Item
Wild Earth Guardians Regulatory Challenge to Office of Surface Minings Approval Process for Mine Plans Litigation [Member]                
Commitment and Contingency [Line Items]                
Number of different coal mines located in four different states for which approvals are challenged               7
Number of different states where seven different coal mines are located for which approvals are challenged               4
Number of challenged approvals transferred to U.S. District Court in Wyoming relating to other OSM approvals             3  
Number Of Subsidiaries Included In OSM Motion To Sever Complaint And Transfer     2          
Northern Plains Resource Council and Wild Earth Guardians Combined complaints [Member]                
Commitment and Contingency [Line Items]                
Number Of Appeals Consolidated         2      
Montana District Court Member [Member]                
Commitment and Contingency [Line Items]                
Days Allowed To OSM For Environmental Analysis 240 days              
Montana Magistrate Judge [Member]                
Commitment and Contingency [Line Items]                
Days Allowed To OSM For Environmental Analysis   180 days            
Cordero Rojo Mine | Wild Earth Guardians Regulatory Challenge to Office of Surface Minings Approval Process for Mine Plans Litigation [Member] | WYOMING [Member]                
Commitment and Contingency [Line Items]                
Number of challenged approvals issued to subsidiaries               1
Spring Creek Mine | Wild Earth Guardians Regulatory Challenge to Office of Surface Minings Approval Process for Mine Plans Litigation [Member] | MONTANA [Member]                
Commitment and Contingency [Line Items]                
Number of challenged approvals issued to subsidiaries               1
Antelope Mine | Wild Earth Guardians Regulatory Challenge to Office of Surface Minings Approval Process for Mine Plans Litigation [Member] | WYOMING [Member]                
Commitment and Contingency [Line Items]                
Estimated Quantity of Mineral Rights Under Challenge | T           15.8    
Acres Related To Estimated Quantity Of Mineral Rights Under Challenge | a           857    
Subsidiary Mine Plans Challenged       1