12, 2013 a group of industrial customers and other stakeholders filed a complaint with the FERC seeking to reduce the ROE component of the transmission rates that MISO transmission owners, including OTP, may collect under the MISO Tariff. The complainants are seeking to reduce the 12.38% ROE used in MISO’s transmission rates over a 15-month period ending in February 2015 to a proposed 9.15%. On October 16, 2014 the FERC issued an order finding that the current MISO ROE may be unjust and unreasonable and setting the issue for hearing. A non-binding decision by the presiding ALJ was issued on December 22, 2015 finding that the MISO transmission owners’ ROE should be 10.32%, and the FERC issued an order on September 28, 2016 setting the base ROE at 10.32%. On November 6, 2014 a group of MISO transmission owners, including OTP, filed for a FERC incentive of an additional 50-basis points for Regional Transmission Organization participation (RTO Adder). On January 5, 2015 the FERC granted the request, deferring collection of the RTO Adder until the FERC issued its order in the ROE complaint proceeding. Based on the FERC adjustment to the MISO Tariff ROE resulting from the November 12, 2013 complaint and OTP’s incentive rate filing, OTP’s ROE will be 10.82% (a 10.32% base ROE plus the 0.5% RTO Adder) effective September 28, 2016.

 

On February 12, 2015 another group of stakeholders filed a complaint with the FERC seeking to reduce the ROE component of the transmission rates that MISO transmission owners, including OTP, may collect under the MISO Tariff from 12.38% to a proposed 8.67% over a 15-month period ending in May 2016. The FERC issued an order on June 18, 2015 setting the complaint for hearings, which were held the week of February 16, 2016. A non-binding decision by the presiding ALJ was issued on June 30, 2016 finding that the MISO transmission owners’ ROE should be 9.7%. The FERC is expected to issue its order in the spring of 2017.

 

Based on a potential reduction by the FERC in the ROE component of the MISO Tariff, OTP recorded a reduction in revenue of $0.1 million in the three-month period ended September 30, 2015, and $1.3 million and $0.9 million in the nine-month periods ended September 30, 2016 and 2015, respectively, and has a $2.4 million liability on its balance sheet as of September 30, 2016, representing OTP’s best estimate of a refund obligation that would arise, net of amounts that would be subject to recovery under state jurisdictional TCR riders, based on a reduced ROE. As a result of the FERC order issued on September 28, 2016 in the first complaint proceeding establishing an allowed ROE of 10.32%, no additional liability was recorded in the third quarter of 2016.