Commitments

Purchase Commitments (1)

We had outstanding purchase commitments consisting of the following (in thousands):

September 30,December 31,
20182017
Capital Commitments
Equipment$5,269$4,191

(1) See Note 5 for information regarding Transportation Commitments.

Contingencies

Litigation

Administrative Appeals of the BLM’s Approval of the West Antelope II South Lease Modification 

Background—On February 1, 2, and 5, 2018, the Powder River Basin Resource Council (“PRBRC”), the Sierra Club, and WildEarth Guardians (“WildEarth”), respectively, filed separate appeals with the Interior Board of Land Appeals (“IBLA”) challenging the Deputy State Wyoming BLM Director’s November 11, 2017 decision, which was publicly noticed on Bureau of Land Management’s (“BLM”) website on January 5, 2018 (“2018 BLM Decision”), to approve Antelope Coal LLC’s (“Antelope Coal”) proposed modification of Antelope Coal’s West Antelope II South (“WAII South”) lease.  Antelope Coal is a 100% owned subsidiary of Cloud Peak Energy.  The 2018 BLM Decision that is the subject of all three appeals approves the proposed amendment of WAII South lease.  This lease modification, which was entered into on February 1, 2018, by BLM and Antelope Coal, adds coal underlying nearly 857 surface acres to Antelope Coal’s existing federal leases.  PRBRC, the Sierra Club, and WildEarth have asked the IBLA to vacate the 2018 BLM Decision and direct the BLM to prepare additional environmental analysis on the impacts of the lease modification.

The 2018 BLM Decision was issued after a previous August 15, 2014 decision (“2014 BLM Decision”) had been set aside by the IBLA following previous administrative appeals filed by PRBRC, WildEarth, and the Sierra Club. On February 7, 2017, the IBLA issued a decision setting aside the 2014 BLM Decision to issue the WAII South lease modification and remanding that decision to BLM on the narrow ground that the Wyoming High Plains District Manager lacked the appropriate delegation of authority to approve such a leasing decision. The IBLA specifically declined to address the merits of WildEarth’s and PRBRC’s claims challenging whether BLM’s underlying environmental analysis was sufficient to support the agency’s lease modification decision. On April 10, 2017, BLM filed a petition with the Director of the Department of Interior’s Office of Hearings and Appeals (the “OHA Director”) asking the OHA Director to reverse the IBLA’s February 7, 2017 decision and remand to the IBLA with instructions to decide the merits of the underlying WildEarth and PRBRC appeals. On September 11, 2017, after full briefing by the parties, the OHA Director denied BLM’s Petition for OHA Director Review thereby concluding the appeals and giving full force and effect to the IBLA’s February 7, 2017 order remanding the matter to BLM and providing BLM with broad discretion on how to proceed. Upon remand, the BLM reapproved the WAII South lease modification through the 2018 BLM Decision.

Intervention by Cloud Peak Energy and State of Wyoming—On February 16 and March 5, 2018, Antelope Coal and the State of Wyoming, respectively, moved to intervene in the PRBRC, WildEarth, and Sierra Club appeals as respondents to defend the 2018 BLM Decision. On April 10, 2018, the IBLA granted both motions to intervene.

Current Schedule.  On March 21, 2018, BLM filed a Motion to Dismiss the Sierra Club appeal due to the Sierra Club’s failure to file a Statement of Reasons by the briefing deadline. On February 27 and March 5, 2018, PRBRC and WildEarth, respectively, each filed a Statement of Reasons in their appeals. On March 29, March 30, and April 2, 2018, the State of Wyoming, BLM, and Antelope Coal, respectively, filed Answer briefs in the PRBRC appeal. On April 3, 5, and 9, 2018, the State of Wyoming, BLM, and Antelope Coal, respectively, filed Answer briefs in the WildEarth appeal. On April 11, 2018, PRBRC filed a reply brief and on April 12, 2018, BLM filed a clarification to PRBRC’s Reply Brief. On June 6, 2018, the IBLA denied BLM’s motion to dismiss Sierra Club’s appeal and instead rejected Sierra Club’s appeal on the merits and affirmed the underlying 2018 BLM’s Decision. The IBLA has not yet ruled on the PRBRC or WildEarth appeals.

We believe the PRBRC and WildEarth pending appeals challenging the BLM’s West Antelope II South lease modification Decision Record are without merit. Nevertheless, if the appellants’ claims are successful, the timing and ability of Cloud Peak Energy to mine the coal underlying the lease modification surface acres could be materially adversely impacted. We are unable to estimate a loss or range of loss for this contingency because (1) the challenges do not seek monetary relief, (2) the nature of the relief sought is to require the regulatory agency to address alleged deficiencies in complying with applicable regulatory and legal requirements and (3) even if the challenges are successful in whole or in part, the IBLA has broad discretion in determining the nature of the relief ultimately granted.

WildEarth’s Regulatory Challenge to OSM’s Approval Process for Antelope Mine Plan

Background—On September 15, 2015, WildEarth filed a complaint in the Colorado District Court challenging the Department of Interior’s and Office of Surface Mining Reclamation and Enforcement’s (collectively, “OSM”) approvals of mine plans for four different coal mines, one of which is located in Colorado and three of which are located in Wyoming. The challenged approvals included one mine plan modification that was issued to Antelope Coal for the Antelope Mine in Wyoming. The plaintiff seeks to vacate existing, required regulatory approvals and to enjoin mining operations at Antelope Mine.

Intervention by Cloud Peak Energy and Others—In November and December of 2015, the State of Wyoming and all the operators of the mines whose mine plans are being challenged—Antelope Coal, New Mexico Coal Resources, LLC, Bowie Resources, LLC, and Thunder Basin Coal, L.L.C., moved to intervene as Defendants to defend the challenged mine plans. On February 18, 2016, the Colorado District Court granted all the parties’ intervention motions.

Current Schedule—On November 25, 2015, the OSM filed a motion to sever WildEarth’s complaint and transfer those claims against the two Wyoming mines (Antelope and Black Thunder) to the District of Wyoming and the New Mexico mine (El Segundo) to the District of New Mexico. Each of the prospective intervenors filed conditional responses in support of OSM’s transfer motion, and WildEarth filed an opposition to OSM’s transfer motion. On June 17, 2016, the Colorado District Court granted OSM’s motion to sever and transfer WildEarth’s claims against the Antelope and Black Thunder mine plans to the District of Wyoming and the El Segundo mine plan to the District of New Mexico. The challenges against the Antelope and Black Thunder mine plans, which are docketed as separate cases, have both been assigned to Judge Johnson of the District of Wyoming. Because Antelope Coal and Wyoming had each been granted intervention by the Colorado District Court, the Wyoming District Court acknowledged both parties as Intervenor-Defendants after WildEarth’s challenge to the Antelope Mine was transferred to the District of Wyoming. On October 7, 2016, OSM filed its administrative record for the case challenging the Antelope mine plan. On October 21, 2016, WildEarth filed a motion to supplement the administrative record with three administrative documents prepared by other federal agencies. On November 4, 2016, OSM and Antelope Coal each filed opposition briefs. On December 1, 2016, after full briefing, the court denied WildEarth’s motion to supplement the record. WildEarth filed its opening merits brief on January 27, 2017. Opposition briefs by OSM, Antelope Coal, and the State of Wyoming were filed April 5, 2017. On June 2, 2017, WildEarth filed its reply brief. On August 22, 2017 and September 20, 2017, WildEarth filed two separate notices of supplemental authority. OSM and Antelope Coal each filed responses to WildEarth’s first notice on September 6, 2017 and September 21, 2017, respectively. Antelope Coal and the State of Wyoming filed a joint response to WildEarth’s second notice on October 27, 2017. The merits briefing has been completed and the parties are awaiting a decision from the court.

We believe WildEarth’s challenge is without merit.  Nevertheless, if WildEarth’s claims against OSM’s approval of the Antelope mine plan modification are successful, any court order granting the requested relief could have a material adverse impact on our shipments, financial results and liquidity, and could result in claims from third parties if we are unable to meet our commitments under pre-existing commercial agreements as a result of any required reductions or modifications to our mining activities. We are unable to estimate a loss or range of loss for this contingency because (1) the challenge does not seek monetary relief, (2) the nature of the relief sought is to require the regulatory agency to address alleged deficiencies in complying with applicable regulatory and legal requirements and (3) even if the challenges are successful in whole or in part, the court has broad discretion in determining the nature of the relief ultimately granted.

WildEarth’s Regulatory Challenge to OSM’s Approval Process for Spring Creek Mine Plan

Background—On June 8, 2017, WildEarth and the Montana Environmental Information Center (“MEIC”) filed a complaint in the Montana District Court challenging OSM’s re-approval of a mine plan modification that was issued to Cloud Peak Energy for the Spring Creek Mine in Montana. WildEarth and MEIC seek to vacate existing, required regulatory approvals and to enjoin mining operations at the Spring Creek Mine.

Intervention by Spring Creek Coal—On August 31, 2017, Spring Creek Coal LLC moved to intervene in the WildEarth and MEIC’s challenge to the mine plan. On September 26, 2017, the court granted Spring Creek Coal’s intervention motion.

Current Schedule— OSM answered the plaintiffs’ complaint on August 24, 2017.  OSM lodged the administrative record with the court and served the record on all parties on January 17, 2018.  Plaintiffs filed their motion for summary judgment on April 6, 2018. Federal Defendants filed their response and cross motion for summary judgment on June 1, 2018; and Spring Creek filed its opposition and cross motion on June 6, 2018.  Plaintiffs filed their reply brief on June 29, 2018 and the reply briefs for the Federal Defendants and Spring Creek were filed on July 23, 2018 and July 25, 2018, respectively.  Merits briefing has been completed. The parties are waiting for the Court to schedule a hearing on the pending cross motions for summary judgment.  

We believe WildEarth’s and MEIC’s challenge is without merit.  Nevertheless, if WildEarth’s and MEIC’s claims against OSM’s approval of the Spring Creek mine plan modification are successful, any court order granting the requested relief could have a material adverse impact on our shipments, financial results and liquidity, and could result in claims from third parties if we are unable to meet our commitments under pre-existing commercial agreements as a result of any required reductions or modifications to our mining activities.  We are unable to estimate a loss or range of loss for this contingency because (1) the challenge does not seek monetary relief, (2) the nature of the relief sought is to require the regulatory agency to address alleged deficiencies in complying with applicable regulatory and legal requirements and (3) even if the challenges are successful in whole or in part, the court has broad discretion in determining the nature of the relief ultimately granted.

California Climate Change Litigation

Background—On July 17, 2017, three California local governments filed separate but largely identical complaints in California Superior Court, naming numerous fossil fuel companies as defendants (together, the “California Climate Change Litigation”).  The Plaintiffs are the County of San Mateo, the County of Marin, and the City of Imperial Beach.  Defendants include Rio Tinto PLC, Rio Tinto LTD, Rio Tinto Energy America Inc., Rio Tinto Minerals Inc., Rio Tinto Services Inc., Chevron Corp., Chevron U.S.A. Inc., ExxonMobil Corp, BP P.L.C., BP America, Inc., Royal Dutch Shell Company LLC, Citgo Petroleum Corp., ConocoPhillips, ConocoPhillips Company, Phillips 66, Peabody Energy Corp., Total E&P USA Inc., Total Specialties USA Inc., Arch Coal, Inc., ENI S.p.A., ENI Oil & Gas Inc., Statoil ASA, Anadarko Petroleum Corp., Occidental Petroleum Corp., Repsol S.A., Repsol Energy North America Corp., Repsol Trading USA Corp., Marathon Oil Company, Marathon Oil Corporation, Marathon Petroleum Corp., Hess Corp., Devon Energy Corp., Devon Energy Production Company, L.P., Encana Corp., and Apache Corp.  Cloud Peak Energy is not a named defendant.

By way of summary only, Plaintiffs allege that defendants knowingly contributed to GHG emissions through the production and sale of fossil fuels that have adversely impacted the environment, thereby creating financial liabilities for the plaintiffs.  Plaintiffs also allege that defendants engaged in a coordinated effort to conceal and deny their own knowledge of those climate change threats, discredit scientific evidence and create doubt in the minds of customers, consumers, regulators, the media, journalists, teachers and the public about the consequences of the impacts of their fossil fuel pollution.  Based on these allegations, plaintiffs assert that defendants are liable under various causes of action including public nuisance, failure to warn, design defect, private nuisance, negligence, and trespass. Plaintiffs seek unspecified compensatory damages, equitable relief to abate the alleged nuisances, attorneys’ fees, punitive damages, disgorgement of profits, costs of suit and other relief as the court may deem proper.

Indemnity Sought From Cloud Peak Energy by Rio Tinto—In August 2017, Cloud Peak Energy received a notice from various Rio Tinto entities, including Rio Tinto Energy America Inc., Rio Tinto Minerals Inc., and Rio Tinto Services Inc., seeking indemnification from Cloud Peak Energy for liabilities in connection with the California Climate Change Litigation.  Cloud Peak Energy entered into various agreements with Rio Tinto and its affiliates in connection with the 2009 IPO and separation from Rio Tinto. Under the Master Separation Agreement, Cloud Peak Energy agreed to indemnify Rio Tinto for certain liabilities relating to Cloud Peak Energy’s business conducted prior to and after the closing of our separation from Rio Tinto, which may potentially include liabilities in connection with the California Climate Change Litigation. 

Current Schedule – On July 17, 2017, Plaintiffs filed their lawsuits in the Superior Court of the State of California for the County of San Mateo, the Superior Court of the State of California for the County of Marin, and the Superior Court for the County of Contra Costa, respectively.  On August 24, 2017, the cases were removed to the U.S. District Court for the Northern District of California, where they were deemed related and assigned to Judge Vince Chhabria.  Plaintiffs indicated that they intended to move to remand the cases back to state court, and the parties stipulated that Defendants would not be required to respond to the complaints until the Court ruled on the motion to remand. The Court signed that Stipulation and Order on September 22, 2017. On September 25, 2017, Plaintiffs filed their motion to remand. The Court granted Plaintiffs’ motion to remand on March 16, 2018.  On March 26, 2018, Defendants filed (1) a Notice of Appeal to the U.S. Court of Appeals for the Ninth Circuit relating to the District Court’s order granting remand, and (2) a motion to stay the remand order pending appeal.  On April 9, 2018, Judge Chhabria granted Defendants’ motion to stay the remand order pending appeal. On June 6, 2018, Plaintiffs filed a motion to partially dismiss Defendants’ appeal, arguing the Court of Appeals lacked jurisdiction to consider certain aspects of the remand order.  Defendants opposed the motion. On August 20, 2018, the Ninth Circuit motions panel referred Plaintiffs’ motion to partially dismiss to the merits panel for decision, and set a schedule for briefing on the merits.  Defendants’ opening brief is currently due October 22, 2018; Plaintiffs’ answering brief is currently due November 21, 2018; and Defendants’ reply brief is due 21 days after service of the answering brief.

If the Plaintiffs were to prevail in the California Climate Change Litigation and if we are required to indemnify Rio Tinto for any portion of the resulting liabilities, those amounts could be significant and could have a material adverse impact on our financial condition, results and liquidity.  We are unable to estimate a loss or range of loss for this contingency because of the broad claims and unspecified damages alleged by the plaintiffs against a significant number of defendants and because of the early stage of the California Climate Change Litigation.

Challenge to BLM’s Approval of Revised Resource Management Plans for MT and WY

BackgroundOn March 15, 2016, a group of environmental plaintiffs—Western Organization of Resource Councils, Montana Environmental Information Center, Powder River Basin Resource Council, Northern Plains Resource Council, Sierra Club, and Natural Resources Defense Council—filed a complaint in the U.S. District Court for Montana challenging the BLM’s September 2015 approval of the Miles City, MT and Buffalo, WY, revised Resource Management Plans (“RMPs”). The Plaintiffs seek to vacate the 2015 RMPs, require BLM to undertake supplemental environmental analysis under the National Environmental Policy Act (“NEPA”), and enjoin BLM and the federal defendants from approving any new leases or project permits for coal or oil and gas resources within the two planning areas until BLM prepares a new NEPA analysis and revises its RMPs.

Intervention by Cloud Peak Energy and OthersIn February, March, and April, 2017, Cloud Peak Energy, the State of Wyoming, and Peabody Caballo Mining, LLC and BTU Western Resources, Inc. (“Peabody”), respectively, moved to intervene in the case. The Court granted all the parties intervention motions in March (Cloud Peak) and April (Wyoming and Peabody), 2017.

Current ScheduleOn March 26, 2018, the Court issued an Amended Opinion and Order (revising the Court’s March 23, 2018 Order) granting the Plaintiffs’ Cross-Motion for Summary Judgment on three claims and granting Defendants’ and Defendant-Intervenors’ Cross-Motions for Summary Judgment on three claims. The Court held that BLM must prepare supplemental environmental impact statements for both the Miles City and Buffalo RMPs. The Court also directed BLM to incorporate the Court’s conclusions in any pending or future coal or oil and gas leases or permits in the Miles City and Buffalo planning areas until BLM completes the supplemental NEPA analysis for both RMPs. The Court further ordered the parties to meet and confer in good faith in an attempt to reach an agreement regarding the appropriate remedy. The parties were ordered to submit separate briefs to the Court by May 25, 2018 recommending appropriate remedies in light of the Court’s March 26th Order if they could not reach a voluntary agreement on remedy.

The parties were unable to reach agreement on the appropriate remedy and each filed a separate remedy brief on May 25, 2018. On June 14, 2018, Federal Defendants and Defendant- Intervenors each filed a motion seeking the Court’s leave to file a brief in response to Plaintiffs’ remedies brief. Plaintiffs filed a joint opposition brief to these motions on June 28, 2018. On July 31, 2018, the Court issued a final remedy order that directed BLM to complete a new remedial environmental analysis (and related coal screening) by November 29, 2019. During the pendency of that supplemental analysis, BLM is also ordered to undertake a comprehensive environmental analysis for any new coal or oil & gas leasing decision in compliance with the Court’s March 26, 2018 Order. The Court rejected Plaintiffs request for injunctive relief that would have impacted mining operations during the completion of BLM’s supplemental environmental analysis.

On August 1, 2018, the Court entered judgment for the Plaintiffs on Claims 1, 3, and 5 of their complaint, and for Defendants and Defendant-Intervenors (including Cloud Peak Energy) on Claims 2, 4, and 6 of Plaintiffs’ complaint. The Court’s judgment also implemented the Court’s July 31, 2018 remedy order. On October 1, 2018, BLM filed a protective notice of appeal in the Montana District Court appealing that Court’s August 1, 2018 judgment to the U.S. Court of Appeals for the Ninth Circuit. On October 11, 2018, the State of Wyoming filed a notice of appeal. On October 12, 2018, Plaintiffs filed a notice of cross-appeal. On October 15, 2018, Cloud Peak and Peabody each filed notices of appeal.

We believe the Plaintiffs’ challenge is without merit. Nevertheless, if Plaintiffs are successful in obtaining their requested remedies on appeal, the timing and ability of Cloud Peak Energy to obtain leases and permit approvals could be materially adversely impacted. We are unable to estimate a loss or range of loss for this contingency because (1) the challenge does not seek monetary relief, (2) the nature of the relief sought is broad and the only relief the Court has ordered to date would require BLM to prospectively address alleged deficiencies in complying with applicable legal and regulatory requirements, and (3) although the Court has declined to issue any injunctive relief that might adversely affect Cloud Peak Energy’s leases and permit approvals, that decision could potentially be revised on appeal.

Other Legal Proceedings

We are involved in other legal proceedings arising in the ordinary course of business and may become involved in additional proceedings from time to time. We believe that there are no other legal proceedings pending that are likely to have a material adverse effect on our consolidated financial condition, results of operations or cash flows. Nevertheless, we cannot predict the impact of future developments affecting our claims and lawsuits, and any resolution of a claim or lawsuit or an accrual within a particular fiscal period may materially and adversely impact our results of operations for that period. In addition to claims and lawsuits against us, our leases by application, leases by modification, permits, and other industry regulatory processes and approvals, including those applicable to the utility and coal logistics and transportation industries, may also continue to be subject to legal challenges that could materially and adversely impact our mining operations, results, and liquidity. These regulatory challenges may seek to vacate prior regulatory decisions and authorizations that are legally required for some or all of our current or planned mining activities. If we are required to reduce or modify our mining activities as a result of these challenges, the impact could have a material adverse effect on our shipments, financial results and liquidity, and could result in claims from third parties if we are unable to meet our commitments under pre-existing commercial agreements as a result of any such required reductions or modifications to our mining activities.

Tax Contingencies

Our income tax calculations are based on application of the respective U.S. federal or state tax laws. Our tax filings, however, are subject to audit by the respective tax authorities. Accordingly, we recognize tax benefits when it is more likely than not a position will be upheld by the tax authorities. To the extent the final tax liabilities are different from the amounts originally accrued, the increases or decreases are recorded as income tax expense.

Several non-income based production tax audits related to federal and state royalties and severance taxes are currently in progress. The financial statements reflect our best estimate of taxes and related interest and penalties due for potential adjustments that may result from the resolution of such tax audits. From time to time, we receive audit assessments and engage in settlement discussions with applicable tax authorities, which may result in adjustments to our estimates of taxes and related interest and penalties.

Concentrations of Risk and Major Customers

For the nine months ended September 30, 2018, there was one customer that represented 10% or more of consolidated revenue. For the nine months ended September 30, 2017, there was no single customer that represented 10% or more of consolidated revenue. We generally do not require collateral or other security on accounts receivable because our customers are comprised primarily of investment grade electric utilities. Credit risk is controlled through credit approvals and monitoring procedures.

Guarantees and Off-Balance Sheet Risk

In the normal course of business, we are party to guarantees and financial instruments with off-balance sheet risk, such as bank letters of credit, performance or surety bonds and indemnities, which are not reflected on the Unaudited Condensed Consolidated Balance Sheets. In our past experience, virtually no claims have been made against these financial instruments. Management does not expect any material losses to result from these guarantees or off-balance sheet instruments.

U.S. federal and state laws require we secure certain of our obligations to reclaim lands used for mining and to secure coal lease obligations. The primary method we have used to meet these reclamation obligations and to secure coal lease obligations is to provide a third-party surety bond, typically through an insurance company. Specific bond amounts may change over time, depending on the activity at the respective site and any specific requirements by federal or state laws. As of September 30, 2018, we had $407.6 million of reclamation and lease bonds backed by collateral of $22.0 million in the form of letters of credit under our A/R Securitization Program used for mining, securing coal lease obligations, and for other operating requirements. If we are unable to obtain or retain required surety bonds, we may be unable to satisfy legal requirements necessary to conduct our mining operations.