4. Oil and Gas Properties

 

The License covers 584,651 gross acres (914 sq. miles) in the State of South Australia. The License grants a 100% working interest in the Prospect, which overlies portions of the Cooper and Eromanga basins.

 

On October 26, 2012, a 100% interest in the License was officially issued to the Subsidiary.

 

On May 19, 2014, the Company received notice from the Government of South Australia that it had issued certain modifications to the License and had suspended the License for a period of six months. Such a suspension functions like an extension. Under the amended License, the Company is required to drill 7 exploratory wells rather than 12, as originally required. The 7 required wells must be drilled in years 3, 4, and 5 (2, 2, and 3 wells, respectively). The amount of required 2D seismic was also reduced to 62 miles (100 km.) in year 3 from 155 miles (250 km.) in year 2 but the total 3D seismic work guarantee increased to 193 sq. miles (500 sq. km.) from 154 sq. miles (400 sq. km.). However, the 3D seismic survey requirement is spread over three years with 39 sq. miles (100 sq. km.) in year 2, 77 sq. miles (200 sq. km.) in year 3 and 77 sq. miles (200 sq. km.) in year 4. Subsequent to this modification and suspension, the Company received two additional six-month suspensions, one in February 2015 and one in July 2015 (this additional suspension commenced upon the conclusion of the suspension received in February 2015). In February 2016, the Company received a third additional suspension, which was for one year and which commenced upon the conclusion of the suspension received in July 2015. Combined, these three additional suspensions amount to an accumulated total suspension of two years.

 

 

On June 22, 2016, the Company terminated the February 2016 License suspension in preparation for a 3D seismic survey (the “Nike Survey”) that was comprised of approximately 69 sq. miles (179 sq. km.) on the southwest portion of the Prospect. After archaeological and environmental reviews of the survey area, fieldwork by the seismic contractor began on July 26, 2016. The Nike Survey and field work were completed on October 30, 2016 and the License was suspended again on November 1, 2016.

 

In July 2017, the License suspension was lifted in order to conduct a Work Area Clearance Survey (“WAC”) of several potential drill sites located in the southern portion of the License. After completing the Nike Survey, the Company requested and received a number of extensions and modifications of the work commitment. As a result of the modifications and suspensions, the remaining work commitments are now as follows:

 

  * Year 3 ending January 28, 2023 - Shoot 3D seismic data totaling at a minimum approximately 135 sq. miles (350 sq. km.).
     
  * Year 4 ending January 29, 2024 - Drill three wells.
     
  * Year 5 ending January 28, 2025 - Drill four wells.

 

While the Company has to date been successful in obtaining such extensions, it has no assurance that any further extensions will be obtained.

 

In four transactions, the Company acquired portions of the royalty interest associated with the PEL 512 License so that the Company now owns an aggregate 5.0% royalty interest, while the previous holders of the original 7.0% royalty interest continue to hold a 2.0% royalty interest.