XML 24 R14.htm IDEA: XBRL DOCUMENT v3.7.0.1
Property, Plant and Equipment
6 Months Ended
Jun. 30, 2017
Property, Plant and Equipment [Abstract]  
Property, Plant and Equipment
6.  PROPERTY, PLANT AND EQUIPMENT

A summary of the historical cost of WES’s property, plant and equipment is as follows:
thousands
 
Estimated Useful Life
 
June 30, 2017
 
December 31, 2016
Land
 
n/a
 
$
4,258

 
$
4,012

Gathering systems and processing complexes
 
3 to 47 years
 
6,905,758

 
6,462,053

Pipelines and equipment
 
15 to 45 years
 
139,344

 
139,646

Assets under construction
 
n/a
 
275,403

 
226,626

Other
 
3 to 40 years
 
30,019

 
29,605

Total property, plant and equipment
 
 
 
7,354,782

 
6,861,942

Accumulated depreciation
 
 
 
2,006,988

 
1,812,010

Net property, plant and equipment
 
 
 
$
5,347,794

 
$
5,049,932



The cost of property classified as “Assets under construction” is excluded from capitalized costs being depreciated. These amounts represent property that is not yet suitable to be placed into productive service as of the respective balance sheet date.

Impairments. During the six months ended June 30, 2017, WES recognized impairments of $167.9 million, including an impairment of $158.8 million at the Granger complex, which was impaired to its estimated fair value of $48.5 million using the income approach and Level 3 fair value inputs, due to a reduced throughput fee as a result of a producer’s bankruptcy. Also during the period, WES recognized additional impairments of $9.1 million, primarily related to (i) a $3.7 million impairment at the Granger straddle plant, which was impaired to its estimated salvage value of $0.6 million using the income approach and Level 3 fair value inputs, (ii) a $3.1 million impairment of the Fort Union equity investment (see Note 7) and (iii) the cancellation of a pipeline project in West Texas.
During 2016, WES recognized impairments of $15.5 million, including an impairment of $6.1 million at WES’s Newcastle system, which was impaired to its estimated fair value of $3.1 million using the income approach and Level 3 fair value inputs, due to a reduction in estimated future cash flows caused by the low commodity price environment. Also during 2016, WES recognized impairments of $9.4 million, primarily related to the cancellation of projects at the DJ Basin complex and Springfield and DBJV systems, and the abandonment of compressors at the MIGC system.