PROPERTY, PLANT AND EQUIPMENT (Production Lines) (Details) (USD $)
12 Months Ended
Dec. 31, 2012
Property, Plant and Equipment [Line Items]  
Construction in Progress, Gross $ 34,969,529
Estimated cost to complete construction 12,795,353
Production Lines [Member]
 
Property, Plant and Equipment [Line Items]  
Construction in Progress, Gross 15,080,014
Estimated cost to complete construction 168,536
Estimated time to complete June, 2013
Plant [Member]
 
Property, Plant and Equipment [Line Items]  
Construction in Progress, Gross 6,983,931
Estimated cost to complete construction 6,142,664
Estimated time to complete April, 2013
Staff Quarters [Member]
 
Property, Plant and Equipment [Line Items]  
Construction in Progress, Gross 12,905,584
Estimated cost to complete construction $ 6,484,153
Estimated time to complete October, 2013